DPSA POA 2010/2011 Presentation to the Portfolio Committee on Public Service and Administration
description
Transcript of DPSA POA 2010/2011 Presentation to the Portfolio Committee on Public Service and Administration
DPSA POA 2010/2011
Presentation to the Portfolio Committee on Public Service
and Administration
Prof Richard M. Levin (DG: DPSA)
4 November 2009
2
Presentation outline
Background
POA for 2010/2011
Detailed Programme of Action (with costing and timeframes) for –
Anti-corruption
Thusong Service Centres
Community Development Workers
Gender mainstreaming and Disability
Concluding remarks
3
Background: planning cycle of government Strategic planning undertaken (June/July)
Submission of MTEF to National Treasury (August)
Preparation of Estimates of National Expenditure (Oct-Dec)
Operational planning (February/March)
Strategic plan tabled before debate on Budget (Mar-June)
Commencement of the financial year (April – March)
4
DPSA 2010/2011 Programme of Action
5
HRM&D (1)
Project Project Outputs/ Deliverables
Output Target/ End Date
Monitoring framework and tool finalised and implemented
1) Annual HRD implementation plans submitted
2) HRD performance report developed annually
Annually
HRD forums at provincial, national and sector levels
Quarterly meetings with all stakeholders and role players held to support coordination
December 2015
Policy on compulsory training programmes for HR practitioners
Policy on compulsory training programmes for HR practitioners developed and implemented
December 2011
6
HRM&D (2)
Project Project Outputs/ Deliverables
Output Target/ End Date
Develop strategic framework for youth development in the Public Service
Youth development strategic framework developed
December 2010
HR Connect implementation roll out
Model for HR connect as a Skills audit driven Process for the public service institutionalised
December 2010
Development of the guideline for institutional support programmes for
engagements
Guideline document on the coordination, facilitation and management of institutional support programmes
November 2010
7
MOC (1)
Project Project Outputs/ Deliverables Output Target/ End Date
Review of pension and medical provisioning in the public service
Implementation of a Revised Policy on Post Retirement Medical Assistance in the public service (Alignment of the PRMA in the Public Service)
December 2010
Implementation of the HR module of the IFMS
Creation of HR generic template
November 2010
Implementation of the HR module in the first lead site (DPSA)
June 2010
Implementation of the HR module in the 2nd lead site (FS DoE)
January 2011
8
MOC (2)
Project Project Outputs/ Deliverables
Output Target/ End Date
Strengthen social partnership for good governance
Public Sector Summit convened
Labour relations culture enhanced with identifiable features
July 2010
Monitoring and evaluation of the wage bill trends in the public service
The wage bill model developed in conjunction with the National Treasury
June 2010
Implementation of a remuneration policy framework of the SPS
Remuneration policy framework for the SPS developed, costed and adopted
2008-2011
9
MOC (3)
Project Project Outputs/ Deliverables
Output Target/ End Date
Design and implementation of the SPS change management programme
Change readiness report for institutions impacted by the SPS completedDraft change management strategy and implementation plan completed
July 2010
Development of a pilot urban mall at the Maponya Mall
Operational Urban Thusong Service Centre at the Maponya Mall
July 2010
10
I&TM (1)
Project Project Outputs/ Deliverables Output Target/ End Date
IT blueprint Architecture blue-print for IT in Government
Establish COBIT/ITIL Framework
July 2010
Information Security
Government Wide Information Security Governance Framework
Government Wide IT Security Blueprint and roadmap for Deployment
2009-2010
GITO Council Strengthen GITO Council & coherence of
IT
Better quality support to the GITO Council
Training & Capacity Building of CIO competence
Ongoing
11
I&TM (2)
Project Project Outputs/ Deliverables
Output Target/ End Date
E-government Prototype Prototype e-enablement of six pro-poor services:• Application for ID.• Child Birth registration• Foster care grant• Application for pension• Application for maintenance
• Notification of death
July 2010
Thusong Service Centre Connectivity
Connect Thusong Service Centres to a centralised ICT infrastructure
March 2011
12
SDI (1)
Project Project Outputs/ Deliverables Output Target/ End Date
Cascading of Batho Pele Change Management Engagement Programme (BPCMEP) across the three spheres
Cascading BPCMEP to National Departments
Cascading BPCMEP to
Provincial Departments
March 2011
Render support in the implementation of the War on Poverty Campaign (WOPC)
Establish an institutional arrangements framework for the implementation of the WOPC
Support implementation of the campaign and review the programme
2008-2014
Co-ordinate and facilitate Learning and Knowledge Management (LKM) platforms and products in the Public Service
Finalisation of LKM strategy December 2010
13
SDI (2)
Project Project Outputs/ Deliverables
Output Target/ End Date
Publication of Service Delivery Review Journal
Public service review journal published
Quarterly
Support to the DRC Census project
Biometric roll out to 9 provinces completed
December 2010
14
Governance (1)
Project Project Outputs/ Deliverables
Output Target/ End Date
2nd Minimum Anti-Corruption Capacity (MACC) Compliance Audit
Compliance Audit Report on the implementation of the MACC requirements
December 2009
Public Sector Anti-Corruption capacity building programme
Improved skills and orientation to fight corruption
December 2012
Phase II of the OECD Anti-Corruption Convention
Phase II evaluation
implemented and completed
(completion of questionnaire
and on-site visit)
Ongoing
15
Governance (2)
Project Project Outputs/ Deliverables Output Target/ End Date
Enforcement and Monitoring Task Team
Enforcement and monitoring of conflict of interest measures
March 2011
Business Anti-Corruption Training Programme
Development of training and awareness material
March 2011
Support to the DRC: Implementation of MoU
Hosting of the Anti-Corruption
Summit and experts' roundtable
to approve the Programme of
Action
Feb 2010
16
Specific focus on –
1. Anti-corruption
2. Thusong Centres
3. Community Development Workers
4. Gender mainstreaming and disability
17
Public Sector Anti-corruption:Programme Objectives
Enhance Integrity in the Public Sector
Effective anti-corruption monitoring and evaluation system
Promotion of national anti-corruption values and interests at regional and international levels
18
Anti-corruption 2010/2011 (1)Project Output Target/ End
Date
Implementation of the 2nd National Anti-corruption Programme (NAP)
March 2011
Implementation of the recommendations of the Anti-corruption M&E impact appraisal
March 2011
Compliance Audit Report on the implementation of the MACC requirements at national and provincial departments
December 2010
Rollout of Anti-Corruption Capacity Building Programme at national and provincial level
March 2011
Implementation of the Business Anti-corruption Training Programme
March 2011
Monitoring and enforcement of conflict of interest measures
March 2011
19
Anti-corruption 2010/2011 (2)Project Output Target/ End
Date
Anti-corruption communication, training and awareness programme implemented and monitored
March 2011
Development and implementation of the anti-corruption framework for the DRC
March 2011
Implementation and monitoring of the Public Service Integrity Management Framework
March 2011
Implementation and hosting of Anti-corruption Management Information System (CMIS)
March 2011
Participation in OCED Anti-corruption Convention Working Group for the implementation of the Anti-bribery Convention
Quarterly
20
Anti-corruption: medium-term budget
Financial year Budget
2010/11 R3,194,000
2011/12 R3,170,000
2012/13 R3,335,000
2121
Thusong Centres:Projects’ objectives
Objective of GCIS-led programme is to bring government services to the people where they live as part of the Government-wide Access Strategy
The DPSA projects are –
Install and maintain Internet connectivity at Thusong Centres
Install General Service Counters at Thusong Centres
Pilot a Thusong Centre in an urban mall
2222
ICT Connectivity
The RFQ for alternate connectivity solutions of the remaining sixty (62) Thusong Service Centres without terrestrial Telkom infrastructure is awaiting appointment of a service provider
The RFQ for LAN Cabling of the remaining fifty (50) centres is awaiting appointment of a service provider.
Letters issued to USASSA for funding, formatting and standardisation of existing tele-centre equipment (37 centres)
2323
ICT connectivity: Summary per Province
Province Site Count Data Lines Installed LAN Connected Building Problems Viable Telkom non-viable
Gauteng 34 11 10 8 26 15
Limpopo 15 5 10 1 14 9
Mpumalanga 16 4 6 1 15 11
Free State 9 7 8 1 8 1
North West 12 4 7 1 11 7
Northern Cape 4 4 4 0 4 0
Kwazulu 22 6 6 7 15 9
Western Cape 19 13 1 1 18 5
Eastern Cape 9 4 5 0 9 5
140 58 57 20 120 62
2424
ICT ConnectivityExpenditure 2009-11
Thusong Service Centre Cost Breakdown Monthly 2009-10 2010-11
Thusong SLA (2.8mbps Internet Link) 78,400.00 940,800.00 940,800.00Thusong Server Housing (43U Cabinet) 6,570.75 78,849.00 78,849.00Thusong Data Link Costs (Telkom) 44 Sites 203,649.74 2,443,796.88 2,443,796.88Thusong VPN Server Maintenance (Monthly) 12,948.67 155,384.04 155,384.04Remote Support and Service Management Service 97,176.00 0.00 1,166,112.00Annual License Maintenance (Monthly) 6,970.00 0.00 83,640.00Thusong Alternate Connectivity data lines (62 Sites) (Monthly) 454,656.00 5,455,872.00 5,455,872.00Thusong Alternate Connectivity (Once-off) 2,559,200.00 0.00Thusong Alternate Connectivity Installation (Once-off) 406,700.00 0.00Thusong Alternate Connectivity VAT (Once-off) 1,259,016.08 0.00Thusong Telephony (VOIP) Central Infrastructure (Once-off) 892,189.86Thusong Telephony (VOIP) Central Infrastructure (Annual Maintenance)
63,000.17
Thusong Telephony (VOIP) Central Infrastructure (Implementation Costs)
5,514,054.48
13,299,618.00
16,793,698.43
2525
General Service Counters
Only twenty-four (24) Thusong Service Centres have a General Service Counter installed, but not all of these General Service Counters are staffed, and not all General Service Counters have functional IT equipment
During the 2009-10 financial year the seventeen (17) General Service Counters, which are adequately staffed will be fitted with computer equipment
Due to space limitations only forty-one (41) General Service Counters can be deployed to current Thusong Service Centres. The forty-one counters will be installed in this financial year
2626
General Service Counters: Expenditure 2009-10
General Service Counters Cost Breakdown
General Service Counters (Drawings, manufacturing and fitment of 41 new GSC’s)
2,200,000.00
Equipment (17 existing GSC‘s) 300,000.00
Equipment (41 new GSC‘s) 700,000.00
TOTAL3,200,000.00
* No expenditure anticipated for 2010-11. All new Thusong Service Centres should be constructed with a General Service Counter inline with existing design and specifications.
2727
Notes on Thusong funding
Funding for the installation of the General Service Counters has been provided by the DPSA
Funding for the support staff for the General Service Counters is provided through a learnership funded by the Umsubomvu Youth Fund
Training and the development of an operations manual to support GSC staff has been funded by DPSA
Deployment of the core shared IT infrastructure for Thusong Centres has been provided by the DPSA
Key challenges remain issues of funding and the absence of a transversal fund to support the connectivity.
No provision has been made for the WAN and LAN infrastructure or the monthly operational costs, which include bandwidth requirements and internet connectivity. No funds have been set aside for IT support.
28
Thusong Centre in an urban mall Project is a flagship and Pilot for the Single Public Service in terms
of integrating services and achieving a joined- up government: showing the concept in action
Provides for integrated approach to services delivery in an urban under-serviced areas
Thusong in an Urban Mall will provide a one-stop Centre for interaction with government - cutting edge front office and back office
Thusong Centre under construction in Maponya Mall, Soweto
29
Maponya TSC: services
Department Service
City of Johannesburg Johannesburg Metro police
Home Affairs Full District Office service (including ID, passports, immigration services, marriages)
Labour Employment Services (career counseling) UIF.
SASSA Use General Service Counter to make referral appointments for SASSA clients
Gauteng Department of Transport Car and Driver license renewals (with eye test).
Gauteng Shared Service Centre Mini GSSC and Gauteng online- applications for vacancies
Gauteng Enterprise Propeller Provide financial and non-financial support to entrepreneurs
Department of Justice Exhibition space
National Youth Development Agency 2 specific services- micro loans and business services with voucher system
30
Maponya TSC:Action plan 2010/11 Blueprint for model to be compiled In-year review of the functioning and progress at the Thusong,
including customer satisfaction reviews Evaluation of the model at the end of the lease period in
September 2011 Discussions and identification of primary leaseholder post expiry of
current lease with Maponya Do it within a framework of pre-agreed conditions:
DPSA and GCIS to ensure that all space fully occupied for duration of extension of lease
Financial responsibilities to be outlined and agreed upon by all stakeholders
DPSA to continue to document and monitor developments at Centre (deal with problems in collaborative manner if not, elevate)
31
Maponya TSC:Budget 2010/11
Lease for 2010/11 : R1, 786 mil
Agreed part of the operational cost as per the legal agreement: R1,891 100.00 Includes salaries of the Centre Manager and General
Service Counter Staff, cleaning services, security services
Excludes utilities (water lights)
Customer Satisfaction survey : R1 mil
32
CDW Programme:Background
The programme was established in 2003 and currently there are 3146 community. development workers employed throughout the country at ward level
The DPSA and COGTA are jointly responsible for the coordination of the programme
DPSA is responsible for the overall coordination of the programme whilst COGTA is responsible for implementation of the programme
33
CDW Programme:programme objectives
Improving service delivery and accessibility
Improving intergovernmental coordination
Improving interaction between government and community
Improving participatory democracy
34
CDW POA 2010/2011
Project End Date
Development and implementation of CDW Programme Policy Framework
March 2012
Finalisation and implementation of CDW Programme Master Plans
March 2012
Training and capacity building for the CDW Programme
Ongoing
Develop norms and standards for the CDW Programme
March 2012
35
CDW Programme:Budget breakdown per province (2009)
36
CDW programme: medium-term budget
Financial year Budget
2010/11 R3,615,000
2011/12 R3,601,000
2012/13 R3,695,000
37
Gender Mainstreaming and DisabilityProgramme Objectives
Gender Mainstreaming in the Public Service: Ensure a transformed, non-discriminatory and fully inclusive Public
Service, which reflects the Constitutional values of non-sexism and non-racialism
Disability in the Public Service: Advance an effective enabling environment within the Public Service
through the adoption of progressive policies, establishment of relevant institutional mechanisms and development of key operational processes to ensure a transformed, non-discriminatory and fully inclusive Public Service.
38
Gender MainstreamingProjects and Activities for 2010-2011Projects ActivitiesMonitoring the implementation of Gender Equality Strategic Framework
Organisational readiness assessment on the implementation of the strategy.Gender Audits based on the HODs 8 Principles Action PlanCapacity development for implementers of the Gender Equality Strategic FrameworkProvide Quarterly reports
Implementation of the Public Service Women Management Week
And Institutional Change
Virtual launch of the Women Management interactions with departments during the virtual lunch
Engaging Gender Focal Points on gender mainstreaming strategies and gender sensitivity programmes collaboratively with the Ministry for Women, Children and Persons with Disabilities
39
Disability (1)Projects and Activities for 2010-2011Projects ActivitiesDevelopment of Policy on Reasonable accommodation and assistive devices in the Public Service
Consultations on the Policy on reasonable accommodation and assistive devices in the Public ServiceReview of the Handbook on Reasonable Accommodation for people with disabilities in the Public Service. Consultations with Ministry for Women, Children, and Persons with Disabilities.
Monitoring the implementation of JobACCESS Strategic Framework
Organisational readiness assessment on the implementation of the strategyConduct disability AuditsCapacity development for implementers of the JobACCESS Strategy. Provide Quarterly reports
40
Disability (2)Projects and Activities for 2010-2011Projects ActivitiesEstablishment of the Public Service Disability Forum
Consultations with Ministry for Women, Children, and Persons with Disabilities
Consultations with departments on the terms of reference regarding establishment of the forum
Quarterly meetings of the forum
Disability awareness programmes as well as
Establishment of working relationships with Disabled People's Organisations
Engaging Disability Focal Points on awareness raising strategies
Engagements with various Disabled People’s Organisations in consultations with Ministry for Women, Children, and Persons with Disabilities
Establishment of a database of people with disabilities
41
Diversity Management: medium-term budget
Financial year Budget
2010/11 R1,726,000
2011/12 R1,120,000
2012/13 R1,075,000
42
Concluding remarks
The Department is prioritising the programmes identified by the Portfolio Committee (Anti-corruption, Thusong Centres, CDW programme and Gender and Disability programmes)
A clear programme of action has been determined for these programmes with budgets and timeframes
The ENE process is currently underway
43
Siyabonga