DRAFT SITE-SPECIFIC WORK PLAN FOR THE RVAAP 08 (LOAD LINE 1) IGNITER TUBE DISPOSAL RAVENNA ARMY AMMUNITION PLANT RAVENNA, OHIO CONTRACT NO. W912QR-04-D-0027 TASK ORDER 0001, MODIFICATION No. 2 OCTOBER 2008

Transcript of Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for...

Page 1: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

DRAFTSITE-SPECIFIC WORK PLAN

FOR THERVAAP 08 (LOAD LINE 1) IGNITER TUBE DISPOSAL

RAVENNA ARMY AMMUNITION PLANTRAVENNA, OHIO

CONTRACT NO. W912QR-04-D-0027TASK ORDER 0001, MODIFICATION No. 2

OCTOBER 2008

Page 2: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 3: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

INSERT CD SLEEVE HERE

Page 4: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 5: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

DISCLAIMER STATEMENT

This report is a work prepared for the United States Government by Shaw Environmental, Inc. In no event shall either the United States Government or Shaw Environmental, Inc. have any responsibility or liability for any consequences of any use, misuse, inability to use, or reliance on the information contained herein, nor does either warrant or otherwise represent in any way the accuracy, adequacy, efficacy, or applicability of the contents hereof.

Page 6: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 7: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

DOCUMENT SUBMISSION FORM

Form Approved 10/29/2007

1. REPORT DATE (DD-MM-YYYY)

2. REPORT STAGE 3. REPORT TYPE

5a. CONTRACT NUMBER 5b. PROJECT NUMBER

4. REPORT TITLE AND SUBTITLE

5c. TASK NUMBER

6. AUTHOR(S) 7. PERFORMING ORGANIZATION NAME(S) AND ADDRESS(ES) 8. SPONSORING/MONITORING AGENCY NAME(S) AND ADDRESS(ES) 9. ARMY ENVIRONMENTAL CLEANUP PERMANENT DOCUMENT REPOSITORY SYSTEM CATALOG NUMBER 10. ABSTRACT 11. SUBJECT TERMS / KEYWORDS

david.crispo
Text Box
Site-Specific Work Plan
david.crispo
Text Box
Draft Site-Specific Work Plan for the RVAAP-08 (Load Line 1) Igniter Tubes Disposal
david.crispo
Text Box
W912QR-04-D-0027
david.crispo
Text Box
0001, Mod 2
david.crispo
Text Box
122788
david.crispo
Text Box
Dave Cobb, David Crispo, P.E.
david.crispo
Text Box
Shaw Environmental, Inc. 100 Technology Center Drive Stoughton, MA 02072
david.crispo
Text Box
U.S. Army Corps of Engineers 600 Martin Luther King, Jr. Place Louisville, KY 40202
david.crispo
Text Box
1.28
david.crispo
Text Box
This document presents Shaw's approach for the handling and disposal of 139 igniter tubes encountered during remediation of soils and dry sediments adjacent to Building CB-13B at RVAAP 08(load line 1).
david.crispo
Note
Unmarked set by david.crispo
david.crispo
Text Box
Igniter tubes
david.crispo
Text Box
October 2, 2008
david.crispo
Text Box
Draft
Page 8: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 9: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

DRAFT SITE-SPECIFIC WORK PLAN

FOR THE RVAAP 08 (LOAD LINE 1) IGNITER TUBES DISPOSAL

Ravenna Army Ammunition Plant Ravenna, Ohio

Contract No. W912QR-04-D-0027 Task Order 0001, Modification No. 2

Prepared for:

United States Army Corps of Engineers 600 Martin Luther King, Jr. Place

Louisville, Kentucky 40202

Prepared by:

Shaw Environmental, Inc. 100 Technology Center

Drive Stoughton, MA 02072

October 2, 2008

Page 10: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 11: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

DOCUMENT DISTRIBUTION

Name Organization Hard Copies Electronic Copies OHARNG 1 1 RVAAP Facility Manager 2 4 USACE Contracting Officer’s Representative 4 4 USAEC Program Manager 1 Shaw Project Manager 2 2 OHARNG – Ohio Army National Guard RVAAP – Ravenna Army Ammunition Plant USACE – U.S. Army Corps of Engineers – Louisville District USAEC – U.S. Army Environmental Center

Page 12: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 13: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

Site-Specific Work Plan October 2008

RVAAP 08 (Load Line 1) Igniter Tubes Disposal Page i

TABLE OF CONTENTS

1.0 INTRODUCTION.......................................................................................................... 1-1

2.0 IGNITER TUBE DISCOVERY AND DESCRIPTION............................................. 2-1 2.1 Igniter Tube Discovery ....................................................................................................2-1 2.2 Igniter Tube Description ..................................................................................................2-1 2.3 Technical Literature Review............................................................................................2-1

3.0 PACKAGING, HANDLING AND SHIPPING OF WASTE..................................... 3-1 3.1 Personnel and Safety and Awareness Training................................................................3-1

3.1.1 MEC Personnel ...................................................................................................3-1 3.1.2 Tailgate Safety Meetings ....................................................................................3-1 3.1.3 Health and Safety................................................................................................3-2

3.2 Profiling and Packaging of Waste....................................................................................3-3 3.3 Offsite Disposal ...............................................................................................................3-3

3.3.1 Disposal Documentation and Notifications ........................................................3-3 3.3.2 Material Loading, Shipment, and Disposal.........................................................3-3

4.0 REPORTING ................................................................................................................. 4-1

5.0 PROJECT SCHEDULE................................................................................................ 5-1

6.0 REFERENCES............................................................................................................... 6-1

***DRAFT***

Page 14: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

Site-Specific Work Plan October 2008

RVAAP 08 (Load Line 1) Igniter Tubes Disposal Page ii

LIST OF FIGURES

Figure 1-1 Site Locus Map ........................................................................................................ 1-2 Figure 1-2 Facility Map ............................................................................................................. 1-3 Figure 2-1 Photograph of an Igniter Tube Removed at Building CB-13B................................ 2-1

LIST OF APPENDICES

Appendix A Field Activity Daily Log Appendix B EP 385-1-95a, Basic Safety Concepts and Considerations for Munitions

and Explosives of Concern (MEC) Response Action Operations, 27 August 2004

Appendix C Munitions and Explosives of Concern (MEC) at the Ravenna Army

Ammunition Plant (RVAAP) – Notification Procedures Appendix D Project Schedule

***DRAFT***

Page 15: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

Site-Specific Work Plan October 2008

RVAAP 08 (Load Line 1) Igniter Tubes Disposal Page iii

LIST OF ACRONYMS

DDESB Department of Defense Explosive Safety Board

ESS Explosives Safety Submission EZ Exclusion Zone

FADL Field Activity Daily Log FPRI Fixed-Price Remediation with Insurance

LMARC Louisville Multiple Award Remediation Contract

MEC Munitions and Explosives of Concern MPPEH Material Potentially Presenting an Explosive Hazard MSD Minimum Separation Distance

OHARNG Ohio Army National Guard Ohio EPA Ohio Environmental Protection Agency

PCP Project Coordination Plan PPE Personal Protective Equipment

QAMP Quality Assurance Management Plan

RTLS Ravenna Training and Logistics Site RVAAP Ravenna Army Ammunition Plant

Shaw Shaw Environmental, Inc. SHERP Site Health and Emergency Response Plan

USACE U. S. Army Corps of Engineers UXO Unexploded Ordnance

***DRAFT***

Page 16: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

Site-Specific Work Plan October 2008

RVAAP 08 (Load Line 1) Igniter Tubes Disposal Page iv

This page intentionally left blank.

***DRAFT***

Page 17: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

Site-Specific Work Plan October 2008

RVAAP 08 (Load Line 1) Igniter Tubes Disposal Page 1-1

1.0 INTRODUCTION

In August 2008, the United States Army Corps of Engineers (USACE) Omaha District issued a modification to Task Order #0001 under Shaw Environmental, Inc.’s (Shaw’s) Louisville Multiple Award Remediation Contract (LMARC) (W912QR-04-D-0027) for the handling and disposal of 139 igniter tubes discovered at RVAAP 08 (Load Line 1) at the Ravenna Army Ammunition Plant (RVAAP) in Ravenna, Ohio (Figure 1-1 and Figure 1-2). The igniter tubes were uncovered adjacent to the southwest corner of Building CB-13B at Load Line 1 during remediation activities associated with the remediation of soils and dry sediments at RVAAP 08-11 (Load Lines 1-4) performed at the RVAAP between 2007 and 2008 by Shaw under its Omaha Fixed-Price Remediation with Insurance (FPRI) contract (DACA45-03-R-0026). In addition, Shaw was also asked to perform a brief search of available records to determine if the igniter tubes could be further identified to allow for an evaluation of it potential contents. This Site-Specific Work Plan was developed to support the off-site disposal of igniter tubes encountered as part of remediation activities under the FPRI and was prepared in accordance with Shaw’s Project Coordination Plan (PCP) (Shaw 2006a), Quality Assurance Management Plan (QAMP) Addendum (Shaw 2006b), Safety Health and Emergency Response Plan (SHERP) Addendum (Shaw 2006c) prepared for Shaw’s FPRI task order. This document summarizes the discovery of the igniter tubes and provides procedures and controls necessary for the packaging, handling, and offsite disposal of the 139 igniter tubes.

***DRAFT***

Page 18: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

Site-Specific WOct

ork Plan ober 2008

RVAAP 08 (Load Line 1) Igniter Tubes Disposal Page 1-2

***DRAFT***

76

80

44

70480

44

14

14

18

5

5

8288

88

LAKE MILTON

MICHAEL J. KIRWANDAM & RESERVOIR

BRACEVILLE

NEWTONFALLS

RAVENNA

.R.RliarnoC Ravenna ArmyAmmunition Plant

.R.RXSC

SCALE IN MILES

3 0 3 6

LOCATION MAP

COLUMBUS

OHIO

CLEVELAND

CANTON

RAVENNA

G03-0075 LL2 Location Map

N

Figure 1-1

Site Locus Map

Page 19: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

Site-Specific Work Plan October 2008

RVAAP 08 (Load Line 1) Igniter Tubes Disposal Page 1-3

Figure 1-2 Facility Map

***DRAFT***

Page 20: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

Site-Specific WOct

ork Plan ober 2008

RVAAP 08 (Load Line 1) Igniter Tubes Disposal Page 1-4

***DRAFT***

This page intentionally left blank.

Page 21: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

Site-Specific Work Plan October 2008

RVAAP 08 (Load Line 1) Igniter Tubes Disposal Page 2-1

2.0 IGNITER TUBE DISCOVERY AND DESCRIPTION

2.1 IGNITER TUBE DISCOVERY

The igniter tubes were uncovered adjacent to the southwest corner of Building CB-13B at Load Line 1 during remediation activities associated with the remediation of soils and dry Sediments at RVAAP 08-11 (Load Lines 1-4) performed at the RVAAP between 2007 and 2008 by Shaw under its Omaha FPRI contract. After informing both the Army and the RVAAP facility manager of the discovery, the igniter tubes were segregated from contaminated soils by trained Shaw Munitions and Explosives of Concern (MEC) specialists. Based on a field inspection of the igniter tubes by Shaw’s MEC personnel and RVAAP installation personnel, the igniter tubes were not considered an explosive concern. The igniter tubes appeared to be a subpart of a larger firing mechanism. Figure 2-1 provides a photograph of one of the igniter tubes encountered at the site.

Figure 2-1 Photograph of an Igniter Tube Removed at Building CB-13B

The igniter tubes were subsequently placed into two 5-gallon pails with secure covers. The 5-gallon pails were transferred and placed into a secured bunker, Magazine 7C4 (Figure 1-2) at the

***DRAFT***

Page 22: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

Site-Specific Work Plan October 2008

RVAAP 08 (Load Line 1) Igniter Tubes Disposal Page 2-2

Ravenna Training & Logistics Site (RTLS), assigned by the Ohio Army National Guard (OHARNG) where they currently await off-site disposal.

***DRAFT***

Page 23: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

Site-Specific Work Plan October 2008

RVAAP 08 (Load Line 1) Igniter Tubes Disposal Page 2-1

2.2 IGNITER TUBE DESCRIPTION

As shown in Figure 2-1, the igniter tubes are composed of metal, are tubular in shape and are approximately 4-5 inches in length. The diameter of the igniter tubes are approximately ¾ of an inch. The tube portion of the piece is perforated on two sides and each end of the tube is capped. The majority of the tubes encountered also have a clip attached to it at about the three quarter point along the length of the tube. A visual inspection of the igniter tube was not able to definitively determine the contents or if any residual propellant material was present. A part number was also not evident on any of the igniter tubes inspected.

2.3 TECHNICAL LITERATURE REVIEW

As required, Shaw MEC and technical personnel performed a technical literature search of available documents in an attempt to more accurately determine the type and composition of the igniter tubes discovered. After reviewing numerous unexploded ordnance (UXO) and MEC books and catalogues, Shaw was unable to find a complete match to the materials encountered. The igniter tubes appear to be part of a larger firing assembly; however, with no part number, the actual composition and content could not be positively identified. The igniter tubes are suspected to contain a powder type propellant and are not considered to represent an explosive hazard.

***DRAFT***

Page 24: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

Site-Specific Work Plan October 2008

RVAAP 08 (Load Line 1) Igniter Tubes Disposal Page 2-2

This page intentionally left blank.

***DRAFT***

Page 25: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

Site-Specific Work Plan October 2008

RVAAP 08 (Load Line 1) Igniter Tubes Disposal Page 3-1

3.0 PACKAGING, HANDLING AND SHIPPING OF WASTE

The objective of this scope of work is to safely and legally package 139 igniter tubes and transport for off-site disposal. The following section will present the procedures associated with the safe handling and packaging of the waste prior to and during off-site disposal activities. Tasks to support this objective include the following:

• Provide properly trained MEC personnel and awareness training for all personnel handling the igniter tubes

• Package the igniter tubes in 5-gallon pails containing the igniter tubes with water to ensure the tubes are properly inert prior to transport

• Characterize and profile the igniter tubes for offsite disposal

• Transfer the 5-gallon pails containing the inert igniter tubes into the approved vendor’s transport vehicle for approved off-site disposal

Per USACE agreement prior to preparation of this site-specific work plan, an Explosive Safety Submission (ESS) work plan will not be required for the performance of this work.

3.1 PERSONNEL AND SAFETY AND AWARENESS TRAINING

3.1.1 MEC Personnel

Personnel and work standards will be in compliance with Department of Defense Explosive Safety Board (DDESB) TP-18 “Minimum Qualifications for UXO Technicians and Personnel”. For this project, the Shaw will utilize a trained MEC Supervisor (MEC Tech II) to oversee packaging of the igniter tubes and ensure the containers are properly handled and loaded onto the contracted disposal vendor’s vehicle. Names and data base numbers of these qualified personnel will be provided prior to mobilization.

The Shaw MEC Supervisor is responsible for ensuring that personnel performing MEC tasks during this project have the required qualifications. The MEC Supervisor oversees and coordinates all MEC work activities. The MEC Supervisor is the final authority for Shaw’s entire MEC field activities performed in support of this project by Shaw personnel or its subcontractors. The MEC Supervisor will document all MEC activities in his log book and on the Field Activity Daily Log (FADL) form included in Appendix A.

3.1.2 Tailgate Safety Meetings

The Shaw MEC Supervisor will conduct a tailgate safety meeting for all personnel prior to commencing packaging and transfer of the igniter tubes. The topics discussed at the tailgate safety meeting will include health and safety considerations for the day’s activities and necessary personal protective equipment (PPE). Attendance records and meeting notes will be maintained with the project files.

***DRAFT***

Page 26: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

Site-Specific Work Plan October 2008

RVAAP 08 (Load Line 1) Igniter Tubes Disposal Page 3-2

3.1.3 Health and Safety

3.1.3.1 Safety Health and Emergency Response Plan Addendum

Shaw will prepare a brief addendum to its SHERP (Shaw 2004) to address the handling and offsite disposal of the igniter tubes prior to the commencement of on site activities. The document will be an addendum to Shaw’s existing SHERP for work performed at Load Lines 1-4.

3.1.3.2 Execution of Work

The Shaw personnel performing work at RVAAP will follow the approved SHERP (Shaw 2004) the associated SHERP Addendum (Shaw 2006c), and the above referenced task specific addendum documents. The anticipated level of PPE is Level D with the following exceptions:

• Hard hats will not be worn unless an overhead hazard exists, (such as when using earthmoving machinery)

• Non-steeled toed protective boots will be worn instead of steel-toed boots

Both of these modifications comply with the requirements of the U.S. Army Engineering and Support Center Basic Safety Concepts and Considerations for MEC Response Action Operations, EP 385-1-95a, included in Appendix B. If the hard hat must be worn by personnel, it should be securely attached to the wearer; otherwise, PPE worn by personnel will be in accordance with the USACE Safety and Health Requirements Manual, EM 385-1-1 (USACE 2003).

3.1.3.3 General Safety Concerns and Procedures

General safety concerns will be addressed by implementing the following procedures before and during MEC operations:

• Only qualified personnel will perform MEC procedures

• Personnel who will be handling MEC items will not wear inner or outer garments having static electricity-generating characteristics nor carry fire or spark producing devices into the site

• All personnel have the right and duty to stop work when conditions are unsafe, and to assist in correcting these conditions

3.1.3.4 Visitors

Authorized visitors will be briefed on the hazards present at that location by the Shaw MEC Supervisor. Visitors will be responsible for compliance with the requirements specified in this section, the SHERP (Shaw 2004), the SHERP Addendum (Shaw 2006c), and the site specific addendum referenced above.

***DRAFT***

Page 27: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

Site-Specific Work Plan October 2008

RVAAP 08 (Load Line 1) Igniter Tubes Disposal Page 3-3

3.2 PROFILING AND PACKAGING OF WASTE

Since the igniter tubes could not be positively identified during the literature search, the material will be packaged to ensure it remains inert during the handling and off-site disposal activities. To ensure the material will remain inert, the existing buckets in which the igniter tubes are currently packaged will be filled with water to create a fluid, non sparking environment around the igniter tubes. The buckets will subsequently be sealed to prevent leaking and properly labeled for disposal in accordance with applicable federal, state and local regulations.

Prior to packaging the waste, Shaw will prepare and submit required waste profiling documents. Once completed, the draft profiling documents will be submitted to the Army for review, approval and signature. The completed waste profiling documents will be forwarded to the identified disposal facility for acceptance. The contents of the containers will be identified so as consistent with the profiling and acceptance criteria received from the accepting disposal facility. It is expected this material will not carry an explosives waste coding.

3.3 OFFSITE DISPOSAL

3.3.1 Disposal Documentation and Notifications

Prior to offsite disposal, Shaw will prepare the proper offsite disposal and transportation documents for RVAAP review and signature as Generator. Shaw’s onsite coordinator will meet with the RVAAP Installation Manager to go over the documents prior to signature to ensure there are no other issues related to disposal.

Shaw will coordinate with RVAAP to schedule a date/time to dispose of collected propellant and will make notification to the Ohio Environmental Protection Agency (Ohio EPA) prior to off-site disposal in accordance with the MEC Notification Procedures in Appendix C.

3.3.2 Material Loading, Shipment, and Disposal

Once the approval to accept the waste has been received from the accepting facility, the material will be shipped off site for disposal at the accepting facility. Shaw has identified Heritage Environmental Services in East Liverpool, OH as the designated facility to accept the igniter tubes. The facility is properly licensed and permitted to accept and handle the waste. Once at the facility, the material will be destroyed via incineration. The facility will provide proof of destruction and proper disposal of the waste for the project file.

During loading operations, a minimum safe separation distance of 200 feet will be established as an exclusion zone (EZ) to protect individual operating units in the event of an accidental detonation while packaging and transfer operations are underway. The minimum of 200 feet is per the EM 1110-1-4009 Engineering and Design Ordnance and Explosives Response, June 23, 2000, USACE, and Memorandum on the Determination of Appropriate Safety Distances on Ordnance and Explosives Project Sites. The 200-foot minimum distance will be used since the probability of encountering MEC in this area is low. In the unlikely event that an MEC item is discovered that has a larger Minimum Separation Distance (MSD) then the EZ safe separation

***DRAFT***

Page 28: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

Site-Specific Work Plan October 2008

RVAAP 08 (Load Line 1) Igniter Tubes Disposal Page 3-4

distance will be re-evaluated and re-established based on the Material Potentially Presenting an Explosive Hazard (MPPEH) found or suspected. Essential personnel are generally considered the Shaw MEC supervisor and the disposal contractor personnel.

Shaw on site personnel will maintain the established EZ perimeter to preclude non-essential personnel from entering the EZ. Vehicle entrances and roadways to the magazine EZ will be blocked to protect errant or non-authorized vehicles from entering the work area during the MEC removal activities.

All work will be performed in accordance with established RVAAP site plans and requirements.

***DRAFT***

Page 29: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

Site-Specific Work Plan October 2008

RVAAP 08 (Load Line 1) Igniter Tubes Disposal Page 4-1

4.0 REPORTING

A report summarizing the off-site disposal activities will be prepared upon completion of all activities. The report will consist of a photographs, copies of disposal and profile documents and a summary of the disposal activities. Three versions of the report (preliminary draft, draft and final) will be submitted for stakeholder review in accordance with RVAAP installation requirements.

***DRAFT***

Page 30: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

Site-Specific Work Plan October 2008

RVAAP 08 (Load Line 1) Igniter Tubes Disposal Page 4-2

This page intentionally left blank.

***DRAFT***

Page 31: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

Site-Specific Work Plan October 2008

RVAAP 08 (Load Line 1) Igniter Tubes Disposal Page 5-1

5.0 PROJECT SCHEDULE

The work described herein is expected to be completed by June 30, 2009. This includes tasks associated with work and safety plan preparation, sampling waste characterization, Army review of the waste profiles and shipping documents, packaging and offsite disposal and final report preparation. The project schedule is presented in Appendix D and is organized sequentially by task and includes task/subtask names, durations and identification of predecessor and successor tasks.

***DRAFT***

Page 32: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

Site-Specific Work Plan October 2008

RVAAP 08 (Load Line 1) Igniter Tubes Disposal Page 5-2

This page intentionally left blank.

***DRAFT***

Page 33: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

Site-Specific Work Plan October 2008

RVAAP 08 (Load Line 1) Igniter Tubes Disposal Page 6-1

6.0 REFERENCES

1. Naval Explosive Ordnance Disposal Technology Division (NAVEODTECHDIV) 1997. “Technical Manual, Explosive Ordnance Disposal Procedures, EOD Disposal Procedures, 60A-1-1-31, Revision 1”. December 31, 1997

2. Shaw Environmental, Inc. (Shaw) 2004. “Final Safety and Health and Emergency Response Plan Addendum for the Remediation of Soils at Load Lines 1, 2, 3 and 4 at the Ravenna Army Ammunition Plant, Ravenna, Ohio”. October 2004.

3. Shaw 2006a. “Final Project Coordination Plan for Structural Analyses and MEC Support at the Ravenna Army Ammunition Plant, Ravenna, Ohio”. October 2006.

4. Shaw 2006b. “Final Quality Assurance Management Plan Addendum for Structural Analyses and MEC Support at the Ravenna Army Ammunition Plant, Ravenna, Ohio”. November 2006.

5. Shaw 2006c. “Final Safety, Health and Emergency Response Plan Addendum for Structural Analyses and MEC Support at the Ravenna Army Ammunition Plant, Ravenna, Ohio.” November 2006.

6. United States Army Corps of Engineers (USACE) 2003. “Safety and Health Requirements Manual, EM 385-1-1”. November 3, 2003.

***DRAFT***

Page 34: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

Site-Specific Work Plan October 2008

RVAAP 08 (Load Line 1) Igniter Tubes Disposal Page 6-2

This page intentionally left blank.

***DRAFT***

Page 35: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

Site-Specific Work Plan October 2008

RVAAP 08 (Load Line 1) Igniter Tubes Disposal

APPENDIX A

Field Activity Daily Log

***DRAFT***

Page 36: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

Site-Specific Work Plan October 2008

RVAAP 08 (Load Line 1) Igniter Tubes Disposal

This page intentionally left blank.

***DRAFT***

Page 37: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

Date: No.

Dai

ly L

og

Sheet of

FIELD ACTIVITY DAILY LOG

PROJECT NAME:

PROJECT NO.

FIELD ACTIVITY SUBJECT:

DESCRIPTION OF DAILY ACTIVITIES AND EVENTS:

VISITORS ON SITE: CHANGES FROM PLANS AND SPECIFICATIONS, AND OTHER SPECIAL ORDERS AND IMPORTANT DECISIONS.

WEATHER CONDITIONS: IMPORTANT TELEPHONE CALLS:

SHAW PERSONNEL ON SITE:

SIGNATURE: DATE:

Page 38: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 39: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

Site-Specific Work Plan October 2008

RVAAP 08 (Load Line 1) Igniter Tubes Disposal

APPENDIX B

EP 385-1-95a, Basic Safety Concepts and Considerations for Munitions and Explosives of Concern (MEC) Response

Action Operations, 27 August 2004

June 2001

***DRAFT***

Page 40: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

Site-Specific Work Plan October 2008

RVAAP 08 (Load Line 1) Igniter Tubes Disposal

This page intentionally left blank.

***DRAFT***

Page 41: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 42: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 43: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 44: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 45: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 46: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 47: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 48: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 49: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 50: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 51: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 52: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 53: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 54: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 55: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 56: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 57: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 58: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 59: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 60: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 61: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 62: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 63: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 64: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 65: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 66: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 67: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 68: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 69: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 70: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 71: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 72: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 73: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 74: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 75: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 76: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 77: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

Site-Specific Work Plan October 2008

RVAAP 08 (Load Line 1) Igniter Tubes Disposal

APPENDIX C

Munitions and Explosives of Concern (MEC) at the Ravenna Army Ammunition Plant (RVAAP) – Notification Procedures

08 April 2005

***DRAFT***

Page 78: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

Site-Specific Work Plan October 2008

RVAAP 08 (Load Line 1) Igniter Tubes Disposal

This page intentionally left blank.

***DRAFT***

Page 79: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

Munitions and Explosives of Concern (MEC) at the Ravenna Army Ammunition Plant (RVAAP) - Notification Procedures

Paragraph 9(a) of the Director’s Final Findings and Orders (journalized June 10, 2004) allows for the following exemption: “The requirement to obtain a hazardous waste facility installation and operation permit, as required by ORC 3734.02 (E), for the storage and treatment (destruction) of MEC (excluding bulk storage of munitions and chemical and biological warfare materiel) at OD#2, and for the in-place treatment (destruction) of MEC (excluding bulk storage of munitions and chemical and biological warfare materiel) discovered at the RVAAP that can not be safely transported to OD#2, provided, however, that Respondent shall comply with all applicable requirements of ORC chapter 3734 and OAC chapters 3745-50 through 3745-68, including but not limited to the hazardous waste requirements set forth at Appendix E.” In the absence of obtaining emergency permits, the following is the type of information that should be provided to Ohio EPA Northeast District Office (NEDO), Division of Emergency and Remedial Response (DERR) [attn: Eileen Mohr] and Division of Hazardous Waste Management (DHWM)[attn: Greg Orr]. The information is divided into categories: prior to destruction of the MEC and subsequent to the destruction of the MEC. Prior to the MEC destruction, notification can be made via either letter or email. Subsequent to detonation, the information can be transmitted in a written summary report after each detonation event or at the conclusion of clearance activities at a particular Area of Concern (AOC).] Information to be provided prior to Blow in Place (BIP) or Detonation at OD#2: 1. Point of Contact (POC) 2. POC’s phone number(s) and fax number 3. Location/date/time/person discovering the MEC 4. Description of MEC to be blown: including type and quantity 5. Proposed destruction location: either at OD#2 or BIP 6. Proposed method of destruction 7. Proposed methods to mitigate/abate potential contamination 8. Preparedness and prevention 9. Notifications to be made Information to be provided subsequent to BIP or Detonation at OD#2: 1. POC 2. POC’s phone number(s) and fax number 3. Description of MEC blown: including type and quantity 4. Location/date/time/person responsible for the MEC destruction 5. Location of destruction activities - description and map with GPS locations listed and (if

applicable) the depth and number of shot holes utilized at OD#2 6. Method of destruction utilized 7. List of donor charges and amounts 8. Any problems encountered 9. Inspection/disposal of residues 10. Confirmation of adherence to minimum isolation distances specified in OAC 3745-68-82 11. Whether or not any subsequent soil samples were collected and location of available

analytical results FINAL 04/08/2005

Page 80: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,
Page 81: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

Site-Specific Work Plan October 2008

RVAAP 08 (Load Line 1) Igniter Tubes Disposal

APPENDIX D

Project Schedule

***DRAFT***

Page 82: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

Site-Specific Work Plan October 2008

RVAAP 08 (Load Line 1) Igniter Tubes Disposal

This page intentionally left blank.

***DRAFT***

Page 83: Draft Site-Specific Work Plan for the RVAAP- 08 Load Line ... · draft site-specific work plan for the rvaap 08 (load line 1) igniter tube disposal ravenna army ammunition plant ravenna,

ID Task Name Duration Start Finish

1 Award Contract Modification 0 days Tue 8/12/08 Tue 8/12/08

2 Technical Literature Search 10 days Tue 8/12/08 Mon 8/25/08

3 Workplan/HASP Preparation 115 days Wed 9/3/08 Tue 2/10/09

4 Preparation of Pre Draft Workplant/HASP 20 days Wed 9/3/08 Tue 9/30/08

5 Army Review of Pre Draft Workplan/HASP 10 days Wed 10/1/08 Tue 10/14/08

6 Preparation of Draft Workplan/HASP 5 days Wed 10/15/08 Tue 10/21/08

7 Army/Ohio EPA Review of Draft Workplan/HASP 33 days Wed 10/22/08 Fri 12/5/08

8 Comment Resolution for Draft Workplan/HASP10 days Mon 12/8/08 Fri 12/19/08

9 Preparation of Final Workplan/HASP 4 days Mon 12/22/08 Thu 12/25/08

10 Approval of Final Workplan/HASP 33 days Fri 12/26/08 Tue 2/10/09

11 Offsite Disposal 35 days Mon 12/22/08 Fri 2/6/09

12 Sampling/Waste Characterization Prep 15 days Mon 12/22/08 Fri 1/9/09

13 Army Review of Waste Characterization 5 days Mon 1/12/09 Fri 1/16/09

14 Facility Acceptance 13 days Mon 1/19/09 Wed 2/4/09

15 Packaging/Offsite Disposal 2 days Thu 2/5/09 Fri 2/6/09

16 Completion Report Preparation 102 days Mon 2/9/09 Tue 6/30/09

17 Preparation of Pre Draft Completion Report 7 days Mon 2/9/09 Tue 2/17/09

18 Army Review of Pre Draft Completion Report10 days Wed 2/18/09 Tue 3/3/09

19 Preparation of Draft Completion Report 5 days Wed 3/4/09 Tue 3/10/09

20 Army/Ohio EPA Review of Draft Completion Report33 days Wed 3/11/09 Fri 4/24/09

21 Comment Resolution for Draft Completion Report10 days Mon 4/27/09 Fri 5/8/09

22 Preparation of Final Completion Report 4 days Mon 5/11/09 Thu 5/14/09

23 Approval of Final Completion Report 33 days Fri 5/15/09 Tue 6/30/09

24 Project Complete 0 days Tue 6/30/09 Tue 6/30/09

8/127/20 7/27 8/3 8/10 8/17 8/24 8/31 9/7 9/14 9/21 9/28 10/5 0/1 0/1 0/2 11/2 11/9 1/1 1/2 1/3 12/7 2/1 2/2 2/2 1/4 1/11 1/18 1/25 2/1 2/8 2/15 2/22 3/1 3/8 3/15 3/22 3/29 4/5 4/12 4/19 4/26 5/3 5/10 5/17 5/24 5/31 6/7 6/14 6/21 6/28

August 2008 September 2008 October 2008 November 2008 December 2008 January 2009 February 2009 March 2009 April 2009 May 2009 June 2009 J

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

Shaw Schedule for Igniter Tube Disposal Version No: 1

Page 1

Project: RVAAP Igniter TubeDate: Tue 9/30/08