DSD-INT 2016 Stochastic Dredge Plume Modelling in the Great Barrier Reef - Schuurman
-
Upload
delftsoftwaredays -
Category
Software
-
view
102 -
download
0
Transcript of DSD-INT 2016 Stochastic Dredge Plume Modelling in the Great Barrier Reef - Schuurman
Stochastic Dredge Plume Modelling
in the Great Barrier Reef
Filip Schuurman, Andrew Symonds &
Marcela Busnelli
Abbot Point port
• Australia’s most northerly and largest bulk port
• Started in 1984
• Capacity 50 Mton/year
• Area 5350 ha
• Operated by Abbot Point Bulkcoal Pty Ltd.
Existing and proposed terminals
Dredging for deepening of berthing place (1.1 million m³)
Onshore dumping of dredged sediment
Scope of work • Data collection and analysis
• Hydrodynamics around the Abbot Point port
• Dredged sediment dispersal and deposition
• Modelling approach:
– 3D hydrodynamic modelling using Delft3D 4
– Sediment dynamics using DelWaq offline
– Assess dredging and onshore dumping strategies
– Account for large variation in meteorological conditions (incl. tides, wind, El Niño, cyclones and regional scale circulations)
110 km by 60 km
Nested grids (3x)
Outer grid = 350 – 550 m
Inner Grid = 30– 60 m
3x water level boundaries
Driving Forces
• Astronomical Tides – water level boundaries derived using DHI Global Tidal Model, KMS.
• Wind and wave data – from regional scale hindcast wave model (resolution 0.05 degrees).
• Wave modelling online with hydrodynamics
• Uniform wind field
• Regional scale circulation processes……
Wave Calibration
0
0.5
1
1.5
2
2.5
3
3.5
4
24/12/2013 31/12/2013 7/01/2014 14/01/2014 21/01/2014 28/01/2014 4/02/2014 11/02/2014
Sign
ific
ant
Wav
e H
eigh
t (m
)
Date
Measured
Modelled
0
90
180
270
360
24/12/2013 31/12/2013 7/01/2014 14/01/2014 21/01/2014 28/01/2014 4/02/2014 11/02/2014
Mea
n W
ave
Dir
ecti
on
(deg
s)
Date
Measured
Modelled
0
2
4
6
8
10
12
14
24/12/2013 31/12/2013 7/01/2014 14/01/2014 21/01/2014 28/01/2014 4/02/2014 11/02/2014
Pea
k W
ave
Per
iod
(S)
Date
Measured
Modelled
Stochastic Modelling
• Modelled 3 years:
– El Nino (1997)
– La Nina (2011)
– Neutral year (2007)
• 10 months dredging period
• 13 scenarios with 21 days difference in starting date
Summary
• Undertook a numerical modelling comparative assessment for offshore disposal sites at Abbot Point
• Extensive modelling required to meet approval requirements
• Study showed that impact to Great Barrier Reef is insignificant
• Study helped identify most suitable dredging conditions