Downtown Core – Phase 1B Streetscape Alternatives City ... · Presentation Team Nathan Stewart...
Transcript of Downtown Core – Phase 1B Streetscape Alternatives City ... · Presentation Team Nathan Stewart...
Downtown Core – Phase 1B Streetscape AlternativesCity Council Workshop – June 14, 2018
McCall, Idaho
Presentation TeamNathan Stewart – City of McCall City Public Works Director
Kurt Wolf – City of McCall Parks and Recreation Director
Michelle Groenevelt – City of McCall Community Development Director
Heidi Carter – Horrocks Engineers Consultant Project Manager
Karie Davidson – Horrocks Engineers Design Engineer
Greg Baer – Baer Design Group Landscape Architect
2013
May – October - Three Community Workshops for McCall Downtown Master Plan
December 19th -Adoption of McCall Downtown Master Plan
2015
November 3rd - Streets L.O.T. Passed
July - Initial Cost Estimate for Improvements
2016
May – November -Feasibility Study and Refined Estimates
November 18th -Council Briefing/Workshop
December 19th–23rd
Informational mailer sent out
2017
January 4th - Open House with Property/Business Owners and Public
March 24th - Final Council Meeting to summarize open house and Feasibility Report
June 9th – Submit final Feasibility Report
June 9th – Preliminary Design Task Order
July 6th – Preliminary Design kickoff
August 25th – Council briefing for aesthetic alternatives
August 30th – Public open house for aesthetic alternatives
December 2nd – Adoption of the TMP
December 8th – Submit preliminary/conceptual design of the Downtown Core
2018January – 2nd & Lenora Final Design Task Order
January 11th – Adoption of Comp. Plan
January 25th – Council briefing/workshop
January – Informational mailer sent out
February – Property/Business owner outreach
March – Property/Business owner follow up
March 23rd – Council briefing/workshop
May 24 – 2nd & Lenora Phase 1A project awarded
June 14 – Streetscape Alternatives Workshop
July - September – 2nd & Lenora Phase 1A construction
Priorities for Alternatives
◦ Providing adequate soil volume for street trees• Promotes growth and long-term success
◦ Incorporating pavers in sidewalks• Provides aesthetics and easier maintenance
• Higher priority on 2nd Street
◦ Utilizing unique lighting • Will define the theme for the Downtown Core
• Especially on 2nd Street
Original Concept Reductions◦ Elimination of concrete intersections – cost savings of $140,406
◦ Number of lights – cost savings of $26,700
◦ Number of street trees – cost savings of $70,000
◦ Net budget reduction of $237,106 to be reallocated
Hardscape Alternatives
Hardscape Alternative 1 – Low Cost
◦ Replaces concrete with pavers in the furnishing zone on 2nd St
◦ Pedestrian zone on 2nd St would remain concrete
◦ Secondary streets would have complete concrete sidewalks
◦ Overall cost is $69,831 less than original estimate
Hardscape Alternative 2 – Medium Cost
◦ Complete paver sidewalks on 2nd
St
◦ Secondary streets would have complete concrete sidewalks
◦ Cost is $109,840 more than original estimate
Hardscape Alternative 3 – High Cost◦ Complete paver sidewalks on 2nd St
◦ Replaces concrete with pavers in the furnishing zone on the secondary streets
◦ The pedestrian zones on secondary streets would remain concrete
◦ Cost is $275,084 more than original estimate
Pavers in Sidewalks
Pros◦ Aesthetically unique◦ City Parks and Recreation can
do any maintenance◦ Have better resistance to
winter climate and deicing methods
◦ Double the lifespan of concrete
Cons◦ Higher initial installation cost◦ Can have issues at material
differentials
Landscape AlternativesAlternative Use of Silva Cells
Silva Cells
A Silva Cell is a subsurface scaffold-like bridge that suspends the sidewalk over a tree and eliminates the need for heavily compacted subsurface material under the sidewalk. The Silva Cell is then
filled with un-compacted soil that is
ideal for root growth of trees, and also
reduces heaving and cracking of
sidewalk surfaces from tree roots.
Silva CellsPros◦ Encourages mature growth of
street trees◦ Protects the sidewalk surface
from root growth◦ Creates a potential for on-site
stormwater management◦ Very little to no maintenance
Cons◦ High initial installation cost
Silva Cells
Alternative A – Low Cost
◦ 12 Silva Cells concentrated at 2nd/Lenora 2nd/Park intersections
◦ Cost is $235,923 over original estimate
Alternative B – Medium Cost
◦ 12 Silva Cells concentrated at 2nd/Lenora 2nd/Park intersections
◦ 12 additional Silva Cells installed at select locations throughout the project area
◦ Cost is $535,923 over original estimate
Alternative C – High Cost
◦ 12 Silva Cells concentrated at 2nd/Lenora 2nd/Park intersections
◦ 24 additional Silva Cells installed at select locations throughout the project area
◦ Cost is $835,923 over original estimate
Illumination – Statement Lights◦ On 2nd Street only, highlighting it as an iconic corridor
Illumination – Standard Lights◦ On Lenora Street, Park
Street, and 1st Street
◦ Seen throughout the city of McCall
Illumination – Intersection Lights◦ 7 Installed at the main intersections in the downtown core
Future Project Add-ons◦ Benches
◦ Trash receptacles
◦ Bike racks
◦ Moveable planters
◦ Various art components
Alternative Matrix
Available Additional Funds◦ Use of Franchise fees
◦ $410,086 reallocated for underground electrical system
◦ Community Development Block Grant
◦ $541,625 for street lights
◦ Additional Streets LOT funds
◦ Revenues have exceeded budgetary expectations (approx. $500,000)
Staff Recommendation
Next StepsCouncil Workshop on Streetscapes June 14, 2018
Phase 1B Design May - November, 2018
Begin Phase 1A Construction July – September, 2018
Council Workshop on Phase 1B August 24,2018
Phase 1B Bidding/Award December, 2018
Phase 1B Construction Spring/Summer, 2019
Questions or Comments?