DR Under FCM – UpdateMetering Configurations – SummaryRegistration Timeline and ExamplesFCM DR Asset Data Conversion Update
Lemuel Gonzalez, ManagerLindsay Perry, Associate AnalystResource Registration & Performance AuditingDRITWG | January 12, 2010
• FCM DR Metering Configurations - Summary
• Asset Registration Timelines
• FCM DR Asset Data Conversion Update
Agenda
2
DR Under FCM – Update | January 12, 2010 DRITWG |
© 2010 ISO New England
FCM DR Metering Configurations
3
DR Under FCM – Update | January 12, 2010 DRITWG |
© 2010 ISO New England
• Metering Configurations were discussed in more detail at the January 6, 2010 DRWG meeting. The presentation is available at:– http://www.iso-ne.com/committees/comm_wkgrps/mrkts_comm/
dr_wkgrp/mtrls/2010/jan62010/drwg_ms_01-06-2010.ppt
• Today’s presentation covers the over all object/data model overview and a summary of the metering configurations
Metering Configurations
DR Under FCM – Update | January 12, 2010 DRITWG |
© 2010 ISO New England4
Terms Used In This Presentation• CFE
– Communication Front End (ISO side, servers that support the communication with Market Participants, or their agents)
• Customer Baseline (CB)– An estimate of an Asset’s electricity consumption had it not responded to
a RTDR or RTEG event.
• DDE– Demand Designated Entity
• DG Output (DG)– The metered output of a Distributed Generator less any parasitic loads.
• Facility– A location where service is provided to an end-use metered customer.
• Facility Metered Load (FML)– Electricity consumed at a Facility that is purchased from the grid.
5
DR Under FCM – Update | January 12, 2010 DRITWG |
© 2010 ISO New England
Terms Used In This Presentation
DR Under FCM – Update | January 12, 2010 DRITWG |
© 2010 ISO New England6
• Hourly Reduction (HR)– The reduction in the Asset’s electricity consumption resulting from
responding to a RTDR or RTEG event, or in the case of passive assets the average demand reduction across the performance/event hours.
• Metering Configuration (MC)• RTDR / RTEG Asset
– One or more measures/facilities located at a single PNode, reporting data as a single set of values and assigned a unique Asset ID by the ISO
• RTU– Remote Terminal Unit (field devices owned by the Market Participants or
DDE that communicate with the CFE system servers)
• Total Facility Load (TFL)– Total Facility Load is the total electricity consumed at a facility inclusive of
that purchased from the grid and that produced on-site from a Distributed Generator. TFL = FML + DG
Demand Resources Hierarchy Overview
7
Facilities
Jim’s Laundry
Mary’s Widgets
Fred’s Salvage
ABC Supply
Measures
RTDR Measure 1
RTDR Measure 2
RTDR Measure 3
RTEG Measure 1
RTEG Measure 2
RTEG Measure 3
Assets
Asset 1
RTDR
Asset 5
RTEG
Demand Resources
DR A
RTDR
Asset 4
RTEG
Asset 3
RTEG
Asset 2 RTDR
DR BRTEG
DR Under FCM – Update | January 12, 2010 DRITWG |
© 2010 ISO New England
ISO Uses Reported Data As Follows:Ref No Metering Configuration Applicable
DR TypesParticipant Reports:
Hourly Reduction Logic CB Based On:
1 DG Output Directly Metered
RTDR, RTEG, OP, SP
DG & FML (if pushback possible) HR = DG No CB
2 Load Reduction - No DG at the Asset RTDR FML HR = CB - FML FML
3 DG Used to Reduce Load at the Asset RTEG FML HR = CB - FML FML
4Load Reduction - DG Used to Reduce Load at Another
On-Site AssetRTDR DG & FML HR = CB - TFL TFL
5DG Used to Reduce Load at the Asset - DG at Another
On-Site AssetRTEG DG & FML HR = CB - TFL TFL
6 Load Reduction Pursuant to M&V Plan
OP, SP monthly performance values
HR = avg MPV across performance hours No CB
Certain RTDRreduction reported
as if it were generation
HR = DG No CB
Metering Configuration - Summary
DR Under FCM – Update | January 12, 2010 DRITWG |
© 2010 ISO New England8
Asset Registration Timelines
9
DR Under FCM – Update | January 12, 2010 DRITWG |
© 2010 ISO New England
• Inform Lead Market Participants and DDEs of the proposed timelines
• As the timelines will display:
– The Lead Market Participants need time to submit the registrations
– The ISO needs time to review new registration and changes– The DDE needs time to accommodate changes to the
communication model each month to reflect registration changes
Purpose for discussing the timelines
DR Under FCM – Update | January 12, 2010 DRITWG |
© 2010 ISO New England10
Measure State Chart
11
DR Under FCM – Update | January 12, 2010 DRITWG |
© 2010 ISO New England
RECEIVEDPENDING
CUSTOMER ACTION
CANCELLED
RETIREDAPPROVED LPREVIEW IN PROGRESS
REJECTED
ISO
ISO
ISO
ISO
LP
ISO
Asset State Chart
12
DR Under FCM – Update | January 12, 2010 DRITWG |
© 2010 ISO New England
• All measures under an asset must be approved before an asset can be “Ready to Respond.”
Note: Meter Installed & Operational (MIO), and a CB built when needed, need to be satisfied prior to R2R.
RECEIVEDPENDING
CUSTOMER ACTION
CANCELLED
READY to RESPONDAPPROVED
REVIEW IN PROGRESS
REJECTED
RETIRED
ISO
ISO
ISO
ISO
LP
ISO
LPISOLP (MIO)
Asset Registration Timeline
• New Assets:– Must allow the ISO 7 full business days to review submittal, as is the
practice today (though in practice our turnaround is quicker)– Must be approved, and have a baseline built when needed, before
the data snapshot is taken to construct the communication model
• Baseline Data– Window for submitting data starts as early as five business days prior
to the registration submittal (CB needed by T-8, e.g., 8/24/2010)
8/31/2010 (Tue)8/1/2010 (Sun) 8/10/2010 (Tue): New Asset Submitted to CAMS
8/25/2010 (Wed) 0:00 (T-7): Final snapshot of Data Model Taken
8/15/2010 (Sun): Deadline to Submit New Assets for 9/1/2010, submittals beyond this date are not guaranteed to be ready for 9/1/2010
8/3/2010 (Tue) – 8/23/2010 (Mon): Window to submit baseline data with a requested operational date of 9/1/2010
13
DR Under FCM – Update | January 12, 2010 DRITWG |
© 2010 ISO New England
Registration Timeline Examples
8/31/2010 (Tue)8/1/2010 (Sun)
8/25/2010 (Wed) 0:00 (T-7): Final snapshot of Data Model Taken
8/9/2010 (Mon) – 8/13/2010 (Fri):
Current Baseline Data Submitted
8/14/2010 (Sat): New Asset
Submitted to CAMS
8/25/2010 (Wed) 0:00 (T-7): Final snapshot of Data Model Taken
8/9/2010 (Mon) – 8/13/2010 (Fri):
Historical Baseline Data Submitted
Preferred Timeline
“Last Minute” Timeline8/24/2010 (Mon): Asset Approved
By ISO
8/15/2010 (Sun): Deadline to Submit New Assets for 9/1/2010
14
DR Under FCM – Update | January 12, 2010 DRITWG |
© 2010 ISO New England
8/31/2010 (Tue)8/1/2010 (Sun)
8/9/2010 (Mon): New Asset Submitted to
CAMS
8/14/2010 0:00 (Sat): Baseline
Built
8/17/2010 (Tue): Asset Approved by ISO
8/15/2010 (Sun): Deadline to Submit New Assets for 9/1/2010
8/15/2010 (Sun): Baseline Built
Registration Timeline Examples (cont.)
8/23/2010 (Mon): New Asset
Submitted to CAMS
Late Timeline
• In this example, the ISO is given less than two business days to review the asset in order for it to be R2R by 9/1/2010.
• Asset’s ready to respond date will be postponed until 10/1/2010 since the asset was approved on 8/27/2010.
15
DR Under FCM – Update | January 12, 2010 DRITWG |
© 2010 ISO New England
8/25/2010 (Wed) 0:00 (T-7): Final Cut of Data Model Taken
8/16/2010 (Mon) – 8/20/2010 (Fri):
Historical Baseline Data Submitted
8/27/2010 (Tue): Asset Approved
By ISO8/31/2010 (Tue)8/1/2010 (Sun)
8/16/2010 (Mon): Deadline to Submit
New Assets for 9/1/2010
8/24/2010 (Tue): Baseline Built
Forward Capacity MarketDR Asset Data Conversion Update
16
DR Under FCM – Update | January 12, 2010 DRITWG |
© 2010 ISO New England
Administrative Reminder• All forms have been sent.
• Forms are due back to ISO Customer Support from EPs by January 31, 2010.
• Follow up questions regarding the form may be directed to ISO Customer Support.
• ISO Customer Support contact information is as follows:– [email protected]– 413-540-4220
• EPs unable to provide required information in a timely manner risk delaying conversion of their LRP assets for the start of the first Capacity Commitment Period on June 1, 2010.
DR Under FCM – Update | January 12, 2010 DRITWG |
© 2010 ISO New England17
Timeline Reminder (Continued)
Dec 9, 2010:Demand Asset data conversion form distributed
Current CAMS
CAMS under FCM
TBD: CAMS under FCM
deployed – Current CAMS may be used for registration for
Transition Period months
June 1, 2010: First FCM
Commitment Period begins – current CAMS
becomes “read-only”
Jan 31, 2010:Demand Asset
data conversion form due
A B C
DR Under FCM – Update | January 12, 2010 DRITWG |
© 2010 ISO New England18
19
Timeline (Continued)
Before form is returned to the ISO (A)
Between form returned and deployment
CAMS under FCM (B)
Once CAMS under FCM is deployed (C)
Make updates to existing LRP assets for FCM
Update XLS Form, and CAMS also if it applies to the Transition Period.
E-mail ISO Customer Support with the request (HEAT ticket). For extensive revisions, submit request to ISO for an updated XLS .Update CAMS if it also applies to the Transition Period.
• TP-only Assets: Current CAMS may be used.FCM –only Assets: Use CAMS under FCM.
• Both: May need to update both systems.
Register New Asset (incl. un-retiring) for Transition Period
Continue to use Current CAMS, plus fill out the revised Additional Information sheet and email to ISO Customer Support .Note: FCM related fields are only needed for LRP assets you want the ISO to cutover to FCM.
Current CAMS may be used for Transition Period only.
Register New FCM Assets
Continue to use Current CAMS, plus fill out the revised Additional Info. sheet and email ISO CS. Use CAMS under FCM.
Where to register new assets and edit asset data
DR Under FCM – Update | January 12, 2010 DRITWG |
© 2010 ISO New England
• MW Allowed to Be Pushed Back field on the “Passive Assets” tab of the form is missing. Please put this value in the Notes/Comments field.
• If an asset’s DR Type is “RTDR” and the Reduction Method is “Start Generation” the form gives you three options for the Metering Configuration field. The ONLY valid option for this combination is “DG Output Directly Metered.” Please disregard the other options.
• MCs with “DG” in their names still apply to RTEG assets. EGs are Distributed Generation.
Corrections and General Comments
DR Under FCM – Update | January 12, 2010 DRITWG |
© 2010 ISO New England20
• Please review the January 6, 2010 presentation if you are interested in more detail regarding commonly asked questions on the asset cutover effort. The presentation is available at:– http://www.iso-ne.com/committees/comm_wkgrps/mrkts_comm/
dr_wkgrp/mtrls/2010/jan62010/drwg_ms_01-06-2010.ppt
For more on commonly asked questions
DR Under FCM – Update | January 12, 2010 DRITWG |
© 2010 ISO New England21
22
Questions
DR Under FCM – Update | January 12, 2010 DRITWG |
© 2010 ISO New England
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31
August 2010For reference to use with the registration timelines
23