Download the SPS project book

110
SPS SPS: Sandwich Plate System The first new heavy engineering material in 150 years inte!ligen_t � eng1neenng

Transcript of Download the SPS project book

Page 1: Download the SPS project book

SPS

SPS: Sandwich Plate System

The first new heavy engineering material in 150 years

111!11 inte!ligen_t � eng1neenng

Page 2: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

CONTENTS

RECENT PROJECTS

1. Stadia2. Buildings3. Bridges4. Maritime5. Offshore6. Special Applications

OTHER INFORMATION

7. Production8. Company Profile

Page 3: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Live Nation SPS Stadia

November 2016

The Atlanta Braves baseball team and Live Nation teamed up to build an iconic entertainment venue adjacent to SunTrust Park, home of the Braves.

SPS terraces were selected for the upper seating area to minimize columns on the lower level, which would have obstructed views of the stage. The slender profile of the SPS terraces enable vertical space/head height to be optimised.

The venue will host 40 music and comedy shows annually helping to drive traffic to the site on non-game days, with an audience capacity of 4,000. It will also play host to special events, the partners said.

Installation of the SPS terraces took place in October/November 2016.

Owner: Live Nation Entertainment GroupArchitects: Wakefield Beasley & AssociatesEngineers: Uzun+Case, LLCGeneral Contractor: Reeves+Young

Page 4: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Liverpool Football Club SPS Stadia

August 2016

Main Contractors: Carillion

Architects: KSS

Engineers: Jacobs

Owners: Liverpool LFC

Steel Contractors: Severfield

Liverpool Football Club’s main stand expansion project was successfully completed in time for the start of the premier league on 13 August. 8,500 seats were added - taking the overall capacity to 54,000. Seven rows of SPS terraces (886m² – 1,500 seats) were incorporated into the design, solving some load and height issues faced by the expansion projects. The seven SPS rows came in 139 sections including six vomitory landings.

Page 5: Download the SPS project book

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

USTA Flushing Meadow - Grandstand SPS Stadia July 2016

Owner: US Tennis Association

Architect: Rossetti Engineer:

WSP-NY Office

Construction Manager: Hunt Construction

The 2016 US Open marked the opening of USTA’s new grandstand at Flushing Meadow, New York. In partnership with Walters Group, IE won the contract from HUNT Construction Group to supply and install SPS terraces for the 5,800 seat grandstand. This was the second SPS stadia project for USTA.

“The SPS stadia system is one of the most accurate stadia systems we have worked with.

· The design build process helped coordinate the accuracy of structural steel andeliminated unforeseen conditions.

· The engineers at SPS helped to coordinate and resolve complex expansion joint issueswhich were a huge concern for our unstable site.

· The SPS system helped to complete a complex, 16 sided stadium in an extremely limitedamount of time.

· As designers of sport venues, we especially appreciate the look of the finished systemfrom below and above. The finish on the system is beautiful.”

DOUGLAS WOODWARD RA, LEED AP, ASSOCIATE, SENIOR DESIGNER, ROSSETTI

Page 6: Download the SPS project book

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Mississippi State University Softball Stadium SPS Stadia July 2016

Location: Starkville Mississippi

Owner: Mississippi State University

Architect: Wier Boerner Allin

Engineer: Structural Engineering Associates LLC

Together with partner Southern Bleacher Co of Graham Texas, IE has delivered the new Mississippi State University softball stadium. 575m² of SPS terraces were installed. The project was finished in summer 2016 and is now in-service.

The use of SPS terraces allowed building to take place under the structure at the same as

work took place above and so the project’s tight schedule could be adhered to.

Page 7: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

London Olympic Stadium West Stand Mid Tier SPS Stadia

October 2015

Owner: Greater London Authority

Architect: Populous

Structural Engineer Buro Happold

Contractor: Balfour Beatty

As part of the London 2012 legacy, the iconic Olympic Stadium has been upgraded to a UEFA Category 4 Football Stadium – the highest category in the world. The lightweight SPS system was selected for the cantilevered terracing in the first class hospitality suite areas. The SPS components were successfully installed by the end of April 2015 in time for the venue to host a number of high profile events, including five Rugby World Cup matches in September and October 2015.

Page 8: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Studio City, Macau SPS Stadia and SPS Buildings

September 2015

Melco Crown Entertainment have completed a cinematically-themed entertainment, retail and gaming resort in Macau, China. SPS was used to construct the terracing, wall and stage floor components of the 3,000 seat cinema and theatre leisure facility. It was also used for a number of smaller boutique theatre units. The venue opened in September 2015.

Owner: Melco Crown Entertainment

Architect: HKS

Structural Engineer Buro Happold

Contractor: Paul Y – Yau Lee Joint Venture

Page 9: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

San José Earthquakes Stadium SPS Stadia

February 2015

Owner: Earthquakes Soccer LLC

Architect: 360 Architecture

Structural Engineer Magnusson Klemencic Associates

Contractor: Devcon Construction

Time lapsed video of the construction of the stadium is available on the following link:

https://www.youtube.com/watch?v=P-PaGOQzN2Q This demonstrates how quickly the SPS Terraces can be installed. Pay careful attention around the 70-second marker or you’ll miss it!

“We congratulate you and your team on the successful installation of your SPS Terracing … [and] … thank the SPS team for all the efforts to make the Avaya stadium one of the best in North America. We hope that there will be future opportunities to work together in new stadium or arena.”

Dave Kaval President, San Jose Earthquakes Avaya Stadium

SPS and Steel Systems Engineering, Inc. win 2014 Tekla award in BIM category.

“For coordination of fabricator and general contractor requirements, providing accurate, latest drawings and minimising workload.”

Page 10: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Philippine Arena SPS Stadia July 2014

Owner: New Era University

Architect: HaeAhn

Contractor: Hanwha Engineering & Construction Co (HENC)

The Philippine Arena is the world’s largest mixed-use indoor theatre. SPS Terraces account for approximately 40,000 of the 55,000 seats. The use of SPS enabled the terraces to be installed after the roof had been completed. This key benefit offered programme flexibility and cost effectiveness which could not be achieved by any other method or material.

Page 11: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Mock-up for Moveable Stands SPS Stadia March 2014

The lightweight (20% of conventional concrete) and the very solid feel of SPS terraces make them ideal for use in stadia which require moveable stands. The erection of the entire bay shown was completed in just over three hours, with a three man crew and lightweight crane.

Page 12: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

National Gymnastics Arena, Baku, Azerbaijan SPS Stadia July 2013

Owner: Pasha Insaat

Architect: Broadway Malyan

Main Contractor: Mace International Ltd

“The SPS units were so light and easy to position. We simply followed the keyplan and erected it just like steel - in fact easier.”

Umut Özdemir Project Management Chief

Sinerji (Erector)

Page 13: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Aquatics Centre - London 2012 Olympics SPS Stadia

Architect: Zaha Hadid Engineers: Arup Contractor: Balfour Beatty

Conversion - May 2013

Construction - January 2011

Completed - June 2012

The two temporary wing-like seating stands containing SPS Terraces were removed during the building’s conversion to a public swimming pool, in-line with the Olympic organisers’ goal of creating a sporting legacy for London.

The SPS Terraces have been sold on for re-use in a new venue.

Page 14: Download the SPS project book
Page 15: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

USTA Flushing Meadow – Court 17 SPS Stadia

January 2012

Owner: US Tennis Association

Architect: Rossetti

Construction Manager: Anchor Contracting

Design Build Erector: Southern Bleacher Company

Page 16: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

The O² Dublin SPS Stadia May 2008

“We designed the arena bowl with SPS terraces in mind; nothing else could have delivered the solution we wanted. I am delighted with the quality of finish we have achieved using SPS Terraces –they are the future.”Damon Lavelle, Architect, HOK Sport

SPS Terraces for The O2 Dublin enabled the delivery of a lightweight, long span, cantilevered bowl, fewer supporting columns, fast, simple installation.

The SPS Terraces used in this new arena help to bring more of the audience close to the stage, maximising the venue’s capacity and versatility.

Page 17: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

The LG Arena, Birmingham SPS Stadia

August 2009

Construct Stadia used SPS terraces to create the 8,000 permanent seats at the LG Arena. SPS terraces require fewer supporting columns than aluminium based stands, making it possible to create more space for concessions and services below the new stands. The terraces were installed in six weeks.

The permanent terracing and seating was ordered, delivered and installed in 12 weeks. The SPS Terraces were delivered to site pre-assembled in banks of two or three terraces, pre-drilled for fitting the seats and with non-slip coatings already applied.

Project type: Multi-purpose indoor arena Area: 4,200m sqLocation: Birmingham, UK Owner: NEC Group Architect: DLA Contractors: Ibex - Construct Stadia

“Using SPS Terraces helped to ensure that our new arena was ready for the start of our season, the Horse of the Year show and has created more space for concessions and services under the new stands.” Phil Mead, Managing Director of Arenas at The NEC Group

Page 18: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Ascot Racecourse Terrace Re-profiling SPS Stadia June 2007

SPS Terraces were first used in 2007 to re-profile the grandstand viewing area at Ascot Racecourse through increasing the rake and elevation of the terraces. 3,250m² of SPS Terraces were manufactured and installed.Weight, speed of installation and enhanced architectural finish were key factors in the selection of SPS.

Page 19: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

CONTENTS

RECENT PROJECTS

1. Stadia2. Buildings3. Bridges4. Maritime5. Offshore6. Special Applications

7. Production8. Company Profile

OTHER INFORMATION

Page 20: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Principle Place Pavilion, London SPS Buildings

November 2016

• Developer - Brookfield• Architects - Fosters and Partners• Engineering Consultants - WSP• Steel Fabricators & Erectors - Severfield Steel

• 9 SP S panels installed over 1 h 15 min over the Network Rail

• SPS allowed an additional floor which couldn't be achieved using conventional materials

• Minimal disruption to Network Rail line and local traffic

• Immedi ate full structural capacity to be used as a working platform as well as storage space

The Team

Page 21: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

New Supreme Group Headquarters Mezzanine Floor SPS Buildings

April 2016

Supreme Group have incorporated SPS mezzanine flooring into their new Headquarters currently under construction in Edmonton, Alberta. Using the strong, prefabricated and lightweight SPS floor system, the new 155m² SPS area is suspended from the ceiling above. The photographs show a view of the underside of the SPS floor (with the last remaining temporary acro-props in place).

A spiral staircase provides access to the SPS floor, highlighting its architectural versatility. The SPS floor panels are exposed on both top and bottom allowing visitors above and below to observe the high degree of panel flatness, as well as experience the impressive vibration and acoustic damping properties of this 27mm thin floor.

Page 22: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Cape Canaveral SPS Buildings December 2015

United Launch Alliance, America’s Ride to Space, has chosen SPS for the structural flooring panels for the top three levels of the new Crew Access Tower at Space Launch Complex 41 at Cape Canaveral Air Force Station.

The SPS product offers an ultra slim deck at 1¼” (3.18cm) thick that is structurally composite with the steel framing of the tower; the panels also offer sound dampening and assist in vibration reduction. SPS is a light weight alternative to other typical structural decking options weighing just 20 psf, with an expected 75 year service life.

Manufactured by Intelligent Engineering, the SPS panels offer a level of durability and protection not achievable with traditional materials. SPS panels have been tested against cellulosic, hydrocarbon and jet fires. They have an A60, H120 and J60 fire rating and offer protection against extreme oil and gas fires. SPS absorbs blast energy and preserves structural integrity.

Page 23: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Tannery Park, Oakville, Ontario SPS Buildings January 2016

195m² SPS panels have been installed at the Tannery Park Observation platform in Oakville, Ontario. The platform is a state-of-the-art outdoor pedestrian walkway that will surround a towering sculpture on the shores of Lake Ontario.

The walkway is the crown jewel in the multi-million dollar redevelopment of the park. SPS panels were chosen due to their sleek profile, light weight and long life span. The walkway will give visitors and ideal vantage point to view the crashing waves and idyllic sunsets.

Client: City of Oakville

Architect: MBTW

Contractor: Lomco

Construction Erector: Iron Bridge

Page 24: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

58 Victoria Embankment SPS Buildings October 2015

The use of SPS Floor panels at 58 Victoria Embankment shows diversification in usage as they move into the multi-storey arena. The panels were used on four of the seven floors, including the roof.

SPS overcame restricted head height issues faced when reconfiguring the interior floor layout, which could not be resolved using conventional materials.

Contractor: Kier

Consultant: Waterman Plc

Architect: TP Bennett

Developer: Kier Developments

Steel Erector: Bourne Steel

The following link will take you to a video showing the installation of SPS panels at 58 Embankment. As the panels are lifted, you will notice large light-coloured areas on the underside. This is factory applied intumescent paint.

http://bit.ly/2dkAju4

Page 25: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Bankside Gym SPS Buildings

June 2015

Located in one of London’s most vibrant cultural destinations, Bankside Health Club was renovated to expand its studio offering. SPS panels were supplied for the roof of the gym. The thin profile of the panels made them ideal for this modern structure. Delivered to site, with coatings applied, the eight roof panels were easily craned into position.

Owner: Native Land

Architect: Rogers Stirk Harbour & Partners

Structural Engineer: Waterman Group

Main Contractor: Carillon

IE Client: Watson Steel

Page 26: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Birmingham New Street Station SPS Buildings

Phase I - May 2012, Phase II – February 2015

Phase I - Completed May 2012

Phase II – Completed February 2015

SPS panels were installed on the north access ramp located on the concourse level as part of a two phase redevelopment of the station. SPS provided a solution that was light weight and easy to handle and install given there was no access from below.

Owner: Network Rail

Engineer: Atkins

Contractor: Mace

Steel Erector: Severfield

Page 27: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Daytona Hospitality Suite Walkway SPS Buildings

September 2014

SPS is contributing to the Daytona Speedway’s enhanced spectator experience by providing improved access to the grandstand and hospitality suites. SPS was selected as it fulfilled the requirement of ‘lightweight decking’ to minimise load on the existing support structure.

Owner: Daytona International Speedway

Architect: Rossetti

Engineer: Walter P Moore

Contractor: Barton Malow

Steel Erector: SteelFab

Page 28: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Owner: Intel Corporation Contractor: Hoffman Construction

· 53,000 SPS popout panels cover access ports on raised floor of chip manufacturing plant

· Weight reduction from 95lb to 28lb, allowing one man to remove and replace panels

· Able to carry the point load of fully laden forklift truck without deflection

· SPS popout panels awarded “best known method” status within Intel

1. Concrete form2. Centre beam3. Unistrut safety cage4. SPS Popout Panel

SPS Popout PanelsSPS BuildingsNovember 2013

Page 29: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

University of Alberta - Innovation Centre for Engineering SPS Buildings

March 2013

Owner: University of Alberta

Architect/Engineer: Dialog

Contractor: EllisDon Construction

Steel Fabricator/Erector: Supreme Group

SPS panels provided many advantages on this project

1) Installation was very easy and took afraction of the time required for concrete

2) Eliminated winter heating requirements,risk of freezing damage to finishedsurfaces and waste materials

3) Thinner panels gave more headroom(40mm vs.150mm for concrete)

I would highly recommend SPS and Intelligent Engineering.

Robert S Holmes, Senior Superintendent, University of Alberta ICE Project, EllisDon

Page 30: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

SPS Modular Construction - Volumetric London Metropolitan Police Custody Centres (Brixton, Kingston, Wood Green, Walworth)

October 2012

SPS delivered as a ‘Modular System’

Lightweight SPS Cells lifted directly into position

Clean architectural finishes

Owner: Metropolitan Police

Architect: Raymond Smith Partners

Main Contractor: Wates Construction

SPS delivered as a ‘Flat Panel System’

Lightweight SPS blast panels quickly aligned and installed SPS Cell roof forms load

bearing floor above

SPS Modular Construction - Flat Panel London Metropolitan Police Custody Centres

(Croydon) August 2011

Page 31: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

nnne Retail Store Mock Up (Pre-completion), California, USA SPS Buildings

September 2012

Owner: --------------------on

Architect: Foster & Partners

Construction Manager: DPR/Skanska

Steel Fabricator/Erector: Schuff Steel

· SPS floor plates used ina large two storey mock-up of a new design for------’s Asia retail stores

· Lightweight SPS panelsused to create 45ftcantilever design with athin leading edge

· 18 SPS floor plateserected in less than halfa day

Page 32: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Carnegie Hall - New York SPS Buildings February 2011

Shrink wrapped pallet of 14 SPS Floor panels (630 sq.ft.)

Restricted access by exterior hoist

Architect: iu + bibliowicz

Structural Engineers: Robert Silman Associates

Construction Manager: Tishman Construction

Steel Erector Fabricator: Metropolitan Walters

Lightweight, easily handled panels facilitate installation in constrained site

Page 33: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

London Gatwick Airport - North Terminal Interchange Extension SPS Buildings

April 2011

Architect: Capita Symonds

Engineers: WSP Group

Erector: Fisher

Page 34: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Weston-super-Mare Pier, UK SPS Buildings October 2010

Architect: Angus Meak Contractor: John Sisk & Sons SPS floor plates were key to meeting the challenges of rebuilding on an old and damaged structure with limitations on weight, restricted access and a demanding schedule. Intelligent Engineering has gone the extra mile in supporting us from design to installation to ensure the success of the project.” A

ndy

McGoldrick, Project Director, John Sisk & Sons Ltd

Page 35: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Data & Calculations concrete SPS SPS extra floor

total gross area (sqm) 118,450 118,450 120,918gross area per floor (sqm) 2,468 2,468 2,468

total floors 48 48 49

total net lettable area (sqm) 76,650 77,183 78,975average NLA per floor (sqm) 1,597 1,608 1,612increase in NLA 1% 3%

floor height (mm) 4,000 3,900 3,900building height above ground (m) 176 172 176construction duration (weeks) 145 132 133

Summary ($m) concrete SPS SPS extra floor

foundation, shell and core 89 83 84floor 17 38 39cladding 98 96 98prelims 72 66 66other 137 137 140sub-total - build cost 413 419 427change 6 15

earlier completion 19 17extra area per floor 8 8extra floor 28sub-total - benefits 27 54

Total Benefit to Owner 20 39

SPS shear walls can also be used to replace concrete core eliminating concrete above ground level, further reducing construction duration and increasing net lettable area,

and increasing total benefit to owner by an additional $20m

SPS Buildings Example of Economic Benefits

Generic Tall Building Example Location: London, UK

Rental Rate ($/sqm/year): 960 Annual Rental Yield: 6.2%

Page 36: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

CONTENTS

RECENT PROJECTS

OTHER INFORMATION

1. Stadia2. Buildings3. Bridges4. Maritime5. Offshore6. Special Applications

7. Production8. Company Profile

Page 37: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Water Street Bridge SPS Bridges

November 2016

Owner: Town of St Mary’s Engineer: BM Ross and Associates Contractor: Maclean Taylor

This was the rehabilitation of an historic structure. A pratt through truss bridge, built in 1890, the Water Street Bridge, St Mary’s needed a new deck and retain all of its original features

The beams, stringers, deck and steel curb were all replaced. The SPS deck arrived on the back of just one truck. It took just two days to install the new SPS bridge deck. The need to minimise the dead load meant that a concrete deck was not an option and lightweight SPS was a suitable solution.

Page 38: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Grand Duchess Charlotte Bridge (Pont Rouge) SPS Bridges October 2016

SPS Bridge Panels and SPS Overlay SPS Bridge Panels and SPS Overlay

Work to widen and strengthen the Grand Duchess Charlotte Bridge in Luxemburg is almost at an end. The final phase of repair to strengthen the four 355m long vehicle lanes (4,874m²) was completed at the end of the year. The strengthening work has been carried out in three stages with IE overseeing the elastomer injections.

SPS panels (2,272m²), manufactured by IE’s German partner, SEH Engineering GmbH, now form the new pedestrian and cycle lanes on either side of the bridge. The bridge has remained open throughout the upgrade.

Page 39: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Pulaski Skyway Bridge Temporary SPS Expansion Joint Cover Plates

March 2015

The Pulaski Skyway Bridge is a four-lane bridge in north-east New Jersey State providing access to Manhattan from Newark. A rehabilitation programme for the bridge structure, required to meet the current safety standards and demands, is on-going. During construction, the existing expansions joints at 10 different locations were removed. Temporary SPS expansion joint cover plates span over these until the permanent expansion joints are installed.

Owner: New Jersey DOT

Engineer: Hardesty & Hanover

Contractor: CCA Civil Inc.

Page 40: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Mettlach Bridge SPS Bridge Panels

January 2015

·

·

Old concrete deck being removed

New SPS deck being installed

· Renovation of Mettlach Bridge in Germanycarried out by Eiffel DeutschlandStahltechnologie (EDS) using prefabricated SPSpanels to replace existing concrete deck

· Use of SPS reduced deck weight by 300 tonnesallowing load restrictions to be lifted. Workscompleted within four months

· Project received prestigious Ulrich FinsterwalderEngineering Award in January 2015

Page 41: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Ovingham Bridge SPS Bridges

May 2014

Owners:

Northumberland County Council Sheffield City Council

Structural Engineers:

Northumberland County Council Intelligent Engineering/Amery

Page 42: Download the SPS project book

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

First Thorcabridge, Hillegom, Netherlands SPS Bridges

December 2012

Page 43: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Wark Tyne Bridge SPS Bridges

September 2011

Owner: Northumberland County Council

Structural Engineers: Northumberland County Council Intelligent Engineering

Construction Manager: Carillion

Fabricator/Steel Erector: DMJ Engineering

Page 44: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Dawson Bridge, Edmonton, Canada SPS Bridges

July 2010

The SPS Bridge Deck allowed the entire project to be completed months faster and millions of dollars less expensively than a traditional concrete deck.

March 2011 issue of the official AISC publication, Modern Steel Construction “Three-Part Perfection, Jeff DiBattista, Kris Lima, Shiraz Kanji”

Winner of the 2011 Sustainability Award Alberta Steel Design Awards of Excellence

Canadian Institute of Steel Construction

Owner City of Edmonton

Engineer: Dialog (formerly Cohos Evamy)

Contractor: ConCreate USL Ltd

Page 45: Download the SPS project book

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

jkfeofsfn

Ma Fang Bridge, China SPS Bridges

December 2009

· SPS offered the solution ofstrengthening the orthotropic bridgedeck

· The SPS construction activities werecontained such that vehicle and railtraffic could continue to utilise the bridge

· The skills necessary to undertake theworks are available globally as thisproject in China demonstrates

Page 46: Download the SPS project book

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

jkfeofsfn

SPS – Bridge in a Box

GENERAL

· new construction· bridge rehabilitation, deck replacement

− maintains roadway elevation− reduces weight− elimination of load restrictions− increase number of lanes (traffic volume)

FABRICATION

· pre-engineered, prefabricated bridges· no formwork required· no camber of longitudinal girders required

SHIPPING / ERECTION

· container (24 tonne capacity for standard 40 ft container)− 80 m2 of bridge deck− transverse beams / diaphragms− curbs and guardrails

· open transport for wide deck plates· no on-site concrete work required· no weather delays

MAINTENANCE

· 75+ year design life for SPS deck plates· 10+ year design life for road surface between renewal· de-icing chemicals or salts can be applied as deck is

protected with waterproofing membrane and lightweightwearing surface

40 ft container guardrail posts

SPS deck plate with integrated curb

transverse beams, diaphragms

standard SPS deck plate

2438 (8 ft)

2438 (8 ft)

coupler profile

SPS deck plate – longitudinal girder connection detail

SPS selected by American Association of State Highway and Transportation Officials as best-in-class product.

“we will, over the next several years, watch this technology move forward to become accepted practice across the nation”

Richard Tetreault Chairman, TIG

Page 47: Download the SPS project book

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

jkfeofsfn

SPS – Fly Over

Existing Condition

SPS Fly Over · construct a 750 m long movable roadway

above existing roadway allowing trafficflow over sections being reconstructed

· minimizes traffic disruption; fuel costsaving based on idling traffic ~$1.6M/day

· safer work conditions - separation oftraffic and construction

· provides weather enclosure reducingassociated risks and construction time

Renewal Construction Sequence Enabling Works · rerouting local services· install local foundation and rail system· erection of fly over section (with ramps)Staged Reconstruction· removal of existing deck section· reconstruction/rehabilitation of piers· erection of new steel girders and

prefabricated SPS deck plates· advancement of the fly over section to

the next stage

Erection of Fly Over Section

Renewed Elevated Expressway

Rehabilitated Structure

Optional Second Tier Construction (e.g. Gardiner Expressway - Toronto, Canada)

· fly over deck plates can be reused for thefirst 750 m of the second tier construction

· provides increased capacity and spacefor rapid transit

· possible to minimize ground level trafficand reuse the space for urban integration

Second Tier Construction

URBAN INTEGRATION

(transform ground level into retail and office space)

Page 48: Download the SPS project book

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

jkfeofsfn

Integrated SPS Bridge Deck Plates and Steel Tub Girders

Pre-Assembled Modules for Transportation

GENERAL · bridge design concept integrating SPS plates and steel tub girders

· allows bridge replacements to be executed quickly and efficiently

FABRICATION & SHIPMENT · SPS bridge deck plates are bolted to steel girders to create:

− exterior modular units with pre-attached guardrails− interior modular units that can be connected on-site

· fabricated modules can be stacked on a truck bed for transportation to site

ERECTION · rapid site erection of units· sequence shown in the figure below· modules are field welded along the length of the bridge

Integrated SPS Bridge Deck Plates and Steel Tub Girders

exterior interior

shaped splice plates

Page 49: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

CONTENTS

RECENT PROJECTS

OTHER INFORMATION

1. Stadia2. Buildings3. Bridges4. Maritime5. Offshore6. Special Applications

7. Production8. Company Profile

Page 50: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Solitaire SPS Maritime

May 2016

Owner AllseasYard United Stevedores, Amsterdam Design 10 – 20 - existing

The 127,500dwt Solitaire, one of the world’s largest pipe-layers had

550m² of tank top in hold number six reinstated. The project was undertaken with LR class approval in just 10 days. Off-hire was significantly reduced.

All steelwork was completed by licensee, SRC, whilst IE undertook all injection work.

Allseas’ Manager Technical Department, Quirien Grul, commented, “I am very pleased with the performance and will consider using SPS again should a similar project have to be undertaken.”

Page 51: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Atlantic OptimistSPS Maritime

April 2016

Owner Ueushuk Fisheries Ltd

Yard Glovertown Shipyards

Design 1/4” - 3/4” - existing

The existing steelwork on board the vessel was badly corroded, access tight and a crop-and-replace repair was an unattractive option.

40m² of deck required steel reinstatement. Solid perimeter bars, that form the boundary of the cavities, and top plates were welded into place and the resulting cavity injected with the elastomer core to form the new composite deck

The SPS deck reinstatement was substantially quicker than an equivalent conventional steel repair.

Captain Rex Simmonds, Ueushuk Fisheries Ltd commented, “I like the fact that the new deck is much stronger because the old deck is still there with a new deck on top bonded by the elastomer core. I recommend this process to anyone who has to replace steel on board ships where the SPS system can be used.”

Page 52: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Fuel Tank Conversion for 2015 Emissions Requirements SPS Maritime

December 2014

Project Summary

Three tankers needed thermal insulation boundaries installed between two Heavy Fuel Oil (HFO) tanks to create a Marine Gas Oil (MGO) tank as part of the shipowner’s strategy to meet new exhaust gas emission requirements.

IMO MARPOL 73/78 Annex VI has been amended to require new standards for marine fuel oils when vessels are operating in defined Emission Control Areas (ECA), specifying a reduction of the sulphur content (SOx) to below 0.1% from January 2015.

This was the first time that SPS had been used in this application; and was verified by Lloyds Register (LR). Carried out in Qatar, by Intelligent Engineering’s partner, CTS Offshore and Marine Limited, for a global shipping company, the three ships had areas of 50m² of SPS Overlay fitted to bulkheads between two adjacent fuel tanks.

Benefit of using SPS: · Cost effective insulation of

boundary between adjacent HFOand MGO tanks

· Maximum HFO and MGO tankcapacity due to compact thicknessof SPS

· No change to existing structure

· Zero through-life maintenance

Page 53: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Wind Turbine Installation and Maintenance Vessel SPS Maritime March 2014

Bottom of leg before SPS strengthening High risk of permanent damage

Bottom of leg with SPS Overlay Reduced stresses and deflections

Structural analysis model of leg and boulder

SPS provides an innovative solution to minimising operational risk and extending the service capability of self-elevating wind turbine and installation vessels. These specialist ships must be capable of safe operation in a wide variety of environmental conditions. In particular, submerged rocks on the sea-bed represent a significant risk to safety and operational integrity. SPS’s inherent resistance to impact and concentrated loads provides a technically superior solution which is fast and cost-effective to apply.

SPS Spudcan Reinforcement delivers: • Increased structural protection from concentrated loads caused by contact with large rocks on the sea bed.• Reduced operational risk and extended ship service capability.

Owner: MPI Offshore Limited Class: DNV

Page 54: Download the SPS project book

jkfeo fs fn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Aurora Australis SPS Maritime

May 2013

Project Summary

The ice breaker research vessel Aurora Australis travels between Australia and Antarctica transporting essential fuel and supplies to the research team. SPS was used to solve a historical fatigue crack problem that periodically affected a knuckle joint in the bulkhead separating the fuel oil and water ballast tanks. This can lead to a risk of contamination of both fuel and water ballast, which would have a serious impact on vessel operations. Used in this location, SPS significantly reduces the local stress levels and virtually eliminates the risk of further fatigue in the knuckle joint. At the same time, SPS provides an extra barrier, giving a second level of defence against future fuel and ballast water contamination.

Owner: P&O Maritime Services Pty Ltd

Repair Yard: Sembawang Shipyard Pte Ltd, Singapore

Class: Lloyd’s Register Design: 8-20-Existing

Page 55: Download the SPS project book

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Project Summary

DSME applied SPS on the bottom shell plating in way of Deck no.3 and Deck no.6 as a sound-deadening and vibration elimination solution. This concludes a 2-phase programme which left the original deck plating unaffected and post-fire strength the same or better after the SPS material is fitted. All SPS work, including steelwork, has been carried out with a riding squad from Marseille and Genoa, across the Mediterranean, to Tunis without affecting the vessel’s sailing schedule.

Builder: Daewoo Shipbuilding & Marine Engineering Co. Ltd (DSME)

Class: Bureau Veritas

Design: 6-25-Existing

Passenger/RoRoSPS Maritime

April 2013

Page 56: Download the SPS project book

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Cruise Vessel Sea Princess SPS Maritime October 2012

Project Summary

SPS reinstatement was carried out in way of Diesel Oil Tanks while passengers enjoyed the wonderful atmosphere of the Sea Princess in the middle of the Pacific Ocean, crossing both the Equator and the International Dateline.

Owner: Princess Cruise Lines, Ltd.

Builder: Riding squad, from San Francisco to New Zealand and Australia

Class: Lloyd’s Register

Design: 8-20- Existing

Page 57: Download the SPS project book

jkfeo fs fn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Cidade De Ilhabela SPS Maritime August 2012

Client Testimonial

“SPS side shell protection improves impact resistant of the vessel in way of supply boat landing area. It is a particularly good solution for single hull tankers like the FPSO CDI as it eliminates the cost of additional void tanks construction and at the same time with no reduction of cargo compartments space of the FPSO. The IE team performed this task on FPSO CDI project in a professional manner.”

Olejniczak Adam, Construction Manager - Single Buoy Moorings Inc.

Owner: Single Buoy Moorings Inc.

Conversion Yard: Guangzhou Dockyard, China

Class: American Bureau of Shipping

Design: 15-30-Existing

Page 58: Download the SPS project book

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

LNG FSU SPS Maritime

April 2012

Project Summary

SPS was applied to the upper surface of the sloping trunk deck on a LNG Floating Storage Unit. The objective was to restore the structural properties of the steel plating and stiffeners which had suffered corrosion due to condensation build-up in the enclosed void space above the LNG tanks. The use of SPS allowed a safe, fast and unhindered repair, while the low-heat-input operations, made possible by the unique design of the repair, avoided damage to the cryogenic membrane containment system located directly beneath the sloping deck.

Conversion Yard: Malaysia Marine and Heavy Engineering (MMHE) Shipyard

Class: American Bureau of Shipping

Design: 8-25-Existing

CLASS SUBMISSION & TENDER DOCUMENT

LON GL GD R 1510 2 OCL

LON GL GD R 1510 2 OCL

1500

EXI STIN G BKT

TRU N K D EC K 2750 0 ABL

TRU N K D EC K 2750 0 ABL DET "B"

SPS 8 (GR E)-25 -EXISTIN G (T YP)

L ON GL GD R 1510 2 OCL

* SPS PANEL 8(GR E) -25-EXI STIN G * SPS PANEL

8(GR E) -25-EXI STIN G

SEE DET "B"

SEE DET "F "

SI M T O DET "E"

SEE DET "F " TSL1 3

SEE DET "L " SEE

DET "A" (T YP)

SEE DET "E" (T YP)

PL AT E SEAMS T O BE AR R AN GED IN PANEL S

T O SUI T FI TTIN G

UPPER D EC K 2420 0 ABL

DET "C "

SEE DET "K"

PART SECTION @ INT BKT SC AL E 1:50

UPPER D EC K 2420 0 ABL *

SPS PANEL 8(GR E) -25-EXI STIN G

DET "D "

TSL1 4

200

*

DET "A" (T YP)

SPS PANEL 8(GR E) -25-EXI STIN G

TSL1 5 SID E SH ELL LON GL BH D 2080 0 OCL 18621 OC L

SID E SH ELL LON GL BH D 2080 0 OCL 18621 OC L

TYPICAL SECTION SC AL E 1:50

DET "D "

EXI ST G PL 11 T H K

CP

TYPICAL SECTION @ WEB FRAME SC AL E 1:50

SEAL WELD DET

DET "K" SPS PANEL

5 CP TR AN SV WEB,

BHD OR BR AC KET 25 x 5

BAC KI N G BAR

L ON GL GD R 15102 OC L

EXI ST G PL 11 T H K

SPS 8(GR E)-25 -EXI STIN G

L ON GL GD R 15102 OC L

T O SUIT L ON GL GD R

SPS 8(GR E)-25 -EXI STIN G

DETAIL "C" SC AL E 1:4

EXI ST G PL

DETAIL "B" SC AL E 1:4

40 x 5 BAC KI N G BAR

4 TH K C OLL AR PL T O SEAL C AVIT Y

(FI T T ED ON E SID E OF WEB ONL Y)

THI S EDGE OF C OL L AR T O BE SEAL ED WI T H C AUL KIN G

DET "M"

* EXI ST G PL22 T H K

"C " 8(GR E) -25-EXI STIN G

* DET "L "

KN UC KL E

5 25 x 5 BAC KI N G BAR

100 x 15 0 x 25 TH K PL T CORN ER S T O BE C H AMF ER ED

EXI ST G PL TO BE WELD ED & BON D ED IN PL AC E SI MIL AR T O D ET"H"

EXI ST G STIF R 300 x 1 1 H P

40 x 25 PERI MET ER BAR

CP *

SPS 8(GR E)-25 -EXI STIN G EXI ST G PL

SPS 8(GR E)-25 -EXI STIN G 25 x 5

DETAIL "F" @ END OF C AVIT Y WI TH SPS ON ON E SID E ONL Y

SC AL E 1:4

DETAIL "D" SC AL E 1:4

BAC KI N G BAR 100 x 150 x 2 5 TH K PL T C OR N ER S T O BE CH AMF ER ED

DETAIL "A" TO T O SUIT L ON GL GDR

IN PL AC E BE WEL D ED & BOND ED

STIF F EN ER C P FL AN GED

SC AL E 1:4 SIMIL AR T O D ET "H "

25 x 5 BAC KI N G BAR

C OR N ER

EXI ST G PL 11 T H K

L ON GL GD R 15102 OC L

EXI ST G PL

* N O WELD C OLL AR T O BE SEAL ED WI T H C AUL KIN G

PI PE D R AIN SPI GOT

* IN T H ESE L OC ATI ON S

DET "J" T O BE FIT T ED AT AF T EN D OF C AVITI ES

50

350 MI NI MU M SI M T O D ET "H "

EXI STI N G D EC K PL AT E T O BE R EN EWED (AS R EQUI R ED ) PR I OR T O

IN ST ALL ATI ON OF SPS OVERL AY

DETAIL "L" SC AL E 1:4

DETAIL "K" SC AL E 1:4

GAPS T O BE FILL ED WI TH SEAL AN T

DETAIL "F" @ END OF C AVIT Y WI TH SPS ON BOT H SID ES

SC AL E 1:4 3000 (T YP)

1 1/4 " SCH 8 0 PI PE

SEAL WEL D GRIN D FL U SH

SID E SH ELL 2080 0 OCL

EXI STIN G T RAN SV TYPICAL DETAIL OF SPS CAVITIES TR AN SV

WEB WEB FR AME

EXI STIN G T RAN SV WEB FR AME

5 CP 5 TR AN SV

WEB

PL AN AT SL OPIN G BH D & U PPER D EC K ST BD SI D E D R AWN POR T SID E SI MIL AR T O OPP H AND

SC AL E 1:2 0

TR AN SV WEB

50x2 5 T H K RI N G PL T AROUN D PEN ETR ATI ON S 25 x 5

BAC KI N G BAR L ON GL GD R

80 L ON G x 2 4 T H K PL (WID T H T O SUIT ) C OR N ER S T O BE CH AMF ER ED 25 x 5

BAC KI N G BAR T O SUIT EXI STI N G WELD S

DETAIL "G" TO BE BOND ED I N PL AC E SC AL E 1:4

DETAIL "J" SC AL E 1:4

25 x 5 BAC KI N G BAR

100 x 15 0 x 25 TH K PL T CORN ER S T O BE C H AMF ER ED

T O SUIT EXI STI N G WELD S T O BE BON D ED IN PL AC E

40 x 25 PERI MET ER BAR

25 x 5 BAC KI N G BAR

EXI ST G PL

SPS T OP PL T R ADIU SED T O SUI T SIZ E OF EXI STIN G SC ALL OPS

IN WEB FR AME PL T T O BE FI TT ED I N T HI S AR EA

25 x 5 BAC KI N G BAR

L ON GL 4 TH K

C OLL AR

DET "G"

25 x 5 BAC KI N G BAR

8(GR E) TH K SPS F AC E PL

DETAIL "J" 3 L OC N S P&S

I. W.O. COF F ERD AM SC AL E 1:4

DETAIL "M" SC AL E 1:4

100 x 15 0 x 25 TH K PL T AF T ER IN JECTI ON S

5 C OR N ER S T O BE CH AMF ER ED

T O SUIT EXI STI N G WELD S T O BE WEL D ED & BOND ED I N PL AC E

100 x 15 0 x 25 TH K PL T CORN ER S T O BE C H AMF ER ED

T O SUIT EXI STI N G WELD S T O BE BON D ED IN PL AC E

8(GR E) TH K SPS DET F AC E PL "H "

25 x 5 BAC KI N G BAR DETAIL "E"

SC AL E 1:4 DETAIL "H"

SC AL E 1:4

NOTES 1. ALL DIMENSIONS IN mm AND TO BE CONFIRMED AT SHIP

PRIOR TO WORK COMMENCING.

2. STEEL - ABS GRADE A OR EQUIVALENT EXCEPT

SPS TOP PLATE WHICH IS TO BE GRADE E. 3. ALL STEEL ON INTERIOR OF SURFACES OF SPS CAVITIES

IS TO BE GRIT BLASTED TO A SURFACE ROUGHNESS OF

60+MICRONS, AND BE CLEAN,DRY,FREE OF GRIT, GREASE

AND OTHER CONTAMINANTS .

4. SPS CAVITIES MUST BE AIR TIGHT. 5. THERE SHALL BE NO SUBSTITUTIONS OF MATERIALS

WITHOUT PRIOR WRITTEN APPROVAL OF

INTELLIGENT ENGINEERING OR THE ABS SURVEYOR.

6. WELDING TO ABS STANDARDS. 7. ALL WELDING TO BE COMPLETE PRIOR TO ELASTOMER

INJECTION.

8. ALL FILLET WELD SIZES SHOWN ARE LEG LENGTH.

9. ALL WORK TO BE PERFORMED IN ACCORDANCE WITHINTELLIGENT ENGINEERING TENDER SPECIFICATION

FOR SPS SLOPING BHD REINSTATEMENT FOR THE

"TENAGA SATU" PREPARED FOR MISC BERHAD.

10. ALL FIT-UP AND WELDING IS TO BE TO THE SATISFACTION

OF THE ATTENDING SURVEYOR.

11. 25 x 5 FB BACKING BAR IS TO BE USED IN ORDER TO FIXTHE SPECIFIED 25mm ELASTOMER THICKNESS AT PANEL

BOUNDARIES.

PROPRIET ARY AND CONFIDENTIAL COPYRIGHT INT ELLIGENT ENGINEERING 2010

2 2011- 10-27 SPS AREA MODIFIED DET "L" & "K" REVISED CJO OS 1 2011-09- 12 SPS AREA REVISED CJO OS

REV DATE MOD DRN CHK DRA WN BY:

CJO

DATE:

2010-09-22

PROJECT No.:

10-178

CHE CKED:

OS

DATE:

2010-09-23

DRA WING No.:

10178-001-02

SCAL E:

AS SHOWN

SHEET SIZE: A1

SHEET OF

2 2

PROJECT:

FSU LEKAS (IMO # 7428457) TITL E:

SPS OVERLAY SLOPING BHD

FIL E NAME: 2011-10-27 10178-001 Rev2.dwg

Intelligent Eng inee r ing (C anad a) Limited 14 Cha mbe rlain Avenue Otta wa, Ontario Canada Te l: +1 -613 -569-311 1 Fax: +1 -613-569-3 222

intelligent engineering

20

350

MIN

IMU

M

UPPE

R DE

CK

SLOP

ING

BHD

Page 59: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

DSME “Storium” - Floating Museum and Exhibition Centre SPS Maritime October 2011

The “Bow Hunter” is the first vessel built by Daewoo Shipbuilding and Marine Engineering. The ship is now converted to a company museum and exhibition centre celebrating more than 35 years of shipbuilding and marine engineering.

The project involved rapid installation of 3,500m² of SPS decks on two levels, providing a flat rigid floor with excellent dynamic and acoustic response.

Page 60: Download the SPS project book

SPS Marine Technologies Limited | Registered in England 3184851 | A member of the IE Group of Companies

Hatch CoverSPS MaritimeJanuary 2010

Page 61: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

CONTENTS

RECENT PROJECTS

OTHER INFORMATION

1. Stadia2. Buildings3. Bridges4. Maritime5. Offshore6. Special Applications

7. Production8. Company Profile

Page 62: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

KK1 SPS Offshore October 2016

FSO Kome Kribi 1 (KK1), converted in 1977 from a ULCC and operated by ExxonMobil for Cameroon Oil Transportation Company has had its sea chest, bottom shell and bulkhead reinstated using SPS.

The repair took place 11km off the coast of Cameroon using steel workers from Cameroon Shipyard and Industrial Engineering Ltd (CNIC).

Chris Williamson, FSO KK1, Chief Engineer said of the repair, “The entire team worked very hard and completed a difficult task like professionals. This type of work in a pump room on an operating oil tanker is not an easy task. The SPS was impressive and I can see areas where it can be utilized in the future.”

Page 63: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Deck Protection SPS Offshore

April 2016

IE developed an impact resistant deck for a tension leg platform which increased the impact resistance of the structure and resisted loads without penetration. The specification defined the energy absorption capability as 765 kJ which is associated with a 3 MT basket dropped at a height of 26 m above the deck. Also a 2.7 MT and a 2.3 MT driller riser type dropped from a height of 17 m above the deck and impact with energies of 450 kJ and 384 kJ, respectively.

It also had to resist the operating service loads from a guideline winch skid and a blowout preventer. The deck could be no higher than 300mm with a maximum weight of 135 tonnes and had to be removable.

An SPS deck was designed to these exacting criteria. The deck panels were manufactured at our Dongkuk S & C production facility.

Page 64: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Noble Paul Romano SPS Offshore August 2015

The high impact resistance that SPS provides made it the perfect solution for the reinstatement of the pipe deck on this semi-submersible, which had suffered damage from dropped objects. Two areas of the deck were repaired with SPS. Its use guaranteed the integrity of below deck service runs which were unaffected by the extensive work above.

Owner: Noble Corporation Repair Location: Texas, USA Class: ABS

Page 65: Download the SPS project book

jkfeofs

fn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Safe Concordia SPS Offshore

April 2015

SPS was used to strengthen the cargo deck on-board this semi-submersible. SPS mitigated the need for steel removal which would have increased the project’s complexity, significantly increasing the repair schedule and associated costs.

Page 66: Download the SPS project book

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

John Shaw SPS Offshore March 2014

Project Summary The semi-submersible platform “John Shaw” has benefited from a repair, impossible by any other means other than SPS. At the time of repair, the vessel was floating alongside and the repair location, several meters below the waterline, made conventional “crop and renew” impossible without a costly and unscheduled dry-docking. SPS was installed in way of two areas damaged by positioning tugs and offshore support vessels to protect and reinforce the hull plating.

In this application, SPS provided a class-approved permanent repair without the need to dry-dock the platform; saving the operators additional time and maintenance costs associated with an unscheduled docking.

Owner: Transocean Ltd Repair Shipyard: Semco Maritime, Esbjerg Class: DNV Design: 8-25-Existing

Page 67: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Petrobras SA FPSOs SPS Offshore

December 2014

SPS compact double hull (CDH) was selected to provide side shell impact protection to the boat landing areas of three FPSOs operated by Petrobras SA. This innovative use of SPS meets the low energy impact resistance requirements of IMO MARPOL Annex I Requirements for FPSOs and FSUs. The solution which protects the adjacent cargo oil tanks was approved by Class Society DNV-GL.

The work was carried out at Enseada do Paraguaçu S.A. Shipyards (EEP) in Brazil and COSCO (Dalian) Shipyard, China. These projects were undertaken during the course of 2014, with the final project being completed in December 2014. A total 2,824m² of SPS was been installed on the three vessels.

Owner: Petrobras Repair Location: China and Brazil Class: DNV-GL

Page 68: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Quad204 Escape Tunnel SPS Offshore

January 2014

Owner: BP Builder: Hyundai Heavy Industries Class: Lloyd’s Register

The blast and fire resistant escape tunnel for the new FPSO Quad204 runs the length of the processing modules and is designed to withstand the harsh environmental conditions of the North Sea and resist extreme emergency loads. Arranged in a novel double-layer, the SPS panels provide a primary barrier to survive accidental loads from both an initial blast and subsequent hydrocarbon and jet fires so that shipboard staff can escape safely to their muster points.

Page 69: Download the SPS project book

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

FPSO Quad 204 SPS Offshore

November 2013

Project Summary

A special fluid is injected into the well to increase the oil recovery. However, the fluid is heat sensitive (coagulates at elevated temperatures); and because the Enhance Oil Recovery (EOR) tanks are adjacent to the fuel oil tanks (usually maintained at around 60 degree C) there is a concern. The EOR fluid is circulated in the tanks to prevent “hot-spots”. BP required the tank walls to be insulated for safety reason. The internal surfaces of the EOR tanks are stainless steel (clad/explosion bonded SS/CS plating) with a thermal resistance through SPS Overlay (R-value) is 0.2819 m²C°/W.

Owner: British Petroleum (BP)

Builder: Hyundai Heavy Industries Ltd.

Class: Lloyd’s Register

Design: 8-50-Existing with stainless steel(LR Grade 316)

Page 70: Download the SPS project book

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

FPSO Kwame Nkrumah MV21 SPS Offshore February 2013

Client Testimonial

“Utilizing the non-intrusive SPS to reinstate the plates on the void tanks and forepeak tank side shells and bulkheads of FPSO Kwame Nkrumah MV21 enabled our FPSO to remain in operation. The SPS team completed this excellent job under difficult conditions and with minimal impact on our productivity. The work was finished with excellent results.”

Bai Li Guo, Project Director - MODEC Offshore Production Systems (Singapore) Pte Ltd

Owner: MODEC Inc.

Repair Location: On station repair at Ghana Offshore

Class: American Bureau of Shipping

Design: 8-25-Existing

Page 71: Download the SPS project book

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

FPSO Cidade De Ilhabela SPS Offshore August 2012

Client Testimonial

“SPS side shell protection improves impact resistant of the vessel in way of supply boat landing area. It is a particularly good solution for single hull tankers like the FPSO CDI as it eliminates the cost of additional void tanks construction and at the same time with no reduction of cargo compartments space of the FPSO. The IE team performed this task on FPSO CDI project in a professional manner.”

Olejniczak Adam, Construction Manager - Single Buoy Moorings Inc.

Owner: Single Buoy Moorings Inc.

Conversion Yard: Guangzhou Dockyard, China

Class: American Bureau of Shipping

Design: 15-30-Existing

Page 72: Download the SPS project book

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

LNG FSU SPS Offshore

April 2012

Project Summary

SPS was applied to the upper surface of the sloping trunk deck on a LNG Floating Storage Unit. The objective was to restore the structural properties of the steel plating and stiffeners which had suffered corrosion due to condensation build-up in the enclosed void space above the LNG tanks. The use of SPS allowed a safe, fast and unhindered repair. The low-heat-input operations, made possible by the unique design of the repair, avoided damage to the cryogenic membrane containment system located directly beneath the sloping deck.

Conversion Yard: Malaysia Marine and Heavy Engineering (MMHE) Shipyard

Class: American Bureau of Shipping

Design: 8-25-Existing

CLASS SUBMISSION & TENDER DOCUMENT

LON GL GD R 1510 2 OCL

LON GL GD R 1510 2 OCL

1500

EXI STIN G BKT

TRU N K D EC K 2750 0 ABL

TRU N K D EC K 2750 0 ABL DET "B"

SPS 8 (GR E)-25 -EXISTIN G (T YP)

L ON GL GD R 1510 2 OCL

* SPS PANEL 8(GR E) -25-EXI STIN G * SPS PANEL

8(GR E) -25-EXI STIN G

SEE DET "B"

SEE DET "F "

SI M T O DET "E"

SEE DET "F " TSL1 3

SEE DET "L " SEE

DET "A" (T YP)

SEE DET "E" (T YP)

PL AT E SEAMS T O BE AR R AN GED IN PANEL S

T O SUI T FI TTIN G

UPPER D EC K 2420 0 ABL

DET "C "

SEE DET "K"

PART SECTION @ INT BKT SC AL E 1:50

UPPER D EC K 2420 0 ABL *

SPS PANEL 8(GR E) -25-EXI STIN G

DET "D "

TSL1 4

200

*

DET "A" (T YP)

SPS PANEL 8(GR E) -25-EXI STIN G

TSL1 5 SID E SH ELL LON GL BH D 2080 0 OCL 18621 OC L

SID E SH ELL LON GL BH D 2080 0 OCL 18621 OC L

TYPICAL SECTION SC AL E 1:50

DET "D "

EXI ST G PL 11 T H K

CP

TYPICAL SECTION @ WEB FRAME SC AL E 1:50

SEAL WELD DET

DET "K" SPS PANEL

5 CP TR AN SV WEB,

BHD OR BR AC KET 25 x 5

BAC KI N G BAR

L ON GL GD R 15102 OC L

EXI ST G PL 11 T H K

SPS 8(GR E)-25 -EXI STIN G

L ON GL GD R 15102 OC L

T O SUIT L ON GL GD R

SPS 8(GR E)-25 -EXI STIN G

DETAIL "C" SC AL E 1:4

EXI ST G PL

DETAIL "B" SC AL E 1:4

40 x 5 BAC KI N G BAR

4 TH K C OLL AR PL T O SEAL C AVIT Y

(FI T T ED ON E SID E OF WEB ONL Y)

THI S EDGE OF C OL L AR T O BE SEAL ED WI T H C AUL KIN G

DET "M"

* EXI ST G PL22 T H K

"C " 8(GR E) -25-EXI STIN G

* DET "L "

KN UC KL E

5 25 x 5 BAC KI N G BAR

100 x 15 0 x 25 TH K PL T CORN ER S T O BE C H AMF ER ED

EXI ST G PL TO BE WELD ED & BON D ED IN PL AC E SI MIL AR T O D ET"H"

EXI ST G STIF R 300 x 1 1 H P

40 x 25 PERI MET ER BAR

CP *

SPS 8(GR E)-25 -EXI STIN G EXI ST G PL

SPS 8(GR E)-25 -EXI STIN G 25 x 5

DETAIL "F" @ END OF C AVIT Y WI TH SPS ON ON E SID E ONL Y

SC AL E 1:4

DETAIL "D" SC AL E 1:4

BAC KI N G BAR 100 x 150 x 2 5 TH K PL T C OR N ER S T O BE CH AMF ER ED

DETAIL "A" TO T O SUIT L ON GL GDR

IN PL AC E BE WEL D ED & BOND ED

STIF F EN ER C P FL AN GED

SC AL E 1:4 SIMIL AR T O D ET "H "

25 x 5 BAC KI N G BAR

C OR N ER

EXI ST G PL 11 T H K

L ON GL GD R 15102 OC L

EXI ST G PL

* N O WELD C OLL AR T O BE SEAL ED WI T H C AUL KIN G

PI PE D R AIN SPI GOT

* IN T H ESE L OC ATI ON S

DET "J" T O BE FIT T ED AT AF T EN D OF C AVITI ES

50

350 MI NI MU M SI M T O D ET "H "

EXI STI N G D EC K PL AT E T O BE R EN EWED (AS R EQUI R ED ) PR I OR T O

IN ST ALL ATI ON OF SPS OVERL AY

DETAIL "L" SC AL E 1:4

DETAIL "K" SC AL E 1:4

GAPS T O BE FILL ED WI TH SEAL AN T

DETAIL "F" @ END OF C AVIT Y WI TH SPS ON BOT H SID ES

SC AL E 1:4 3000 (T YP)

1 1/4 " SCH 8 0 PI PE

SEAL WEL D GRIN D FL U SH

SID E SH ELL 2080 0 OCL

EXI STIN G T RAN SV TYPICAL DETAIL OF SPS CAVITIES TR AN SV

WEB WEB FR AME

EXI STIN G T RAN SV WEB FR AME

5 CP 5 TR AN SV

WEB

PL AN AT SL OPIN G BH D & U PPER D EC K ST BD SI D E D R AWN POR T SID E SI MIL AR T O OPP H AND

SC AL E 1:2 0

TR AN SV WEB

50x2 5 T H K RI N G PL T AROUN D PEN ETR ATI ON S 25 x 5

BAC KI N G BAR L ON GL GD R

80 L ON G x 2 4 T H K PL (WID T H T O SUIT ) C OR N ER S T O BE CH AMF ER ED 25 x 5

BAC KI N G BAR T O SUIT EXI STI N G WELD S

DETAIL "G" TO BE BOND ED I N PL AC E SC AL E 1:4

DETAIL "J" SC AL E 1:4

25 x 5 BAC KI N G BAR

100 x 15 0 x 25 TH K PL T CORN ER S T O BE C H AMF ER ED

T O SUIT EXI STI N G WELD S T O BE BON D ED IN PL AC E

40 x 25 PERI MET ER BAR

25 x 5 BAC KI N G BAR

EXI ST G PL

SPS T OP PL T R ADIU SED T O SUI T SIZ E OF EXI STIN G SC ALL OPS

IN WEB FR AME PL T T O BE FI TT ED I N T HI S AR EA

25 x 5 BAC KI N G BAR

L ON GL 4 TH K

C OLL AR

DET "G"

25 x 5 BAC KI N G BAR

8(GR E) TH K SPS F AC E PL

DETAIL "J" 3 L OC N S P&S

I. W.O. COF F ERD AM SC AL E 1:4

DETAIL "M" SC AL E 1:4

100 x 15 0 x 25 TH K PL T AF T ER IN JECTI ON S

5 C OR N ER S T O BE CH AMF ER ED

T O SUIT EXI STI N G WELD S T O BE WEL D ED & BOND ED I N PL AC E

100 x 15 0 x 25 TH K PL T CORN ER S T O BE C H AMF ER ED

T O SUIT EXI STI N G WELD S T O BE BON D ED IN PL AC E

8(GR E) TH K SPS DET F AC E PL "H "

25 x 5 BAC KI N G BAR DETAIL "E"

SC AL E 1:4 DETAIL "H"

SC AL E 1:4

NOTES 1. ALL DIMENSIONS IN mm AND TO BE CONFIRMED AT SHIP

PRIOR TO WORK COMMENCING.

2. STEEL - ABS GRADE A OR EQUIVALENT EXCEPT

SPS TOP PLATE WHICH IS TO BE GRADE E. 3. ALL STEEL ON INTERIOR OF SURFACES OF SPS CAVITIES

IS TO BE GRIT BLASTED TO A SURFACE ROUGHNESS OF

60+MICRONS, AND BE CLEAN,DRY,FREE OF GRIT, GREASE

AND OTHER CONTAMINANTS .

4. SPS CAVITIES MUST BE AIR TIGHT. 5. THERE SHALL BE NO SUBSTITUTIONS OF MATERIALS

WITHOUT PRIOR WRITTEN APPROVAL OF

INTELLIGENT ENGINEERING OR THE ABS SURVEYOR.

6. WELDING TO ABS STANDARDS. 7. ALL WELDING TO BE COMPLETE PRIOR TO ELASTOMER

INJECTION.

8. ALL FILLET WELD SIZES SHOWN ARE LEG LENGTH.

9. ALL WORK TO BE PERFORMED IN ACCORDANCE WITHINTELLIGENT ENGINEERING TENDER SPECIFICATION

FOR SPS SLOPING BHD REINSTATEMENT FOR THE

"TENAGA SATU" PREPARED FOR MISC BERHAD.

10. ALL FIT-UP AND WELDING IS TO BE TO THE SATISFACTION

OF THE ATTENDING SURVEYOR.

11. 25 x 5 FB BACKING BAR IS TO BE USED IN ORDER TO FIXTHE SPECIFIED 25mm ELASTOMER THICKNESS AT PANEL

BOUNDARIES.

PROPRIET ARY AND CONFIDENTIAL COPYRIGHT INT ELLIGENT ENGINEERING 2010

2 2011- 10-27 SPS AREA MODIFIED DET "L" & "K" REVISED CJO OS 1 2011-09- 12 SPS AREA REVISED CJO OS

REV DATE MOD DRN CHK DRA WN BY:

CJO

DATE:

2010-09-22

PROJECT No.:

10-178

CHE CKED:

OS

DATE:

2010-09-23

DRA WING No.:

10178-001-02

SCAL E:

AS SHOWN

SHEET SIZE: A1

SHEET OF

2 2

PROJECT:

FSU LEKAS (IMO # 7428457) TITL E:

SPS OVERLAY SLOPING BHD

FIL E NAME: 2011-10-27 10178-001 Rev2.dwg

Intelligent Eng inee r ing (C anad a) Limited 14 Cha mbe rlain Avenue Otta wa, Ontario Canada Te l: +1 -613 -569-311 1 Fax: +1 -613-569-3 222

intelligent engineering

20

350

MIN

IMU

M

UPPE

R DE

CK

SLOP

ING

BHD

Page 73: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

CONTENTS

RECENT PROJECTS

1. Stadia2. Buildings3. Bridges4. Maritime5. Offshore6. Special Applications

OTHER INFORMATION

7. Production8. Company Profile

Page 74: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Balcony Prototype SPS Special Applications

April 2016

SPS balconies provide a prefabricated, lightweight, quick to install alternative to the conventional reinforced concrete solution. SPS balconies meet all dynamic requirements and provide an economically competitive solution which gives architects and contractors considerable flexibility in both design and build programme.

Photographs above show the prototype balcony being delivered and installed for final testing. This application was developed with a partner company. Pending first orders indicate a substantial international market.

Page 75: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | SPS Pop-up Panels | January 2016 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

Vehicle Barriers SPS Special Applications

January 2016

The rising anti-ram SPS vehicle barrier, tested successfully in the UK to industry standards in May 2015, has now gone into production. The vehicle barriers which successfully brought a 40 tonne truck to a complete standstill are for national and international clients.

Page 76: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

SPS Citadel Access Protection SPS Special Applications

May 2015

Background

Citadel protection is a proven concept that has a successful track record for protecting ships and crew from piracy. The internationally recognised Best Management Practice to Deter Piracy in the Gulf of Aden and off the Coast of Somalia recommends that due consideration should be given to establishing a secure Citadel that “is designed and constructed to resist a determined pirate trying to gain entry for a fixed period of time”. SPS is an ideal product for Citadel hardening.

Slice through SPS panels View from inside Citadel View from outside Citadel

Location: Access openings leading to safe area or “Citadel” SPS protection panels

Design: 3-15-3

Installation: By ship’s crew/steel contractors

Fleet Deals: BP Fleet

SPS Citadel Access Protection provides:

· A new final barrier to delay and deterpirate attacks

· Protection within 90 seconds

· Enhanced protection from impact loads,blasts and projectiles

· FB6 ballistic compliant designs available

Page 77: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Column Protection SPS Special Applications

July 2015

70 Tonne Tug Master

Design Criteria · absorb energy from radial impacts or glancing

blows without contact or damage to column· impact protection system is replaceable

Design · consists of SPS 20-25-20 circular plate, 15 mm

thick Y-shaped steel stiffeners, steel-concretecomposite reaction wall secured to a basestructure and embedded in the tarmacadjacent to columns supporting the airportpiers

· designed to resist a direct impact from a towhitch on a 70 tonne tug master moving at30 km/hr (kinetic energy = 2.4 MJ)

Proven Impact Resistance · the design was verified by advanced finite

element analyses for all possible impactscenarios (critical load case is radial impactalong centreline)

· full-scale test demonstrates impact resistance

Production · 22 units under production in Singapore by

client. IE to undertake injection.· To be installed by client

Page 78: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Flood Panel SPS Special Applications

June 2015

IE worked with Florida based Flood Panel LLC to develop a flood protection product for small businesses hardest hit by Hurricane Sandy for the New York City Economic Development Corporation. The SPS Flood Panel was selected from 200 applicants for the city’s $30 million federally-funded RISE: NYC competition to find the world’s most promising resiliency technologies to prepare businesses for future storms, sea level rise and other effects of climate change.

Page 79: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Mining Truck Body SPS Special Applications

December 2014

· Heavy mining trucks carry payloads up to 400 tons; structures are vulnerable to impactdamage and rapid wear

· Analysis verifies engineering and economic benefits of SPS

− reduced weight increases payload − reduced wear-rate and impact damage increases service life

· SPS solution applicable to reinstatement of existing vehicle and construction of newvehicles

Page 80: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Transformer Casing SPS Special Applications

November 2013

· SPS Transformer Casingsincrease stiffness, reduceweight and dampen vibrationand sound

· Six projects completed todate, using the Overlaymethod in-situ, to verifydesign and benefits

· High volume production willuse prefabricated SPSpanels

Page 81: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

CONTENTS

RECENT PROJECTS

1. Stadia2. Buildings3. Bridges4. Maritime5. Offshore6. Special Applications

OTHER INFORMATION

7. Production8. Company Profile

Page 82: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Pohang, Korea SPS Production Plant

February 2015

The new SPS production facility at Dongkuk S & C commenced production in February 2015. First on its order book were the SPS terraces, floors and walls for Melco Crown Entertainment, Studio City Magic Theatres, Macau. It is the primary production facility for all SPS products.

Page 83: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Gwangyang, Korea SPS Production Plant

March 2014

· overflow facility

· 3 bays - 25m x 150m

· 5-10 tonnes overhead cranes

· painting facilities

· convenient to ports

· photographs below show SPSterraces in production

Page 84: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Production Process SPS Production Plant

March 2014

Steel plate surface preparation Fast low heat robotic welding

Injecting PU CNC drilling of bolt holes

Panels stacked Panels loaded for shipment

Page 85: Download the SPS project book

jkfeofsfn

Intelligent Engineering (UK) Limited | Registered in England 3184851 | A member of the IE Group of Companies

Shipment SPS Production September 2013

Loads 77 to 79 to Philippine Arena, Manila, Philippines Total 64,471 kgs of longest SPS Terraces fabricated to date (up to 12,183mm)

Big R Demo Bridge to Greeley, Colorado, USA 3 concept bridge deck panels with innovative connection details - Total 4,370 kgs

Load 73 to Philippine Arena, Manila 22,112 kgs wide back of bowl

terraces

Loads 3 & 4 to Q204 Escape tunnel Mokpo, Korea Total 22,670 kgs of flat, large radius outer tunnel & small

radius inner tunnel panels up to 4,925mm long

Page 86: Download the SPS project book

intelligent engineering company profile

Page 87: Download the SPS project book

SPS being applied to the tank top (bottom of cargo hold) on a bulk carrier

Page 88: Download the SPS project book

3

what is SPS?

Conventional Stiffened Steel

Conventional Concrete and Steel Structure

SPS is a structural composite comprising two metal plates bonded with a polyurethane elastomer core.

SPS is much simpler and more robust than stiffened steel plate and much lighter and faster to erect than reinforced concrete.

SPS is used in a wide variety of applications including structural flooring, stadia and arena terraces, ship repair, shipbuilding and bridges.

SPS Structure

Page 89: Download the SPS project book

4

benefits of SPS

SPS is a structural material used to make the load-bearing plates found in a wide variety of maritime and civil structures. SPS offers benefits in performance, economics, sustainability and safety.

Maritime applications

In maritime structures, such as the hulls and bulkheads of ships, load-bearing plates are usually made from steel, which is heavily stiffened to prevent buckling. SPS eliminates the stiffening elements, making these structures much less complicated and much less prone to fatigue and corrosion.

Civil applications

In civil engineering structures, such as the decks of bridges and floors in buildings, load-bearing plates are usually made from reinforced concrete. This is because it is difficult to control fatigue and vibration using steel and, with the exception of long-span bridges, the weight penalty of using concrete is tolerated. SPS controls fatigue and vibration and is much lighter than concrete. In addition, SPS plates are prefabricated to a high degree of dimensional accuracy. Using SPS plates reduces ‘wet-work’ on site and de-risks and accelerates the build programme.

Repair and conversion

SPS can also be used to reinstate or strengthen existing plate structures, such as the cargo holds of ships and the decks of bridges. Here again, the benefits are a much reduced schedule and a very robust and long lasting solution. Across the full range of applications, the composite properties of SPS give rise to a number of other valuable benefits. In summary, SPS offers:

Lifting a pre-assembled triple unit of SPS stadia terracing

Simpler, faster fabrication

> Elimination of stiffeners simplifies structures

> Prefabrication and ease of erection shortens and de-risksconstruction schedules

> Eliminating ‘cropping’ makes SPS a much faster and lessrisky method of reinstatement and strengthening

Improved designs and in-service performance

> Less susceptible to fatigue and corrosion, local bucklingand the formation and propagation of cracks, compared toconventional stiffened steel structures

> Reduces weight and thickness and allows increased spanscompared to conventional reinforced concrete structures

Cost savings and economic benefits

> Reduces build cost

> Reduces construction schedule and risk

> Reduces maintenance cost

> Increases service life

> Increases cargo capacity

> Increases rentable floor area

Enhanced protection and safety

> Greater resistance to accidental or extreme impact loads

> Built-in structural fire protection

> Built-in blast and ballistics protection

> Built-in acoustic insulation

Improved environmental sustainability

> Fully recyclable and reusable gives reduced carbon footprint

> Reduced weight results in less materials, less waste andfewer truck loads

> Faster construction means less disruption and publicinconvenience

Page 90: Download the SPS project book

5

markets

The Silver Bell tank tops reinstated with SPS Overlay

> New construction for full range of ship types includingcomponents such as:• Hatch covers• Vehicle decks• Tank tops• Bulkheads• Hull plating• Citadel protection

> Repair and conversion of:• Offshore vessels and structures• Bulk carriers and tankers• RoRos, ferries and passenger vessels• A wide variety of other applications

> Stadia and arena terraces• New venues• Reprofiling• Extensions

> Structural floors• High rise• Concourses• Low rise• Car parks

> Bridge decks including:• New bridges• Bridge replacement• Deck reinstatement

> Naval vessels with particular benefits for:• Blast belts• Flight decks

> Construction including:• Crash decks• Blast walls

> Industrial applications:• Transformer casings• Turbine enclosures• Heavy machinery

SPS Floors eliminate the need for concrete at height

Page 91: Download the SPS project book

6

6

SPS

SPS has set a new standard for ship repair and conversion, delivering a faster, less disruptive alternative to traditional ‘crop and replace’ techniques.

SPS repairs the existing plating as one side of a steel composite panel formed by a new top plate and an elastomer core. The results fully restore or enhance the strength of the original structure to deliver high impact resistance and permanently flatter surfaces that improve performance and cargo handling.

The benefits of SPS include:

> Faster repair schedules, minimal labour andreduced downtime

> Non-disruptive, safe, permanent improvements

> Reduced repair costs, lower operating costs andincreased revenue potential

Maritime and Offshore projects have been completed. These fall into four categories:

> Offshore vessels and structures including FPSOs andFSOs, drilling rigs, semi-submersibles, and LNGs

> Bulk carriers and tankers including Capesize andPanamax vessels

> RoRos, car carriers, freight and passenger ferries

> A wide variety of other vessels from barges, dredgersand floating pontoons to helidecks and side shellprotection

Page 92: Download the SPS project book

7

7

> SPS has been used for extensive deck reinstatement of six Stena Line and sixteen P&O ferries (with twenty-six repairs).

The non-intrusive nature of SPS Overlay contributed to significant schedule savings and ensured the vessels were back in service quickly.

“The original programme of

repairing 10,000m² of deck

on three ships back to back

in 70 days was the most

demanding schedule that I

have overseen as technical

superintendent. The project

would not have been possible

with conventional repair

techniques.”

Nigel Baalham, Technical Superintendent,

Stena Line

Illustrative cross section showing new top plate and elastomer core of SPS. In spite of diminution and ‘dishing’, the original deck plate can be retained to form the bottom plate of

the sandwich. New lashing pots are integrated during process.

> The helideck of the Transocean Legend needed strengthening to accommodate heavier helicopters. The SPS solution was completed in 17 days.

“We are delighted with the

end result and the speed

with which the

strengthening took place.”

Guy Cantwell, Transocean

Page 93: Download the SPS project book

8

> The Capesize Docebay had 1,932m² of tank tops, hopper sides and stools reinstated with SPS in Cosco Nantong, China.

The “dishing” of the tank tops has been eliminated, which will lead to better cargo handling and reduced turnaround times.

“Using SPS rather than

conventional crop and replace

methods reduced our repair

schedule by 40%.”

Atle Paulsen, Superintendent, V.Ships

Page 94: Download the SPS project book

9

9

> Wear and tear had resulted in steel diminution to the FPSO Conkouati’s side and bottom shell.

SPS was used to reinstate the structural strength of the hull. Areas of side shell, which are vulnerable to impact damage from offloading tankers, were strengthened externally, while the bottom shell was strengthened intercostally below the waterline without the need for dry docking.

“SPS was an obvious choice

for us. The repairs were not

intrusive and were carried

out on-station whilst normal

operations continued on

board. The equipment used

for the job was small and

portable and meant

that its movement did not

cause major inconvenience

or involve many people.

The work was finished with

excellent results.”

Klervi Keryhuel, Marine Engineer, Perenco

> SPS was used as side impact protection in the conversion of an FPSO to satisfy IMO MEP139 (53) “Guidelines for the application of MARPOL Annex1 Requirements for FPSOs and FSUs”. It is also Classand Flag State approved.

“Keppel Singapore, Intelligent

Engineering’s licensee of SPS

Overlay continues to provide

innovative, proven solutions for

FPSO customers. The adoption of

SPS offers the ideal side shell

protection for FPSOs and we are

pleased to be instrumental in this

first application.”

Louis Chow, General Manager Commercial

(Conversions) Keppel Shipyard Ltd

Page 95: Download the SPS project book

10

maritime new construction

IE and DSME (Daewoo Shipbuilding and Marine Engineering Co Ltd) have established a joint venture, SPS Marine Technologies Ltd, to bring SPS into mainstream shipbuilding. The company provides SPS solutions and licences the technology to other shipyards around the world. A wide variety of applications have been developed including hatch covers, vehicle decks, tank tops, bulkheads and hull plating.

SPS hatch cover at DSME shipyard

Benefits include:

> Simplified more robust structures

> Up to 40% reduction in labour, 50% less welding and 20%less surface area

> Superior in-service performance and reduced through-lifemaintenance

> Prefabrication guarantees quality and efficiency inconstruction

“Lloyd’s Register was the first to

approve SPS for ship repair and now

that this is well established we’re

delighted to be supporting IE and DSME

in their joint venture to bring SPS into

new ship construction.”

Richard Sadler CEO, Lloyd’s Register

Page 96: Download the SPS project book

11

> Through the MTL partnership, DSME constructs and supplies SPS hatch covers for containerships. The advanced design uses SPS panels to replace the stiffened steel plating of a conventional hatch cover, eliminating all secondary stiffeners and greatly simplifying the structure. SPS hatch covers are functionally identical to the standard steel items, but possess greatly enhanced strength and resistance to impact and puncture from dropped or mishandled containers.

Hatch covers are obvious applications for SPS, not just for containerships, but also for bulk carriers and general cargo vessels. The simplified structure and inherent puncture resistance reduce maintenance costs, enhance lifetime performance and minimise the risk of costly delays due to accidental damage.

> IE designed a Type C Tanker for the Rhine River to meet ADNR and Germanischer Lloyd requirements. A mock-up structure was built in Hanover, Germany. This verified the construction and assembly processes, confirmed the construction quality standards and demonstrated the simplicity resulting from the use of SPS.

> MV “Bow Hunter” was one of the first vessels built by DSME. In 2011 DSME converted her into a floating company museum or “Storium”. DSME selected SPS panels for the newly installed decks to provide high performance control of noise and vibration and allow fast installation in confined working areas.

“In the conversion of MV Bow Hunter,

SPS gives installation and performance

benefits over a normal steel deck. The

innovation contained in SPS technology

captures the spirit of DSME and is

symbolic of DSME’s past and future.”

ManSoo Kim, Vice President, Head of Hull Design, DSME

Page 97: Download the SPS project book

12

SPS stadia

SPS Terraces save weight, time and cost in the construction of high quality stadia and arenas:

> SPS weigh less than 25% of concrete terraces. This enables a25% reduction in structural frame weights and 15% lighterfoundations

> SPS can be erected quickly, with 6-10 times more units beingtransported per truck and 3-4 times more units lifted perhoist than concrete alternatives

> Project cost savings of over 20% are achieved using SPS

> At the end of a venue’s life SPS can be readily demounted andreused on future venues

Safe non-slip surface

Connected in factory, or on site, to create integrated bank

Integrated steel rises

High quality coated faces

Page 98: Download the SPS project book

13

> SPS stadia terraces delivered a lightweight, long span, cantilevered bowl with minimal supporting columns – allowing more of the audience to be closer to the stage and maximizing the venue’s capacity and versatility.

Winner of BEX 2009 International Award for Best Use of Architectural or Structural Design

“We designed the arena bowl with

SPS in mind; nothing else could

have delivered the solution we

wanted.

I am delighted with the quality of finish

we have achieved using SPS

– they are the future.”

Damon Lavelle, Architect, Populous

> The LG Arena at The NEC, Birmingham has been redesigned, enlarged and completely refitted. SPS was used to create 8,000 permanent seats, of the total 16,000 capacity at the new venue.

“Using SPS helped to ensure that our new

arena was ready for the start of our

season, the Horse of the Year show, in October

and has created more space for concessions

and services under the new stands.”

Phil Mead, Managing Director of Arenas at The NEC Group

> Zaha Hadid’s Aquatics Centre for the London 2012 Olympics is the iconic structure of the games. SPS helped to deliver a uniquely demountable structure with the feel of a permanent venue with the opportunity for the whole structure to be resold after the games. A breakthrough in sustainable construction and a valuable legacy.

“If it was up to me, I’d choose SPS over

prefab concrete slabs every time. We

threw them up onto the steelwork much

faster than I’d first imagined possible,

and with a schedule as tight and

important as the Aquatics Centre build,

that makes all the difference.”

Steve Burley, Site Manager, Watson Steel Structures

Page 99: Download the SPS project book

14

SPS buildings

SPS enable significantly lighter structures with shorter, safer construction programmes.

> SPS weighs one quarter of comparable concrete flooring; theyare supported by lighter frames and foundations

> The panels are delivered to site finished to the highesttolerances ready to be assembled using standard steelworking practices

> Using SPS reduces construction schedules. Panels areinstalled quickly and predictably with panels of SPS beinglifted at the same time as the structural frame

> They provide 100% working load capacity as soon as theyare fixed in position and with no wet-work above ground level

work can start earlier and be completed faster

> SPS reduce health and safety risks by providing increasedprotection against falling objects and minimizing a range ofon site hazards

> Using SPS reduces contractors’ costs associated with timeon site and project risk

> SPS provide increased revenue for developers from earlierproject completion and extra floors on tall buildings

A full-scale 9m x 9m bay, fitted out with M&E, suspended ceilings and raised access floors has been fully tested at the UK Building Research Establishment (BRE). Inset picture shows Techniks ceramic raised floor system installed on SPS panels

Page 100: Download the SPS project book

15

Residential Building

Weston-super-Mare Grand Pier

> It is proposed to use SPS Floors on a 27 storey residential building in London.

“SPS panel system is the step change

we have been waiting for in off-site

construction. The system finally enables

us to bring precision manufacturing and

assembly to the site eliminating multiple

trades to deliver the building faster and

ultimately cheaper than conventional

techniques.”

David Glover, Global Head of Building Engineering, AECOM

> SPS has been used to rebuild the main structural floor of the Grand Pier in Weston-super-Mare. The pier, which was gutted by fire in 2008, was being rebuilt on the existing 105 year old structure and extends 400m into the Bristol Channel.

The picture on the right, taken at low tide, shows work in progress on the superstructure and the SPS deck about 75% complete. Note the crane barge alongside.

“SPS were key to meeting the

challenges of rebuilding on an old and

damaged structure with limitations on

weight, restricted access and a

demanding schedule. Intelligent Engineering has gone the extra mile in supporting

us from design to installation to ensure the success of the project.”

Andy McGoldrick, Project Director, John Sisk & Son Ltd

> SPS formed part of the improvements to Carnegie Hall, which is a 120 year old heritage structure and a New York City landmark. They were used for the renovation of a mezzanine floor in the South Tower and floor additions in the North Tower, which resulted in minimal disruption to the music hall, provision of immediate load capacity on installation and an easy installation in a site restricted area.

For the South Tower, the SPS forms office space that is suspended at mid-height between top and bottom flanges of an existing truss. In the North Tower, the floors add lounge areas to existing rehearsal halls.

Page 101: Download the SPS project book

16

SPS bridges

SPS is much lighter and less complicated than conventional concrete and steel structures. New construction, replacement and repair can be carried out much faster and with less disruption. SPS Bridge Decks are less vulnerable to fatigue and corrosion and have a longer service life.

Installation of new SPS Bridge Deck

New bridge decks

Prefabricated SPS panels make new bridges more economic. As an alternative to concrete decks, the 70% lighter, prefabricated SPS enable shallower, longer, lighter spans to be constructed faster and with less disruption to traffic. As an alternative to orthotropic steel decks SPS offer a lighter solution with simple surfaces that are much less prone to fatigue and corrosion.

Replacement decks

The replacement of old concrete decks with SPS can take days rather than weeks and bridges can often remain operational

throughout the procedure. Load restrictions can be removed and extra lanes added without the need for additional substructure.

Deck reinstatement

SPS is used to reinstate or strengthen steel bridge decks. This process does not require the removal of existing structure and is therefore much faster and less disruptive. SPS improves the distribution of wheel loads, decreasing deflections and increasing the life of the bridge.

Page 102: Download the SPS project book

17

Schönwasserpark Bridge

> Prefabricated SPS panels were used to replace concrete panels in four pedestrian bridges across the M6 motorway in England. The installation process required the motorway to be closed for just a few hours overnight, keeping disruption to a minimum.

“The Highways Agency is always on

the lookout for new ways to get the job

done and SPS is one of them.”

Peter Harner, Project Manager, UK Highways Agency

> The Schönwasserpark Bridge is an orthotropic steel bridge spanning a busy state motorway in Germany. Using SPS to strengthen the bridge deck ensured the existing structure was retained and additional work on the superstructure was avoided. Disruption to traffic was kept to a minimum and the whole bridge deck was reinstated in just five weeks.

“SPS Overlay technology has proved

to be an effective refurbishment

measure to make steel deck bridges

fit for modern traffic.”

Prof. Dr.-Ing Markus Feldmann, RWTH Aachen University

> The Dawson Bridge is a 100 year old, 5 span truss bridge that forms an important link across the North Saskatchewan River running through the centre of Edmonton, Canada. SPS were selected as the alternative that offered the simplest, quickest installation that minimized truss strengthening and provided another 100 years life for the bridge deck.

“SPS allowed the entire project to

be completed months faster and

millions of dollars less

expensively than a traditional

concrete deck.”

Jeff DiBattista, Principal, Dialog

Page 103: Download the SPS project book

18

protection and defence

SPS can be used in military and civil applications to reduce vulnerability and to increase survivability and safety. SPS is a lightweight alternative to stiffened plate and reinforced concrete with built-in fire protection and vibration damping as well as energy absorbing properties that enhance the blast, ballistics and impact resistance of structures.

Blast tests carried out at US Navy’s Naval Surface Warfare Center (NSWC) demonstrate how SPS absorbs more blast energy, reduces risk of premature rupture and limits fragment penetration. The conventional steel panel (left) is ruptured by the blast while the SPS panel (right) absorbs the energy and deforms without rupture.

Tests carried out at the UK MoD’s Defence Evaluation Research Agency (QinetiQ) showed that SPS stops projectiles at shorter strike ranges and higher angles of attack. SPS reduced risk of penetration by 75% compared with equivalent all steel structure.

The benefits of using SPS include:

> Lighter, stiffer, simpler structures with improved fatigue andcorrosion resistance, more internal space and permanentlysmooth external surfaces

> Superior blast protection, transferring less energy to supportingstructures and reducing risk of rupture

> Increased protection from projectiles at shorter ranges andhigher angles of attack

> Built-in fire protection

> Reduced structure-borne noise and vibration signature

> Greater resistance to high energy impacts including groundings,collisions and falling objects

Example applications:

SPS protection can be incorporated into new designs, prefabricated for on-site installation or retrofitted as an SPS Overlay to existing structures.

> New build designs automatically incorporate full range ofprotection benefits wherever SPS is used as structural material

> Optimised designs where structures have specific requirements,e.g. high point loads on flight decks; reduced vulnerability onamphibious craft

> Retrofitted blast belt applied as additional protection above andbelow water-line or to provide impact protection for side shellsof offshore structures

> Blast walls in refineries or vulnerable public buildings

> Crash decks (during construction) and permanent blast andimpact resistant flooring structures

Page 104: Download the SPS project book

SPS for pontoons of drilling rig is able to absorb impact of 3 tonne drill collar falling from height of 37 metres without rupture.

SPS impact test dropping 2 tonne rocks from 3 metres onto a section of SPS deck. SPS sustained no damage; the all-steel equivalent was destroyed.

SPS impact test - sharp point-load on a 2 tonne sled striking SPS plate at 5m per second. SPS sustained minor indentation; the all-steel alternative was punctured through.

Tests carried out at the Danish Institute of Fire Technology (DIFT) show un-insulated steel structure red hot (left) after 60 minutes at 945°C vs. maximum temperature for SPS of 38°C (note the bare feet).

CASE STUDY SPS Citadel Access Protection

> Citadel protection is a proven concept that has a successful track record for protecting ships and crew from piracy. The internationally recognized Best Management Practice to Deter Piracy in the Gulf of Aden and off the Coast of Somalia recommends that a “Citadel is designated and lock-down procedures rehearsed to delay access to ship controls and buy time”.

SPS Citadel Access Protection delays and deters entry to the safe refuge. Once installed, the SPS barrier creates a detail free surface that can be rapidly deployed within 2 minutes. When closed, the SPS panels create an extremely strong barrier that can withstand far higher impact loads than equivalent steel structures with superb blast protection against ballistics and shrapnel damage.

19

Page 105: Download the SPS project book

20

sustainability

SPS delivers a more sustainable, long term alternative to conventional steel and concrete when measured against key indicators including environmental, social and economic impact.

The steel and PU components of SPS can be readily recycled into high grade materials

SPS products offer important benefits in sustainability and the reduction of environmental risk in the construction and shipbuilding industries. These include increased structural efficiency and reduced use of materials and resources in construction. In service SPS structures are less vulnerable to damage, require less maintenance and have a longer service-life. SPS is easily recycled and, unusually for heavy engineering materials, SPS is easily reused. This means that SPS structures can also yield lower through-life emissions and a smaller carbon footprint than conventional concrete and steel structures.

> Potential for 100% reuse or recycling of all SPS materials

> Reduction in other construction materials and resources

> Off-site prefabrication reduces on-site disruption

> Reduced maintenance and increased service-life

> Increased safety and reduced environmental risk

Shipbuilding

SPS can improve sustainability and reduce the environmental impact of the construction and operation of ships in several ways. SPS requires less steel, welding and coatings to produce. SPS structures are less susceptible to fatigue and corrosion thereby increasing service-life. They are less vulnerable to accidental and extreme impact events thereby reducing the risk of environmental damage. SPS designs have the potential to allow for increased cargo volumes, resulting in proportionally fewer vessel movements, less fuel consumed and reduced risk.

Page 106: Download the SPS project book

21

SPS panels are bolted into position and can be as easily unbolted for reuse at the end of a structure’s life

Construction

Incorporating SPS in a building can improve its sustainability performance and rating with BREEAM and LEED. SPS have been developed for 100% reuse. At the end of a structure’s life SPS can be demounted and, unlike comparable concrete products, can be reused in new buildings without any additional processing. Alternatively at the end of their life the SPS panels can be recycled into new SPS and other high grade materials.

An independent study completed by Decarbonize concluded that reusing SPS can reduce the carbon footprint of a whole building by 10-20% compared with using concrete.

Using SPS also contributes to:

> 25% reduction in the overall weight of materials used ina structure

> 70% reduction in truck movements

> A reduction in site waste

> Safer on-site working practices resulting in fewer accidentsand injuries

Building with SPS can reduce truck movements by 70%

Reinstatement and Conversion

In the repair or strengthening of ships and bridges, SPS incorporates – rather than cutting out and replacing – the existing structure, thereby reducing the quantity of new steel used by up to 75%. The process uses much less welding and is much less labour intensive in what are typically hazardous conditions. SPS requires a fraction of the time needed for conventional repairs and, in the case of bridges, can be completed with only partial closure, thereby substantially reducing the disruption to traffic.

Ongoing initiatives

IE continues to explore opportunities to further develop the sustainability benefits of SPS, including:

> Minimizing the full life emissions of a building

> Working with architects and engineers to design structuresthat capitalise on the potential to reuse SPS products

> Working with suppliers to maximize the recycled content in allSPS products and applications

Page 107: Download the SPS project book

22

Industry partners SPS technology has been developed and commercialised in collaboration with leading designers, fabricators and regulatory authorities in the maritime and civil engineering sectors. These long term partners provide the platform for SPS increasing its profits, activities and projects in many international markets.

The continuing support of these parties is secured through partnership agreements and a network of licensees. These agreements deliver market access and capacity for the fabrication of SPS plates, in addition to technical expertise and the reliability of execution of SPS projects in the field. SPS licensees ensure that both current and future SPS patents are controlled by IE and are available to all licensees. This network of strategic partnerships is being extended by application and by region.

SPS in Construction

IE is working with market leading architects, engineers and specialists including:

BASF

IE and BASF jointly developed the core material for the SPS technology. An exclusive agreement provides for continuing collaboration in research and development and the joint prosecution and maintenance of intellectual property rights.

SPS Partners and Licensees

IE has licensed a number of service providers to deliver SPS, while continuing to maintain an IE field team to support the execution of specialist projects.

These include:

> ASOM Pte Ltd> BalconIE Ltd> Bourne Group> CTSOM Ltd> Dongkuk S & C> Goldwave Steel> Samaras Group

> SEH Engineering GmbH> SRC Group AS> Supreme Group> Walters Group Inc> TSG Marine

> AECOM> AKT II> Anderson Green> Angus Meek> Arup> Atkins> BIGR> Bovis Lend Lease> Broadway Malyan> Buro Happold> Carillion> Capita Symons> Dialog> DLA> DSME> FCB studios> Franklin Sports business> Foster + Partners> Gardiner and Theobald> HaeAhn> HKS> HOK> Hoffman Construction, Inc.> IU + Bibliowicz> John Sisk & Sons> KSS

> KSI> Laing O’Rourke> MACE Group Ltd.> MKA> Mott MacDonald> Populous> Raymond Smith PTR> Robert Silman Associates> Rogers Stirk Harbour and PTR> Rossetti> Severfield> Structural Engineer Asso. LLC> The Sadler Group> Thornton Tomasetti> Tishman> TP bennett> Uzun+Case, LLC> Wakerfield Beasley & Assoc.> Walls> Walter P Moore> Wates> Waterman Group> Wilson Owens Owens> Wier Boerner Allin> WSP

SPS Customers

SPS is used by market leading companies:

> Balfour Beatty plc> BP P.L.C.> Construct Ltd.> DSME Co., Ltd.> ES Global Ltd.> Exxon Mobil Corp.> Fisher Construction, Inc.> HENC Co.> Hoffman Construction Co.> Hunt Construction Group> John Sisk & Sons Ltd.> MACE Group Ltd.> Manchester Airport Group> MAPSSS> MPB Structures Ltd.

> Paul Y – Yau Lee J.V.> P&O Cruises> Petrobas> Prosafe SE> SBM Construction> Schuff Steel Co.> Severfield plc> Shell plc> Siemens AG> Starbulk S.A.> Stena Line Co.> Supreme Group> Southern Bleacher Co.> Wates Group> Walter Watson Steel

Page 108: Download the SPS project book

23

SPS was invented by Dr Stephen Kennedy following years of primary research in the field of ice-strengthened structures. Intelligent Engineering was established to develop and commercialise SPS technology and now licensees the use of SPS to market leaders by application and by region.

IE’s team of over 60 professional staff work from offices in Europe, North America and Asia. Supervised by IE holdings Ltd, the management team is supported by an operating board of directors and Advisory Board made up of leading experts and businessmen.

Page 109: Download the SPS project book

SPS panel in production

Page 110: Download the SPS project book

Intelligent Engineering (UK) Ltd

Shire House, West Common Gerrards Cross Buckinghamshire SL9 7QN United Kingdom Tel: +44 1753 890575 Fax: +44 1753 899056

[email protected] www.ie-sps.com

SPS is a registered trademark of Intelligent Engineering

PO Box 83 Ordnance House 31 Pier Road St Helier Jersey JE4 8PW