Draft BMS Spec

download Draft BMS Spec

of 168

Transcript of Draft BMS Spec

  • 8/11/2019 Draft BMS Spec

    1/168

    DRAFT BMS SPEC

    DRAFT BMS SPECIFICATION

    ALAN JONES

  • 8/11/2019 Draft BMS Spec

    2/168

    DRAFT BMS SPEC

    Content

    1.0 AUTOMATIC CONTROLS ............................................................................................................ 1

    1.1 Project outline 1

    1.2 Extent of work 2

    1.3 Scope 3

    1.4

    Standards, Codes and Regulations 7

    1.5 Quality control 8

    1.6

    Responsibilities 8

    1.6.1 Design 8

    1.6.2 Supply 8

    1.6.3 Installation 9

    1.6.4

    Co-ordination with others 9

    1.6.5

    Setting to work the automatic controls 9

    1.6.6 Setting to work the building services 9

    1.6.7

    Monthly Return visits 10

    1.6.8 Handover 10

    1.6.9

    Documentation 10

    1.6.10 Training 10

    1.6.11

    Power requirements 10

    1.7 Services equipment and packaged plant 10

    1.7.1

    Packaged fan starters 11

    1.7.2 Pump starters 11

    1.7.3

    Fan starters 12

    1.7.4 Inverters 12

    1.7.5

    DX systems 12

    1.7.6

    Smoke damper control system 12

    1.7.7 Smoke dampers 13

    1.7.8

    Cold water booster sets 14

    1 7 9 Sprinkler pumps and tanks 14

  • 8/11/2019 Draft BMS Spec

    3/168

    DRAFT BMS SPEC

    1.7.20 Water meters 16

    1.7.21 Transformer monitoring 16

    1.7.22 Trace Heating 16

    1.7.23 Sump pumps 17

    1.7.24 Side stream de-aerator 17

    1.7.25

    System Uvex 17

    1.7.26 Lift monitoring 17

    1.7.27 Disabled toilet alarm 17

    1.8

    Commissioning and Guarantee 17

    1.8.1 General 17

    1.8.2 Commissioning Requirements 18

    1.8.3 Third party attendance 19

    1.8.4 Installation Report 19

    1.8.5 Environmental report 20

    1.9 Approvals and acceptance 21

    1.9.1 Test equipment and instruments 21

    1.9.2 Test certificates 22

    1.9.3 Control and starter panel tests off site 22

    1.9.4 Software testing off site 22

    1.9.5 User Interface off site testing 22

    1.9.6 Pre-commissioning checks 22

    1.9.7 Electrical wiring 23

    1.9.8 Point to graphic 23

    1.9.9 Sensor calibration 23

    1.9.10

    Identification 23

    1.9.11

    Local authority demonstrations 23

    1.9.12 Commissioning records 23

    1.10 Standards of Materials and Workmanship 23

    1 10 1 Submittals 23

  • 8/11/2019 Draft BMS Spec

    4/168

    DRAFT BMS SPEC

    1.17.1 General 30

    1.17.2 Control cables 31

    1.17.3 Power cables 31

    1.18 Field mounted equipment 31

    1.18.1 Control valve selection 31

    1.18.2 Control valves 31

    1.18.3 Sensors 32

    1.18.4 Flow meters 34

    1.19 Electrical supply 34

    2.0 CONTROL PANELS AND CONTROL PANEL ........................................................................... 36

    2.1.1 General 36

    2.1.2 Motor Control Centre (MCC) 36

    2.1.3 Mechanical services power board 37

    2.1.4 Motor sizes 37

    2.1.5 Inverters and Thyristor 37

    2.1.6

    Outstation panels 37

    2.1.7 Off site inspection 38

    2.1.8

    Outstation UPS 38

    2.2 Construction 38

    2.2.1 Door Interlock 38

    2.3 Painting and Finishing 39

    2.3.1 Painting 39

    2.3.2 Galvanising 39

    2.4 Cable Entries 39

    2.5

    Internal Wiring 40

    2.5.1 General 40

    2.5.2 Power Wiring (220 Volts and Above) 40

    2.5.3 ELV Wiring (Control, Indication or Alarm Circuit) 40

    2 5 4 Neutral Bar or Link 41

  • 8/11/2019 Draft BMS Spec

    5/168

    DRAFT BMS SPEC

    2.10 Control Circuits 46

    2.11 Indicator Lights and Alarms 46

    2.12 Electrical power meters 47

    2.13 BMS keypad and display 47

    2.14 Selector Switches 47

    2.14.1 Operation in test position 48

    2.15

    Current Transformers 48

    2.16 Isolators 48

    2.17 Fuse Protection 48

    2.18 Miniature Circuit Breakers 49

    2.19 Earthing 49

    2.20

    Internal Lighting 49

    2.21 Panel heating or ventilation 49

    2.22 Laptop Power 49

    2.23 Rubber Mat 49

    2.24 Drawing Holder 49

    2.25 Ease of Maintenance 49

    2.26 Component Labelling 50

    2.27 Name Plates and Labels 50

    2.28

    Safety Interlocks 502.28.1 Safety 50

    2.28.2 BMS monitoring and action 50

    2.28.3 Individual Plant isolation 50

    2.28.4

    Electric heater batteries 50

    2.28.5 AHU frost thermostats 51

    2.28.6

    Fan isolation dampers 51

    2.28.7 Humidifiers 51

    2.28.8

    Chillers 51

    2.28.9 Boilers 51

    3.0 DESCRIPTION OF PLANT AND SYSTEM OPERATION .......................................................... 52

  • 8/11/2019 Draft BMS Spec

    6/168

    DRAFT BMS SPEC

    3.7 Automatic control valves 56

    3.8 Ventilation Systems 56

    3.8.1 General 56

    3.8.2

    Office Ventilation AHU/R/1 and AHU/R/2 57

    3.8.3 Entrance Hall 60

    3.8.4

    Office toilet extract 61

    3.8.5 Basement plant room ventilation 62

    3.8.6

    Ventilation loading bay extract 63

    3.8.7 Office and Basement smoke extract 63

    3.8.8 Boiler house ventilation 64

    3.8.9 Basement toilet extract 65

    3.8.10 Bin store transfer fan 65

    3.9 Chilled water cooling systems 65

    3.9.1 General 65

    3.9.2

    CHW distribution pumps 66

    3.9.3 Primary cooling pumps P/B/R/1, 2 and 3 67

    3.9.4

    Command 67

    3.9.5 Fault rotation 68

    3.9.6

    Pump Duty rotation 68

    3.9.7 Operation 68

    3.9.8 Fault rotation 68

    3.9.9 Pump Duty rotation 68

    3.9.10 Chiller R1, R2, 68

    3.9.11 Hydraulic pressurisation units 69

    3.10

    Heating Systems 69

    3.10.1

    Secondary circulation heating pumps 70

    3.10.2 Secondary LTHW/DHWS heating pumps 71

    3.11

    CHP 72

    3 11 2 Gas boiler B1 B2 73

  • 8/11/2019 Draft BMS Spec

    7/168

    DRAFT BMS SPEC

    3.13.7 Water Meters 75

    3.14 Other plant interfaces 76

    3.14.1 Trace Heating 76

    3.14.2 Lift monitoring 76

    3.14.3 Control panel power monitoring 76

    3.14.4 Disabled toilet alarm 76

    4.0 BUILDING MANAGEMENT SYSTEM ......................................................................................... 77

    4.1 Building Management System 77

    4.2 General 78

    4.3 Infrastructure 79

    4.4

    Tenants interface 80

    4.5 Responsibility 80

    4.6

    System Supervisor 80

    4.6.1 Central Processor Unit (CPU) 81

    4.6.2

    Visual Display Unit (VDU) 82

    4.6.3 Printer 82

    4.6.4

    Router 82

    4.7 Outstations 82

    4.7.1

    General 82

    4.7.2 Capacity 83

    4.7.3 Installation 83

    4.7.4 Transmission system 84

    4.7.5 Analogue inputs 84

    4.8

    Software upgrades 84

    4.9

    Direct digital control (DDC) 84

    4.10 Logic diagrams 85

    4.11 Electrical supply 85

    4.12 Operational Facilities 85

    4.12.1 General 85

    4 13 S ft 86

  • 8/11/2019 Draft BMS Spec

    8/168

    DRAFT BMS SPEC

    4.13.11 Historical data programme 90

    4.13.12 Event Totalisation 90

    4.13.13 Start and power failure restart programme 91

    4.13.14 Control point reset programme 91

    4.13.15 Sequence Control and Rotation of Plant 91

    4.13.16

    Fault duty rotation 92

    4.13.17 Control loop initiation 92

    4.13.18 Load Cycling Control 92

    4.13.19

    Weather Compensation Control 92

    4.13.20 Sensor default control 92

    4.13.21

    Thermal control 93

    4.13.22 Pressure control 93

    4.13.23

    Control Valve and Actuator Cycling 93

    4.13.24 Minimum plant operation 94

    4.13.25 Fan coil maintenance strategy 94

    4.13.26 Equipment Cycling Protection 94

    4.13.27 Alarm programme 95

    4.13.28 Energy measurement and metering calculation program 97

    4.13.29 Electrical energy 97

    4.13.30 Maximum Demand 97

    4.13.31 Run time totalisation program 98

    4.13.32 Gas and water utility metering 98

    4.14 Graphics 98

    4.14.1 General 98

    4.14.2

    Movement between the Graphics 99

    4.14.3 Data Display 99

    4.14.4 Specific graphic displays 99

    4.15 Installation, Training and Commissioning 100

    4 15 1 S f T t 101

  • 8/11/2019 Draft BMS Spec

    9/168

    DRAFT BMS SPEC

    1.0 AUTOMATIC CONTROLS

    The Controls Contractor shall read this document in conjunction with all sections of the Contract

    preliminaries, Technical specifications, Architectural, Structural and Services drawings.

    The Automatic Control system, or Building Management System (BMS), will provide control and monitoring

    for the shell and core services. The system will be a Direct Digital Control (DDC) type with fully distributed

    intelligence. The system shall be configured to allow full access viaa web browser and be expandable to

    other systems by use of BacNet/IP, LonMark/IP or Modbus/IP.

    The control system will be provided by a single supplier who shall have full responsibility for the works.

    The system shall comprise of a number of local control instruments and intelligent outstations that can

    operate independently of other parts of the project. When global information is required, this may be

    transmitted viathe BMS network. However, all safety interlocking and some demand based signals shall be

    transmitted by hardwired connections between outstations.

    The Contractor is to note the building is a Section 20 building.

    Where specialist systems are provided, the installation and engineering shall in all ways reflect the full

    requirements of this specification. Wherever the term controls contractor is used this shall apply equally to

    the specialist suppliers.

    The stair/lobby fire fighting ventilation system is provided by a specialist supplier.

    The fan coils may be provided with an integral control system. Where this is the case the FCU supplier shall

    take full responsibility for the interface to the BMS and shall have a full time site presence during the flushing

    and commissioning of the water and air systems and the BMS associated with the FCUs.

    The smoke damper control system is provided by a specialist supplier. The system shall operate in the

    smoke mode as dictated by the smoke control system during any emergency mode. The above ground

    system shall during normal operation interface to the BMS to allow floor by floor operation of the smoke

    dampers to provide isolation for unoccupied floors. The below ground installation shall be monitored by the

    BMS for damper status only. The interfaces shall be software utilising Modbus or BACnet. The installation

    and engineering shall in all ways reflect the full requirements of this specification. The specialist supplier

    shall have a full time presence during the commissioning of the BMS associated with the dampers. The

    specialist supplier shall take full responsibility for the software interface to the BMS. The controls contractor

    shall include sufficient engineering time and costs to fully integrate these specialist systems within the BMS.

    The BMS shall provide tenant interfaces on each floor for software and hardwired extension of the base build

    BMS.

  • 8/11/2019 Draft BMS Spec

    10/168

    DRAFT BMS SPEC

    The Building Management System is a direct digital control system with fully distributed intelligence. Each

    major plant item shall be wired and controlled from the local motor control centre with all drives having

    inverters. Control panels shall be provided for each fan coil unit.

    1.2 Extent of work

    The controls contractor shall design, supply, install, set to work, test and commission the complete automatic

    control and building management system required to serve all mechanical services installations specified, in

    the project specification, unless specifically stated otherwise hereafter. The scope will incorporate all starterpanels, mechanical services power distribution boards, control outstations, software, control field devices,

    valve and damper actuators, inverters, all controls and power wiring, including carrier systems, setting to

    work, commissioning and all documentation and training necessary to allow the user to operate the

    installation both reliably and safely.

    The Controls Contractor will offload, transport to its final location and position all equipment of his supply.

    He will fit all equipment of his supply other than the valve bodies and pipeline temperature pockets. The

    Mechanical Contractor will fit all necessary pipework pockets and valves and connect to any pipeline

    differential pressure switches.

    If large plant items such as control panels are to be split for delivery, the controls contractor shall include all

    costs for handling and reassembly and insulation testing of power sections.

    The power to the fan coil units shall be wired by the electrical contractor with a fused spur. Final termination

    from the spur to the control unit shall be by the controls contractor.

    The electrical contractor shall provide power to the plant room Mechanical plant power distribution boards

    and all remote outstations and network hubs.

    The controls contractor will size, provide and install all power wiring and carrier system between the Control

    enclosures, the Mechanical services power boards, the MCCs and the drives including isolators and lockstop

    circuits.

    The exception to this is the power and control wiring to the staircase smoke control fans and all motorised

    smoke dampers, other than those that are directly related to fans. The specialist contractors shall carry out

    this wiring installation.

    The controls contractor will size, provide and install all controls wiring and carrier systems between; MCCs

    and Outstations, and all field mounted controls instruments and actuators and other equipment BMS

    interfaces.

    The Automatic Control enclosures shall house all motor starters, hand/off/auto switches, on/off and duty

    selector switches, electric interlocking and recycling relays, indicator lights, electronic control equipment,

  • 8/11/2019 Draft BMS Spec

    11/168

    DRAFT BMS SPEC

    It is the Controls Contractor's responsibility to size and select every item required for the project. The

    information provided in this document is for tender purposes only.

    1.3 Scope

    The controls system shall interface to and control the building services equipment shall include but is not

    limited to the following:

    1. Controls to office AHU AHU/R/1 and associated extract fans and ran around pump inverters,

    supplied by controls contractor, fitted and wired to motor by controls contractor. Set to work by the

    controls contractor;

    2. Controls to office AHU AHU/R/2 and associated extract fans and ran around pump inverters,

    supplied by controls contractor, fitted and wired to motor by controls contractor.. Set to work by the

    controls contractor;

    3. Controls for the office smoke extract fans. inverters, supplied by controls contractor, fitted and

    wired to motor by controls contractor. Set to work by the controls contractor. (The controls

    contractor shall include at tender stage extra over costs for the motors being star/double star type,

    including additional power caballing to each motor)

    4. Controls for the office toilet extract fans. inverters, supplied by controls contractor, fitted and wired

    to motor by controls contractor. Set to work by the controls contractor.

    5. Controls to entrance hall AHU inverters, supplied by controls contractor, fitted and wired to motor

    by controls contractor. Set to work by the controls contractor.

    6. Controls to boiler house ventilation supply and extract fans inverters, supplied by controlscontractor, fitted and wired to motor by controls contractor, set to work by the controls contractor.

    Thyristor and controls for the electric heater supplied and set to work by the controls contractor.

    7. Controls to basement AHU and associated extract fan inverters, supplied by controls contractor,

    fitted and wired to motor by controls contractor. Set to work by the controls contractor;

    8. Controls to loading bay extract fans. inverters, supplied by controls contractor, fitted and wired to

    motor by controls contractor. Set to work by the controls contractor. These fans double up as

    smoke extract, when in smoke control the fan speed is achieved from the fire control panel

    9. Controls interface to basement toilet extract fan. Package starter provided by mechanical

    contractor, fitted and wired by controls contractor.

    10 Controls for all chilled water circulation pumps; inverters supplied by controls contractor fitted and

  • 8/11/2019 Draft BMS Spec

    12/168

    DRAFT BMS SPEC

    15. Interface to the gas boilers, through hardwired interlocks - boiler controls and starter supplied, and

    commissioned by mechanical contractor. All interconnecting wiring by boiler supplier;

    16. Controls associated with the heating plate heat exchangers;

    17. Controls interface to the heating pressurisations units;

    18. Controls interface to the heating water treatment systems;

    19. Boiler house gas system complete with gas valve, gas safety systems. Monitoring gas meter, meter

    provided by mechanical contractor.

    20. Main gas incomer, monitoring gas meter, meter provided by mechanical contractor

    21. Controls interface to the CHP

    22. Controls and inverters for the CHP system circulation pumps

    23. Controls and inverters for the CHP ventilation fans. Including controls for the heating coils.24. Controls interface to the heating pressurisations units

    25. Controls interface for the thermal stores

    26. CHP gas valve and gas safety systems. Monitoring gas meter, meter provided by mechanical

    contractor

    27. Monitor the landlords oil system

    28. Controls Interface to the basement smoke system control panel through software connections for

    monitoring purposes

    29. Controls Interface to the lobby ventilation control system. The lobby ventilation control system

    including panels shall be provided , installed and set to work by the specialist supplier

    30. Interface to the smoke system control panel to allow floor by floor zoning. Smoke control system tobe provided with Modbus or BACnet connectivity. Dampers to be controlled and monitred for

    position through the BMS. Fire system shall take precedence in a fire mode

    31. Hardwired connections to all smoke ventilation dampers actuators, associated with fans that require

    to be operated by the BMS. Actuators and dampers to be supplied by the mechanical contractor.

    A t t fitt d d i d b th t l t t

  • 8/11/2019 Draft BMS Spec

    13/168

    DRAFT BMS SPEC

    37. Alternatively where FCUs with integral controls are provided, the FCU supplier shall configure all

    FCU control strategies and provide full engineering interface for software to the BMS. The FCU

    supplier shall have a full time site presence during flushing and air/water balancing of all FCU

    systems. The specialist supplier shall have a full time presence during all BMS commissioning

    associated with the FCUs.

    38. Controls for all duct mounted heater/cooler batteries

    39. Controls for all space heating zones

    40. Controls interfaces and monitoring of LV switchroom cooling systems

    41. Controls interfaces and monitoring of management suite cooling systems

    42. Power provision and monitoring the trace heating systems

    43. Monitoring the potable water storage tanks. All tank high level switches and temperature sensors

    provided by the controls contractor.

    44. Supply and set to work the storage tank motorised isolation valve RAWS approved-. Valve

    hardwired to tank high level and water leak detection system

    45. Monitoring the water sterilisation treatment system;

    46. Monitoring the UV water sterilisation system;

    47. Monitoring the cold water potable water booster set - Integral controls and starters supplied, installed

    and commissioned by the mechanical contractor. The controls contractor shall carry out allinterconnecting wiring between the tanks and the pump control panel

    48. Monitoring the non-potable water storage tanks. Al tank high level switches and temperature

    sensors provided by the controls contractor.

    49. Supply and set to work the storage tank motorised isolation valve RAWS approved-. Valve

    hardwired to tank high level and water leak detection system

    50. Monitoring the water sterilisation treatment system;

    51. Monitoring the UV water sterilisation system;

    52. Monitoring the cold water non potable water booster set - Integral controls and starters supplied,

    installed and commissioned by the mechanical contractor. The controls contractor shall carry out all

    i t ti i i b t th t k d th t l l

  • 8/11/2019 Draft BMS Spec

    14/168

    DRAFT BMS SPEC

    58. Supply and set to work all water meters RAWS approved, associated with the mains water , the

    feeds to the pressurisation units and the distribution systems

    59. Monitoring the sump pumps. All interconnecting wiring between the floats and the control panel to

    be carried out by the mechanical contractor

    60. Monitoring the lifts;

    61. Monitoring the disabled toilet alarm system - alarm system to be supplied, installed and

    commissioned by the electrical contractor;

    62. Monitoring the transformers;

    63. Monitoring LV tripping batteries

    64. Monitoring the generator.

    65. All control valves and actuators. Combined thermal control and differential valves for valves other

    than the terminal units - to be Tour and Anderson type KT and KTM. The controls contractor shall

    select all valves in conjunction with the mechanical contractor and TA;

    66. All control valves and actuators for the terminal units such as FCUs , perimeter heating remote duct

    mounted heating/cooling coils.. All valves to be combined thermal control and differential valves - to

    be Frenger Optima range. The controls contractor shall select all valves in conjunction with the

    mechanical contractor and Frenga

    67. All actuators for ventilation dampers that require to be operated by the BMS;

    68. All field instruments that form the automatic controls system

    69. Provision and installation of all instruments for two optimisers per floor. Provision and installation of

    two RH sensors to each floor.

    70. All mechanical services power boards and support frames. The roof and basement essential powerboards shall be cubicleised form 4 type 2.

    71. All control panels and support frames

    72. Where panels are located outside the building, the controls contractor shall provide a weatherproof

    enclosure and ant condensation heaters. MSPB-R-1, CE-R-1/1, 1/2, 1/3. 1/4

  • 8/11/2019 Draft BMS Spec

    15/168

    DRAFT BMS SPEC

    79. All networks, inclusive of outstations, routers, switches, panel mounted UPS and the like

    80. All main plant controllers to have UPS. All routers and switches to have UPS. UPS to maintain

    communications from plant controllers to head end for a minimum of 60 minutes.

    81. Tenants Interface outstations on each floor for hardwired and software interface for tenant complete

    with spare and addressed RJ45 socket, for future tenants network.

    82. Interface on each floor for future connection to heat/coolth meter. Lon or M-bus.

    83. All operating software, firmware and licences;

    84. Complete BMS engineering and configuration;

    85. Energy monitoring and management package;

    86. BMS head end supervisor, inclusive of all operating software and server, complete with web browser

    email and SMS functions. The controls contractor shall provide a 30 minute UPS for the head end

    workstation;

    87. Line printer for alarm and general messages;

    88. A3 colour laser jet printer for reports;

    89. Keypad and display screen on the MCC fascia in both the roof AHU compound and the boiler house;

    90. Fully integrated BMS/controls and plant testing, setting to work and commissioning;

    91. Return visits to retune the system operations;

    92. Full commissioning of all inverters irrespective if these are provided by the controls contractor or not

    93. Detailed trend logging and installation report of complete system;

    94. Operating and maintenance manuals

    95. Assistance with production of the building log book

    96. Training of operators

    97. All necessary consumables for the project. At project completion provide new printer cartridges and

    paper.

    1.4 Standards, Codes and Regulations

    The Automatic Controls will be designed, installed, tested and commissioned in accordance with the

  • 8/11/2019 Draft BMS Spec

    16/168

    DRAFT BMS SPEC

    Current Institute of Plumbing Standards;

    The current Electrical Regulations with amendments;

    The Environmental Health and Safety Office; and

    Manufacturers Recommendations for Installation Testing Commissioning and

    The Landlords Regulations and Approvals.

    Materials and installation will conform to the relevant current Local Standards where applicable.

    Where no such standards exist, the equipment will include for the known factors and requirements

    and will be installed to suit the manufactures recommendation.

    All equipment furnished for the project will be suitable for their location and suitable for purpose.

    Reference will be made to BS 6204, BS 5850, BS 6527, BS 6667, BS 800, BS 5486, CIBSE Guides

    and Commissioning Code C, BS 5750 and the Controls Group Publications.

    1.5 Quality control

    The contract will be carried out under following the principles of the Contractor's Quality Assurance

    documentation. All equipment supplied will receive commercial tests to comply with IEE Regulations.

    All equipment will be CE marked.

    1.6 Responsibilities

    1.6.1 Design

    The Controls Contractor will examine all drawings and documentation and will produce for approval the basis

    of design. The design will be carried out by competent engineers and will be suitable for the intended

    purpose. The design will incorporate any necessary statutory requirements with respect to Health and

    Safety.

    The Controls contractor shall produce the system description of operations. These shall clearly show the

    system operation, hardwired and software interlocks, the operation during fault conditions, alarm handling,

    head end adjustments.

    The Controls Contractor will advise the Engineer of any changes that the Controls Contractor considers

    would be beneficial to the system. These modifications will not involve additional costs to the Engineer

    unless the Controls Contractor demonstrates, at tender stage, that the documentation issued by the

    Engineer is unworkable.

    1 6 2 Supply

  • 8/11/2019 Draft BMS Spec

    17/168

    DRAFT BMS SPEC

    themselves. The Controls Contractor will off-load, position in its final location and fix all equipment of their

    supply.

    1.6.3 Installation

    The Controls Contractor will install and wire all equipment necessary for the complete operation of the

    building management system. The control system will be installed by competent engineers regularly

    employed by the Controls Contractor.

    The complete system will be installed under the supervision of an experienced field supervisor familiar with

    all parts of the control system. He will ensure that the work is of the highest standard and will carry out the

    daily co-ordination and system interface as required to ensure the completion of the project within the agreed

    programme of works.

    The installation shall include all necessary carrier systems and supporting steel work for control panels and

    inverters.

    1.6.4 Co-ordination with othersThe Controls Contractor will liaise closely with all other Contractors to ensure that the installation works

    proceed in an orderly and co-ordinated manner. They will, for instance, provide within 14 days of receipt of

    an instruction to precede a panel schedule. This will identify the size and location of every panel to be

    installed. The schedule will also show all electrical requirements.

    With regards to main wiring routes, the Controls Contractor will provide their desired routes to others in the

    form of drawings. The Controls Contractor will appreciate that they will not always be able to route their

    cables in whatever direction they demand. The single conduit runs may be site co-ordinated and will beinstalled in a neat and orderly manner.

    It is a requirement of this document that the Controls Contractor provides floor plans showing the location of

    any control device that is to be mounted in the occupied space. These are to be provided to the architect

    two weeks after receipt of the instruction to proceed.

    1.6.5 Setting to work the automatic controls

    The controls contractor shall be responsible for setting to work the system of his supply. The controlscontractor shall recognise that the BMS is an integral part of the building services and as such the operation

    of the major plant requires close co-operation with the M & E contractors and their appointed

    representatives. The controls contractor shall allow in the contract costs for the standalone commissioning

    of his system, i.e. the BMS from the head end to the field interface with a third party and his own equipment.

    In addition the controls contractor shall allow for the integrated testing required to set the building services

  • 8/11/2019 Draft BMS Spec

    18/168

    DRAFT BMS SPEC

    electrical interfaces such as breaker positions and power meters are to be carried out by the controls

    contractor.

    1.6.7 Monthly Return visits

    The controls contractor shall include in the contract costs three return visits after contract completion. These

    shall be at four monthly intervals and have a duration of at least one month at each visit. During this time the

    controls contractor shall review the operating parameters of the plant to ensure efficiency of use, provide

    enhanced training to the user, modify head end displays as appropriate, verify the remote interfaces such asSMS and web browsers, review the maintenance and management reports. The cooling systems shall be

    inspected in the cooling periods and the heating in the heating period. The time shall not be spent correcting

    contract defects, nor carrying out maintenance.

    1.6.8 Handover

    The controls contractor shall work in conjunction with all other contractors to enable the complete project to

    be handed over as set out in the contract documents. The controls contractor shall recognise that the

    Automatic Controls is likely to be the last system completed and therefore sufficient engineering staff shall be

    available throughout the hand over process.

    1.6.9 Documentation

    The controls contractor shall provide all documentation necessary to allow the user to operate the plant both

    efficiently and safely. The controls contractor shall provide sufficient information to and co-operate with the

    mechanical contractor for the production of the building log book.

    1.6.10 Training

    The controls contractor shall train the users staff in all aspects of the automatic controls and BMS.

    1.6.11 Power requirements

    The controls contractor shall carry out all power wiring of equipment connected to the motor control centres

    and the controls outstations. Inclusive of cabling between the spurs the LCMs and the outstations.

    The controls contractor shall make all final power connections, including the provision of any required cablingbetween the local fused spur and the terminal equipment. This shall include but not be limited to:

    Fan coil units

    All free standing outstations

    The power cables shall be installed within a flexible steel conduit and fixed to the building structure

  • 8/11/2019 Draft BMS Spec

    19/168

    DRAFT BMS SPEC

    The packaged plant shall be delivered to site complete with all starters and hardwired control systems. The

    package controls shall allow the plant to operate without the external influence of the BMS. The extent of

    packaged plant shall be developed, but shall include the following:

    Chillers

    Gas fire boilers

    Electric heaters

    Sump pumps Water pressurisation units

    Twin fan units

    Split DX systems

    Trace heating

    Domestic hot water system

    Cold water booster sets, including all, starters and interconnecting wiring between the tank high andlow level switches and the booster set panel; and

    Smoke damper control system

    Fire fighting staircase ventilation system

    1.7.1 Packaged fan starters

    Where packaged fan starters are provided, these shall be installed and commissioned by the mechanical

    Contractor. The IP65 control panel shall include duty change over and duty sharing timers for twin fan setsand all motor protection and speed controllers. The starters shall be interfaced to the BMS through an extra

    low voltage interface and be complete with a local/remote selector switch. The panel shall include fan run

    indicator and fault lamps. The interface to the BMS shall include:

    1. Single Fan set

    Unit enable;

    Fan 1 running;

    Fan 1 fault

    2. For dual fans

    Unit enable;

  • 8/11/2019 Draft BMS Spec

    20/168

    DRAFT BMS SPEC

    contacts that shall be wired to the inverter enable circuit. The plant supplier shall configure the inverter

    such that manual operation is only possible once all external safety interlocks are satisfied. It shall be

    unacceptable that any inverter can be run from the key pad without the safety interlocks being healthy.

    All pumps greater than 1.1kW shall have inverters.

    1.7.3 Fan starters

    Each fan shall be provided with a matched inverter wired to the motor. The power wiring shall be to the

    recommendation of the inverter manufacturer and shall be not less than 4-core with an earthed screen. Anisolator shall be provided up stream of the inverter. The isolator shall have early brake late make auxiliary

    contacts that shall be wired to the inverter enable circuit. The plant supplier shall configure the inverter

    such that manual operation is only possible once all external safety interlocks are satisfied. It shall be

    unacceptable that any inverter can be run from the key pad without the safety interlocks being healthy.

    All fans greater than 1.1kW shall have inverters.

    1.7.4 InvertersThe inverters shall be provided by the controls contractor. The inverters forming part of the staircase smoke

    ventilation system shall be provided by the specialist supplier.

    The contractor supplying the inverter shall set to work and commission the units to match the BMS

    operations. The inverter supplier shall be responsible for all technical aspects of the inverters as described

    both in the mechanical specification and in clause 2.8 of this specification. The controls contractor shall

    however provide management of all inverters and shall provide support during commissioning to establish

    the operation of all inverters.Where critical systems fans are provided with inverters they shall be set to operate in the fire mode utilising

    the fire jog commands. If other speeds are required during a fire mode these shall be set using combination

    of relays wired direct to the inverter jog command.

    All inverters shall be IP 54 and complete with a keypad and connected to the BMS through hardwired and

    software connections.

    1.7.5 DX systems

    The mechanical contractor shall supply and install all works for the DX cooling systems. The equipment

    shall include the internal and external units along with all controllers. The mechanical contractor shall

    include all interconnecting wiring and carrier systems for the power and controls between the external and

    internal units and the room controllers. The BMS shall enable the units and monitor for fault, the controllers

    shall communicate to the internal and external units

  • 8/11/2019 Draft BMS Spec

    21/168

    DRAFT BMS SPEC

    The BMS shall provide software signals to the smoke damper control system to allow each floor ground and

    above to operate independently of any other. The software and necessary hardware shall be developed and

    supplied by the controls contractor. The smoke control system supplier shall provide engineering services at

    no cost to the controls contractor for this work.

    1.7.7 Smoke dampers

    The dampers complete with suitable actuators and decoders shall be supplied and fitted by the mechanical

    contractor. They shall be motor open/motor closed and spring closed/open on power failure. The fail safeposition shall be determined to suit the life safety operation. The actuators and decoders shall be located

    out of the smoke extract compartment, or enclosed in a suitably fire rated enclosure. The actuator shall have

    separate end switches indicating closed and open positions, these shall be adjustable between 90oand 70

    o.

    The actuators that are required to be driven by the BMS for normal operation, interlocked directly with

    ventilation fans, shall be 24VAC type and be complete with open position end switches.

    The actuators that are controlled by the smoke control system and powered directly from the essential power

    circuits shall be 240V.The actuators shall be located out of the fire zone or provided by the mechanical contractor with a fire rated

    enclosure.

    All wiring associated with the control of the dampers shall be carried out in fire rated cable FP600. Where

    the damper is directly associated with a ventilation fan the wiring between the MCC/outstation and the

    damper shall be by the controls contractor. All 'remote' dampers shall be wired by the damper specialists.

    1.7.7.1 Smoke make up ventilationThe air make up to the offices and basement areas shall be provided from the opening shafts and the main

    office ventilation fans as appropriate. When required to operate the smoke control system shall set the

    isolation dampers to the appropriate position either open or closed and open the appropriate air make up

    routes.

    The appropriate fans shall be set to run using hardwired strategy in the control panels. This is initiated by

    the local fire/smoke system interface units.

    1.7.7.2 Office smoke extract ventilation

    The roof mounted smoke extract fans provide extract from the office floors via the normal extract duct route.

    When required to operate the smoke damper control system sets the floor isolation dampers to the

    appropriate position. The two duty extract fans are enabled via hardwired signals from the fire detection OR

    smoke damper control system as appropriate

  • 8/11/2019 Draft BMS Spec

    22/168

    DRAFT BMS SPEC

    The system shall be provided and to set work by the mechanical contractor or the specialist supplier. The

    specialist supplier shall provide all control panels, fan inverters, actuators, controllers, controls and power

    wiring including carrier systems for the complete system.

    1.7.8 Cold water booster sets

    The cold water booster sets, shall be provided with integral controls and interconnecting wiring by the

    mechanical contractor. The BMS shall interface for monitoring.

    The controls contractor shall provide and install a water board approved motorised shut off valve for theincoming water system. The actuator shall be suitable for the BMS operation and operated through

    hardwired control from a controls contractor supplied and installed panel. The valve shall close if the tank

    high level alarm is or the water leak detection is active. The valve shall remain closed for minimum of (30)

    minutes after the alarm has cleared.

    The controls contractor shall carry out all interconnecting wiring between the pumps and the tanks. The tank

    low level switches shall be hardwired interlocked with the pumps to prevent pumps running dry.

    The cold water booster set supplier shall provide the tank1/tank2/tank1&2 selector switches on the coldwater booster set control panel.

    1.7.9 Sprinkler pumps and tanks

    The sprinkler system shall be a self contained package with interface monitoring provided by the fire

    detection system. The BMS shall monitor the system for status.

    1.7.10 Wet riser pumps and tanks

    The sprinkler system shall be a self contained package with interface monitoring provided by the fire

    detection system. The BMS shall monitor the system for status.

    1.7.11 Water leak detection

    The tank room water leak detection system shall be supplied and installed by the controls contractor. The

    BMS shall interface for monitoring and activation of shut off valves through hardwired interlocks. The system

    shall be zoned such that major tank areas are separately monitored.

    1.7.12 Fan coil units

    The fan coil units shall be provided by the mechanical contractor. The controls contractor shall free issue all

    control items to the FCU supplier, including the valves actuators and temperature sensors.

    If th FCU id d ith i t l t ll th t t t f th BMS k th FCU li

  • 8/11/2019 Draft BMS Spec

    23/168

    DRAFT BMS SPEC

    1.7.13 Three speed conventional FCU

    The FCU supplier shall supply the fan speed controller, fan enable relay and transformer both for the FCU

    and the BMS controller. The FCU supplier shall wire all components and supply these in a steel enclosure

    fixed to the side of the FCU chassis. The FCU shall be delivered to site complete with a 3m flying lead for

    power. The BMS Contractor shall liaise with the supplier during the construction and provide the necessary

    assistance to ensure that the wiring and panel design is suitable. The controls contractor shall visit the

    supplier and test 10% of the FCUs to verify the production process. The units shall have heating and cooling

    two port modulating valves, supply and return air temperature sensors all provided by the controls contractor.The meeting room units shall have supply air and room temperature sensors complete with temperature

    adjust and override button.

    1.7.14 Variable speed FCU

    The FCU supplier shall supply the fan speed controller, the enable relay, running and fault indication. The

    BMS contractor shall free issue the controller, controls transformer, heating and cooling two port modulating

    valves for wiring off site by the FCU supplier.

    The FCU shall be delivered to site complete with a 3m flying lead for power. The BMS Contractor shall liaise

    with the supplier during the construction and provide the necessary assistance to ensure that the wiring and

    panel design is suitable. The controls contractor shall visit the supplier and test 10% of the FCUs to verify

    the production process. The units shall have two port modulating valves, supply and return air temperature

    sensors.

    1.7.15 Chillers

    The mechanical contractor shall provide all integral controls for the chillers. The chillers shall have hardwired interlocks to the BMS for control and monitoring.

    The chillers external safety interlocks such as the evaporator flow switches shall be wired by the controls

    contractor.

    The chiller package shall include a relay coil driven by the power feed for the crankcase heater. The

    normally open contacts shall be monitored by the BMS to determine power status.

    1.7.15.1 Chilled water flow temperature.

    The chiller shall be provided with a 4-20mA connection that shall allow the BMS to reset the chilled water

    flow temperature between limits 5.5oC to 10

    oC. The flow temperature shall default to 5.5

    oC if the input signal

    fails.

  • 8/11/2019 Draft BMS Spec

    24/168

    DRAFT BMS SPEC

    1.7.18 Gas valves and meters

    The controls contractor shall provide, all gas valves and meters for the project. The gas valves shall be

    wired from an appropriate control panel and interlocked as appropriate with the ventilation and fire systems.

    The boiler house valve shall be hardwire interlocked to the fire alarm and the boiler house gas detection and

    thermal link system. The valve 'closed' status shall be monitored at the panel and displayed with a lamp. In

    the event of gas detection, boiler house fire alarm, EPOs or the thermal links being active, the gas valve

    shall close and an audible alarm be raised on the detection panel and the boiler house control panel.

    The CHP gas valve shall be hardwire interlocked to the fire alarm and the CHP gas detection and thermal

    link system. The valve 'closed' status shall be monitored at the panel and displayed with a lamp. In the

    event of gas detection, boiler house fire alarm, EPOs or the thermal links being active, the gas valve shall

    close and an audible alarm be raised on the detection panel and the CHP control panel

    The gas valves shall be supported by the gas UPS. The UPS shall support all gas safety systems.

    A reset button shall be provided for each valve on the CE. In the event of a power fail and restoration a BMS

    pulsed output wired in series with the reset buttons shall attempt to reset the valve. The pulse shall remainactive for (10) seconds only.

    Each valve shall have an associated meter, with pulsed outputs provided by the mechanical contractor. The

    BMS shall monitor the gas usages via pulsed outputs.

    1.7.19 Heat meters

    The heat meters shall be supplied and installed by the controls contractor, with all necessary controls

    interfaces. These shall include but not be limited to: pulsed outputs for volume flow rate and energy usage.

    In addition a software connection shall be provided and connected to the BMS for data recording.

    All meters shall be provided with matched temperature sensors. The controls contractor shall carry out all

    interconnecting power and controls wiring associated with the meters.

    Heat meters are required for two purposes. The primary plant meters are required for monitoring and control

    of the main equipment, these meters shall be installed as part of the base build works.

    Tenants floor meters are required for future billing and monitoring of tenants services. These meters shall

    not be installed in this contract. However all BMS infrastructure shall be provided including the on flooroutstation and the M-bus or LON card.

    1.7.20 Water meters

    The controls contractor shall provide all water meters with pulsed outputs for volume flow rate. The meters

  • 8/11/2019 Draft BMS Spec

    25/168

    DRAFT BMS SPEC

    The power to the trace heating panels shall be wired by the trace heating contractor, from isolators providedby the controls contractor.

    1.7.23 Sump pumps

    The mechanical contractor shall provide, install and set to work the sump pumps for the project. The pumps

    shall have local control panels with volt free monitoring points provided for the BMS interface. The

    monitoring points shall include but not be limited to:

    Power available

    Pump fault (common)

    Pump running (common)

    Sump high level

    1.7.24 Side stream de-aerator

    The mechanical contractor shall provide, install and set to work the side stream de-areators. The BMS shall

    monitor the units for status and fault.

    1.7.25 System Uvex

    The mechanical contractor shall provide, install and set to work the system Uvex. The BMS shall monitor the

    units for status and fault.

    1.7.26 Lift monitoring

    The lift contractor shall supply and install the lift management system. Within each lift motor room the lift

    contractor shall provide an ELV panel to which, the lift contractor shall wire the lift monitoring points to this

    ELV panel. The controls contractor shall monitor the lift status from these volt free contacts.

    Lift alarms shall include:

    Lift in fire mode

    Passenger alarm

    Maintenance

    Common fault

    1.7.27 Disabled toilet alarm

    The electrical contractor shall provide, install and set to work the system. The BMS shall monitor the units

    for status and fault

  • 8/11/2019 Draft BMS Spec

    26/168

    DRAFT BMS SPEC

    proper working order. The controls contractor shall formulate and issue the test method statementsindicating the testing to be carried out and the expected results. At the completion of any test the controls

    contractor shall issue the result sheets, signed and annotated with relevant comments.

    The commissioning will also include the off site testing of all software, starter and control panels.

    The Controls Contractor will include in his bid for all labour, special instruments, materials, tools, plant and

    equipment required to carry out the pre-commissioning and the performance testing of the control systems,

    all in accordance with the relevant CIBSE Commissioning Codes and this specification.

    The Controls Contractor will demonstrate to the complete satisfaction of the Client Representative that the

    installation or any portion thereof, which has been set to work, complies with the requirements of the

    specification.

    Any defects of workmanship, materials, performance, maladjustment's, non-compliance with this

    specification, or other irregularities which become apparent during the tests will be rectified by the Controls

    Contractor, at no additional cost to the contract, and the cost of the original test together with any repeat

    tests will be at the Controls Contractors expense until the whole is proved free from defects and in complete

    working order to the complete satisfaction of the Client Representative. All systems will be left sound andcorrect.

    The Controls Contractor will pursue his own claims against others in respect of tests that fail due to his work

    being damaged by others. Damage to other work caused by failures under test will be made good at the

    Controls Contractor's expenses and the Controls Contractor will make provision for meeting claims made

    against him for damage to other trades works as a result of failure of the controls installations undergoing

    tests.

    The Controls Contractor will be required to co-ordinate and co-operate with the commissioning contractorduring these works, who will direct and co-ordinate the commissioning of all controls, mechanical services,

    ductwork, air handling plant and electrical work associated. The Controls Contractor is required to provide

    labour, staff and work with the commissioning Contractor until all systems are commissioned and balanced

    to the Client Representatives satisfaction.

    After the above-mentioned conditions have been met in full and the system is fully operational, it shall be

    guaranteed for the defects liability period stated herein. Following each sectional completion of the works,

    the controls manufacturer shall allow for a minimum of four additional separate visits to site to check oncontinued satisfactory control performance.

    1.8.2 Commissioning Requirements

    The testing and commissioning shall be as described elsewhere in the specification and conform to the

    following requirements:

  • 8/11/2019 Draft BMS Spec

    27/168

    DRAFT BMS SPEC

    All contractors shall provide services of skilled commissioning engineers, certified test equipment, tools andinstruments for any tests and make good any defects.

    The controls contractor shall test, calibrate, adjust, check and reset thermostatic and automatic controls and

    shall provide all test certificates and calibration charts.

    The Contractors shall provide all necessary temperature and humidity records and charts and attendance so

    that records can be taken of plant performance in such areas that the Client Representative may decide.

    The controls contractor shall test all electrical equipment associated with the automatic controls installationand provide test certificates.

    The controls contractor shall establish from the main contractor that the installation is covered by insurance

    prior to carrying out full performance tests under actual working conditions.

    The controls contractor shall check the operation of all alarms, safety devices and plant interlocking by

    simulating fault conditions.

    During the defects liability period the controls contractor shall make several visits to the site and shall carry

    out thorough checks for continued satisfactory controls operation.

    Such adjustments that are necessary to the controls installation under actual working conditions shall be

    made by the controls contractor and reported to the Client Representative and shall take due account of

    variation due to occupancy of the building, seasonal changes or variations in the operation of mechanical

    plant under control etc.

    Until the final check and adjustment has been carried out the contract shall not be considered for final

    acceptance and the balance of retention sums shall not be released.

    1.8.3 Third party attendance

    The Electrical and mechanical contractors shall provide attendance to the controls contractor to allow the

    controls contractor to set required field measurements such as system operating pressures required to

    achieve design air and water flow rates.

    Particular attention is required where the fan coil units, the smoke dampers and the fire fighting lobby

    systems are integrated within the BMS.

    The electrical and mechanical contractors shall provide attendance both from themselves and specialist

    plant supplier, to allow the controls contractor to test all interfaces to third party equipment. The testing shall

    not be limited to simulations, but will include full testing from end to end of each plant item. This would

    include for instance: forcing water system high and low pressures through adding and draining water from

    the systems, forcing boilers to lock out, forcing chillers to flow failures, forcing DX/VRF to fail, forcing

  • 8/11/2019 Draft BMS Spec

    28/168

    DRAFT BMS SPEC

    During the seven day period the mechanical contractor shall arrange for step changes to be made to theplant to demonstrate that the BMS is able to recognise the change and react accordingly.

    The mechanical and electrical contractor shall provide a detailed test plan prior to commencing the works.

    The testing shall include but not be limited to such items as:

    1. Optimised start;

    3. Building frost protection;

    4. Plant frost protection;

    5. Individual boiler failures;

    6. Individual chiller failures;

    7. Individual pump failures;

    8. Inverter faults;

    9. Fan coil operation

    10. Smoke damper operation

    11. Staircase lobby smoke control system

    12. Failures of the pressurisation units;

    13. Failures of water treatment plant;

    14. Power failures to individual MCCs;

    15. Power failures to individual remote outstations;

    16. Failed temperature, pressure and humidity sensors;

    17. Disconnection of network at individual MCCs;

    18. Manual plant operation from the head end;

    19. Issuing of emails and SMS text messages during fault conditions;

    20. Operation of MCC and plant room emergency knock off buttons;

    21. Failure of main switchboards;

    22. Failure of mains incoming power;

    23. Generator operation and failure;

    24. Oil system failure;

    25. Transformer faults

    26. Fire cause and effect.

  • 8/11/2019 Draft BMS Spec

    29/168

    DRAFT BMS SPEC

    The Mechanical and Controls Contractor shall submit a record of this survey in the form of a bound reportshowing plant operating conditions and times, outside and inside temperature and humidity and supply

    systems wet and dry bulb temperatures.

    The survey shall monitor air temperature and moisture content (including control tolerance) for at least six

    positions per floor for a period of 14 days. The survey shall include the monitoring of plant start/stop times,

    morning boost operation, heating and chilled water primary and secondary system flow and return

    temperatures, supply and extract air temperatures and humidity.

    The survey shall include the demonstration of plant loading and unloading at the dictates of the turbine watermeters and demonstration of the pump variable speed control under load variation viathe differential

    pressure monitoring sensors. Appropriate commissioning contractor attendance shall be provided to

    manually adjust the system where necessary to simulate load variance and to validate controls calibration for

    flow measurement and differential pressure.

    Include with the survey three sets of control drawings and schedules showing final set points of all controllers

    required to obtain the above results.

    1.9 Approvals and acceptance

    Services will be tested to show their compliance with this specification and to the requirements of the

    relevant service authority. Proof of compliance with any service authority requirements will be supplied to

    the Client Representative. After receipt of the commissioning reports the Client Representative will check

    that the claimed results are within the allowed tolerances. The Controls Contractor will give the Client

    Representative 7 days written notice of his intention to demonstrate and seek an acceptance certificate for

    any item or system. All tests for acceptance certification of systems or items of equipment will be witnessed

    by the Client Representative or their appointed representatives. The Controls Contractor will allow for givingsuch notice and making adjustments, setting up, and other preparations for testing and for the Client

    Representative or their representatives attendance in witnessing such tests. The Controls Contractor will

    carry out testing and commissioning work using trained, experienced engineers. The supervising

    commissioning engineers will have a minimum of five years experience in the testing and commissioning of

    heating, air-conditioning and ventilation controls installations.

    The controls contractor shall demonstrate the works to the main contractor who shall approve the installation

    along with the appropriate mechanical and electrical contractor. The main contractor shall initial all testsheets indicating their approval and comments. When satisfied with the works the main contractor shall offer

    the system for review to the Employer.

    1.9.1 Test equipment and instruments

    The Controls Contractor will supply and fix all necessary apparatus and instruments for making tests on the

  • 8/11/2019 Draft BMS Spec

    30/168

    DRAFT BMS SPEC

    1.9.2 Test certificates

    The Controls Contractor will provide four copies of test certificates to the Client Representative bearing the

    signatures of the Controls Contractor. Test certificates will serve as a certified record that the item referred

    to has been shown under test to meet the requirements of this document, Local Standards, Statutory and

    Local Authority Regulations and the like, wherever applicable. Test certificates will be dated, numbered and

    clearly referenced to the item tested by means of serial, chassis, or other manufacturer's reference number

    permanently marked in a conspicuous position on the item concerned.

    If the Client Representative does not attend to witness tests on receipt of correct period of written notice fromthe Controls Contractor then the tests will be carried out by the Controls Contractor who will sign and submit

    certified copies of test certificates to the Client Representative. The Client Representative reserves the right

    to have such sections of the work tested by the Controls Contractor but not witnessed by the Client

    Representative, re-tested. In the event that such a re-test shows the work to be defective the Controls

    Contractor will bear the cost of this and any necessary subsequent tests.

    In addition to the above, test certificates will be submitted to Statutory or Local Authorities as may be

    required.

    1.9.3 Control and starter panel tests off site

    The Controls Contractor will test all control and starter panels off site. The work will verify that the panel has

    been built to the approved wiring diagrams. The controls contractor shall issue both a method statement

    outlining the testing and a test report indicating the results.

    All fuse/MCB sizes, overload and contactor rating are to be confirmed. The hand and automatic operation of

    all switches is to be verified. All interlocks are to be tested. The panels are to be pressure tested to 2.0 KV

    for one minute. An insulation resistance test will then be completed.

    The Client Representative will be invited to attend the tests.

    1.9.4 Software testing off site

    The Controls Contractor will test all software off site. The offsite set-up will as close as possible reflect the

    number of necessary interconnected outstations to simulate the site works. The software will be

    demonstrated by wiring the outstation to switches lamps and potentiometers. These will represent digital

    and analogue input/output points. The testing will include the full dynamic graphics to include all user

    interfaces, alarm messages and dynamic displays of the simulated field points. This testing is important and

    the Controls Contractor must allow plenty of time to demonstrate every point and allow the client and his

    representative every opportunity to understand and if necessary modify the software or user interfaces.

    It is important that these tests are started early in the project

  • 8/11/2019 Draft BMS Spec

    31/168

    DRAFT BMS SPEC

    1.9.7 Electrical wiring

    Wiring terminations to all control equipment supplied by the Controls Contractor will be checked both for

    compliance with the control wiring diagrams and interlocks with other equipment shown on the electrical and

    mechanical sub- Contractor's wiring diagrams. All motors will be checked for rotational direction.

    The commissioning of all instrumentation supplied with the control panels will be the responsibility of the

    Controls Contractor.

    1.9.8 Point to graphic

    Every field point shall be verified from field to graphic. Where this includes third party equipment the third

    party supplier shall provide full attendance during this work.

    1.9.9 Sensor calibration

    Every sensor shall be verified with a certified instrument, to show that the measured value is displayed

    accurately in the controller and at the head end. Where this includes third party equipment the third party

    supplier shall provide full attendance during this work.

    1.9.10 Identification

    The identifying labels on all items of equipment will be checked as being in accordance with the

    requirements detailed elsewhere and corrected where in error.

    1.9.11 Local authority demonstrations

    The Mechanical contractor shall co-ordinate with the local authority all tests and demonstrations demandedby building control. The controls contractor shall assist with the works, along with the fire detection

    specialist. The tests shall include, but not be limited to: demonstrations of the life safety fans, including air

    flow and differential pressure measurements, demonstrations of the fire detection system and its interaction

    with the mechanical services.

    1.9.12 Commissioning records

    The Controls Contractor will submit to the Client Representative a complete set of data on all equipment and

    systems which he commissions. The submittals will be on A4 size paper and the form which they take willbe agreed with the Client Representative before their submission. They will show the design figures and the

    final operating values at which the systems and equipment were set by the commissioning engineer.

    1.10 Standards of Materials and Workmanship

  • 8/11/2019 Draft BMS Spec

    32/168

    DRAFT BMS SPEC

    The Controls Contractor will provide for approval, within the agreed programme period, samples of anycomponent that is to be mounted within the occupied space. The Controls Contractor will provide points

    charts within twenty-eight days following the placing of the main order.

    The Controls Contractor will provide block wiring diagrams and schedules appertaining to the interfaces

    between the Controls Contractor works and other parties. All block wiring diagrams will be complete with the

    Controls Contractors terminal numbers.

    Where the controls interfaces with other equipment the controls contractor will co-ordinate the interface

    wiring diagrams and provide the necessary interface hardware.

    1.10.2 Inspections/approval/requirement

    The contract requires that the works of the Controls Contractor will be to the inspection, approval,

    agreement, satisfaction or requirements and the like of the Client Representative. No such inspection,

    approval, agreement, satisfaction or requirements and the like of the Client Representative will in any way

    imply or be construed as relieving the Controls Contractor of his responsibilities for performance and

    dimensions or other responsibilities described in this contract or otherwise at Law.

    Where the Client Representative is required to affix their inspected stamp to the Controls Contractor's

    detailed specification, drawings, manuals, samples and the like, no such inspection or stamp will in anyway

    imply or be construed as relieving the Controls Contractor of his responsibilities for performance, dimensions

    or other responsibilities described in this contract or otherwise at Law.

    No alteration to the performance or other requirements of this specification will be made unless a variation

    instruction is issued by the Client Representative, which expressly requires such alteration.

    1.11 Common Contro l Requirements

    1.11.1 General

    The following control requirements shall be common to all systems except where specified to the contrary in

    subsequent sections of the specification:

    1. All duplicated equipment will be configured for automatic changeover in the event of fault and duty

    rotation cycle on a daily cycle. Plant that duty rotates after a fault remains in the new position until

    the next duty rotation, even if the system alarms are cleared. If a duty rotation is required and the

    current standby plant is in a fault condition, the duty rotation is suppressed.

    2. All main plant such as chillers, boilers and the like shall duty rotate on a weekly basis and if in a fault

    condition.

  • 8/11/2019 Draft BMS Spec

    33/168

    DRAFT BMS SPEC

    off. During this action unnecessary ventilation plant shall not be energised such as fan coil units,underfloor or trench heating systems.

    7. All duplicated equipment, located in a common MCC, shall have their contactors cross-wired such

    that only one drive can run at a time. If both are in the hand mode and the running drive trips the

    standby drive shall start.

    8. The hardwired safety interlocks for plant operation shall operate in both the MCC hand and auto

    switch position. All hardwired interlocks shall be mimicked in software.

    9. Fire alarms shall shut down or initiate the systems as appropriate. Stage one frost protection shall

    be active during a fire mode, if required. The fire alarms shall override the auto and hand position

    of all drives but not the off. Major ventilation fans shall be controlled through hardwired interlocks,

    hydraulic systems shall be controlled through software.

    10. When shutting down, through normal software all drives shall have a run on period set. This shall

    form part of the software and is normally associated with the dissipation of heat or humidity.

    11. System control loops for temperature and pressure shall be initiated, when air or water flow is proven

    at the system drive. The loops shall also be enabled to suit system demands such as frost,

    optimiser functions and valve positions. Heating systems shall be disabled when outside air

    temperatures are above (18)oC, unless demands exist for such strategies as dehumidification.

    12. High limit protection systems shall be provided for all low-pressure hot water heating and domestic

    hot water service installations to restrict water temperatures within safe limits.

    13. Every point will have mis-match alarms set. These include drives running when commanded to stop,

    drives stopped when called to run, temperature values outside of acceptable range e.g. supply air

    temperatures < 8oC, >30oC, room temperatures < 16oC, > 26oC.

    14. Every drive, with the exception of small packaged plant, will be individually monitored by the BMS.

    Drives are to be monitored by DP switches, current sensing relays, and phase angle shift

    measurement as appropriate. The flow proving device shall be wired through auxiliary contacts on

    the starter, or in series with the inverter run status such that the status of each drive is known.

    Pump and fan DP switch pressure tappings shall be located down stream and upstream of any local

    isolating valves or dampers.

    15. Where small packaged plant is provided, typically

  • 8/11/2019 Draft BMS Spec

    34/168

    DRAFT BMS SPEC

    22. In the event of power supply failure all safety valves shall be arranged to either close or open toreach a safe condition.

    23. The hydraulic static pressure can be considered to be sixteen bar with a differential of 350 Kpa.

    24. All damper actuators shall be sized to suit the damper torque. For tender purposes each actuator

    shall be limited to 1m2 of damper area. All damper actuators shall have external indicators. All

    damper actuators shall have end switches for monitoring purposes

    25. Any flying leads associated with the actuators are to be of a LSOH material and have a maximum

    length of 1500 mm. Where the dampers are used for fire or smoke control the control cabling shall

    be fire rated.

    26. The power cabling installation will include isolators to every packaged plant item. Motors driven from

    the MCC will have isolators for drives up to and including 5kW and isolators and lockstop buttons for

    all drives above 5kW. The isolators for drives shall all have auxiliary early brake late make contacts

    that form part of the control circuit.

    27. All equipment will be suitable for the environment in which it is to be placed. This, for example,

    means that any device located outside of the building envelope will be IP65 rated. The use of

    protective bags is an unacceptable solution.

    28. The Controls Contractor will wire every outgoing control cable from the panels of their supply.

    29. Each point in the control system will be connected to a single outstation terminal. The use of

    multiplexers, raise/lower modules or the like is not permitted.

    30. Sufficient hardware will be provided to allow every point: field and virtual to be logged simultaneously

    for 24 hours at 1-minute intervals.

    31. Sufficient hardware / software will be provided to allow global commands to be sent to the terminal

    units for: stop / start, change temperature set point, open fully all control valves, 100% output on

    electric heaters.

    32. Each life safety drive shall have an available input wired to the BMS. This shall show that: power is

    available in the starter cubicle, the starter has not tripped, the field isolator/lockstop is healthy, and

    the MCC T/O/A switch is in the auto position.

    33. All dials and gauges indicating pressure or temperature, etc., shall be marked in metric units.

    34. The response time of all control sensing and actuating equipment shall be related to the needs of the

    installations under control in order to ensure quickness of response consistent with freedom from

    "hunting". The control systems shall be sufficiently sensitive to meet the control band requirements

    specified without "hunting" Any limitations in this respect shall be stated in the Tender

  • 8/11/2019 Draft BMS Spec

    35/168

    DRAFT BMS SPEC

    38. All set points shall be adjustable between reasonable limits at the head end. The software shall beconstructed such that unacceptable values can not be entered by mistake. I.e. CHW flow shall not

    be possible below 5oC, HTG flow above 80

    oC, Air supply temperatures below 11

    oC or above 30

    oC. It

    shall be possible to adjust the slope of compensated circuits using the heating water values not the

    outside air temperature.

    39. All BMS wiring will be carried out in twisted pair cables, each pair being individually screened.

    40. If multicore cables are used then, if acceptable to the Controls manufacturer, a common outer

    screen may be employed.

    41. BMS extra low voltage cables will have a minimum cross sectional area of 0.75 mm2(7/0.37 mmdia).

    With due regard to cable resistance for sensors.

    42. All power cabling shall be installed in conduit, trunking or on tray as appropriate. All power cables

    shall be single core LSF in conduit with XLPE/LSF/SWA being used on tray or any exposed

    surfaces. Low voltage power cables shall have a minimum csa of 2.5mm2

    43. All field cables associated with an Inergen extract system shall be run in FP 400. Motor isolators

    shall be metal clad.

    44. All field power cables associated with the building smoke extract system shall be run in Pyro. Motor

    isolators shall be metal clad.

    45. All field controls cables associated with the building smoke extract system shall be run in fire rated

    material.

    46. All fans unless otherwise indicated shall be provided with an inverter. Where these are used for

    variable flow the inverter shall be controlled accordingly. In other instances, the inverter shall becontrolled at a fixed speed utilising the fixed speed command at the inverter with the speed set in the

    inverter software.

    1.12 Instructions to client

    The Controls Contractor will include in his Bid for instructing the Client and his representatives in the

    operation of the system during testing and commissioning.

    The Controls Contractor will include for a one week site training course for four operators identified by theend user.

    1.13 Building log book part L compliance

    The mechanical contractor shall provide the user with the building log book to comply with the building

  • 8/11/2019 Draft BMS Spec

    36/168

    DRAFT BMS SPEC

    3. Description of operations and hardcopy of software.

    4. Description of the management use of the head end supervisor. This would include but is not limited

    to: booting of the system, signing on, setting and changing passwords and access levels, graphical

    navigation, setting all set points, acknowledging and resetting alarms. Setting of alarm parameter

    and error messages, archiving data, back up and restoration, creation of dynamic graphics,

    assigning point names to field and graphic devices. The provision of a catalogue is not acceptable.

    The descriptions shall be written specifically for the project.

    5. Handbooks, maintenance instructions, drawings and spare parts list for all components, plant andequipment used in the Contract works.

    6. Line diagrams indicating the main features of the plant, drawing attention to the method of setting the

    control dampers, switchgear, safety precautions etc.

    7. Schedule of routine maintenance, complete with list of normal consumables.

    8. Schedule of periodic and preventative maintenance for specialised equipment.

    9. Schedules of methods of adjustments, typical fault-finding routines.

    10. Schedule of operation and maintenance risk assessment sheets in accordance with the Construction

    (Design and Management) Regulations 2007.

    11. Wiring diagrams of plant etc, including points, charts and logic diagrams

    12. Service manual for all specialised plant, giving all details as listed above.

    13. Schedule for obtaining and ordering replacement parts.

    14. Schedules of equipment valves and motors related to the "As Installed" drawings and giving names,

    address and telephone number of manufacturer, serial number of plant, kilowatt-power electrical

    supply, performance duties and location within the building.

    15. Description of emergency action that should be taken in case of a breakdown of equipment.

    Telephone numbers of essential contacts shall be included.

    16. Outline design data of plant.

    17. Test and performance data, including all set points.18. Test Certificates.

    19. Schedule of "As Installed" Drawings. These shall indicate the location and reference of every field

    mounted instrument and actuator.

    20 L d f l d d i

  • 8/11/2019 Draft BMS Spec

    37/168

    DRAFT BMS SPEC

    Prepare the Operation and Maintenance Manuals in draft as soon as the Installation Drawings are in hand.

    Make two temporary manuals with provisional record drawings and preliminary performance data available at

    commencement of the project and populate throughout the works. These should be of the same format as

    the final manuals with temporary insertions for items, which cannot be finalised until the Contract is

    commissioned, and performance tested.

    The cover shall be printed with the following information:

    Operating and Maintenance Instruction Manual (Project Name and Service).

    Where more than one volume is required, the cover shall also be printed with volume number.

    Each section of the manual shall be divided by a stiff divider of the same size as the holder. The divider

    shall be labelled as to the section of the manual.

    All written instructions within the manual shall be typewritten with a margin on the left-hand side.

    The arrangement of the manual shall be as follows:

    1. Section One Index

    2. Section Two

    Description of the Design Intent

    3. Section Three

    Description of plant operation. The description must include step by step instructions on starting and

    stopping each plant or system and a fault diagnosis procedure in diagrammatic and tabular form toshow the action necessary to correctly identify defective pieces of equipment and the steps to be

    taken to rectify faults. The final set points shall be indicated.

    4. Section Four

    Planned maintenance instruction. This section must include systematically instruction on the

    maintenance of all items of plant. Data shall also be provided for ordering replacements. Full sets of

    manufacturers maintenance instructions including wiring diagrams, cable schedules, and circuit

    chart. Protection and overload relay settings shall be recorded and calibration charts shall beincorporated.

    5. Section Five

    A set of record drawings and Test Certificates. If necessary due to the number of drawings, which

    have to be included in the manual, each drawing shall be photographically reduced to size to suit the

  • 8/11/2019 Draft BMS Spec

    38/168

    DRAFT BMS SPEC

    It shall be the Controls contractors responsibility, whenever a successive phase of contract is handed over,to amend and update the previously issued version of the Operation and Maintenance Manuals, bring it to

    the appropriate stage of completion and submit same to the Engineer in due time to comply with the Health

    & Safety at Work Act.

    1.15 Maintenance cont ract

    The Controls Contractor will include a separate quotation at the time of tender for a full maintenance contract

    for the system offered. This will include:

    1. Routine maintenance.

    2. All replacement parts excluding consumables.

    3. Immediate call out in the event of a fault, on a 24 hour, 365 day a year basis. The quotation will be

    based on a fixed price with an agreed formula for increased costs.

    4. The maintenance will include on a yearly cycle:

    5. Upgrades of the operating system software as new standard developments are issued.6. Data back up and archiving.

    7. Documentation upkeep.

    8. Calibration of all sensors with replacement as necessary.

    9. Testing all actuators and linkages with replacement as necessary.

    10. Testing all battery back up and replacement as necessary.

    11. Performance testing of each system and adjustment of parameters to achieve a balanced

    environment versus energy use. If the controlled plant, e.g. boiler, is shown to have degraded year

    on year, then this is outside of the controls maintenance regime.

    12. Thermal imaging to ascertain weak spots of all controls starter panels with repairs as necessary.

    13. Testing all safety devices with replacement as necessary.

    14. All equipment necessary for the maintenance, including access tools, will be provided by the

    maintenance Contractor.

    1.16 Labelling

    All equipment provided by the Controls Contractor will clearly labelled. The labels will be traffolyte with black

    lettering on white background. The labels will, with due care and attention, be screwed to the equipment.

  • 8/11/2019 Draft BMS Spec

    39/168

    DRAFT BMS SPEC

    1.17.2 Control cables

    All low voltage cables will be single core PVC, insulated Butyl, with an LSOH outer sheath and screened if

    necessary to the relevant specification, having stranded copper conductors. All BMS system wiring will

    conform to the current edition of the IEE regulations. Cables will not be connected directly to the outstations.

    All cables will terminate at screwed terminals and subsequently be wired to the outstation. Electrical

    screening will be provided to the extra low voltage cable by the use of screened cable.

    All BMS wiring will be carried out in twisted pair cables, each pair being individually screened. If multicore

    cables are used then, if acceptable to the Controls Contractor, a common outer screen may be employed.Multicore cables may be used so long as all conductors are terminated on the outstation. Any unused

    conductors will be terminated to earth at both ends.

    BMS extra low voltage cables will have a minimum cross sectional area of 0.75 mm2 (7/0.37 mm dia). With

    due regard to cable resistance for sensors.

    Low voltage cables will have a minimum cross sectional area of 1.5 mm2.

    Screening will be provided by an aluminium/polyester foil shield with a multistrand drain wire (7/0.37). All low

    voltage BMS cables will be sheathed in LSOH material.

    All controls cabling, including the BMS network will be installed in conduit or trunking.

    1.17.3 Power cables

    All power cables within conduit or trunking shall be single core XL/LSF 6491B. The minimum cross-sectional

    area shall be 4mm2. Conductors shall be stranded throughout.

    1.18 Field mounted equipment

    1.18.1 Control valve selection

    All control valves will be selected and sized to be suitable for the systems application and operating

    conditions. Unless otherwise stated valves will be of the asymmetrical modulating type with rangeability of

    50:1 having equal percentage characteristic as necessary to provide acceptable system control.

    All systems with two port control valves shall have Frese Optima combination valves fitted.

    Where the Frese Optima range is not available the two port valves shall be TA KTM type.

    All main plant control two port valves shall be TA KTM type.

    1.18.2 Control valves

  • 8/11/2019 Draft BMS Spec

    40/168

    DRAFT BMS SPEC

    Valve authorities will be between 0.3 and 0.5 computable with economic valve pressure drops sufficient toprovide adequate control without promoting cavitation. Ensure actuators on all valves, particularly two port

    valves, are capable of opening and closing the valves against maximum system operating pressures.

    Provide all valves, other than on terminal units such as fan coil units, with external position indicators. They

    will be complete with actuators, mounting brackets and all necessary auxiliary switches.

    Unless otherwise specified and in all circumstances where valve seat leakage is likely to cause nuisance,

    unnecessary bypassing or mixing losses, energy consumption, control instability, temperature conditions

    above or below the required control band or where circuit isolation is required, all control valves will be of thetight shut-off type, which may entail special seatings, particularly for double-seated valves and will not be of

    the rotating shoe or sliding disc type.

    Seats and stems will be removable and of stainless steel, except where alternative seating material is

    necessary to provide tight shut off.

    Valves less than 40 NB will be of screwed BSP bronze bodied construction with stainless steel trims.

    Valves of 50 NB and above will be of cast/modular iron or steel bodied construction as suitable for the

    pressure and temperature conditions having stainless steel trim and flanged to PN 16.

    The copper content of alloy valves will be as high as possible to avoid dezincification.

    All valves will be embossed with the manufacturer's logo, valve size and direction of flow.

    Provide valves with clutch or lifting mechanism to enable the valves controlled manually in the event of

    power source failure.

    Provide all butterfly valves with resilient settings.

    1.18.3 Sensors

    All sensors shall be selected and installed in accordance with the Building Controls Group document

    Control Sensor Installation.

    1.18.3.1 Temperature sensors

    Will be PT1000 with an accuracy of +/- 0.5oC. and a yearly drift of not more than 0.1K per year. Resistance

    temperature sensors will have a hysteresis value of less than 0.05%.

    Room air types

    Will have an accuracy of + 0.5K will be fixed in a representative location, be positioned approximately 1.5M

    above finished floor level and be at least 0.5m away from any part of the heating or cooling system where

    fitt d Will t t l lt d b it bl f ti B iti h St d d St d d d it

  • 8/11/2019 Draft BMS Spec

    41/168

    DRAFT BMS SPEC

    Will have an accuracy of + 0.5K will be provided with a pocket to allow withdrawal for servicing, andinspection, without the need for draining the system, be installed in the pocket using a silicon gel or similar

    non corrosive heat transfer medium. Will be positioned so that the active part of the element is wholly

    submerged in the liquid.

    The combined pocket an