Douglas R. Failing, P.E. Executive Director, Highway Program LA Metro’s Highway Program May 10, 2013 Construction Management Association of America (CMAA)

Transcript of Douglas R. Failing, P.E. Executive Director, Highway Program LA Metro’s Highway Program LA...

Page 1: Douglas R. Failing, P.E. Executive Director, Highway Program LA Metro’s Highway Program LA Metro’s Highway Program May 10, 2013 Construction Management.

Douglas R. Failing, P.E. Executive Director, Highway Program

LA Metro’sHighway Program

LA Metro’sHighway Program

May 10, 2013

Construction Management Association of America (CMAA)

Page 2: Douglas R. Failing, P.E. Executive Director, Highway Program LA Metro’s Highway Program LA Metro’s Highway Program May 10, 2013 Construction Management.

Highway ProjectsHighway Projects

2

Page 3: Douglas R. Failing, P.E. Executive Director, Highway Program LA Metro’s Highway Program LA Metro’s Highway Program May 10, 2013 Construction Management.

3Possible problem Major issue!On targetOK

State Route 710 NorthState Route 710 North

Construction CompleteConstruction CompleteCurrent

2029Current

2029Forecast

2029Forecast

2029

SCHEDULESCHEDULE

Alternatives Analysis Fall 2012Draft EIR/EIS Spring 2014Public Hearing Spring 2014Final EIR/EIS Summer 2015Record of Decision Summer 2015

Total Cost ($ mil.)Total Cost ($ mil.)

Current$780

Current$780

Forecast$2.6 – 5.4B*

Forecast$2.6 – 5.4B*

BUDGETBUDGET

Secured Funds: Measure R - $780MUnsecured Funds: $1.82B – $4.62B*Potential P3 Opportunity

!

* Denotes a range of cost for several higher cost alternatives

OK

Page 4: Douglas R. Failing, P.E. Executive Director, Highway Program LA Metro’s Highway Program LA Metro’s Highway Program May 10, 2013 Construction Management.

• Alternatives Analysis – completed in Dec. 2012• http://www.dot.ca.gov/dist07/resources/envdocs/docs/710s

tudy/

• Alternatives:– No Build– Transportation System Management/Transportation

Demand Management (TSM/TDM) – Bus Rapid Transit (BRT)– Light Rail Transit (LRT)– Freeway Tunnel

4

State Route 710 NorthState Route 710 North

Page 5: Douglas R. Failing, P.E. Executive Director, Highway Program LA Metro’s Highway Program LA Metro’s Highway Program May 10, 2013 Construction Management.

State Route 710 North Build State Route 710 North Build AlternativesAlternatives BRT LRT Freeway Tunnel*

5

Page 6: Douglas R. Failing, P.E. Executive Director, Highway Program LA Metro’s Highway Program LA Metro’s Highway Program May 10, 2013 Construction Management.

6Possible problem Major issue!On targetOK

Cost

Interstate 710 South EIR/EIS*Interstate 710 South EIR/EIS*

Construction CompleteConstruction CompleteCurrent

2028Current

2028Forecast

2028Forecast

2028

SCHEDULESCHEDULE

Draft REIR/REIS 2014 2014 Public Hearing 2014 2014 Final REIR/REIS 2015 2015 Record of Decision 2015 2015

Multiple Early Action Study Projects with various schedules

Total Cost ($ mil.)Total Cost ($ mil.)

Current$395

Current$395

Forecast$6.75B

Forecast$6.75B

BUDGETBUDGET

Secured Funds: Measure R - $395MUnsecured Funds: $6.36B – TBD*Potential P3 Opportunity

!

Begin Construction 2020 2021

*Some of these funds will be utilized for I-710 Early Action Projects

!

Page 7: Douglas R. Failing, P.E. Executive Director, Highway Program LA Metro’s Highway Program LA Metro’s Highway Program May 10, 2013 Construction Management.

7Possible problem Major issue!On targetOK

I-710 Early Action ProjectsI-710 Early Action Projects

Total Cost ($ mil.)Total Cost ($ mil.)

Current$26.8

Current$26.8

Forecast$26.8

Forecast$26.8

BUDGETBUDGET

SCHEDULESCHEDULE

various (see below)

Completed 0 $ 000 N/AOngoing 1 $10,400 2013Future 4 $16,400 2018

TOTAL* 5 $26,800 2030

#APPR. PROJECTSBUDGET

(000’S) COMPLETION

*Multiple projects to be programmed with various schedules through 2030

Page 8: Douglas R. Failing, P.E. Executive Director, Highway Program LA Metro’s Highway Program LA Metro’s Highway Program May 10, 2013 Construction Management.

8Possible problem Major issue!On targetOK

Cost

High Desert Corridor (Environmental)High Desert Corridor (Environmental)

Total Cost ($ mil.)Total Cost ($ mil.)

Current$65

Current$65

Forecast$65

Forecast$65

BUDGETBUDGET

Funds include: STIP (GF), Measure R, Measure I, and federal earmarks• Scope includes Project Approval and Environmental Document (PA/ED) only

Environmental Document CompleteEnvironmental Document Complete

Current2014

Current2014

Forecast2014

Forecast2014

SCHEDULESCHEDULE

Draft ED CirculationPublic Hearing Final EDRecord of Decision

2013201320142014

OK

Page 9: Douglas R. Failing, P.E. Executive Director, Highway Program LA Metro’s Highway Program LA Metro’s Highway Program May 10, 2013 Construction Management.

9Possible problem Major issue!On targetOK

Total Cost ($ mil.)Total Cost ($ mil.)

Current$700

Current$700

Forecast$700

Forecast$700

BUDGETBUDGET

Funds include: Measure R, Prop C 25%, Toll Revenues and SHOPP

OK

PROJECTS UNDER CONSIDERATION:• I-5 North Capacity Enhancements (Phase 2A: Truck Lane + HOV from SR-14 to Parker Rd.)•I-5 Pavement Rehabilitation • SR-71 Expressway Gap Closure (from I-10 to Mission Blvd.)• SR-71 Expressway Gap Closure (from Mission Blvd. to Rio Rancho Rd.)• Soundwall Package 10: I-210 Pasadena and Arcadia• Soundwall Package 11: I-405 & SR 170 in Los Angeles

Construction CompleteConstruction CompleteCurrent

2030Current

2030Forecast

2019Forecast

2019

SCHEDULESCHEDULE

RFQRFP Financial CloseConstruction Complete

OK

2013 2013/14 2014/15 2019

2013 2013/14 2014/15 2019

Accelerated Regional Transportation Improvements Accelerated Regional Transportation Improvements (ARTI) Project(ARTI) Project

Page 10: Douglas R. Failing, P.E. Executive Director, Highway Program LA Metro’s Highway Program LA Metro’s Highway Program May 10, 2013 Construction Management.

10Possible problem Major issue!On targetOK

Construction CompleteConstruction CompleteCurrent

2026Current

2026Forecast

2026Forecast

2026

SCHEDULESCHEDULEOK

• Multiple projects to be programmed with various schedules through 2030

• Feasibility Study 2012

• Project Study Report 2013

• Preliminary Engineering 2014-2015

Total Cost ($ mil.)Total Cost ($ mil.)

Current$590M*Current$590M*

Forecast$590M*

Forecast$590M*

BUDGETBUDGET

Secured Funds: Measure R - $590MUnsecured Funds: TBD

*Denotes current secure funding and not expected to cover Feasibility Study improvement needs. Project costs to be determined post Feasibility Study

I-605 Corridor “Hot Spot” InterchangesI-605 Corridor “Hot Spot” Interchanges

Page 11: Douglas R. Failing, P.E. Executive Director, Highway Program LA Metro’s Highway Program LA Metro’s Highway Program May 10, 2013 Construction Management.

1111Possible problem Major issue!On targetOK

Completed 1 $ 575 N/AOngoing 7 $ 15,573 2018Future 32 $ 40,852 2020

TOTAL 40 $57,000 2020

Measure R provides $170.0 Million over 30 years of which $57 Million has been programmed in the Subregion for FYs 2010-2016. Ongoing is defined as projects with executed Funding Agreements. Future is defined as projects with future phases of existing Projects or first years funding of a Project is beyond FY 2013.

Total Cost ($ mil.)Total Cost ($ mil.)

Current$32.4

Current$32.4

Forecast$170

Forecast$170

BUDGETBUDGET SCHEDULESCHEDULE

various (see below)

#APPROVED PROJECTS

BUDGET (000’S)

COMPLETION

Arroyo Verdugo COG Measure R Operational Arroyo Verdugo COG Measure R Operational Improvements ProgramImprovements Program

Page 12: Douglas R. Failing, P.E. Executive Director, Highway Program LA Metro’s Highway Program LA Metro’s Highway Program May 10, 2013 Construction Management.

1212Possible problem Major issue!On targetOK

Completed 0 $ 0 N/AOngoing 9 $ 25,661 2018Future 7 $ 66,139 2020

TOTAL 16 $91,800 2020

Measure R provides $175.0 M over 30 years, $93.8 Million has been programmed for the Subregion by the Metro Board for FY’s 2010-16. Ongoing is defined as projects with executed Funding Agreements. Future is defined as projects with future phases of existing Projects or first years funding of a Project is beyond FY 2013.

Total Cost ($ mil.)Total Cost ($ mil.)

Current$91.8

Current$91.8

Forecast$175

Forecast$175

BUDGETBUDGET SCHEDULESCHEDULEvarious (see below)

COMPLETIONBUDGET

(000’S)#APPROVED PROJECTS

Las Virgenes/Malibu COG Measure R Operational Las Virgenes/Malibu COG Measure R Operational Improvements ProgramImprovements Program

Page 13: Douglas R. Failing, P.E. Executive Director, Highway Program LA Metro’s Highway Program LA Metro’s Highway Program May 10, 2013 Construction Management.

1313Possible problem Major issue!On targetOK

COG Admin/Development N/A $ 6,754 2022Contingency/Reserves N/A $ 25,077 2019Completed 3 $ 2,152 2012Ongoing 18 $ 63,351 2022Future 36 $ 94,806 2022

TOTAL 57 $192,140 2022

Measure R provides $906.0 Million over 30 years of which $192.1 Million has been programmed in the Subregion for FYs 2012-2019. Ongoing is defined as projects with executed Funding Agreements. Future is defined as projects with future phases of existing Projects or first years funding of a Project is beyond FY 2013.

Total Cost ($ mil.)Total Cost ($ mil.)

Current$176.5

Current$176.5

Forecast$906

Forecast$906

BUDGETBUDGET SCHEDULESCHEDULEvarious (see below)

#APPROVED PROJECTS

BUDGET (000’S)

COMPLETION

South Bay (I-405, I-110, I-105 and SR-91) Ramp and South Bay (I-405, I-110, I-105 and SR-91) Ramp and Interchange Operational Improvements ProgramInterchange Operational Improvements Program

Page 14: Douglas R. Failing, P.E. Executive Director, Highway Program LA Metro’s Highway Program LA Metro’s Highway Program May 10, 2013 Construction Management.

Upcoming Procurements Upcoming Procurements A&E Professional Services, Motorist Services & P3 ServicesA&E Professional Services, Motorist Services & P3 Services

14

http://www.metro.net/projects/pm-dept/(Highway Program Look Ahead Reports)

Page 15: Douglas R. Failing, P.E. Executive Director, Highway Program LA Metro’s Highway Program LA Metro’s Highway Program May 10, 2013 Construction Management.

Highway Projects in ConstructionHighway Projects in Construction

15

http://www.metro.net/projects/pm-dept/(Highway Program Look Ahead Reports)

Page 16: Douglas R. Failing, P.E. Executive Director, Highway Program LA Metro’s Highway Program LA Metro’s Highway Program May 10, 2013 Construction Management.

Questions?Questions?