Drainage and wastewater - maps.wessexwater.co.uk · • models (verified) of surface water sewers...
Transcript of Drainage and wastewater - maps.wessexwater.co.uk · • models (verified) of surface water sewers...
Drainage and wastewater
management plan -
Non-technical summary
Wessex Water
September 2018
DWMP non-executive summary Wessex Water
Ref: ASSET-1192332194-25 Version: 1.1 2
Contents
1. Introduction ........................................................................................................... 3
2. Background ........................................................................................................... 4
3. Planning areas ....................................................................................................... 5
4. Levels of service ................................................................................................... 6
5. Customer and stakeholder engagement .............................................................. 8
6. Plan development .................................................................................................. 9
7. Programme appraisal .......................................................................................... 10
8. Summary of programme outputs ....................................................................... 11
DWMP non-executive summary Wessex Water
Ref: ASSET-1192332194-25 Version: 1.1 3
1. Introduction
We are producing long-term (25 year) Drainage and Wastewater Management Plans
(DWMP) in line with a consistent approach across water companies in England and Wales,
as developed through the 21st Century Drainage Programme. The DWMP is intended to
give visibility of our long-term sewerage investment plans.
The DWMP will set out how we will enhance our assets and networks to ensure we continue
to deliver for our customers and the environment in a sustainable and affordable way and in
the face of future challenges such as population growth and climate change.
Through the DWMP, we are planning and working with stakeholders at three levels:
1. At company level (see Figure 1-1) we are working with a range of stakeholders
through the Wessex Regional Flood and Coastal Committee.
2. At a management catchment level, we will be working with stakeholders through the
Catchment Partnerships, as described in Section 3.
3. At a sewage treatment works (STW) catchments level; any with high or medium risks
will have Drainage Strategy summary reports developed. These will be reviewed at
Lead Local Flood Authority level.
Figure 1-1: Wessex Water regional area
DWMP non-executive summary Wessex Water
Ref: ASSET-1192332194-25 Version: 1.1 4
2. Background
Wessex Water is the regional sewerage business serving 2.8 million customers in the
Wessex area, as shown in Figure 1-1. This includes parts of Dorset, Hampshire, Somerset
and Wiltshire and large conurbations including Bristol and Bournemouth.
We have 48 designated bathing waters on our two coastlines. Major coastal tourism towns
are Weston-Super-Mare on our northern coast and Weymouth, Poole and Bournemouth on
our southern coast.
Our aim is to give all customers excellent standards of service by providing high quality
water and environmental services that protect health, improve the environment and provides
customers good value for money.
We are recognised by our regulators as one of the leading water and sewerage companies
in England and Wales.
Figure 2-1 is a schematic of our asset statistics. Storm overflows, also known as Combined
Sewer Overflows, are an important part of our drainage system. Severe wet weather can
increase the flow in a combined sewer, which conveys both wastewater from homes and
businesses and storm water from roofs and yards. Storm overflows act as relief valves,
allowing excess storm water to be released to the river or sea, protecting properties from
sewer flooding. Flows from the storm overflows are very diluted due to the large volumes of
rainwater in the sewer. Flows are further diluted by the receiving river or sea, which will also
be swollen by the severe wet weather.
Storm overflows are licenced by the Environment Agency and we have a programme to
ensure all storm overflows are monitored by 2023.
Figure 2-1: Wessex Water wastewater asset statistics
DWMP non-executive summary Wessex Water
Ref: ASSET-1192332194-25 Version: 1.1 5
3. Planning areas
We are already working with strategic partners at a river basin catchment level, shown in
Figure 3-1. We are hosting two of these (Bristol Avon and Dorset) and participate in the
other two (Somerset and Hampshire).
Below are the links to the catchment partnership websites, where you can find more details:
Bristol Avon partnership
Dorset partnership
Hampshire Avon partnership
Somerset partnership
These catchment partnerships seek to improve the water environment and provide wider
benefits for people and nature at a catchment scale. We want to have sub-meetings to focus
on and promote flooding schemes and opportunities for partnership working to deliver
sutianable solutions to obtain more wider benefits to the environment.
Figure 3-1: Catchment partnership areas
We are also already meeting Lead Local Flood Authorities (LLFA) and the Environment
Agency (EA) on a regular basis to review flood risks. There are 11 LLFAs councils in the
Wessex area. We attend over 100 meetings a year to review flood risks with our flood
partners.
We will be reporting the partnership schemes and our own investment requirements at a
sewage treatment works (STW) catchments level. STW catchments with high or medium
risks will have Drainage Strategies summary reports available on our website by 2023.
DWMP non-executive summary Wessex Water
Ref: ASSET-1192332194-25 Version: 1.1 6
4. Levels of service
Flooding is one of the worst service failures our customers can experience, so we have
invested millions to ensure we are industry leading - with the lowest number of flooding
incidents inside people’s houses. We want to continue to be industry leading and have set
ourselves some challenging targets (performance commitments) summarised in Figure 4-1.
Figure 4-1: Flooding performance commitments
Figure 4-1 summarises four of the wastewater targets. We have several other performance
commitments to ensure that we deliver our long-term sewerage outcomes:
• Properties at risk of flooding in a storm
• Sewer collapses
• STW compliance
• Pollutions
• Natural capital (SSSI)
• Partnership working
• Length of rivers improved
• Reduce frequent spilling overflows
More details can be found on our 2020-2025 business plan (here) in supporting document
5.4 and appendix 8.9.A.
DWMP non-executive summary Wessex Water
Ref: ASSET-1192332194-25 Version: 1.1 7
Flooding is challenging because when it rains heavily, the flood water can be from several
sources, for which different flood risk management authorities are responsible (see
Figure 4.2). Wessex Water are responsible for flooding from sewers, but we work with other
authorities, as described in Section 3, to reduce flooding risks.
Figure 4-2: Flooding responsibilities
The majority of flooding incidents are caused by inappropriate materials being flushed down
toilets, for example wet-wipes, which cause blockages.
We will continue our targeted campaigns to promote only flushing 3-Ps (paper, pee and poo)
as well as other local campaigns, such as Bag it and Bin it.
Figure 4-2 shows a video clip
explaining that wet-wipes should
not be flushed, even if they are
being promoted by the
manufacturers as being ‘flushable’.
They may flush, but they are the
major case of sewer blockages
because they do not degrade like
toilet paper does.
Figure 4-3: Publicity campaign
DWMP non-executive summary Wessex Water
Ref: ASSET-1192332194-25 Version: 1.1 8
5. Customer and stakeholder engagement
Our flood reduction and DWMP proposals were included in our draft business plan that was
tested with customers between January and June 2018.
The customer research is designed to test whether customers find the plan acceptable and
affordable. The stimulus material covered our overall package of service improvements,
statutory enhancements and bill impacts. We tested our plan with household customers,
business customers, retailers, those in vulnerable circumstances and industry stakeholders.
Results were triangulated across a variety of qualitative and quantitative methodologies to
maximise the robustness of both the sample and conclusions.
Testing has shown that 96% of our customers find our business plan acceptable.
Acceptability is above 90% across all demographic subgroups. Those in vulnerable
circumstances were slightly less accepting of the plan than other groups, but still at a very
high level.
A large majority of household customers (92%) consider our plans are affordable for them.
Over 90% of businesses found the plan to be affordable. Vulnerable customers also found
the plan acceptable and affordable and were positive about the assistance that we provide
to this group.
Full details of our acceptability testing can be found in Supporting document 1.1 Summary of
research findings and details of how we address affordability and vulnerability are in included
in Supporting document 2.1 Vulnerability strategy in our business plan.
Figure 5-1: What customers think of our business plan (2020 to 2025)
DWMP non-executive summary Wessex Water
Ref: ASSET-1192332194-25 Version: 1.1 9
6. Plan development
The DWMP and Drainage Strategies are under development.
We are aiming to summarise our Drainage Strategies for all high and medium risk
catchments by 2023.
We are currently prioritising catchments through a screening process.
The highest risk catchments will undergo desk studies, including computer hydraulic
modelling, to evaluate the existing and future risks, known as baseline risk and vulnerability
assessment (BRAVA). This BRAVA will be completed by 2020.
By 2022 we will have undertaken optioneering to evaluate investments needs for the highest
risk catchments. This will include cost benefit analysis of different options, particularly if the
options are only required due to prospective development or potential climate change
implications. In these cases, adaptive pathways may allow some minor improvements in the
short to medium term, deferring major investment until it is needed.
Like our current process, our options appraisals will look at both traditional solutions, such as
storage tanks (Figure 6-1) and more sustainable solutions (Figure 6-2) such as sustainable
urban drainage systems (Suds). We will continue to innovate.
Figure 6-1: Figure 6-2:
Underground storage solution Sustainable urban drainage solution
DWMP non-executive summary Wessex Water
Ref: ASSET-1192332194-25 Version: 1.1 10
7. Programme appraisal
We have been undertaking long term planning for many decades. However, the new DWMP
Framework requires us to start re-evaluating risks in all catchments and report in a manner
consistent across water companies in England and Wales. This is a long and complicated
process that will take a few years to deliver.
Our programme to deliver the DWMP framework is summarised below:
• initial catchment screening by 2019
• detailed catchment assessments (BRAVA) by 2020
• 85% coverage of models (verified) of foul and combined sewers by 2020
• 15% coverage of models (unverified) of foul and combined sewers by 2020
• models (verified) of surface water sewers with known issues by 2021
• models (unverified) of all other public surface water sewers by 2022
• working with our partners to build integrated models (i.e. including third party assets
such as watercourses, highway drainage and overland flow routes) for a couple of
specific catchments by 2025.
Figure 7-1 shows our proposed programme of delivery for the DWMPs. This will be
completed by 2023, so that the findings can be used for long-term planning in our next
business plan (2025-2030). This is likely to include a larger investment programme than
historical investment on the sewerage infrastructure.
Figure 7-1: DWMP programme
DWMP non-executive summary Wessex Water
Ref: ASSET-1192332194-25 Version: 1.1 11
8. Summary of programme outputs
We have developed a DWMP website (Figure 8-1) and DWMP portal (Figure 8-2).
These currently have a handful of Drainage Strategy summary reports, Infiltration Reduction
summary reports and case studies. Over the next few years and by 2023, this website and
portal will become more populated as we publish our strategies.
Figure 8-1: Wessex Water’s DWMP website
Figure 8-2: Wessex Water’s DWMP portal showing local Drainage Strategies