DORE & TOTLEY RAILWAY STATION Consultation Leaflet.pdf · The current parking facilities at Dore &...
Transcript of DORE & TOTLEY RAILWAY STATION Consultation Leaflet.pdf · The current parking facilities at Dore &...
This leaflet provides you with information about South Yorkshire Passenger Transport Executive’s (SYPTE) proposals to build a Park & Ride facility at Dore & Totley Railway Station in Sheffield.
SYPTE is currently trying to secure funds to deliver this project. As part of this process we are progressing the design and consultation to ensure the park and ride can be delivered as quickly as possible when funding is confirmed.
Current arrangements
The current parking facilities at Dore & Totley Railway Station are inadequate and surrounding residential streets are crowded with parked cars which cause problems for local people. This causes traffic congestion and is not a situation which pleases either passengers wishing to use the station or people who live close by.
The story so far...
SYPTE purchased the site adjacent to the station in April 2010 with the desire to build a Park & Ride facility. In June 2010 the site was fenced off and the buildings on the site were demolished. It was not possible to allow temporary parking due to health and safety reasons at the site.
INTRODUCTION CONSULTATION EVENT BACKGROUND
To meet the project team and to ask questions about the proposals, SYPTE staff will be available at a drop in session on 20 January 2011.
Anyone who cannot attend and wishes to provide feedback, please complete the details on the back of this leaflet.
Dore & Totley Railway Station Park & Ride Consultation event.Thursday 20 January 2011 2pm to 7.30pm Abbeydale Sports Club, Abbeydale Road, Sheffield, S17 3LJ
Planning permission is required for the Park & Ride and through consultation, people are invited to provide feedback and comments on the outline proposals.
Following the review of all the information recieved during the four week consultation period a submission to Sheffield City Council will be made for planning permission in March 2011.
LATEST NEWS
Leaflets are available from:
• Totley Library• Post Office, Dore Village• Dore Methodist Church• Dore Parish Church• Dore Medical Centre, Dore Road• Abbeydale Sports Club• Other smaller outlets in the local area
1. New entrance to the car park and railway station.
2. One way system around the car park.
3. 139 car parking spaces.
4. Blue badge parking facilities.
5. Pedestrian access point to the platform is maintained in current location.
6. Existing trees will be removed. A boundary fence/treatment will be incorporated as part of the design.
7. Proposal for new location for the bus stop in order that a safe pedestrian crossing facility can be provided.
8. Pedestrian crossing facility to be provided.
9. Designated drop off/pick up point including rail replacement services.
10. Entrance to vehicles will be closed.
11. Access to adjacent properties.
12. Covered cycle shelter.
13. Restrictions on Abbeydale Road South prohibiting parking, waiting and loading.
7
4
10
9
8
12
3
6
2
1
13
11
THE OUTLINE PROPOSALS
DORE STATION
DROP OFF5
Name
Address
Postcode
Telephone
Do you support the proposals to build a Park & Ride facility at Dore & Totley Railway Station?
Yes No use the space to expand if you wish.
Do you support the design and layout of the proposed Park & Ride facility at Dore & Totley Railway Station?
Yes No use the space to expand if you wish.
General comments on the proposals
Thank you for your comments about the proposals. SYPTE will continue to keep local people updated on the progress of this scheme.
• January 2011 Public Consultation (10 January - 6 February 2011)
• March 2011 Planning application submitted to Sheffield City Council
• Summer 2011 Subject to funding work could begin on site
If you have any question or comments, please fill in the form opposite or contact us on using the details below.
Gillian PalmerSouth Yorkshire Passenger Transport ExecutivePO Box 801SheffieldS2 5YT
Or email: [email protected]
For further details on the project log on to sypte.co.uk
THE NEXT STEPS FEEDBACK FORM
12-10-1050
Please send your completed feedback forms to:
Gillian PalmerSouth Yorkshire Passenger Transport ExecutivePO Box 801SheffieldS2 5YT
If you have any question or comments please email: [email protected] or log on to sypte.co.uk
DORE & TOTLEY RAILWAY STATIONPark & Ride public consultation proposals – January 2011