Draft Detailed Project Report On on Name of ULB: Sagar...

51
Draft Detailed Project Report On Investment Grade Energy Audit Conducted on BEE MuDSM Programme. Name of ULB: Sagar Municipality, Madhya Pradesh. By EPIC Energy Ltd, Mumbai. ESCO & IGE Auditors. Period From 25.06.2009 To 10.7.2009

Transcript of Draft Detailed Project Report On on Name of ULB: Sagar...

Page 1: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

Draft Detailed Project Report

On

Investment Grade Energy Audit

Conducted – on

BEE MuDSM Programme.

Name of ULB: Sagar Municipality,

Madhya Pradesh.

By EPIC Energy Ltd, Mumbai.

ESCO & IGE Auditors.

Period – From 25.06.2009 To 10.7.2009

Page 2: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

Prepared by

1. R. Kalainesan, Junior Energy Auditor2. M. Sivaananth, Junior Energy Auditor3. G. Selva Manikandan, Junior Energy Auditor4. Vijay Shankar, Junior Energy Auditor5. Amit Prathap Singh, Junior Energy Auditor6. Vinod Pal Singh, Junior Energy Auditor7. A. Vignesh Narayanan, Junior Energy Auditor8. Neeraj Kapoor, Certified Energy Auditor9. R. K. Budhiraja, Certified Energy Auditor10. P. Anandaraj, Certified Energy Auditor11. S. Karuppasamy, Senior Professional Energy Auditor12. R. Purushothaman, Senior Professional Energy Auditor13. I. Ramachandran, Senior PEA & IPMVP Professional Energy Auditor14. Dr. V. Shanmugavel, Senior PEA & Lead Energy Auditor.

Page 3: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

CONTENTS

1. Executive Summary

2. Municipality – Energy Budget – Sector Wise

3. Municipality – Energy Uses – Present Consumption

Future Consumption

Energy Saving

4. Municipality – Energy Saving – Sector Wise

5. IGEA on Building

6. IGEA on WT Pump in WTP – Pump House and 15No. Bore Well Pumps

7. IGEA on Transformer Study and Distribution Audit

8. IGEA on Street Lighting System

9. Annexure

A1 Connected Load Details

A2 Submersible Pumping System Details

A3 Lux Reading Measurement Recorded

A4 Data Logger Download Measurement

A5 Voltage Profile Measurement

A6 PF Profile Measurement

A7 List of Instruments and Tool used for IGEA

A8 Operation & Maintenance Cost – Bill Details

A9 Abstract Summary on Base Line, Current & Energy Saving Calculation

A10 Comparison Table between Conventional 40W TFL with magnetic choke and T528W Lamps

A11 Comparison Table between Conventional HPSV Lamps & T5 Based Street LightLamps

A12 Building Mapping

A13 WTP – Pump House Mapping

A14 Street Lighting System 34 Switch Points Mapping

Page 4: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

A15 Lux Level Standards – IS 1944 Part II of BIS

A16 Cash Flow Statement for Energy Performance Project

A17 Energy Management

A18 Risk Matrix

A19 Risk Sharing Mechanism between Municipality & ESCO – on ESCO Model

A20 Technical Specification of Sample Lights Used

A21 Brochure on Energy Saver

A22 Brochure on Fuel Saver

A23 Format for Complaint Register

A24 List of Qualified Energy Saving Companies

A25 List of Energy Saving Equipment Suppliers

A26 Reduction of GHG Emission due to Energy Saved

A27 Reference, Quality of Calculation Procedures, Creditability of Assumptionused in IGEA.

Page 5: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

BEE - MuDSM PROGRAMME

Name of ULB : Sagar Municipality, MP. Name of ESCO & IGEA : M/s. EPIC Energy,Mumbai.

EXECUTIVE SUMMARY

Introduction : There is an ever increasing wide gap between ‘Supply and Demand’ inthe “Electricity and Diesel “ Energy sectors, at a galloping speed. To mitigate this problem,a two way approach can be employed.

(1) Increasing the capacity addition to the Grid;

and (2) Decreasing the demand on the grid by Energy Efficiency/Saving methods.

By going in for Solution (1), huge capital investment is required with a range of Rs.6 - 8 Crores per MW for establishment of a Thermal Power Station with an incubationperiod of 3 - 5 years depending on the size of the project. Also, it depends on theavailability of funds, fuel , water, land and transport; Pollution control - environmentalfactors etc., Hence this cannot offer an immediate solution.

By going in for Solution (2), the following benefits can be reaped :

(a) Reduced demand on the grid on both KVA and KWH by adopting EnergyConservation measures;

(b) It is cost effective;(c) The capital investment is paid back from the accrued energy savings;(d) “ One Unit Saved is Two Units generated. ”(e) By using Energy Efficient equipments, the performance is improved giving the

benefits to the End-users;(f) The Service provider viz., the Municipality can remove Customer dissatisfaction

in order to achieve satisfaction and the final goal of Customer delight ! ;(g) In addition to cost savings in energy, savings on reduced failure replacements

due to use of ‘ long burning hours capacity type EE equipments ’.

(h) Breakdowns / failures get reduced drastically and work force utilized for preventivemaintenance works.

The Government of India is seized of the problem. Capacity addition will not offera “Whole, Total and Holistic” solution to meet the immediate needs and also thereare huge leakages existing by way of energy losses on both the Supply andDemand sides; i.e., Generation, Transmission and Distribution sides. Hence theElectricity Act 2003 through Electricity Act 2001 was passed which gives wide scopefor Energy conservation by Energy Audit with Demand Side Management. Forimplementation, the BEE have started the very ambitious program on the Municipal,Agricultural and SME industrial sectors.

Page 6: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

Most of the Municipalities suffer for want of funds as 80 % of their O & M funds arespent as Energy bills on administrative buildings, WTP, STP and Street Lighting Systems.Even after meeting out these expenses, the performance of the Municipal system is not up tothe expected level, bringing more complaints on irregular supply of water; poor clearing ofsewage and the lack of safety and security to be offered by the Street Lighting system etc.,More failures and break down of water lines; water supplied without adequate pressure; StreetLight Lamp failures and not caring for reducing the down time in rectifying the defects, breakdowns etc. ; no preventive or routine maintenance works or inspection being carried out.There is no proper upkeep and maintenance of Complaints Register to bringimprovement in redressal of grievances of the public.

*************

‘Sagar’ is a medium town located in Madhya Pradesh State and about 75 Km awayfrom Bina Town. Being a backward area, the livelihood comes mainly from agriculture.

Population : 5,00,000 approx.

No. of Wards : 48

The town is governed and maintained by the Sagar Municipality. One CivilEngineer and one Electrical Engineer oversee the efficient functioning of the Street LightingSystem, Water Supply to the public and Municipal building maintenance works. 19employees of the Municipality are at hand for carrying out these works.

I. STREET LIGHTING SYSTEM :

Town Illumination :

The prime objectives are : (a) hold back the day;

and (b) to give a character to the town at night.

A well illuminated town gives :

(i) Safety : Safety for Walking, Cycling, Biking, Motoring etc., to thepublic thereby reducing accidents.

(ii) Security : Helps in prevention of thefts, crimes etc., thereby improvingcitizens’ life style — by offering freedom from fear.

Enhancement of night time ambience promotes business as well as social interaction.

The Madhya Pradesh State Electricity Distribution Company supplies Electricalenergy to the Municipality under various Account heads for the Service connectionseffected.

Page 7: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

STREET LIGHTING :There are 5, 059 Nos. of Street Lights consisting of Tube lights,

Sodium Vapour and Metal Halide lamps, CFL and other lights and are beingmaintained by the Municipality’s employees. The spare materials for proper maintenanceare ordered by the Municipality and kept as stock.

STREET LIGHTS :Total Nos. of Service connections : 34

Approved total load : 621.5 KW.

Total Electrical consumption charges/month : Rs. 4, 76, 860 / -

Annual expenditure :

(a) Maintenance cost (labour) and,

(b) Replacement cost of defective / failedStreet lights / accessories : Rs. 7, 30, 000 / -(Materials’ cost)

Annual Maintenance Expenditure : Rs. 88, 00, 000 / -(Labour & Materials)

The existing arrangement of the Municipal Lamps mounted on MPEB leads to delayin rectification of failures. Line clear / Shut down has to be availed from MPEB. Theearthing system is also not up to the mark ; Street light cables used are of poor insulation ;leakages have been noticed and losses are on the high side.

II. Water Supply Scheme :

Sagar Municipality have established a Protected clear water supply scheme andmaintain Water supply to the residents of 29 wards.

(a) Raw water is pumped from the Raj Ghat River course by using 2 Nos. Motor Pumpsets ( 170 KW each ) operating in parallel for 17 Hrs. / day for 2 days with 1 daybreak. Additionally, 2 Nos. equivalent capacity Motor-Pump sets are available foralternate use / standby.

(b) The pumped raw water is connected via pipes to the Water Treatment Plantlocated about 2 Kms. away from the River water PH. The raw water now treatedat the Water Treatment Plant is passed on to the Clear Water Pump House. 2Nos. Motor-Pump sets ( 845 KW each ) operate in parallel for 17 Hrs. / day for 2days with 1 day break to pump the ‘Clear’ water to an elevated Reservoirlocated on a small hill top 8 KMs. away from the pump house. Here also 2Nos. equivalent spare Motor-Pump sets are available for alternate use / standbypurposes.

Page 8: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

The elevated Reservoir’s outlets are connected to 6 Nos. Overhead Tanks viapipes ; water reaches these tanks by gravitation, which in turn distribute water supply tothe residents.

( c) There is one 33 / 6.6 KV - 400 V Sub - station with 2 Nos. 33 / 6.6 KV Transformersand 1 No. 33 KV / 400 V Transformer receiving power from MPEB with a Sanctioned /Contract demand of 1684 KVA in WTP and Clear water PH, supplying energy toboth Raw Water PH, WTP and Clear water PH.

Note : By operating 2 pumps each at RWPH & CWPH, the energy consumptionexceeds the MD of 1684 KVA by 868 KVA the Municipality incurs penalty and paysaround Rs. 24 lakhs. This can be saved as per IGEA done.

(d) In addition to this, 19 wards not covered by the Municipal water lines under waterService connections are served by supplying ‘Untreated’ water directly from 2Nos. Open well Pumps and Water Tankers and 13 Nos. Submersible Pumpswith open water Taps.

The schedule of water supply is delivery for 2 days with 1 day break.There are no complaints from the public and the performance is found to be satisfactory.

III. Municipal Buildings :The Municipality functions in 4 Nos. Buildings spread across the town.1. H.O - Nagar Palika Nigam2. Pavilion - Zone office I ;3. Zone office II ;4. Zone office III.The average annual billed consumption is 34,916 Units and the bill payable is Rs.

1,90,000. The lighting is maintained by the personnel of the Municipality.

IV. Disposal of Sewage :Sewage is let out on open canals built on the sides of the streets. The Municipality is

not maintaining them.

The chart shows the Municipality Budget Energy wise and the above scheme wise.Energy Bills received from MPEB are just passed and paid by the Municipality. Most ofthe Energy meters are not functioning. The energy usage and bills are to be checked andpassed. No complaints register is available at the site offices. Maintenance of the complaintsregister shall help the Municipality to review and bring down the down time of eachcomplaint ; Better co-ordination with the MPEB.There are three options before the Municipality :

Page 9: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

Conclusion :

(1) The Municipality can reduce its Energy Budget from its existing level to % both onenergy & Operation & maintenance costs – saving is %.

As a first step, the 34 switch points have to be properly metered. The monitoring systemoperating on GSM Technology connected to a central computer, displaying of burning status,operating the switches on time slot basis, consumption details of each switch point so that themunicipality can have better control over consumption & burning status, redressal of complaints byreducing down time of each complaint. By this arrangement over all improvement of burning status,reduction in no. of complaints and down time of each complaint, and consumption in each switchpoint can be achieved. Municipality can bring all the lights on control gears & under monitoringsystem to give service to the public.

Energy saving, money saving in operation & maintenance cost, cash in-flow, out-flow and ARR arealso given in calculation and chart forms. From the above, Energy Audit Detailed project Report is aviable, profitable and bankable project.

(2) The funds can be obtained through banks wherever necessary(3) In addition to monetary saving, the services will be improved a lot to serve the public

with better water supply system and street lighting system.(4) This is a win-win situation to every body – The beneficiaries are :

Municipality – Cost reduction, better services

MPEB – Demand & unit reduction to be used for clearing pending newservice applications.

State Govt – Energy Bill reduction.

Central Govt – Energy Bill reduction.

Global – Environment protection by reduction of GHG emissions.

General public – Better services on STP – Better illumination, safety, security,reduction in accidents, better ambience, improved social

interaction & business, Environmental protection, etc .Optimum water supply.

********************

Page 10: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

BEE – MuDSM Programme

Name of ULB: Sagar Municipality, M P. Name of ESCO: EPIC Energy Ltd, Mumbai.

Period of Audit: 25.06.2009 To 10.07.2009.

Municipality Energy Budget

S.No Description

IGEA

BuildingsWater Supply

Scheme

Street Lighting

System

1.Base Line

Consumption

Units 41, 725

1684 + 868 KVA

+

77, 22, 999

17, 67, 002

Rs. 2, 27, 000 2, 73, 39, 000 56, 54, 000

Page 11: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior
Page 12: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

BEE – MuDSM Programme

Name of ULB: Sagar Municipality, M P. Name of ESCO: EPIC Energy Ltd, Mumbai.

Period of Audit: 25.06.2009 To 10.07.2009.

Municipality Energy Uses

Description

IGEA

BuildingsWater Supply

Scheme

Street Lighting

SystemTOTAL

Base Line

Consumption

Units 41, 725

( 1684 + 868 )

KVA +

77, 22, 999

17, 67, 002

(1684 + 868)

KVA +

95, 31, 726

Rs. 2, 27, 000 2, 73, 39, 000 56, 54, 000 3, 32, 20, 000

Current

Consumption

Units 33, 0701684 KVA +

60, 50, 69410, 14, 225

1684 KVA + 70,

97, 989

Rs. 1, 80, 000 2, 01, 83, 000 32, 45, 000 2, 36, 08, 000

Energy Saving

Units 8, 655868 KVA +

16, 72, 3077, 52, 777

868 KVA + 24,

33, 739

Rs. 47, 000 71, 56, 000 24, 09, 000 96, 12, 000

Page 13: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior
Page 14: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

BEE – MuDSM Programme

Name of ULB: Sagar Municipality, M P. Name of ESCO: EPIC Energy Ltd, Mumbai.

Period of Audit: 25.06.2009 To 10.07.2009.

Municipality Energy Saving

S.No Description

IGEA

BuildingsWater Supply

Scheme

Street Lighting

System

1. Energy Saving

Units 8, 655868 KVA +

16, 72, 3077, 52, 777

Rs. 47, 000 71, 56, 000 24, 09, 000

Page 15: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior
Page 16: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

BEE - MuDSM Programme

Name of ULB : Sagar Municipality, Name of ESCO : EPIC Energy Ltd,Madhya Pradesh. Mumbai.

IGEA – Municipal Buildings

The following 4 No. Buildings are audited as per Investment Grade Energy Audit under BEEMunicipal Demand Side Management Programme.

1. Head Office Building – Nagar Nigam – 2 Floors.2. Pavilion Building – Single Floor3. Zone office Building – 2 – Single Floor &4. Zone office Building – 3 – Single Floor

The Annual consumption details for three years, 2006 – 2007, 2007 – 2008 & 2008 – 2009obtained from Sagar Municipality are given in Annexure.

Computed Consumption Calculation

ConnectedEquipments No. Wattage

CircuitWattage

OperatingHours. Consumption in Hours.

Conventional40 W TFL

74 40 53 7 x 300 = 210074 x (53 / 1000) x 2100

= 8236

CFL14 36 -- 7 x 300 = 2100

14 x (36 / 1000) x 2100

= 1,058

Fan50 60 -- 7 x 75 = 525

50 x(60 / 1000) x 2100

= 6,300

Computers. 3 100 -- 1 x 300 = 3003 x (100 / 1000) x 300

= 90

Room Cooler 21 250 -- 7 x 300 = 210021 x (250 / 1000) x 2100

= 11,025

Exh. Fan4 75 -- 7 x 300 = 2100

4 x (75 / 1000 ) x 2100

= 630

GLS2 60 -- 7 x 300 = 2100

2 x (60 / 1000 ) x 2100

= 252

SV Lamp2 300 -- 10 x 300 = 3000

2 x (300 / 1000) x 3000

= 1,800

Total Annual Computed Consumption = 29, 391 /-

Extra working of Municipal Staff on Election, Relief, Medical works etc @ 20 % = 5, 878 /------------------

35, 269 /- Units----------------

Page 17: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

Base Line Consumption

Average Annual Computed Consumptionbased on connected Load } 35, 269 Units

Average Annual Billed Consumptionbased on Recorded in utility meter } 34, 916 Units

The Least of the two can be fixed as Base Line Consumption.

Base Line Consumption = 34, 916 Units

Bill Payable = Rs. 5.45 x 34, 916

= Rs. 1, 90, 000 / -

Energy Saving Calculation

From the Annexure shown in the Comparison Table, replacement of conventional Tube Lights byT5- EE Lamps will bring 45 % Energy Cost Savings.

Hence, Energy Saving = 74 x ( 53 - 28 ) x 7 x 3651000

= 4, 727 Units.

In Rs. = 5.45 x 4727

= Rs. 25, 762 /- or say

= Rs. 26, 000/-

Current Consumption = 34, 916 – 4, 727

Current Consumption after introduction ofEnergy Saving measure = 30, 189 Units

In Rs. = 5.45 x 30, 189

= 1, 64, 000 /-

Cost of investment = Rs. 74 x 500

= Rs. 37, 000 /-

Cost of Benefit Ratio = 37, 000-----------26, 000

= 1.42

Simple Pay Back Period = 18 Months.

*****************

Page 18: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

ANNEXURE

BEE - MuDSM Programme

Name of ULB : Sagar Municipality, Name of ESCO: EPIC Energy Ltd,Madhya Pradesh. Mumbai.

IGEA – Municipal Building – Main Nagar Palika Nigam Office Building

Consumption Details – Service connection No. 107 – 10 – 1 – 2786904

S.No. Name ofMonth

Consumption in UnitsYear.

2006 – 2007 2007 – 2008 2008 – 20091 April 2606 4777 31222 May -- 3429 32313 June -- 4228 44334 July -- 4242 34065 August -- 3271 32106 September 17648 2689 36747 October 2314 2731 24668 November 2087 2477 21089 December 2469 2132 1063

10 January 1770 2091 303811 February 2066 2274 188412 March 2705 2775 2337

Total 33, 665 37, 116 33, 972

Total Actual Annual Consumption for Three years = 33, 665 + 37, 116 + 33, 972 Units

= 1, 04, 753 Units.

Annual Average Recorded Consumption = 34, 918 Units

Bill Payable = Rs. 5.45 x 34, 918

= Rs. 1, 90, 301 or say

= Rs. 1, 90, 000 /-

Page 19: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

IGEA – On Pavilion Buildings

Connected Load Details :

Conventional 40 W TFL with Magnetic Choke - 8 Nos.

Fan - 6 Nos.

Room Cooler - 1 No.

Exhaust Fan - 4 Nos.

HPSV Lamps - 2 Nos.

Base Line Consumption Calculation:

Annual Recorded & Billed consumption - 5,811 Units.

Computed consumption based on connected Load :

= ( 8 x 53 / 1000 x 7 x 300 ) + ( 6 x 60 / 1000 x 7 x 300 )

+ ( 1 x 60 / 1000 x 7 x 300) + ( 4 x 75 / 1000 x 7 x 300)

+ ( 2 x 300 / 1000 x 3 x 300 )

= 890 + 756 + 126 + 630 + 540

= 2, 942 Units.

The highest of these two is fixed as Base Line Consumption as the meter recorded consumption isaccurate. It is noted that the recorded consumption is very high compared to computed consumption(5811 - 2942) ie, 2869 units. The existing meters are electronic type. Probably this excess may be dueto holding some functions in the pavilion. However after implementing IGEA recommendation, theexpected energy savings have been worked out.

Base Line Consumption = 5, 811 Units.

Bill Payable = Rs. 32, 000 /-

Current Consumption

= ( 8 x 28 / 1000 x 7 x 300 ) + ( 6 x 60 / 1000 x 7 x 300 )

+ ( 1 x 60 / 1000 x 7 x 300) + ( 4 x 75 / 1000 x 7 x 300)

+ ( 2 x 120 / 1000 x 3 x 300)

= 470 + 756 + 126 + 630 + 216

= 2, 198 Units.

Page 20: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

Bill Payable = Rs. 5.45 x 2, 198

= Rs. 11, 979 /- or say

= Rs. 12, 000 /-

Energy Saving = 5, 811 – 2, 198

= 3, 613

In Rs. = 20, 000 /-

In percentage = 62 %

Cost of Investment = Rs. ( 8 x 500 ) + ( 2 x 2, 000 )

= Rs. 8, 000 /-

Cost of Benefit Ratio = 8, 000 / 20, 000

= 0.4

Simple Pay Back Period = 0.4 x 12

= 5 Months.

*****************

Page 21: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

Bill Details of Pavilion Building

Service connection No. 55445107 – 10 – 1 – 658601

S.No. MonthYear

2006 – 2007 2007 – 2008 2008 – 2009

1 April174

208 461

2 May109

186 397

3 June--

881 615

4 July289

319 298

5 August--

271 498

6 September0

372 516

7 October22

347 894

8 November743

367 382

9 December159

369 308

10 January1160

1366 684

11 February307

52 778

12 March352

432 621

Total 3,315 5,170 6,452

Average Annual Consumption = 5,170 + 6,452 / 2

= 11, 622 / 2

= 5, 811 Units.

Annual Bill Payable = Rs. 5.45 x 5,811

= Rs. 31, 670 or say

= Rs. 32, 000 /-

Page 22: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

IGEA on Zone 2 Building

Bill Details – New Service Connection in January 2008

Projected Bill for 2007 – 2008 = 540 units

Annual Bill for 2008 – 2009 = 347 units

Total units for 2 years. 887 units

Average Annual Recorded & Billed Consumption : 887 / 2 = 444 units

= Rs. 5.45 x 444

= Rs. 2, 419.80 or say

Annual Bill Payable = Rs. 2, 420 /-

Connected load Details :

Conventional 40W TFL = 4 No.

Fan = 3 No.

Room Cooler = 1 No.

Exh. Fan = 2 No.

Base Line Consumption = 444 units

Bill Amount = Rs. 2, 420 /-

Current Consumption = 234 units

Bill Amount = Rs. 1, 275 /-

Energy Saving = 4 x ( 25 / 1000 ) x 7 x 300 = 210 units

in Rs. = 5.45 x 210

= Rs. 1, 145 /-

Cost of Investment = Rs. 500 x 4

= Rs. 2,000 /-

Cost Benefit Ratio = Rs. 2, 000 x 1, 145 = 1.75

Simple Pay Back Period in months = 1.75 x 12 = 21 Months

Page 23: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

IGEA on Zone 3 Building

Connected Load Details

Conventional 40W TFL = 2 No.

Fan = 2 No.

Exhaust Fan = 2 No.

Billing Details

Service connection No. 5104 – 8 – 11 – 48598

New connection given in February 2007.

Annual Recorded & Billed consumption in 2007 – 2008 = 517 Units

2008 – 2009 = 590 Units

Average Annual Recorded & Billed consumption = ( 517 + 590 ) / 2

= 554 Units

Annual Bill Payable = Rs. 5.45 x 554

= Rs. 3,019 /-

Current Consumption = 449 Units

Bill Payable = Rs. 5.45 x 449

Current Consumption after Energy saving measures bill payable = Rs. 2,447 /-

Energy Saving = 2 x ( 25 / 1000 ) x 7 x 300 = 105 Units

= 5.45 x 105

In Rs. = 572 /-

Cost of Investment = Rs. 500 x 2 = 1,000 /-

Cost of Benefit Ratio = 1000 / 572 = 1.75

Simple Pay Back Period in months = 1.75 x 12 = 21 Months.

Page 24: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

ABSTRACT SUMMARY

On

IGEA on Buildings

Sl.No

Details

Base LineConsumption

in Rs.

CurrentConsumption

in Rs.

EnergySaving

in Rs.

Inpercent

–age

in %

Cost ofInvest–ment

in Rs.

CostBenefitRatio

SimplePay BackPeriod inMonths

1Main

Buildings1, 90, 000 1, 64, 000 26, 000 14 37, 000 1.42 18

2PavilionBuilding

32, 000 12, 000 20,000 62 8,000 0.4 5

3Zone 2

Building2,420 1, 275 1,145 47 2,000 1.75 21

4Zone 3

Building3,019 2,447 572 20 1,000 1.75 21

Total 2, 27, 000 1, 80, 000 47, 000 21 48, 000 1.02 12

Page 25: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

BEE – MuDSM PROGRAMME

Name of ULB : Sagar Municipality, Name of ESCO : EPIC Energy Ltd,Madhya Pradesh. Mumbai.

IGEA on WTP and Water Supply Scheme

Sagar Municipality have established and maintain

1) 1 No. - Raw water Pump House with 4 Nos. Motor Pump sets at RajGhat River course.

2) 1 No. - Water Treatment Plant.3) 1 No. - Clear Water Pump House with 4 Nos. Motor Pump sets.4) 1 No. - Elevated water Reservoir to supply water under Town water supply

scheme to Sagar Town through 6 No. Over Head Tanks of capacity :

2 No. x 3500 KL2 No. x 3000 KL2 No. x 2500 KL

In addition to these, the areas not covered by municipal water lines and water serviceconnections, untreated water is being supplied directly from 2 Nos. Open well Pumps andwater Tankers and 13 Nos. Submersible Pumps with open water Taps.

The schedule of water supply to the public by Sagar Municipality is delivering watersupply for 2 days with 1 day break.

There are 22,000 house water Service connections with a Tariff of Rs. 100 /- PerMonth and 400 Commercial water Service connections with a Tariff of Rs. 300 /- Per Month.

The schedule of works approved by BEE & carried out by ESCO are as follows.

Water Treatment Plant : As per approval As per Site

Pump Study - 21 Nos. - 23 Nos. ( 8 + 15 )Parallel Operation Study - 10 Nos. - 4 Nos. only (Others not possible).Transformers’ Study & - 1 No. - 1 No.Distribution Audit

Page 26: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

The details of River Intake - Dam in Raj Ghat :

1) Catchment area - 472 Sq. Kms.2) Catchment area - 1700 Hectares.3) Full Storage - 96 Million Litres.

Live Storage - 80 Million Litres.Dead Storage - 16 Million Litres.

4) Length of Dam - 1680 Meters.5) Rock Portion - 1280 Meters.6) River Bed Level - 495 Meters.7) Lower chill Level - 509 Meters.8) Highest Bed Level - 518 Meters.9) Max. Flood Level - 520.5 Meters.

The City’s requirement of water under the water Supply Scheme assessed as :(i) 15 MLD for the People of 29 Wards out of 48 Wards and,(ii) 5 MLD for the balance 19 Wards (through Tankers & open Line Taps).

The excisting Schedule of Operation of Motor Pumps sets at Raj Ghat Pump House is2 Nos. of 170 KW capacity each running at 17 Hrs / day for 2 Days with 1 Day break.

Pump Capacity = 2 x 1969 m3 / Hr.= 2 x 1969 x 1000 x 17= 67 MLD.

A single Motor Pump can meet out the Town’s requirement of 15 MLD. This notonly reduces the demand on the Transformers, the consumed Unit Charges and also improvesthe performance of the water supply Scheme, giving water to the public for all days with outany break.

By running one No. Motor Pump set only for 17 Hrs. per day continuously

(without any holiday) and operating the other spare pump sets cyclically daily,

Water pumped = 1 x 1969 x 1000 x 17

= 33, 473, 000 LD or

= 33 MLD.

This will be able to meet the Town’s requirement of 15 MLD.

Page 27: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

The KW reduction due to running of only one No. pump for 17 Hours daily insteadof the existing running of 2 No. Pumps for 17 Hours daily for 2 days with one day breakis noted below:

MD reduction & KWhr reduction :

Actual Reading = 40 KWh x 120 / day when 2 motor-pumps operated in parallel.= 4800 KWh / day= 4800 / 17= 282.4 KW for 2 motor-pumps sets running.

By using 1 motor-pump = 282.4 / 2 KW

Reduction in Energy = 141.2 KW or say= 141 KW.

Therefore % Loading = ( 141 / 170 ) x 100= 83 %.

The PF measured is = 0.56.

For each Motor 80 KVAR- power capacitors are in service. Hence, the motors willoperate with 83 % loading which is in the higher efficiency region and does not require anyimprovement. These existing power factor correction capacitors are not enough in capacity.Adding 130 KVAR Capacitors may not be cost effective as energy reduction will be 2%only.

Recommendation :

The existing practice of running 2 No. pumps for 17 hours per day for 2 days withone day break can be stopped and instead 1 No. pump can be run for 17 hours daily withchange of spare pumps cyclically daily to meet the Town’s water requirements.

By the above, the MD as well as Unit reduction can be achieved to obtain EnergySavings.

Clear Water Pump House :

One No. Pump running for 17 Hrs daily can meet the Town’s requirements= 1 x 1875 x 17 x 1000= 31, 875 MLD or say= 32 MLD.

Page 28: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

The KWh reduction and the KVA - MD reduction by running one No. pump set dailyinstead of running 2 No. pump sets for 2 days and with one day break are detailed below.

Energy Saving Calculations :

At Raj Ghat Raw Water PH :

KVA MD Reduction - 170 / 0.8 = 212.5 KVA

At WTP - Clear Water PH :

KVA MD reduction = 845 / 0.8= 1056 KVA by operating one motor-pump

instead of two motor-pumps.

Total KVA reduction by stopping one No. motor at Raw Water Pump House as wellas Clear Water Pump House is given below :

Total KVA reduction = 212.5 + 1056= 1268.5 KVA

Without any investment, by stopping one motor pump set and running only one motorpump daily at Raw Water & Clean Water Pump House, Energy reduction will be :

Total KVA reduction = 1268.5 KVA

The Contract Demand with Utility = 1684.0 KVA

Sagar Municipality unnecessarily pays penalty every month and this can be avoidedby containing the MD to the level of CD - 1684 KVA.

KWh reduction :

Annual Energy Saving = 170 KW x ( 68 - 51 ) x 10 x 12 +845 KW x ( 68 - 51 ) x 10 x 12

= 3, 46, 800 + 17, 23, 800= 20, 70, 600 Units

Annual Monetary benefit = Rs 2.95 x 20, 70, 600= Rs 61, 08, 270 or say= Rs 61, 08, 2000 /-

Page 29: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

Total Annual Energy Saving = 1268.5 KVA + 20, 70, 600 units

Total Annual Energy Saving = Rs 17, 51, 000 + Rs 61, 08, 000= Rs 78, 59, 000 /-

Cost of Investment = “ NIL ’’

The average recorded demand - 2552.0 KVAThe KVA reduction, recommended - 1268.5 KVA

-------------------The KVA utilization & recording will be - 1283.5 KVA

-------------------This is well within the Sanctioned and Contract Demand with MPSEB = 1684 KVA

with a cushion of 400.5 KVA to accommodate any emergency or additional requirement.

Now the Municipality pays penalty for exceeding the Contract Demand of 1684 KVAunnecessarily. By the above arrangement, the Contract Demand of 1684 KVA can becontained. Hence paying penalty for exceeding the Contract Demand will be a saving to theMunicipality. After implementing the proposed Schedule, the MD is restricted to 1684 KVAwhich is the Contract Demand.

Energy Saving by avoiding excess consumption over Contract Demand :

Penalty paid by Sagar Municipality in respect of Raj Ghat

Water Supply Project at Sagar, Loc. Code : 1554500Cons. Code : 600035

Bill for January 2009

Recorded Demand - 2552 KVAContract Demand - 1684 KVAExcess over CD - 868 KVA

Present Energy Consumption:

Per Month Charges for Contract Demand 1684 KVA = Rs. 115 x 1684

= Rs. 1, 93, 660 /-

Per Month Penalty for excess over CD = (115 x 1.5 x 253) + (115 x 2 x 615)

= Rs. 1, 85, 093 /-

Therefore Total Annual Charges for KVA Demand = (1, 93, 660 + 1, 85, 093) x 12

= Rs. 45, 45, 036 /-

Energy Consumption per Year = 76, 15, 200 Units.

Page 30: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

Charges for the Energy Consumption = Rs. 2.95 x 76, 15, 200

= Rs. 2, 24, 64, 840 /-

Total Electricity bill for one year = Rs. 2, 70, 09, 876 /- or say

= Rs. 2, 70, 10, 000 /-

After Municipality Energy Conservation schedule Maximum demand will be within 1684

KVA (Contract Demand). At Rajghat Raw water PH Only one pump of 170 KW is going to run for

17 Hrs / Day for 365 days in a year.

Similarly one pump of 845 KW is going to run at Water treatment plant for 17 Hrs

for 365 days.

Now, Current Annual Energy Consumption = (170 x 17 x 365) +(845 x 17 x 365) Units

= 10, 54, 850 + 52, 43, 225

= 62, 98, 075 Units / Year

Electricity bill for 1 year = MD Charges + Energy Consumption

= (1684 x Rs. 115x 12) +

(Rs. 2.95 x 62, 98, 075)

= Rs. 23, 23, 920 + Rs. 1, 85, 79, 321

= Rs. 2, 09, 03, 24 /- or say

= Rs. 2, 09, 03, 000 /-

Saving in Energy = Rs.2, 70, 10, 000 – Rs. 2, 09, 03, 000

= Rs. 61, 07, 000 /-

Page 31: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

BEE – MuDSM PROGAMME

Name of ULB: Sagar Municipality, MP. Name of ESCO: EPIC Energy Ltd, Mumbai.

IGEA on Water Supply Scheme

SERVICE CONNECTION NO. : 5601605

CAPACITY : 3.75 KW / 5 HP

CONSUMPTION FOR :

Months UnitsAPRIL 2008MAY 2008JUNE 2008JULY 2008AUGUST 2008SEPTEMBER 2008OCTOBER 2008NOVEMBER 2008DECEMBER 2008JANUARY 2009FEBRUARY 2009MARCH 2009

556823503324358267385

0633205328259

TOTAL 4, 641 UnitsAVERAGE 421 Unit /Month

On measurement, the voltage supplied to the service connection is low with lowPower Factor, leading to losses in the motor pump operation. To avoid losses and bring energysaving, Energy saver with built in MCCB control, stabilizer and Power Factor Correction Capacitorsmay be provided.

BASE LINE CONSUMPTION :

Based on Connected Load = 13, 688 UnitsBased on Recorded Consumption = 5, 052 Units

Least of two is fixed as Base Line Consumption = 5, 052 UnitsBill Payable = Rs. 3.05 x 5, 052Annual Bill = Rs. 15, 408 /-

Current Consumption = 0.85 x 5, 052 = 4, 294 UnitsEnergy Saving = Base Line Consumption – Current Consumption

= 5, 052 – 4, 294 Units= 758 Units

Monetary Savings = Rs. 2, 312 /-

Page 32: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

BEE – MuDSM PROGAMME

Name of ULB: Sagar Municipality, MP. Name of ESCO: EPIC Energy Ltd, Mumbai.

IGEA on Water Supply Scheme

SERVICE CONNECTION NO. : 2226601

CAPACITY : 5.75 KW / 7.5 HP

CONSUMPTION FOR :

Months UnitsAPRIL 2008MAY 2008JUNE 2008JULY 2008AUGUST 2008SEPTEMBER 2008OCTOBER 2008NOVEMBER 2008DECEMBER 2008JANUARY 2009FEBRUARY 2009MARCH 2009

865857

1396947932

1025714

-821629

1121806

TOTAL 10, 113 UnitsAVERAGE 919 Unit /Month

On measurement, the voltage supplied to the service connection is low with lowPower Factor, leading to losses in the motor pump operation. To avoid losses and bring energysaving, Energy saver with built in MCCB control, stabilizer and Power Factor Correction Capacitorsmay be provided.

BASE LINE CONSUMPTION :

Based on Connected Load = 20, 422 UnitsBased on Recorded Consumption = 11, 028 Units

Least of two is fixed as Base Line Consumption = 11, 028 UnitsBill Payable = Rs. 3.05 x 11, 028Annual Bill = Rs. 33, 635 / -

Current Consumption = 0.85 x 11, 028 = 9, 374 UnitsEnergy Saving = Base Line Consumption – Current Consumption

= 11, 028 – 9, 374 Units= 1654 Units

Monetary Savings = Rs. 5, 045 /-

Page 33: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

BEE – MuDSM PROGAMME

Name of ULB: Sagar Municipality, MP. Name of ESCO: EPIC Energy Ltd, Mumbai

IGEA on Water Supply Scheme

SERVICES CONNECTION NO. : 2264900CAPACITY : 5.75 KW / 7.5 HP

CONSUMPTION FOR :

Months UnitsApril 2008May 2008June 2008July 2008August 2008September 2008October 2008November 2008December 2008January 2009February 2009March 2009

13090-1403-61894969414308940894

Total 8, 191 unitsAverage 1024 unit /month

On measurement, the voltage supplied to the service connection is low with lowPower Factor, leading to losses in the motor pump operation. To avoid losses and bring energysaving, Energy saver with built in MCCB control, stabilizer and Power Factor Correction Capacitorsmay be provided.

BASE LINE CONSUMPTION :

Based on Connected Load = 20, 422 Units

Based on Recorded Consumption = 12, 288 Units

Least of two is fixed as Base Line Consumption = 12, 288 UnitsBill Payable = Rs. 3.05 x 12, 288

Annual Bill = Rs 37, 478 /-

Current Consumption = 0.85 x 12, 288 = 10, 445 Units

Energy Saving = Base Line Consumption – Current Consumption= 12, 288 – 10, 445 Units

= 1, 843 Units

Monetary Savings = Rs. 5, 621

Page 34: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

BEE – MuDSM PROGAMME

Name of ULB: Sagar Municipality, MP. Name of ESCO: EPIC Energy Ltd, Mumbai.

IGEA on Water Supply Scheme

SERVICE CONNECTION NO. : 2293805CAPACITY : 10 HP

CONSUMPTION FOR :

Months UnitsAPRIL 2008MAY 2008JUNE 2008JULY 2008AUGUST 2008SEPTEMBER 2008OCTOBER 2008NOVEMBER 2008DECEMBER 2008JANUARY 2009FEBRUARY 2009MARCH 2009

2643121018932500118510271201108527521146996754

TOTAL 18, 392 UnitsAVERAGE 1532 Unit /Month

On measurement, the voltage supplied to the service connection is low with lowPower Factor, leading to losses in the motor pump operation. To avoid losses and bring energysaving, Energy saver with built in MCCB control, stabilizer and Power Factor Correction Capacitorsmay be provided.

BASE LINE CONSUMPTION :

Based on Connected Load = 27, 229 Units

Based on Recorded Consumption = 18, 392 Units

Least of two is fixed as Base Line Consumption = 18, 392 UnitsBill Payable = Rs. 3.05 x 18, 392

Annual Bill = Rs 56, 096 /-

Current Consumption = 0.85 x 18, 392 = 15, 633 Units

Energy Saving = Base Line Consumption – Current Consumption= 18, 392 – 15, 633 Units

= 2, 759 Units

Monetary Savings = Rs. 8, 415 /-

Page 35: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

BEE – MuDSM PROGAMME

Name of ULB: Sagar Municipality, MP. Name of ESCO: EPIC Energy Ltd, Mumbai.

IGEA on Water Supply Scheme

SERVICE CONNECTION NO. : 3729606CAPACITY : 3.75 KW / 5 HP

CONSUMPTION FOR :

Months UnitsAPRIL 2008MAY 2008JUNE 2008JULY 2008AUGUST 2008SEPTEMBER 2008OCTOBER 2008NOVEMBER 2008DECEMBER 2008JANUARY 2009FEBRUARY 2009MARCH 2009

3290

57315001419930800115107484388

-TOTAL 6, 645 Units

AVERAGE 665 Unit /Month

On measurement, the voltage supplied to the service connection is low with lowPower Factor, leading to losses in the motor pump operation. To avoid losses and bring energysaving, Energy saver with built in MCCB control, stabilizer and Power Factor Correction Capacitorsmay be provided.

BASE LINE CONSUMPTION :

Based on Connected Load = 13, 688 Units

Based on Recorded Consumption = 7, 980 Units

Least of two is fixed as Base Line Consumption = 7, 980 UnitsBill Payable = Rs. 3.05 x 7, 980

Annual Bill = Rs 24, 339 /-

Current Consumption = 0.85 x 7, 980 = 6, 783 Units

Energy Saving = Base Line Consumption – Current Consumption= 7, 980 – 6, 783 Units

= 1, 197 Units

Monetary Savings = Rs. 3, 650 /-

Page 36: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

BEE – MuDSM PROGAMME

Name of ULB: Sagar Municipality, MP. Name of ESCO: EPIC Energy Ltd, Mumbai.

IGEA on Water Supply Scheme

SERVICE CONNECTION NO. : 2103000CAPACITY : 2.24 KW / 3 HP

CONSUMPTION FOR :

Months UnitsAPRIL 2008MAY 2008JUNE 2008JULY 2008AUGUST 2008SEPTEMBER 2008OCTOBER 2008NOVEMBER 2008DECEMBER 2008JANUARY 2009FEBRUARY 2009MARCH 2009

497362320295170223523198259279

-220

TOTAL 3, 346 UnitsAVERAGE 304 Unit /Month

On measurement, the voltage supplied to the service connection is low with lowPower Factor, leading to losses in the motor pump operation. To avoid losses and bring energysaving, Energy saver with built in MCCB control, stabilizer and Power Factor Correction Capacitorsmay be provided.

BASE LINE CONSUMPTION :

Based on Connected Load = 8, 176 Units

Based on Recorded Consumption = 3, 650 Units

Least of two is fixed as Base Line Consumption = 3, 650 Units

Bill Payable = Rs. 3.05 x 3, 650

Annual Bill = Rs 11, 132 /-

Current Consumption = 0.85 x 3, 650 = 3, 103 Units

Energy Saving = Base Line Consumption – Current Consumption= 3, 650 – 3, 103 Units

= 547 Units

Monetary Savings = Rs. 1668 /-

Page 37: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

BEE – MuDSM PROGAMME

Name of ULB: Sagar Municipality, MP. Name of ESCO: EPIC Energy Ltd, Mumbai.

IGEA on Water Supply Scheme

SERVICE CONNECTION NO. : 5002801CAPACITY : 2.24 KW / 5 HP

CONSUMPTION FOR :

Months UnitsAPRIL 2008MAY 2008JUNE 2008JULY 2008AUGUST 2008SEPTEMBER 2008OCTOBER 2008NOVEMBER 2008DECEMBER 2008JANUARY 2009FEBRUARY 2009MARCH 2009

8391352

-1245

--

845591719926657480

TOTAL 7654 UnitsAVERAGE 850 Unit /Month

On measurement, the voltage supplied to the service connection is low with lowPower Factor, leading to losses in the motor pump operation. To avoid losses and bring energysaving, Energy saver with built in MCCB control, stabilizer and Power Factor Correction Capacitorsmay be provided.

BASE LINE CONSUMPTION :

Based on Connected Load = 13, 688 Units

Based on Recorded Consumption = 10, 205 Units

Least of two is fixed as Base Line Consumption = 10, 205 Units

Bill Payable = Rs. 3.05 x 10, 205

Annual Bill = Rs 31, 125 /-

Current Consumption = 0.85 x 10, 205 = 8, 674 Units

Energy Saving = Base Line Consumption – Current Consumption= 10, 205 – 8, 674 Units

= 1, 531 Units

Monetary Savings = Rs. 4, 670 /-

Page 38: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

BEE – MuDSM PROGAMME

Name of ULB: Sagar Municipality, MP. Name of ESCO: EPIC Energy Ltd, Mumbai.

IGEA on Water Supply Scheme

SERVICE CONNECTION NO. : 4378204CAPACITY : 2.24 KW / 3 HP

CONSUMPTION FOR :

Months UnitsAPRIL 2008MAY 2008JUNE 2008JULY 2008AUGUST 2008SEPTEMBER 2008OCTOBER 2008NOVEMBER 2008DECEMBER 2008JANUARY 2009FEBRUARY 2009MARCH 2009

447454312

-303

-481374288306372355

TOTAL 3692 UnitsAVERAGE 369 Unit /Month

On measurement, the voltage supplied to the service connection is low with lowPower Factor, leading to losses in the motor pump operation. To avoid losses and bring energysaving, Energy saver with built in MCCB control, stabilizer and Power Factor Correction Capacitorsmay be provided.

BASE LINE CONSUMPTION :

Based on Connected Load = 8, 176 Units

Based on Recorded Consumption = 4, 430 Units

Least of two is fixed as Base Line Consumption = 4, 430 Units

Bill Payable = Rs. 3.05 x 4, 430

Annual Bill = Rs 13, 512 /-

Current Consumption = 0.85 x 4, 430 = 3, 765 Units

Energy Saving = Base Line Consumption – Current Consumption= 4, 430 – 3, 765 Units

= 665 Units

Monetary Savings = Rs. 2028 /-

Page 39: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

BEE – MuDSM PROGAMME

Name of ULB: Sagar Municipality, MP. Name of ESCO: EPIC Energy Ltd, Mumbai.

IGEA on Water Supply Scheme

SERVICE CONNECTION NO. : 447108CAPACITY : 3.75 KW / 5 HP

CONSUMPTION FOR :

Months UnitsAPRIL 2008MAY 2008JUNE 2008JULY 2008AUGUST 2008SEPTEMBER 2008OCTOBER 2008NOVEMBER 2008DECEMBER 2008JANUARY 2009FEBRUARY 2009MARCH 2009

527576486553395489289625163470470470

TOTAL 5513 UnitsAVERAGE 459 Unit /Month

On measurement, the voltage supplied to the service connection is low with lowPower Factor, leading to losses in the motor pump operation. To avoid losses and bring energysaving, Energy saver with built in MCCB control, stabilizer and Power Factor Correction Capacitorsmay be provided.

BASE LINE CONSUMPTION :

Based on Connected Load = 13, 688 Units

Based on Recorded Consumption = 5, 513 Units

Least of two is fixed as Base Line Consumption = 5, 513 Units

Bill Payable = Rs. 3.05 x 5, 513

Annual Bill = Rs 16, 815 /-

Current Consumption = 0.85 x 5, 513 = 4, 686 Units

Energy Saving = Base Line Consumption – Current Consumption= 5, 513 – 4, 686 Units

= 827 Units

Monetary Savings = Rs. 2, 522 /-

Page 40: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

BEE – MuDSM PROGAMME

Name of ULB: Sagar Municipality, MP. Name of ESCO: EPIC Energy Ltd, Mumbai.

IGEA on Water Supply Scheme

SERVICE CONNECTION NO. : 2231402CAPACITY : 2.24 KW / 3 HP

CONSUMPTION FOR :

Months UnitsAPRIL 2008MAY 2008JUNE 2008JULY 2008AUGUST 2008SEPTEMBER 2008OCTOBER 2008NOVEMBER 2008DECEMBER 2008JANUARY 2009FEBRUARY 2009MARCH 2009

189276232164

-163568679-

6686

TOTAL 1397 UnitsAVERAGE 140 Unit /Month

On measurement, the voltage supplied to the service connection is low with lowPower Factor, leading to losses in the motor pump operation. To avoid losses and bring energysaving, Energy saver with built in MCCB control, stabilizer and Power Factor Correction Capacitorsmay be provided.

BASE LINE CONSUMPTION :

Based on Connected Load = 8, 176 Units

Based on Recorded Consumption = 1, 676 Units

Least of two is fixed as Base Line Consumption = 1, 676 Units

Bill Payable = Rs. 3.05 x 1, 676

Annual Bill = Rs 5, 112 /-

Current Consumption = 0.85 x 1, 676 = 1, 425 Units

Energy Saving = Base Line Consumption – Current Consumption= 1, 676 – 1, 425 Units

= 251 Units

Monetary Savings = Rs. 766 /-

Page 41: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

BEE – MuDSM PROGAMME

Name of ULB: Sagar Municipality, MP. Name of ESCO: EPIC Energy Ltd, Mumbai.

IGEA on Water Supply Scheme

SERVICE CONNECTION NO. : 4527902CAPACITY : 3.75 KW / 5 HP

CONSUMPTION FOR :

Months UnitsAPRIL 2008MAY 2008JUNE 2008JULY 2008AUGUST 2008SEPTEMBER 2008OCTOBER 2008NOVEMBER 2008DECEMBER 2008JANUARY 2009FEBRUARY 2009MARCH 2009

711668447471

-940514432500

1135514553

TOTAL 6885 UnitsAVERAGE 625 Unit /Month

On measurement, the voltage supplied to the service connection is low with lowPower Factor, leading to losses in the motor pump operation. To avoid losses and bring energysaving, Energy saver with built in MCCB control, stabilizer and Power Factor Correction Capacitorsmay be provided.

BASE LINE CONSUMPTION :

Based on Connected Load = 13, 688 Units

Based on Recorded Consumption = 7, 511 Units

Least of two is fixed as Base Line Consumption = 7, 511 Units

Bill Payable = Rs. 3.05 x 7, 511

Annual Bill = Rs 22, 908 /-

Current Consumption = 0.85 x 7, 511 = 6, 384 Units

Energy Saving = Base Line Consumption – Current Consumption= 7, 511 – 6, 384 Units

= 1127 Units

Monetary Savings = Rs. 3437 /-

Page 42: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

BEE – MuDSM PROGAMME

Name of ULB: Sagar Municipality, MP. Name of ESCO: EPIC Energy Ltd, Mumbai.

IGEA on Water Supply Scheme

SERVICE CONNECTION NO. : 5069907

CAPACITY : 3.75 KW / 5 HP

CONSUMPTION FOR :

Months UnitsAPRIL 2008MAY 2008JUNE 2008JULY 2008AUGUST 2008SEPTEMBER 2008OCTOBER 2008NOVEMBER 2008DECEMBER 2008JANUARY 2009FEBRUARY 2009MARCH 2009

57762246440241352944039139892

1134488

TOTAL 5, 950 UnitsAVERAGE 496 Unit /Month

On measurement, the voltage supplied to the service connection is low with lowPower Factor, leading to losses in the motor pump operation. To avoid losses and bring energysaving, Energy saver with built in MCCB control, stabilizer and Power Factor Correction Capacitorsmay be provided.

BASE LINE CONSUMPTION :

Based on Connected Load = 13, 688 Units

Based on Recorded Consumption = 5, 950 Units

Least of two is fixed as Base Line Consumption = 5, 950 Units

Bill Payable = Rs. 3.05 x 5, 950

Annual Bill = Rs 18, 148 /-

Current Consumption = 0.85 x 5, 950 = 5, 058 Units

Energy Saving = Base Line Consumption – Current Consumption= 5, 950 – 5, 058 Units

= 892 Units

Monetary Savings = Rs. 2720 /-

Page 43: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

BEE – MuDSM PROGAMME

Name of ULB: Sagar Municipality, MP. Name of ESCO: EPIC Energy Ltd, Mumbai.

IGEA on Water Supply Scheme

SERVICE CONNECTION NO. : 494907CAPACITY : 3.75 KW / 5 HP

CONSUMPTION FOR :

Months UnitsAPRIL 2008MAY 2008JUNE 2008JULY 2008AUGUST 2008SEPTEMBER 2008OCTOBER 2008NOVEMBER 2008DECEMBER 2008JANUARY 2009FEBRUARY 2009MARCH 2009

317812284224214580783532712636695615

TOTAL 6404 UnitsAVERAGE 534 Unit /Month

On measurement, the voltage supplied to the service connection is low with lowPower Factor, leading to losses in the motor pump operation. To avoid losses and bring energysaving, Energy saver with built in MCCB control, stabilizer and Power Factor Correction Capacitorsmay be provided.

BASE LINE CONSUMPTION :

Based on Connected Load = 13, 688 Units

Based on Recorded Consumption = 6, 404 Units

Least of two is fixed as Base Line Consumption = 6, 404 Units

Bill Payable = Rs. 3.05 x 6, 404

Annual Bill = Rs 19, 532 /-

Current Consumption = 0.85 x 6, 404 = 5, 444 Units

Energy Saving = Base Line Consumption – Current Consumption= 6, 404 – 5, 444 Units

= 960 Units

Monetary Savings = Rs. 2928 /-

Page 44: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

BEE – MuDSM PROGAMME

Name of ULB: Sagar Municipality, MP. Name of ESCO: EPIC Energy Ltd, Mumbai.

IGEA on Water Supply Scheme

SERVICE CONNECTION NO. : 5373207CAPACITY : 4 HP

CONSUMPTION FOR :

Months UnitsAPRIL 2008MAY 2008JUNE 2008JULY 2008AUGUST 2008SEPTEMBER 2008OCTOBER 2008NOVEMBER 2008DECEMBER 2008JANUARY 2009FEBRUARY 2009MARCH 2009

232-

243143300

-479

0182200370326

TOTAL 2475 UnitsAVERAGE 275 Unit /Month

On measurement, the voltage supplied to the service connection is low with lowPower Factor, leading to losses in the motor pump operation. To avoid losses and bring energysaving, Energy saver with built in MCCB control, stabilizer and Power Factor Correction Capacitorsmay be provided.

BASE LINE CONSUMPTION :

Based on Connected Load = 10, 890 Units

Based on Recorded Consumption = 3, 300 Units

Least of two is fixed as Base Line Consumption = 3, 300 Units

Bill Payable = Rs. 3.05 x 3, 300

Annual Bill = Rs 10, 065 /-

Current Consumption = 0.85 x 3, 300 = 2, 805 Units

Energy Saving = Base Line Consumption – Current Consumption= 3, 300 – 2, 805 Units

= 495 Units

Monetary Savings = Rs. 1, 510 /-

Page 45: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

BEE – MuDSM PROGAMMEName of ULB: Sagar Municipality, MP. Name of ESCO: EPIC Energy Ltd, Mumbai.

IGEA on Water Supply Scheme

SERVICE CONNECTION NO. : 226402CAPACITY : 3 HP

CONSUMPTION FOR :

Months UnitsAPRIL 2008MAY 2008JUNE 2008JULY 2008AUGUST 2008SEPTEMBER 2008OCTOBER 2008NOVEMBER 2008DECEMBER 2008JANUARY 2009FEBRUARY 2009MARCH 2009

160558342257344367400793246337332239

TOTAL 4, 375 UnitsAVERAGE 365 Unit /Month

On measurement, the voltage supplied to the service connection is low with lowPower Factor, leading to losses in the motor pump operation. To avoid losses and bring energysaving, Energy saver with built in MCCB control, stabilizer and Power Factor Correction Capacitorsmay be provided.

BASE LINE CONSUMPTION :

Based on Connected Load = 8, 176 Units

Based on Recorded Consumption = 4, 375 Units

Least of two is fixed as Base Line Consumption = 4, 375 Units

Bill Payable = Rs. 3.05 x 4, 375

Annual Bill = Rs 13, 344 /-

Current Consumption = 0.85 x 4, 375 = 3, 719 Units

Energy Saving = Base Line Consumption – Current Consumption= 4, 375 – 3, 719 Units

= 656 Units

Monetary Savings = Rs. 2, 000 /-

Page 46: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

BEE – MuDSM PROGRAMME

Name of ULB : Sagar Municipality, MP. Name of ESCO : EPIC Energy Ltd, Mumbai.

IGEA on Transformer and Distribution Audit

Sagar Municipality have established 1 No. Power Substation 33 KV / 6.6 KV – 400 VSubstation and availed 1 No. HT service connection from Utility M/s M.P.Poorv KshetraVidyut Vitaran Co. Ltd. Loc. code : 1554500, Cons. code : 600035 and S/C No. 0000000.

The details of Transformers connected are :

2 Nos. x 33 / 6.6 KV - Capacity of 3150 KVA = 6, 300 KVA

1 No. x 33 / 400 V - Capacity of 500 KVA = 500 KVA

Total Transformer Capacity = 6, 800 KVA

Sanctioned / Contract Demand - 1684 KVA

Load Factor of Station based on Transformer Capacity = 6, 34, 600 KVA

6, 800 x 0.9 x 24 x 31

= 6, 34, 600

45, 53, 280

= 0.12

Load Factor based on Max Demand / Contract Demand = 6,34,600

1684 x 24 x 31

= 6,34,600

11, 27,606

= 0.56

The Load Factor - Utilization Capacity to the existing Capacity available ( TransformerCapacity ) is too less. This can be improved by providing 2 x 500 KVA 6.6 KVTransformer and 1 No. 500 KVA 400 V Transformer. By this the load losses can beavoided by achieving Energy Saving.

Page 47: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

By providing the change in Transformer = 6, 34, 600

the Load Factor will become ( 2 x 1000 + 500 ) x 0.9 x24 x 31

= 6, 34, 600

18, 60, 000

= 0.34

The reduction in Transformer Capacity = 6, 800 - 2, 500

= 4, 300 KVA

Energy Saving = 1.0 x 4, 300 x 0.9 x 24 x 365

100

in Units = 3, 39, 012

in Rs = 3, 39, 012 x 2.95

= 10,00,085 or say

= 10,00,000 .

By changing the above Transformers available with the Municipality in the abandonedWater Works, there will be no investments for the Municipality.

By surrendering the Sanctioned / Contract Demand, the existing Load Factor will also beimproved. This proposal has already been given in WTP Audit.

Energy Saving without investment = 3,39,012 units

= Rs. 10,00,000.

* * * * * * * * * * * * * * * * *

Page 48: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

BEE - MuDSM Programme

Name of ULB : Sagar Municipality, Name of ESCO: EPIC Energy Ltd,Madhya Pradesh. Mumbai.

Period of Audit: 28.6.2009 to 09.07.2009.

IGEA on Street Lighting System

Sagar Municipality is serving the general public and road users of Sagar Town byoperating 34 No. Switch points through Timer switching control and MPEB Energy Metersto switch on / off the Street Lighting System and record energy used by Street Lights.

Existing System of Operation and Maintenance of Street Lights

The Municipality uses MPEB Service line poles for fixing Street Light Lamp fittings. There are no separate poles for the Municipality Street Lighting System.

The disadvantages of the existing arrangement of the Municipality

1. The design of the Street Lighting System as per BIS code to bring optimization inLux level and units consumption of electricity.

2. The down time of rectification of failure units is not in the hands of theMunicipality. Even if the Municipality is ready with spare units to replace thedefective ones, the Municipality have to depend on the MPEB to get shut - down andline clear, which makes more down time due to delay on MPEB side.

3. The earthing system also depends on the earth and maintenance on the part ofMPEB, which is not up to the mark. On measuring the leakage and Earth current,Earth current is found to be on the higher side bringing more losses due to poorearthing and leakage current due to unbalancing in the three phases and poorinsulation of Street Light Cables used by MPEB.

Hence the Municipality can plan for independent Street Light poles as per the design basedon BIS 1944 Part II Standards, which will give solution to the above defects bringing moreEnergy Efficiency, Energy Savings, more safety to the road users and general public, betterambience due to improvement in burning status and less down-time etc.

Page 49: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

The Lamps used in the Street Lighting System are given below.

HPSV 180 W Lamps - 1059 No.

Metal Halide 300 W Lamps - 388 No.

Conventional 40 W TFL withMagnetic Choke - 2720 No.

GLS bulb 100 W - 859 No.

CFL – 36 W - 2 No.

CFL – 24 W - 31 No.--------------

Total : 5059 No.--------------

No. of Lamps Burning - 3761 No.

Burning Status - 74 %

Burning status of the Municipal lighting system shall increase from 74 % to 100 % byreducing the down-time of each type of failure by proper Planning and better coordinationwith MPEB by the Municipality.

Base Line Consumption

On review of Bills, it is noted that the energy meter in most of the switch points are foundto be defective and the MPEB adopts average billing. Hence, the Annual recorded / billedconsumption is not considered for fixing of the Base Line Consumption.

Base Line Consumption based on connected Load per Annum

= Circuit Watts / 1000 x No. of Bulbs x Operating Hours

= [ ( 180 / 1000 x 1059 x 3285 ) + ( 300 /1000 x 388 x 3285 ) +

( 53 / 1000 x 2720 x 3285 ) + ( 100 / 1000 x 859 x 3285 ) +

( 36 / 1000 x 2 x 3285 ) + ( 24 / 1000 x 31 x 3285 ) ]

= ( 190.6 + 116.4 + 144.2 + 85.9 + 0.07 + 0.7 ) x 3285

= 537.9 x 3285

= 17, 67, 002 Units.

Annual Base Line Consumption = 17, 67, 002 Units.

Page 50: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

Annual Bill Payable = Rs. 3.20 x 17, 67, 002

= Rs. 56, 54, 406 /- or say

= Rs. 56, 54, 000 /-

Energy Efficiency and hence Energy Saving can be achieved in the Street Lighting Systemby

1. ( a ) Replacing the conventional HPSV – 150 W Lamps by EE - T5 120 W StreetLight Lamps.

( b ) Replacing the conventional 40 W Lamps by EE-T5 Lamps.

{The advantages can be seen from the comparison Table given in the Annexure.}

( c ) Replacing the Filament Lamps 100 W by CFL 36 W.

2. By providing control gears with GSM Technology for better control andMonitoring of Energy consumption, non – burning locations etc., in the CentralComputer at the Municipal office.

By installing Energy Saver with in-built MCCB, Stabilizer and Dimmer withthree selectable slots for fixing burning Hours of Street Lights

--with Voltage Reduction of 10 % during 07:30 pm to 12.00 pm;

--with Voltage Reduction of 20 % during 12.00 pm to 02.30 am;

--with Voltage Reduction of 30 % during 02.30 am to 05.30 / 06.30 am next day.

This brings 15 %, 30 % & 45 % Energy Savings in the Energy bills respectively. ForEnergy Saving calculations, minimum 10 %, 20 % & 30 % values of the three are slotsnoted above are adopted.

Current Consumption Calculations

KW reduction due to 1. (a, b & c ) and ( 2 ) above, in KW.

By1. (a, b & c ),

KW reduction = 537.9 – ( 60 / 1000 x 1059 ) + ( 25 / 1000 x 2720 )

– ( 36 / 1000 x 859 )

= 537.9 – ( 63.5 + 68 + 30.9 )

= 537.9 – 162.4

= 375.5 KW

Page 51: Draft Detailed Project Report On on Name of ULB: Sagar ...sagarmunicipalcorporation.com/downloads/Contents.pdf · Selva Manikandan, Junior Energy Auditor 4. Vijay Shankar, Junior

By ( 2 ),

KW reduction = 0.10 x 375.5 for 4.5 Hrs. = 37.55 KW

= 0.20 x 375.5 for 2.0 Hrs. = 75.10 KW

= 0.30 x 375.5 for 2.5 Hrs. = 112.65 KW

Current Consumption = KW after reduction x Operating Hours.

= ( 337.95 x 4.5 x 365 ) + ( 300.4 x 2 x 365 ) +

( 262.85 x 2.5 x 365 )

= 5, 55, 083 + 2, 19, 292 + 2, 39, 850

= 10, 14, 225 Units.

Bill payable = Rs. 3.20 x 10, 14, 225

= Rs. 32, 45, 000 / -

Energy Saving = BLC – Current Consumption

= 17, 67, 002 – 10, 14, 225

= 7, 52, 777 Units.

In Rs. = 3.20 x 7, 52, 777

= Rs. 24, 09, 000 / -

Monetary Benefit is = Rs. 24, 09, 000 /-

Cost of Investment = Rs. ( 1025 x 2000 ) + ( 2640 x 500 ) +

( 859 x 100 ) + ( 34 x 12500 )

= Rs. 20, 50, 000 + 1, 32, 000 + 86, 000 + 4, 25, 000

= Rs. 26, 93, 000 /-

Cost Benefit Ratio = 26, 93, 000 / 24, 09, 000

= 1.12

Simple Pay Back Period = 1.12 x 12

= 13 Months.

***********************