Duluth Airport Master Plan Master Plan Advisory Committee (MPAC) Meeting #4 December 16, 2020

Transcript of Duluth Airport Master Plan

Page 1: Duluth Airport Master Plan

Duluth Airport Master PlanMaster Plan Advisory Committee (MPAC) Meeting #4

December 16, 2020

Page 2: Duluth Airport Master Plan

Zoom Online Meeting Basics

Please mute your microphone to limit feedback

noise when not talking.

You can chat with the participants in

the meeting by clicking Chat.

Page 3: Duluth Airport Master Plan

Zoom Online Meeting Basics

How to raise your hand

Page 4: Duluth Airport Master Plan

Tom Werner C.M.Executive Director

Duluth Airport [email protected]

Kaci NowickiProject Manager/Sr. Aviation Planner

[email protected]

Introductions

Page 5: Duluth Airport Master Plan

• Name• Organization• Role

Introductions

Page 6: Duluth Airport Master Plan

• Welcome and introductions• Master Plan progress update• Stakeholder Involvement Update

• Updates from the Technical Advisory Committees• Master Plan next steps• Part 150 Noise Study

Meeting agenda

Page 7: Duluth Airport Master Plan

Master Plan Progress Update

Page 8: Duluth Airport Master Plan

Master Plan Stages

Page 9: Duluth Airport Master Plan

Inventory Chapter Progress

Page 10: Duluth Airport Master Plan

• Airside facilities - Complete• Building and pavement assessments - Complete• Landside facilities – Complete• Existing environmental inventory – Complete• Exhibit A Property Map – Research complete, Mapping in

progress. Expected end of December

• Inventory Chapter continues to be in a working draft.

Inventory Chapter Progress

Page 11: Duluth Airport Master Plan

Aviation Forecast and Air Service

Page 12: Duluth Airport Master Plan

Airline Service – Forecasts Update

• COVID-19 continues to impact air travel nationally

0

500,000

1,000,000

1,500,000

2,000,000

2,500,000

3,000,000

3,500,000

4,000,000

4,500,000

5,000,000

3/1/2020 4/1/2020 5/1/2020 6/1/2020 7/1/2020 8/1/2020 9/1/2020 10/1/2020 11/1/2020 12/1/2020

TSA checkpoint travel numbers for 2020 and 2019

Total 2020 Traveler Throughput Total 2019 Traveler Throughput (Same Weekday)

Page 13: Duluth Airport Master Plan

Airline Service – Forecasts Update

• And locally at DLH

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

18,000

ENPLANED PASSENGERS AT DLH

2018 2019 2020

Page 14: Duluth Airport Master Plan

Air Service – Pandemic impacts on DLH

• Delta currently providing 4 flights per day to MSP• United currently providing 2 flight per day to ORD • Slow return to business travel may delay recovery at

airports like DLH with strong business use

• United Airlines is introducing the Embraer 175 to DLH in January. Larger aircraft with dual cabin service.

Page 15: Duluth Airport Master Plan

Activity Forecasts

• While the pandemic will create a multi-year dip in enplanements, the 5-year forecast levels remain consistent with pre-pandemic projections.

• Forecasts consider a conservative estimate of enplanement levels.

• Baseline levels for Master Plan does not include American service which was briefly in the market

• Low growth over the first 5 years• Alternate scenarios are included

• Addition of Denver service (United)• Addition of a low-cost carrier (such as Sun Country)

Page 16: Duluth Airport Master Plan

Stakeholder and Public Outreach

Page 17: Duluth Airport Master Plan

Written:NewslettersWebsite blog postsSocial media posts

In Person/Virtual:Public Open House One-on-one stakeholder meetingsTechnical Advisory Committees (TACs)

- Runway 3/21 - Taxiway network and aircraft parking- Economic Development- Air Traffic Control Tower- Sustainability AC

Stakeholder presentations and events

Stakeholder Outreach Overview

Page 18: Duluth Airport Master Plan

Runway 3/21 TAC Update

Page 19: Duluth Airport Master Plan

• Part 150 Noise Study (separate project) is evaluating noise impacts of extension.

• Joint Airport Zoning Board (JAZB) submitted proposed Airport Safety Zoning ordinance to MnDOT Aeronautics for review (project is separate from Master Plan)

• Anticipate re-engaging with this TAC in Spring 2021

Next Steps

Page 20: Duluth Airport Master Plan

Economic Development TAC

Page 21: Duluth Airport Master Plan

• Has met two times (April and Sept. 2020)• Goals

• Inform the Master Plan process and how the airport can support economic development

• Inform the ultimate airport land use• Inform future DAA investments• Understand the role DLH plays in the overall regional

economy

Economic Development TAC

Page 22: Duluth Airport Master Plan

Stakeholder feedback: Potential types of on-airport development

Aero

nauti

cal

deve

lopme

nt • Recreational hangar space• Corporate hangar space• Rent ready hangars • Aeronautical manufacturing

space• Rotorwing designated area• Additional ramp space for

large aircraft• Facilities for future UAV

users Non-

aero

nauti

cal u

se

• Potential complementary businesses needed on/near airport• Daycare• Hotel• C-store/auto

maintenance/gas station• Housing• Others

Page 23: Duluth Airport Master Plan

Stakeholder feedback: Development Needs

Deve

lopme

nt Ne

eds • Large sites needed (50-100+

acres)• Potentially better roadway access

(particularly for freight)• Reliable broadband• Parking• Utility extensions (north side)

Page 24: Duluth Airport Master Plan

Air Traffic Control Tower TAC

Page 25: Duluth Airport Master Plan

• ATCT is at the end of its useful life• Does not have adequate site lines to all areas of the

airfield• Evaluate alternatives for replacing aging tower

• Alternative sites• Alternative types

(ie. Remote Tower)

Air Traffic Control Tower

Page 26: Duluth Airport Master Plan

• What is it?• A remote tower uses a variety of sensors, visual,

infrared, track-based (radar), etc. to provide an air traffic controller, located in a remote facility, with a comprehensive picture of the airport surface and local airspace.

Remote Air Traffic Control Tower

Page 27: Duluth Airport Master Plan

• FAA is evaluating this technology to assess its suitability for use in the National Airspace System.

• Two remote tower systems are under development and evaluation in US:

• Northern Colorado Regional Airport (FNL) – Loveland – Ft. Collins, CO

• Public-private partnership• ~95,000 annual operations, 270 based aircraft• C-III, diverse mix of aircraft

• Leesburg Executive Airport (JYO) – Leesburg, VA• Public-private partnership• ~115,000 annual operations, 250 based aircraft

• World’s first remote tower center (Sundsvall, Sweden)• 4 airports

Status of Remote Towers

Page 28: Duluth Airport Master Plan

• Panel Discussion with TAC (Aug 2020)• David Ulane, Director – CDOT Aeronautics• Jason Licon, Airport Director, Northern Colorado

Regional Airport• Remote tower site

• FAA Office of Next Gen Outreach

TAC – Remote Air Traffic Control Tower

Page 29: Duluth Airport Master Plan

FAA Remote Tower Update

• TAC was interested in hybrid option if available• Currently little support for developing a path to certify

only elements of a remote tower system. • Certification of only parts of the system may be

feasible in the future, but there is no current path.

• Currently focused on Contract Tower Program, the program could expand to FAA towers in the future, but it will take time.

Page 30: Duluth Airport Master Plan

Stakeholder Feedback

Page 31: Duluth Airport Master Plan

ATCT Development Areas – NW Quadrant

Page 32: Duluth Airport Master Plan

ATCT Development Areas – SW Quadrant

Page 33: Duluth Airport Master Plan

Preferred ATCT Alternatives

Alternatives 1A, 1D, 1E, 1I, 1K

Page 34: Duluth Airport Master Plan

Taxiway Network and Aircraft Parking TAC

Page 35: Duluth Airport Master Plan

Proposed Taxiway Design StandardsPavement Width

Shoulder Width Accommodates

Taxiway A 75’ 25’ Meets 148th needs / exceeds critical aircraft

Runway 9/27 Connectors 75’ 25’ Meets 148th needs / exceeds critical aircraft

Taxiway C 50’ 20’ Critical Aircraft (A319)Runway 3/21 Connectors 50’ 20’ Critical Aircraft (A319)Taxiway D 75’ 25’ Meets 148th needs /

exceeds critical aircraftTaxiway F Network 75’ 25’ Meets 148th needs

A full-length Taxiway D alternative is still be evaluated and will continue to be considered

It is proposed Taxiway C be designed to the standards of the Critical Aircraft (A319). Larger aircraft will be required to back-taxi on Runway 3/21 to the Guard Ramp

Page 36: Duluth Airport Master Plan

• Runway 3/21 Taxiway Network continues to be evaluated• Taxiway A TAC preferred alignment is shown

Taxiway Layout

Page 37: Duluth Airport Master Plan

• Meeting on December 2nd

• Focused on: • Aircraft parking• Hangar development• Aeronautical development and redevelopment areas• Reserving a location for the air traffic control tower

Taxiway and Aircraft Parking TAC

Page 38: Duluth Airport Master Plan

Shovel Ready Sites – SW Quadrant

Monaco

Exiting electrical

vault

Cargo Ramp

Air Traffic Control Tower

Monaco Ramp

Page 39: Duluth Airport Master Plan

Shovel Ready Sites – NBDA

Page 40: Duluth Airport Master Plan

Western Airport Road (West of Cirrus)

Page 41: Duluth Airport Master Plan

• Survey was sent to the TAC group this week for follow-up• Seeking feedback on highest and best use for various

development and redevelopment areas

• Continue to balance the needs for aeronautical and non-aeronautical development

Building Area Alternatives

Page 42: Duluth Airport Master Plan

• To be established after the new year• TAC goals in development

Sustainability TAC

Page 43: Duluth Airport Master Plan

• Task kicked off in December 2020• Approximately a 6-month task

• Will evaluate financial feasibility of recommendations• Financial feasibility must be considered in the

evaluation of development recommendations• Goal: A feasible implementation plan

Financial Implementation Plan

Page 44: Duluth Airport Master Plan

What are the next tasks?

• Forecast submittal and FAA approval • Facility recommendations• Alternatives Analysis

• Preferred taxiway alternatives• Apron and aircraft parking layout• Building area development and redevelopment

alternatives• Misc. airside and landside alternatives

• Sustainability Technical Advisory Committee (TAC)

• Financial Implementation Plan

Page 45: Duluth Airport Master Plan

Part 150 Noise StudyProject Update

Page 46: Duluth Airport Master Plan

• Project website • https://duluthairport.com/noise-study/

• Involvement in Public Advisory Committee (PAC)

Part 150 Noise Study

Page 47: Duluth Airport Master Plan

Part 150 Noise Study ProgressStudy Initiation

Data Collection Forecast Validation Radar Data Analysis

Existing Noise Exposure Map

Initial Future Noise Exposure Map

Noise Abatement Alternatives

Land Use ManagementAlternatives

Noise Abatement Plan

Implementation Plan

Land Use Management Plan

Draft Noise Compatibility Program & NEMs

Draft Documents and Public Hearings

Recommended Noise Compatibility Program &

Final NEMs

Review and Approval

PAC Mtg. #3Fall 2020

Public Workshop #2

Fall 2020

Public Workshop #3Jan/Feb 2021

PAC Mtg. #4Jan/Feb 2021

Page 48: Duluth Airport Master Plan

• Public Advisory Committee #4 (virtual)• Noise abatement alternatives• Land use management alternatives

• Public Workshop #3 (virtual)• Completion of documentation

• Project website • https://duluthairport.com/noise-study/

Part 150 Study Next Steps

Page 49: Duluth Airport Master Plan

• MPAC Meeting #5• March 17, 2020 at 7:30 pm

What's Next for the Master Plan?

Page 50: Duluth Airport Master Plan