Document of
The World Bank
Report No: ICR00003433
IMPLEMENTATION COMPLETION AND RESULTS REPORT
(IDA-41380, IDA-44290, IDA-49060)
ON A
CREDIT IN THE AMOUNT OF SDR 69.1 MILLION
($100 MILLION EQUIVALENT)
CREDIT IN THE AMOUNT OF SDR 59.6 MILLION
($98.1 MILLION EQUIVALENT)
CREDIT IN THE AMOUNT OF SDR 63.6 MILLION
($100 MILLION EQUIVALENT)
TO THE
DEMOCRATIC SOCIALIST REPUBLIC OF SRI LANKA
FOR A
ROAD SECTOR ASSISTANCE PROJECT
June 22, 2016
Transport and ICT Global Practice
Sustainable Development
South Asia Region
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
CURRENCY EQUIVALENTS (Exchange Rate Effective as of February 21, 2016)
Currency Unit = Sri Lanka Rupee
LKR 1.00 = $0.00712824
$1.00 = LKR 140.2871
FISCAL YEAR
January 1 – December 31
ABBREVIATIONS AND ACRONYMS
$ All dollars are in United States dollars unless otherwise indicated
ADB Asian Development Bank
AF Additional Financing
AM Aide-memoire
CAS Country Assistance Strategy
CPS Country Partnership Strategy
DO Development Objective
EIRR Economic internal rate of return
EMP Environmental Management Plan
ERR Economic rate of return
FM Financial management
GoSL Government of Sri Lanka
HDM Highway Development and Management Model
ICR Implementation Completion Report
IRI International roughness index
ISR Implementation Status Report
JICA Japan International Cooperation Agency
MoF Ministry of Finance
MoH Ministry of Highways
MoT Ministry of Transport
M&E Monitoring and evaluation
MTR Midterm Review
NPV Net present value
NRMP National Road Master Plan
NWSDB National Water and Sewage Development Board
PAD Project Appraisal Document
PDO Project Development Objective
PMU Project Management Unit
RAMS Road Assets Management System
RDA Road Development Authority
RMTF Road Maintenance Trust Fund
RSAP Road Sector Assistance Project
TAC Technical Advisory Committee
VoC Vehicle operating cost
SRI LANKA
ROAD SECTOR ASSISTANCE PROJECT
CONTENTS
Data Sheet
A. Basic Information
B. Key Dates
C. Ratings Summary
D. Sector and Theme Codes
E. Bank Staff
F. Results Framework Analysis
G. Ratings of Project Performance in ISRs
H. Restructuring
I. Disbursement Graph
1. Project Context, Development Objectives and Design ............................................... 1
2. Key Factors Affecting Implementation and Outcomes .............................................. 8
3. Assessment of Outcomes .......................................................................................... 17
4. Assessment of Risk to Development Outcome ......................................................... 26
5. Assessment of Bank and Borrower Performance ..................................................... 27
6. Lessons Learned ....................................................................................................... 30
7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners .......... 31
Annex 1. Project Costs and Financing .......................................................................... 33
Annex 2. Outputs by Component ................................................................................. 35
Annex 3. Economic and Financial Analysis ................................................................. 37
Annex 4. Bank Lending and Implementation Support/Supervision Processes ............ 42
Annex 5. Beneficiary Survey Results ........................................................................... 44
Annex 6. Stakeholder Workshop Report and Results ................................................... 45
Annex 7. Summary of Borrower's ICR and/or Comments on Draft ICR ..................... 49
Annex 8. Comments of Cofinanciers and Other Partners/Stakeholders ....................... 62
Annex 9. List of Supporting Documents ...................................................................... 63
Annex 10. QAG Report ……………………………………………………………….64
Annex 11. MAP ……………………………………………………………………….74
Regional Vice President: Annette Dixon
Country Director: Francoise Clottes
Senior Global Practice Director: Pierre Guislain
Practice Manager: Karla Gonzalez Carvajal
Task Team Leader:
ICR Team Leader:
Amali Rajapaksa
Radia Benamghar
- i -
DATA SHEET
SRI LANKA
ROAD SECTOR ASSISTANCE PROJECT
A. Basic Information
Country: Sri Lanka Project Name: SL - Road Sector
Assistance Project
Project ID: P086411 Credit Number(s):
IDA-41380
IDA-44290
IDA-49060
ICR Date: 06/22/2016 ICR Type: Core ICR
Lending Instrument: Specific Investment Loan Borrower: Democratic Socialist
Republic of Sri Lanka
Original Total
Commitment: XDR 69.10 million Disbursed Amount: XDR 180.16 million
Revised Amount: XDR 180.16 million Cancelled amount XDR 12.14 million
Environmental Category: B
Implementing Agencies:
Ministry of Ports and Highways through Road Development Authority
Ministry of Provincial Council and Local Government
Ministry of Finance and Planning
Cofinanciers and Other External Partners:
B. Key Dates
Process Date Process Original Date Revised / Actual
Date(s)
Concept Review: 12/18/2003 Effectiveness 03/16/2006 03/16/2006
Appraisal: 09/26/2005 Restructuring(s):
06/23/2008
03/15/2011
04/08/2013
09/23/2014
06/30/2015
06/23/2008
03/15/2011
04/08/2013
09/23/2014
06/30/2015
Approval: 12/15/2005 Midterm Review: 01/12/2009 03/02/2009
Closing: 09/30/2011 06/30/2015
C. Ratings Summary
C.1 Performance Rating by ICR
Outcomes: Moderately Satisfactory
Risk to Development Outcome: High
Bank Performance: Moderately Satisfactory
- ii -
Borrower Performance: Moderately Satisfactory
C.2 Detailed Ratings of Bank and Borrower Performance (by ICR)
Bank Ratings Borrower Ratings
Quality at Entry: Moderately Satisfactory Government: Moderately Satisfactory
Quality of Supervision: Moderately Satisfactory Implementing
Agency/Agencies: Moderately Satisfactory
Overall Bank
Performance: Moderately Satisfactory
Overall Borrower
Performance: Moderately Satisfactory
C.3 Quality at Entry and Implementation Performance Indicators
Implementation
Performance Indicators
QAG Assessments (if
any) Rating
Potential Problem Project at
any time (Yes/No): No
Quality at Entry
(QEA): 2 (Likely to achieve DOs)
Problem Project at any time
(Yes/No): No
Quality of Supervision
(QSA): None
DO rating before
Closing/Inactive status: Satisfactory – –
D. Sector and Theme Codes
Original Actual
Sector Code (as % of total Bank financing)
Central government administration 6 6
Rural and Inter-Urban Roads and Highways 90 90
Subnational government administration 4 4
Theme Code (as % of total Bank financing)
Administrative and civil service reform 17 17
Environmental policies and institutions 16 16
Infrastructure services for private sector development 33 33
Other social development 17 17
Rural services and infrastructure 17 17
E. Bank Staff
Positions At ICR At Approval
Vice President: Annette Dixon Praful C. Patel
Country Director: Francoise Clottes Peter C. Harrold
Practice Manager/Manager: Karla Gonzalez Carvajal Guang Zhe Chen
Project Team Leader: Amali Rajapaksa Isabel Chatterton
- iii -
ICR Team Leader: Radia Benamghar
ICR Primary Author: Radia Benamghar
Mirtha Pokorny
Tabjeel Ashraf
F. Results Framework Analysis
Project Development Objectives (from Legal Agreement)
The objective of the Project is to lower transportation costs through sustainable delivery of an efficient
national road system.
Revised Project Development Objectives (as approved by original approving authority)
The PDO remained unchanged throughout the life of the Project.
Note on Indicators: For the purposes of a split evaluation, indicators below refer to either RSAP-1
(original project and first Additional Financing), or RSAP-2 (second Additional Financing). Questions
regarding validity of some of the baseline data for RSAP-1 arose during implementation. This issue is
discussed in sections 1.3, 2.3 and 3.2.
(a) PDO Indicator(s)
Indicator Baseline Value
Original Target
Values (from
approval
documents)
Formally
Revised
Target Values
Actual Value
Achieved at
Completion or
Target Years
Lower transportation costs through sustainable delivery of an efficient national road system
Indicator 1 (a) RSAP–1 Reduction in average network vehicle operating costs for average vehicle of
3.8% by 2010
Value
(quantitative or
qualitative)
LKR 23.9 per km LKR 22.9 per km LKR 14.97 per km
Date achieved 11/16/2005 09/30/2011 09/30/2011
Comments
(including %
achievement)
Target achieved by more than 100%.
RSAP-1: The final value well surpassed the 3.8% target (by several hundred percent);
however, an exact determination of the extent of the overachievement for this indicator
cannot be precisely quantified, due to uncertainties related to baselines, mentioned
above. (See section 1.3, 2.3 and 3.2 for further discussion.)
Indicator 1 (b) RSAP-2 Reduction in average network vehicle operating costs for average vehicle
Value
(quantitative or
qualitative)
LKR 14.6/km LKR 10.5/km LKR 13.88/km
Date achieved 03/15/2011 03/15/2011 06/30/2015
Comments
(including %
achievement)
Original target 128% achieved; revised target not achieved. While the VoC was
reduced by 4.9% (exceeding the original 3.8% RSAP-1 target), target was revised under
RSAP-2, increasing the percentage reduction to 28% (LKR 13.88/km). The lower
- iv -
achievement may have been partially affected by post-conflict country priorities,
discussed in section 3.2.
Indicator 2 (a) RSAP-1 Reduction in average network roughness from 9.5 in the International
Roughness Index (IRI) in 2005 to 8.39 IRI in 2010
Value
(quantitative or
qualitative)
9.5 8.39 6.45
Date achieved 11/16/2005 09/30/2011 09/30/2011
Comments
(including %
achievement)
Target achieved by more than 100%. As with Indicator 1 (a) the target was exceeded
(272%); however, there are uncertainties regarding baseline. (See sections 1.3, 2.3 and
3.2.)
Indicator 2 (b) RSAP-1I Reduction in average network roughness from 9.5 on the International
Roughness Index (IRI)
Value
(quantitative or
qualitative)
6.2 5.9 5.9
Date achieved 03/15/2011 09/30/2014 06/30/2015
Comments
(including %
achievement)
100% Achieved.
Indicator 3 (a) RSAP-1 Reduction in percentage of the network in poor and bad condition from 52%
in 2005 to 35% in 2010
Value
(quantitative or
qualitative) (%)
52% 35% 40%
Date achieved 11/16/2005 09/30/2011 09/30/2011
Comments
(including %
achievement)
Partially achieved (70%)
Indicator 3 (b) RSAP-1I Reduction in percentage of the network in poor and bad condition to 35%
Value
(quantitative or
qualitative) (%)
38 35 – 35
Date achieved 11/16/2005 09/30/2011 – 06/30/2015
Comments
(including %
achievement)
100% Achieved. Although there had been considerable progress, the target had not
been fully achieved under RSAP-1 so target was not changed.
Indicator 4 (a) RSAP-1 Increase in annual maintenance expenditure from $13 million to $46.3 million
in 2010
Value
(quantitative or
qualitative) ($)
13 million 46.3 million – 44 million
Date achieved 11/16/2005 09/30/2011 – 09/30/2011
Comments
(including %
achievement)
95% Achieved. The Borrower reported maintenance expenditures had been
substantially higher than the target ($56 million vs $46.3 million). The task team noted
the $44 million figure excludes funding for periodic maintenance in 2010 that has been
channeled outside of the RMTF, and when these funds are added, the target is
- v -
substantially exceeded. However as the higher figures do not appear in relevant ISRs
or the Project Paper for the 2nd AF, the lower figure is reflected here. See related
comment for 4 (b) below.
Indicator 4 (b) RSAP-2 Progressive increase in annual road maintenance expenditure
Value
(quantitative or
qualitative)
LKR 4.2 billion/year LKR 6.6 billion/year – LKR 5 billion
Date achieved 03/15/2011 12/31/2014 – 06/30/2015
Comments
(including %
achievement)
Not achieved. This indicator is a continuation of indicator 4 (a) under RSAP-1. The
term “progressive” was added (in the Project Paper) to capture annual improvements
over the life of the Project. Unit of measurement changed from $ to LKR.
As above, Borrower reported as achieved and task team noted maintenance expenditures
had been substantially higher, and that the intent was to increase annual maintenance,
while this indicator measured the amount channeled through the RMTF.
Indicator 5 RSAP-2 Improved level of satisfaction of road users (for 3 roads: A002, A003, and
A006) (Percentage)
Value
(quantitative or
qualitative)
A002 40.38%
A003 36.22%
Combined: 38.3%
–
A002 62.16%
A003 74.14%
Combined: 68.1%
A006: 81.2%
Date achieved 03/15/2011 – 06/30/2015
Comments
(including %
achievement)
Achieved. While user satisfaction surveys for both A002 and A003 were carried out
using standard methodology, including baselines, A006 was assessed using a recall post
survey which did not include a baseline. Satisfaction improved substantially, however,
no target was established.
(b) Intermediate Outcome Indicator(s)
Component 1: Maintenance and Rehabilitation of National Roads
Indicator Baseline Value
Original Target
Values (from
approval
documents)
Formally
Revised Target
Values
Actual Value
Achieved at
Completion or
Target Years
Indicator 1(a) RSAP-1 About 620 km of national roads resurfaced
Value
(quantitative
or qualitative)
0 620 – 617
Date achieved 11/16/2005 09/30/2011 – 09/30/2011
Comments
(incl. %
achievement)
99.5% Achieved. All activities carried out as planned.
Indicator 1(b) RSAP-2 134 km of national roads resurfaced
Value
(quantitative
or qualitative)
0 134
43 (Orig. section)
A2 17 km
A3 17.7 km
78
Date achieved 03/15/2011 09/30/2014 09/30/2014 06/30/2015
- vi -
Comments
(including %
achievement)
100% Achieved (of revised target) New indicator for 134 km of national roads under
RSAP-1I. It later became evident that widening the full 134 km from 2 to 4 lanes would
entail substantial land acquisition issues which could not be resolved during the life of
the Project. Therefore, 134 km section was divided into 2 phases: phase 1 retained 43
kilometers of the original section; phase 2 replaced the remainder with road sections
A2, 17 km and A3, 17.7 km. 43 + 35 = 78 km.
Indicator 2a RSAP-1 Reduction in IRI for project roads from 7.8 to 2.9 (for 620km)
Value
(quantitative
or qualitative)
7.8 2.9 – 2.8
Date achieved 11/16/2005 09/30/2011 – 09/30/2011
Comments
(including %
achievement) 103% Achieved.
Indicator 2b RSAP-1I Reduction in IRI for project roads
Value
(quantitative
or qualitative)
6
4.3 (A002)
3.1 (A003)
2.8
2.4
2.4
2.33
1.9
2
Date achieved 03/15/2011 09/30/2014 09/30/2014 06/30/2015
Comments
(including %
achievement)
More than 100% achieved.
This indicator refers to the road section resurfaced that was split into two phases (See
indicator 1 (b) above.) The original target for phase 1 remained. New targets of 2.4 IRI
were set for the two new sections. Road sections A6, A002 and A003 were achieved by
115%, 127%, and 151%, respectively.
Indicator 3 RSAP-1 50% of relevant staff in the Planning and Maintenance Division of the RDA
trained in road asset management
Value
(quantitative or
qualitative) (%)
0 50 – 67
Date achieved 11/16/2005 09/30/2011 – 09/30/2011
Comments
(including %
achievement) 134% Achieved.
Indicator 4 RSAP-2 Reduced travel time on project national roads in minutes
Value
(quantitative
or qualitative)
66
13.8 for (A002);
26.5 for (A003)
42
12.5
23.9
40
11.31
23.58
Date achieved 03/15/2011 09/30/2014 09/30/2014 06/30/2015
Comments
(including %
achievement)
More than 100% achieved.
This indicator was added for the reasons mentioned above in indicator 2b. Road
sections A6, A002 and A003 were achieved by 108%, 191%, and 112%, respectively.
Indicator 5 RSAP-2 About 60 km of national roads on which periodic maintenance was carried out.
Value
(quantitative or
qualitative)
0 60 – 64.50
Date achieved 03/15/2011 09/30/2014 – 06/30/2015
- vii -
Comments
(including %
achievement) 107% Achieved.
Component 2: Maintenance and Rehabilitation of Rural Roads Pilot
Indicator 6 Rural roads improved (635 km) - RSAP-1
Value
(quantitative or
qualitative)
0 635 km 157 km 167 km
Date achieved 11/16/2006 09/30/2011 09/30/2014 09/30/2015
Comments
(including %
achievement)
Achieved 106% of revised target RSAP-1 and RSAP-1I.
The initial target length of 635 km for improvement of rural roads was based on
assumption that only minor maintenance would be required. However, upon
formulation of a new Rural Road Strategy Study, and after extensive stakeholder
consultation, it was decided to carry out more extensive improvements, thus
necessitating a reduction to 157 km, which was achieved after restructuring in 2013.
Indicator 7 RSAP-1 Reduced travel time on project rural roads by 10%
Value
(quantitative or
qualitative) (%)
0% 10% reduction
(overall average) – 60%
Date achieved 11/16/2005 09/30/2011 – 09/30/2011
Comments
(including %
achievement)
Target exceeded substantially. While detailed travel-time baselines could not be
prepared for the PAD, large scale monitoring and assessments were carried out. In
many cases, even 60% improvement does not capture the full level of improvement as
many of the roads had been non-motorable.
Component 3: Institutional Strengthening and Policy Support
Indicator 8 Annual road maintenance program is approved by the RMTF
Value
(quantitative or
qualitative)
Not approved Approved
annually Approved
Date achieved 03/15/2011 06/30/2015 06/30/2015
Comments
(including %
achievement)
100% achieved
This is an RSAP-1I indicator.
G. Ratings of Project Performance in ISRs
No. Date ISR
Archived DO IP
Actual Disbursements
($, millions)
1 06/21/2006 Satisfactory Satisfactory 4.39
2 12/12/2006 Satisfactory Satisfactory 13.61
3 06/22/2007 Satisfactory Satisfactory 24.59
4 12/20/2007 Satisfactory Satisfactory 32.67
5 06/30/2008 Satisfactory Satisfactory 64.85
6 10/01/2008 Satisfactory Satisfactory 74.21
- viii -
7 04/30/2009 Satisfactory Satisfactory 80.79
8 08/06/2009 Satisfactory Satisfactory 87.21
9 02/07/2010 Satisfactory Satisfactory 156.78
10 12/16/2010 Satisfactory Satisfactory 159.52
11 02/16/2011 Satisfactory Satisfactory 159.52
12 08/20/2011 Satisfactory Satisfactory 164.08
13 04/14/2012 Satisfactory Moderately Satisfactory 181.01
14 10/16/2012 Satisfactory Moderately Satisfactory 186.79
15 05/15/2013 Satisfactory Moderately Satisfactory 221.64
16 12/01/2013 Satisfactory Satisfactory 234.07
17 02/07/2014 Satisfactory Satisfactory 240.26
18 03/24/2014 Satisfactory Satisfactory 240.26
19 05/05/2014 Satisfactory Satisfactory 244.63
20 12/23/2014 Satisfactory Moderately Satisfactory 269.46
21 06/22/2015 Satisfactory Satisfactory 279.95
H. Restructuring (if any)
Restructuring
Date(s)
Board
Approved PDO
Change
ISR Ratings at
Restructuring
Amount
Disbursed at
Restructuring
in $ millions
Reason for Restructuring and
Key Changes Made DO IP
06/23/2008 -- S S 64.85
Additional Financing of $98.1 million
to help finance the costs associated
with the cost overrun of civil works
under the national roads component of
the Project due to unprecedented rise
in world fuel prices in 2007/08.
04/12/2011 -- S S 162.73
A second Additional Financing of
$100 million to scale-up the activities
through additional road sections in two
phases for the rehabilitation of 134km
in 2 phases:
Phase 1. Rehabilitation of 43km of
roads from Kanthale to Trincomalee on
the A6.
Phase 2. Rehabilitation of 91 km of
roads Ambepussa to Dambulla on the
A6. The operation also included
(a) financing of periodic maintenance
through the Bank assisted RMTF,
(b)TA of RMTF, (c) capacity building
of RDA; and (d) the piloting of a
safety corridor. In addition, the
original project was extended by three
years from September 30, 2011 to
September 30, 2014.
04/08/2013 -- S MS 209.06 A Restructuring to address the
following changes: Phase 2 related to
rehabilitation of 91 km of roads
- ix -
Ambepussa to Dambulla on the A6
was replaced by priority urban sections
in the western province. It included
rehabilitation and upgrading of
approximately 34.7 km of ‘A’ class
urban roads. It also included design
review and supervision of these
sections. In addition reallocation of
categories.
09/23/2014 -- S MS 262
The proposed restructuring was for
extension of closing date by 6 months
from September 30, 2014 to March 31,
2015. In addition, reallocation of
financing proceeds from category 1
(supporting parts A, B3, and B4 of the
Project) to category 2 (supporting Part
B1 of the Project) an amount of $1.4
million to finance the periodic
maintenance contracts through RMTF.
06/30/2015 -- S S 279.95
The proposed restructuring was for
partial cancellation of the Project
proceeds in the amount of SDR 8.5
million (approximately US$12
million). In addition, the Project was
extended by three months from March
31, 2015 to June 30, 2015.
- x -
I. Disbursement Profile
- 1 -
1. Project Context, Development Objectives and Design
1.1 Context at Appraisal
Country Context
1. At the time of appraisal of the Road Sector Assistance Project (RSAP) (Credit 4138-CE,
‘the parent Project’) the Government of Sri Lanka (GoSL) expected the economy to grow at annual
rates of 6 to 8 percent during the next five years. Infrastructure was considered paramount to
achieving these expected growth targets. The GoSL planned to increase the level of public
expenditure to reach 8 percent of gross domestic product, a substantial increase from the 5 percent
in 2004. To that end, a broad agenda was laid out for the road sector, including connecting poor
regions and production centers to domestic and international markets, building a national highway
system and an integrated road network, enhancing road safety, and promoting private sector
participation in the sector.
Sector Issues
2. Road infrastructure in 2004 was inadequate to support economic growth. Uncontrolled
roadside development, years of neglect, and poorly maintained roads had resulted in low traffic
speeds and poor levels of services, discouraging long-distance traffic and hindering the spread of
economic activities and development away from the Colombo metropolitan area. Given Sri
Lanka’s road density of 1.5 km per km2, there was an urgent need to address the issues of asset
preservation.
3. The focus on the road sector was taking place at a time when there was substantial progress,
albeit slow, on the peace front. There were considerable improvements in the lives of the people
in the north and east, and the entire country was benefitting from the cease-fire of 2002. Roads
were being reopened, suspended rail services were resumed, and considerable reconstruction had
occurred. In this scenario, the GoSL and the Asian Development Bank (ADB) agreed on a
medium-term sector reform framework as part of ADB’s Road Sector Development Project that
was under implementation. The World Bank, Japan Bank for International Cooperation (JICA),
and ADB agreed in November 2004 to coordinate their activities in the sector to support a
medium-term reform program that was based on three pillars: (a) strengthening the Road
Development Authority (RDA), a statutory institution assigned to the Ministry of Highways
(MoH) and responsible for implementing the development strategy for the sector, as well as
strengthening the provincial road agencies; 1 (b) establishing a mechanism for providing
1 The Ministry of Transport (MoT) has overall responsibility for policies concerning land transport services,
including bus transport and railways. The National Transport Commission, a regulatory body under the MoT is
responsible for policy formulation and subsidy disbursement. The MoH has overall responsibility for policies and
programs concerning the national road network. The RDA under the MoH is responsible for planning and managing
the national roads. Provincial roads are the responsibility of Provincial Councils and local roads under the
responsibility of local authorities.
- 2 -
sustainable funding for financing road maintenance; and (c) developing the domestic private sector
in the road industry.
Rationale for Bank Involvement
4. The Bank had remained disengaged from the transport sector in Sri Lanka for almost a
decade. However, there was an increased demand for the Bank to support infrastructure
development and the IDA Credit, the subject of this report, was seen as the appropriate vehicle for
reentering the transport sector at a time when GoSL was showing signs of abandoning its previous
reluctance to commit to sector reform. The emerging sector reforms included the closure of a
state-owned construction company that was causing serious distortions in the market, and the
decision to implement a Road Maintenance Trust Fund (RMTF) as an interim mechanism for
financing road maintenance. GoSL expected that, eventually, dedicated fuel taxes would fund the
RMTF. Furthermore, under the right circumstances, the Project would help to put in place the
necessary legal and regulatory framework for a ‘second generation’ road fund, that is, with a
governance structure that included major stakeholders.
5. Within this framework, the Bank agreed to take the leadership to address the issue of
sustainable road maintenance financing; JICA agreed to take leadership of the issue of private
sector development in the road construction industry; and ADB agreed to continue to lead the
dialogue on institutional strengthening and capacity building.
1.2 Original Project Development Objectives (PDO) and Key Indicators
6. The Project Development Objective (PDO) in the Project Appraisal Document (PAD)
differs slightly from the one in the Credit Agreement. In both documents, the PDO is stated as:
The objective of the Project is to lower transportation costs through sustainable delivery of an
efficient national road system. In the PAD, this statement is followed by the phrase that serves
the needs of road users and the Sri Lankan public at large. The latter phrase is not included in the
PDO in the Credit Agreement. The difference is not material within the context of the project and
results framework; therefore, the Credit Agreement PDO is treated as operative for the purpose of
this Implementation Completion and Results Report (ICRR).
7. The achievement of the PDO was to be monitored and evaluated using the following
indicators (as described in the PAD):
PDO Indicators
Reduction in the average network VoC for standard commercial vehicles of 3.8
percent by 2010;
Reduction in the average network roughness from 9.50 in the international roughness
index (IRI) in 2005 to 8.39 IRI in 2010;
Reduction in percentage of the network in poor and bad condition from 52 percent in
2005 to 35 percent in 2010;
Increase in annual maintenance expenditure from projected US$13 million in 2005 to
US$46.3 million in 2010.
- 3 -
Intermediate Indicators
About 620 km of national roads resurfaced;
Reduced IRI for project roads from 7.8 to 2.9;
50 percent of relevant staff in Planning and Maintenance Divisions of the RDA to be
trained in road asset management;
About 635 km of rural roads improved;
10 percent reduction in travel time;
An increase in annual maintenance expenditure from projected $13 million in 2005 to
$30 million in 2010; allocation based on Road Assets Management System (RAMS);
regular consultation with road users; publication of the RMTF Annual Reports in public
domain.
1.3 Revised PDO (as Approved by Original Approving Authority) and Key Indicators, and
Reasons/Justification
8. The PDO remained unchanged throughout the life of the Project but the outcome and
intermediate indicators were revised to reflect new activities supported by a $100 million Second
Additional Financing in 2011. Changes affecting the indicators included the rehabilitation of
additional road sections in two phases for 134 km in the East-West corridor, and the financing of
road maintenance through the Road Maintenance Trust Fund (RMTF). (See Section 1.6., Revised
Components.)
9. A subsequent restructuring was approved in 2013 to drop one of the National road sections
from the Second AF, replacing it with two urban road sections. The replacement was in response
to GoSL’ s request to widen the National road section from two to four lanes due to increased
traffic; however, the widening would have entailed land acquisition adding a significant amount
of time to the contract period, exceeding the timeline envisaged under the Project.
10. The new activities undertaken for RSAP-1I also provided an opportunity to utilize and
incorporate improved road data that was being collected through enhanced monitoring of the road
network. Inadequate data had, in some cases, resulted in indicators with deficient baselines. It
was not until several years into the project that more reliable data became available.
11. Table 1 below summarizes the changes in the indicators and targets that occurred over the
life of the project, including the original credit, the additional financings, and the restructuring in
2013.
- 4 -
Table 1. Indicator and Target Changes during the Project
Original targets to be
achieved by 2011 as set out in
the PAD
Target revisions made at the
second AF Restructuring in 2013
Type of
change
made Reduction in the average network
VoCs for standard commercial
vehicles from 23.9 (baseline) to
22.9
Reduction in the average network
VoCs for standard commercial
vehicles to LKR 10.5 per km –
Target value
Reduction in the average network
roughness from 9.50 in the IRI to
8.39 IRI
Reduction in the average network
roughness from 6.2 to 5.9 in the
IRI
–
Target value
Reduction in percentage of the
network in poor and bad condition
from 52 percent in 2005 to 35
percent
Reduction in percentage of the
network in poor and bad condition
from 38 to 35 percent (not
technically a revision, but PAD
target had not been fully achieved
so it was continued for RSAP2)
–
Target value
Increase in annual maintenance
expenditure from projected $13
million in 2005 to $46.3 million in
2010
Progressive increase in annual
maintenance expenditure from
LKR 4.2 billion ($45.1 m equiv.) in
2011 to LKR 6.6 billion in 2014
–
Target value
– Improved level of satisfaction of
road-users (new indicator) –
New
Indicator for
RSAP-1I
Intermediate Indicators- PAD Second AF - 2011 Restructuring Paper - 2013 Type of
change made
About 620 km of national project
roads resurfaced
About 134 km of national roads to
be resurfaced in two phases.
(Revised in 2013 restructuring –
see cell one down to the right)
–
New
Indicator for
RSAP-1I
– –
134 km revised to 78 km of national
roads to be resurfaced. Phase 2 split
into 2 roads (A002 & A003)
Target value
Reduced IRI for 620 km national
project roads from 7.8 to 2.9 (same
km as cell above)
– –
Reduced IRI for 134 km project
roads from 6.0 to 2.8 (same km as
cell above)
–
New
Indicator for
RSAP-1I
– –
Split into separate roads (reduced km)
necessitated having individual IRI
targets: from 4.3 to 2.4 for A002 road
and from 3.1 to 2.4 for A003
Target value
–
Reduced travel time for 134 km
project roads from 2.3 to 1.8 (same
km as cell above)
–
New
Indicator for
RSAP-1I
– – Split (reduced km) required new travel
times: from 13.8 to 12.5 for A002
Target value
- 5 -
Original targets to be
achieved by 2011 as set out in
the PAD
Target revisions made at the
second AF Restructuring in 2013
Type of
change
made road and from 26.5 to 23.9 for A003
–
About 60 km of national roads on
which periodic maintenance has
been carried out.
–
New
Indicator for
RSAP-1I
– Annual road maintenance program
is approved by Board of Trustees. –
New
Indicator for
RSAP-1I
50% of relevant staff trained in
road asset management – –
About 635 km of rural roads
improved –
157 km of rural roads improved (This
was changed based on the new Rural
Road Strategy Study)
Target value.
Reduced Travel Time (rural roads)
(Same km for indicator above) – –
Routine and periodic maintenance
funding increased to $46.3 million – –
1.4 Main Beneficiaries
12. The primary beneficiaries of the Project are the road users and road-related transport
services. More specifically, road users and road transport services directly benefit from
improvement in key linkages, with decreased transport costs and travel times, which improve
connectivity and road safety for its users, and promote economic growth in the region. In the
socioeconomic context, the improvement of local roads directly influences the daily social life of
the population who live in rural areas. As a result, rural populations have better access to public
amenities such as schools, health care, business centers, and markets. In addition, the execution
of rural roads generated new jobs and stimulated the local economy through the indirect purchasing
of local goods and services. The rural development improved safety for working women.
Furthermore, the highways safety component of the project helped to decrease road accidents and
fatalities and contribute to lower accident-related road costs to the economy.
1.5 Original Components
13. The parent Project (RSAP-1) consisted of the following three components (see Table 2 for
costs).
Component 1: Maintenance and Rehabilitation of National Roads. Consisted of the
following: (a) civil works along national roads, comprising resurfacing and improvement
of about 620 km of Class A and B roads; (b) technical assistance for the selection, design
and construction supervision of these works; (c) training and institutional strengthening;
and (d) incremental operating costs.
Component 2: Maintenance and Rehabilitation of a Rural Roads Pilot. Consisted of
the following: (a) rehabilitation and maintenance of about 635 km of rural roads, and
strengthening of the rural road management and maintenance systems in three project
Provincial Councils and nine project Pradeshiya Sabhas; (b) feasibility, design, and
construction supervision consultant services; (c) training and institutional strengthening;
- 6 -
and (d) incremental operating costs. This was a pilot project to help the GoSL for future
rural road improvement programs.
Component 3: Institutional Strengthening and Policy Support. This component
comprised technical assistance to improve sector policies for road maintenance financing.
1.6 Revised Components
14. The original components were revised and updated at the time of the second AF for $100
million and the 2013 Restructuring. The components below include the new activities funded
under the AF.
Component 1: Rehabilitation of Priority National Roads in the East-West Corridor
Providing Connectivity to the Eastern and Northern Provinces. This component consisted of
resurfacing and improving about 134 km of class A roads which was part of the government’s
strategy to provide connectivity to the Northern and Eastern Provinces. It was designed to be
implemented in two phases. While phase 1 was completed as planned, Phase 2 was modified
under a 2013 restructuring, due to the government’s request that the road sections be widened
from two to four lanes, because of increased traffic. The proposed widening, however, required
significant land acquisition which could not be completed within the timeline envisaged under
the Project. Therefore, priority urban sections in the western province were selected for
upgrading in Phase 2.
Component 2: Institutional Strengthening and Improvements in Asset Management
Practices. This component provided funding for periodic maintenance, technical assistance and
strengthening of the systems within the RMTF and RDA relating to road maintenance, institutional
strengthening of the RDA, and addressing issues identified through the capacity assessment
relating to road safety.
15. The component allocations under each key phase of the project – the parent project, the
first and second additional financings, and the restructuring in 2013 – are shown in Table 2.
- 7 -
Table 2. Revised Project Costs by Components ($ millions)
Components
Original + First Additional Finance
2005
(Original Project)
2008
(1st AF) Component 1 - Maintenance and Rehabilitation
of National Roads 82.64 66.64
Component 2 - Maintenance and Rehabilitation
of Rural Roads Pilot 11.04
Component 3 - Institutional Strengthening and
Policy Support 0.66
Unallocated (physical and price
contingencies/First AF) 5.67
31.46
Includes VAT
Sub-Total 100.00 98.10
**Total Project Costs (original +First AF) 198.10
Components with Second Additional
Finance and Restructuring 2013
2011
(2nd AF)
2013
Restructuring Component 1 - Maintenance and Rehabilitation
of national Roads 85.50 81.00
Component 2 - - Institutional Strengthening and
Asset management practices 14.50 19.00
Sub-Total 100.00 Reallocation
**Total Project Costs 100.00
TOTAL (Original + First AF + Second AF +
RP) 298.00
1.7 Other Significant Changes
16. First Additional Financing 2008. The First AF under RSAP-1 (for $98 million
equivalent) was approved on September 16, 2008 to cover financing gaps due to: (a) the
unprecedented oil price increase in the world market that had led to the escalation of prices in
oil-based materials; and (b) the use of higher standards for national highways to improve safety
environment as stipulated in the National Road Master Plan (NRMP) adopted in December 2007.
(See Factors outside the control of the Government, pages 9-10, for additional detail.)
17. Second Additional Financing 2011. As mentioned above, the purpose of the AF was to
scale up the parent project and enhance its impact through the rehabilitation of national roads,
providing funding for periodic road maintenance, technical assistance to the RMTF and RDA,
and address safety issues identified in a capacity assessment. The Government was keen to
achieve quick results in order to: (a) capitalize on the benefits of the cessation of the conflict and
its impact on the development of the previously conflict affected areas, and (b) maximize the
usage of the already established implementation mechanisms and institutional arrangements in
order to scale-up activities within the agreed extended timeframe.
18. Restructuring 2013. In addition to the changes already mentioned, the length of rural
roads targeted for improvement was reduced from 635 km to 157 km in Component 2 of the parent
project. Subsequent to the formulation of the Rural Roads Strategy Study financed under the
Project, and after extensive stakeholder consultations carried out during project preparation, it was
decided that a full upgrade of the rural roads should be carried out, rather than proceeding with a
relatively low cost but temporary maintenance regimen, i.e., pothole filling, patching, etc. The
- 8 -
decision was made to provide a more comprehensive upgrade, which required a reduction in the
number of kilometers of road.
19. Restructuring 2014 was a six-month project extension to allow sufficient time to complete
the rehabilitation on sections of A002 and A003.
20. Restructuring 2015 included a partial cancellation of $12 million equivalent at the request
of the Borrower due to underuse of price and physical contingencies and savings resulting from
sliding fuel prices, and lastly, the depreciation of the Sri Lanka Rupee. The restructuring also
included a final project extension of three months to accommodate the completion of unfinished
works.
21. Establishing and functioning of the RMTF. The Ministry of Finance (MoF) was
responsible for the implementation of all activities related to the set-up and adequate financing for
a trust fund related to sustainable road maintenance finance. However, the RMTF under the MoF
was not fully operationalized because of administrative difficulties and lack of capacity. This
resulted in re-establishment of the RMTF under the Ministry of Ports and Highways to take the
agenda forward through the Second AF.
22. RMTF and road maintenance funding. The funding for road maintenance was
channeled to the RDA through the RMTF under an annual budgetary allocation. Although it was
originally envisaged that taxes from the sale of petrol and diesel would be made available to the
RMTF, the funding for road maintenance was provided as a budgetary allocation. The annual
funds collected from the sale of fuel were only $8 million to $10 million—far less than the
maintenance needs.
2. Key Factors Affecting Implementation and Outcomes
2.1 Project Preparation, Design and Quality at Entry
23. Soundness of the background analysis and design. The project responded to the
government’s transport priorities where civil conflict had been prolonged for many years and had
contributed to the poor condition of the road network. Immediate rehabilitation was required to
augment the condition of the road network. The project design was highly relevant to Sri Lanka’s
needs and in line with the priorities of the Country Assistance Strategy (CAS). The FY2003–06
CAS aimed to improve social and economic inclusion of the poor and facilitate broad-based
economic growth. Both the government and the Bank strategies placed high priority on developing
road infrastructure and recognized its contribution to the development of the private sector and the
desired increase in revenues to achieve high levels of public investment. The lessons learned from
earlier operations included: (a) providing adequate post-project maintenance; (b) the importance
of environmental and social management; (c) improving rural roads management; (d) providing
targeted training and capacity building for local governments; (e) the need for the Project’s design
to include the first steps toward developing an appropriate sector policy framework, (f)
empowering and strengthening the local authorities to discharge responsibilities, and (g) providing
targeted and practical training programs built into the rural roads pilot component.
- 9 -
24. Paticipatory process. The project was prepared in a participatory manner with the
involvement of key stakeholers, including government ministries, designated government
implementation agencies, local and provincial government units, development partners and local
communities, and road users.
25. Risk and mitigation measures. A range of risks were identified during project
preparation and appropriate mitigation measures were considered. The main risks were related to:
(a) the consolidation of the peace process and political stability to oversee meaningful sector and
economic reforms; (b) exogenous shocks to the economy impairing aggressive revenue raising
strategy; (c) vested interests supporting the status quo; (d) weak national construction capacity to
undertake the works; and (e) institutional capacity for the day-to-day implementation of the
Project. These risks were mitigated by the already proven strong commitment of the government
and the resources committed by the ADB and the Bank to facilitate the process of implementing
reforms. Finally, the risk of a weak national construction capacity to undertake works under the
Project was addressed by suitable packaging of contracts to accommodate both National
Competitive Bidding and International Competitive Bidding. One risk that was not forseen at
appraisal, yet materialized during implementation was the effect of the rapid surge of the
construction activity in the country, which contributed to the shortage of human and material
resources and the resulting increase in construction costs. The issue of counterpart funding was
well foreseen during preparation and eventually, remained under monitoring.
26. A Quality at Entry (QAG) assessment was carried out by the Quality Assurance Group
on November 7, 2008 and the project was rated Satisfactory (likely to achieve its development
objectives). In particular, the report comments, “The DOs expressed exactly what they neeeded,
and they are still highly relevant.” The report also remarks, “The project design adequately
evidences that measures were taken to promote positive social impacts…With regard to poverty,
project covers the poorest segments of the country including provinces close to the conflict areas
and proposes labor intensive interventions…Stakeholder consultations were organized in a manner
that ensured gender equality.”2
2.2 Implementation
27. The project implementation period could be broadly divided into two phases:
(a) RSAP-1 (parent project and First AF)—for a period of six years (December 2005–
September 2011)
(b) RSAP-1I (additional components through the Second AF and two Restructurings) for
an additional period of four years (March 2011–June 2015), for an overall project
period of about 10 years.
28. Project implementation, including compliance with both the original Project and its two
AFs, was generally rated satisfactory in all of the Implementation Status Reports (ISRs) and
2 The report from the Quality Assurance Group is in annex 9.
- 10 -
slipped into moderately satisfactory for about 18 months (April 2012, May 2013, and December
2014). Project implementing agencies had amassed considerable experience through
implementation over the 10-year period and developed an adequate technical capacity in
procurement, contract management, social and environment related aspects. There were some
events that occurred during the Project’s life that delayed implementation. These are outlined
below.
Factors outside the control of the Government
29. The increase in construction costs in Sri Lanka necessitated an AF of $98 million, i.e. 59.2
percent of the Project cost. This cost overrun was due to two reasons:
A worldwide escalation of oil and commodity prices resulted in an increase in construction
costs in Sri Lanka following the Project start-up. The analysis undertaken during project
implementation showed that all key cost drivers under Components 1 and 2 suffered major
increases between 2005 and 2009: Bitumen (433 percent), fuel (241 percent) among other
factors. Works on the national roads under the parent project experienced cost overruns
averaging 86.5 percent, and ranging from 51.4 percent to 132.4 percent.
The use of higher standards for national highways to improve the safety environment as
stipulated in the National Road Master Plan (NRMP) adopted in December 2007. Under
the Project, this new policy of the Ministry of Highways and Road Development
necessitated widening of roads to 6.2 meter national standards with a 0.65 meter hard
shoulder on the inside of the numerous bends. As a result of the change in width of
carriageway, all culverts had to be extended and other related matters addressed.
Factors generally subject to Government control
Unrealistic estimates. Bid prices were 6.8 percent above estimated prices at a time in
which a construction boom brought about by reconstruction works after the end of the civil
war, and rebuilding after the tsunami of December 2004 resulted in shortages of resources
that affected the cost and pace of implementation.
Limited availability of bitumen during the first two years of project implementation due to the high demand created by construction works in the country. The state monopoly
supplier, Ceylon Petroleum Corporation, was not able to increase supply to match the new
demand. Eventually, after a concerted effort by international donors, the GoSL approved,
starting in January 2008, importing bitumen for interested contractors through Maga
Naguma, a subsidiary of RDA.
Unrealistic estimation of contract periods for works and designs. The original periods
had been understated and the contracts neither fully appreciated nor reflected the work
involved in difficult terrains. They also did not reflect the additional work due to variations
in time needed to obtain environmental clearances, which later required additional time for
expansion of the scope of work.
- 11 -
Delay in obtaining Environmental Protection Licenses and/or Explosive Permits,
processes that in many cases took more than 10 months.
Lack of coordination with utilities agencies. Civil works were slowed because of
difficulties in getting sufficient crews mobilized to work simultaneously on several
contracts, particularly for utilities relocation. Despite monthly coordination meetings
being chaired by RDA’s management, the utility companies performed slower than
expected. This was particularly true of the National Water and Supply and Drainage Board
(NWSDB). For works on the Second AF, coordination improved substantially through a
different allocation of responsibilities. In particular, RDA procured the water pipes and
their laying was part of the civil work contracts. This allowed for the water and road works
to be completed on these corridors simultaneously avoiding wastage due to uncoordinated
activities that the country has been suffering for a long time.
Frequent turnover of the PMU staff. The PMU staff turnover which resulted in losing
institutional capacity and memory was a major challenge to project implementation. Four
different project directors headed the PMU during the course of the Project.
No appropriate approval delegation, ownership, and accountability from the MoF with
regard to operationalizing the RMTF, which necessitated the reestablishment of the RMTF
within the Ministry of Port and Highways.
Cost overruns on the national roads parent project could range from 51.4 percent to 132.4
percent, and time overruns from 7.6 percent to 180.7 percent. Cost overruns in the civil
works under the Second Additional Financing were substantially lower. The cost
improvements were achieved through better distribution of responsibilities between RDA
and consultants for the different stages of implementation. For the original Project, design
and supervision of works were entrusted to consultants. The lack of involvement of RDA’s
provincial staff had, in some cases, led to variation orders being received several years after
commencement of contracts.
With respect to supervision, the parent Project was affected by multiple problems. These
ranged from changes in staffing of the consulting firm, to the difficulties in dealing with
multiple projects spread over a large area. These problems were also compounded by
(some) poorly qualified consultants both with respect to design as well as supervision.
During a workshop for the preparation of this ICR that took place in Colombo in June 2015,
there was a consensus among the main stakeholders that the pressure to quickly start
projects contributed to less than optimal designs. Time overruns were also substantially
contained although contractors claimed that the time estimated to complete projects was
too optimistic.
30. The Midterm Review (MTR) was carried out in March 2009 with 41 percent of funds
disbursed (of RSAP-1). Both the PDO and IP were rated satisfactory. The MTR highlighted
overall project progress, including lessons learned from the challenges discussed above. The MTR
discussed some revisions to the Results Monitoring Framework and some changes were suggested,
notably that the number of km of rural roads targeted for spot improvements would likely need to
- 12 -
be reduced from 635 to 157, and changing the road condition target. Although these changes were
noted in the aide memoire, there was no formal restructuring of the results framework until the AF
two years later. Part of the reason for this seems to have been government uncertainties during a
period of rapid change, i.e., identifying and agreeing on the number and location of roads to be
rehabilitated and a change in the government’s view post-MTR regarding changing the road
condition targets because of budget considerations. That said, adjustments could have been made
sooner in a restructuring. The relevant observations and findings from the MTR were used to
corroborate the ICR’s team’s observations and analysis with respect to implementation challenges
and progress.
31. The Rural Roads Pilot. The objective of the Rural Roads pilot was to develop a
sustainable system that could be scaled up in future programs. The emphasis was on the preparation
of a Rural Roads Strategy/Manual, development of a rural roads improvement program, providing
maintenance on the targeted roads, and the creation of a rural roads database. While the number of
kilometers was reduced in order to provide greater rehabilitation to a smaller network of roads, the
works, as well as the strategy, database and other activities, were successfully completed and the
pilot has been expanded to other provinces, an important step toward a sustainable system.
32. The Roads Maintenance Trust Fund (RMTF) was established in order to improve
transparency in the allocation of resources and disbursement of funds, as well as to carry out
efficient monitoring of the maintenance programs. The intention was to ensure a sustainable well-
maintained road network in the long term by maximizing the use of resources applied to the
rehabilitation of the network.
33. The Roads Maintenance component focused on supporting GoSL to set up an interim
mechanism for road financing in the form of a trust fund under the Trust Ordinance for earmarked
road maintenance funds. At the time, it was to support the writing of the draft bill, and its
presentation to Parliament, and necessary legislation to establish a dedicated Road Maintenance
Fund. The Fund would be financed by fuel taxes and managed as a statutory body by an
independent board and funding. The RMTF was set up, as agreed, at the beginning of the Project
under the MoF, and the GoSL appointed a Board of Trustees and a Technical Advisory Committee
(TAC). A separate budget line allocated funds to the RMTF and these funds were transferred to
RDA after the approval of its annual maintenance plan.
34. The Fund, however, only attained a meaningful role as an overseer of maintenance
practices after the approval of the Second AF, late in 2011. Lack of strong commitment of the
main stakeholders in fully launching the Fund combined by frequent changes in the Board of
Trustees and TAC contributed to the delays.
35. During the preparation of the Second AF it was decided to return momentum to the Fund
through the inclusion of a road maintenance component to be cofinanced by the Bank and RMTF.
The Credit Agreement included a disbursement condition for adequate staffing of the Fund that,
after problems finding suitable candidates, was accomplished by transferring some RDA staff. As
a result, the role of the Fund in approving the annual road maintenance plans was carried out with
an increased technical capability. In addition the Fund started to play an active role in overseeing
works and ensuring the adequate use of the approved allocations.
- 13 -
36. The Road Asset Management System (RAMS) has been successfully implemented.
The implementation phase witnessed not only the enhanced capacity of the RDA and PMU for
implementation but also improvement in the construction industry overall. The institutionalization
of RAMS has resulted in sustained maintenance grants through the RMTF with more emphasis
given to collecting scientific data. Though much improvement is needed for the analyses of such
data, the presence of RAMS will lead to the sustainable functioning of a maintenance system for
the highways in Sri Lanka. Awareness of environmental and social safeguards during construction
activities has increased among the practitioners in the road sector. The public participatory process
in these activities through stakeholder consultations, and the approval process of yearly
maintenance plans, may open opportunities for enhanced quality, transparency, and accountability.
37. Road traffic safety pilot. Concerned by the fact that the substantial road improvements
taking place in Sri Lanka were allowing increased speeds and potentially detrimental effects on
traffic accidents, the Second AF included a pilot safety corridor to address these concerns.
Twenty-seven km of the A002 was selected as the road safety demonstration corridor due to its
existing high-level of road accidents. A committee was formed from multiple organizations that
had not cooperated previously, and a considerable amount of time and effort was used to mobilize
them and the communities. Organizations included, among others, RDA, the Traffic Police,
Ministry of Health, four local authorities on the corridor, the University of Moratuwa, and the
National Council for Road Safety (NCRS). The committee was tasked to scope and implement
the demonstration corridor. Traffic Police coordinated public awareness measures and
enforcement, working closely with the public to mitigate initial reluctance. In addition to
awareness programs, interventions included placing of pedestrian crossings, especially in view of
schools and bus stands, street lighting, provision of safety barriers, raised foot walks, availability
of ambulance and fire facilities and training of staff for emergency care, provision of an emergency
number to access these facilities, safety awareness for schools, three wheelers and private buses,
enforcement of speeds, etc.
Table 3. Changes in Accident Patterns Along A002 Pilot Safety Corridor 2015-2016
Category 2015 2016
Fatal 10 5
Grievous 40 5
Minor Injured 101 22
Total 151 30
2.3 Monitoring and Evaluation (M&E) Design, Implementation and Use
38. M&E design. The project M&E systems were planned using the Results Framework
designed at appraisal. The PDO outcome and intermediate results indicators were adequate from
a technical standpoint to measure improvements in road conditions (IRI), reduction in VoCs,
sustainability, and efficiency. The indicators were, in principle, appropriate to measure the PDO
to reduce transportation costs through sustainable delivery of an efficient national road system.
- 14 -
39. However, three out of the five PDO indicators encompassed the whole network, in
particular, VoC, IRI and the percentage of roads in poor and bad condition. While the PDO and
associated outcome indicators were to reduce the transport costs through sustainable delivery of
an efficient national road system for the whole network (12,000 km), the Project works were
responsible directly for only 755 km, which is about 6 percent. To address the greater network,
the project incorporated a number of institutional strengthening activities; however, the results
framework falters in showing direct causal links between the project’s institutional activities and
the national targets. These weaknesses raise attribution issues.
40. The PDO could have been more focused by separating the sub-objectives more distinctly,
i.e., lowering the transportation costs for the targeted project roads, and supporting sustainable
delivery of an efficient national road system. In fact, the project indicators that measure the
reduction of transport costs for the targeted roads in the project are precise and easily measurable,
and closely related to the road improvements and related activities. It is the references to the
national roads that weaken the framework. A relatively simple change in the language of the PDO
and the three PDO indicators could have gone a long way towards strengthening the evaluative
framework, i.e., substituting “targeted roads, or corridors” for “national network”. Many projects
with similar components do just this: frame the objective to “reduce the transports costs along the
targeted corridor,” instead of “reduce transport costs for the whole national network”.
41. The establishment of baselines and target values for RSAP-1 was also marred by flawed
data. According to one aide-memoire,3 the baseline value of the network IRI for RSAP-1 was
fixed at 9.5 based on 226 km out of 9,913 km of road network in the year 2004. Yet even the
methodology used in assessing the 226 kilometers was not clear. This resulted in indeterminate
baselines the VoC and IRI of the parent project. The Bank recognized the flaws and at various
points took steps to improve the framework, but reliable data – even four or five years into the
project – was not always available. It was only by the time of the Second AF in 2011, when annual
national road surveys had been instituted, that the Bank team was able to agree with the
government on significant changes to the results framework and establish clear and reliable
baselines and targets. (The PDO target values for the VoC and IRI were revised because the Project
had already achieved a much lower value than the target value in 2009.)
42. M&E Implementation and Use. RDA and the Ministry of Provincial Councils and Local
Governments (MPCLG) were responsible for collecting, analyzing, and reporting project
performance indicators. The Bank had access to the data necessary to analyze performance and
other monitoring issues. The Bank used this information, to the extent possible, to carry out the
project’s restructuring and prepare the AFs. The Results Framework matrix was adjusted
accordingly, particularly at the Second AF.
43. An independent M&E report in 2009 found that monitoring alone was not sufficient and
more focus needed to be placed on analysis and evaluation to improve strategic decision making.
Improvements were made, albeit gradually.
3 Annexure 2 of aide-memoire of June 2008.
- 15 -
44. Progress towards achievement of the final targets was monitored through regular project
progress reports by RDA and the Bank’s implementation Status and Results Report (ISR). Progress
under the institutional development component and compliance with related covenants, were
reported in semi-annual progress reports prepared by RDA, while regular supervision missions
and comprehensive aide-memoires monitored progress and results achieved. An MIS system was
used by RDA to provide monthly progress reports to sector stakeholders, including the Bank, on
physical and financial, as well as technical progress for all road sections and contracts. HDM-4
was used to monitor selected project indicators. The project was able to train an adequate number
of persons on RAMS and RDA is well equipped with the latest survey equipment, including laser
road profilometers and falling-weight deflectometers. Survey teams now collect data annually.
2.4 Safeguard and Fiduciary Compliance
Environment Safeguards
45. The project triggered Bank safeguards policies Environmental Assessment (OP/BP 4.01)
and Natural Habitats (OP/BP 4.04), and was classified as an environmental category B project.
An Environmental Management Plan (EMP) was prepared by the RDA. Overall, the EMP was
satisfactorily implemented by contractors and monitored under the supervision of the RDA.
During implementation, this was confirmed with no major impacts or safeguard compliance issues
arising. The successful adoption and implementation of the Bank’s environmental guidelines on
the initially reluctant local and international construction firms is one of the important
achievements of the Project. Sri Lankan law requires environmental assessments and actions for
road constructions, but not for rehabilitations. However, the Project helped introduce and include
environmental clauses as part of the contract documents of these rehabilitation works. By the end
of the Project, many of the local contractors were adopting the same preventive and remedial
environmental protection measures on other projects with no such requirements.
Social Safeguards
46. Social safeguards management of the Project showed gradual progress throughout the
Project implementation period. In keeping with the Bank’s safeguard policies, the RDA prepared
an Environmental and Social Management Framework for the overall project.
47. The project triggered OP 4.12 (Involuntary Resettlement) to mitigate impacts to the
properties and structures along the roads. However, no physical or economic displacement of
persons or resettlement impacts were experienced by the Project and most of the lands used for
expansion of the roads were within the domain of the RDA or obtained through voluntary land
donations from project beneficiaries.
48. Most of the adverse social impacts were due to construction-induced issues related to
expansion of the width of roads, affecting property owners residing along the roads, and drainage
lines that obstructed planned improvements. Social Impact Assessments and site-specific
Resettlement Actions Plans were prepared to identify the potential, adverse social impacts and
mitigation measures were implemented to reduce them. A key highlight of the Project was the
systematic implementation of a grievance redress mechanism according to the Policy Framework.
Also, for the first time in a road project in Sri Lanka, an independent third-party monitoring system
- 16 -
was introduced to engage project-affected persons to provide feedback and systematic monitoring
of project implementation. In addition to the above measures, the Project undertook a series of
awareness creation programs on HIV/AIDS in compliance with the Bank’s policy. Overall,
implementation of social safeguards was Satisfactory throughout the Project period.
Procurement
49. Procurement of goods, works, technical assistance, and non-consulting services was
carried out in accordance with the Bank’s procurement guidelines. All contracts, with minor
exceptions, were signed and completed before project closing. At appraisal, the procurement
capacity of the implementation agency was assessed and a Procurement Plan was prepared. The
procurement activities were managed by the related project implementation agencies.
Procurement under the Project was rated Satisfactory throughout most of the Project
implementation period, with very few exceptions, where it received a Moderately Satisfactory
rating due to procurement and contract delays. However, it was noted in two aide-memoires
(December 2010 and April 2015) and interviews that procurement and contract management were
at times affected by a lack of proper monitoring and supervision by the implementing agency
which, in turn, affected fiduciary compliance. The project experienced substantial time and cost
overruns largely due to unrealistic estimates, and poor performance in works that showed
premature pavement failures on three packages under the national roads component of the parent
Project. At the end of completion of the original Project in December 2010, about $10 million
was financed by the government’s own funds due to additional works that were carried out without
the Bank’s agreement, and which were found to be ineligible due to unacceptable variations in
price indices for the calculation of price adjustments and the use of unacceptable market rates.
Financial Management
50. The performance of the implementing agencies in financial management (FM) has been
satisfactory in a majority of the implementation support review missions. On two occasions,
during November 2011 and December 2013, the overall FM rating was downgraded to Moderately
Satisfactory. The reasons for the downgrade was primarily due to one or more of the following:
inadequate FM staffing, issues in submission of interim unaudited financial reports, inadequate
internal audits, delayed external audit, and inadequate counterpart funds flow on a timely basis.
However, other than on these two occasions, basic arrangements handled at the PMU, Project
Consultancy Unit, and RMTF level, including budgeting, financial reporting, external auditing
arrangements, accounting, FM staffing, funds flow, and internal controls, did not have major issues
and hence, the overall implementation was managed satisfactorily. It should be noted, however,
that during the last few years of implementation, the Project’s internal audit failed to perform at
its optimum level due to internal audit staffing constraints that were prevailing at the ministerial
level. This was identified as a systemic issue that could affect any project going forward. It is
envisaged that this area could be given special focus and perhaps training might be provided to
enhance the capacity to perform internal audits.
2.5 Post-completion Operation/Next Phase
51. The project roads from the parent project and Phase 1 of Component 1 of the Second AF
have now been in operation for some years. Despite cracks detected in pavements of three road
- 17 -
sections (parent project) and surface irregularities in pavements of a Phase 1 section, maintenance
is under way on these roads. The projects of Phase 2 of Component 1 of the Second AF have been
taken over and post-project activities such as issuance of Taking over Certificates and Defect
Liability periods have been completed.
52. An annual maintenance plan is being developed by the RDA and approved by the RMTF
for periodic maintenance and routine maintenance of roads. The funding is channeled through the
RMTF using budgetary grants. During 2005 to 2013, the budgetary allocation to road maintenance
through the RMTF increased from $13 million to $63 million. However, more sustainable avenues
for funding need to be explored and an output and performance-based contracts system may be
implemented for rehabilitation and maintenance of projects for longer duration. The project has
been transformational in its attempts to address the backlog of maintenance due to years of
neglect. In addition, this project helped both the Bank and the RDA undertake several institutional
changes and reforms, such as financing the piloting of several initiatives to address adverse issues
within the sector, including development of the contract management capacity within the RDA.
53. Based on the experience of the RSAP, the Bank is considering another project for long-
term development of the capacity of the RDA as well as the maturity of the construction industry
with renewed focus on good governance. Given the country’s history of inadequate maintenance
of existing assets and the Bank’s strong support for maintenance reflected through its entire
support to the road sector in Sri Lanka, an asset management approach is being proposed through
design-build-maintain-operate-transfer methodology. 4
3. Assessment of Outcomes
3.1 Relevance of Objectives, Design and Implementation
Rating of Relevance of Objectives: High
54. The project objectives at appraisal were highly relevant to Sri Lanka’s needs and in line
with the priorities of the CAS for FY2003–06 that aimed to improve social and economic inclusion
of the poor and facilitate broad-based economic growth. Both the government and Bank strategies
highly prioritized the development of road infrastructure and recognized its contribution to the
development of the private sector and the desired increase in revenues to achieve higher levels of
public investment. Improvement of the road network to maintainable conditions was considered
a necessary condition to sustain the expected surge in economic growth.
55. It cannot be overemphasized that civil conflicts had severely impacted the country for a
number of years and had contributed to the poor condition of the road network. Its rehabilitation
was essential to the country’s recovery process.
4 A new project with many of these features was approved on May 9, 2016.
- 18 -
56. The project objectives were and continue to be highly relevant and fully aligned with the
current FY2013–16 CPS, which identified three areas for the World Bank Group’s engagement to
assist Sri Lanka in addressing its long-term strategic and structural development challenges and
middle-income country agenda. The CPS’ areas of focus are linked to the three central goals of
the government's Mahinda Chintana vision, namely: (a) facilitating sustained private and public
investment; (b) supporting structural shifts in the economy; and (c) improving living standards and
social inclusion. The Bank supports Sri Lanka’s transport sector with the objective of improving
the quality and sustainability of roads.
57. The project was linked to the third central goal of the government’s Mahinda Chintana
vision and the third pillar of the CPS. The third goal was to ensure access to basic, related services
and provide improved quality of services, and the Project was fully aligned with this objective.
The project supported the government’s efforts to improve connectivity and enhance
competitiveness through lowering of transportation costs and providing better and all-weather
accessibility to related services for 80 percent of Sri Lanka’s population that live in rural areas.
The improved level of services resulted in enhanced highway safety, reduced travel time, and lower
transportation costs, which resulted in more social inclusion and improved living standards.
Rating of Relevance of Design: Modest
58. The project design had a balanced mix of civil works and institutional strengthening
components which were closely aligned with the government’s reform priorities. The lending
instrument was Specific Investment Lending (SIL) and was found to be the appropriate instrument
for the Bank to re-engage in the Transport sector after being absent for decades. The Project’s
design recognized the need to lower transportation costs and the sustainable delivery of a road
system, which is an appropriate description of the objectives.
59. However, as mentioned previously, the M&E framework did not have an adequate
mechanism to attribute the impact of these activities directly to the project which raises
attributional questions. Given the scope of the project and its components, the formulation of the
PDO was overly ambitious. In addition, the establishment of some baselines and target values
were shown to be problematic because of weaknesses in the data which was not fully resolved
until the second additional financing.
60. While the above weaknesses should not be understated, and are the direct cause for the
Modest rating for Relevance of Design, it should not be lost that the project design had some highly
relevant and innovative features that have had, and continue to have, a transformative influence on
road maintenance, contracting, safety, and financing in Sri Lanka.
3.2 Achievement of Project Development Objectives
Rating: Substantial (RSAP-1) and Substantial (RSAP-2)
61. The project was initially scheduled to close on September 30, 2011, although two
additional financings and several restructurings extended the closing date to June 30, 2015. In
addition to the closing date changes, there were significant changes to the results framework. With
this in view, the ICR used a split evaluation as outlined in the ICR Guidelines. As the primary
demarcation over the life of the project was the second AF, which was a scale-up, and which
- 19 -
introduced new activities and significant changes in the results framework, the project has been
evaluated based on this milestone. The two phases comprise RSAP-1, which includes the parent
project up through the first AF; and RSAP-2, which includes the project from the second AF
through its closing.
62. The PDO was to reduce the transport costs through sustainable delivery of an efficient
national road system comprising a network of 12,000 km. While most of the civil works were
limited to about 6% of the network roads, the project counterbalanced the limited civil works with
a broad range of institutional activities that included capacity building and financial support to the
Road Maintenance Trust Fund. Support funded improved network maintenance, promoted greater
transparency in the allocation of resources and disbursement of funds, and carried out efficient
monitoring of the maintenance programs. Between 2005 and 2013, the allocation for road
maintenance channeled through the RMTF increased from $13 million to $63 million.
63. Support was also provided for the establishment of a Road Asset Management System,
which was a key component of the second additional financing aimed at building capacity and
strengthening systems within the RMTF and RDA relating to road maintenance, and geared to
better maintaining and prioritizing the country network of national roads. Funding was provided
for periodic maintenance, training of staff, developing the right tools and developing a strategy for
moving from a post-conflict system of historically poor road maintenance to a modernized and
competitive working national system.
64. The Project PDO and some of the associated outcome indicators were not ideally
formulated to align with the project scope. As mentioned in the M&E section, this weakens certain
causal links. At the same time, discounting achievements because of poor formulation risks
discounting substantial outcomes.
First Objective - Lowering Transport Costs
65. Lowering transportation costs has been monitored and evaluated through outcome
indicators via reducing average network VoCs, average network roughness, share of network roads
in poor and bad condition, and maintenance expenditure for project roads. Taking into account that
each indicator is split by the multiple implementation periods, the project achieved, and in many
cases exceeded, the targets of the large majority of these indicators.
Reduction in VoC and Roughness
66. Reduction in VoC was fully achieved for RSAP-1. The target was a 3.8 percent decrease;
the actual decrease was closer to 35 percent. As mentioned above, however, the result should be
interpreted with caution as the VoC was overestimated at the appraisal stage of RSAP-1. For
RSAP-2, reduction in VoC was not fully achieved. Although the decrease achieved about a 5
percent reduction (improving upon RSAP-1’s target), the target had been reset in the 2nd AF from
3.8 percent to 28 percent. In contrast, the roughness (IRI) of the Project roads was decreased
substantially and the target was fully achieved. This duel result suggests that despite significant
improvements in road quality there was only a modest reduction in VoC. This could be due to
increased traffic on the roads due to the road improvements, or increased speeds of vehicles on the
roads, resulting in higher fuel consumption (or both). The Borrower has suggested, although it
- 20 -
awaits confirmation, that subsequent to the cessation of the conflict in 2009, the amount of funding
to the road sector increased substantially, but was disproportionately targeted to rebuild the
network in areas that had suffered severely from the conflict. However, the road network in the
conflict affected areas does not carry as much traffic as the road network in the urban areas, and
thus, fewer users would result in a smaller impact on the network’s VoC.
67. The achievement of the first objective was also linked to project outputs measured by
intermediate indicators, namely, to lowering transportation costs through resurfacing of national
roads, improving rural roads, increasing of periodic maintenance, and increasing annual
maintenance expenditure, which were almost all achieved, and in several cases, exceeded.
Second Objective – Sustainable delivery of an efficient national road system
Increase in Annual Maintenance Expenditure
68. The achievement of this second objective was linked to project outputs that were
implemented successfully, including: capacity building, the establishment of the RMTF, the rural
roads maintenance pilot that included the development of a rural roads maintenance strategy,
country rural roads investment plan and database; safety capacity assessment; and a 5 percent
reduction in traffic accidents in the selected demonstration corridor as a result of measures
supported by the Project.
69. The expenditures of $0.66 million and $19 million for institutional strengthening in
(RSAP-1 and RSAP-2, respectively) resulted in building capacity for data collection and analyses,
design of enhanced decision support systems, better internal organizational management, and
additional support for maintenance financing for periodic maintenance work.
70. As noted under the first objective, though with different emphasis, the project supported
the establishment of RAMS and the RMTF, two of the highlights of the project which have had a
transformative impact. RMTF was set up to ensure the sustainable and transparent allocation of
resources and funds, but also carries out efficient monitoring of road maintenance, while RAMS
aids RDA in building capacity to optimize the selection of roads for maintenance and align its
processes toward minimizing costs. A related notable achievement has been the strengthening of
the capacity of local governments to prioritize road expenditures and select appropriate technical
interventions for rural road maintenance. The Project substantially achieved the intermediate
indicators that assess this objective.
71. The outcome indicator related to sustainability was to monitor the funding levels for yearly
maintenance for periodic and routine maintenance works. The original target for RSAP-1 was
substantially achieved; $44 million (up from $10 million) against the target value of $46.3 million.
The target for RSAP-1I was not achieved, LKR 5 billion against the target of LKR 6.6 billion.
The indicator, however, does not take into account that GoSL has increasingly channeled funds
for periodic maintenance through other projects not reflected under the budget item for RMTF. In
addition, GoSL channels funding for improvements which include periodic maintenance
expenditure which cannot be easily separated as a result of streamlining budgetary processes, and
recently moving to a multi-year budgetary system.
- 21 -
72. In sum, although the results framework had inherent weaknesses, the project accomplished
most of its major objectives: resurfacing, rehabilitating or maintaining over 800 km of roads,
developing budgetary systems that are generating institutional changes and new approaches to road
maintenance and financing; innovating in programs for road safety; and piloting new methods and
strategies for rural roads maintenance. Taken together, the cumulative impact of these activities,
together with the achievement of most of the project targets, suggests the project had a major
impact on the improvements to the national network. Quoting from the Borrower’s ICR: “The
culture change that RSAP catalyzed that ranged from the improved practice of safeguards and an
effective grievance redress system to better efficiency in all aspects of project design and
implementation will be key to the sustainability of its outcomes. The setting up of the RMTF and
maintenance systems, the building of capacity within the RDA, including the capacity to manage
contracts, and the development of the private contracting industry, are all key factors that influence
sustainability.”
The efficacy of the project is rated Substantial.
Table 4. Assessment of Efficacy Pre- and Post- Restructuring
Table 1. Assessment
of Efficacy Pre- and
Post- Restructuring PDO Indicator
Targets Actual Values Percent Achieved
Aggregate Rating of Efficacy: Original Efficacy – Substantial ; Revised Efficacy - Substantial
Specific Objective 1: Main objective - Lower Transport Costs through sustainable delivery of an efficient national
road system
Rating (against revised target): Substantial
RSAP-1
(i) Reduction in average
network VoC by 3.8%,
Original:
LKR 22.9 per
km
Actual value: 14.97 Original: Achieved
The value achieved in 2006/08 was 15.37/km
and the mission considered VoC to be very
low and after examination of the estimation,
it was found that the methodology was
unknown (AM-June 2008
(ii) Reduction in IRI in
average network
Original: 8.39
Actual value: 6.45 Original: Achieved
Similar as above, the survey data collected in
2004 was being used. It was found that only
226 km out of 9913 km of national highways
were surveyed for IRI in the year 2004 or
before. Therefore the source of the
information of the baseline year 2004 of IRI
9.5 could not be known.
(iii) Reduction in
percentage of the network
in poor and bad condition
Original:35%
Actual value: 44% Achieved: 70%
(iv) Increase in annual
maintenance expenditure
Original:
$46.3 million
Actual value: 44 Achieved 95%
- 22 -
RSAP-1I
(i) Reduction in average
network VoC
Original:
LKR 10.5
Actual value: 13.88
Original target of 3.8% achieved; revised
target of 28% not achieved
(ii) Reduction in IRI in
average network
Original: 5.9 Actual value: 5.9 Achieved
(iii) Reduction in
percentage of the network
in poor and bad condition
Original:
35%
Actual value: 35% Achieved
(iv) Progressive increase
in annual road
maintenance
Original: $66
million
Actual value: $50
million
Not achieved
(v) Improved level of
satisfaction of road users
Original:38.3
0
Actual value: 68.15 Achieved
Intermediate outcomes
RSAP-1 (i) # of KM of National
roads resurfaced
Original: 620 Actual value:
617km
Achieved
(ii) reduction in IRI for
project roads (620km)
Original: 2.9 Actual value: 2.8 Achieved
(iii) Reduced travel time
on project roads (620km)
Original: 42 Revised (split) Achieved
(iv) # of km of Rural
Roads improved
Original: 635
Revised: 157
Actual value:
167km
Original: Revised from spot improvement to
rehabilitation due to rural strategy.
Revised: Achieved
(v) Reduced travel time
on project rural roads by
10%
Original: 4% Actual value: 60% Achieved
(vi) Relevant staff to be
trained in road asset
management
Original:
50%
Actual value: 67% Achieved
RSAP-1I (i) # of KM of National
roads resurfaced
Original: 134
Revised: 78
Actual value:
78
Revised: Achieved
(ii) reduction in IRI for
project roads
Original:2.8
Revised: 2.4
Actual value: 2.33
Revised value: 2
Original: Achieved
Revised: Achieved
(iii) Reduced travel time
on project roads
Original: 42
Revised: 12.5
Revised: 23.9
Actual value: 40
Actual value: 11.31
Actual value: 23.58
Achieved
Achieved
Achieved
(iv) Periodic maintenance Original:
60km
Actual value: 64.50 Achieved
- 23 -
3.3 Efficiency
Rating: Modest (RSAP-1) and Substantial (RSAP-2)
73. The national roads sections rehabilitated under the parent project were selected on the basis
of development priorities and economic viability and assessed during appraisal using the Highway
Development and Management Model (HDM-4) software. The net present value (NPV) of the
investments in the 15 original road sections was estimated at $103 million and the economic
internal rate of return (EIRR) at 31 percent. Sensitivity analysis showed that changes in costs and
benefit scenarios would have limited impact on the results. The analysis of the ICR is conducted
for 12 road sections. After project completion, the NPV is estimated to be $225 million and the
economic internal rate of return (EIRR) is 29 percent. This difference in the NPV values (between
the PAD and ICR) is driven by a difference in the assumptions of the PAD and ICR—the analysis
in the PAD is conducted for an 11-year time horizon while the analysis of the ICR is conducted
for a 20-year time horizon. If we limit the time horizon of the ICR analysis to 11 years then the
resulting NPV is $23.6 million and EIRR is 17 percent. This reduction in EIRR and NPV is
consistent with the increase in construction costs between the initial economic analysis and the
revised analysis. With cost overruns ranging from 51.4 percent to 132.4 percent, the efficiency of
this phase of project, that is, RSAP-1, is rated as Modest.
74. In the roads financed under the Second AF, the economic analysis was carried out for both
sections using HDM-4 by the RDA. Here we compare the results for the ICR to those in the
Restructuring Paper. The estimates of NPV and the EIRR for the K-T section, A002, and A003
increased after project completion. For the KT section, the NPV and EIRR at the time of
restructuring was $24 million and 21 percent, respectively—the NPV is $8 million higher and the
EIRR is 3 percentage points higher after project completion. For A002, the NPV and EIRR at the
time of restructuring was $101 million and 29 percent, respectively—the NPV is $28 million
higher and the EIRR is 10 percentage points higher after project completion. For A003, the NPV
and EIRR at the time of restructuring was $132 million and 47 percent, respectively—the NPV is
$14 million higher and the EIRR is 4 percentage points higher after project completion5. With
cost overruns ranging from negative to 20.8 percent, the efficiency of this phase of project RSAP-
2 is rated as Substantial.
75. Table 5 summarizes the main results, comparing the EIRRs before and after the Project.
All EIRRs after project completion remain above the 12 percent threshold. For both RSAP-1 and
RSAP-1I the benefits from travel time savings are higher than the benefits from vehicle operating
cost savings.
5 The analysis at both the appraisal and ICR stage is conducted using HDM4 which is calibrated for Sri Lanka, it is based on the same time
horizon and accounts for the same benefits (VoC and VoT).
- 24 -
Table 5. Results of Economic Analysis-Before and After the Project
Length
EIRR at
Appraisal
(%)
NPV at appraisal
($, millions)
EIRR at ICR
(%)
NPV at ICR
($, millions)
620 km(using
different time
horizon)
31 103 29 225
620 km (using
same time
horizon)
31 103 17 24
Before Restructuring
134 km
(A006) 51 522 Dropped and replaced with A002, A003
After Restructuring
K-T Section 21 24 24 32
A002 29 101 39 129
A003 47 132 51 146
76. Final results were heavily dependent on the soundness of input data and quality of analyses.
This remained a matter of concern during project life. The Bank mission highlighted the issue of
quality of data and more need of analyses to apprehend the scenarios better.6 Therefore, the ICR
team has taken cost overruns into account as well for assessment of efficiency. The project's overall
efficiency was rated as Modest (rounding down the efficiencies of two phases of the project
because the parent project is given more weightage due to more cost).
3.4 Justification of Overall Outcome Rating
Rating: Moderately Satisfactory
77. The ICR considers the overall outcome of the Project as Moderately Satisfactory. The
rating is based on the relevance of objectives, relevance of design, achievement of PDOs, and
efficiency, and using the weighted system, before and after the Second AF, which was a major
change in scope of work. The related indicator values during project life were rounded off to the
nearest whole number. The assessment is given in Table 6.
6 AM of mission in December 2013. The mission discussed the shortcomings in development of asset management
system in the RDA, highlighting data management issues.
- 25 -
Table 6. Assessment of Overall Project Outcome
Against Original
Outcome
Indicators before
2nd Restructuring
Against Revised
Outcome Indicators
after 2nd
Restructuring Overall Comments
1 Relevance to
objectives and design Substantial Substantial – –
2 Achievement of
project outcome Substantial Substantial – –
3 Efficiency Modest Substantial – –
4 Overall rating Moderately
Satisfactory Satisfactory – –
5 Rating value 4 5 – –
6
Weight (% disbursed
before/after 2nd
Restructuring)
57 43 – –
7 Weighted value 2.28 2.15 4.43 Rounded to 4,
which arrives at
Moderately
Satisfactory 8 Final rating – –
Moderately
Satisfactory
3.5 Overarching Themes, Other Outcomes and Impacts
(a) Poverty Impacts, Gender Aspects, and Social Development
78. The project is expected to have had an indirect positive impact on poverty and social
development—improving transport conditions fuels the economy, creating jobs, and access to
markets. Improved transport conditions facilitate better connected communities, foster access to
social facilities, and reinforce social nets. Poverty impact and social development were higher-
level objectives of the Project success and have not been specifically assessed.
(b) Institutional Change/Strengthening
79. The project collaboration has had important benefits in driving the institutional reform
agenda for road asset management. The Project financed several courses to improve the capacity
of the RDA and the construction industry in areas of construction capacity, maintenance, asset
valuation, preservation, highway safety, environment and social safeguards, FM, and procurement
management.
80. The project made significant contributions to institutional strengthening of Sri Lanka’s
transport sector. In particular the Project:
Provided technical assistance for the strengthening of procurement, planning, and contract
management.
Improved the capacity to resolve social and environmental safeguards issues by training
RDA and other implementing agencies,
Provided capacity building in the functionality of the RMTF,
- 26 -
Strengthened RDA to design and supervise consultants’ and contractors’ work including
laboratory tests, etc.,
Strengthened RDA to work with other inter agencies such as utilities, water body, police
etc, and
Supplied technical Assistance in Asset Management, HIMS, PMS, HDM-4, inventory,
selection, prioritization, database for rural roads.
(c) Other Unintended Outcomes and Impacts (positive or negative)
81. There were no noticeable or irreversible negative impacts of this project.
3.6 Summary of Findings of Beneficiary Survey and/or Stakeholder Workshops
82. The ICR team carried out a workshop with stakeholders during the mission of June 8-12,
in order to obtain their impressions and lessons learned. The workshop was attended by a large
audience from the various government agencies, PMU, contractors, consultants, and beneficiaries
who provided valuable input for the ICR. This workshop sought to capture the lessons learned to
improve the design of future transport projects in Sri Lanka. The findings of this workshop were
rich and are presented in annex 6.
4. Assessment of Risk to Development Outcome
Rating: High
83. The joint strategy by the GoSL to rehabilitate the national road network along with the
rural road project was supported through a collaborative effort of the Bank, ADB, and JICA that
agreed on funding the maintenance backlog which affected the road network. Sustainability of the
road network largely depends on adequate maintenance; thus, the focus of the Project on
supporting the RDA in developing capacity in assets management and reducing the backlog in
maintenance was critically important. Proper maintenance of the road assets remains one of the
priorities in the transport sector.
84. The risk to the development outcome is High. It is clear that through persistent efforts and
consistent programs, GoSL has managed to improve the road network during the past 10 years. It
has continued gradual progress in strengthening road management at the national and rural levels,
brought increased transparency to the allocation of resources through the use of the RMTF, and is
working to put in place the right institutions and policies to secure continued inroads in traffic
safety. However, there is a significant risk to relaxing the level of funding for road maintenance
as maintenance budgets for roads infrastructure may be crowded out by large investments in new
construction and for works stated in this section.
85. Political will to invest in the maintenance of roads is critical. In this case, it was witnessed
that with the change of regime, the interim government reduced the budgetary allocation for road
maintenance from LKR 6.6 billion to LKR 5 billion.
- 27 -
86. From a broader perspective, the financing of the sector continues to raise doubts in its
capacity to meet the actual needs of the road network with regard to rehabilitation and
maintenance. Although the increases in road maintenance budget allocations made it possible to
partially catch up with the road maintenance backlog, the current budget is insufficient to mitigate
road deterioration in the coming years.7 This means that any additional resources allocated to the
road rehabilitation and maintenance will reduce the extent of the expected deterioration rather than
contribute to absolute improvements on the road network.
5. Assessment of Bank and Borrower Performance
5.1 Bank Performance
(a) Bank Performance in Ensuring Quality at Entry
Rating: Moderately Satisfactory
87. The Bank's performance during the preparatory period was Moderately Satisfactory.
Overall, the Project was well prepared and reflected the government’s priorities at the time of the
appraisal. The project design included: (a) the incorporation of most lessons learned; (b) the
pragmatic approach for dealing with unknowns in the rural roads sector; (c) identification of most
of risks early in the Project; and (d) strong attention to safeguards.
88. The Bank's performance, with regard to the strategic relevance and approach and paying
adequate attention to fiduciary and safeguards arrangements was satisfactory. The Bank team was
comprised of experienced professionals who worked with the GoSL and development partners on
project preparation. The project was also designed based on the GoSL’s development strategy and
in the framework of the CAS and donor transport strategy. In this respect, there was a strong Bank
effort to coordinate its interventions in the transport sector with ongoing efforts from other
international financial organizations, particularly ADB and JICA.
89. The project was designed taking into account the insurgency in Sri Lanka and its impacts,
which exacerbated the lack of available vital data at entry, the nonexistent or limited capacity of
the implementing agency in RAMS practices, the relative inexperience of the local private
construction industry, and the need to address the country’s huge backlog of road maintenance
through a systematic and programmatic approach. The urgency of the crisis made moving quickly
a high priority, thus limiting the amount of time for preparation. The team handled most of these
challenges well. However, as explained in previous sections, the PDO and associated indicators
were overly ambitious and disproportionate to the Project scope, particularly for a post conflict
affected state. The Results Framework was inadequately designed, and in addition there were
7 Final Book; Directions and Destinations by World Bank Group Sri Lanka. Page 6; “road maintenance has been
chronically under-funded across the different types of roads. The total funding requirement for periodic and routine
maintenance of roads from 2007 to 2013 was approximately LKR 81 billion, but only LKR 38 billion was made
available during the period.”
- 28 -
some causal disconnects between inputs, outputs and outcomes which made it difficult to assess
the contribution and achievement of the Project activities as stated in the PAD.
90. Keeping this in mind, the quality at entry is rated as Moderately Satisfactory, although
QAG’s rating was satisfactory. (Annex 9).
(b) Quality of Supervision
Rating: Moderately Satisfactory
91. The Bank provided constant and appropriate implementation support to the borrower and
took proactive action on issues that arose during implementation. Clear examples of this have been
the prompt attention to process two AF operations, explained previously in this ICR. The operation
took into account the priorities of the borrower and the need to ‘fine tune’ the design of the project,
incorporating a focus on road traffic safety issues and tailoring the design and supervision of civil
works to the specific needs of Sri Lanka. The timely processing of the 2nd AF was pivotal in
nature to ensure continuity of the Bank's engagement in the country with already well performing
implementation arrangements. The Bank also provided special training on the use of HDM-4,
procurement, contract management, social and environment management to RDA.
92. The Bank team carried out at least two implementation support missions per year. The
field-based Task Team Leader and other team members worked directly with the client and ensured
timely responses. Continuity in the team was maintained from preparation through completion.
Implementation support extended beyond operational missions. The task team possessed the
appropriate skills mix with the technical, institutional, fiduciary, and safeguards knowledge. The
Task Team had the experience to work effectively with the client, review documentation and
provide advice on the quality of works. The team recommended new approaches in the
implementation of institutional support components which was appreciated by the client. This
resulted in an excellent integration of procurement supervision activities with the overall
supervision effort, and for the consistency, clarity, and comprehensiveness of documentation of
safeguards supervision.
93. In addition, the Bank helped to introduce and include environmental clauses as part of the
contract documents of rehabilitation works. Because of this project, many of the local contractors
adopted the same preventive and remedial environmental protection measures on other non-Bank
financed projects that previously had had no such requirements. Therefore, the Project was
instrumental in elevating the awareness of using high standards of safeguards practiced by several
contractors.
94. The Bank Team, however, needed to have updated the M&E Results Framework more
vigorously and on a more timely basis. As the weakness of the data became apparent in the early
years of the project, efforts should have been made to prioritize data collection and analysis. If it
became clear that data was not going to become available, then baselines and targets (and perhaps,
objectives) should have been reassessed. While the results framework was revised during the
second AF, this was five years into the project. In addition, at no time during project
implementation – including the second AF, or the restructuring in 2013 – was the issue of
attribution ever considered. If addressed earlier, indicators/objectives affecting attribution could
- 29 -
have been revised, creating stronger links to the PDO, and bringing a more robust coherence to the
results framework.
(c) Justification of Rating for Overall Bank Performance
Rating: Moderately Satisfactory
95. The Bank team put substantial effort in project preparation and implementation support,
which led to the Project (mostly) achieving its development goals. The implementation support
was provided amidst the escalating conflict where in certain parts of the project period the
particular roads could not be accessed due to terrorist activities. The Bank, albeit with some
shortcomings in design and supervision, achieved implementation of a project with complex civil
works, challenging safeguards features, and the need to manage a large multidisciplinary team, all
that in a pre and post conflict state for decade.
96. Therefore, considering the ratings for the Bank's performance at entry and quality of
supervision Bank performance is rated Moderately Satisfactory.
5.2 Borrower Performance
(a) Government Performance
Rating: Moderately Satisfactory
97. The GoSL remained fully supportive of the efforts for smooth implementation of the civil
works component of the Project, the expansion to the whole country of the strategy for rural roads
maintenance, and the successful implementation of a pilot traffic safety effort. The GoSL was
instrumental in reshaping the road maintenance regime in the country; its commitment made it
possible to achieve a majority of the performance indicators.
98. Shortages in counterpart funds were evidenced at different points of project
implementation; however, the government was able to provide the funds at a later stage. Actions
toward fully launching the RMTF dragged on during the first three years of the Project but with
continuous engagement of the Bank's Task Team and approval of the Second AF, the fund became
operational, and the GoSL was able to establish the RMTF. Maintenance allocations during the
life of the Project were mostly in line with the agreed amounts, and the output indicator related to
maintenance expenditure was mostly achieved.
99. The Government's performance is rated Moderately Satisfactory due to delays in the
release of counterpart funds and delay of a fully functioning RMTF, which impeded the
implementation of the maintenance component.
- 30 -
(b) Implementing Agency or Agencies Performance
Rating: Moderately Satisfactory
100. The project was implemented by a dedicated PMU. Despite initial problems with staffing
due to internal regulations affecting outside recruitment and a rather high rotation of staff because
of the then ongoing construction boom and high demand for skilled professionals, the PMU was
helpful in carrying out the implementation of the Project related activities. The PMU had adequate
reporting systems, submitting bi-annual progress reports to the Bank that contained updated
information on project financing, procurement, physical progress of works, safeguards, and key
implementation issues.
101. However, the implementing agency failed to provide key technical performance data
(roughness, condition, and traffic survey report) which was reflected through ISRs and AMs. The
provision of this data on a yearly basis was a covenant.
102. The main weakness of the PMU and the RDA related to contract management and close
control with respect to growing variations which were found to be ineligible. For instance, physical
variations on the 12 civil work contracts ranged from 7% to 88%. The cost increase by the end of
the project was 34% more than the original contracts cost and 11% over the variations at MTR
which stood at LKRs. 3.9 billion. The implementing agency showed a lack of proactivity in the
use of remedial actions to address the issue of underperforming supervision consultants. The
project faced cost and time overruns throughout project life. Many quality-related issues were
highlighted and were attributed to non-satisfactory performance of the supervisory consultant,
poor designs, and engineering practices. Premature failures in pavements in three road sections
were witnessed.
103. The PMU and RDA could have avoided many of these issues through better monitoring
and supervision and proper contract management. Overall, the implementing agencies
performance is Moderately Satisfactory.
(c) Justification of Rating for Overall Borrower Performance
Rating: Moderately Satisfactory
104. Based on the above considerations, the Borrower’s performance is rated Moderately
Satisfactory.
6. Lessons Learned
105. The long-term and continued Bank’s engagement and coordination efforts in the
country’s road subsector provides a robust platform for well performing projects. The
Bank’s continued presence in the transport sector helped to strengthen and enhance supervision
effectiveness and deepen understanding issues in Sri Lanka’s road subsector. The Bank has been
active in the subsector since 2004 with consistent objectives. This continued presence has allowed
for the strengthening of the transport sector across the board through the introduction of innovative
road stabilization programs and sound periodic and routine road maintenance policies.
- 31 -
106. Extensive turnover of the key RDA project team weakens the institutional memory.
Continued RDA key staff is pivotal for a project's success. Continuity of the same project team
and task team leader of the Bank from the preparation to completion helped achieve most of its
PDOs. The high turnover of many project team members of the RDA (four project directors were
changed during the Project) resulted in many problems related to cost and schedule overruns and
quality of civil works.
107. A dedicated project management consultant will help both the Bank and the Borrower
to have more effective control on project implementation. The RSAP project suffered major cost
overruns and issues with quality and risk management. These issues are related to project
management implementation. In the case of the RDA, the authority was assisted by supervisory
consultants and individual consultants but close investigation of their terms of reference indicated
that these consultants were subject to area specialists (engineering, finance, etc.) and they were
given additional segmental project management activities. In the era of project management role
delineation, the engagement of a dedicated project management consultant on big projects will
help the Borrower in their project management effort.
108. Adopting sustainable funding sources for the RMTF is key for its optimum functioning.
Though setting-up institutional arrangement for the creation of a road fund seems simple,
implementation of associated Policy and Legislative Frameworks throughout the sector becomes
difficult. Nevertheless, autonomous arrangement of the RMTF and road funds provide an
opportunity for progress on management, accountability, transparency, and increased awareness
on the need to address long-neglected maintenance. Whereas the concept of highway maintenance
and development financing through marginal social costing is very popular and remained the
essence of this project, another revenue stream from road user fees might have added to the much-
needed additional source of funding.
109. Formulating a proper M&E system (with improved and adequate Results Framework)
is instrumental for the evaluation of project. The choice of the PDO indicators should take into
account the type of data that can be collected during implementation. The Bank should ask the
Borrower to provide reliable data with the frequency stated in covenants. The baseline and target
values should be based on reliable data, should be realistic, and should be based on sound
engineering.
110. Importance of RAMS practices is key. One of the achievements of this project was to
highlight the importance of a comprehensive system for maintaining the road network through
RAMS practices. RAMS not only helped in reducing the transportation costs and increasing public
perception about the importance of maintenance but was also instrumental in supporting the
national economy through better and sustainable connectivity and mobility. Further enhancements
in the current RAMS will help the transportation sector manifold in the country.
7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners
(a) Borrower/implementing agencies
- 32 -
111. The Borrower’s ICR, as well as their comments on this document are included in
Annex 7. Any corrections and/or other changes that have been suggested have been incorporated
where appropriate and where evidence was available to substantiate recommended changes.
(b) Cofinanciers.
Not applicable.
(c) Other partners and stakeholders.
Not applicable
- 33 -
Annex 1. Project Costs and Financing
(a) Project Cost by Component (in $, millions equivalent)
Components
Appraisal
Estimate
(Original)
($, millions)
Revised
Estimate
($,
millions)
Actual/Fi
nal
($,
millions)
Percentage
of
Appraisal
Percentage
of Revised
Estimate
Component 1 of Parent Project:
Maintenance and Rehabilitation of National
Roads
112.51 179.15 239.00 78.06 49.23
Component 2 of Parent Project:
Maintenance and Rehabilitation of Rural Roads 10.04 10.04 13.07 6.97 2.76
Component 3 of Parent Project:
Institutional Strengthening and Policy Support 0.60 0.60 0.66 0.42 0.16
Second AF:
Rehabilitation of Priority National Roads and
Maintenance Finance
– 81.00
19.00
63.06
12.07 0.00 27.48
Total Baseline Cost 123.14 363.87 327.86 85.44 79.64
Unallocated (physical and price contingencies) 20.98 74.08 0 14.56 20.36
Total Project Costs 144.12 363.97 327.86 – –
(b) Financing
Source of Funds Appraisal Estimate ($,
millions)
Actual/Latest
Estimate ($,
millions)
Percentage of
Appraisal
Percentage of
Actual/ Latest
Borrower 44.12 54.63 12.89 17.64
IDA 298.00 255.00 87.08 82.36
Total 342.22 309.63 – –
(c) Project Cost by RSAP-1 and RSAP-1I
Components
RSAP-1
(Original + First AF)
2005
Appraisal Estimate
(Original)
($, millions)
2008
Annex 1 of PP
Revised Estimate
($, millions)
2010/11
Actual/Final
($, millions)
Maintenance and
Rehabilitation of National
Roads
112.51 179.15 239.00
Maintenance and
Rehabilitation of Rural
Roads
10.04 10.04 13.07
Institutional Strengthening
and Policy Support 0.60 0.60 0.66
Total Baseline Cost 123.14 189.79 252.73
- 34 -
Unallocated (physical and
price contingencies) 20.98
74.08
Also includes VAT 0.00
**Total Project Costs 144.12 263.87 252.73
Components
RSAP-1I (Second AF)
2011
Appraisal Estimate
(Original)
($, millions)
2013
Annex 1 of PP
Revised Estimate
($, millions)
2015
Actual/Final
($, millions)
Rehabilitation of Priority
National Highways 85.50 81.00 63.06
Maintenance Finance and
Institutional Strengthening 14.50 19.00 12.07
**Total Project Costs 100.00 100.00 75.13
** Total (Original +First
AF+Second AF) 244.12 363.87 327.86
(d) Financing per Credit and Share
Source of Funds Appraisal Estimate
($, millions)
*Actual Latest
($, millions)
CR 4138
Borrower 44.12 54.63
IDA 100.00 96.40
CR 4429
Borrower 0.00 0.00
IDA 98.10 83.60
CR 4906
Borrower 0 0
IDA 100.00 75.00
Total
Borrower 44.12 54.63
IDA 298.10 255.00
Grand Total 342.22 309.63
Note: *Current value for client connection.
- 35 -
Annex 2. Outputs by Component
Output Indicators Status at
Closing Actual Achievement %
Baseline Original
Target
1st Revised
Target
Second AF
2nd
Revised
Target
Component 1. Maintenance and Rehabilitation of National Roads
RSAP-1 (Parent Project and First AF)
National roads resurfacing and
improvement (km) 0 620 – – 617 Successfully achieved target for national roads
Reduction in IRI for project roads 7.8 2.9 – – 2.8 Successfully achieved
RSAP-1I (Second AF)
National roads resurfacing and
improvement (km) 0 134 – 78 78
Successfully achieved revised target for national
roads
Reduction in IRI for project roads A6 6.0
A2 4.3
A3 3.1
2.8
–
2.4
2.4
2.33
1.9
2.0
Successfully achieved
Reduction of travel time
A6 66
A2 13.8
A3 26.5
42
–
12.5
23.9
40
11.31
23.58
Successfully achieved
Component 2. Maintenance and Rehabilitation of Rural Roads
RSAP-1 (Parent Project and First AF)
Rural Roads resurfacing and
improvement (km) 0 635 – 157 162.3
Achieved. Formally revised target was reduced
and restricted in 2013.
Reduction of travel time (%) 10 – – 60 Successfully achieved
Component 3. Institutional Strengthening and Policy Support
RSAP-1 (Parent Project and First AF)
Establishment of and fully
operational bodies such as the
RMTF, Board Trustee, TAC, and
Trust Fund Secretariat
– – – – – Successfully achieved
50% of relevant staff in the
Planning and Maintenance of RDA
trained in road asset management 0 50% – – 67%
Successfully achieved
Training on Asset management, HDM-4,
Maintenance Manual, Contract management,
Social and Environment Management, PPP’s in
highways
- 36 -
Rural road Maintenance
Strategy/Manual Successfully prepared and delivered and used.
Rural Road Database established
Successfully established and used for the whole
country. Out of 342 Local Authorities to be
covered, the road databases and investment land
for226 Las have already been prepared
RSAP-1I (Second AF)
Annual road maintenance program
approved by the RMTF New Approved – – Approved Successfully achieved
About 60 km of national roads on
which periodic maintenance has
been carried out
New 60 – – 64.50 Successfully achieved
Rural road Strategy/Manual
Note: A2 =; A3 =; TAC =;
- 37 -
Annex 3. Economic and Financial Analysis
Introduction
1. Economic analysis is performed to assess whether the economic benefits of the Project are
higher than its economic cost and whether these benefits are similar to those estimated at the
appraisal stage. We accomplish this by first assessing whether the economic internal rate of return
(EIRR)8 is greater than 12% and then comparing it to the EIRR estimated at the appraisal stage.
Framework
Assumptions:
2. The following general assumptions are made when performing the economic analysis:
The analysis is performed for a period of 20 years—the analysis period starts from the
construction commencement year since traffic is allowed to use the road during
construction.
Project discount rate is assumed to be 12%.
For the conversion rate it is assumed that USD 1 is equivalent to LKR 140.2871
The vehicle classification used in the analysis consists of 10 vehicle. The ten vehicle
types considered are medium goods vehicle (MGV), Van (VAN), medium bus (MBU),
light goods vehicle (LGV), motorcycle or scooter (MCL), three wheeler (TWL), car
(CAR), large bus (LBU), 3 axle truck (HG3), and articulated truck (ART).
To convert financial costs into economic costs a conversion factor of 0.97 is used
(based on the 2014 Central Bank data).
With vs. Without Project Scenario:
3. The without project case assumes that the current maintenance regime that allows for a
gradual deterioration of the road continues. The with-project case entails the actual rehabilitation
of the roads and subsequent improvement in road maintenance. It is assumed that there is minimal
routine maintenance in both scenarios with a slight improvement in the project case to reflect
current government intentions to sustain the conditions of the newly rehabilitated roads. Periodic
maintenance works items is assumed to vary with the surface type of the road while routine
maintenance works will not.
Costs and Benefits:
4. The economic benefits of improved road infrastructure is assumed to stem from two
sources: (1) time savings benefits (VoT) and (2) reduction in VoC. For the analysis, traffic volume
and growth data for each road was extracted from the relevant Feasibility Study Reports.
8 EIRR is the discount rate that equates the discounted stream of benefits and costs.
- 38 -
5. Project costs account for both improvements (road widening) and maintenance (routine
and periodic). To account for improvements the whole package is considered as a single section
and the cost per km varies for each package. Maintenance (routine and periodic) costs are recurring
and apply in both ‘with’ and ‘without’ project with some difference in the work items. These work
items depend on the general maintenance policy adopted by the RDA in their normal maintenance
works. A key difference in the modeling of the periodic and routine maintenance is that the former
is allowed to vary with the surface type of the road while the latter is not. The total capital costs
in financial terms for project were Rs. 30,059 Million or $214.3 Million. The breakdown of the
cost by contract is presented in table 3.1.
Table 3.1: Contract Package Details Contract
No. Road Length
Final Contract
Amount (Rs)
Date of
commencement
Actual Date of
Completion
WB/RSAP/CP/01
Rehabilitation and Improvement on Ingiriya-Ratnapura Rd
35.08 km 932,713,752.94 1-Mar-2006 27-Nov-2009
WB/RSAP/C
P/02
Rehabilitation and Improvement on
Nittambuwa-Kandy Road 75.30 km 2,683,861,789.60 15-Mar-2006 8-Dec-2009
WB/RSAP/CP/03
Rehabilitation and Improvement on Bandarawela-Haliela Road
22.14 km 980,242,714.82 6-Sep-2006 10-Jul-2009
WB/RSAP/C
P/04
Rehabilitation and Improvement on
Bandarawela-Haliela Road 20.200 km 829,534,965.36 6-Sep-2006 29-Jun-2009
WB/RSAP/C
P/05
Rehabilitation and Improvement on Galle - Deniyaya Road & Deniya
Akuressa
80.09 km 1,918,216,256.91 6-Nov-2006 5-Jan-2010
WB/RSAP/C
P/06
Rehabilitation and Improvement on Dengama - Mulatiyana Road and
Hakmana - Talahaduwa Road
22.98 km 948,393,818.31 21-Mar-2006 6-Jan-2009
WB/RSAP/C
P/08
Rehabilitation and Improvement on
Medawachchiya-Punewa Road 24.61 km 971,282,211.38 6-Nov-2006 11-Aug-2009
WB/RSAP/C
P/09
Rehabilitation and Improvement
onWellawaya-Siyambalanduwa 69.28 km 1,573,584,156.66 6-Nov-2006 19-Nov-2009
WB/RSAP/C
P/10
Rehabilitation and Improvement on
Siyambalanduwa-Ampara-Karathiv Road
77.83 km 1,763,152,639.85 6-Nov-2006 26-Mar-2010
WB/RSAP/C
P/11
Rehabilitation and Improvement on
Maradankadawala-Jayanthipura Road
59.90 km 1,897,490,215.49 5-Jan-2007 30-Jun-2009
WB/RSAP/C
P/12
Rehabilitation and Improvement on
Jayanthipura - Trikondimadu Road 68.66 km 2,286,806,255.81 24-Aug-2007 14-Aug-2009
WB/RSAP/CP/13
Rehabilitation and Improvement on Padeniya - Puttlam Road
61.37 km 1,768,861,093.87 8-Mar-2007 30-Jun-2009
WB/RSAP-
1I /KT/01
Rehabilitation and Improvements on
Ambepussa-Kurunegala-
Trincomalee Road (A06)from 157+000 km to 167+280 km &
Kantale to Perathuweli (B196) Road
10.2 km 916,085,524.85 11-Jul-2011 18-Oct-2012
WB/RSAP-1I/KT/ 02
Rehabilitation and Improvements on
Ambepussa-Kurunegala-Trincomalee Road (A06) from
167+280Km to 178+000Km
10.72 km 867,898,141.30 11-Jul-2011 18-Oct-2012
WB/RSAP-
1I/KT/ 03
Rehabilitation and Improvements on Ambepussa-Kurunegala-
Trincomalee Road (A06) from
178+000 Km to 190+000Km
12.0 km 740,367,191.80 11-Jul-2011 10-Oct-2012
WB/RSAP-
1I/KT/ 04
Rehabilitation and Improvements on
Ambepussa-Kurunegala-
Trincomalee Road (A06) from 190+000Km to199+300Km
9.3 km 986,889,478.40 11-Jul-2011 10-Oct-2012
WB/RSAP-
1I/WK/ICB 01 - Lot 01
Rehabilitation and Improvements on
Colombo – Galle - Hambanthota
Road (A02) from Maliban Junction to Cross Junction (from 13+275 km to
18+480 Km) and AB011 Road from
5.28 km 1,872,510,000.00 7-Jul-2013 31-Aug-2014
- 39 -
Cross Junction to Panadura Bridge
(from 0+000Km to 0+080Km)
WB/RSAP-
1I/WK/ICB
01 - Lot 02
Rehabilitation and Improvements on Colombo – Galle - Hambanthota
Road (A02) from Panadura Bridge to
Nalluruwa Junction (From 25+240 km to 30+300 km) and AB011 Road
from Cross Junction to Panadura
Bridge (from 0+080Km to 6+780Km)
11.76 km 2,786,250,000.00 7-Jul-2013 30-Apr-2015
WB/RSAP-
1I/WK/ICB
01 - Lot 03
Rehabilitation and Improvements on
Peliyagoda – Puttlam Road (A03) from Peliyagoda to Mahabage (from
0+600 km to 9+000 Km)
8.4 km 1,701,840,000.00 7-Jul-2013 31-Jan-2015
WB/RSAP-
1I/WK/ICB
01 - Lot 04
the Rehabilitation and Improvements
on Peliyagoda – Puttlam Road (A03)
from Mahabage to Ja-ela (from
9+000 km to 18+310 Km)
9.3 km 1,633,850,000.00 7-Jul-2013 31-Jan-2015
Analysis
6. Since the various phases of the Project started at different points in time, the economic
analysis for each phases is conducted for different time horizons—the economic analysis for
RSAP-1 is conducted from 2006 to 2025, the economic analysis for RSAP-1I phase I (sections A2
and A3) is conducted from 2012 to 2031, and the economic analysis for RSAP-1I phase II (section
A6) was conducted from 2011-2030. Therefore, we report NPV and EIRR for these three phases
separately.
7. Cost benefit analysis indicates that the Project achieved a favorable economic internal rate
of return (EIRR)—See table 3.2.
The EIRR for RSAP-1 is 29% and the NPV is $225 million;
The EIRR for RSAP-1I phase I is 44% and the NPV is $275 million; and
The EIRR for RSAP-1I phase II is 24% and the NPV is $32 million.
8. This indicates that the realized benefits of the Project were sufficient to make it a successful
for RSAP-1 and the two phases of RSAP-1I. Table 2 presents the breakdown of the NPV by road
sections. As expected, the NPV of benefits is positive for all road sections and the EIRRs for each
road section varies from 16% to 51%. All EIRRs are well above the 12% threshold.
- 40 -
Table 3.2: HDM-4 Analysis Summary
NPV (in Million)
Road Section EIRR Rupees USD
RSAP-1:
CP01-A008: Ingiriya – Ratnapura 28% 1,631 12
CP02-A001: Nittambuwa–Kandy CP 51% 9,318 66
CP03-A016: Haliela -Bandarawela CP 38% 3,074 22
CP04-B044: Bandarawela –Welimada 21% 633 5
CP05-A017: Galle – Deniyaya –Madampe 26% 2,672 19
CP06-B098: Denagama –Mulatiyana 23% 798 6
CP08-A014: Medawachchiya -NCP Boundary 17% 389 3
CP09-A004: Wellawaya –Siyambalanduwa 33% 3,830 27
CP10-A025: Siyambalanduwa–Ampara 22% 1,558 11
CP11-A011: Maradankadawala–Jayanthipura 16% 581 4
CP12-A011: Jayanthipura –Tirukkondainmadu 21% 1,788 13
CP13-A010: Padeniya- Puttalam 31% 5,241 37
Sub-Total: 29% 31,513 225
RSAP-1I -Phase I (sections A2, A3):
CP01-A002: Maliban Junction - Walana Junction 39% 18,128 129
CP02-A003: Nawaloka Junction – Seeduwa 51% 20,465 146
Sub-Total: 44% 38,593 275
RSAP-1I-Phase II (section A6):
CP05-A006: 157+000 km to 167+280 km 24% 1,546 11
CP06-A006: 167+280km to 178+000km 21% 773 6
CP07-A006: 178+000 km to 190+000km 21% 628 4
CP08-A006: 190+000km to199+300km 28% 1,530 11
Sub-Total 24% 4,477 32
Comparison to PAD
9. We compare the various phases of the Project before and after project completion (see table
3.3). For the 620 km road section, we compare the economic analysis in the PAD to the economic
analysis in the ICR. For the KT Section, A002, and A003, we compare the economic analysis of
the restructuring paper to the economic analysis of the ICR.
- 41 -
Table 3.3. Results of Economic Analysis-Before and After the Project
Length
EIRR at
Appraisal
(%)
NPV at appraisal
($, millions)
EIRR at ICR
(%)
NPV at ICR
($, millions)
620 km (using
different time
horizon)
31 103 29 225
620 km (using
same time
horizon)
31 103 17 24
Before Restructuring
134 km
(A006) 51 522 Dropped and replaced with A002, A003
After Restructuring
K-T Section 21 24 24 32
A002 29 101 39 129
A003 47 132 51 146
10. The results of this comparison are presented in table 3.6. For the 620km section, the NPV
at the time of appraisal was $103 million and the EIRR was 31 percent. In comparison the NPV
after project completion (at ICR) is $225 million and the EIRR is 29 percent. This difference in
the NPV values is driven by a difference in the assumptions of the PAD and ICR—the analysis in
the PAD is conducted for an eleven year time horizon while the analysis of the ICR is conducted
for a twenty year time horizon. If we limit the time horizon of the ICR analysis to eleven years
then the resulting NPV is $23.6 million and EIRR is 17 percent9.
11. The estimates of NPV and the EIRR for the K-T section, A002, and A003 increased after
project completion. For the KT section, the NPV and EIRR at the time of restructuring was $24
million and 21 percent, respectively—the NPV is $8 million higher and the EIRR is 3 percentage
points higher after project completion. For A002, the NPV and EIRR at the time of restructuring
was $101 million and 29 percent, respectively—the NPV is $28 million higher and the EIRR is 10
percentage points higher after project completion. For A003, the NPV and EIRR at the time of
restructuring was $132 million and 47 percent, respectively—the NPV is $14 million higher and
the EIRR is 4 percentage points higher after project completion. For both RSAP-1 and RSAP-1I
the benefits from travel time savings are higher than the benefits from vehicle operating cost
savings.
9 Ideally, the analysis in the PAD and ICR should be performed over the same time horizon.
- 42 -
`Annex 4. Bank Lending and Implementation Support/Supervision Processes
(a) Task Team Members
Names Title Unit Responsibility/
Specialty
Lending
Isabel Chatterton Financial Specialist SASEI Team Leader
Amali Rajapaksa Senior Infrastructure Specialist GTIDR Co-Team Lead
Rajesh Bahadur Singh Dongol Program Assistant GFMDR Team Support
Deepal Fernando Senior Procurement Specialist GGODR Procurement
Surendra Govinda Joshi Consultant GTIDR Tran. Spec.
Sumith Pilapitiya Lead Environmental Specialist GENDR Environment
Swaminathan A K Consultant GTIDR Tran. Spec.
Simon Thomas Lead Transport Economist SASDT - HIS Economist
Supervision/ICR
Amali Rajapaksa Senior Infrastructure Specialist GTIDR Team Leader
Ishtiaque Ahmed Transport Specialist SASDT - HIS Transport
Zia Al Jalaly Senior Social Development Specialist OPSOR Social Dev.
Farahnaz Azoor Program Assistant GFAAR Team Support
Darshani De Silva Environmental Specialist GENDR Environment
Rajesh Bahadur Singh Dongol Program Assistant GFMDR Team Support
Deepal Fernando Senior Procurement Specialist GGODR Procurement
Susanne Holste Lead Social Development Specialist GSURR Social Dev.
Sashikala Krishani Jeyaraj Program Assistant SACSL Team Support
Ashok Kumar Senior Highway Engineer GTIDR Transport
Sumith Pilapitiya Lead Environmental Specialist GENDR Environment
Zafar Iqbal Raja Senior Highway Engineer GTIDR Transport
Amali Rajapaksa Senior Infrastructure Specialist GTIDR Team Leader
Eashwary Ramachandran Operations Analyst GENDR Operations
Rajesh Rohatgi Senior Transport Specialist GTIDR Transport
Sunethra Chandrika Samarakoon Procurement Specialist GGODR Procurement
Jiwanka B. Wickramasinghe Senior FM Specialist GGODR Financial Mgt.
Bernadeen Enoka Wijegunawardene FM Specialist GGODR Financial Mgt.
Samantha Prasada Wijesundera Water and Sanitation Specialist GWADR Wat. & San.
Haider Raza Senior Procurement Specialist GGODR Procurement
Comfort Onyeje Olatunji Program Assistant GTIDR Team Support
- 43 -
(b) Staff Time and Cost
Stage of Project Cycle
Staff Time and Cost (Bank Budget Only)
No. of staff weeks $, thousands (including Travel
and Consultant costs)
Lending
FY04 19.71 49.18
FY05 42.02 141.9
FY06 47.82 176.3
FY07 0.87 4.8
FY08 0.0 0.0
Total 110.42 372.18
Supervision/ICR
FY04 – 0.00
FY05 – 0.00
FY06 17.41 65.38
FY07 42.45 101.00
FY08 29.64 91.01
FY09 51.88 110.31
FY10 48.21 128.99
FY11 33.99 113.24
FY12 60.75 174.16
FY13 83.53 173.55
FY14 31.98 64.66
FY15 27.05 115.82
FY16 14.24 60.71
Total 441.13 1198.83
- 44 -
Annex 5. Beneficiary Survey Results
- 45 -
Annex 6. Stakeholder Workshop Report and Results
1. A Bank mission visited Sri Lanka during June 8–12, 2015 to gather information for the
preparation of the ICR. The mission team comprised Radia Benamghar (Transport Specialist/ICR
Team Leader), Mirtha Pokorny (ICR Author), Amali Rajapaksa (Senior Infrastructure
Specialist/Project Team Leader), Darshani de Silva (Environmental Specialist), Haider Raza
(Senior Procurement Specialist), Razaak Ghani (Senior Social Development Specialist), Susrutha
Goonasekera (Social Development Specialist), Enoka Wijegunawardene (FM Specialist), Comfort
Olatunji (Program Assistant), and Sriyakanthi Sujeeva Roshinie Pieris (Team Assistant).
2. The mission’s objective was to collect information and inputs that will help in drafting the
ICR. As part of this mission, the ICR team (a) exchanged views with the implementing agency
about the drafting of the completion report; (b) carried out site visits of two roads, A002 and
A003; (c) conducted interviews with the relevant government agencies and stakeholders, including
the MOH, Ministry of Investment Promotion, RDA, PMU, contractors, communities, and so on;
and (d) delivered an ICR workshop along with working group session to draw the lessons learned
from the Project.
3. The workshop was attended by a large audience from the various government agencies,
PMU, contractors, consultants, and beneficiaries who expressed ideas and provided valuable input
for the ICR. The following topics were discussed during the workshop:
Design, Construction, and Supervision of Civil Works (Group 1)
Design and Quality of Supervision of Civil Works
(a) Problems in the design and supervision stage
Lack of proper investigations due to insufficient time allocations (pavement
design and changes during construction)
Poor attention to hydrology and drainage matters and related construction issues,
lead away drains, and so on (acquisition)
Design issues with vertical alignment with hydrology and access to adjoining
land properties
Acquisition issues during construction, public complaints, and general
intervention
(b) How to address the problems
Identify proper evaluation of the design components
Coordination between design team and stakeholders
(c) How to ensure that design and design review are compatible
- 46 -
Design a checklist for design and design reviews and strictly follow the same
4. Supervision of work
Problems in controlling quantity and quality of the construction work
Continue receiving inputs (availability) from the design team throughout the
Project duration (responsibility concerns)
Adequate staff allocation and time allocation and review of the experience of
staff in the relevant field
5. Construction industry
Developments in the local construction industry through project implementation
such as the following:
o Need for tremendous improvements for staff training and transfer of
knowledge to be continued (the discussion centered on whether this has been
done adequately)
o Improvements to labs and laboratory equipment and continuous review of the
standards of the same
o Contract administration capacity should be improved
Road Maintenance (Group 2)
(a) RMTF
Yes
It makes a system to identify in priority maintenance program *HDM and it created
the situation to government to collect funds from fuel CESS and so on. Because of
this the quality of the road was improved.
Yes
Continue Funding - Bank/Donors
50–50%
40–60%
30–70%
20–80%
- 47 -
(b) Asset management
All decisions with regard to roads are based on engineering and technical
information and for that purpose asset management is important
Updated correct/reliable data for management to take decisions
This systems allows to take intervention decisions based on economic value and
value for money
Funding for data collection to be established
(c) Rural roads
Appropriate data-based system has to be developed for road information for them
to take decisions on interventions
Make allocations through RMTF (with the increased capacity of RMTF)
Road Safety (Group 3)
Road safety corridor was selected based on accident data statistics
Police was very weak in coordination during construction
Utility shifting agencies were weak in shifting utilities on time
Utility agencies are not able to provide existing underground utility details
Pilot to be improved (junction mirrors can be provided)
Contract period should be selected carefully
Both side fencing can be implemented
Roadside parking should be restricted by providing identified parking area
Environmental and social safeguards (Group 4)
1. GoSL/bank policies
LAQ
NEA
L/Government
2. NEA
- 48 -
LAA
NIRP (2001)
Environmental and Social Safeguards Manual
3. LAD—v/Land Donation
GRM
E&S Committee at Project Level
GRC – D.S. Level
4. Voluntary land donation should be avoided
- 49 -
Annex 7: Part 1 -- Borrower's ICR
1. Introduction
1. In 2004, the GoSL sought the World Bank’s re-engagement in the road sector after a lapse of over a
decade, to help address the critical state of the country's road network due to a huge backlog of road maintenance
at all levels – national, provincial and rural. Contributing to (and exacerbating) the disrepair and deterioration of
roads was the increasing traffic congestion in the national roads, which compelled the government to increase
road capacity – a costly process requiring land acquisition – at the expense of the maintenance of all classes of
roads. In addition, Sri Lanka’s violent civil conflict, experienced since the early 1980s, took a heavy toll on the
government’s treasury. Sri Lanka needed considerable investment to bring its road system to a level of
performance consistent with its DOs.
2. The GoSL’s development strategy highlighted the urgent need to develop its roads and increase
connectivity and interaction between the provinces for both social integration and economic development. This
coincided with the World Bank’s assistance strategy that supported investment in roads as an essential
infrastructure development area for pro-poor growth linked to shared prosperity. Both strategies emphasized the
importance of developing private industry for road construction and maintenance. By disbanding the state-owned
Road Construction Development Company (RCDC) in 2003, the GoSL demonstrated that it was serious about
revitalizing the road sector by enabling the participation of the private construction industry. The RDA’s reliance
on the RCDC for most road works funded by the government had inhibited the growth of Sri Lanka’s domestic
road construction capacity.
3. Thus, the GoSL was committed to institutional and policy reforms to meet the needs and targets of the
road sector. In November 2004, the Bank, JICA, and the ADB decided to coordinate their activities in the road
sector within the context of the Reform Framework. The GoSL began addressing Sri Lanka’s road rehabilitation
needs for the first time through the RSAP. The project was designed to focus on the “maintenance of existing
assets”. The maintenance focus was supported by the rehabilitation of national roads, establishing a sustainable
arrangement for continuous maintenance as well as carrying out the preparatory work necessary for the
rehabilitation of rural roads. This was supported initially through an International Development Association
(IDA) credit of $100 million. The roads rehabilitated in this original phase provided the much-needed
connectivity to all of the provinces, including the north and the east. Additional funding of $98 million in 2008
and subsequently another $100 million in 2011 was channelled to improve the road conditions in the urban
sections in the high traffic areas of the western province. The project assisted Sri Lanka to increase the percentage
of national roads in good and fair condition from 48 percent to 65 percent.
4. With regard to rural roads, although ADB is providing support for rural infrastructure including rural
roads in the southern, north central, north western, and central provinces, this and overall donor assistance to
this sector, had been modest compared to the needs. For this reason, the Project prepared the necessary
framework and built the required capacity for the rural road sector to absorb funding for their rehabilitation needs
by establishing a rural road strategy, preparing a comprehensive database and providing training to the
Pradeshiya Sabhas (provincial authorities) in related areas, including the prioritization and selection of
investments.
2. Assessment of Project Objectives, Design, Implementation Experience and Outcomes
Project Objective: RSAP’s DO was to lower transportation costs through the sustainable delivery of an
efficient national road system that serves the needs of road users and the Sri Lankan public at large.
5. Project Design: The project’s design had to take into account the country’s huge backlog of road
maintenance – a situation compounded by not just financial constraints but also inadequate institutional capacity
in the road sector – and the urgent need to improve connectivity between provinces by rehabilitating the priority
- 50 -
corridors of the national network. The RMTF was established to ensure a sustainable mechanism for continuous
funding for the maintenance of road assets and to prevent the recurrence of the deterioration of the road network.
6. To achieve the increased workload from road rehabilitation, the private contracting industry needed to
be co-opted and provided work. To support this, the RCDC was closed down and hands-on support provided to
improve the capacity of contractors in a well-coordinated effort by the three main road sector donors. Moreover,
as the rehabilitation of the rural roads was also a priority concern and the capacity to achieve it insufficient, the
Project laid the framework for developing institutional capabilities for road infrastructure rehabilitation and
maintenance within Sri Lanka’s decentralized governance system
7. RSAP did not simply focus on the rehabilitation of roads. It emphasized the improvement of
development effectiveness by identifying and catalysing the changes the sector needs to make to achieve the
required efficiencies in the longer term. RSAP supported RDA to establish a fully-fledged asset management
system to inventorize, prioritize, monitor and manage its network with a view to increasing the organisation’s
ability to provide road users with a level of service that they would demand. Concerning Rural Roads, the Project
began its process of addressing maintenance needs of rural roads by incorporating a small pilot component.
8. RSAP’s national roads component covered maintenance, rehabilitation and minor upgrading in eight
provinces10. It resurfaced and improved 685.475km of Class A and B roads; provided technical assistance for
the selection, design and construction supervision of the civil works; building capacity within the RDA; and
enabled the development of the local construction industry. The rural roads component rehabilitated 162.23km
of rural roads in nine local government areas, whose selection was based on the recently completed poverty map
of Sri Lanka; built capacity within local authorities and of local contractors for road rehabilitation and
maintenance; and created a comprehensive rural roads database for the entire country that would support more
rational planning and prioritising in the development of rural roads, which represents nearly 75 percent of the
country’s total road network. The institutional strengthening and policy support component cut across the
first two components, providing technical support for institutional changes and the adoption of more efficient
mechanisms and systems for improved road maintenance. RSAP was equally a capacity building project as it
was one of infrastructure development.
9. Implementation experience: At the outset, a pressing challenge was to complete the procurements for
the RSAP road packages within a strict timeline due to the urgency of achieving the Project’s objectives. Delays
in the implementation of RSAP would have caused serious bottlenecks and holdups in the GoSL’s socio-
economic recovery and development process. The mobilization of consultants and the invitation and evaluation
of bids had to be done in quick succession. The Bank conducted training sessions for government officials on
how to select consultants following the Bank procedures. Training was also carried out to introduce the RSAP
perspective to contractors. The Bank was also responsive to the GoSL’ s request to use the standard bidding
document of the Institute of Construction Training and Development (ICTAD), as the contractors were familiar
with it. This helped move the procurement process.
10. Due to the relatively small number of contracts previously offered to the private sector, the local
construction industry had limited opportunities to develop. This lack of experience in turn resulted in most
companies being unqualified to meet the World Bank’s requirements for bidding. As a solution to this impasse,
RSAP encouraged a joint venture facility that enabled companies to join forces and combine capacities. This
would become one of the momentous strategies to be adopted by the Project. Another strategy adopted to support
the local construction industry was the division of the Kantale - Trincomalee highway into four equal segments
10 However, the Northern Province could not be included as it was not accessible for a project of this nature due to
the conflict.
- 51 -
to enable smaller companies to bid for the contracts. Local contractors recognize RSAP as the Project that was
key to the development of the local construction industry.
11. The National Road Sector Master Plan, which was finalized in 2007, required the widening of roads
from 5.5m to 6.2m. This called for changes in design after the award of the civil works contracts – causing delays
in implementation as well as the escalation of costs and sometimes questioning the capacity of the contractors
to undertake the increased workload. The project experienced variations, which were 31 percent of the original
awarded price. The design changes made to accommodate the widening of the road as well as designs of culverts
and drains not being identified up-front have contributed to this issue. This situation arose due to the appropriate
design requirements regarding culverts and drains not being identified at the design stage.
12. The Grievance Redress System that the Project put in place made it possible for the public to resolve
their problems quickly, transparently and out of court. The public also had the benefit of a specially allocated
hotline to access project management with concerns and complaints. If people do not agree with the solution
offered, a grievance redress committee (GRC) is formed so that they could make their case. If there was no
agreement, people could take legal action. RSAP received over 4000 complaints; all but two were resolved on
site. More than 60 percent of the public complaints or requests were related to house access, 25 percent to road
access, and 10 percent to retaining and parapet walls. People often referred to the Bank’s safeguard policies to
protect their interests.
13. RSAP also took practical measures to improve coordination on road development between national
agencies. For example, the RDA and the NWSDB have frequently been accused of lack of coordination in
project planning, where the NWSDB would dig up the roads to lay water pipelines as soon as a road was
rehabilitated. The road works planned in the urban road sections within RSAP, with the laying of water pipelines
in coordination with NWSDB, has started a new working relationship that would avoid such waste of resources.
14. A vital initiative supported by RSAP was the RMTF, set up to ensure the sustainable and transparent
allocation of resources and funds as well as to carry out efficient monitoring of maintenance. The financing of
maintenance works by the World Bank was intended to help the RDA to build capacity to optimize the selection
of roads for maintenance and align its processes toward minimizing costs. An innovative concept that the RSAP-
1ntroduced as a pilot initiative on the Kantale - Trincomalee road was Third Party Monitoring, which is
essentially a system of benefits monitoring from the perspective of users and stakeholders. This would be a
means of gaining their views regarding the road construction so that they could influence the design and
implementation of the Project. The long-term objective was to make benefit monitoring by project beneficiaries
an integral part of road sector monitoring processes.
15. A five-pillar approach formulated by the UN on road safety was adopted to design a 17km
demonstration road safety corridor from Ratmalana to Nalluruwa – a stretch of road with a high level of road
accidents. A committee comprising representatives from the MOH, the RDA, the Traffic Police, the Ministry of
Health, the four local authorities on the corridor (Dehiwala/Mt. Lavinia, Moratuwa, Panadura and Kalutara), the
University of Moratuwa, the MOT and the National Council for Road Safety (NCRS) designed and implemented
the demonstration corridor that strengthened some of the pillars identified, such as improving infrastructure that
is safe, improving road user behavior, and commencing a dialogue toward strengthening post-crash care services.
The launch of the new safety corridor saw the parallel launch of an awareness campaign using multimedia
including street drama and animated road signs to promote good pedestrian practice.
16. The Project gave rise to a new form of social responsibility among contractors. In all construction
packages of the national roads components and in some in the rural roads component, contractors funded and
carried out several activities, addressing the needs of communities. These included repairs to access roads,
construction and renovation of buildings and providing for the needs of service providers such as police stations,
schools and health clinics. These actions of contractors helped create goodwill between the contractors and the
community and this, in turn, had a positive impact on the relationship between the community and the Project,
especially in managing conflicts and disputes.
- 52 -
17. In the area of technology too, RSAP made some clear advances. It was with this project that road
construction in Sri Lanka was updated from the use of macadam and double bituminous surface treatment
(DBST) to asphalt, which provides smoother surfaces as well as the ability to better withstand wear and tear.
Although the initial investment was higher, the considerable savings on maintenance costs meant that the switch
to asphalt, based on sound economic analysis, proved beneficial. Thus, the introduction of asphalt for the national
roads resulted not only in improved quality but also in long-term financial benefits. This required contractors to
purchase asphalt plants, which RSAP facilitated with an advance payment. By December 2014, the Central
Environmental Authority had granted 140 Environmental Protection Licences for asphalt plants, of which RDA
owns and operates ten.
18. The RSAP-1I roads pass through the most urbanized and congested areas in the country. Finished road
levels have reached their highest levels in relation to adjacent properties. Overlay with milling will become
increasingly necessary in future pavement strengthening projects. Considering the Project requirement and future
benefit to the RDA, a Milling Machine was procured under RSAP and used for the Project. In low lying areas
where reconstruction is necessary, high water table has limited excavation depth. This precludes the possibility
of increasing the pavement thickness by excavating below existing road level and was a problem when a thick
overlay is required. Alternatively, for the same pavement life and strength, pavement thickness reduced
significantly by reinforcing with paving fabric (at AC level) and geo-grid (at DGAB level) and geotextile (at
sub-base level).
19. RSAP trained all project engineers on environmental safeguards, in a one-year process done in modules,
in collaboration with the University of Peradeniya. The Southern Transport Development Project – the
construction of the southern expressway – was used as the case study to understand what went wrong, what went
right; and the training process also helped the engineers to see the true value of an Environment Impact. The
RDA and the construction companies improved their proficiency to implement safeguards and manage safeguard
issues while putting in place the systems and procedures that were needed to institutionalize these practices.
20. The RDA had over a period suffered from external consultants carrying out designs with the risk of that
design requiring additional quantities, or technical errors being borne by the government. RSAP encouraged the
designs to be carried out through RDA's design units established with the re-engineering of the RDA. This was
the first opportunity that RDA had of implementing its own designs under an externally funded project. A similar
initiative was carried out for building supervision capacity, where a pilot project was implemented to supervise
the Kantale - Trincomalee section by a unit within the RDA. RDA is also increasingly carrying out feasibility
studies and economic analysis of its own projects. The RSAP helped improve capacity in construction
management, planning, project formulation, construction design, acquisitions, construction supervision, and
maintenance.
21. Project Outcomes: PDOs has two components they are the lowering transportation cost and
sustainable delivery of an efficient National Road system. Lowering transportation cost has been achieved
through: Outcome indicators on the National Road Networks via reduction in VoC, reduction in average network
roughness, reduction in network poor and bad condition roads, number of kilometres rehabilitated and
intermediated indicators on the National Road Networks was achieved via: reducing Travel Time, Annual Road
Maintenance Program and User Satisfaction Survey.
22. The road sections for upgrading and rehabilitations were selected based on the NRMP (2007 – 2017)
and the VoC calculation proposed under “target” has been based on the NRMP. The majority of the candidate
roads identified for upgrading in the NRMP were in the western province that carry a high volume of traffic.
The level of traffic has a high impact on the VoC. However since the cessation of the conflict, to address socio
economic issues, more funds were channeled in to the eastern and Northern provinces that were starved of any
investment over a long period of time due to the conflict and accessibility issues. These investments were not
featured in the NRMP due to these areas not being accessible at the time of preparing the NRMP.
- 53 -
Table 7.1. Results Framework and Monitoring Indicators
Outcome Indicators
Target Values
Ach
ieve
men
t o
f O
utc
om
e
Ref
eren
ce
Do
cum
ents
Bas
elin
e
2006 2007 2008 2009 2010 2011 2012 2013 2014
Targ
et
Ach
ieve
d
Targ
et
Ach
ieve
d
Targ
et
Ach
ieve
d
Targ
et
Ach
ieve
d
Targ
et
Ach
ieve
d
Targ
et
Ach
ieve
d
Targ
et
Ach
ieve
d
Targ
et
Ach
ieve
d
Targ
et
Ach
ieve
d
Reduction in VoC
2005 (PAD)
23.9 (LKR per km)
0.00%
15.37 0.60%
14.91 1.50%
14.83 2.70%
14.32 3.80%
14.21
Not Achieved
2011 (Project Paper)
14.6 (LKR per km)
13.6 14.21 12.5 14.13 11.5 14.03 10.5 13.88
Reduction in average network IRI from 9.5 IRI to 8.4 IRI
2005 (PAD)
9.5 9.53
6.8 9.31 6.7 9.02 6.5 8.66 6 8.39 6.2
Achieved 2011 (Project Paper)
6.2 6.1 6.2 6.1 6.1 6 5.9 5.9 5.9
Reduction in network in poor and bad condition from 52% to 35% (in percentage)
2005 (PAD)
48 52 48 48 47 43 44 38 38 35 40
Achieved 2011 (Project Paper)
38 37 40 36 35 36 34 35 33
Component 1: About 620km of National roads resurfaced
– To be undertaken YR 1
– – 150 – 300 – 450 – 620 620 – Achieved
Reduction in network IRI for RSAP roads from 7.8 TO 2.9
– 7.8 8.6 6.93 7.9 – 4.5 – 2.8 4.03 2.9 2.8 – Achieved
50% of relevant staff in the Planning and Maintenance Divisions of RDA trained in road assets management
– 0% 0% – 10% – 30% – 40% – 50% 67% – Achieved
Component 2: About 635km of Rural Roads improved
– To be undertaken YR 1
– – 50 – 250 – 450 50.03 635 101.38 – 162 –
Achieved
Restructured
Reduced Travel Time for Rural Roads (%)
– 0 0 – 0 – 3 – 3 – 4 60 – Achieved
Component 3: Routine and Periodic maintenance funding increased to $46.3 million (constant 2005 prices) (in $, millions)
– 13 30.0
28.24 34.8 30.82 38.3 28.65 42.2 26.53 46.3 56.54 45.22 70.55 43.10 46.72 46.48 39.89 50.55 28.53 Achieved
- 54 -
km of roads rehabilitated
– – – – – – – – – – – – 0 – 41 – 80
80.155
– – Achieved
Reduction in Network Roughness IRI for project Roads
Phase 1
– 6
–
2.8 2.33 – – – – Achieved
A2
– 4.3 – – – – 2.4 1.9
Achieved
A3
– 3.1 – – – – 2.4 2
Achieved
Reduced Travel Time on project roads
Phase 1
– 66 42 40 – – – – Achieved
A2
– 13.8 – – – – 12.5 11.3
Achieved
A3
– 26.5 – – – – 23.9 23.5
Achieved
Improved level of satisfaction of road – users
Phase 1
– – – – – – – – – – – – – – – – – – – 80.89 –
A2
– – – – – – – – – – – – – – – – – –
38.3 68.15 Achieved A
3
–
No collected
– – – – – – – – – – – – – – – –
Intermediate Result (Component 2): Road Maintenance Trust Fund in Operation and road Maintenance 3-year program implemented
About 60km of National roads on which periodic maintenance has been carried out
– 0
–
0 – 20 – 45 – 60 64.5 Achieved
Annual road Maintenance program is approved by RMTF
– New Baseline
– – Approved
– Approved
– Approved
Approved
–
Parent Project Component 2
Number of km Rural Roads improved
– – – – – – – – – 157 162
Achieved
- 55 -
23. Over the period from 2007–2012 alone, the GoSL has in effect achieved 109 percent of the NRMP.
Even though a considerable length of roads in the northern, eastern, and southern provinces, which carry a very
low traffic volume were rehabilitated, this was not adequate to compensate for the loss of VoC from the high
traffic volume of western province roads. This has resulted in falling short of the VoC targets forecasted.
24. The Maintenance funds disbursed lag behind the target value when considering the reported figures
which are only for the periodic and routine maintenance of roads and bridges, and hence reflect as not achieving
the target.
25. However there were maintenance works carried out for the widening and improvement of roads, which
were carried out with funds from outside the RMTF, such as from the GoSL, ADB, JICA and other Donors.
These cost were not taken into the reported routine and periodic maintenance expenditure. Table 2 (below)
clearly shows that with the cumulative expenditure for both maintenance of roads and bridges and for road
widening results in achievement of the target for maintenance expenditure.
Table 7.2. Maintenance Expenditure
2006 2007 2008 2009 2010 2011 2012 2013 2014
Ta
rget
Ach
iev
ed
Ta
rget
Ach
iev
ed
Ta
rget
Ach
iev
ed
Ta
rget
Ach
iev
ed
Ta
rget
Ach
iev
ed
Ta
rget
Ach
iev
ed
Ta
rget
Ach
iev
ed
Ta
rget
Ach
iev
ed
Ta
rget
Ach
iev
ed
Maintenance of
Roads and Bridges -
$, million (Table 1)
30.00
28.24
34.8
30.
82
38.
3
28.65
42.
2
26.
53
46.
3
56.54
45.
22
70.55
43.
10
46.7
2
46.4
8
39.89
50.
55
28.5
3
Widening and
Improvement of
Roads ($, million)
28.88 41.
41 55.87
47.
84 78.51 134.7
130.
68
171.2
5
110.
48
Total ($, million) 57.12 72.
23 84.52
74.
37
135.0
5
205.2
5
177.
4
211.1
4
139.
01
26. Although initially 635 km of rural roads were identified, subsequent restructuring of the Project saw
this reduced to 157 km, with 162 km of roads being rehabilitated, and hence the target was achieved.
27. The second component which is the sustainable delivery of an efficient National Road System was
achieved via the establishment of RMTF and channelling of funds into road rehabilitation and maintenance,
closure of RCDC and establishing capacity of contractors, establishing efficient cooperation amongst utility
providers to prevent damage to the investment toward the latter part of the Project, and ensuring that all utility
relocation costs are financed through the Project, and achieving environment and social sustainability through
changing the culture of RDA and contractors to comply and follow environmental safeguards, as well as effective
implementation of Grievance Redress Committee and third party monitoring.
28. In addition to the rehabilitation of 162 km of rural roads and the building of local capacity in the sector,
RSAP’s rural roads pilot project produced a rural roads database and along with it a rural roads development
strategy. The data generated includes information such as road condition, vulnerability of roads to flooding,
number of families with direct access, percentage of Samurdhi (government welfare) recipients living along the
roads, and the main use of the roads, for example, whether used mainly for industrial or agricultural transport.
The pilot project provided a good indication of the benefits arising from simple, but well-structured road
interventions that enhanced both mobility and access to services and markets.
- 56 -
29. In the Rural Roads Pilot Project, the following key results11 were observed: The percentage of families
with immediate access to an “All Weather Road” rose from 48.3 percent to 70.9 percent. Agricultural sales points
increased by 160 percent and service providers of different sorts – ranging from communications centres to
repair workshops – increased by 143 percent. In the survey areas, 14 percent of students moved from their poorly
resourced schools and gained admission to schools located in towns – with better facilities and better quality
teachers. Moreover, school attendance of both students and teachers showed a definite improvement. Student
attendance increased by an average of 45 percent - ranging from 40 percent to 60 percent with seasonal
fluctuations. A competitive market environment emerged, with small enterprises diversifying their range of
products and increasing annual turnover. However, some small businesses who found it difficult to adjust to the
changing environment, became nonviable and closed down. Improved roads also created a competitive
environment for marketing agriculture produce, with local producers better able to negotiate for favorable prices.
Improved labour mobility and employment opportunities for people saw household incomes taking an upward
turn. Road development encouraged new settlements – leading to increased land values. Due to the reduction of
Transport Cost, Traffic volume of trishaws, vans/cars, busses, and lorries have increased significantly.
30. New systems and practices: RSAP recognized that environmental and social risk management
requires appropriate planning, implementation and monitoring, even for small works. The GoSL regulations
stipulate an Environmental Impact Assessment for the construction of new roads, but this does not apply for the
rehabilitation of roads, which does not generally call for land acquisitions. However, the Bank requires that its
environmental safeguard policies be put in place to ensure long-term sustainability, even when government
regulations didn't call for them.
3. Factors Affecting Implementation
31. The implementation of RSAP was somewhat constrained due to the country’s security situation. The
project had to contend with a failed ceasefire and renewed hostility soon after it commenced work. However,
with the cessation of violence in 2009, implementation took place at a steadier pace. A summary of the other
factors affecting implementation are given below.
32. Delays in approvals: Road contractors had to deal with delays caused by the time taken by both the
Central Environment Authority and the Geological Survey and Mines Bureau (GSMB) to issue approvals and
licenses.
33. Estimation of Contract periods: The original contract periods had been understated and the contracts
neither fully appreciated nor reflected the work involved in difficult terrains, nor the additional work due to
variations not fully reflecting the time for delays in environmental clearances, which later required additional
time for expansion of the scope of work.
34. Sufficient time for completion of designs: Some of the shortcomings of the designs arose as a result
of the short time periods allowed for the designs due to the urgency of the Project.
35. Involvement of Provincial Staff: Effective engagement and interest of the provincial staff did not take
place at the design stage.
36. Spread of roads in the Project and staff of the supervision consultant: As the RSAP was the first
project for rehabilitation, the priority roads across the entire nation were included and the geographical spread
made it more difficult to supervise all of these sections as the RDA themselves were not accustomed to
11 Rural Accessibility Survey - Rural Roads Pilot Component, Ministry of Local Government and Provincial
Councils. 2012
- 57 -
supervision at such a scale. This was made especially difficult because there were multiple donors involved in
the rehabilitation of national roads.
37. Unavailability of bitumen: The project has suffered from shortages in the availability of bitumen due
to the high demand created by the road-works. The monopoly supplier, the Ceylon Petroleum Corporation, in
the past was not able to match demand with supply.
38. The isolation of the PMU: The PMU was earlier isolated due to limited participation from other units
of the RDA – a situation somewhat aggravated by the differences in the incentives structure that applied to PMUs
within the government systems. The earlier interventions of the Project suffered teething problems as a result of
this separation.
39. These areas of concern and bottlenecks were addressed as the Project progressed and resulted in
improvements in the design of subsequent project phases/credits.
4. Transition Arrangements for Sustainability of Project Achievements
40. The “culture change” that RSAP catalyzed that ranged from the improved practice of safeguards and an
effective grievance redress system to better efficiency in all aspects of project design and implementation will
be key to the sustainability of its outcomes. The setting up of the RMTF and maintenance systems, the building
of capacity within the RDA, including the capacity to manage contracts, and the development of the private
contracting industry, are key factors that influence sustainability. A Road User Satisfaction Survey carried out
toward the end of the Project confirmed that the general public perceived the RDA’s role current and changing
role positively.
41. The RDA has for decades been compelled to carry out ad hoc maintenance based on the availability of
finance, putting the already rehabilitated network at risk. The newly energized RMTF will provide a sustainable
flow of funding for the rehabilitation of roads. Moreover, the RDA’s transitioning from a project implementation
agency to an asset management agency, where the planning, the interventions and managing the country’s road
assets is done over a longer time horizon, will make a significant difference both in cost-effectiveness and
sustainability. It will also allow the private contractors to attend to required interventions on a timely basis, using
a Design-Build-Maintain-Operate and Transfer Model. Due to the sharing of risk between the RDA and the
contracting entity, some of the issues previously encountered by RDA can be mitigated.
42. The construction contracts currently in implementation in Sri Lanka are based on payment being made
on the amount of materials used; there is little incentive for contractors to save costs. As a result, the quantity
variations and resulting contract payments are high. The government is therefore unable to have certainty in
expenditure and need to secure funds beyond the budgeted amount. Moreover, if something goes wrong with the
design, that risk must also be borne by the government. The Bank is assisting the RDA to adopt a contract format
that is more beneficial for the country as a whole, which will provide the government price certainty, and share
risks between the government and the contractor. This will also encourage innovation by providing incentives
to the contractor to save costs, ensuring value for money.
43. A road-specific EMP was developed for each segment of road rehabilitation. The EMP identified issues
based on various activities that will happen within the contract – and came up with mitigation measures. The
contractors could then decide which final solution they wanted to employ and bid for the cost of the work
involved. The World Bank’s strategy of building capacity in the compliance of safeguards changed the mind-set
of the road agency as well as of the contractors. Today, many contractors are adopting these environmental and
safety standards, as normal procedure, even outside RSAP.
- 58 -
5. Risks for Sustainability
44. One of the continuing risks for sustainability is that there is still no independent source of finance for
road rehabilitation and maintenance. The government still depends on a budget allocation. Another crucial need
is a revision of the National Roads Master Plan so that it reflects the current context better – incorporating more
updated information on crucial aspects like increasing road congestion. The Plan would also need to outline a
strategy and an investment plan, clearly outlining its view of what needs to happen and where the funding is
coming from. RMTF was established in 2006 with the intention of improving adequacy, reliability, and
consistency of maintenance financing for all types of roads. However these objective yet not been reflected in
annual maintenance allocations. The government facilitates finance for RMTF through domestic sources. Since
2012, the World Bank co-financed (50 percent share) for identified twelve road projects through RMTF. The
contribution of each party was equal to $10 million and these project roads were rehabilitated during 2012 to
2015.
6. Lessons Learned
45. RSAP was of course not an entirely smooth journey. The challenges experienced have been carefully
documented so that the lessons learned and recommendations made can be taken into account in future projects.
During the long period of implementation of RSAP much of the learning has already been taken into account
and changes reflected in the recent investments.
46. The lessons learned include the following: the need for appropriate guidelines to enable the speedy
issue of licenses; the importance of identifying all of the parameters at the beginning of project implementation
to prevent recourse to avoidable design variations that are time and cost intensive; the need to stipulate cross
sections at shorter intervals when preparing detailed engineering designs; the importance of looking at the
benefits of using ‘Design-Build’ and ‘Fixed-Price Lump Sum’ contracts to prevent avoidable physical variations
during project implementation; the importance of not comprising on the time allocated for the designs; the need
to effectively engage provincial staff at the design stage to prevent some of the variation orders that resulted
from provincial requirements reaching the Project several years after its commencement; the need to carry out
community consultations not only before the implementation of the contracts but also during implementation,
as people are more likely to become engaged when construction has begun.
47. Involvement of Communities: Consultations were carried out at the inception of the Project to fully
understand the requirements of communities and to incorporate these needs within the Project at the design stage.
Experience has however shown that communities effectively engage in such discussions predominantly during
implementation.
48. Co-ordination between involved Agencies: where hitherto there had been a lack of co-ordination and
co-operation between Utility providers, the RSAP fostered a culture of dialogue between concerned Agencies,
so that the road rehabilitation could be undertaken with minimum disruption
49. Some of the key lessons learned which was reflected in this project are: Cost overruns – these have
occurred in most of the road contracts due to various reasons. Delays in the contract completion – this occurred
due to poor resource planning, poor construction methodologies and so on. Lack of attention to maintenance in
rural roads.
Bank’s Performance
50. The GoSL saw the Bank's role as going beyond that of a donor to one of an advisor and facilitator. The
systems the Bank helped put in place for project implementation and monitoring will have a long-term impact
on the efficiency of Sri Lanka's road sector. Improving capacity within the RDA, the agency responsible for
steering the Project, was a process that began from the preparatory stages, reaching several significant milestones
as the Project progressed.
- 59 -
51. At the beginning of the Project, a pressing challenge was to complete the procurements for the RSAP
road packages within a strict timeline. The mobilization of consultants, the invitation of bids, and the evaluation
of bids had to be done in quick succession. The Bank collaborated with the RSAP to ensure that contracts were
awarded in a timely manner. When it comes to donor-funded projects the criticism that the GoSL often gets is
that the start-up time is very long. The GoSL’s previous experience is received, which is a considerable waste
of time. But in this particular project, an advance payment was received from the intended loan to begin the
design work. Later, it was absorbed into the main loan. This saved a lot of time. With RSAP we were able to
design various subprojects as we went along, ensuring the smooth implementation of the Project.
52. The local office responded to urgent project requirements quickly without having to always wait for
advice or the go ahead from Washington. The Bank also consistently responded to issues within the industry in
a manner that was sensitive to the situation in the country, without adopting a bureaucratic one-size-fits-all
approach, while at the same time ensuring that the solutions were appropriate and had implications for
sustainability. The Bank’s close partnership with Sri Lanka’s other main donors in the road sector – ADB and
JICA – with whom they had regular consultations also at the field level, helped avoid duplication of work and
ensured that there was no conflict.
8. Conclusions
53. The main achievement of RSAP-1s that it has enabled the road sector in Sri Lanka to develop its all-
round capacity for progress and sustainability. The World Bank’s close collaboration with the RDA generated
innovative and practical solutions to address a range of challenges. Crucially, most of these approaches, based
on clearly defined principles, are being incorporated and institutionalized to enable the sector's long-term
development. The extent of RSAP’s achievements can be attributed largely to the World Bank’s long-term
strategic partnership with the GoSL in the country’s continuing efforts to modernize and streamline its road
sector.
Annex 7: Part 2 -- Borrower Comments on Final Implementation Completion and Results
(ICR) Report
54. This has reference to the letter signed by DKR Swarna, Addl. Director General (Projects) For Director
General Road Development Authority dated 20 April 2016 on above subject. Our comments on the finding of
the report are given below.
55. Page iii - Indicator 1(b) - We also agree that use of Network level VoC as PDO indicator is not suitable
as the project interventions are very limited to reflect at network level as indicated in the report. And also without
having the baseline data at approval level calculation of achievement is not reasonable
56. Indicator 4 (a) and 4(b) - Road Maintenance Expenditure: Annual maintenance allocation for national
roads are provided in the Annual budget Estimate as a maintenance item under the name of "Maintenance of
Roads & Bridges (Road Maintenance Fund)". But there other items in the budget estimate which will be used
for maintenance activities such as periodic maintenance which has not been reflected in the value as it is difficult
to separate out from other activities at head office level. As such total expenditure on maintenance of National
roads is more than the allocation indicated in the item. It is to be noted here that the original maintenance
allocation in the year 2010 was Rs. 4200 mn (US $ 37.1) as per Budget Estimate and actual expenditure under
the maintenance item in the year 2010 was Rs6,342.0 (US $56.0mn) (at the rate of 1 US $=Rs.113 at 2010).
57. Page 11- Para 32 - Factors generally subject to Government control
• Unrealistic Estimates: The Estimates were prepared by International consultant using available
data and the prices at the time of preparation of project. Due to the rapid increase of construction activity
all price went up due to the reasons indicated in the report. As such it is out of control of government.
As such it is better not to consider this as a government control item. However the bid price increase to
a level of 6.8% is normal.
- 60 -
• Inadequate initial Engineering design: The design of the Original contract package was carried
out by international consultant with the traffic and safety assessment by their experts. It is to be noted
here that RDA use the "Geometric Design Standards of Roads developed in 1998" for all RDA design.
It require minimum of 6.2 m for two lane road. However these design done by international consultant
has not gone through the standards. This has to be avoided in future projects.
• Unavailability of bitumen: There was a shortage of bitumen time to time due to high demand.
If contractors were programmed their works it could have been reduce the impact due this situation.
RDA wanted to import bitumen through Maganeguma to control the quality of the bitumen supply.
• Time overrun: All the packages of parent project was design by international consultant and
also supervised by international consultant. As such the consultant should held responsible for the wrong
design. Even if the time allocated for the design is short the consultant should deploy adequate staff for
realistic design. This should be reflected in future design activities.
58. Page 12
• Culverts and drains were not properly identified: Design of Parent project roads were done by
international consultant. After realization of this situation it was corrected by carrying out the design in-
house by RDA for roads under the RSAP-1I
• Delay in obtaining Environmental protection/ Explosive permits: Due to the situation of the
country at that time issue of permit to use of explosive had to go through several screening process.
However it can be a delay of the contractor also not following correct procedure.
• Lack of coordination with utility agencies: The name of NWSDB should be corrected as
"National Water Supply and Drainage Board".
• Frequent turnover of the PMU staff: All changes of Project Directors were done at the latter
part of the project. But there were not much issues such as cost overrun in that period.
59. Page 13 - Bullet 12 - ( Para 2) - This is entirely the mismanagement of international consulting firm
who carried out the supervision work and they should have control of getting qualified staff not the individual
local consultant. If local consultant is not performing team leader of the international consultant could change
the consultant.
60. Page 16 para 44 - There was a delay in HDM 4 data evaluation due to the migration of old data to new
system which has been upgraded through the project.
61. Page 19 para 54 - This is good as a pilot project to identify issues of implementation of DBMOT method.
It is required to have very good data bases as well as the good understanding of behavior of road especially
pavement with the situation of the road in terms of traffic and other parameters. As per the standard practices of
selecting payment methods for road works, Lump Sum type contracts are suitable only for the Projects, where
uncertainties for change of scope during implementation is minimal. With the lack of knowledge of the behavior
of road, the bidder will tends to price high to cover up the risk. Therefore, suitability & cost effectiveness of this
method will be known only with the receiving of bids.
62. Page 22 Para 64 - Reduction in VoC - It has been indicated here that with the significant reduction of
IRI of project roads, only modest reduction of VoC was achieved. It has to be noted here that assuming of
increase of speed to have high fuel consumption is not reasonable as these roads are operating at low level speeds.
With the improvement of the roads there can be increase of traffic volume on these roads due to attraction. This
will keep the speed at same range before the intervention or reduce the speed below the project level resulting
of modest reduction of VoC.
63. Page 23 Para 69 - By 2015 GoSL had spent LKR 370 billion to be corrected as "By 2015 GoSL had
spent LKR 187.64 billion on National roads"
64. Page 26- Para 75 - Economic analysis period of using 11 years is not reasonable. As indicated in the
para it should be same and more appropriately it should be 20 years.
- 61 -
65. Page 34 - Para 104 - In this section it is stated that the supervision consultant's performance is non-
satisfactory, produced poor designs and followed poor engineering practices and it affected performance of all
12 civil works contracts. It is the clear evidence of poor management of the project by lead consulting firm, but
not due to poor performance of few individual local consultants, as highlighted in this report.
66. Page 35 - Para 109 - A dedicated project management consultant - It is to be noted here that project
management is responsibility of Team Leaders and Resident Engineers of the supervising consultancy firm. It is
necessary to consider their experience in selecting of these staff in future projects.
67. Page 35 - Para 110 - Quality of engineering design, construction supervision should ensure defect free-
work - This is very good lesson learned from the project. Add to this most of the issues were due to the poor
performance of the international consultant selected for the project in all phases of the project implementation.
It is better to revisit the selection process of these consultant. It is proposed to adopt following process in future
project implementation
a. All the designs procedures, adopted by the Consulting firms shall be reviewed by RDA
specialized divisions. This requirement should be made mandatory and the PMU should submit them to
RDA for review. If the present capacity of those divisions are not sufficient to take action to mobilize
more resources
b. The consulting firms, engaged in RDA projects, should follow only RDA design manuals or
any other standards, approved by RDA. All the designs manuals shall be updated, if required.
c. Prepare Contract Administration manual and update already available manuals and make it
mandatory for using them by the Consulting firms and PMUs.
d. Standardized Contract documents and make mandatory for using them by all PMUs.
e. Formulate Technical Audit Division for updating standardized documents and Manuals, using
experience of past and ongoing projects to avoid/minimize problems and to improve performance.
f. Ministry or RDA to form separate section under Director (Quality Assurance) to carry out
random quality control testing in all project.
68. Page 35 - Para 111 -Adopting sustainable funding sources for the RMTF - RMTF is a good mechanism
for the sustainable maintenance of road network and transparency in maintenance fund usage. Management of
road sector agencies need to provide high level of commitment for the functioning of RMTF.
62
Annex 8. Comments of Cofinanciers and Other Partners/Stakeholders
63
Annex 9. List of Supporting Documents
1. The World Bank (2005) Project Appraisal Document on a Proposed Grant in the Amount of US$100
million equivalent to the Democratic Socialist Republic of Sri Lanka for a Road Sector Assistance
Project.
2. The World Bank (2008) Project Paper on a Proposed First Additional Financing Credit in the Amount
of US$98.1 million equivalent to the Democratic Socialist Republic of Sri Lanka for a Road Sector
Assistance Project.
3. The World Bank (2011) Project Paper on a Proposed Second Additional Financing Credit in the
Amount of US$100 million equivalent to the Democratic Socialist Republic of Sri Lanka for a Road
Sector Assistance Project. 4. Restructuring Papers, 2008, 2011, 2013, 2014, 2015. 5. QAG Report Quality at Entry, 2008
6. Evaluation of Implementation of Environmental and Social Management Framework of the Road
Sector Assistance Project., 2012
7. Rural Accessibility Survey – Rural Road Pilot Component, 2012
8. Road User Satisfaction Survey
9. Aide Memoires for Project Supervision missions 2005-2015.
10. Project Implementation Status Report, Project Files 2005-2015
64
Annex 10. QAG Report
QUALITY ASSESSMENT OF LENDING PORTFOLIO (QALP-1)
Summary Assessment Sheet
COUNTRY Sri Lanka PROJECT Sri Lanka - Road
Sector Assistance
REGION SAR SECTOR Transport
TASK TEAM LEADER Amali Rajapaksa SECTOR MANAGER Michel Audige
COUNTRY DIRECTOR Naoko Ishii
LN/CR AMOUNT ($MIL) 100 LN/CR NUMBER 41380
PROJECT ID P086411 TTL (Please indicate if HQ Headquarters
or Field-based)
DATE APPROVED 12/15/2005 DATE EFFECTIVE 03/16/2006
MTR DATE (Planned) 01/12/2009 MTR DATE (Actual) Not Assigned
ORIGINAL CLOSING DATE 09/30/2011 REVISED CLOSING
DATE 09/30/2011
FRAGILE STATE (Yes/No) No PREVIOUS QAG
ASSESSMENT(s) None
SECTORAL COVERAGE
Roads & highways (90%)
Central govt. admin (6%)
Sub-natl. govt. admin (4%)
SPVN BUDGET $000 (incl. TF): FY06 FY07 FY08
ACTUAL: 65.4 100.6 91
DO/IP RATING: FY07 FY08
ISR: DO S
IP S
DO S
IP S
EA CATEGORY Partial Assessment ASSESSMENT DATE
10/10/2008 LIKELIHOOD OF ACHIEVING DOs: 2
Guidance: 1= Highly Likely; 2 = Likely; 3 = Moderately Likely; 4 = Moderately Unlikely; 5 = Unlikely; 6 =
Highly Unlikely.
65
PERSON(s) INTERVIEWED
Amali Rajapaksa; Isabel Chatterton; Sumith Pilapitiya; Darshani De Silva; Sunethra Chandrika Samarakoon; Jiwanka B. Wickramasinghe; Samantha Prasada Wijesundera; Deepal Fernando; Zia Al Jalaly; Zafar Iqbal Raja;
Ishtiaque Ahmed; Ashok Kumar
MODERATOR Peter Ludwig OBSERVER(S)
PANEL MEMBER(S) SPECIALIZED REVIEWERS:
Robin C. Carruthers; Jacques Bure; Arie Chupak
1. Social Santhadevi Meenakshy 2. Environment John Buursink
3. Procurement Jorge Claro
QUALITY ASSESSMENT OF LENDING PORTFOLIO (QALP-1)
COUNTRY: Sri Lanka PROJECT TITLE: Sri Lanka - Road Sector Assistance
QALP-1 Assessment: Likelihood of Achieving Development Objectives
List of DOs: Ratings:
PDO The objective of the Project is to lower transportation costs through sustainable delivery of an
efficient national road system that serves the needs of road users and the Sri Lankan public at large.
DO1
DO2
DO3
DO4
DO5
Other (if Applicable)
Likelihood of Achieving DOs Comments: The chosen indicators will not show whether an efficient national road network has been
delivered on a sustainable basis, and even if it has, whether this is likely to contribute to economic (implicit
in the phrase “needs of road users”) and social development (implicit in the phrase “Sri Lankan public at
large”). But if the civil works are implemented together with those of the other funding agencies in the
sector, the indicator values will be achieved.
2
Overall Comments
A. Quality of Design
1. The original physical component of the Project (improvement to national roads) was
designed to meet a specific government request. A rather different physical component (a pilot
exercise in upgrading rural roads) was later added to meet a request from the next government.
Adding the additional component was a justifiable risk, given the less acceptable alternatives, and
in the event, has turned out well. The institutional component relied on a component in a parallel
project being implemented by the ADB. This was a marginally acceptable risk, given that ADB
had assumed the role of lead agency in the sector, but has not turned out so well.
2. The DOs are closely related to the first and third project components, and the outcome
indicators were crafted to meet some subtle differences in how the objectives might be achieved.
66
It was a justifiable simplification to use Vehicle Operating Costs (VoC) and not truck tariffs as the
indicator of transportation costs, given the circumstances of Sri Lanka and the difficulties that
would have been encountered in trying to estimate tariffs. But in future road development projects
in Sri Lanka, as elsewhere, more attention should be paid to the structure of the trucking industry
and the reasonableness of the implicit assumption in the DO that reductions in VoC will be passed
on to users. It would not be essential to go to the next stage (as suggested at the interview) and link
changes in truck tariffs to increased economic and social activity, as such impacts take time to
become apparent whereas the lower tariffs should be observable more quickly.
3. The method of selecting sections of road to be improved in the national roads component
included a thoughtful balance of technical and social considerations, as well as taking account of
the roads being improved under the parallel ADB roads project. More attention should have been
given to the design standards used, as they were subsequently found to need improving to achieve
an acceptable level of road safety. The design concept for the rural roads component, of including
pilot projects for different types of rural road improvement, was a justifiable compromise between
rejecting the new government request to include a rural roads component in the Project and fully
accepting such a component as an equally significant component as that for national roads.
4. The institutional component aimed at the creation of a road fund for road maintenance, a
Board of Trustees to manage the fund, and a Technical Advisory Committee to provide technical
support. This was an ambitious agenda, particularly taking account that the existing road agency
that would have to be restructured was also implementing the civil works component of the Project
and similar projects of other financing agencies. Under these circumstances the use of a PIU (or
multiple PIUs) was more justifiable than would otherwise have been the case, since this insulated
management of the civil works from much of the institutional disruption.
B. Quality of Implementation
5. Given the continued civil unrest in Sri Lanka, the Government’s attention to the Project
has been strong. When it became clear that the increases in unit costs for civil works could result
in some of them not being completed, the Government took appropriate action to request additional
Bank funding. However, some of the additional funding was to meet a change in design standards
between contracting the civil works and completing them. While having a plausible justification
in meeting higher safety standards, more consideration could have been given to completing the
existing contracts under the original design standards, since they could not have been so unsafe as
to be unacceptable. The response to rapidly escalating bitumen costs was to allow the contractors
to import bitumen as an exception to the Government policy of having it provided by a state
monopolist. Unfortunately this response was too little and too late, as the set up logistics costs for
individual contractors to importing relatively small quantities of bitumen has not resulted in
significant cost reductions, and this could have been foreseen. A quicker, more innovative and
comprehensive response was needed.
6. There have been delays in contracting the consultant that has the task of designing the new
road maintenance funding system, a delay that is compatible with the current Government’s
reluctance to pursue institutional changes. Whatever the reason, the slow progress jeopardizes the
chances of achieving the DO objective of delivery of an efficient national road system.
67
7. The Government has been responsive in purchasing new equipment that will facilitate more
measurements of the IRI (the values of which constitute one of the outcome indicators) and has
been diligent in trying to understand how the previous government arrived at the baseline values.
They have also been making estimates of vehicle operating costs (another outcome indicator).
C. Quality of Bank Supervision
8. The Bank (both the task team and management) has been responsive in addressing the rapid
escalation of contract costs and the Government’s proposed solution for dealing with the cost
overruns. While there is little evidence of collusion between contractors in seeking price variations
based on unit cost increases, more thorough investigations could have been made, together with
other road funding agencies, to verify that this has not happened. Experience from other countries
indicates that when unit costs increase rapidly, some contractors take advantage of the situation to
increase their invoices even more. The Bank has been diligent in maintaining frequent contact with
other agencies active in the road sector, particularly the ADB as the lead agency. These contacts
have not been as productive as they might have been, for example in devising a scheme to reduce
the impact of increases in bitumen costs, or reappraising the implementation of the design change
to on-going contracts. The Bank has given much attention to the interests of residents close to the
roads being improved and to efforts to minimize construction impacts on them. However, in
agreeing to change the design standard of rural roads from gravel surface to a more expensive but
less environmentally intrusive paved surface, perhaps more attention should have been given to
the neighbors and users of roads that cannot now be improved as more funding has been given to
on-going projects. The decision to adopt this more expensive design concept will have large scale
implications for the whole rural roads program.
D. Panel Recommendations
9. There is a high probability that the civil works components of the Project will be completed
more or less on time, but well over the original budget but probably within the modified budget
(taking account of the additional Bank funding and that the worst of the unit cost escalations might
now be past). So in the second half of the implementation period more attention can be given to
the third project component, Institutional Strengthening and Policy Advice, that addresses the part
of the DO related to the delivery of an efficient national road system. This system will require a
secure funding for new roads as well as road maintenance and a national road agency that has
effective incentives and access to human and financial resources to address them. The performance
of the ADB in progressing this agenda has not met the expectations indicated in the PAD and
implicit in the DO of the Project. The World Bank will have to take a more proactive role if this
agenda is to be met.
10. One way that this could be done is through the rural roads program where the role of the
World Bank is stronger than it is for national roads. Given that the new CAS puts a strong emphasis
on rural roads and their development role, the pilot projects included in the on-going project could
provide a wealth of useful information and support for policy initiatives related to broader issues
of funding for roads and the institutional arrangements for building and maintaining them. This
relates particularly to design standards and the trade-offs between constructing fewer but better
roads or more but less costly roads that are perhaps more difficult to maintain.
68
11. The strategy of designing road maintenance funds based on models used in other countries
might no longer be sustainable. While road maintenance needs could often be met from a surcharge
on transport fuels of the order of U$0.05 to U$0.09 per liter, with the increase in costs of road
maintenance it is probable that this level of surcharge would have to at least double, and increase
even more if the global economic downturn results in a slower rate of growth of traffic (road
maintenance needs are largely fixed and only decrease slowly in relation to decreases in traffic).
There is conflicting evidence as to whether it is the absolute level of the surcharge (an increase of
about U$0.05 per liter) that limits the feasibility of an increase, or its share of the total cost of fuel
(if the surcharge doubles while the cost of fuel increases three fold or more, the impact of the
surcharge might be less than expected). The impacts of the changing global economic context will
need to figure prominently in the assessment of an appropriate road maintenance funding
mechanism.
12. The Technical Audit has an important role in the supervision of this project. Emphasis
should be given in future Aide Memoires to the findings of the audits.
13. The review has noted some apparent inconsistencies in the physical and financial progress
of the Project: physical progress is estimated at about 50%, disbursements also estimated at 50%,
but contractual costs including escalation factors have been about 50% higher than indicated in the
original contracts. These three facts cannot all pertain at the same time. Preparation for the Mid-
term review provides a good opportunity for the percentage progress figures to be shown consistent
with the cost escalation estimates.
E. Any Systemic Lessons
14. The DOs and the indicators used to measure them do not give any indication as to whether
economic or social development will result from the Project. The projected values of at least two
of the indicators (VoC and IRI values) will be achieved if the Project civil works are implemented,
and so are not in themselves indicators as to whether any development will result from the Project.
Great care needs to be taken in defining DOs that are not so ambitious that even if they are achieved,
such achievement cannot reasonably be attributed to the Project, while at the same time not making
them so trivial that so long as the civil works are completed, the indicators will show that the DOs
have been achieved.
15. Institutional changes invariably take much longer than expected, so some provision for a
slower implementation (a “Plan B”) should be made. This could be an addition to the “Measures
taken to mitigate risks.” It would indicate what measures should be taken should any of the risks
be realized; it is not enough just to show what has been done to reduce them.
69
Rejoinder from the Region
QUALITY ASSESSMENT OF LENDING PORTFOLIO (QALP-1)
Guidance Questionnaire
Summary Assessment Sheet
Assessment Rating
1 = Highly Satisfactory/Likely
2 = Satisfactory/Likely
3 = Moderately Satisfactory/Likely
4 = Moderately Unsatisfactory/Unlikely
5 = Unsatisfactory/Unlikely
6 = Highly Unsatisfactory/Unlikely
NA = Not Applicable
QALP-1 Assessment
Quality of Design 2
Quality of Implementation 2
Quality of Bank Supervision 2
Focus on Development Effectiveness 3
Fiduciary/Safeguard Aspects 2
Supervision Inputs and Processes 2
Candor and Realism of ISRs 2
QALP-1 ASSESSMENT: Likelihood of Achieving DOs 2
Likelihood of achieving DOs is rated on the same six-point scale as other ratings. In arriving at a final judgment
on outcomes, panelists should exercise their judgment and take into account quality of design, implementation
and Bank supervision, as well as country conditions and known risks.
QUALITY ASSESSMENT OF LENDING PORTFOLIO (QALP-1)
Guidance Questionnaire
Context Section
A. Quality of Design 2
(i) Strategic relevance and appropriateness of DOs?
Comments: The project design did more or less what the
Government wanted. The DOs expressed exactly what they needed, and they are still
highly relevant.
2
70
(ii) Appropriateness of project design, complexity, and approach, given the country’s past track record
and absorptive capacity?
Comments: The original fears that the pilot rural road projects might detract from the focus on
the national roads component were not realized.
2
(iii) Adequate attention to technical, financial and economic aspects?
Comments: The selection of road sections to be upgraded made sensible use of the Highway
Development Model 4(HDM4), as did the overall evaluation. However, the technical design
should have looked more at the safety implications of using a relatively narrow road width of
5m, since it was later found desirable to change it to 6.2m.
3
(iv) Quality of the Results Framework to achieve the DOs, including realism of causal links between the
Project’s inputs, activities, outputs, and intended outcomes?
Comments: Given the development objectives, the outcome indicators and causal links are
adequate.
2
(v) Quality of arrangements for monitoring and evaluation (including clarity and precision of the
performance indicators to assess progress and outcomes and availability of baseline data)? 2
16. Comments: The Roads Development Authority (RDA) is measuring in regular intervals
the IRI, VoC and the conditions of the network. However they have gotten the initial baseline
values wrong for the IRI, through overuse of extrapolation. The task team is taking adequate
precautions to ensure that the subsequent measurements are more reliable.
(vi) Adequacy of measures incorporated in project design to address policy constraints?
Comments: RDA was being redesigned, therefore selection of PIU for project
implementation was justifiable. The ADB is taking the lead on RDA restructuring and Road
Fund. While at the time it was correct not to question the leadership of ADB as the Bank
was absent from the road sector for 10 years, the subsequent failure to achieve the expected
changes indicates a more proactive response from the World Bank will be needed to achieve
the DOs.
2
(vii) Level of Borrower ownership, commitment?
Comments: The Borrower has demonstrated strong ownership throughout project execution,
exemplified by the requests to include rural road pilot studies and for additional funding
when it was necessary.
2
(viii) Extent of integration and quality of arrangements for governance and anti-corruption in project design?
Comments: The use of third party technical audits is an excellent means to keep the implementing
agency, contractors and consultants on their toes with respect to the quality of civil works executed.
Also see comments under FM (xi) and procurement (xii) below, which are both rated satisfactory.
2
(ix) Extent of integration and quality of social development aspects in project design? 2
17. Comments: Development objective of the Project provides opportunity to address
vulnerability due to poverty, isolation, and gender.
71
18. The project design adequately evidences that measures were taken to promote positive
social impacts result from the Project implementation. As part of project preparation, social impact
assessments have been completed and social framework was generated though the Project does
not trigger OP 4.12. The framework proposes continued consultations with the stakeholders during
every stage of the Project to ensure social safeguard compliance is maintained throughout the
Project cycle, and provides the principles and the methodology for evolving a grievance redress
mechanism. It goes to state that a Grievance Redress Committee (GRC) will be established with
critical roles for civil society and concerned stakeholder.
19. With regard to poverty, project covers the poorest segments of the country including
provinces close to conflict areas and proposes labor intensive interventions where appropriate.
20. Stakeholder consultations were organized in a manner that ensured gender equity. The
social impact assessment report proposes ways to integrate gender dimension within the earth
works. The project design would have benefitted by establishing criteria for gender focus in: (i)
earth works; (ii) proposed stakeholder dialogue during implementation; and (iii) institution of
safety measures in congested areas such as wide sidewalks and proper lighting of sidewalks to
enable safe mobility of poor female road users.
(x) Extent of integration and quality of environmental aspects in project design?
Comments: Environmental aspects of this “Category B - Partial Assessment” project have been
fully integrated into project design. Sufficient attention was given to the financial and human
resources required to monitor and supervise the multiple environmental issues of national and rural
roads during project implementation. Environmental management is well integrated into project
design and implementation.
2
(xi) Extent of integration and quality of FM aspects in project design?
Comments: Adequate actions to ensure the Project’s FM arrangements to properly record and
control project’s financial activities were in place before Loan effectiveness. Adequate attention
was also given to mitigate the potential risk of fraud and corruption. Thus, required FM
arrangements were in place at an early stage of project implementation.
2
(xii) Extent of integration and quality of procurement aspects in project design? 2
21. Comments: Governance and anti-corruption: As reported in other Sri Lanka projects
evaluated, the country does not appear to have a high incidence of corruption although the CPAR
did warn about institutional weaknesses, the absence of appropriate procurement controls
including the absence of a formal system for performing procurement audits, and a weak capacity
to implement the procurement laws and regulations, rating the risk of fraud and corruption as
Medium. The same year of the release of the CPAR, Transparency International ranked Sri Lanka
as No 67 in a survey of 145 countries, which coincides with the medium classification of the CPAR.
22. The overall procurement risk in this particular project is also classified as Medium although
the CPAR is not mentioned. The procurement arrangements in the PAD are very good and
consistent with a project of this nature, with stringent controls, ex-ante review of procurement
actions and very frequent procurement review missions that include field visits, on-site inspections
and post-reviews of procurement actions. In addition, like most major road projects, it has the usual
independent consulting engineering supervision.
72
23. Procurement aspects: The procurement aspects at project design were very well laid out,
properly organized and straightforward. In fact there was substantial procurement readiness at
project inception with an 18 month procurement plan agreed upon from the start.
(xiii) Quality of institutional framework for the Project?
Comments: Using several PIUs to avoid problems with RDA, which was in the restructuring
process was a necessary precaution to ensure implementation of the physical components of the
Project.
2
(xiv) Quality of risk assessment and management? 4
24. Comments: While risks were described in the PAD, there were no mitigation measures
mentioned. While perhaps not obligatory at the time, it would have been a desirable addition.
1. Quality of Implementation 2
QUALITY ASSESSMENT OF LENDING PORTFOLIO (QALP-1)
Table 1. Risk Flags and DO/IP Status
COUNTRY: Sri Lanka REGION: SAR
PROJECT ID: P086411 PROJECT TITLE: Sri Lanka - Road Sector Assistance
DO/IP/Risk Factor FY07 FY08
ISR Panel ISR Panel
DO/GO S S S S
IP S S S S
Project Components
Maintenance and Rehabilitation of
National Roads S S S S
Maintenance and Rehabilitation of Rural
Roads S S S MS
Sustainable Maintenance Financing
Arrangements S S S S
Discretionary Flags
Counterpart Funds No No No No
Financial Management No No No No
Legal Covenants No No No No
Monitoring and Evaluation No No No No
Project Management No No No No
Procurement No No No No
Safeguards No No No No
Sub-Total 0 0 0 0
1/ Exogenous Flags
Disbursements Delays No No No No
73
Effectiveness Delays No No No No
Country Environment No No No No
Country Record Yes Yes Yes Yes
Long-Term Risk Flag No No No No
Sub-Total 1 1 1 1
Total Flags 1 1 1 1
Golden Flag No No No No
2/ Overall Risk Status Low-Risk Low-Risk Low-Risk Low-Risk
25. Comments
1/ Exogenous flags are system generated flags and have the same ratings for both ISR and
Panel.
2/ APP (DO) - DO rated below the line.
APP (IP) - IP rated below the line.
APP (DO/IP) - Both DO and IP rated below the line.
Potential - Non-problem projects with 3 or more flags and without a golden flag.
2-flag - Non-problem projects with only 2 flags and without a golden flag.
Low risk - Non-problem projects with 0 or 1 flag and without a golden flag.
74