Salient Features
Floor area = 190,000 sft Basement
Lower Ground Floor
Upper Ground Floor
First Floor
Second Floor
Third Floor
Basement Floor Plan Functions 149’-6”x189’-6”= 28,474 sft
Basement Parking for 35 cars + 70 motor cycles
Generator Electrical Room, Mechanical Room, Storage, Lifts 4 nos, Stairs 3 Nos,
Male supporting Female supporting
Security, Drive ways
Lower Ground Floor Functions 149’-6”x189’-6”= 27,163 sft
Lower Ground Floor
Pathology Lab, Blood Bank, ECG, CT Scan,
X-ray, Ultra Sound, Heart and Lung Lab,
Pharmacy, CSSD,
Laundry, Waitin,g Ramp
Upper Ground Floor Functions 149’-6”x189’-6”= 29,851 sft
Upper Ground floor
Consulting, Waiting, Lobby,
Entrance, Executive Check-up,
Emergency, Minor OT,
Emergency Theatres,
ENT, Surgery, Supplies
First Floor Functions 27,427 sft
First Floor
Male Female Surgical Wards, Paeds Ward,
CCU, ICU, Neo Natal, Male Orthopaedic,
X-ray, General Ward, Recovery Monitoring,
Pre Anesthesia, Labour Room
Ots, Anesthesia, Gynae
Second Floor Functions 27,887 sft
Second Floor
Private Rooms 16 Nos,
VIP Rooms 16 Nos,
Male Medical Ward,
Female Medical,
Ward, Isolation
Third Floor Functions 27,887 sft
Third Floor
Male Ward, Female Ward,
Beds Normal -23 Nos
Beds Upper- 6 Nos
Cost Up to Foundation Exc for Foundation 540,000 cft @ 3.50 = Rs 1,890,000 Excavation trenches 5,700 cft @ 4.00 = Rs 22,800 Filling with sand 40,000 cft@ 6.00 = Rs 240,000 Eartfill 10,000 cft @ 3.0 = Rs 30,000 Disposal earth outside 55,000 cft @ 2 = Rs 110,000 Laying earth within 480,000 cft @ 2 = Rs 960,000 Termite control 46,000 sft @ 1.5 = Rs 69,000 Lean concrete 1:4:8 13,000 cft @150 = Rs 1,950,000 RCC in foundation 75,000 cft @ 300 = Rs 22,500,000 Steel to upper gr floor 243,750 kg @ 125 = Rs 30,468,750 Total up to foundation
= Rs 58,240,550
Quantities Up to Foundation Cement = 13,885 bags x 530 = Rs 7,359,050
Sand = 35,200 cft x 6 = Rs 211,200
Aggregate = 70,400 cft x 35 = Rs 2,464,000
Steel = 243,750 kg x100= Rs24,375,000
Cost of Waterproofing in Foundation Waterproofing ret walls 12,500 sft @ 6= Rs 75,000
Waterproofing raft 28,000 sft @ 5 = Rs 140,000
Water stopper 1,000 Rft @ 15 = Rs 15,000
Brickwork in found 2,500 cft @ 100 = Rs 250,000
Total of Waterproofing in Foundatio = Rs 480,000
Quantities in Waterproofing Foundation
Membrane waterproofing at ret walls= 12,500 sft
Membrane waterproofing in raft = 28,000 sft
Water stopper = 1,000 Rft
Bricks = 35,000 Nos
Cost of Basement Slab, Lower Gr &
Upper Gr Fl Slab Grey Str RCC basement slab 75,000 cft @30 = Rs 22,500,000
lower gr & upper
gr fl slab
Steel basement 487,500 kg @ 125 = Rs 30,468,750
slab lower gr & upper
gr fl slab
Total up to upper ground floor = Rs 52,968,750
Quantities Up to Upper Gr Fl Slab Cement = 12,750 bags x 530 = Rs 6,757,500
Sand = 30,000 cft x 6 = Rs 180,000
Aggregate = 60,000 cft x 35 = Rs 2,100,000
Steel = 243,750 kg x 100= Rs24,375,000
First, Second and Third Floor Slabs RCC first floor 24,000 cft @ 300 = Rs 7,200,000
RCC 2nd floor 24,000 cft @ 300 = Rs 7,200,000
RCC 3rd floor 25,000 cft @ 300 = Rs 7,500,000
Steel 3 floors237,250 kg @ 150 = Rs 35,587,500
Grey str upto 3rd floor = 57,487,000