Transcript of Dr. Prem Reddy Health Sciences Building - Construction Update - October 2014
Future new entrance into existing science bldg, connecting the two bldgs. with covered walkway from the anatomy labs. Rebar Cages are for walkway columns
Entrance to exit foyer at anatomy labs & cadaver rooms. Rebar Cages shown are for columns at new covered walkway connecting two bldgs.
(Note width of door here is 4’-4”)
Future courtyard space. Shade structures will be erected.
Different view of Courtyard Space, looking toward new building. Shade structures will be erected.
Future covered walkway between existing bldg. and foyer to chemistry labs
North side of bldg., looking at doors to new electrical room, and beyond that the door to the exit foyer leading to science/chemistry labs. Covered walkway will connect the new bldg. to old bldg.
Interior shot looking at the exit door from foyer at chemistry/science labs to the new covered walkway connecting to existing bldg.
Conduit stub ups for panels – Located in main electrical room
Additional conduit stub ups for panels – Located in main electrical room
Looking into space for future Beds & Equip, Medical Supplies & utility roomsThis doorway is door #110 on plans
Taken from the medical supplies room, looking out at the beds & equipment space. Door 112C is straight ahead, and door 110 to the right
Plumbing wall for student restrooms
Also student restrooms, looking into space that will become the custodial, fire riser, and vestibule spaces. You can see the waste lines for sinks & a 4” wall cleanout. A sliver of door 102 can be seen to the left.
Conduit stub ups inside future electrical sub panel room. Just beyond, to the right, is the door from meeting room to exterior of bldg.
Mens & Womens Faculty Toilets
Another shot of the Mens & Womens Faculty Toilets: the in-wall plumbing.
This is the cadaver room (closest) and the cat storage room (beyond). These rooms both have floor drains and depressed slabs, and will get ceramic tile flooring. The cat storage room has build up concrete bases for cabinets to
sit on.
This is the anatomy / physiology lab. The round protrusions are for the duct that will run up into the center of each of the student work tables.
Looking at the exterior wall of Meeting room and adjacent Dean’s office. These windows will look out onto the courtyard area between the two buildings
This opening will become the sliding door entrance at south side of bldg., leading into the corridor to simulation center and anatomy labs
This space will be home to the Simulation center, with its SIM labs, observation rooms and control booths. Interior walls will be framed to create each room. The door seen to the left is door 137B
Also of the Simulation Center space, looking to the north. The opening in the CMU wall is the space shown as the study area, with hall/corridor beyond.
Plumbing for the Patient Toilet, located off the patient room SIM lab.
This is the main entrance hall, looking out toward where the revolving door entrance will be. To the right is the entrance area to the student restrooms.
In the main entry hall, this will be the home of two display cases, set back into an alcove space. These will be to the right, as a person enters through the revolving door.
Future home of the nursing faculty offices & copy room. Door seen straight ahead is the door to the maintenance storage room.
Also in the future faculty offices. Right ahead will be the space for rooms designated as 125 and 124 on plans, with exterior door 126B seen to the right.
To the left, where all the scaffolding is placed, is the location of new sliding entrance, door 127A
This is the future home of the new Nursing Fundamentals Lab. This space is adjacent to the faculty offices, and has double doors connecting it to the beds & equipment room
Chemistry Lab space. Chemical balance room to the far right corner, and then chemistry lab adjacent. Doorway seen to the right is the door for exit foyer
These are the stone columns that line corridor 127, between the science labs and the rotunda space. There will be glass running between the columns along this wall, that will look out onto the courtyard space.