Due South: The construction and controversy of Charlotte’s South Corridor Light Rail Project
-
Upload
dustin-tyler-joyce -
Category
Documents
-
view
222 -
download
0
Transcript of Due South: The construction and controversy of Charlotte’s South Corridor Light Rail Project
-
8/11/2019 Due South: The construction and controversy of Charlottes South Corridor Light Rail Project
1/9
DUE SOUTHThe construction and controversy ofCharlottes South Corridor Light Rail Project
By DUSTIN TYLER JOYCE | URBPL 2010 | 9 DECEMBER 2004
-
8/11/2019 Due South: The construction and controversy of Charlottes South Corridor Light Rail Project
2/9
DUE SOUTH | DUSTIN TYLER JOYCE | 2
N 14 M ARCH 19381, Charlotte bid farewell to its last operating streetcar, No. 85. After
decades of loyal service to the city, the trolleys were being retired and replaced with new,
modern, gasoline-powered buses. The era of hearing the bell and the clickity-clack of the
trolley as it made its way from the center city to the streetcar suburbs it facilitated was over.
In 1940, two years after streetcar service ended, Charlotte had only 100,899 residents spread
over 19.3 square milesthe 91st-largest city in the country.2 By 2030, experts suggest, the
metropolitan areas population will double its current number to over 4 million.3
All those people willbring with them cars, and all those cars will bring with them traffic, congestion, and pollution. And
those will bring a lower quality of life.
While such rapid growth will certainly be a boon to the region, it also has the potential to be
disastrous. To avoid the catastrophe that threatens, Charlotte is looking to its rail-transit past. On 18
September 2002, representatives of the Charlotte Area Transit System (CATS) made a proposal to
the Metropolitan Transit Commission (MTC) to construct a multi-billion dollar transit system
integrating light rail, commuter rail, bus rapid transit, enhanced bus service, and even restored
streetcar lines. CATS will construct this system over a period of twenty-five years using the revenuegenerated by a .5% sales tax approved by voters in 1998 as well as a combination of state and federal
funds. The first phase of that system will be the South Corridor Light Rail Project (SCLRP). This is
its story and the debate surrounding it.
O
FIGURE 1Early twentiethcentury streetcar
A trolley makes its wayeast on the 100 blockof East Trade Street inuptown Charlotte.
FIGURE 2Light-rail vehicle:
front and sideprofiles
-
8/11/2019 Due South: The construction and controversy of Charlottes South Corridor Light Rail Project
3/9
DUE SOUTH | DUSTIN TYLER JOYCE | 3
SYSTEM AND CORRIDOR OVERVIEW
To understand the South Corridor light rail line, it must be put in the context of the
comprehensive transit system it will be a part of.
The backbone of the system will be five transit corridors that extend like spokes
of a wheel from the center city. (See FIGURE 4.) In designing the system, planners studiedthe attributes of each corridorexisting infrastructure, current development and transit
use, future plans for the area, projected ridership numbers, etc.and matched a mode of
transit to meet the corridors needs. (See TABLE 1.) In the southeast and west/airport corridors, where
bus rapid transit was preferred, the MTC recommended retaining light rail as an option; in the
northeast/University City corridor, a BRT line will extend from the University of
North Carolina at Charlotte to just beyond the county line.
Uptown, the central business district, will be the hub of the system. The
existing Charlotte Transportation Center on East Trade Street, which currentlyserves as the central hub of the bus network, will also be the terminus of the light
rail lines. A complementary multi-modal station on West Trade Street will connect
commuter rail, bus rapid transit, Amtrak intercity trains, and Greyhound buses.
Modern streetcar lines will link the two transit centers to each other and the rest of
the central city. Charlottes historic trolley line between uptown and the South
End neighborhood immediately to the south of the CBD has recently been
restored and features vintage early twentieth century streetcars. (SeeFIGURE 3.)
CATS will build the system in phases by 2025. There has been somediscussion of an even more extensive system connecting Charlotte to its outer
suburbs; planning for this larger system will probably continue after the first
phases of the current plan are completed.
Financing the system
The price tag of capital investment to construct this system: $1.99 billion, inflated to the time of
construction. The city has already spent $39.7 million to restore the historic trolley line4; the South
Corridor light rail line is expected to cost an additional $398.7 million5
. A variety of sources will finance the line. The transit sales tax is estimated to raise $2.55
billion in inflated dollars from 2002 through 2025, though most of these funds will help pay for
operating costs over the next quarter-century. The state and federal governments will provide the bulk
of capital funds. The Federal Transit Administration is expected to pay half the cost through its New
Starts program; a decision on federal funding will be made later this year. The State of North
Carolina has agreed to cover a quarter of the cost.6
TABLE 1Recommended transit modesin each corridor
north commuter railnortheast light railsoutheast bus rapid transitsouth light rail
west/airport bus rapid transit
FIGURE 3Charlottes restoredstreetcar line
A vintage trolleymakes an early-morning run between
the South End anduptown, 18 October2004.
-
8/11/2019 Due South: The construction and controversy of Charlottes South Corridor Light Rail Project
4/9
DUE SOUTH | DUSTIN TYLER JOYCE | 4
The South Corridor
The first phase of the 2025 plan to be constructed will be the South Corridor light rail line, which
will extend 9.6 miles from uptown to Interstate 485 just north of the suburb of Pineville. Trains will
stop at fifteen stations along the line, nine of which will have park-and-ride lots. Feeder bus routes
FIGURE 42025 System PlanThis map shows thepreferred modes,alignments, and stationlocations in eachcorridor.
-
8/11/2019 Due South: The construction and controversy of Charlottes South Corridor Light Rail Project
5/9
DUE SOUTH | DUSTIN TYLER JOYCE | 5
will connect the stations with the surrounding neighborhoods and are expected to be in place by the
lines anticipated opening in October 2006. By 2025, CATS estimates that over 17,000 should be
riding the South Corridors trains every day. Land use policies and patterns have been established to
increase the density in the areas surrounding each station, and developers have responded with over
$400 million dollars of investment in the South End neighborhood aloneseveral years before the
line even opens.7
MAKING THE CASE FOR LIGHT RAIL
This letter to the editor of The Charlotte Observer is typical of the debate that has
occurred in the newspapers pages and throughout the community concerning the
SCLRP and the 2025 System Plan. CATS and other proponents of the plans offer
the following reasons in support of rapid transit:
The regions population growth and its strain on existing infrastructure require
alternative forms of transportation.
As stated above, Charlottes metropolitan population should double by 2030. Of
that growth, 85% will occur outside Charlottes urban core. The pressure for
continued outward, auto dependant development will intensify within the
metropolitan area and wider region. Trend growth v. sustainable growth will be a
choice with significant consequences now and more so in the future. The only way
to ensure sustainable growthdefined by CATS as a more compact growth
pattern with diverse development opportunities offering improved integration of
LETTER TO THE EDITOR
San Diego demonstrates our
potential for rail8
The writer is associate professor ofarchitecture and urban design, UNCCharlotte.
In response to Reality of light rail: I won't work here (Sept. 11 Forum):
The population density of San DiegoCounty, like that of MecklenburgCounty, is less than four persons peracre. Many San Diegans predicted lightrail, financed with a half-cent sales taxand no federal assistance, would fail.
But the success of the county's firstline (from downtown south) has led to
three additional lines and a fourth underconstruction. Increased tax revenues on
the higher valuations of land in proximity to light rail is three times the cost ofoperating and maintaining the system.
That's reality!
Nelson S. BenzingCharlotte
FIGURE 5I-485 StationThe Interstate 485station just north ofPineville will be thesouthern terminus of
the light-rail line and the largest of the linesnine park-and-rides.
-
8/11/2019 Due South: The construction and controversy of Charlottes South Corridor Light Rail Project
6/9
DUE SOUTH | DUSTIN TYLER JOYCE | 6
living, working, shopping, educating and recreating uses, as well as expanded
travel choiceswill be to implement CATS Metropolitan Vision, which
promises to enhance livability and environmental health, and promote economic
vitality.9
Charlottes residents are ready for an alternative.CATS suggests several factors prove that area inhabitants seek alternatives to the
regions predominantly suburban, auto-dependant lifestyle: Transit ridership is up 38.4% since 1998. 10 Center-city neighborhoods have resurged as some of the most coveted
addresses in the city.11 Developers have responded with increased and intense development in both
the center city and along transit corridors.
Suburban towns actively encourage transit access through creating transit-oriented development.12
Proponents of the project argue that mass transit is the alternative many are looking for to
address the challenges presented by the regions population growth and the strain on existing roads
and the environment that growth will bring.
ARGUING AGAINST THE LINE
The system and its supporters have their critics, of course. Various individuals and
groups, including Patrick Ballantine, the former Republican candidate for North
Carolina governor; Charlotteans for Affordable and Sensible Transit (C-FAST);
Citizens for Effective Government (CFEG); and everyday citizens have voiced
concerns about the proposed system. Of greatest concern are the systems cost and
viabilitywillthat many people actually use the system? And if not many people
will use transit, should billions of dollars be spent on it?
The most vocal opposition group is C-FAST. Their mission statementreads: Informing tax-payers [ sic ] of Charlotte-Mecklenburg about the myths
surrounding light rail and exposing why light rail is being pushed upon the
taxpayers and citizens of Charlotte. There are affordable and sensible solutions, as
opposed to the visions of the planners. The group claims that local government,
business, and civic leaders were so anxious to construct railtoo anxious, in fact
that they stretched the truth to the public, inflated ridership estimates, downplayed capital investment
LETTER TO THE EDITOR
Reality of light rail:It wont work here 13
The writers are presidents of C-FAST andCFEG, respectively.
In response to Ballantine in a box(Aug. 27 Editorial):
Less expensive alternatives to light rainclude but are not limited to HOV lanesand buses.
If proponents had done their duediligence, they would have found that incities the size and natural density ofCharlotte light rail fails to perform aspromised to the taxpayers.
Mike CastanoLewis GuignardCharlotte
FIGURE 6TradeMarkThis condo tower,announced 2December 2004, is anexample of the high-density development
that is a part ofuptowns renaissanceas a residential center.
-
8/11/2019 Due South: The construction and controversy of Charlottes South Corridor Light Rail Project
7/9
DUE SOUTH | DUSTIN TYLER JOYCE | 7
costs, and overstated the success of such systems in cities similar to Charlotte in terms of size,
development patterns, and density. 14
Questions have been raised recently about the systems design, especially given the opening
of Houstons first light-rail line earlier this year and the abnormally high number of collisions that
have occurred between the trains and personal automobiles.15 Comparisons to other existing light-rail
systems have been frequent, particularly centering on the other systems shortcomings and failuresranging from construction setbacks and cost increases to lack of ridership in less-dense communities
and admissions by leaders in those communities that rail was a mistake. Additional objections include:
Charlotte-Mecklenburg and the surrounding region do not and will not have the density
necessary to justify the cost of a rapid-transit system.
Mass transit requires just that: mass, a density sufficient to allow people to use transit effectively and
efficiently. Charlottes decades-long pattern of suburban growth has led to development that is not
dense enough to support rapid transit. This issue is compounded by the fact that mass-transit systemsneed a large population of workers and residents in the central business district to utilize trains and
buses; opponents argue that Charlottes core, like its suburbs, does not have the required density.
Projected ridership will not support mass transit.
Because the Charlotte region has such a low density, the expected ridership by 2025 will not be
enough to support the system and justify the cost of its construction and maintenance.
The money could be better spent building more roads.Patrick Ballantine: We need to build roads better and faster. Road money is for roads.16
Opponents accuse local leaders of turning their backs to the publics best interest and
promoting construction of the train lines despite the course the development in the region is expected
to take over the next quarter-century. They describe the entire systemand particularly the rail
portions of itas a waste of money, denying that it will have the numbers of riders necessary to
justify its cost. Ultimately, they decry it as a burden that will be carried by generations to come.
FIGURE 7 (LEFT)Train arriving at astation
FIGURE 8 (RIGHT) Archdale Station A depiction of the grade-separated Archdale Drive stationfrom ground level.
-
8/11/2019 Due South: The construction and controversy of Charlottes South Corridor Light Rail Project
8/9
DUE SOUTH | DUSTIN TYLER JOYCE | 8
CONCLUSIONSHOULD LIGHT RAIL BE BUILT?
Full implementation of the 2025 System Plan is one of the best things
that can be done to ensure a bright and sustainable future for the City
of Charlotte and enhance an already high quality of life. In fact, I
question whether the plan is ambitious enough. But as it stands, the
proposal is an excellent response to the needs of the region and is
impressive in its design, functionality, and beauty.
The idea that roads and freeways should continue to be built
ad infinitum in the Charlotte area is untenable. After all, Charlotte has
plenty and the problem is still there, while studies have repeatedly shown that more roads are not the
answer. Conversely, the idea that the ridership expected on any of the lines will make a significant
difference in the amount of cars on the road is unrealistic. I doubt that the thousands of commuters
on Charlottes streets and freeways every morning and afternoon will notice much of a difference in
their commute after October 2006. However, the thousands of commuters on the train will. Thats
the real strength of this plan.
Charlottes density is already enough to support the system if it existed currently. While the
metropolitan areas density is lower than in other areas in the nation, it must be remembered how
that density is distributed. People do not live in the citys extensive buffer zones and
forests; rather, the density of the citys developed land is comparable to other cities
where light rail has been successful. This density is concentrated in the transit
corridors and center city, and will continue to be as the city and the region grow,
aided by land use policies and development that support transit.
Charlottes urban core, like the suburbs, has a sufficient concentration of
workers and residents to support the system. For example, while uptown itself has
only 60,000 workers, inclusion of other nearby central city areas such as Midtown,
the hospital district, and the South End push the number toward 200,000 workers
alone. Residential development in the center city is increasing and intensifying in density. There are
more than enough to support the system. While supporters should seek to address transit opponents concerns, the plan should not be
held back by them. Charlotte, CATS, and the federal governmentwhose approval of paying half the
cost of the system is still awaitedshould push ahead and complete the system as soon as possible so
that its benefits, which are so desperately needed, will come as quickly as possible. The South
Corridor Light Rail Project is only the first step in a long-range plan that will be a positive aspect of
the Charlotte region for generations to come.
FIGURE 10Transit-orienteddevelopmentLandDesign, a site andlandscape planningfirm, has planned this
type of transit-oriented developmentalong the light-rail and
trolley lines. This is th type of sustainable,pedestrian- and
transit-centereddevelopmentCharlotte needs.
FIGURE 9Light-rail vehicleThe front-end designof the cars currently
being built by Siemens
-
8/11/2019 Due South: The construction and controversy of Charlottes South Corridor Light Rail Project
9/9
DUE SOUTH | DUSTIN TYLER JOYCE | 9
NOTES
1. Charlotte Trolley, Inc. Meet the Vintage Cars.http://www.charlottetrolley.org/vintage.html ,accessed 3 November 2004.
2. United States Bureau of the Census. Population of the100 Largest Urban Places: 1940.http://www.census.gov/population/documentation/
twps0027/tab17.txt , accessed 3 November 2004.3. News 14 Carolina. Rapid growth brings challenges.http://www.news14charlotte.com/content/local_ne
ws/mecklenburg/?SecID=3&ArID=61900 , accessed3 November 2004.
4. Dianne Whitacre. Trolleys 1st run draws only 5. TheCharlotte Observer , 19 October 2004.http://www.charlotte.com/mld/charlotte/news/transportation/9955141.htm , accessed 19 October 2004.
5. Dianne Whitacre. Feds signal light rail OK likely.TheCharlotte Observer , 10 September 2004.http://www.charlotte.com/mld/charlotte/9625600.htm , accessed 10 September 2004.
6. Charlotte Area Transit System. Corridor System Plan, 18September 2002, pp. 33-34.
7. Charlotte Area Transit System. South-Project
Description.http://www.charmeck.org/Departments/CATS/Rapid+Transit+Planning/South-Project+Description.htm , accessed 4 November2004.
8. Nelson S. Benzing. The Observer Forum: San Diegodemonstrates our potential for rail. The CharlotteObserver, 17 September 2004.http://www.charlotte.com/mld/observer/news/opinion/9685626.htm , accessed 17 September 2004.
9. Charlotte Area Transit System. Recommended System
Plan PowerPoint presentation, 18 September 2002.10. News 14 Carolina. Gas prices, traffic boost public
transit.http://www.news14charlotte.com/content/headlines/?SecID=41&ArID=72546 , accessed 9 December2004.
11.
Doug Smith. W. Trade to get condo high-rise. TheCharlotte Observer , 2 December 2004.http://www.charlotte.com/mld/charlotte/business/columnists/doug_smith/10317904.htm , accessed 9December 2004.
12. Erica Beshears. Will transit harm charm of Cornelius?The Charlotte Observer , 11 September 2004.http://www.charlotte.com/mld/charlotte/news/9635860.htm , accessed 11 September 2004.
13. Mike Castano and Lewis Guignard. The ObserverForum: Reality of light rail: It wont work here.TheCharlotte Observer , 11 September 2004, page unknown.
14. Charlotteans for Affordable and Sensible Transit.http://www.c-fast.org , accessed 4 November 2004.
15. Dianne Whitacre. Houstons light-rail bumper cars on way?The Charlotte Observer , 15 August 2004.
http://www.charlotte.com/mld/charlotte/news/columnists/dr_traffic/9406048.htm , accessed 4September 2004.
16. quoted in Sharif Durhams and Richard Rubin. Ballantineraps rail spending. The Charlotte Observer , 25 August2004.http://www.charlotte.com/mld/charlotte/news/9487748.htm accessed 23 September 2004.
IMAGE CREDITS
FIGURE 1 http://www.cmhpf.org/photoGallery/4/scars1.jpg , accessed 4 November 2004
FIGURE 2 http://www.charmeck.org/Departments/CATS/Virtual+Transit/lightrail.htm , accessed 23 September 2004FIGURE 3 http://www.charlotte.com/mld/charlotte/news/transportation/9955141.htm , accessed 19 October 2004.
FIGURE 4 Charlotte Area Transit System. 2025 System Plan.
FIGURE 5 personal e-mail correspondence with Jennifer Green, Charlotte Area Transit System, 26 October 2004
FIGURE 6 http://www.charlotte.com/mld/charlotte/business/columnists/doug_smith/10317904.htm , accessed 7
December 2004
FIGURE 7 http://www.charmeck.org/Departments/CATS/Rapid+Transit+Planning/South-
What+will+stations+look+like%3F.htm , accessed 13 October 2004
FIGURE 8 http://www.charmeck.org/Departments/CATS/Rapid+Transit+Planning/Archdale+Drive+Station.htm ,
accessed 13 October 2004
FIGURE 9 http://www.charmeck.org/Departments/CATS/Rapid+Transit+Planning/South+Corridor.htm , accessed 23
September 2004
FIGURE 10 http://www.landdesign.com/html/portfolio/projects/plan_8.html , accessed 4 November 2004
http://www.charlotte.com/mld/charlotte/news/9487748.htmhttp://www.charlotte.com/mld/charlotte/news/9487748.htmhttp://www.charlotte.com/mld/charlotte/news/9487748.htmhttp://www.charlotte.com/mld/charlotte/news/9487748.htmhttp://www.charlotte.com/mld/charlotte/news/9487748.htm