Duke Energy Carolinas - S.C. Energy Office Duke Energy Carolinas Integrated... · The Plan Duke...

download Duke Energy Carolinas - S.C. Energy Office Duke Energy Carolinas Integrated... · The Plan Duke Energy Carolinas Annual Plan ... Commensurately, the update contained in this year’s

If you can't read please download the document

Transcript of Duke Energy Carolinas - S.C. Energy Office Duke Energy Carolinas Integrated... · The Plan Duke...

  • Duke Energy Carolinas

    South Carolina 2017 Integrated Resource Plan

    (Annual Report)

    September 1, 2017

    Confidential

    PUBLIC

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    2

    DEC SC 2017 IRP TABLE OF CONTENTS

    SECTION: PAGE:

    ABBREVIATIONS ...................................................................................................................... 3

    1. INTRODUCTION............................................................................................................... 6

    2. 2017 IRP SUMMARY ........................................................................................................ 7

    3. IRP PROCESS OVERVIEW........................................................................................... 11

    4. SIGNIFICANT CHANGES SINCE 2016 IRP ............................................................... 14

    5. LOAD FORECAST .......................................................................................................... 34

    6. ENERGY EFFICIENCY AND DEMAND SIDE MANAGEMENT ........................... 46

    7. DEVELOPMENT OF THE RESOURCE PLAN .......................................................... 69

    8. SHORT-TERM ACTION PLAN .................................................................................... 81

    9. CONCLUSIONS ............................................................................................................... 89

    10. DUKE ENERGY CAROLINAS OWNED GENERATION ......................................... 91

    11. NON-UTILITY GENERATION & WHOLESALE .................................................... 101

    12. CROSS-REFERENCE OF IRP REQUIREMENTS & SUBSEQUENT ORDERS ........... 104

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    3

    ABBREVIATIONS

    AMP Aging Management Programs

    CAIR Clean Air Interstate Rule

    CAMR Clean Air Mercury Rule

    CC Combined Cycle

    CCR Coal Combustion Residuals

    CCS Carbon Capture Sequestration

    CECPCN Certificate of Environmental Compatibility and Public Convenience and Necessity

    CFL Compact Fluorescent Light bulbs

    CHP Combined Heat and Power

    CO2 Carbon Dioxide

    COD Commercial Operation Date

    COL Combined Construction and Operating License

    CPCN Certificate of Public Convenience and Necessity

    CPP Clean Power Plan

    IPI Manufacturing Industrial Production Index

    CSAPR Cross State Air Pollution Rule

    CT Combustion Turbine

    DC Direct Current

    DEC Duke Energy Carolinas

    DEP Duke Energy Progress

    DOE Department of Energy

    DSM Demand Side Management

    EE Energy Efficiency Programs

    EGU Electric Generating Unit

    EIA Energy Information Administration

    EPA Environmental Protection Agency

    EPC Engineering, Procurement, and Construction

    EPRI Electric Power Research Institute

    FERC Federal Energy Regulatory Commission

    FGD Flue Gas Desulfurization

    FLG Federal Loan Guarantee

    GALL Generic Aging Lessons Learned Report

    GHG Greenhouse Gas

    HB 589 Competitive Energy Solutions for North Carolina (House Bill 589)

    HRSG Heat Recovery Steam Generator

    HVAC Heating, Ventilation and Air Conditioning

    IGCC Integrated Gasification Combined Cycle

    IRP Integrated Resource Plan

    IS Interruptible Service

    ILR Inverter Load Ratio

    ITC International Trade Commission

    ITC Investment Tax Credit

    JDA Joint Dispatch Agreement`

    KW kilowatt

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    4

    ABBREVIATIONS (CONT.)

    LCR Table Load, Capacity, and Reserve Margin Table

    LEED Leadership in Energy and Environmental Design

    LOLE Loss of Load Expectation

    MACT Maximum Achievable Control Technology

    MATS Mercury Air Toxics Standard

    MMBtu 1 million British Thermal Units

    MW Megawatt

    MWh Megawatt-hour

    NAAQS National Ambient Air Quality Standards

    NC North Carolina

    NCDAQ North Carolina Division of Air Quality

    NCEMC North Carolina Electric Membership Corporation

    NCMPA1 North Carolina Municipal Power Agency #1

    NC REPS North Carolina Renewable Energy and Energy Efficiency Portfolio Standard

    NCTPC NC Transmission Planning Collaborative

    NCUC North Carolina Utilities Commission

    NERC North American Electric Reliability Corp

    NGCC Natural Gas Combined Cycle

    NOx Nitrogen Oxide

    NRC Nuclear Regulatory Commission

    NSPS New Source Performance Standard

    NUREG Nuclear Regulatory Commission Regulations

    OATT Open Access Transmission Tariff

    O&M Operations and Maintenance

    ONS Oconee Nuclear Station

    PC Pulverized Coal

    PEV Plug-In Electric Vehicles

    PMPA Piedmont Municipal Power Agency

    PPA Purchase Power Agreement

    PSCSC Public Service Commission of South Carolina

    PV Photovoltaic

    PVRR Present Value Revenue Requirements

    PURPA Public Utility Regulatory Policies Act

    QF Qualifying Facility

    REC Renewable Energy Certificates

    REPS Renewable Energy and Energy Efficiency Portfolio Standard

    RFP Request for Proposal

    RIM Rate Impact Measure

    RPS Renewable Portfolio Standard

    SAE Statistically Adjusted End-Use Models

    SAT Single-Axis Tracking

    SC South Carolina

    SC DER South Carolina Distributed Energy Resource Program

    SCE&G South Carolina Electric & Gas

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    5

    ABBREVIATIONS (CONT.)

    SCR Selective Catalytic Reduction

    SEPA Southeastern Power Administration

    SERC SERC Reliability Corporation

    SG Standby Generation

    SIP State Implementation Plan

    SLR Subsequent License Renewal

    SO2 Sulfur Dioxide

    SRP-LR Standard Review Plan for Review of License Renewal Applications for Nuclear Power Plants

    SRP-SLR Standard Review Plan for Review of Subsequent License Renewal Applications for Nuclear Power

    Plants

    STAP Short-Term Action Plan

    TAG Technology Assessment Guide

    TRC Total Resource Cost

    The Company Duke Energy Carolinas

    The Plan Duke Energy Carolinas Annual Plan

    UCT Utility Cost Test

    UEE Utility Energy Efficiency Programs

    U.S. United States

    VACAR Virginia/Carolinas

    VAR Volt Ampere Reactive

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    6

    1. INTRODUCTION:

    For more than a century, Duke Energy Carolinas (DEC or the Company) has provided affordable

    and reliable electricity to customers in South Carolina (SC) and North Carolina (NC) now

    totaling more than 2.5 million in number. The Company continues to serve its customers by

    planning for future demand requirements in the most reliable and economic way possible using

    increasingly clean forms of energy.

    Historically, each year, as required by the Public Service Commission of South Carolina

    (PSCSC) and the North Carolina Utilities Commission (NCUC), DEC submits a long-range

    planning document called the Integrated Resource Plan (IRP) detailing potential infrastructure

    needed to match the forecasted electricity requirements for our customers over the next 15 years.

    As per the PSCSC Order No. 98-502 Approving Least-Cost Integrated Resource Planning

    Process, the Company is providing a Short-Term Action Plan, a 15-year plan and other pertinent

    information compliant with said Order.

    The Company files separate IRPs for South Carolina and North Carolina. However, the IRP

    analyzes the system as one DEC utility across both states including customer demand, energy

    efficiency (EE), demand side management (DSM), renewable resources and traditional supply-

    side resources. As such, the quantitative analysis contained in both the South Carolina and North

    Carolina filings is identical, while certain sections dealing with state-specific issues such as state

    renewable standards or environmental standards may be specific to that states IRP.

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    7

    2. 2017 IRP SUMMARY:

    Each year, as required by the PSCSC, DEC submits an IRP detailing potential infrastructure

    needed to meet the forecasted electricity requirements for its customers over the next 15 years.

    The 2017 IRP is the best projection of how the Companys capacity and energy portfolio will

    look over the next 15 years, based on current data assumptions. This projection may change over

    time as variables such as the projected load forecasts, fuel price forecasts, environmental

    regulations, technology performance characteristics and other outside factors change.

    The proposed plan will meet the following objectives:

    Provide reliable electricity especially during peak demand periods by maintaining

    adequate reserve margins. Peak demand refers to the highest amount of electricity being

    consumed for any given hour across DECs entire system.

    Add new resources at the lowest reasonable cost to customers. These resources include a

    balance of EE, DSM, renewable resources, nuclear facilities, hydro generation and

    natural gas generation.

    Improve the environmental footprint of the portfolio by meeting or exceeding all federal,

    state and local environmental regulations.

    In the 2017 IRP, DEC developed four cases which reflect updates to the 2016 IRP base case. The

    first case, or the Base Case, is an update to the presented base case in the 2016 IRP, which

    includes the expectation of future carbon legislation and no relicensing of existing nuclear

    units. Additionally, a No Carbon Case was developed in which no carbon legislation, without

    nuclear relicensing, is considered. Finally, given the uncertainty of new and existing nuclear

    generation, the Base Case and No Carbon Case were also evaluated with relicensing of existing

    nuclear units. All results presented in this IRP represent the Base Case without nuclear relicensing,

    except where otherwise noted. As discussed in more detail throughout this report, two significant

    updates in this years IRP are developments around the Lee Nuclear project and changes in

    DECs renewable energy forecast.

    Lee Nuclear

    On December 19, 2016, the Company received the Combined Construction and Operating

    License (COL) for the Lee Nuclear Project from the United States Nuclear Regulatory

    Commission (U.S. NRC). On August 25, 2017, DEC filed a request to cancel the Lee Nuclear

    Project as that project was originally envisioned and included in prior IRPs. Also, that

    cancellation request is now pending before the North Carolina Utilities Commission (NCUC) in

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    8

    Docket Nos. E-7, Sub 819 and E-7 Sub 1146. DECs decision to cancel the project resulted from

    events that have occurred subsequent to receipt of the Lee Nuclear COL. These events include

    the AP-1000 technology owner, designer and engineer, Westinghouse, and its parent company,

    Toshiba Corporation, indicating that they intend to exit the nuclear construction business in the

    U.S., including the Lee Project; the subsequent bankruptcy of Westinghouse, and the substantial

    cost increases and schedule delays associated with the Vogtle and V.C. Summer new nuclear

    construction projects; the latter of which South Carolina Electric & Gas Company (SCE&G) and

    project joint owner, Santee Cooper, recently canceled.

    In addition to these developments, revised projections indicate that new nuclear baseload capacity is

    needed only under a carbon-constrained scenario with the assumption of no existing nuclear re-

    licensing. Even in that scenario, the added capacity would not be needed until much later in the 15-

    year planning horizon (2031, 2033) than projected in the 2016 IRP.

    Over the next year, the Company will continue to monitor and analyze key developments on factors

    impacting the potential need for future new baseload nuclear generation. Such factors include

    further developments on the Vogtle project, progress on existing unit relicensing efforts and

    changes in fuel prices and carbon policy.

    Renewable Energy

    The Company continues to aggressively pursue additional cost-effective renewable resources as

    a growing part of its energy portfolio. The Companys commitment, coupled with supporting

    legislation such as South Carolinas Distributed Energy Resource Program Act (SC DER

    Program) and North Carolinas Renewable Energy and Energy Efficiency Portfolio Standard

    (NC REPS), have led to significant growth in renewable resource development in the Carolinas.

    Furthermore, on July 27, 2017, North Carolina Governor Cooper signed into law the Competitive

    Energy Solutions for North Carolina bill or House Bill 589 (HB 589). As discussed in more detail

    in Section 4.b. of this report, HB 589 calls for the establishment of a competitive procurement

    process by which the Company will pursue additional solar resources in its South Carolina and

    North Carolina service territory, provided that they are cost-effective for consumers.

    Commensurately, the update contained in this years IRP reflects the initial forecast of increases in

    renewable additions as a result of HB 589.

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    9

    It must be noted, however, that at the time of this report filing, the rules, regulations and details

    surrounding the implementation of HB 589 are still under development. As these rules are finalized

    and as the Company gains experience with the new competitive procurement process, updated

    forecasts will be presented in subsequent IRPs.

    In addition to the Lee Nuclear and Renewable Energy updates, other changes since the 2016 IRP

    are discussed in this document. Those changes include:

    Load Forecast

    Combined Heat & Power (CHP) Projections

    Resource Adequacy

    Fuel Costs

    Carbon Assumptions

    Technology Construction and Operating Costs

    Transmission Planned and Under Construction

    As shown in the 2017 IRP Base Case, projected incremental needs are driven by load growth and

    the retirement of aging generation resources and expiration of purchase power contracts. The

    2017 IRP seeks to achieve a reliable, economic long-term power supply through a balance of

    incremental renewable resources, EE, DSM, and traditional supply-side resources planned over

    the coming years which allows the Company to maintain a diversified resource mix while also

    providing increasingly clean energy. Chart 2-A represents the incremental investments required to

    meet future needs.

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    10

    Chart 2-A 2018 and 2032 Base Case Winter Capacity Mix and Sources of Incremental

    Capacity

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    11

    3. IRP PROCESS OVERVIEW:

    To meet the future needs of DECs customers, it is necessary for the Company to adequately

    understand the load and resource balance. For each year of the planning horizon, the Company

    develops a load forecast of cumulative energy sales and hourly peak demand. To determine total

    resources needed, the Company considers the peak demand load obligation plus a 17% minimum

    planning reserve margin.

    The projected capability of existing resources, including generating units, EE and DSM, renewable

    resources and purchased power contracts, is measured against the total resource need. Any deficit

    in future years will be met with a mix of additional resources that reliably and cost-effectively meet

    the load obligation and planning reserve margin while complying with all environmental and

    regulatory requirements.

    Growth in Peak

    Demand and Energy

    Consumption

    + Resource Retirements = New Resource Needs

    It should be noted that DEC considers the non-firm energy purchases and sales associated with the

    Joint Dispatch Agreement (JDA) with Duke Energy Progress (DEP) in the development of its

    independent Base Case. To accomplish this, DEC and DEP plans are determined simultaneously to

    minimize revenue requirements of the combined jointly dispatched system while maintaining

    independent reserve margins for each company.

    For the first time in the 2016 IRP, DEC developed resource plans that also include new resource

    additions driven by winter peak demand projections inclusive of winter reserve requirements. The

    completion of a comprehensive reliability study demonstrated the need to include winter peak

    planning in the IRP process. The study recognized the growing volatility associated with winter

    morning peak demand conditions such as those observed during recent polar vortex events. The

    study also incorporated the expected significant growth in solar that provide valuable assistance in

    meeting summer afternoon peak demands on the system but do little to assist in meeting demand for

    power on cold winter mornings. As discussed in more detail in the Resource Adequacy section, the

    significant penetration of solar resources and the associated impact on summer versus winter

    reserves is the primary driver for the Companys shift to winter capacity planning. Based on results

    of the reliability study, DEC is now utilizing a winter planning reserve margin of 17% in its

    planning process.

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    12

    For the 2017 Update IRP, the Company presents a Base Case with a carbon tax beginning in 2026.

    The Clean Power Plan (CPP) rule that was finalized on August 3, 2015 by the EPA is under

    interagency review for potential repeal. As a result, the timing and details of any potential future

    carbon legislation are highly uncertain. While future carbon legislation is unknown, the Company

    feels that it is prudent to continue to plan for this scenario, as well as other potential future

    scenarios. Furthermore, a primary focus of this update IRP is the Short-Term Action Plan (STAP),

    which covers the period 2018 to 2022. It was determined that the inclusion of the carbon tax did not

    have a significant impact on the STAP, and therefore the majority of the data presented in this report

    represents the Base Case.

    Figure 3-A represents a simplified overview of the resource planning process in the update years

    (odd years) of the IRP cycle.

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    Figure 3-A Simplified IRP Process

    13

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    14

    4. SIGNIFICANT CHANGES FROM THE 2016 IRP:

    As an initial step in the IRP process, all production cost modeling data is updated to include the

    most current data. Throughout the year, best practices are implemented to ensure the IRP best

    represents the Companys planning assumptions including load forecast, generation system,

    conservation programs, renewable energy and fuel costs. The data and methodologies are regularly

    updated and reviewed to determine if adjustments can be made to further improve the IRP process

    and results.

    As part of the review process certain data elements with varying impacts on the IRP, inevitably

    change. A discussion of new or updated data elements that have the most substantial impact on the

    2017 IRP is provided below.

    a) Load Forecast

    The Company continues to utilize the statistically adjusted end use models (SAE) provided by

    ITRON to forecast sales and peaks with reasonable results.

    Each time the forecast is updated, the most currently available historical and projected data is used.

    The Spring 2017 forecast which was used in the development of the Companys 2017 IRP utilizes:

    Moodys Analytics January 2017 base economic projections

    End use equipment and appliance indexes reflecting the 2016 update of ITRONs end-use

    data, which is consistent with the Energy Information Administrations 2016 Annual

    Energy Outlook

    A calculation of normal weather using the period 1987-2016

    Additional focus is being placed on the hourly shaping of sales, which plays a critical role in

    forecasting summer and winter peaks. While much of this work is ongoing and will be incorporated

    in the 2018 IRPs, the Company continues to review the weather sensitivity of winter and summer

    peaks, as well as the hourly shaping of behind-the-meter solar, utility sponsored energy efficiency

    programs (UEE), electric vehicles, and other variables.

    Additional focus is also being placed on Duke's load research sample data, to gain a better

    understanding of historical hourly demand trends, winter and summer peaking characteristics by

    customer class, and minimums by customer class, in continuous efforts to improve forecast

    accuracy.

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    15

    Table 4-A depicts the projected average annual growth rates of several key drivers from DECs

    Spring 2017 Forecast.

    Table 4-A Key Drivers

    2018-2032

    Real Income 2.7%

    Manufacturing Industrial Production Index (IPI) 1.3%

    Population 1.6%

    In addition to economic, demographic, and efficiency trends, the forecast also incorporates the

    expected impacts of utility sponsored energy efficient programs, as well as projected effects of

    electric vehicles and behind-the-meter solar technology.

    The results of the Spring 2017 Forecast as compared to Spring 2016 Forecast is presented in Table

    4-B below.

    Table 4-B 2017 Load Forecast Growth Rates vs. 2016 Load Forecast Growth Rates

    (Retail and Wholesale Customers)

    2017 Forecast

    (2018 2032)

    2016 Forecast

    (2017 2031)

    Summer

    Peak

    Demand

    Winter

    Peak

    Demand

    Energy

    Summer

    Peak

    Demand

    Winter

    Peak

    Demand

    Energy

    Excludes impact of

    new EE programs 0.7% 1.0% 0.7% 1.3% 1.4% 1.1%

    Includes impact of

    new EE programs 0.4% 0.9% 0.4% 1.2% 1.3% 1.0%

    b) Renewable Energy

    The growth of renewable generation in the United States continues to outpace that of non-renewable

    generation. In 2016, more than 16,000 megawatts (MW) of wind and solar capacity were installed

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    16

    nationwide compared to approximately 10,000 MW for natural gas, coal, nuclear, and other

    technologies.1

    North Carolina ranked in the top five in the country in solar capacity added in 2016, second behind

    only California in total solar capacity online. Duke Energys compliance with NC REPS and the

    Public Utilities Regulatory Policy Act (PURPA) as well as the Federal Investment Tax Credit (ITC)

    were key factors behind the high penetration of solar in the state. North Carolinas current favorable

    avoided cost rate and 15-year contract terms for qualifying facilities (QFs) under PURPA have

    contributed to record numbers of projects in the interconnection queue, with the DEC and DEP

    combined solar queue representing more than 7,000 MW.

    To reduce the dependence on PURPA while continuing to support solar growth in a sustainable and

    economically attractive manner, on July 27, 2017 Governor Cooper signed into law the

    Competitive Energy Solutions for North Carolina bill or House Bill 589 (HB 589). The law

    reduces the maximum size of standard contracts offered to solar projects to 1 MW and reduces the

    contract term to 10 years.

    HB 589 also introduces a competitive procurement process for renewable resources including large-

    scale solar facilities that continues to enable third-party and utility-owned renewable development.

    Capacity referred to as the Transition MW in this document represents the total capacity of

    projects in the combined Duke Balancing Authority area that are (1) already connected; or (2) have

    entered into purchase power agreements and interconnection agreements as of the end of the 45-

    month competitive procurement period, provided that they are not subject to curtailment or

    economic dispatch. HB 589 targets 2,660 MW of competitively procured renewable resources over

    a 45-month period, which may vary based on the amount of Transition MW at the end of the 45-

    month period. It is expected that 3,500 MW of Transition MW will exist in the combined Duke

    Balancing Authority area at the end of the 45-month period. The capacity additions from the

    competitive procurement will be in addition to the expected 3,500 MW of Transition MW.

    Projects in both North Carolina and South Carolina are eligible for the competitive procurement

    process.

    Growing customer demand, the federal ITC, and declining installed solar costs make solar capacity

    the Companys primary renewable energy resource in the 2017 IRP. The 2017 IRP makes the

    following key assumptions regarding renewable energy:

    1 All renewable energy MW represent MW-AC (alternating current) unless otherwise noted.

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    17

    Installed solar capacity increases in DEC from 889 MW in 2018 to 2,890 MW in 2032;

    Achievement of the SC DER Program goal of 120 MW of solar capacity located in DEC-

    SC;

    Compliance with NC REPS continues to be met through a combination of solar, other

    renewables, EE, and Renewable Energy Certificate (REC) purchases;

    and

    Passage of HB 589 and continuing solar cost declines drive solar capacity growth above and

    beyond NC REPS requirements.

    Interconnection Queue and the Transition

    Through the end of 2016, DEC had more than 500 MW of third party utility scale solar on its

    system, with approximately 200 MW interconnecting in 2016. When renewable resources were

    evaluated for the 2017 IRP, DEC reported another approximately 35 MW of third party solar under

    construction and more than 1,500 MW in the interconnection queue. Table 4-C depicts the

    interconnection queue for DEC as of June 30, 2017.

    Table 4-C DEC QF Interconnection Queue (as of June 30, 2017)

    Utility FacilityState Energy Source Type

    Number of

    Pending Projects

    Pending Capacity

    (MW AC)

    DEC NC Biogas * 1 0

    Biomass 3 11

    Hydroelectric 1 4

    Landfill Gas 1 2

    Solar 137 1,220

    NC Total 143 1,237

    SC Landfill Gas 1 5

    Natural Gas * 1 0

    Other 1 0

    Solar 57 630

    SC Total 60 635

    DEC Total 203 1,872

    * No Capacity entered into system

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    18

    Projecting future solar connections from the interconnection queue has presented a significant

    challenge due to the large number of project cancellations and ownership transfers. If the aggregate

    capacity in the Transition exceeds 3,500 MW, the competitive procurement volume of 2,660 MW

    will be reduced by the excess amount; conversely, if the Transition falls short of 3,500 MW the

    Companies will conduct additional competitive procurement.

    DECs contribution to the Transition depends on a number of variables including connecting

    projects under construction, the number of projects in the queue with power purchase and/or

    interconnection agreements, SC DER Program Tier I, and capacity connected as a result of the RFP

    for NC REPS compliance issued in the Fall of 2016.

    The DEC RFP for NC REPS compliance is expected to be the greatest contributor of Transition

    MW beyond the over 500 MW currently connected as more than 300 MW of solar may connect to

    meet the 750,000 MWHs requested in the RFP. In total, DEC may contribute roughly one-quarter of

    the Transition MW with DEP accounting for the remaining three-quarters.

    NC REPS Compliance

    DEC remains committed to meeting the requirements of NC REPS, including the poultry waste,

    swine waste, and solar set-asides, and the general requirement, which will be met with additional

    solar, hydro, biomass, landfill gas, wind, and energy efficiency resources. DECs long-term general

    compliance needs are expected to be met through a combination of renewable resources, including

    solar RECs obtained through the HB 589 competitive procurement process.

    HB-589 Competitive Procurement and Utility-Owned Solar

    DEC continues to evaluate utility-owned solar additions to support its NC compliance targets and to

    grow its renewables portfolio. For example, DEC has recently connected two new utility-scale solar

    projects in NC as part of its efforts to encourage emission free generation resources and help meet

    its NC compliance targets, totaling 75 MW-AC:

    Monroe Solar Facility 60 MW, located in Union County, NC placed in service on March

    29, 2017; and

    Mocksville Solar Facility 15 MW, located in Davie County, NC placed in service on

    December 16, 2016.

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    19

    As mentioned above, HB 589 calls for 2,660 MW of additional solar in the Carolinas, which may

    vary depending upon how the actual Transition MW compare to the initial 3,500 MW estimate.

    RFPs will be issued over a 45-month period under the competitive procurement process; DEC may

    own up to 30% of the competitive procurement volume it self-develops. DEC will also evaluate the

    potential for acquiring facilities where appropriate. HB 589 does not stipulate a limit for DECs

    option to acquire third party projects. Since the majority of the solar projects connected during the

    Transition will be in DEPs territory, DEC is expected to have the majority of the competitive

    procurement projects, helping to balance the portfolios and mitigate additional operational

    challenges in DEP.

    HB 589 requires that competitive bids are priced below utilitys avoided cost rates, as approved by

    the NCUC, or it will not be selected. Therefore, the cost of solar is a critical input for forecasting

    how much of the competitive procurement will materialize. Avoided cost forecasts are subject to

    variability due to changes in factors such as natural gas and coal commodity prices, system

    energy and demand requirements, the level and cost of generation ancillary service

    requirements and interconnection costs. Changes in these factors will result in changing

    avoided cost values over the upcoming years with the potential to impact the cost-effectiveness

    of future competitive procurement solicitations.

    Similarly, solar costs are also influenced by a number of variables. Panel prices have decreased at a

    significant rate and are expected to continue to decline. However, there are political factors, such as

    the Suniva International Trade Commission (ITC) case, that have the potential to increase panel

    prices. Additional factors that could put upward pressure on solar costs include direct

    interconnection costs, as well as costs incurred to maintain the appropriate operational control of the

    facilities. 2

    Finally, as panel prices have decreased, there has been more interest in installing single-

    axis tracking (SAT) systems and/or systems with higher inverter load ratios (ILR) which change the

    hourly profile of solar output and increase expected capacity factors. DEC will incorporate different

    configurations further in the 2018 IRP.

    In summary, there is a great deal of uncertainty in both the future avoided cost value of solar

    and the expected price of solar installations in the years to come. As a result, the Company

    2 In April, 2017, Suniva officially filed a petition to the ITC under Section 201 of the Trade Act of 1974. Suniva is

    requesting relief against imports from all geographic sources and requesting both a minimum price on crystalline silicon

    photovoltaic modules (initially $0.78/W) and a tariff on cells (initially $0.40/W). As expected, the petition only applies

    to crystalline silicon. (GTM Research Suniva Trade Dispute Update)

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    20

    will continue to closely monitor and report on these changing factors in future IRP and

    competitive procurement filings.

    In preparation for the HB 589 competitive procurement process, the Company continues to build its

    relationships with suppliers, Engineering, Procurement, and Construction Contractors (EPCs), and

    other entities to create greater efficiencies in the supply chain, reduce construction costs, reduce

    operating and maintenance costs (O&M), and enhance system design. In anticipation of future solar

    growth, DEC is positioning itself to properly integrate renewable resources to the grid regardless of

    ownership.

    In addition to ensuring DEC has operational control over future solar associated with HB 589, the

    intermittency of solar output will require the Company to evaluate and invest in technologies to

    provide solutions for voltage, volt-ampere reactive (VAR), and/or higher ancillary reserve

    requirements.

    HB 589 Customer Programs

    In addition to the competitive procurement process, HB 589 offers direct renewable energy

    procurement for major military installations, public universities, and other large customers, as well

    as a community solar program. These programs will be a great complement to the existing customer

    oriented strategies in DEC such as the Green Source Rider and SC DER Program.

    The Green Source Rider allows DEC to procure renewable energy on behalf of the customer. The

    customer pays for the REC during their project term and DEC may acquire the REC following the

    contract term. Numerous customers have participated in this program, which stands at

    approximately 99 MW-AC (nameplate capacity) and is expected to grow to just over 103 MW-AC

    by 2017.

    The renewable energy procurement carve out for large customers such as military installations and

    universities may have similarities to the Green Source Rider program. The program allows for up to

    600 MW of total capacity, with set asides for military installations (100 MW of the 600 MW) and

    the UNC system (250 MW of the 600 MW). The 2017 IRP base case assumes all 600 MW of this

    program materialize, with the DEC/DEP split expected to be roughly equal. If all 600 MW are not

    utilized, the remainder will roll back to the competitive procurement, increasing its volume.

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    21

    The community solar portion of HB 589 calls for up to 20 MW of shared solar in DEC. This

    program may have similarities to SC DER Programs community solar program. The 2017 IRP base

    case assumes that all 20 MW of the program materialize.

    HB 589 also calls for a rebate program for rooftop solar as well as a leasing program, and the

    establishment of revised net metering rates. Given the uncertainty around the timing and structuring

    of these programs, it is challenging to assess the impact HB 589 will have on rooftop solar adoption

    in NC.

    SC DER Program Solar

    Steady progress continues to be made with the first two tiers of the SC DER Program summarized

    below, unlocking the third tier:

    Tier I: 40 MW of solar capacity from facilities each >1 MW and < 10 MW in size.

    Tier II: 40 MW of behind-the-meter rooftop solar facilities for residential, commercial and

    industrial customers, each 1 MW, 25% of which must be 20 kilowatts (kW). Since Tier

    II is behind the meter, the expected solar generation is embedded in the load forecast as a

    reduction to expected load.

    Tier III: Investment by the utility in 40 MW of solar capacity from facilities each >1 MW

    and

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    22

    and its customers to evaluate the costs and impacts of batteries deployed at a significant scale,

    explore the nature of new offerings desired by customers, and fill knowledge gaps. Among the DEC

    and DEP territories, as much as 75 MW of utility-owned and operated battery storage may be

    dispersed in the 2019-2021 time period. Additionally, HB 589 calls for an energy storage study to

    assess the economic potential for NC customers.

    DEC considers wind a potential energy resource in the long term to support increased renewables

    portfolio diversity and long-term general compliance need. Therefore, DEC issued a RFP on August

    15, 2017 for delivered energy, capacity, and associated RECs from wind projects ranging in size

    from 100 to 500 MW, and capable of delivering energy on or before December 31, 2022. To

    represent the RFP, a placeholder of 200 MW was added to the 2017 IRP base case starting in 2023.

    Summary of Expected Renewable Resource Capacity Additions

    The 2017 IRP incorporates the base case renewable capacity forecast below. This case includes

    renewable capacity required for compliance with SC DER Program, NC REPS, non-compliance

    PURPA renewable purchases part of the Transition MW of HB 589, as well as Green Source

    Rider, and the additional three components of HB 589 (competitive procurement, renewable energy

    procurement for large customers, and community solar). The Company anticipates a diverse

    portfolio including solar, biomass, hydro, wind, and other resources. Actual results could vary

    substantially for the reasons discussed previously, as well as, other potential changes to legislative

    requirements, tax policies, technology costs, and other market forces. The details of the forecasted

    capacity additions, including both nameplate and contribution to winter and summer peaks are

    summarized in Table 4-D below.

    While solar does not normally reach its maximum output at the time of DECs expected peak load

    in the summer, solars contribution to summer peak load is large enough (46% of nameplate solar

    capacity) that it may push the time of summer peak from hour beginning 4:00 PM to 5:00 PM or

    later if solar penetration levels continue to increase. However, solar is unlikely to have a similar

    impact on the morning winter peak due to lower expected solar output in the morning hours (5% of

    nameplate solar capacity). Contribution to peak assumptions will continue to be evaluated in 2018,

    with specific attention given to different configurations of solar projects with fixed tilt or tracking

    systems and different ILRs. Wind is assumed to contribute 13% of nameplate capacity to both the

    winter and summer peaks.

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    23

    Table 4-D DEC Base Case Total Renewables

    While high and low solar penetration scenarios were not evaluated compared to the base case for the

    2017 IRP, volumes can certainly vary greatly, especially for solar resources. Solar installations may

    fall short of the Base Case if the competitive procurement for universal solar facilities, renewable

    energy procurement for large customers, and/or community solar programs of HB 589 dont

    materialize to their limits for some of the reasons mentioned earlier. On the upside, there is also the

    unknown of what occurs after HB 589 which is assumed to have no additional solar growth in the

    Base Case. While new policy may stimulate additional growth, a high sensitivity could occur given

    further improvements in the economics for solar through events such as high carbon dioxide

    emission regulations or taxes, lower solar capital costs, economical solar plus storage, and/or

    continuation of renewal subsidies, and/or stronger renewable energy mandates.

    c) Nuclear Assumptions

    In its last filed IRP on September 1, 2016, DEC indicated it continued to have a long-term need

    for new nuclear generation. The Base Case scenario, which included a cost on carbon emissions,

    assumed new nuclear resources to meet load and minimum planning reserve margin with Lee

    Nuclear additions in 2026 and 2028 (2,234 MW).

    On December 19, 2016, the Company received the Combined Construction and Operating

    License (COL) for the Lee Nuclear Project from the U.S. Nuclear Regulatory Commission. On

    August 25, 2017, DEC filed a request to cancel the Lee Nuclear Project as that project was

    originally envisioned and included in prior IRPs. On August 25th, DEC filed notice of its request

    Solar

    Biomass/

    Hydro Wind Total Solar

    Biomass/

    Hydro Wind Total Solar

    Biomass/

    Hydro Wind Total

    2018 889 121 0 1010 409 121 0 530 2017/2018 34 121 0 155

    2019 1214 116 0 1330 558 116 0 674 2018/2019 44 116 0 160

    2020 1333 115 0 1448 613 115 0 728 2019/2020 61 115 0 176

    2021 1711 115 0 1826 787 115 0 902 2020/2021 67 115 0 182

    2022 2088 96 0 2184 960 96 0 1056 2021/2022 86 96 0 182

    2023 2482 90 200 2572 1142 90 26 1232 2022/2023 104 90 26 194

    2024 2890 88 200 2978 1329 88 26 1417 2023/2024 124 88 26 212

    2025 2963 86 200 3049 1363 86 26 1449 2024/2025 144 86 26 230

    2026 2949 77 200 3026 1356 77 26 1433 2025/2026 148 77 26 225

    2027 2934 74 200 3008 1350 74 26 1424 2026/2027 147 74 26 221

    2028 2919 76 200 2995 1343 76 26 1419 2027/2028 147 76 26 223

    2029 2905 76 200 2981 1336 76 26 1412 2028/2029 146 76 26 222

    2030 2890 73 200 2963 1329 73 26 1402 2029/2030 145 73 26 218

    2031 2890 66 200 2956 1329 66 26 1395 2030/2031 145 66 26 211

    2032 2890 60 200 2950 1329 60 26 1389 2031/2032 145 60 26 205

    * Solar includes 0.5% per year degradation

    DEC Base Renewables - Compliance + Non-Compliance

    MW Nameplate MW Contribution to Summer Peak MW Contribution to Winter Peak

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    24

    with the Public Service Commission of South Carolina in Docket 2011-20-E. Also, that request is

    now pending before the NCUC in Docket Nos. E-7, Sub 819 and E-7 Sub 1146. DECs decision

    to cancel the project resulted from events that have occurred subsequent to receipt of the Lee

    Nuclear COL. These events include the AP-1000 technology owner, designer and engineer,

    Westinghouse, and its parent company, Toshiba Corporation, indicating that they intend to exit

    the nuclear construction business in the U.S., including the Lee Project; the subsequent

    bankruptcy of Westinghouse, and the substantial cost increases and schedule delays associated

    with the Vogtle and V.C. Summer new nuclear construction projects; the latter of which SCE&G

    and project joint owner, Santee Cooper, recently canceled.

    In addition to these developments, revised projections indicate that new nuclear baseload

    capacity is needed only under a carbon-constrained scenario with the assumption of no existing

    nuclear re-licensing. Even in that scenario, the added capacity would not be needed until much

    later in the 15-year planning horizon (2031, 2033) than projected in the 2016 IRP.

    The Company views all of its existing nuclear fleet as excellent candidates for license

    extensions, however to date, no existing nuclear plant operating licenses have been extended

    from 60 years to 80 years in the United States. As such, there is uncertainty regarding license

    extension, and any costs associated with continuing to operate for an additional 20 years. Given

    the uncertainty of license extension, the IRP Base Case does not assume license extension at this

    time, but rather considers relicensing as a sensitivity to the Base Case. The Company is

    evaluating the feasibility of relicensing its existing nuclear resources. A discussion of the

    Companys activities is included below.

    Subsequent License Renewal (SLR) for Nuclear Power Plants

    License Renewal is governed by Title 10 of the Code of Federal Regulations (10 CFR) Part 54,

    Requirements for Renewal of Operating Licenses for Nuclear Power Plants. Additionally, the

    NRC has issued regulatory guidance documents, specifically the Generic Aging Lessons Learned

    (GALL) Report (NUREG-1801) and U.S. Nuclear Regulatory Commission Regulation-1800

    (NUREG-1800), Standard Review Plan for Review of License Renewal Applications for Nuclear

    Power Plants (SRP-LR) as a basis for determining the adequacy of Aging Management

    Programs (AMPs). Currently the Nuclear Regulatory Commission (NRC) has approved

    applications to extend licenses to 60 years for 87 nuclear units with applications for 5 nuclear

    units currently under review.

    On August 29, 2014 the Nuclear Regulatory Commission issued a Staff Requirements

    Memorandum to provide the NRC staff with direction on SLR, i.e., extending nuclear power

    plant licenses to 80 years. Consistent with that direction, the NRC drafted guidance documents

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    25

    specifically applicable to SLR applications. In December 2015, NUREG-2191 (Generic Aging

    Lessons Learned for Subsequent License Renewal (GALL-SLR) Report) and NUREG-2192

    (Standard Review Plan for the Review of Subsequent License Renewal (SRP-SLR) Applications

    for Nuclear Power Plants) were issued for public comment. Following an extensive comment

    process involving Duke Energy, the nuclear industry, and other stakeholders, the NRC published

    the final NUREGs in the Federal Register on July 14, 2017, thereby establishing formal

    regulatory guidance for SLR.

    Dominion Energy announced on November 6, 2015 that it would pursue SLR for its Surry plant

    as a Lead Plant and submitted a letter of intent to the NRC. Exelon Corporation made a similar

    announcement for its Peach Bottom plant on June 7, 2016. Currently, Exelon is planning to

    submit the Peach Bottom SLR Application in mid-2018 while Dominion is targeting early- 2019

    for Surry. On May 17, 2017 a third utility notified the NRC of its intent to submit an SLR

    application by the end of 2017. The letter providing the notification was submitted requesting

    withholding information from public disclosure and as a result the name of the utility and

    licensee(s) is not publicly available.

    Duke Energy is considering Oconee Nuclear Station (ONS) for submission of its first SLR

    application to extend the licenses to 80 years. The remaining nuclear sites will follow where the

    cost/benefit proves acceptable.

    An Advance Funding was approved on May 12, 2016 for the development portion of the ONS

    SLR project. These funds are being used to further develop and refine the Project Plan including

    scope, schedule, cost, risk, and other project elements. At this time, a final decision to extend the

    ONS or any other Duke Energy nuclear power plants' operating licenses to 80 years has not been

    made.

    d) Combined Heat and Power

    Combined Heat and Power systems, also known as cogeneration, generate electricity and useful

    thermal energy in a single, integrated system. CHP is not a new technology, but an approach to

    applying existing technologies. Heat that is normally wasted in conventional power generation is

    recovered as useful energy, which avoids the losses that would otherwise be incurred from separate

    generation of heat and power. CHP incorporating a gas-fired combustion turbine (CT) and heat

    recovery steam generator (HRSG) is more efficient than the conventional method of producing

    power and usable heat separately with a CT/generator and a stand-alone steam boiler.

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    26

    Duke Energy is exploring and working with potential customers with good base thermal loads on a

    regulated Combined Heat and Power offer. The CHP asset is included as part of Duke Energys

    IRP as a placeholder for future projects as described below. The steam sales are credited back to the

    revenue requirement of the projects to reduce the total cost of this resource. Along with the

    potential to be a cost-competitive generation resource, CHP can result in carbon dioxide (CO2)

    emission reductions, and is a potential economic development opportunity for the state.

    DEC has signed agreements and obtained regulatory approval for a 15 MW CHP at Clemson

    University, which is expected to be in service by 2020. Filing for a Certificate of Public

    Convenience and Necessity (CPCN) for a 21 MW CHP at Duke University has been delayed

    pending the resolution of issues raised by the University. Discussions with other potential steam

    hosts are currently underway.

    Projections for CHP have been included in the following quantities in this IRP:

    2020: 43 MW (winter) / 40 MW (summer)

    2022: 43 MW (winter) / 40 MW (summer)

    As CHP development continues, future IRPs will incorporate additional CHP as appropriate.

    Additional technologies evaluated as part of this IRP are discussed in Chapter 7.

    e) Resource Adequacy

    Background

    Resource adequacy refers to the ability of the electric system to supply the aggregate electrical

    demand and energy requirements of the end-use customers at all times, taking into account

    scheduled and reasonably expected unscheduled outages of system elements. Utilities require a

    margin of reserve generating capacity in order to provide reliable service. Periodic scheduled

    outages are required to perform maintenance, inspect generating plant equipment, and to refuel

    nuclear plants. Unanticipated mechanical failures may occur at any given time, and may require

    shutdown of equipment to repair failed components. Adequate reserve capacity must be available

    to accommodate these unplanned outages and to compensate for higher than projected peak demand

    due to forecast uncertainty and weather extremes. The Company utilizes a reserve margin target in

    its IRP process to ensure resource adequacy. Reserve margin is defined as total resources minus

    peak demand, divided by peak demand. The reserve margin target is established based on

    probabilistic assessments as described below.

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    27

    2016 Resource Adequacy Study

    The Company retained Astrap Consulting in 2016 to conduct an updated resource adequacy study.

    The updated study was warranted due to two primary factors.3 First, the extreme weather

    experienced in the service territory in recent winter periods was so impactful to the system that

    additional review with the inclusion of recent years weather history was warranted. Second, the

    system has added, and projects to add, a large amount of solar resources that provide meaningful

    capacity benefits in the summer but very little capacity benefits in the winter. Solar resources

    contribute approximately 45% (DEC 46%, DEP 44%) of nameplate capacity at the time of the

    expected summer peak demand which typically occurs during afternoon hours. However, solar

    resources only contribute about 5% of nameplate capacity at the time of expected winter peak

    demand which typically occurs during early morning hours. As discussed in the Renewables

    section of this document, there is a potential to add significantly to the solar resources already

    incorporated on the system.

    Methodology

    The 2016 resource adequacy study incorporated the uncertainty of weather, economic load growth,

    unit availability, and the availability of transmission and generation capacity for emergency

    assistance. Astrap analyzed the optimal planning reserve margin based on providing an acceptable

    level of physical reliability and minimizing economic costs to customers. The most common

    physical reliability metric used in the industry is to target a system reserve margin that satisfies the

    one day in 10 years Loss of Load Expectation (LOLE) standard. This standard is interpreted as one

    firm load shed event every 10 years due to a shortage of generating capacity. From an economic

    perspective, as planning reserve margin increases, the total cost of reserves increases while the costs

    related to reliability events decline. Similarly, as planning reserve margin decreases, the cost of

    reserves decreases while the costs related to reliability events increase, including the costs to

    customers for loss of power. Thus, there is an economic optimum point where the cost of additional

    reserves plus the cost of reliability events to customers is minimized.

    Winter Capacity Planning

    3 Astrap Consulting is an energy consulting firm with expertise in resource adequacy and integrated resource

    planning.

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    28

    In the past, loss of load risk was typically concentrated during the summer months and a summer

    reserve margin target provided adequate reserves in the summer and winter. However, the

    incorporation of recent winter load data and the significant amount of solar penetration in the

    updated study, shows that the majority of loss of load risk is now heavily concentrated during the

    winter period. Since solar capacity contribution to peak is much greater in the summer compared to

    the winter, maintaining a summer reserve margin target would result in declining winter reserve

    margins over time due to the impact on summer versus winter reserves as solar capacity increases.

    Thus, use of a summer reserve margin target will no longer ensure that adequate reserve levels are

    maintained in the winter, and winter load and resources now drive the timing need for new capacity

    additions. As a result, a winter planning reserve margin target is now needed to ensure that adequate

    resources are available throughout the year to meet customer demand.

    It is noted that the primary driver for the shift to winter capacity planning is the high penetration of

    solar resources and the associated impact on summer versus winter reserves. Winter load volatility

    impacts LOLE and puts upward pressure on the reserve margin target; however, winter load

    volatility or the seasonality of summer versus winter peaks is not the driver for the shift to winter

    capacity planning.

    Results

    Based on results of the 2016 resource adequacy assessment, the Company has adopted a 17%

    minimum winter reserve margin target for scheduling new resource additions. The Company will

    continue to monitor its generation portfolio and other planning assumptions that can impact resource

    adequacy and initiate new studies as appropriate.

    Adequacy of Projected Reserves DECs resource plan reflects winter reserve margins ranging from approximately 17% to 22%.

    Reserves projected in DECs IRP meet the minimum planning reserve margin target and thus

    satisfy the one day in 10 years LOLE criterion. Projected reserve margins often exceed the

    minimum 17% winter target by 3% or more in years immediately following new resource

    additions. For example, reserves exceed the 17% minimum target by 3% or more during

    2017/2018 through 2019/2020 as a result of the addition of the Lee combined cycle unit in the Fall

    of 2017 combined with a reduction in the wholesale load forecast beginning 2019. Reserves also

    exceed the minimum 17% target by 3% or more as a result of resource additions in 2024/2025,

    2028/2029 and 2031/2032.

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    29

    The IRP provides general guidance in the type and timing of resource additions. As previously

    noted, projected reserve margins will often be somewhat higher than the minimum target in years

    immediately following new generation additions since capacity is generally added in large blocks to

    take advantage of economies of scale. Large resource additions are deemed economic only if

    they have a lower Present Value Revenue Requirement (PVRR) over the life of the asset as

    compared to smaller resources that better fit the short-term reserve margin need. Reserves

    projected in the Companys IRP are appropriate for providing an economic and reliable power

    supply.

    f) Fuel Costs

    Similar to the 2015 IRP and the 2016 Biennial IRP Report, the first 10 years of natural gas prices

    are based on market data and the remaining years are based off of fundamental pricing.

    Specifically, DEC and DEP are using market based prices for the first 10 years of the planning

    period (2018 2027). Following the 10 years of market prices, the Companies transition to

    fundamental pricing over a 5 year period with 100% fundamental pricing in 2033 and beyond.

    Market prices represent liquid, tradable gas prices offered at the present time, also called future or

    forward prices. These prices represent an actual contractually agreed upon price that willing buyers

    and sellers agree to transact upon at a specified future date. As such, assuming market liquidity,

    they represent the markets view of prices for a given point in the future. Fundamental prices

    developed through external econometric modeling, on the other hand, represent a projection of fuel

    prices into the future taking into account changing supply and demand assumptions in the context of

    the changing dynamics of the external marketplace. The natural gas market is a liquid market with

    multiple buyers and sellers of natural gas that are willing to transact at longer transaction terms.

    To provide price discovery and demonstrate continued market liquidity, the Company has

    purchased a fixed price natural gas forward swap for 2,500 million British Thermal Units per day

    (MMBtu/day) extending nearly ten years forward. It is worth noting that this purchase shows a

    continued decline in natural gas prices. The 10-year average price for the most recent purchase,

    executed on August 17, 2017, was lower than a similar purchase made in April of 2017 and lower

    than the prices used in the development of the 2016 IRP.

    As in the 2016 Biennial IRP Report, coal prices continue to be based on 5 years of market data in

    the 2017 IRP. Following the 5 years of market prices, the Companies transition to fundamental

    pricing over a 5-year period with 100% fundamental pricing in 2028.

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    30

    g) Carbon Assumptions

    On August 3, 2015, the EPA finalized a rule establishing CO2 new source performance standards

    for pulverized coal (PC) and natural gas combined cycle (NGCC or CC) electric generating units

    (EGUs) that initiate construction after January 8, 2014. The EPA finalized emission standards of

    1,400 lb CO2 per gross megawatt-hour (MWh) of electricity generation for PC units and 1,000 lb

    CO2 per gross MWh for NGCC units. The standard for PC units can only be achieved with carbon

    capture and sequestration technology. Numerous parties filed petitions with the U.S. Court of

    Appeals for the District of Columbia (D.C. Circuit) challenging the EPAs final emission standard

    for new PC units. Briefing in the case is complete, but oral argument is not currently scheduled. On

    April 28, 2017, the D.C. Circuit ordered that the litigation be suspended while it considers a motion

    from EPA to hold the case in abeyance. The court has not ruled on EPAs motion.

    In response to a March 28, 2017 Executive Order, the EPA has undertaken a review of the rule to

    determine whether it should be suspended, revised, or rescinded. The rule remains in effect pending

    the outcome of litigation and EPAs review of the rule. The EPA has not announced a schedule for

    completing its review.

    On August 3, 2015, the EPA finalized the Clean Power Plan, a rule to limit CO2 emissions from

    existing fossil fuel-fired EGUs (existing EGUs are units that commenced construction prior to

    January 8, 2014). The CPP required states to develop and submit to EPA for approval

    implementation plans designed to achieve the required CO2 emission limitations. The CPP required

    states to submit initial plans by September 6, 2016, and final plans by September 6, 2018. The CPP

    established two rate-based compliance pathways and two mass-based compliance pathways for

    states to choose from when developing their state implementation plans. The CPP required

    emission limitations to take effect beginning in 2022 and get gradually more stringent through 2030.

    Numerous legal challenges to the CPP were filed with the D.C. Circuit. On February 9, 2016 the

    Supreme Court issued a stay in the case, halting implementation of the CPP through any final

    decision in the case by the Supreme Court. This means the CPP has no legal effect, and EPA

    cannot enforce any of the deadlines or rule requirements while the stay is in place.

    Briefing of the case before the D.C. Circuit was completed in April, 2016. Oral argument before the

    full D.C. Circuit occurred on September 27, 2016. The D.C. Circuit has not issued a decision in the

    case. On April 28, 2017, the D.C. Circuit ordered that the litigation be suspended while it considers

    a motion from EPA to hold the case in abeyance. The court has not ruled on EPAs motion.

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    31

    In response to the March 28, 2017 Executive Order, EPA initiated a review of the CPP to determine

    whether it should be suspended, revised, or rescinded. On June 8, 2017, the EPA sent a proposed

    rule to the Office of Management and Budget to repeal the CPP. Once interagency review is

    complete, EPA will issue the proposal for public comment. EPA has yet to announce what it will

    do regarding the possible replacement of the CPP with another rule. There is no schedule for EPA to

    issue the proposal or to determine what it will do regarding replacement of the CPP.

    In light of the uncertainty of future carbon legislation, the Base Case assumes a carbon cost

    beginning in 2026.

    h) Transmission Planned or Under Construction

    This section lists the planned transmission line additions and discusses the adequacy of DECs

    transmission system. Table 5-E lists the line projects that are planned to meet reliability needs.

    Table 4-E: DEC Transmission Line Additions

    Location Capacity Voltage

    Year From To MVA KV Comments

    2020 Lincoln CTs Longview Tie N/A 230

    Install new

    230/100 kV tie

    station in

    existing double

    circuit line near

    Maiden, NC

    There are presently no new lines, 161 kV and above, under construction in DECs service area.

    DEC Transmission System Adequacy

    Duke Energy Carolinas monitors the adequacy and reliability of its transmission system and

    interconnections through internal analysis and participation in regional reliability groups. Internal

    transmission planning looks 10 years ahead at available generating resources and projected load to

    identify transmission system upgrade and expansion requirements. Corrective actions are planned

    and implemented in advance to ensure continued cost-effective and high-quality service. The DEC

    transmission model is incorporated into models used by regional reliability groups in developing

    plans to maintain interconnected transmission system reliability. DEC works with DEP, North

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    32

    Carolina Electric Membership Corporation (NCEMC) and ElectriCities to develop an annual NC

    Transmission Planning Collaborative (NCTPC) plan for the DEC and DEP systems in both South

    and North Carolina. In addition, transmission planning is coordinated with neighboring systems

    including SCE&G and Santee Cooper under a number of mechanisms including legacy interchange

    agreements between SCE&G, Santee Cooper, DEP, and DEC.

    The Company monitors transmission system reliability by evaluating changes in load, generating

    capacity, transactions and topography. A detailed annual screening ensures compliance with DECs

    Transmission Planning Guidelines for voltage and thermal loading. The annual screening uses

    methods that comply with SERC Reliability Council (SERC) policy and North American Electric

    Reliability Corporation (NERC) Reliability Standards and the screening results identify the need for

    future transmission system expansion and upgrades.

    Transmission planning and requests for transmission service and generator interconnection are

    interrelated to the resource planning process. DEC currently evaluates all transmission reservation

    requests for impact on transfer capability, as well as compliance with the Companys Transmission

    Planning Guidelines and the Federal Energy Regulatory Commission (FERC) Open Access

    Transmission Tariff (OATT). The Company performs studies to ensure transfer capability is

    acceptable to meet reliability needs and customers expected use of the transmission system.

    Generator interconnection requests are studied in accordance with the Large and Small Generator

    Interconnection Procedures in the OATT.

    SERC audits DEC every three years for compliance with NERC Reliability Standards. Specifically,

    the audit requires DEC to demonstrate that its transmission planning practices meet NERC

    standards and to provide data supporting the Companys annual compliance filing certifications.

    SERC conducted a NERC Reliability Standards compliance audit of DEC in December 2016. The

    scope of this audit included standards impacting the Transmission Planning area. DEC received

    No Findings from the audit team in the Transmission Planning area.

    DEC participates in a number of regional reliability groups to coordinate analysis of regional, sub-

    regional and inter-balancing authority area transfer capability and interconnection reliability. The

    reliability groups purpose is to:

    Assess the interconnected systems capability to handle large firm and non-firm

    transactions for purposes of economic access to resources and system reliability;

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    33

    Ensure that planned future transmission system improvements do not adversely

    affect neighboring systems; and

    Ensure interconnected system compliance with NERC Reliability Standards.

    Regional reliability groups evaluate transfer capability and compliance with NERC Reliability

    Standards for the upcoming peak season and five- and ten-year periods. The groups also perform

    computer simulation tests for high transfer levels to verify satisfactory transfer capability.

    Application of the practices and procedures described above have ensured DECs transmission

    system is expected to continue to provide reliable service to its native load and firm transmission

    customers.

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    34

    5. LOAD FORECAST:

    Methodology

    The Duke Energy Carolinas Spring 2017 Forecast provides projections of the energy and peak

    demand needs for its service area. The forecast covers the time period of 2018 2032 and

    represents the needs of the following customer classes:

    Residential

    Commercial

    Industrial

    Other Retail

    Wholesale

    Energy projections are developed with econometric models using key economic factors such as

    income, electricity prices, and industrial production indices, along with weather and appliance

    efficiency trends. Population projections are used in the Residential customer model.

    The economic projections used in the Spring 2017 Forecast are obtained from Moodys Analytics, a

    nationally recognized economic forecasting firm, and include economic forecasts for the Carolinas.

    The Retail forecast consists of the three major classes: Residential, Commercial, and Industrial.

    The Residential class sales forecast is comprised of two projections. The first is the number of

    residential customers, which is driven by population. The second is energy usage per customer,

    which is driven by variables such as weather, regional economic and demographic trends, electric

    prices, and efficiency trends.

    The usage per customer forecast was derived using a Statistical Adjusted End-Use Model (SAE).

    This is a regression based framework that uses projected appliance saturation and efficiency trends

    developed by ITRON using Energy Information Agency (EIA) data. It incorporates naturally

    occurring efficiency trends and government mandates more explicitly than other models. The

    outlook for usage per customer is slightly negative through much of the forecast horizon, so most of

    the growth in sales is related to customer (population) increases. The projected growth rate of the

    Residential class after considering all impacts (i.e., customer growth, energy efficiency, behind-the-

    meter solar, etc.) is 0.9% for the period 2018-2032.

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    35

    The Commercial forecast also uses a SAE model in an effort to reflect naturally occurring as well as

    government mandated efficiency changes. The three largest sectors in the Commercial class are

    Offices, Education and Retail. The projected growth rate of commercial in the Spring 2017 Forecast

    after considering all impacts, is 0.2% for the period 2018 to 2032.

    The Industrial class is forecasted using a standard econometric model, with drivers such as

    industrial production and the price of electricity. Overall, Industrial sales are expected to grow 0.5%

    over the forecast horizon, after all impacts.

    System peak demands were projected using the SAE approach in the Spring 2017 Forecast. The

    peak forecast was developed using a monthly SAE model, similar to the sales SAE models, which

    includes monthly appliance saturations and efficiencies, interacted with weather and the fraction of

    each appliance type that is in use at the time of the monthly peak. Over the forecast period, the

    summer peak demand is expected to grow 0.4% (after all impacts), while the winter peak demand is

    growing 0.9% (after all impacts).

    Weather impacts are incorporated into the models by using Heating Degree Days with a base

    temperature of 59 and Cooling Degree Days with a base temperature of 65. The forecast of degree

    days is based on a 30-year average, which is updated every year.

    Forecast Enhancements

    In 2013, The Company began using the statistically adjusted end use models (SAE) provided by

    ITRON to forecast sales and peaks. The end use models provide a better platform to recognize

    trends in equipment /appliance saturation and changes to efficiencies, and how those trends interact

    with heating, cooling, and other or non-weather related sales. The appliance saturation and

    efficiency trends are developed by ITRON using data from the EIA. ITRON is a recognized firm

    providing forecasting services to the electric utility industry. These appliance trends are used in the

    residential and commercial sales models. In conjunction with peer utilities and ITRON, the

    company continually looks for refinements to its modeling procedures to make better use of the

    forecasting tools, and develop more reliable forecasts.

    Each time the forecast is updated, the most currently available historical and projected data is used.

    The Spring 2017 forecast utilizes:

    Moodys Analytics January 2017 base economic projections.

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    36

    End use equipment and appliance indexes reflect the 2016 update of ITRONs end-use data,

    which is consistent with the Energy Information Administrations 2016 Annual Energy

    Outlook.

    A calculation of normal weather using the period 1987-2016.

    Additional focus is being placed on the hourly shaping of sales, which plays a critical role in

    forecasting summer and winter peaks. While much of this work is ongoing and will be incorporated

    in the 2018 IRPs we continue to review the weather sensitivity of winter and summer peaks, as

    well as the hourly shaping of behind-the-meter solar, UEE, electric vehicles, and other variables.

    Additional focus is also being placed on Duke's load research sample data, to gain a better

    understanding of historical hourly demand trends, winter and summer peaking characteristics by

    customer class, and minimums by customer class, in our continuous effort to improve forecast

    accuracy.

    Assumptions

    Below are the projected average annual growth rates of several key drivers from DECs Spring

    2017 Forecast.

    2018-2032

    Real Income 2.7%

    Manufacturing Industrial Production Index (IPI) 1.3%

    Population 1.6%

    In addition to economic, demographic, and efficiency trends, the forecast also incorporates the

    expected impacts of utility sponsored energy efficiency programs, as well as projected effects of

    electric vehicles and behind-the-meter solar technology.

    Wholesale

    The wholesale contracts are included in the forecasted sales and peaks in the following tables.

    Please note that Duke is expected to lose a portion of wholesale load in support of NTE Energy

    (Kings Mountain combined cycle ) resource. For a complete description of the Wholesale forecast,

    please see Chapter 11.

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    37

    Historical Values

    It should be noted that long-term decline of the Textile industry and the recession of 2008-2009

    have had an adverse impact on DEC sales. The worst of the Textile decline appears to be over, and

    Moodys Analytics expects the Carolinas economy to show solid growth going forward.

    In tables 5-A & 5-B below the history of DEC customers and actual sales are given.

    Table 5-A Retail Customers (Thousands, Annual Average)

    Table 5-B Electricity Sales (GWh Sold - Years Ended December 31)

    Note the values in Table 5-B are not weather adjusted.

    2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 Avg Annual

    Growth Rate

    Residential

    1,916 2,012 2,024 2,034 2,041 2,053 2,068 2,089 2,117 2,148 1.3%

    Commercial

    322 334 331 333 335 337 339 342 345 349 0.9%

    Industrial

    7 7 7 7 7 7 7 7 6 6 -1.0%

    Other

    13 14 14 14 14 14 14 15 15 15 1.8%

    Total

    2,258 2,367 2,376 2,388 2,397 2,411 2,428 2,453 2,483 2,519 1.2%

    2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 Avg Annual

    Growth Rate

    Residential 27,459 27,335 27,273 30,049 28,323 26,279 26,895 27,976 27,916 27,939 0.3%

    Commercial 27,433 27,288 26,977 27,968 27,593 27,476 27,765 28,421 28,700 28,906 0.6%

    Industrial 23,948 22,634 19,204 20,618 20,783 20,978 21,070 21,577 22,136 21,942 -0.8%

    Other 278 284 287 287 287 290 293 303 305 304 1.0%

    Total Retail 79,118 77,541 73,741 78,922 76,986 75,023 76,023 78,277 79,057 79,091 0.1%

    Wholesale 2,454 3,525 3,788 5,166 4,866 5,176 5,824 6,559 6,916 7,614 14.3%

    Total System 81,572 81,066 77,529 84,088 81,852 80,199 81,847 84,836 85,973 86,705 0.7%

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    38

    Utility Energy Efficiency

    UEE continues to have a large impact in the acceleration of the adoption of energy efficiency. When

    including the energy and peak impacts of UEE, careful attention must be paid to avoid the double

    counting of UEE efficiencies with the naturally occurring efficiencies included in the SAE

    modeling approach. To ensure there is not a double counting of these efficiencies, the forecast rolls

    off the UEE savings at the conclusion of its measure life. For example, if the accelerated benefit

    of a residential UEE program is expected to have occurred 7 years before the energy reduction

    program would have been otherwise adopted, then the UEE effects after year 7 are subtracted

    (rolled off) from the total cumulative UEE. With the SAE models framework, the naturally

    occurring appliance efficiency trends replace the rolled off UEE benefits serving to continue to

    reduce the forecasted load resulting from energy efficiency adoption.

    Table 5-C below illustrates this process:

    Column A: Total energy before reduction of future UEE

    Column B: Historical UEE Roll-Off

    Column C: Forecasted UEE Incremental Roll-On

    Column D: Forecasted UEE Incremental Roll-Off

    Column E: UEE amount to subtract from Column A

    Column F: Total energy after incorporating UEE (column A less column E)

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    39

    Table 5-C UEE Program Life Process (GWh)

    Results

    A tabulation of the utilitys forecasts for 2018-2032, including peak loads for summer and winter

    seasons of each year and annual energy forecasts, both with and without the impact of UEE

    programs, are shown below in Tables 5-F and 5-G.

    Load duration curves, with and without UEE programs, follow Tables 5-F and 5-G, and are shown

    as Charts 5-A and 5-B.

    The tables below show the results of the forecast:

    Table 5-D: Total retail customers by class

    Table 5-E: Retail sales (at the meter) after the impacts of energy efficiency

    Table 5-F: Forecasted system summer peak, winter peak, and sales before including the

    impact of utility sponsored energy efficiency programs (at generation)

    Chart 5-A: Load duration curve before including the impact of utility sponsored energy

    efficiency programs

    Forecast Historical UEE Forecasted UEE Forecasted UEE UEE to Subtract Forecast

    Before UEE Roll Off Incremental Roll on Incremental Roll Off From Forecast After UEE

    2017 95,326 0 422 0 422 94,903

    2018 96,506 9 777 0 786 95,739

    2019 96,269 37 1,134 0 1,172 95,172

    2020 97,251 95 1,482 0 1,576 95,864

    2021 98,121 193 1,820 0 2,013 96,495

    2022 98,589 328 2,157 0 2,484 96,761

    2023 99,470 484 2,496 4 2,984 97,461

    2024 100,395 646 2,815 9 3,469 98,234

    2025 101,169 790 3,127 24 3,941 98,856

    2026 102,005 901 3,460 66 4,428 99,513

    2027 102,814 981 3,898 105 4,984 100,001

    2028 103,613 1,029 4,764 527 6,321 100,405

    2029 104,214 1,054 6,696 2,144 9,895 100,716

    2030 104,733 1,066 7,018 2,250 10,335 101,032

    2031 105,287 1,070 7,288 2,338 10,697 101,407

    2032 105,871 1,070 7,511 2,410 10,991 101,840

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    40

    Table 5-G: Forecasted system summer peak, winter peak, and sales after including the

    impact of utility sponsored energy efficiency programs (at generation)

    Chart 5-B: Load duration curve after including the impact of utility sponsored energy

    efficiency programs

    Table 5-D Retail Customers (Thousands, Annual Average)

    Residential Commercial Industrial Other Retail

    Customers Customers Customers Customers Customers

    2018 2,198 356 6 15 2,576

    2019 2,220 359 6 16 2,601

    2020 2,243 362 6 16 2,627

    2021 2,266 365 6 16 2,652

    2022 2,289 367 6 16 2,678

    2023 2,312 370 6 16 2,704

    2024 2,335 374 6 16 2,731

    2025 2,359 376 6 17 2,758

    2026 2,383 379 6 17 2,785

    2027 2,407 382 6 17 2,812

    2028 2,432 385 6 17 2,839

    2029 2,457 388 6 17 2,867

    2030 2,481 391 5 17 2,895

    2031 2,507 394 5 18 2,924

    2032 2,532 397 5 18 2,953

    Avg. Annual

    Growth Rate 1.0% 0.8% -0.8% 1.0% 1.0%

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    41

    Table 5-E Retail Sales (GWh Sold - Years Ended December 31)

    Residential Commercial Industrial Other Retail

    Gwh Gwh Gwh Gwh Gwh

    2018 27,702 28,564 22,368 299 78,933

    2019 27,773 28,631 22,608 297 79,310

    2020 27,945 28,717 22,927 294 79,884

    2021 28,138 28,747 23,253 291 80,429

    2022 28,372 28,805 23,425 288 80,891

    2023 28,650 28,904 23,646 286 81,486

    2024 28,950 29,053 23,847 285 82,135

    2025 29,240 29,139 24,009 283 82,671

    2026 29,540 29,267 24,135 280 83,222

    2027 29,823 29,347 24,157 278 83,605

    2028 30,103 29,422 24,092 277 83,895

    2029 30,367 29,435 24,035 276 84,113

    2030 30,649 29,403 24,004 274 84,331

    2031 30,946 29,390 23,993 273 84,602

    2032 31,255 29,421 23,964 272 84,912

    Avg. Annual

    Growth Rate 0.9% 0.2% 0.5% -0.7% 0.5%

  • Duke Energy Carolinas

    South Carolina

    PUBLIC

    2017 IRP Annual Report

    Integrated Resource Plan

    September 1, 2017

    42

    Table 5-F Load Forecast without Energy Efficiency Programs (at Generation)

    Note: Table 7-A differs from these values due to a 47 MW PMPA backstand contract through 2020.

    SUMMER WINTER ENERGY

    (MW) (MW) (GWH)

    2018 18,953 18,770 96,515

    2019 18,908 18,818 96,306

    2020 19,109 19,033 97,346

    2021 19,267 19,230 98,314

    2022 19,368 19,409 98,917

    2023 19,531 19,639 99,954

    2024 19,690 19,908 101,041

    2025 19,860 20,088 101,959

    2026 20,060 20,324 102,907

    2027 20,250 20,548 103,795

    2028 20,416 20,800 104,643