Draft Transmission Planning Guideline Mar 2012
-
Upload
aldwin-arcilla-camance -
Category
Documents
-
view
219 -
download
0
Transcript of Draft Transmission Planning Guideline Mar 2012
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
1/91
Draft Guidelines for Transmission Planning
March 2012
Prepared for
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
2/91
Draft as of March 2012 2
Table of Contents
ABBREVIATIONS ............................................................................................................... 6
DEFINITION OF TERMS ...................................................................................................... 9
GENERAL STATEMENT ..................................................................................................... 12
1. INTRODUCTION ....................................................................................................... 13
1.1 Introduction ............................................................................................................... 13
1.2 Planning Horizon ........................................................................................................ 13
1.3 Planning Process ........................................................................................................ 14
2. Forecasting ............................................................................................................. 16
2.1 Introduction ............................................................................................................... 16
2.2 Forecast Information .................................................................................................. 16
2.3 Forecasting Methodology ........................................................................................... 17
3. Standards and Criteria ............................................................................................. 19
3.1 Introduction ............................................................................................................... 19
3.2 Performance Standards as per the PGC ....................................................................... 20
3.2.1 System Losses ..................................................... ................................................................. .......... 20
3.2.2 Congestion .................................................................................................................................... 20
3.3 Planning Criteria and Limits ........................................................................................ 21
3.3.1 Planning for Redundancy .............................................................................................................. 21
3.3.2 Technical Limits ............................................................................................................................. 22
3.3.3 Power Factor Considerations ........................................................................................................ 26
3.3.4 Minimum and Peak Load Demand Considerations ....................................................................... 263.3.5 Planning for Disposal of Assets ..................................................................................................... 27
3.3.6 Planning for Generation ................................................................................................................ 27
4. Technical Studies ..................................................................................................... 28
4.1 Introduction ............................................................................................................... 28
4.2 Data Requirement ...................................................................................................... 28
4.3 Load Flow Studies ...................................................................................................... 32
4.3.1 Minimum Data Requirements ....................................................................................................... 32
4.3.2 Criteria and Study Scenarios ......................................................................................................... 334.3.3 Load Assumptions ......................................................................................................................... 33
4.3.4 Generation Assumptions ............................................................................................................... 34
4.4 Short Circuit Studies ................................................................................................... 35
4.5 Switching Studies ....................................................................................................... 36
4.6 Voltage Stability ......................................................................................................... 36
4.7 Transient Stability ...................................................................................................... 38
4.7.1 Minimum Data Requirements ....................................................................................................... 38
4.7.2 Criteria ........................................................................................................................................... 38
4.7.3 Methodology ................................................................................................................................. 39
4.7.4 Results ........................................................................................................................................... 41
4.7.5 Transient Instability ....................................................................................................................... 424.8 Small Signal Stability .................................................................................................. 43
4.8.1 Minimum Data Requirements ....................................................................................................... 43
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
3/91
Draft as of March 2012 3
4.8.2 Criteria ........................................................................................................................................... 434.8.3 Methodology ................................................................................................................................. 44
4.8.4 Results ........................................................................................................................................... 45
4.9 Sub-synchronous Resonance (SSR) Studies .................................................................. 45
4.9.1 Minimum Data Requirements ....................................................................................................... 46
4.9.2 Frequency Scanning ...................................................................................................................... 47
4.9.3 Eigenvalue Analysis ....................................................................................................................... 47
4.10 Generation Facilities ................................................................................................... 484.10.1 Integration of Generation Facilities .......................................................................................... 484.10.2 Renewable Generation ............................................................................................................. 49
4.10.3 Minimum Data Requirements .................................................................................................. 50
4.10.4 Type of Studies ......................................................................................................................... 50
4.11 Quality of Supply Studies ............................................................................................ 50
4.11.1 Unbalance Studies .................................................................................................................... 50
4.11.2 Voltage Distortion Studies ........................................................................................................ 51
4.12 Right of Way and Environmental Considerations ......................................................... 51
5. Transmission Assets................................................................................................. 52
5.1 Introduction ............................................................................................................... 52
5.2 Transformers ............................................................................................................. 52
5.3 Switchgear ................................................................................................................. 53
5.3.1 PCBs ............................................................................................................................................... 53
5.3.2 Isolators or Disconnecting Switches .............................................................................................. 54
5.3.3 Gas Insulated Switchgear .............................................................................................................. 54
5.4 Transmission Lines ..................................................................................................... 54
5.4.1 Design of Transmission Lines ........................................................................................................ 54
5.4.2 Thermal Limits ............................................................................................................................... 55
5.4.3 Voltage Limits ................................................................................................................................ 56
5.4.4 Conductor Optimization ................................................................................................................ 56
5.5 Capacitors (Series and Shunt) ..................................................................................... 56
5.5.1 General .......................................................................................................................................... 56
5.5.2 Shunt Capacitors ........................................................................................................................... 56
5.5.3 Series Capacitors ........................................................................................................................... 58
5.6 Reactors (Series and Shunt) ........................................................................................ 59
5.6.1 Application of Shunt Reactors ....................................................................................................... 59
5.6.2 Switchgear ..................................................................................................................................... 60
5.6.3 Other Types of Reactors ................................................................................................................ 60
5.7 HVDC Schemes ........................................................................................................... 61
5.8 FACTS Devices ............................................................................................................ 625.8.1 SVCs ............................................................................................................................................... 62
5.8.2 STATCOM ...................................................................................................................................... 63
5.8.3 TCSC ............................................................................................................................................... 63
5.8.4 Unified Power Flow Controller (UPFC) .......................................................................................... 64
5.8.5 Thyristor Controlled Breaking Resistor (TCBR) .............................................................................. 64
5.9 Busbar ....................................................................................................................... 64
6. Transmission Planning in a Market Environment...................................................... 65
6.1 Introduction ............................................................................................................... 65
6.2 Coordination Among the Regulated Transmmission Entity, Grid Customers, System
Operator and Market Operator............................................................................................... 65
6.3 Open Access and Grid Planning ................................................................................... 65
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
4/91
Draft as of March 2012 4
6.4 Alleviation of Congestion to Enhance Market Efficiency .............................................. 65
6.5 Market Impact Studies to Assess Impact on WESM of Congestion Alleviation CAPEX
Projects .................................................................................................................................. 66
6.6 Impact of Different Generation Patterns ..................................................................... 66
7. Project Selection and DocumenTation ...................................................................... 67
7.1 Introduction ............................................................................................................... 677.2 Project Evaluation ...................................................................................................... 67
7.2.1 Defining the Problem .................................................................................................................... 68
7.2.2 Selecting Potential Solutions ......................................................................................................... 697.2.3 Technical Analysis.......................................................................................................................... 70
7.2.4 Market Analysis ............................................................................................................................. 70
7.2.5 Financial Analysis .......................................................................................................................... 74
7.3 Prioritization .............................................................................................................. 78
7.4 Project Documentation .............................................................................................. 78
REFERENCES ................................................................................................................... 81
APPENDIX A: List of Standards used by the Regulated Transmission Entity for Transmission
Line design ..................................................................................................................... 83
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
5/91
Draft as of March 2012 5
Date Issued: 21 March 2012
Document Name: Transmission Planning Guideline rev 8
Document Version: Draft Transmission Guideline
Project Team: Pieter Nel, Machiel Coetzee, Dr Yen-Shong Chiao, Kris Tampinco
Name of Project: Development of Transmission Planning Guidelines
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
6/91
Draft as of March 2012 6
ABBREVIATIONS
ABBREVIATION TERM
A
A Ampere
AAC All Aluminum ConductorAAAC All Aluminum Alloy Conductor
AC Alternating Current
ACSR Aluminum Conductor Steel Reinforced
AIS Air Insulated Switchgear
AVR Automatic Voltage Regulator
B
C
CAPEX Capital Expenditure
CCC Capacitor Commutated Converter
CPV Concentrated PhotovoltaicCSP Concentrated Solar Power
CT Current Transformer
CVC Constraint Violation Coefficient
D
DC Direct Current
DCF Discounted Cash Flow
DDP Distribution Development Plan
DFIG Double-fed Induction Generator
DOE Department of Energy
DU Distribution Utility
EEENS Expected Energy Not Supplied
EPIRA Electric Power Industry Reform Act (R.A. No. 9136)
Eq Voltage behind Transient Reactance
ERC Energy Regulatory Commission
F
FACTS Flexible AC Transmission System Devices
G
GIS Gas Insulated Switchgear
GTO Gate Turnoff
H
HVAC High Voltage Alternating Current
HVDC High Voltage Direct Current
Hz Hertz
I
IGBT Insulated Gate Bipolar Transistor
J
K
kA Kilo Ampere
km Kilometer
kV Kilovolt
kWh kilo Watt Hour
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
7/91
Draft as of March 2012 7
ABBREVIATION TERM
L
LC Inductive-Capacitive
LV Low Voltage
LWAP Load Weighted Average Price
M
MAE Mean Absolute ErrorMAPE Mean Absolute Percentage Error
MDOM Market Dispatch Optimization Model
MOV Metal Oxide Varistor
ms Milliseconds
MSE Mean Squared Error
MTS Main Transmission System
MV Medium Voltage
MVA Megavolt Ampere
MVAr Megavolt Ampere Reactive
MW Megawatt
MWH Megawatt Hour
N
NGCP National Grid Corporation of the Philippines
NPV Net Present Value
O
OPGW Optical Fiber Ground Wire
P
PCB Power Circuit Breaker
PDM Price Determination Methodology
PDP Power Development Program
PEP Philippine Energy Plan
PGC Philippine Grid CodePhP Philippine Pesos
PSM Price Substitution Methodology
PSS Power System Stabilizers
PSS/E Power System Simulator for Engineering
pu Per Unit
PV Photovoltaic
Q
R
RMS Root-Mean-Square
RMSE Root Mean Squared ErrorsRTWR Rules for Setting Transmission Wheeling Rates
RTU
S
SCO Synchronous Condenser
SIL Surge Impedance Loading
SPS Special Protection System
SRMC Short Run Marginal Cost
SSE Sum of Squared Errors
SSR Subsynchronous Resonance
STATCOM Static Condenser or Compensator
SVC Static VAr Compensator
T
TCBR Thyristor Controlled Breaking Resistor
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
8/91
Draft as of March 2012 8
ABBREVIATION TERM
TCR Thyristor Controlled Reactor
TCSC Thyristor Controlled Series Capacitors
TDP Transmission Development Plan
TIS Torsional Interaction Susceptibility
TSC Thyristor Switched Capacitor
TOSP Time of System Peak
UUPFC Unified Power Flow Controller
V
VAr Volt Ampere Reactive
VSC Voltage Sourced Converter
VT Voltage Transformer
W
WESM Wholesale Electricity Spot Market
X
Y
Z
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
9/91
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
10/91
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
11/91
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
12/91
Draft as of March 2012 12
GENERAL STATEMENT
This document serves as a guide to the Regulated Transmission Entity of the Philippines in planning
its transmission network and to aid in the preparation of the capital expenditure (CAPEX) forecasts in
the Revenue Application that it must submit to the Energy Regulatory Commission (ERC) prior to each
regulatory period. It is intended that the information to be submitted to support the RevenueApplication will have a similar content and structure to the Transmission Development Plan (TDP) that
will be submitted to the Department of Energy (DOE) but may include additional information specific to
the requirements set out by the DOE and the Philippine Grid Code (PGC).
The requirements set out in this guideline are the minimum requirements of the ERC but do not
replace or supersede any additional requirements set out in the Rules for Setting Transmission
Wheeling Rates (RTWR) and the PGC. In addition, the requirements set out in this guideline should
not be interpreted as overriding the responsibility of the Regulated Transmission Entity to determine
and justify the CAPEX needed to provide the level of service its consumers expect.
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
13/91
Draft as of March 2012 13
1. INTRODUCTION
1.1 INTRODUCTION
Efficient and effective grid planning is critical for maintaining the quality of service expected
from the Regulated Transmission Entity as well as in managing the growth of the power
system. Such planning process includes assessments that will assist in ensuring that theRegulated Transmission Entitysassets are fully leveraged and that availability and quality of
supply is not sacrificed. The processes detailed in this guideline will aid the Regulated
Transmission Entity in identifying solutions to network problems as well as prioritizing the
improvements by undertaking the necessary analysis that will ensure the appropriate balance
between the overall cost of a project and the expected benefit to the customers.
The RTWR1requires the Regulated Transmission Entity to provide its forward forecasts of its
proposed annual CAPEX for each year of the regulatory period. Such forecasts will be
reviewed as to whether it is cost effective; reasonably efficient from a design and
implementation point of view; and is likely to support the forecast growth in customer, co-
incident peak demand and energy delivered to enable the Regulated Transmission Entity to at
a minimum meet its target levels of performance. Furthermore, the PGC2 identifies that the
Regulated Transmission Entity has lead responsibility for grid planning and has further
specified the required technical studies and planning procedures. From these requirements it
is apparent that the Regulated Transmission Entity should have an accurate and robust
planning process in place not only to support its proposed CAPEX but also to align with the
objectives of the Electric Power Industry Reform Act3(EPIRA) to set an efficient grid planning
process in order to ensure the quality, reliability, security and affordability of electrical
transmission services.
This guideline was developed consistent with the requirements of the PGC. The documentspecifies standards and criteria for grid planning as well as explains the required technical
studies not only taking into account the power quality requirements in the PGC but also
considering the best practices of transmission entities in other jurisdictions. Moreover, to aid
the Regulated Transmission Entity in planning transmission projects, this guideline also
includes information on planning transmission equipment; planning in a market environment;
and how to evaluate as well as prioritize projects.
1.2 PLANNING HORIZON
The RTWR specifies that the electricity transmission system planning horizon is fifteen (15)
years or as otherwise determined by the ERC based on reasonable planning policies. Thus,for purposes of grid planning by the Regulated Transmission Entity, long-term studies
employing a planning horizon of fifteen (15) years (unless revised by the ERC), are required to
be conducted in order to determine the most beneficial technologies to serve long-term
system requirements and identify strategic power corridors. The same planning horizon shall
be utilized for evaluating the expected level of use of transmission assets in order to manage
the effect of optimization on CAPEX projects.
1 Rules for Setting Transmission Wheeling Rates for 2003 to around 2027, Energy Regulatory Commission, Philippines,
September 2009.2Philippine Grid Code Amendment No. 1, Grid Management Committee, Energy Regulatory Commission, Philippines, April
2007.3Electric Power Industry Reform Act (Republic Act No. 9136), Congress of the Philippines, July 2000.
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
14/91
Draft as of March 2012 14
1.3 PLANNING PROCESS
It is the intent of this guideline to set an effective planning process in order to ensure
sustainability and efficiency of transmission services which is the primary objective of
regulation. Moreover, in relation to the regulatory reset process for the Regulated
Transmission Entity, this guideline will aid in the preparation of the proposed CAPEX referred
to in Section 5.10 of the RTWR which forms part of the Revenue Application to be submitted
by the Regulated Transmission Entity to the ERC. Such Revenue Application will be submittedat the date determined by the ERC after reviewing all the issues raised following the release of
the Issues Paper. Pursuant to Section 7.1.2 of the RTWR, the Issues Paper will be published
not less than 21 months prior to the start of each regulatory period. The Third Regulatory
Period has commenced on January 1, 2011 and will end on December 31, 2015. Thus, it is
expected that the Fourth Regulatory Period will commence on January 1, 2016.
The RTWR and the Issues Paper specifies the minimum requirements for CAPEX
applications. To further assist the Regulated Transmission Entity in its application to the ERC,
this guideline details the specific process the Regulated Transmission Entity has to follow in
formulating project requests keeping in mind issues relating to the technical, environmental
and economic aspects of the project.
Transmission Development Plan (TDP)
While this guideline is intended to assist in the regulatory reset process, it is expected that
having an effective planning process in place will also assist in the preparation of the TDP
given that as per Section 10(a) of the EPIRA, the TDP is primarily a plan for managing the
transmission system through efficient planning.
The main difference between the TDP and the forecast CAPEX application is that the TDP is
prepared annually by the Regulated Transmission Entity to be submitted for approval to the
DOE for integration into the Power Development Program (PDP) and the Philippine Energy
Plan (PEP). On the other hand, the forecast CAPEX application is prepared once every
regulatory reset. It should be noted however that any plan for expansion or improvement of
transmission facilities is required to be approved by the ERC pursuant to Section 10(c) of the
EPIRA,
Another difference between the forecast CAPEX and the TDP is that the forecast CAPEX
considers only projects for the next five (5) years of the regulatory period while the TDP
covers a 10-year plan. The Regulated Transmission Entity has however indicated that the first
years of the TDP normally constitute the CAPEX approved by the ERC for the Regulatory
Period while the latter years of the 10-year period are indicative projects.
The Regulated Transmission Entity is required under the EPIRA to consult electric power
industry participants in the preparation of the TDP. In relation to grid planning, and as also
indicated below, it is recommended that the grid users, market operator and system operator
also be consulted during the planning process in order to assist the Regulated Transmission
Entity in identifying congestion problems that may result in increased electricity prices due to
transmission congestion.
Philippine Grid Code (PGC)
Section 5.2.1 of the PGC states that the Regulated Transmission Entity shall have leadresponsibility for grid planning including:
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
15/91
Draft as of March 2012 15
a) Analyzing the impact of the connection of new facilities;
b) Planning expansion of the grid to ensure its adequacy to meet forecasted demand
and the connection of new generating plants; and
c) Identifying congestion problems that may result in increased outages or raise the
cost of service significantly.
It is worth emphasizing that while the lead responsibility falls under the Regulated
Transmission Entity, coordination with grid users, the market operator and the system
operator is necessary during the planning process (and not only during real time) in order to
assist in identifying congestion problems that may result in increased electricity prices due to
transmission congestion. This need is further explained in Section 6 of this guideline.
Consistent with Chapter 5 of the PGC, Section 4 of this guideline specifies the different grid
planning studies required to be conducted by the Regulated Transmission Entity in order to
ensure the safety, reliability, security and stability of the grid. Section 4 also includes other
studies deemed necessary to efficiently perform the responsibilities of the Regulated
Transmission Entity. Moreover, Section 4 of this document also details the data requirementsfor the different types of planning studies to be undertaken by the Regulated Transmission
Entity.
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
16/91
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
17/91
Draft as of March 2012 17
present the results of the analysis to the ERC in relation to the affected CAPEX projects as
part of its Revenue Application.
In terms of the forecasts required for the Market Simulation Model, it is recommended that the
relevant historic load data e.g. hourly load for each modeled node, are obtained from the
market operator for the purpose of preparing the forecast load profile or load duration curve for
the forecast years.
In order to ensure consistency with the DDP, PDP, as well as with the forecasts used in the
WESM, the Regulated Transmission Entity should not alter any forecasts provided by DUs for
use in the development of its own forecasts. However in the review of the submitted forecasts,
the Regulated Transmission Entity is encouraged to clarify any issues with regards to the
forecasts provided by the DUs and await any revision to the forecasts if necessary.
2.3 FORECASTING METHODOLOGY
Forecasting models can be divided into statistically based and intelligence-based models and
all have different characteristics, features and strengths. The selection of the most suitable
forecasting model is highly dependent on the following parameters: forecast time frame, dataavailability, the accuracy and cost of the forecast, the application and purpose of the forecast.
5
Regarding the forecast time frame, as indicated in Section 2.1 above, the forecasting
technique required in relation to the regulatory reset process of the Regulated Transmission
Entity is long term forecasting which is intended for applications in relation to capacity
expansion as well as studies on the return of capital investments. The long term forecast is
required for a period of fifteen (15) years, which is the planning horizon set as per the RTWR
unless it is otherwise revised by the ERC, which will then be used to develop the capital
requirement for the next five (5) years which is the prescribed time frame for a regulatory
period.
Long term forecasts take into account historical load data, the number of customers in
different categories, the economic and demographic data and their forecasts, and other
factors. Typically, power utilities serve customers of different types such as residential,
commercial and industrial, and different factors affect the forecasting of each class. However,
in the case of the Regulated Transmission Entity, there appears to be no requirement to take
into account the different types of customers since these will already be taken into account in
the submitted forecasts by the DUs. Given this, the focus of the Regulated Transmission
Entity will be on historical load data, the economic and demographic data and their forecasts,
and other factors.
Statistically based methods forecast the current value of a variable by using explicit
mathematical combinations of the previous values of that variable and, possibly, previous
values of exogenous factors.6Long term forecasting using statistically based models require
years of economic and demographic data and is affected by environmental, economic, political
and social factors. The econometric approach is broadly used for long term forecasting which
combines economic theory and statistical techniques for forecasting electricity load demand.
The approach estimates the relationships between energy consumption and factors
5 Business Intelligence in Economic Forecasting: Technologies and Techniques, F. Elakrmi and N. A. Shikhah, Amman
University, Jordan.6Power System Planning, Howard Technology, Middle East.
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
18/91
Draft as of March 2012 18
influencing consumption. The relationships are typically estimated by the least-squares
method or time series methods.7
It should be noted that the availability of accurate and consistent information is an important
factor in the determination of which model to use. One reason for this is the difficulty in
forecasting demographic and economic factors versus that of load forecasting.8 If accurate
information on economic and demographic factors is not readily available, then the
econometric approach may not be the most suitable model. Extrapolation models whichinvolve fitting trend curves to basic historical data are simple and easy to use however is most
appropriate for short term projections because it ignores the possible interaction of load
demand with other economic factors.9 Thus, for long term forecasting using extrapolation
models, it is appropriate to take into account discounting the earliest elements of the forecast
by incorporating weighting factors (suitable weighting factors are from 0.25 to 0.90) in the
calculation of the least squares (best fit) solution.10
Intelligence-based models e.g. Fuzzy Systems, attempts to model the human reasoning
process at a cognitive level which requires expert knowledge. The algorithms associated with
intelligence-based models neither require a mathematical model that will map inputs to
outputs nor require precise inputs.11
Results of studies undertaken in different countries have indicated differences in terms of what
is most appropriate for long term forecasting. From other studies, statistically based models
are recommended to be used while there are also studies that indicate that intelligence-based
models prove superior to statistically based models.
It is the Regulated Transmission Entitys responsibility to select the most appropriate model
(or models, as several load forecasting methods may be used in parallel), whether it be
statistically based, intelligence based or a combination of different model types. To assist in
the selection, the Regulated Transmission Entity shall test the acceptability or the accuracy of
the algorithms. There are different measures to test the accuracy of a model e.g. the mean
absolute error (MAE), mean absolute percentage error (MAPE), sum of squared errors (SSE),
mean squared error (MSE) and root mean squared errors (RMSE).12
The MAPE and the SSE
are the most widely used for load forecasting, and in such accuracy tests, the difference
between the actual load and forecast load is calculated and the model with an error ranging
from 2-5% is considered as exhibiting good performance. Among the models that have
passed the test on accuracy, the model with the least error is the most suitable. The results of
the test on the model selection shall be documented by the Regulated Transmission Entity
and shall be made available during the review of the expenditure forecasts. Such
documentation should also be made available earlier in the regulatory reset process in the
event that the ERC requires such information to be submitted as part of the Revenue
Application.
7Applied Mathematics for Power Systems, E. A. Feinberg and D. Genethliou, State University of New York, New York.
8Modern Power System Analysis, D.P. Kothari, I.J. Nagrath, New York, 2008.
9Demand Forecasting for Electricity, N. Bohr.
10
Computer Analysis Methods for Power Systems, G.T. Heyat, New York. 11Fuzzy Ideology based Long Term Forecasting, J. H. Pujar, World Academy of Science, Engineering and Technology, India.
12 Long Term Energy Consumption Forecasting Using Genetic Programming, K. Karabulut, A. Alkan, A. Yilmaz, Yasar
University, Turkey, 2008.
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
19/91
Draft as of March 2012 19
3. STANDARDS AND CRITERIA
3.1 INTRODUCTION
The overall goal of the planning activities can be expressed as follows:
The planning of the grid or transmission system shall aim at the identification of the least-costalternative, or the alternative which maximizes the net benefit with due attention being paid to
major uncertainty factors and providing adequate security and reliability.
Grid planning has to be based on realities concerning geographical conditions, technical
status and possibilities, and the sizes and locations of the power markets. Due to the fact that
the Philippines power system is covering a widespread geographical area with scattered
population and long distances between the most inexpensive power resources and the power
market, integrated generation and grid planning has to be performed. Thus, grid planning also
has to be undertaken with the intention of identifying projects in close coordination and
cooperation with not only with DUs but more importantly with generation facilities.
The main task for the power industry in the Philippines would be to supply the customers with
electric power, in sufficient amount and with an economically viable supply quality.
In most countries, there is substantial competition between the different industry sectors of the
society to get capital for necessary investment and rehabilitation projects. The Philippines is in
this respect no exception. Since the power industry is so capital intensive, the requirements on
power supply reliability should generally not be too rigid; the stricter the criteria the higher the
investment to be called for.
A basic principle of grid planning is that all equipment should be within normal capacity ratings
and normal voltage limits when the system is operating with all scheduled elements in service
and is not experiencing faults or other abnormal faults or disturbances.
Furthermore, the system should be capable of operating within emergency capacity ratings
and emergency voltage limits immediately following a system fault that results in the loss of a
single element (N-1). The system operator will then manage the transmission system to return
to a healthy operating condition as soon as possible to ensure continuity of supply within the
capacity ratings and voltage limits.
An objective of this guideline is to use planning criteria also recognized in other jurisdictions to
assist the Regulated Transmission Entity in developing a secure and reliable transmission
system. The planning criteria described in this guideline shall be used for any new
transmission system development project in the Philippines.
It is the Regulated Transmission Entitys13
responsibility to identify many possible solutions to
satisfy the need and to comply with the planning criteria. It is also the task of the Regulated
Transmission Entity to rank the possible solutions in such a way that it can be acceptable to
the environment, complete the implementation in the time specified and that it is the best
solution with a good balance between technical fit and economic viability (techno-economic).
13 The Regulated Transmission Entity as the system planning engineer is responsible for the expansion needs of the
transmission system by conducting the appropriate power system studies to comply with the requirements as set out in thisguideline and the PGC.
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
20/91
Draft as of March 2012 20
The transmission system plan must comply with all the statutory and technical limits as
documented in the PGC and all other relevant standards and specifications that may be
applicable in the Philippines.
3.2 PERFORMANCE STANDARDS AS PER THE PGC
The Regulated Transmission Entity must ensure that the transmission system is designed to
comply with the quality requirements as stipulated in Chapter 3 of the PGC.
3.2.1 System Losses
The transmission system losses are a major concern to any utility. The aim for any system
planning engineer is to reduce the system losses as far as technically possible in the process
of developing the transmission system. It is the task of the Regulated Transmission Entity to
calculate the system losses for all possible alternatives considered and to use these results as
one of the drivers to determine the best techno-economic solution for system development.
Typically the Regulated Transmission Entity will calculate the impact on system losses for the
life time of the expected new project infrastructure as part of the project justification.
System loss shall be classified into three categories: Technical loss, non-technical loss and
administrative loss.
The technical loss shall be the aggregate of conductor loss, the core loss in transformers, and
any loss due to technical metering error.
The non-technical loss shall be the aggregate of the energy loss due to meter-reading errors
and meter tampering.
The administrative loss shall include the energy that is required for the proper operation of the
Grid.
3.2.2 Congestion
Congestion in relation to operating in a market environment has yet to be defined in the PGC.
For the purpose of grid planning as set out in this guideline, transmission congestion shall
mean a situation where, because the transmission limit of a transmission line or the capacity
of a transformer is reached and no more power may be transmitted through this line or
transformer, cheaper power from a generating unit cannot be dispatched and transmitted
through this line or transformer and instead more expensive power has to be dispatched to
meet the load demand.
While Chapter 3 of the PGC does not contain standards in relation to transmission congestion
as defined above, it is primarily the Regulated Transmission Entitys responsibility to identify
the congestion problems that may result in increased outages or raise the cost of service or
the electricity prices due to transmission congestions significantly. This is further explained in
Section 6 of this guideline.
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
21/91
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
22/91
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
23/91
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
24/91
Draft as of March 2012 24
During system healthy conditions no interconnected line is allowed to exceed the
normal continuous (thermal) limit of the line. This is the 75C thermal rating of the
transmission line.
2. N-1 Contingencies
During a single contingency or N-1 condition, no interconnected line is allowed to
exceed the emergency thermal limit of the line for a maximum period of 2 (two) hours.The thermal ratings are a function of the design and construction of the transmission
line. The rating of the terminal equipment should be taken into consideration. It is
possible that the terminal equipment of a specific line could be lower than the
emergency rating of the conductor and this will then act as the emergency rating of the
transmission line. It is advisable for the Regulated Transmission Entity to identify
these limiting conditions and replace the terminal equipment to increase the
emergency rating of the line to be equal to the conductor limit or 90C thermal rating of
the transmission line.
The Regulated Transmission Entity normally considers only the 75C thermal rating of
the transmission lines during system planning studies and not the 90C thermal rating
of the transmission line because such thermal rating of the transmission line should be
used for operational purposes only.
Loading of Transformers
The specific assessment to be used for any new development or upgrading of the
transmission system, must comply with the following criteria for transformer loading:
1. System Healthy Conditions
During system healthy conditions no transformer is allowed to exceed the nameplatecontinuous Megavolt Ampere (MVA) rating of the transformer. This is typically the
100% nameplate rating of the transformer in MVA.
2. N-1 Contingencies
During a single contingency or N-1 condition, no transformer is allowed to exceed the
nameplate continuous MVA rating of the transformer. This is typically the 100% of the
nameplate rating of the transformer in MVA.
The overloading of transformers is only for system operations and not for the purpose
of grid planning specifically in the consideration for system planning studies.
Series Capacitor Banks
The series capacitor bank must be designed in line with IEC standards. The IEC standard
specifies the following design criteria and any new development or upgrading of the
transmission system must be compliant to these criteria:
8 hours in a 12-hour period: 1.1 times rated current;
hour in a 6 hour period: 1.35 times rated current; and
10 minutes in a 2 hour period: 1.5 times rated current.
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
25/91
Draft as of March 2012 25
Shunt Capacitors or Shunt Reactors
The use of shunt capacitor banks or shunt reactors for voltage control must be sized in such a
way that it does not cause a voltage change of more than three percent (3%) during system
healthy conditions when it is active in the transmission system. Furthermore, in an N-1
contingency scenario, the voltage change must not exceed five percent (5%) when it is active
in the transmission system.
Power Circuit Breakers
Newly-commissioned power circuit breakers (PCBs) should be selected with somewhat high
interrupting capacities, potentially more than the initial fault level in the area. This is to avoid
frequent replacement every time there are new generation facilities nearby or new
transmission lines terminated at the station that contributes to higher fault level. The
Regulated Transmission Entity shall standardize on PCB sizes which will be a good strategic
method to minimize the number of spares that will be required.
The following is the limits specified for PCBs and shall not be exceeded:
Single-phase breaking current: 1.15 times 3 phase fault current
Peak breaking current: 2.55 times 3 phase root-mean-square (RMS) fault
current
Tap Changer
In order to determine whether capacitors are required to correct any voltage violations, all
transformers equipped with on-load tap changers should be adjusted to nominal rating. The
full range of the transformer taps should be available for the use of the system operator in
order to control the system voltages.
Voltage Control and Reactive Power Support
The Regulated Transmission Entity is not encouraged to use the reactive power capability of
generation facilities or the transformer tapping range to control system voltages in planning
studies. The use of shunt capacitors and shunt reactors should be considered to ensure
voltage limits are complied with during system healthy and contingency operation of the
transmission system.
The use of series compensation could be considered to increase voltage levels in long radial
networks. Static VAr compensators (SVCs) should be considered to provide dynamic voltagecontrol during system contingencies. The SVCs reactive capability should, however, not be
used during steady state operating conditions.
The reactive power capability of generation facilities and the tapping of transmission
transformers should only be used during N-1 contingencies and emergency situations and
should be viewed as operational supporting mechanisms rather than planning solutions.
For reactors the following planning criteria should be adhered to:
The size of switched reactors should be restricted to limit the change in system
voltage when any one unit is switched in or out of service. The voltage change shouldnot exceed three percent (3%) of the nominal voltage during system healthy condition
or five percent (5%) of the nominal voltage during single contingencies;
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
26/91
Draft as of March 2012 26
During minimum load and any one reactor out of service, the maximum continuous
system voltage should not be exceeded;
During minimum load and any one reactor out of service, the maximum reactive
power absorption capability of no generator unit may be exceeded; and
The steady state voltage at the line open end, resulting from energizing or tripping of a
transmission line circuit breaker during normal operating conditions, should notexceed the maximum continuous system voltage.
System Stability Limits
It is the objective of system stability simulations to analyze the stability of the transmission
system in a given time period. Consistent with Section 4.4.9.3 of the PGC, the maximum
clearing time per voltage level that shall be used for simulations in relation to grid planning
shall be as per the limits below. This is further explained in Section 4.7 of this guideline.
85 milliseconds (ms) for 500 kilovolt;
100 ms for 230 kV and 138 kV; and
120 ms for voltages less than 138 kV.
3.3.3 Power Factor Considerations
The power factor of the load has a major impact on the transmission system as it affects the
voltage profile and transmission losses. A bad power factor17
requires a high amount of
reactive power from the system. The Regulated Transmission Entity must either install
reactive devices to supply the MVArs for the load or buy reactive energy from the generation
facilities connected to the grid. The process of buying reactive energy is currently via Ancillary
Services Procurement Agreements between the Regulated Transmission Entity and interested
and qualified generation facilities; however, in the future ancillary services may already be
traded in the WESM. Even though, at this stage, power factor correction methods will be to a
certain extent an expensive exercise for the Regulated Transmission Entity, improving the
power factor at the loads will decrease the system losses and have a direct impact on
operating cost.
It is recommended that the Regulated Transmission Entity encourages the DUs and other
large customers to improve their power factor at the point of common coupling to values of
around 0.95 which is a typical practice in other jurisdictions.
Currently, the Regulated Transmission Entity utilizes the load power factors based on the
actual average power factor from the billing information of customers for purposes of
undertaking simulations.
3.3.4 Minimum and Peak Load Demand Considerations
The Regulated Transmission Entity has indicated that the minimum load demand in Luzon is
assumed to be 45% of the peak demand while for Visayas and Mindanao it is 60%. These
ratios according to the Regulated Transmission Entity are based from historical data, which
are then used to study the over-voltages during off-peak periods.
17A bad power factor is typically anything less than 0.95.
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
27/91
Draft as of March 2012 27
3.3.5 Planning for Disposal of Assets
At the end of the useful life of equipment, the Regulated Transmission Entity should undertake
a condition assessment in order to determine whether the equipment is required to be
replaced. It should be noted that assets should only be disposed when they can no longer be
economically justified and not because it has already reached the end of its useful life. In the
event that assets have already been identified for disposal based on the result of the condition
assessment, then such assets should be considered for replacement. It should however benoted that such projects, even if it is considered as a replacement project only, should still be
evaluated and documented in accordance with this guideline.
3.3.6 Planning for Generation
Power Plant location
It would be an ideal solution if the generation facilities could be located as close as possible to
the load which is in many cases is unattainable due to physical constraints or the specific
interest of investors. It is however recommended for the Regulated Transmission Entity to
make available the sites where incoming generation facilities can connect which entailsminimal transmission system reinforcement. In cases when the generation facility has already
decided on a location, the Regulated Transmission Entitys participation shall be in the
integration studies.
Embedded Generation
New embedded generation facilities will have an impact on the quality of supply, the fault
levels and stability of the grid and eventually on the operation, voltage control and operating
reserves. Thus, it is encouraged that embedded generation integration studies shall be a joint
effort among the relevant DU or large customer and the Regulated Transmission Entity.
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
28/91
Draft as of March 2012 28
4. TECHNICAL STUDIES
4.1 INTRODUCTION
This section provides guidelines for the different applicable studies that are required to be
performed as part of developing a transmission system plan. This guideline is established
specifically for developing a plan that will assist the Regulated Transmission Entity in theregulatory reset process but is also foreseen to aid in the development of the TDP. The
applicable studies described in this section include load flows (steady state analysis), transient
stability, voltage stability, small signal analysis, quality of supply, frequency stability and
switching studies.
4.2 DATA REQUIREMENT
Any technical study requires information describing assets to various levels of technical detail.
Below is a list of required data that shall be used in performing the required technical studies.
The following data requirement is also consistent with the requirements set in the PGC.
Historical energy and load demand data
Forecasted energy and load demand data
Generator unit data
o De-rated capacity (in Megawatt (MW));
o Additional capacity (in MW) obtainable from generating units in excess of net
declared capability;
o Minimum stable loading (in MW);
o Reactive power capability curve;
o Stator armature resistance;
o Direct axis synchronous, transient, and sub-transient reactances;
o Quadrature axis synchronous, transient, and sub-transient reactances;
o Direct axis transient and sub-transient time constants;
o Quadrature axis transient and sub-transient time constants;
o Turbine and generating unit inertia constant (in MW sec/MVA);
o Rated field current (in Ampere (A)) at rated MW and MVAr output and at rated
terminal voltage; and
o Short circuit and open circuit characteristic curves.
The following information for step-up transformers is required for each generating unit:
o Rated MVA;
o Rated Frequency (in Hertz (Hz));
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
29/91
Draft as of March 2012 29
o Rated voltage (in kV);
o Voltage ratio;
o Positive sequence reactance (maximum, minimum, and nominal tap);
o Positive sequence resistance (maximum, minimum, and nominal tap);
o Zero sequence reactance;
o Tap changer range;
o Tap changer step size; and
o Tap changer type (on load or off circuit).
The following excitation control system parameters is required for each generating
unit:
o
Direct current (DC) gain of excitation loop;
o Rated field voltage;
o Maximum field voltage;
o Minimum field voltage;
o Maximum rate of change of field voltage (rising);
o Maximum rate of change of field voltage (falling);
o Details of excitation loop described in diagram form showing transferfunctions of individual elements;
o Dynamic characteristics of over-excitation limiter; and
o Dynamic characteristics of under-excitation limiter.
The following speed-governing system parameters is required for each reheat steam
generating unit:
o High pressure governor average gain (in MW/Hz);
o Speeder motor setting range;
o Speed droop characteristic curve;
o High pressure governor valve time constant;
o High pressure governor valve opening limits;
o High pressure governor valve rate limits;
o Re-heater time constant (active energy stored in re-heater);
o Intermediate pressure governor average gain (in MW/Hz);
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
30/91
Draft as of March 2012 30
o Intermediate pressure governor setting range;
o Intermediate pressure governor valve time constant;
o Intermediate pressure governor valve opening limits;
o Intermediate pressure governor valve rate limits;
o Intermediate pressure governor loop; and
o A governor block diagram showing the transfer functions of individual
elements.
The following speed-governing system parameters is required for each non-reheat
steam, gas turbine, geothermal, and hydro generating unit:
o Governor average gain;
o Speeder motor setting range;
o Speed droop characteristic curve;
o Time constant of steam or fuel governor valve or water column inertia;
o Governor valve opening limits;
o Governor valve rate limits; and
o Time constant of turbine.
The following plant flexibility performance data is required for each generation facility:
o Rate of loading following weekend shutdown (generating unit and generation
facility);
o Rate of loading following an overnight shutdown (generating unit and
generation facility);
o Block load following synchronizing;
o Rate of load reduction from normal rated MW;
o Regulating range; and
o Load rejection capability while still synchronized and able to supply load.
The following auxiliary load demand data is required:
o Normal unit-supplied auxiliary load for each generating unit at rated MW
output; and
o Each generation facility auxiliary load where the station auxiliary load is
supplied from the grid.
General grid data required:
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
31/91
Draft as of March 2012 31
o The electrical diagrams and drawings are required to indicate the quantities,
ratings, and operating parameters of the following:
Equipment (e.g., generating units, power transformers, and circuit
breakers);
Electrical circuits (e.g., overhead lines and underground cables);
Substation bus arrangements;
Grounding arrangements;
Phasing arrangements; and
Switching facilities.
o The following circuit parameters are required:
Rated and operating voltage (in kV);
Positive sequence resistance and reactance (in ohm);
Positive sequence shunt susceptance (Siemens or ohm-1);
Zero sequence resistance and reactance (ohm); and
Zero sequence susceptance (Siemens or ohm-1).
o The following data is required for a step-up and power transformers:
Rated MVA;
Rated voltages (kV);
Winding arrangement;
Positive sequence resistance and reactance (at max, min, and
nominal tap);
Zero sequence reactance for three-legged core type transformer;
Tap changer range, step size and type (on-load or off-load); and
Basic lightning impulse insulation level (in kV).
o The following information is required for the switchgear, including circuit
breakers, load break switches, and disconnect switches:
Rated voltage (in kV);
Rated current (in A);
Rated symmetrical RMS short-circuit current (in kA); and
Basic lightning impulse insulation level (in kV).
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
32/91
Draft as of March 2012 32
o The following data on independently-switched reactive power compensation
equipment is required:
Rated capacity (in MVAr);
Rated voltage (in kV);
Type (e.g., shunt inductor, shunt capacitor, SVC); and
Operation and control details (e.g. fixed or variable, automatic, or
manual).
o The following data is required if a customers load demand may be supplied
from alternative connection point(s):
The alternative connection point(s);
The demand normally supplied from each alternative connection
point;
The demand which may be transferred from or to each alternative
connection point; and
The control (e.g., manual or automatic) arrangements for transfer
including the time required to affect the transfer for forced outage and
planned maintenance conditions.
The data requirement specified in Section 4.2 is required, where relevant, if a distribution
system (or other customer or end-user system) has embedded generation facilities and
significantly large motors. The short circuit contribution of the embedded generating units and
the large motors at the connection point shall be provided by the DU (or the other customer or
end-user). The short circuit current shall be calculated in accordance with the IEC Standards
or any equivalent national standards.
4.3 LOAD FLOW STUDIES
Load flow studies are typically conducted using a computer simulation package (e.g. Power
System Simulator for Engineering (PSS/E)) with a valid study file containing the grid model.
The purpose of the study is to determine whether an existing or reinforced system can satisfy
the voltage and current limits, under steady state conditions, when the system is healthy or
when one or more components are out of service.
4.3.1 Minimum Data Requirements
To be able to compare a proper load flow scenario the following data is required at a
minimum:
Load forecast for peak and light load at each substation
Positive sequence parameters for all equipment:
o Resistance;
o Reactance;
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
33/91
Draft as of March 2012 33
o Susceptance;
o Line length; and
o Rating of equipment.
Generation patterns and constraints
4.3.2 Criteria and Study Scenarios
Load flow studies should be conducted for the following network conditions:
a) annual peak load, typical generation pattern with peaking plant in generation mode;
and
b) light load scenario (the minimum load given by the load forecast) and generation
scaled down to light load scenarios.
The grid should be studied for healthy conditions and for N-1 contingencies. N-2 or greater
contingencies (including generation contingencies) will only be investigated when it isconsidered likely that a valid business case will exist to justify the additional capital
expenditure to address them.
For light load conditions, the system is only studied for healthy conditions as maximum
voltages are likely to occur with all lines in service. Potentially, the only contingency condition
that could increase the voltage is the loss of a shunt reactor or the loss of load. Furthermore,
if there is shunt reactors in the system under investigation, studies must still be conducted to
ensure that no unacceptable over-voltages will occur.
Each network scenario should include a calculation of system losses which will typically form
part of the financial justification of the project.
4.3.3 Load Assumptions
Since individual loads peak at different times, the total system maximum demand at time of
system peak (TOSP) is less than the sum of the individual peak loads. To obtain realistic
generation conditions and average loading and losses in studies of the overall transmission
system, each individual peak load is scaled down by a diversity factor such that the total load
on the generation facilities matches the forecasted load for the total system. The adjusted
loads are known as diversified maximum demands.
For studies of selected areas in the system (regions or islands), individual loads should beadjusted such that the total load in that area matches the actual or expected maximum value.
It is probable that these values will occur at a time different from the TOSP.
For studies where the supply to only one specific load point or customer is being investigated,
the actual undiversified peak value of this load or substation should be used.
For light loading scenarios the minimum load must be based on historical data for each grid,
e.g.:
Luzon 45% of system peak
Visayas 60% of system peak
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
34/91
Draft as of March 2012 34
Mindanao 60% of system peak
4.3.4 Generation Assumptions
The Regulated Transmission Entity is currently undertaking studies using the dispatch
scenarios for Luzon, Visayas and Mindanao as set out below. These have been reviewed and
assessed to be acceptable and is therefore recommended to be used in the conduct of load
flow studies.
Luzon
The following generation dispatch conditions shall be used:
Maximum North-Wet (all generation facility outputs in the northern part of the grid are
set to their maximum capacities)
Maximum South-Dry (all generation facility outputs in the southern part of the grid are
set to their maximum capacities)
Typical scenario (generation facility outputs are based on the typical output levels of
plants during system peak load).
The above scenarios shall ensure that regardless of dispatch combination, the N-1
compliance of the grid is assessed for all possibilities. Additional scenarios are also currently
being considered by the Regulated Transmission Entity for particular study areas where
varying dispatch output of associated generation facilities could result in additional
transmission system constraints.
Visayas
The following generation dispatch conditions shall be used:
Maximum Leyte Scenario (the geothermal generation facilities in Leyte are maximized
while the generation facilities in Panay serve as regulating plants; the power plants in
Cebu, Negros and Bohol are maximized)
Maximum Panay Scenario (the generation facilities in Panay are maximized while the
geothermal generation facilities in Leyte serve as regulating plants; the generation
facilities in Cebu, Negros and Bohol are maximized).
For the Visayas dispatch scenarios above, the following general considerations shall be
observed:
Base load generation facilities are priority dispatch over peaking generation facilities.
In case base load generation facilities are already sufficient to supply the entire load
requirement of the Visayas grid, which is mostly the case upon entry of additional
generation facilities, all peaking plants are assumed to be offline;
Intermittent generation facilities are assumed either at full dispatch or offline
depending on which is the worst scenario; and
Embedded generation facilities are assumed online until the end of their bilateral
contract.
Mindanao
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
35/91
Draft as of March 2012 35
The generation dispatch scenario that shall be used for Mindanao is the Maximum North
Scenario. This scenario shall be used to guarantee the adequacy of transmission lines that will
deliver power to the South and Northwestern Mindanao areas during contingencies. The
assumption for the scenario is that the power, especially those coming from hydro-electric
generation facilities are maximized thereby stressing the highest loading to the transmission
lines that supply power to the load centers i.e. Davao and General Santos.
4.4 SHORT CIRCUIT STUDIES
Fault level studies should be done for a number of reasons as listed below:
Any new planned grid reinforcement requires a fault level analysis to determine if fault
level values are going to exceed the ratings of existing equipment such as circuit
breakers, current transformers (CTs), or other switchgear and busbars;
For relevant new assets, appropriate fault ratings are determined by fault level studies
which should consider planned projects including generation which may have an
impact on the fault level in future. This is to ensure that new equipment is not required
to be replaced due to rising fault level increases in the short term;
Studies for the connection of new voltage waveform distorting load (e.g. arc furnaces,
mine winders, etc.) or switching of large motors require that the minimum credible
fault level is determined;
Fault level studies should be performed as an input to calculating protection settings.
This is to ensure that protection relays operate correctly in response to faults;
Fault level studies should be performed for high voltage direct current (HVDC)
termination points in the network to determine the relative maximum size of a
converter station when conventional HVDC is considered; and
Fault level studies should be performed to determine the maximum size of shunt
devices at a specific location.
Overview studies of fault levels throughout the system only require the calculation of three (3)
phase fault levels (using only the positive sequence network). Generation facilities should be
represented by a voltage of 1 per unit (pu) behind a saturated sub-transient reactance and all
transformers by their reactances on nominal tap. The Regulated Transmission Entity shall
consider the scenario of all generation facilitiesonline to get the most conservative values.
When higher accuracy is required, fault studies should follow a load flow study in which themagnitude and angle of the generation facility voltages behind transient reactances are
derived and the appropriate tap positions and reactances of the various transformers are
calculated. To determine maximum possible fault levels, all existing generation facilities (even
small generation units) should be in service and active.
Single phase fault analysis requires setting up the negative and zero sequence parameters in
addition to the positive sequence parameters in the PSS/E model. Furthermore, the
grounding setup for transformers needs to be accurately modeled. It is noted that, if
transformers are solidly earthed a single phase fault level can exceed three (3) phase levels in
certain scenarios.
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
36/91
Draft as of March 2012 36
Circuit breakers that exceed rupturing capacity18
and other assets for which technical
limitations have been breached should be replaced to avoid risk of damage to assets and
personnel. As an interim solution, or permanent solution at the expense of operational
flexibility, the assets which were identified to be replaced could be operated by reducing fault
in-feeds19
instead of replacing these assets. This reduction in fault in-feeds can be done by
splitting busbars, adding fault limiting reactors, or bypassing the over-stressed bus with certain
lines. It is important to note that the above solution is an operational solution and not a
planning solution and the solution is therefore not viewed as a medium to longer term solution
when planning the network.
Fault level revisions should be communicated to customers whenever an expansion plan is
expected to have a significant impact on fault levels. Communicating to customers in a timely
manner will allow customers the opportunity to take necessary action to ensure their
equipment can withstand the revised fault levels.
To determine the minimum credible fault level at a particular point of the transmission system,
a fault level study is performed with a load flow solution including the most onerous
contingency (N-1) or as appropriate. The values obtained is used to determine if a large motor
can be started; or if additional reinforcement is required to raise the fault level sufficiently to
start the motor; or the customer could be advised that a soft motor starting system should be
installed. In general, this is more of a consideration for DUs than the Regulated Transmission
Entity, unless a customer is connected directly to the grid.
4.5 SWITCHING STUDIES
Load flow studies are typically used to calculate the initial and final steady state voltages when
lines, capacitors, reactors or loads are switched. On the other hand, switching studies
contribute to the decision making of the size and location of equipment such as capacitors and
reactors. Line reactors are tested to ensure that transmission lines can be energized without
exceeding voltage limits when a reactor is in service. These studies should be conducted to
ensure that the voltage change is less than three percent (3%) when switching shunt
capacitors in and out or when switching interruptible loads. A typical value of 5% can be used
during single contingencies in the network.
For switching studies, variable MVAr devices are allowed to operate normally, but transformer
taps are fixed and no switching of shunt capacitors or reactors is allowed.
Dynamic switching studies, to determine instantaneous voltages after a switching operation
may be required for insulation coordination. These studies require the use of dynamic
programs (travelling wave, electro-magnetic transient programs etc.) and are generally theresponsibility of the generation facilities (however, the Regulated Transmission Entity may
participate in such studies).
4.6 VOLTAGE STABILITY
Voltage stability refers to the ability of a system to maintain steady voltages at all buses in the
system, from a given initial operating condition, after being subjected to a fault or disturbance.
Voltage stability depends on the ability of the system to maintain equilibrium between load
supply and load demand. Voltage instability occurs in the form of a progressive rise or fall of
18 Rupturing capacity or breaking capacity expresses the current that a circuit breaker is capable of breaking at a givenrecovery voltage under certain set conditions of operation.19
Fault in-feeds refer to fault current flowing into the transmission system linked directly to an asset or assets.
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
37/91
Draft as of March 2012 37
voltages of some buses and may lead to the loss of load in an area, tripping of transmission
lines and other elements by their protection circuits. These outages may lead to more
outages that in turn may lead to loss of synchronism or activation of the under field current
limit protection of some generation facilities.
At transmission voltages (higher voltages), the voltage drop at the receiving end is mainly
caused by the flow of reactive power through the reactance of the transmission system. The
reactive power flow in the system will be reduced if reactive power is supplied at the receivingend. This is typically achieved by means of e.g. shunt capacitors, SVCs, generation facilities,
synchronous condensers or some flexible AC transmission system (FACTS) devices.
Generation facilities, synchronous condensers and SVCs are variable reactive power or MVAr
sources and could be used to supply reactive power and to keep the voltage more constant.
The maximum angle, as measured between two directly connected substations, should
preferably not exceed 45oor 50
o.
The voltage stability limit can be established for any given system by carrying out load flow
studies with progressively increased loads until the load flow fails to converge20
. The power
flow just before the point of non-convergence is assumed to be the maximum power that can
be supplied before the voltage collapses. It would be impractical to attempt to operate the
system at this point since small load variations are bound to occur. In practice, the maximum
power transfer should be restricted to a value of typically ten percent (10%) below the
maximum value (knee-point of the power voltage-curve).
The maximum power transfer is limited either by voltage collapse or by an unacceptably low
receiving end voltage as follows:
ten percent (10%) less than the power level corresponding the point of non-
convergence as described above, or
the power which causes the receiving end voltage to reach the minimum
recommended value.
When an SVC is available in the area of study, the SVC dynamic range should not be used
completely to determine the steady state transfer capability. The maximum power transfer
should be limited to the point before the SVC starts to operate outside its normal steady state
position.
The Regulated Transmission Entity should look at the following equipment to improve the
voltage collapse limit of the transmission system:
Shunt capacitor banks to improve receiving end voltages;
Series capacitor banks to reduce line impedance and effectively increase receiving
end voltages. Series capacitor banks also increase the Surge impedance loading
(SIL) of a transmission line; and
Transmission lines as a more expensive solution to reduce system impedance.
20Being able to converge is the term used to explain that the load flow software found a numeric solution to the network model
which indicates that the solution modelled appear viable from a numeric perspective. Fails to converge is the term used toexplain that the load flow software did not find a numeric solution to the network model which indicates that the solutionmodelled appear not to be viable from a numeric perspective.
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
38/91
Draft as of March 2012 38
4.7 TRANSIENT STABILITY
The grid relies on synchronous machines for generation of electrical power and a necessary
condition for satisfactory system operation is that all synchronous machines remain in
synchronism. Transient stability is the ability of the system to maintain synchronism when
subjected to a severe fault or disturbance, such as a short circuit on a transmission line. The
resulting system response involves large excursions (oscillating or alternating motion away
from a point of equilibrium) of generator rotor angles and is influenced by the nonlinear power-angle relationship. Transient stability in this regard relates to first swing stability of the
transmission system.
4.7.1 Minimum Data Requirements
The following data is required to perform transient stability analysis:
Load flow case file representing the pre-fault state of the system;
Dynamics data file representing the dynamic behavior of each dynamic component;
and
Sequence of events.
The following items must be included in the dynamics data file to perform transient stability
simulations as the equipments dynamic behavior may influence the results:
Generation facilities;
Excitation systems;
Power system stabilizers (PSS);
Governors;
Loads; and
SVCs or HVDC or synchronous condensers (SCOs) or FACTS devices.
4.7.2 Criteria
Study scenarios
The characteristics of the transmission system should be such as to maintain stabilityfollowing:
A three phase line or busbar fault, cleared in normal protection times, with the system
healthy and the most onerous system loading condition;
A single phase fault cleared in bus trip times21
, with the system healthy and the most
onerous system loading condition; and
21Bus trip time is the time that the bus zone protection will take to strip a busbar when required due to a specific fault condition
and will differ from substation to substation.
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
39/91
Draft as of March 2012 39
A single phase fault cleared in normal protection times, with any one line out of
service and the generation facility loaded to average output.
Fault Clearing Times
The fault clearing time is defined as the time it takes for the protection equipment to clear or
remove the fault from the power system to allow normal operation to proceed. Typical fault
clearing times for the protection installed in the power system are as per the table below:
Table 1: Typical Clearing Times
TYPE OF FAULT 500kV 138 kV - 230kV
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
40/91
Draft as of March 2012 40
Faults that change the topology of the transmission system, change the system reactance and
alter the power-angle relationships of generation facilities shall be applied. These faults are
considered to have the most onerous impact on system stability and are specified as follows:
A three-phase zero impedance line-end fault cleared by tripping the faulted line;
A three-phase busbar fault cleared by tripping the relevant outlets from the associated
busbar;
Loss of generation;
Loss of major load; and
Loss of tie-lines.
As a note, three-phase faults are considered to have the most onerous impact on the system
from a transient stability point of view compared with that of a single phase faults.
Output Parameters
The following output parameters are not specific to transient stability results and contain
typical output parameters for any kind of stability study. The analysis of the output channels
(or variables that provide the resulting values from the study) allows the Regulated
Transmission Entity to differentiate between the different stability phenomena. The following
outputs are useful when interpreting the outcome of any stability analysis and can typically be
plotted relative to time.
Relative Rotor Angle and Speed: This information is used to determine whether the
machines(s) would remain in synchronism or not (pole-slip) following a fault. These
plots provide an indication of how the machines in an area are oscillating with respectto each other. The rotor angle variable output is used in assessing the magnitude and
duration of post-fault power system oscillations.
Generation Real Power: The real power variable output is used to determine whether
or not the power output of the generating unit is less than zero which would indicate
that the generating unit acts as a motor. In this event, the inverse power relay settings
should be examined to determine whether this would result in unit tripping. Typically,
an indication of oscillation frequencies and system damping can also be obtained from
these variable outputs.
Generation Reactive Power: The generation reactive power variable output is usedto determine whether or not the reactive power output will be sufficiently damped and
return within the continuous rating of the machine. Insufficient steady state voltage
support exists if the reactive power fails to recover within the continuous rating.
Bus Voltage: Variable output for bus voltages provide information on whether
machines remain in synchronism or not. The bus voltage variable output is useful in
assessing the magnitude and duration of post-fault voltage dips and peak-to-peak
voltage oscillations. Furthermore, these variable outputs provide an indication of
system damping and the level to which voltages are expected to return to its steady
state value.
-
7/25/2019 Draft Transmission Planning Guideline Mar 2012
41/91
Draft as of March 2012 41
Bus Frequency: The bus frequency variable output provides the magnitude and
duration of the post-fault frequency decline or increase in the transmission system,
especially during loss of load or generation.
Line Flows: The line flow variable output provides information on the magnitude of
the post-fault active and reactive power swings on transmission lines. Furthermore, it
provides information on transient power exchange and the occurrence of possible out-
of-step conditions between two grids or islands. As a note, when large powerreversals occur on transmission lines, out-of-step conditions may be evident.
Accelerating Power: The accelerating power variable output provides information
regarding the dynamic response of the prime mover system (turbine and governor
control system) of the machine. It also provides information on whether the machine
would remain in synchronism or not following a fault.
Generator Field Voltage: The generator field voltage variable output provides
information on the dynamic response of the exci