Document of The World Bank FOR OFFICIAL USE ONLY€¦ · Guidelines, unless the Project...
Transcript of Document of The World Bank FOR OFFICIAL USE ONLY€¦ · Guidelines, unless the Project...
Document of
The World Bank
FOR OFFICIAL USE ONLY
Report No: 67555-EG
EMERGENCY PROJECT PAPER
ON A
PROPOSED LOAN
IN THE AMOUNT OF US$200 MILLION
TO THE
ARAB REPUBLIC OF EGYPT
FOR AN
EMERGENCY LABOR INTENSIVE INVESTMENT PROJECT
June 13, 2012
Human Development Sector
Middle East and North Africa Region
This document has a restricted distribution and may be used by recipients only in the
performance of their official duties. Its contents may not otherwise be disclosed without World
Bank authorization.
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
ii
CURRENCY EQUIVALENTS
(Exchange Rate Effective June 13, 2012)
Currency Unit = Egyptian Pound (EGP)
EGP 1 = US$0.17
US$1 = EGP 6.044
FISCAL YEAR
January 1 – December 31
ABBREVIATIONS AND ACRONYMS
ADB African Development Bank
CAS Country Assistance Strategy
CCT Conditional Cash Transfer
CDA Community Development Association
CPAR Country Procurement Assessment Report
DANIDA Danish International Development Agency
EEAA Egypt Environmental Affairs Agency
EC European Commission
EGP Egyptian Pound
ELIIP Emergency Labor Intensive Investment Project
ESSAF Environmental and Social Screening and Assessment Framework
EU European Union
FDI Foreign Direct Investment
FI Financial Intermediary
GDP Gross Domestic Product
GoE Government of Egypt
GTZ German Agency for Technical Cooperation
HCD SFD‟s Human and Community Development Department
IA Intermediary Agencies
IAD SFD‟s Internal Audit Department
IBRD International Bank for Reconstruction and Development
ICB International Competitive Bidding
IDA International Development Association
ILO International Labor Organization
ISN Interim Strategy Note
KfW Kreditanstalt für Wiederaufbau Development Bank
MIS Management Information System
MOHP Ministry of Health and Population
M&E Monitoring and Evaluation
MFI Microfinance Institution
iii
MSE Micro and Small Enterprises
NCB National Competitive Bidding
NGO Non-Governmental Organization
OM Operations Manual
O&M Operation and Maintenance
PFM Public Financial Management
PIU Project Implementation Unit
PWP Public Works Programs
SA Sponsoring Agencies
SFD Social Fund for Development
SIL Specific Investment Loan
SME Small and Medium Enterprise
SRFP Standard Request for Proposal
TA Technical Assistance
TOR Terms of Reference
UNDP United Nations Development Program
Vice President: Inger Andersen
Country Director: A. David Craig
Sector Manager: Yasser El-Gammal
Task Team Leader: Alaa Mahmoud Hamed Abdel Hamid
iv
Arab Republic of Egypt
Labor Intensive Investment Project
CONTENTS
Page
A. Introduction ...................................................................................................................... viii
B. Emergency Challenge: Country Context, Recovery Strategy and Rationale for Proposed
Bank Emergency Project............................................................................................................. 2
C. Bank Response: The Project ............................................................................................... 6
D. Appraisal of Project Activities ............................................................................................ 8
E. Implementation Arrangements and Financing Plan .......................................................... 14
F. Key Risks and Mitigating Measures ................................................................................. 17
G. Terms and Conditions for Project Financing .................................................................... 17
Annex 1: Detailed Description of Project Components ........................................................... 18
Annex 2: Results Framework and Monitoring ........................................................................ 20
Annex 3: Summary of Estimated Project Costs ....................................................................... 23
Annex 4: Operational Risk Assessment Framework (ORAF) ................................................ 24
Annex 5: Financial Management and Disbursement Arrangements ..................................... 27
Annex 6: Procurement Arrangements ...................................................................................... 38
Annex 7: Implementation and Monitoring Arrangements ..................................................... 43
Annex 8: Project Preparation and Appraisal Team Members ............................................... 50
Annex 9: Environmental and Social Safeguards Framework ................................................ 51
Annex 10: Economic and Financial Analysis ........................................................................... 67
Annex 11: Documents in Project Files ...................................................................................... 71
Annex 12: Statement of Loans and Credits .............................................................................. 72
Annex 13: Country at a Glance ................................................................................................. 73
Annex 14: Maps........................................................................................................................... 75
v
EGYPT
EMERGENCY LABOR INTENSIVE INVESTMENT PROJECT
PROJECT PAPER
MIDDLE EAST AND NORTH AFRICA
MNSHD
Basic Information
Country Director: A. David Craig
Sector Manager/Director: Yasser El
Gammal/ Steen Lau Jorgensen
Team Leader: Alaa Mahmoud Hamed
Abdel Hamid
Project ID: P126339
Expected Effectiveness Date : October
12, 2012
Lending Instrument: ERL
Sectors: Other Social Services
Themes: Human Development
Environmental category: B
Expected Closing Date: December 31,
2015
Joint IFC: N/A
Joint Level: N/A
Project Financing Data
[ X] Loan [ ] Credit [ ] Grant [ ] Guarantee [ ] Other:
Proposed terms: The loan is a Variable Spread Loan with a 29-year maturity and seven (7)
year grace period with commitment linked level repayment pattern.
Financing Plan (US$m)
Source Total Amount (US $m)
Total Project Cost:
Cofinancing:
Borrower:
Total Bank Financing:
IBRD
IDA
New
Recommitted
200
Client Information
Recipient: Arab Republic of Egypt
Responsible Agency: The Social Fund for Development
Contact Person: Ms. Ghada Waly
Telephone No.:
Fax No.: (202) 2391-2815
Email:
Estimated disbursements (Bank FY/US$m)
FY FY13 FY14 FY15 FY16
Annual 10 55 60 75
Cumulative 10 65 125 200
vi
Project Development Objective and Description
Project development objective:
The objectives of the Project are: (i) to create short-term employment opportunities for
unemployed unskilled and semi-skilled workers; and (ii) to provide access to basic
infrastructure services to the target population in poor areas in the Borrower‟s territory.
Project description:
Component 1: Employment-Intensive Sub-projects
This component will include provision of grants to sponsoring agencies by governorates
and local authorities, for sub-projects consisting of small-scale infrastructure works
including, but not limited to: canal cleaning and protection, and rehabilitation of schools,
housing, and rural roads.
The sub-projects will be contracted out to private contractors.
This component will also include provision of grants to sponsoring agencies, by
governorates and local authorities, for sub-projects consisting of community services
including, but not limited to, early childhood education services, outreach for maternal and
child health, nutrition, population services, solid waste collection, and youth employment
in rural and urban settings.
The sub-project implementation will be contracted out to NGOs.
Component 2: Implementation Support
This component will include provision of project implementation support, including
project management, audits, public information and communication, technical verification
and quality assurance, monitoring and evaluation, and social accountability mechanisms.
Safeguard and Exception to Policies
Safeguard policies triggered:
Environmental Assessment (OP/BP 4.01)
Natural Habitats (OP/BP 4.04)
Forests (OP/BP 4.36)
Pest Management (OP 4.09)
Physical Cultural Resources (OP/BP 4.11)
Indigenous Peoples (OP/BP 4.10)
Involuntary Resettlement (OP/BP 4.12)
Safety of Dams (OP/BP 4.37)
Projects on International Waterways (OP/BP 7.50)
Projects in Disputed Areas (OP/BP 7.60)
[ X]Yes [ ] No
[ ]Yes [ X ] No
[ ]Yes [ X ] No
[ ]Yes [ X] No
[ ]Yes [ X ] No
[ ]Yes [ X ] No
[ ]Yes [ X ] No
[ ]Yes [ X ] No
[ ]Yes [ X ] No
[ ]Yes [ X ] No
Does the project require any exceptions from Bank policies?
Have these been approved by Bank management?
[ ]Yes [ X ] No
[ ]Yes [ ] No
Conditions and Legal Covenants:
Agreements References Description of
Condition/Covenant
Date Due
vii
(Project Agreement) Schedule
Section IA, Paragraph 3
For the purposes of proper
implementation of the Project,
the Borrower shall cause the
Project Implementing Entity, not
later than six months after the
Effective Date, to appoint for the
duration of Project
implementation, and on terms
and conditions acceptable to the
Bank, an Independent
Verification Expert (IVE) to
assess and verify that: (i) Project
outcomes have been met; (ii) the
quality of works undertaken in
carrying out Sub-projects; and
(iii) whether Sub-projects are
implemented and maintained in
accordance with the
requirements of the Maintenance
Manuals, the ESSAF and the
Operations Manual.
Not later than 6 months
after Effective Date
(Project Agreement) Schedule,
Section IA, Paragraph 4
The Borrower, through the
Project Implementing Entity,
shall update its existing
automated accounting system to
record and report on the new
project activities
Not later than one month
after the Effective Date
(Project Agreement) Schedule,
Section IC, Paragraph 1
To facilitate the carrying out of
Part A of the Project, the
Borrower shall ensure that the
Project Implementing Entity
shall make Sponsoring Agency
Grants to Sponsoring Agencies
in accordance with eligibility
criteria and procedures mutually
acceptable to the Bank and the
Borrower.
viii
(Loan Agreement) Schedule 2,
Section IV, B1
Notwithstanding the provisions
of Part A of this Section, no
withdrawal shall be made:
(a) for payments made prior to
the date of this Agreement; or
(b) under Category (2) unless a
procurement advisor has been
appointed on terms and
conditions mutually acceptable
to the Bank and the Borrower; or
(c) under Category (1) in the
event that the ESSAF requires
the preparation of a Sector-
specific EIA/EMP, and/or
Environmental Safeguard
Guidelines, unless the Project
Implementing Entity has
accordingly prepared, disclosed
and held consultations on the
aforementioned Sector-specific
EIA/EMP, and, where required
under the ESSAF, has prepared
Environmental Safeguard
Guidelines for the particular Sub-
project for which the application
for withdrawal is required.
A. Introduction
1. This Project Paper seeks the approval of the Executive Directors to provide a loan in an
amount of US$200 million to the Arab Republic of Egypt for an Emergency Labor Intensive
Investment Project (ELIIP). Fundamental political changes in Egypt have followed the collapse
of President Mubarak‟s regime in February 2011. Parliamentary elections were conducted in
March 2012. A 100-person assembly is being formed to draft a new constitution, which in turn
will be subject to a popular referendum. At the time of the EPP, presidential elections are
ongoing with two final candidates running for presidency. The transitional Government in place
has requested Bank support for employment creation in poorer areas of Egypt in the short-term
to maintain social stability during this period of transition. The employment and poverty
situations in Egypt are critical. Unemployment is high (more than 13 percent), with an increase
of 3.5 percentage points over the last year, and over 90 percent of all unemployed are youth. In
addition, Egypt faces enormous fiscal challenges as the fiscal deficit widened to 9.5 percent of
GDP in FY11, a substantial increase compared with the 8.1 percent deficit in FY10 and 7.9
percent originally budgeted for that year. Poverty rates also increased to 25 percent, from 21
percent in 2009. The growing financing needs of the Government have built up pressure in
domestic financial markets, where yields on one year T-Bills increased to 13.6 percent in
September 2011. Limited fiscal space and political uncertainty, combined with rising
unemployment, poverty and regional disparities, could derail the transition process.
2. The proposed Project will address the following priorities (as defined in Paragraph 4 of
World Bank Guidelines for OP 8.00): (a) establishing and/or preserving human, institutional,
and/or social capital; (b) assisting with the crucial initial stages of building capacity for risk
reduction; and (c) supporting measures to mitigate or avert the potential effects of imminent
emergencies or future emergencies or crises in countries at high risk. On February 29, 2012, the
World Bank Regional Vice President approved the processing of this operation on an emergency
basis for OP 8.00.
3. The objectives of the Project are: (i) to create short-term employment opportunities for
unemployed unskilled and semi-skilled workers; and (ii) to provide access to basic infrastructure
services to the target population in poor areas in the Borrower‟s territory. This will be carried
out through the construction/maintenance of community level infrastructure using labor-
intensive techniques and the provision of community services.
4. Specifically, the proposed operation will focus on two main components. The first
component, Employment-Intensive Sub-projects (US$198.0 million), will support two types of
labor intensive sub-projects: (i) small-scale local infrastructure public works sub-projects: canal
cleaning and protection, rehabilitation of schools, housing, and rural roads; and (ii) community
service sub-projects. The second component, Implementation Support (US$2.0 million), will
finance support to project management; audits, public information and communication; technical
verification and quality assurance; monitoring and evaluation; auditing; and social
accountability.
5. The project will be financed through an Emergency Recovery Loan (ERL). The EU is
considering co-financing the proposed project with an amount of Euro 75.00 million. The Danish
International Development Agency (DANIDA) is considering providing parallel financing in the
2
amount of US$ 3.0 million to this project. In addition, parallel financing will be provided by the
International Labor Organization (ILO) through technical assistance to the Government to
support capacity building in use of labor-intensive approaches and techniques. UNDP will also
provide parallel financing in the form of a project that will pilot innovative approaches for public
works. Furthermore, the World Bank, through the Japanese Social Development Fund (JSDF), is
planning to provide grant support (US$2.85 million) to a project aimed at minimizing the risks of
chronic and/or unsafe unemployment among marginalized youth by facilitating their access to
pertinent opportunities for job readiness and job placement.
B. Emergency Challenge: Country Context, Recovery Strategy and Rationale for
Proposed Bank Emergency Project
Country Context
6. The deteriorating security situation and uncertainty following the January 25, 2011
Revolution has slowed down economic activity, and increased poverty and unemployment. On
February 11, 2011, President Hosni Mubarak resigned from the Presidency of Egypt as a result
of a people‟s revolution that erupted on January 25, 2011. As Egypt is going through a
transitional stage of political and economic uncertainty, there have been significant increases in
unemployment rates, from 9.6 percent before the revolution to about 13 percent in December
2011,1 and poverty rates also increased from 21 percent
2 to 25 percent during the same period.
3
In addition, the long-standing deprivation in the poorer parts of Egypt is threatening to derail the
political transition and lead to a surge in extremism. Unskilled and semi-skilled workers,
especially those who are already unemployed, will be more vulnerable as they are among the
poorest segments of society. This may add to the complexity of the transition and could be a
trigger for continuing social unrest, hence the urgency of addressing this important issue.
7. This effect is compounded by the return to Egypt of migrants who were working and living
in Libya. These migrants who remain in Egypt account for an increase in unemployment by an
additional 0.6 percent. This situation has been aggravated as more migrants return to Egypt as a
result of the unrest that is occurring in other Middle Eastern countries.
8. The implications for the Egyptian economy of the crisis in Libya are significant. Libya is the
top destination within the region for Egyptian youth, with 38 percent of youth migrants going to
Libya, followed by 29.4 percent to Saudi Arabia. The estimated 330,000 Egyptians in Libya
remitted up to US$33 million per annum. Official figures state that by March 22, 2011, about
147,900 Egyptians had returned to Egypt from Libya. The profile of returning migrants is as
follows: (i) most come from rural areas (85 percent); and (ii) they tend to have only a basic level
of education, with 25 percent being illiterate, and another 24 percent with a vocational education.
Only fifteen percent have a general secondary high school or university background.4
1 CAPMAS, Labor Force Survey, July-September 2011
2 The World Bank. Poverty in Egypt 2008-09: Withstanding the Global Economic Crisis. January 2011
3 CAPMAS, Household Expenditure Survey, 2012
4 International Organization for Migration (IOM) Cairo 2011
.
3
9. The expected increase in unemployment and underemployment adds to the complexity of
an already existing problem of high unemployment, increasing poverty rates and regional
disparities. Loss of employment is the most prominent cause of households falling into
poverty. The sudden economic slowdown in the context of accelerating inflation in 2008/2009
reversed the gains in poverty reduction achieved during the period of rapid growth before
2008/2009.5 At the same time, the incidence of extreme poverty (the inability to meet basic food
needs) increased by about 20 percent, as high inflation and rising food prices eroded the
purchasing power of the population. This has created an additional strain on the economy‟s
demand for labor. As a result, extreme and absolute poverty actually increased: as many as 5.1
million Egyptians were severely food deprived in 2008/09 (double the number in 2004/05), and
absolute poverty increased from 19.6 percent to 22 percent. During the period 2008/09, 31
million Egyptians (around 40 percent of the population) were poor or near poor. The 2008/09
period was also characterized by a dramatic reduction in opportunities to get out of poverty. The
population‟s vulnerability to sudden employment losses during this period was due to the
absence of any targeted social safety net mechanisms to protect the poor, who typically work in
the informal sector in low-earning occupations. This situation has recently been aggravated as
the Central Agency for Public Mobilization and Statistics (CAPMAS) announced that the
poverty prevalence rate further increased, reaching 25 percent.
10. In the short-run, the events since January 2011 have impacted the Egyptian economy
through many channels, including the following:
(a) Direct Economic losses. Economic losses occurred following serious disruptions in
production, stock market turbulence and capital flight. CAPMAS estimated that the
economic losses were US$1.7 billion (US$650 million in manufacturing, US$150 million
in tourism and US$130 million in construction, with the remainder spread across other
sectors). The Ministry of Finance indicated that the losses during the 18 days of
demonstrations amounted to US$310 million per day. It is expected that economic
growth for the current year could drop to a mere 1.2 percent from over 5 percent prior to
the revolution.
(b) Decrease in exports. Exports in January 2012 declined from EGP 8.2 billion to EGP 7.7
billion and continue to decrease.
(c) Reduction in tourism. Tourist resorts, hotels and tourism companies in Red Sea
governorates forced 90 percent of workers into open-ended periods of leave without pay
after tourism sharply declined. Other tourist resorts decided to keep security and
gardening laborers without paying bonuses. The number of workers in the Red Sea hotel
sector is estimated at 400,000 and most of them come from governorates in south Egypt.
Since a number of foreign airlines closed their branches at Hurghada Airport, workers
were given open-ended periods of leave until the resumption of tourist flights. Occupancy
rates at hotels and tourist resorts at Hurghada, Marsa Alam and Al-Qoseir failed to
surpass 15 percent in 80 percent of the resorts, the lowest rate recorded in recent years. In
addition, over 250,000 tourists cancelled their flights to the Red Sea in the days following
the revolution. The tourism sector has not yet rebounded. Hotels in Luxor and Aswan
report occupancy rates of less than 10 percent. All major tourist sites in Cairo lack
5 The World Bank. Poverty in Egypt 2008-09: Withstanding the Global Economic Crisis. January 2011.
4
visitors and companies declared that pre-booking for the 2011-12 winter seasons was the
lowest witnessed for a winter season in the whole of the previous decade.
(d) Migration. Migration is observed in two directions: Egyptians emigrating (minimal effect
due to general situation in the region) and returnees coming back from Libya (see above).
(e) Withdrawal of Foreign Direct Investment (FDI). Mainly for security reasons, FDI was
practically non-existent in 2011.
(f) Inflationary pressure. It is expected that inflation has increased as a result of the
shortage of food during the unrest, as well as high oil prices. Food prices have reportedly
not returned to their pre-revolution levels.
11. Public works programs, which have been suitable in similar crises, are not part of Egypt’s
safety net system. In general, programs that have been launched in response to a crisis in other
countries fall into two broad groups: (a) programs aimed at providing immediate short-term
employment opportunities (i.e., some variant of public workfare programs), and (b) transfer
programs, cash or in-kind, conditional or unconditional, mainly to maintain a critical minimum
consumption level of vulnerable households to prevent irreversible damage to the accumulation
of human capital. In Egypt, the role of workfare has diminished over time as the public works
program, implemented by the Social Fund for Development (SFD) for the last 20 years, has been
starved of funding.
12. Currently, Egypt’s safety net system is dominated by subsidies on food and energy.
Increases in budget allocations during the last few years have focused on expanding the food
subsidy program.
13. To mitigate social stress associated with the 2008/2009 food crisis, public spending
increased through FY08-09, further distorting the safety net towards subsidies. In spite of
several rounds of reforms to energy subsidies, which are available for all consumers and
producers, subsidies still represent the largest burden on the budget (around 6 percent of GDP).
The food subsidy program consists of two parts: (a) Baladi bread; and (b) ration cards. Bread
subsidies, available for purchase by all Egyptians, are the second largest item in Egypt‟s safety
net (accounting for around 1.5 percent of GDP). Spending on ration card subsidies, provided
only to registered households, comprises only about 0.5 percent of GDP and a recent study
revealed serious flaws in this program. In contrast, spending on cash transfers, which benefit
mostly the poor and vulnerable, amounts to a very small 0.1 percent of GDP, while spending on
public works has decreased to insignificant figures.
14. This Project will complement existing safety nets in Egypt by building up the public works
pillar while addressing the emergency situation. While this Project is designed to meet the
needs of the emergency situation, it should also help build the institutional capacity for PWPs in
Egypt, a tool that is likely to be used frequently in the medium term. The inclusion of PWPs as
an essential part of Egypt‟s safety net was recommended by the Bank as early as 2005, to be
scaled up and down quickly to respond to shocks based on the country‟s situation.
5
Government Response
15. The Government of Egypt (GoE) is planning to implement a PWP for Egypt that would
adopt labor-based methods to address Egypt‟s short-term needs on an emergency basis to
generate job opportunities. The proposed Project supports this strategy.
16. The proposed Project will be implemented by the Social Fund for Development (SFD). The
SFD is a legally autonomous, well-established development organization with a 20-year track
record of providing support to needy and underserved communities. Established in 1991, the
SFD‟s initial key objective was to help mitigate the negative effects of Egypt's structural
adjustment programs. In 1999, the SFD obtained a permanent mandate to focus on job creation.
The SFD has managed considerable amounts of donor resources through grants and loans from
more than 20 multilateral and bilateral donors. The World Bank has been a lead agency in
developing and supporting the SFD and has granted three IDA credits to the SFD, totaling
US$310 million during the period 1992-2005. In addition, the SFD, with the Ministry of Health
and Population (MOHP), jointly implemented the IDA-financed Population Project (Cr. 2830,
closed in 2005). The SFD also is the implementing entity for the Enhancing Access to Finance
for Micro and Small Enterprises Project (Loan 7850-EG, approved March 25, 2010).
17. The SFD is well-placed to implement this Project, as a well-established institution with
significant experience in interventions that provide services and employment to the poor, and
with an increasing focus on community participation, cooperation with NGOs, and
decentralization. Since 1992, about EGP 1.8 billion worth of projects have been implemented by
SFD in infrastructure under its Community and Human Development Department. In the area of
public works, the SFD currently implements two projects, one financed by the EC and another
by the Kreditanstalt für Wiederaufbau (KfW) Development Bank. Over the years, the most
common sub-projects implemented were water supply and sanitation projects, pavement of
roads, cleaning of canals, buildings and riverbank protection.
18. The results of an independent impact evaluation of SFD activities in the areas of public
works and community development for the period 2000-2004 provided a number of insights
which are still relevant today. The evaluation concluded that, regardless of the type of
intervention, communities considered almost all interventions (an average 99.4 percent) to have
been community priorities. Participating communities generally observed a high beneficial
impact of SFD interventions (between 80 and 90 percent of communities with interventions in
education, potable water, road pavement, and environmental projects observed high impacts).
Most communities attributed the positive impact of SFD interventions to improvements in health
and living standards. The evaluation report also concluded that the allocation of PWP funds has
been progressively targeted toward the poorer governorates.
Rationale for Bank Involvement
19. The GoE has requested the Bank‟s technical and financial support in the design and
implementation of a PWP for Egypt. The program will adopt labor-based methods in order to
address Egypt‟s short-term needs by generating short-term job opportunities for income support
to unemployed unskilled and semi-skilled workers. A secondary objective will be the creation
and/or maintenance of infrastructure and community assets.
6
20. The Bank has the technical knowledge and long term experience in supporting PWPs as an
important component of the overall safety net package in many IBRD and IDA countries,
including Egypt. Other donors are considering support for the Government‟s program,
leveraging this proposed Project.
C. Bank Response: The Project
21. The proposed Loan, at US$200 million, will help to finance the costs associated with creating
short-term employment opportunities for the unemployed unskilled and semi-skilled workers in
poor locations in Egypt.
22. The Project will adopt a gradual and phased approach in improving the original design of the
PWP implemented by the SFD in the previous three IDA-financed projects. There are three
important improvements to the model: (i) increasing the percentage of labor intensity;6,7
(ii)
using geographic, community, and self targeting of the poor;8 and (iii) including labor-intensive
community service sub-projects.
Project Development Objectives
23. The objectives of the Project are: (i) to create short-term employment opportunities for
unemployed unskilled and semi-skilled workers; and (ii) to provide access to basic infrastructure
services to the target population in poor areas in the Borrower‟s territory.
Summary of Project Components
Project description:
Component 1: Employment-Intensive Sub-projects (US$198 million)
24. This component will include provision of grants to sponsoring agencies, by governorates and
local authorities, for sub-projects consisting of small-scale infrastructure works including, but
not limited to: canal cleaning and protection, rehabilitation of schools, housing, and rural roads.
The sub-projects will be contracted out to private contractors.
25. This component will also include provision of grants to sponsoring agencies, by local
communities, for sub-projects consisting of community services including, but not limited to,
early childhood education services, outreach for maternal and child health, nutrition, population
services, solid waste collection, and youth employment in rural and urban settings. The sub-
project implementation will be contracted out to NGOs.
6 Labor cost ranging between 50-70 percent of total cost is advised by international literature. The multiplier of a
labor-intensive approach is at least 1.5 compared to only 0.7 for equipment-intensive construction techniques. 7 Current labor intensity applied by SFD average percentage ranges between 22-36%.
8 Geographic targeting will be guided by the Egypt Poverty Map and SFD Poverty targeting toolkit.
7
26. These grants will enable the SFD to also target more skilled unemployed youth in the
provision of social services and could also target more urban settings where skilled
unemployment is a greater concern. UNDP and ILO are working with SFD to expand the menu
of options specifically targeting youth, and if such proposals fit the overall criteria as laid out in
the Operations Manual, they could also be included.
Component 2: Implementation Support (US$2 million)
27. This component will include provision of project implementation support, including project
management, audits, public information and communication, technical verification and quality
assurance, monitoring and evaluation, and social accountability mechanisms.
Eligibility for Processing under OP/BP 8.00
28. The proposed Project is fully consistent with the Bank‟s Rapid Response Guidelines (OP
8.00) criteria. It complies with the guiding principles of the Bank‟s policy on rapid response to
crises and emergencies as it will address the major adverse economic and social impacts
resulting from the effects of economic slowdown since the January 25th revolution and the return
of Egyptian migrants from neighboring countries, especially Libya, in the wake of the uprisings
in the region. The Project will provide a rapid response to the GoE‟s request for urgent assistance
for the above-mentioned emergency.
Consistency with Country Strategy (CAS or ISN)
29. The proposed Project directly supports the second pillar of support (job creation, through
direct emergency lending) of the draft Interim Strategy Note (ISN). The ISN is expected to be
presented to the Board at the same time as the proposed Project. The proposed Project also
supports the draft ISN‟s objective of “creating opportunities for short-term productive job-
creation and initiating steps to improve the environment for longer-term private sector job
creation”.
Expected Outcomes
30. The main outcome indicator will be the number of job opportunities created under the
Project.
31. The intermediate outcome indicators will include: the percentage of labor intensity, the
number of person/days created, and the amount of wages paid. In terms of outputs, these
indicators will include: the number of kilometers of canals cleaned, the number of kilometers of
River Nile banks protected, the number of houses of the poor refurbished, the number of
kilometers of rural roads paved or maintained, and the number of schools maintained.
8
D. Appraisal of Project Activities
Economic Analysis
32. The estimated cost-benefit ratios for the proposed Project (under different scenarios) are
presented in Annex 10 and compare favorably with other successful public works programs
implemented in other areas of the world.
Technical Analysis
33. Global experience indicates that a PWP can be an important component of a safety net in
response to a rapidly deteriorating employment and poverty situation. As discussed above, the
Project will fill this gap in the current safety net system in Egypt.
34. Experience has shown that for the same level of investment in local infrastructure, the use of
labor-based methods can create between two and four times more employment (mostly
unskilled), drop foreign exchange requirements by 50 to 60 percent, decrease overall costs by 10
to 30 percent, and reduce environmental impacts. Further, there is a labor component in the
materials themselves as they are all produced locally (pipes, cement, aggregates, etc.). The
employment multiplier effect of such projects is at least 1.5 because of the injection of money
into the local economy (use of local materials and other inputs, salaries mainly spent on basic
needs).
35. Many PWPs are now being established with a long-term vision of being an integral part of
the country‟s social safety net (scalable PWPs that can be extended during crises). In addition to
infrastructure, social services and restoration of the natural resource base can be added to the
classic menu of public/community works. Key features of a successful PWP would include:
(a) A wage rate lower than the prevailing market wage for comparable (skilled and semi-
skilled) labor, wherever feasible;
(b) A high labor intensity;
(c) A combination of supply-driven sub-projects (sponsored by the Central Government)
and demand-driven sub-projects (sponsored by local authorities and communities); and
(d) Significant communication efforts that enabled potential participants to register
themselves at notified places for public works activity of their choice (totally unskilled,
low-skilled, semi-skilled, skilled, etc).
36. Allocation of funds. Given that a significant part of the public works program benefits accrue
from the infrastructure created, the location of the infrastructure becomes important for
allocation of funds. To increase the chances that the sub-projects will improve living conditions
for those least able to protect themselves against the economic shocks, the locations for the
works were selected using Egypt‟s poverty map taking into consideration the readiness for
implementation and the intensity of labor of the proposed sub-projects.
37. Private Contracting. In Egypt, it is common practice to use contractors to execute public
works programs. The Project will introduce one or more new methods to use contractors such
as: (i) defining the share of labor in each specific contract during the tendering process, and
9
enforcing it; (ii) providing a list of laborers in each locality whom contractors could hire for any
specific activity, with the possibility of directly paying them; and (iii) asking contractors to
specify percent of labor cost in each sub-project that they plan to execute, with the provision that
one of the selection criteria would be the share of labor in total cost, and subsequently picking
the one that promises to meet quality standards and use the highest labor share in total cost.
Alternative ways to allow the Government to fix the wage level for contractors to abide by will
be explored. Again, contractors will be asked to use at least 50 percent of the available local
labor, and only if such local labor is unavailable, will they be permitted to use outside labor.
38. Flexibility and Quick Scale-Up. The team examined the suggested design features that would
enable flexibility and quick scaling up of workfare programs during periods of economic
hardship. The most important opportunity for the team is to enable the Project to support the
move toward greater efficiency, targeting accuracy, and labor intensity. This will then be
evaluated, in the case of a need to scale-up so that the SFD, as a potential organization to
implement this safety net approach, would be in a position to respond quickly. Given its
implementation track record, existing regional offices and name recognition, scaling up would
not be a challenge.
39. Technical viability of SFD. Technical viability has been demonstrated by over 20 years of
successful public works, community and local development activity in Egypt. Investment cost
estimates, physical contingencies, prices and estimates of inputs and outputs are based on actual
historical data under the three previous IDA financed projects, as well as other donor financed
projects. For public works, the SFD uses standardized designs which have been approved by the
relevant line ministries. These standardized designs include engineering, technical, financial, and
economic feasibility aspects, O&M, simple environmental guidelines and cost parameters. Field
evidence demonstrates that these simple, practical standards have enhanced sub-project quality,
sustainability and cost-effectiveness. All sub-projects will be screened by SFD staff and
intermediary agencies. The sponsoring agency will be able to contract technical assistance to
help in the design and implementation of sub-projects, as needed. Training programs are also
being offered to develop the capacity of the implementing partners to prepare, implement,
operate, and maintain sub-projects as well as to acquaint them with the Egypt Environmental
Affairs Agency (EEAA) environmental regulations.
Fiduciary
40. Financial Management. SFD will be responsible for financial management and reporting,
using systems and procedures acceptable to IBRD. Project records will be kept according to
generally accepted accounting principles. They will be audited annually, following international
standards on auditing, by qualified independent external auditors acceptable to the Bank. The
Bank expects the Borrower to submit terms of reference for the project external audit for the
Bank‟s prior review and approval within 3 months of effectiveness. Audit reports will be
submitted to the Bank within six months from the end of each fiscal year (January 1st to
December 31st). There are no outstanding reports or IFRs under projects implemented by the
SFD.
10
41. Procurement. For labor intensive sub-projects, procurement is the responsibility of the
Sponsoring Agencies (SA), which are ministries, governorates, or NGOs; and the Intermediary
Agencies (IA), which are the technical directorates of the governorates and Community
Development Associations (CDAs). These procurement activities will be under the shopping
thresholds for works, US$350,000, and goods, US$100,000. The Procurement Department of the
SFD and its officers in the regional offices will ensure conformity of implementation according
to PM regulations and procedures. For that purpose, they will conduct ex-post reviews, assess
the capacity of the intermediary agencies, and conduct capacity building activities using as a
basis the SFD Procurement Manual for the Labor Intensive Sub-projects. The SFD will sign
Framework Agreements (also known as “Sponsoring Agency Grant Agreements”) with the
SA/NGO which describe the guidelines to be followed and each party‟s role in the
implementation of the sub-project. The SA/NGO then could sub-contract the work with a
contractor and/or supplier. Where activities will be undertaken by an IA, the SA will enter into a
further agreement with the IA, known as an Intermediary Agency Grant Agreement which will
govern the use of the funds.
42. The SFD will have primary responsibility for monitoring physical and financial progress of
the works undertaken by the SA/NGO. Procurement under the proposed Project will include
small value contracts that constitute weed reduction, River Nile bank protection, upgrading of
rural housing conditions, pavement of rural roads, school rehabilitation, solid waste collection
and disposal, etc. The maximum financing for a Labor Intensive Framework Agreement will be
around US$2,000,000 that includes small works in dispersed communities, estimated not to
exceed US$350,000. Large contracts would not arise at the SA/NGOs level due to the nature of
the works involved, and therefore, ICB is not foreseen.
43. All consulting service contracts under Component 2 will be procured at the SFD central
level. The SFD Headquarters Office will be supported by a qualified procurement adviser who
has experience with World Bank procurement procedures.
44. A summary of the procurement capacity assessment and project procurement arrangements
are provided in Annex 6. Risks have been identified and the overall procurement risk is assessed
as high. The main mitigation measures are updating of the procurement manual (a condition of
negotiation which has been completed) and hiring of a qualified procurement adviser, a condition
of disbursement whereby no withdrawal of funds shall be made from the services, non-
consulting services and incremental costs category of the withdrawal schedule unless a
procurement advisor on terms mutually acceptable to the Bank and Borrower.
45. To enhance project readiness for implementation, SFD will distribute the procurement
manual and its annexes to stakeholders after a “validation workshop” once the manual is
finalized and agreed with the Bank. Subsequently, the Procurement Department will train the
procurement officers of the regional offices and the sponsoring and intermediary agencies
concerning the appropriate use of the procurement manual and its annexes.
11
Social
46. From a social perspective, the Project‟s impact is likely to be positive. With the emphasis on
rural areas with priority targeting to Upper Egypt and the targeting of villages in the lowest 20
percent of the poverty map, the poorest and most vulnerable groups are likely to see an increase
in employment, social and economic opportunities. The youth are likely to be the primary
beneficiaries of employment opportunities, as they have higher unemployment rates. Females
also will be targeted through supporting community services sub-projects.
47. Gender. The impact on women will be positive, especially from the social services sub-
projects, where women would be more likely to be among beneficiaries of the services, as well
as more likely to be employed to deliver the services. The gender differentiated impacts will be
monitored by the monitoring and evaluation framework and will be a special focus of the social
accountability measures to allow for adjustment during implementation to improve the impact on
women. Given that male under- and unemployment, combined with discrimination within the
areas where the Project will be located was part of what drove the revolution in Egypt, it is
appropriate to target males in the project areas through infrastructure works.
48. Targeting. Under this program, special emphasis is being given to the poorest communities
and vulnerable groups. A well targeted program is one that reaches the people affected by a
country shock. Targeting beneficiaries of public works programs poses special challenges. The
targeting methods that will be used will depend on the nature of sub-projects as follows:
a. For community infrastructure sub-projects using private contractors, the methods that
were mentioned to improve the contracting procedures will be applied given the
undesirable market distortions by setting wages to less than the market rates.
b. For community social services, community targeting will be used combined with a Proxy
Means testing, wherever it is applicable and as determined by the Ministry of Social
Affairs.
49. Social Accountability. This will be taken into consideration through different mechanisms
as follows: (i) a grievance and transparency mechanism that allows citizens to provide feedback
to the SFD about project implementation and allows potential beneficiaries who were not
included in the program to seek redress; (ii) public information on the availability of employment
opportunities created by the project at relevant levels of implementation; (iii) client satisfaction
surveys, especially for community social services sub-projects; (iv) quality assurance surveys,
especially for community infrastructure services using regional universities; and (v) independent
verification of results of sub-project implementation using NGOs.
Environment
50. The proposed environmental category is “B” and OP/BP 4.01 is triggered. The Task Team
has prepared an Environmental and Social Screening and Assessment Framework (ESSAF),
attached in Annex 9, to address, in a sound environmental manner and in line with the World
Bank safeguards policies, any likely negative environmental impacts potentially resulting from
12
the sub-project activities. The ESSAF was disclosed in-country on March 27, 2012, and also in
the Bank‟s Infoshop on April 2, 2012.
51. The sub-projects of the proposed Project are likely to result in a number of positive
environmental and socio-economic impacts. All of the sub-projects are expected to generate
employment opportunities and improve income generation for many individuals as well as
improving living conditions and livelihoods, especially for those representing the low or poorest
segments of society in targeted areas and communities. This includes the improvement of
housing conditions and solid waste collection for the poor which will lead to positive health and
environmental impacts. However, despite the substantial positive environmental impacts that will
result from the implementation of the sub-projects, there may still be some negative
environmental impacts, though potentially minor and not significant.
52. Consistent with the World Bank OP/BP 8.00, an ESSAF has been developed to ensure
compliance with the Bank‟s safeguard policies during project implementation. The ESSAF
provides general policies, guidelines, codes of practice and procedures to be integrated into
project implementation. The ESSAF also identifies the types of environmental assessment
instruments that are suitable for each sub-project after initial approval. The ESSAF has been
developed specifically to ensure environmental due diligence for all the sub-projects funded by
this Project. It is intended to ensure that, for all activities financed by the proposed Project, all
efforts are made to avoid and minimize environmental and social impacts; and where they cannot
be avoided, that these impacts are identified and the necessary mitigation measures are
developed and implemented following the relevant Egyptian laws as well as the World Bank
policies. In addition, the ESSAF is to assist the SFD in screening all the sub-projects for their
likely environmental impacts, identifying documentation and preparation requirements.
53. Most of the proposed sub-projects are likely to focus on canal weed reduction and protection
of river banks, rehabilitation of rural housing, maintenance of rural roads, school rehabilitation,
and solid waste collection. Individual sub-projects will be screened and assigned the appropriate
environmental category and environmental due diligence will be conducted in accordance with
OP 4.01.
54. Considering the nature and magnitude of potential environmental impacts from the relatively
limited scale and magnitude of reconstruction works, only sub-projects classified as “B” or “C”
will be financed by the Project. Any sub-projects classified as category „A‟ will not be eligible
for funding under this operation.
55. While ensuring due diligence in managing potential environmental risks, one has to
recognize the emergency nature of the proposed Project which aims to provide assistance
towards creating or maintaining infrastructure using labor-intensive techniques. Given that, the
ESSAF is based on the following principles:
The proposed operation will support multiple sub-projects, the detailed designs of which
may not be known at appraisal. To ensure effective application of the World Bank‟s
safeguard policies, the ESSAF provides guidance on the approach to be taken during
implementation for the selection and design of sub-projects and the planning of
mitigation measures;
13
The proposed Project supports only environmental category “B” or “C” sub-projects as
per the World Bank classification for safeguards;
No sub-projects entailing resettlement will be eligible for funding under the Project;
No sub-projects that involve the use or pollution of international waterways will be
financed under this Project;
Sub-projects entailing weeding activities shall be manual weeding (i.e., by hand) and will
not involve the use of pesticides. As a result, World Bank OP 4.09 is not triggered; and
Consultation and disclosure requirements will be simplified to meet the special needs of
these operations. The ESSAF was shared with and disclosed in the SFD and relevant
governorates in Egypt as well as in the World Bank InfoShop.
Lessons learned from previous country experience and/or from Bank-wide experience with
emergency response operations
56. The lessons learned which are summarized below have emerged as relevant to this Project.
This summary places a strong emphasis on lessons learned during the first three phases of Bank
support to the SFD, lessons learned from related projects in Egypt, and lessons learned from best
practice programs around the world.
57. It is critically important to select the program for an emergency operation that could have
some degree of success in mitigating the adverse impacts of the crisis on the poor. If countries
already have well-functioning safety nets, the response to the crisis could be relatively quick.
However, in the absence of a strong functioning safety net, the response is often to expand
whatever program existed before the crisis regardless of its capacity to reach the poorest, or to
launch a new program in haste that may run the risk of poor implementation and lead to
governance issues.
58. Based on Egypt’s context, the PWP as an emergency response to a systemic shock,
supporting short-term, well-targeted, labor-intensive infrastructure sub-projects, can help the
transient poor over the short-term. On the other hand, energy subsidies, poverty, inequality,
unemployment, food security and agriculture are continuing challenges and require key reforms
within a medium-term framework.
59. Targeted interventions can have a strong impact on local area well-being and help poor
communities. Egypt uses contractors to implement infrastructure sub-projects, therefore the
dependence on “self-selection” or self-targeting as the key method of targeting is not feasible. A
combined targeting mechanism will be used to target project interventions, including geographic
targeting, community targeting, selection of sub-projects of high labor intensity, and tendering
contracts in small sizes to allow selection of local labor.
60. Specifically, poverty targeting mechanisms that are kept simple, verifiable, and based on
objective criteria can foster transparency, minimize political interference in resource
allocation and ensure that project resources reach the poorest areas. While it is expected that
there will be issues of political economy that might weigh in on the targeting process, this will be
14
addressed through the use of Egypt‟s Poverty Map which is an objective assessment of priority
poor areas.
61. Investments in monitoring and evaluation systems facilitate the sub-project evaluation
process, provide feedback and necessary information to improve targeting and efficiency, and
are an essential management and planning tool. In order to address the weaknesses in M&E
experienced under previous projects, SFD‟s MIS system has been upgraded (with EU support)
and enables users to receive real time monitoring of the entire sub-project cycle.
62. Continued emphasis on technical quality, including environmental screening processes,
enhances impact and sustainability. Standardization of technical designs and unit costs
simplifies the sub-project preparation and evaluation process, improves the quality of sub-
projects, facilitates the procurement of goods and works, prevents over-design, and enables
participation of poorer communities. The environmental screening checklist has been updated
under the previously completed Bank-financed Social Fund III Project to optimize the criteria
and procedures (and their application) for evaluating the environmental impact of sub-projects.
63. Operations and maintenance procedures need to be defined and agreed upon with
beneficiaries and other stakeholders during the sub-project design phase. Operations and
maintenance of public infrastructure and services is a systemic problem in Egypt.
Recommendations from SFD‟s operation and maintenance pilots in the Sharqiya and Fayoum
Governorates conclude that feasibility studies for labor intensive sub-projects should include an
assessment of whether recurrent and operations and maintenance costs will be made available.
64. There are no policy exceptions and the Project is ready for implementation.
E. Implementation Arrangements and Financing Plan
Project Costs
65. The total estimated costs for the proposed Project amount to US$200 million, including about
0.7 percent physical and price contingencies.
Project Cost Summary
(US$ million)
Components
Cost
Including
Contingencies
% of
Total
IBRD
Financing
%
Financing
Comp-1: Labor Intensive Sub-projects 198
99.0
198
100.0
Comp-2: Implementation Support 2
1.0
2
100.0
Total PROJECT COSTS 200
100.0
200
Other cost tables are presented in Annex 3: Summary Cost Tables.
15
Implementation Arrangements
66. The SFD will be the implementing agency for the proposed Project. The SFD will be
responsible for the overall program, using its own fiduciary management systems that are in
compliance with World Bank regulations and procedures, with institutional arrangements and
procedures in place as a result of the previous three phases of World Bank support to the SFD.
The SFD will rely on its Human and Community Development Central Sector (HCD) and the
capacities of the Financial Management Department, the Internal Audit Department, the
Environmental Safeguards Department, and the Planning, Monitoring, and Evaluation
Department in implementing this Project. There will be no separate Project Implementation Unit
established for the SFD Headquarters. On the other hand, Project Implementation Units (PIUs)
will be established in the Sponsoring Agencies.
67. The SFD will work in close partnership with the governorates, sectoral ministries at the
governorate level, local authorities, NGOs, and CDAs. The SFD will be responsible for
implementing and coordinating the activities of this project with the support of its 27 regional
offices which monitor project progress and reporting structures.
Main Partners:
The SFD will select the intervention areas guided by Egypt‟s poverty map and will fund
eligible sub-projects based on criteria defined in its Operations Manual. SFD‟s regional
offices will oversee the implementation of sub-projects and provide assistance as may be
required to sponsoring agencies (Central Ministry9/Local government offices/ or NGOs
with an established track record of successful intervention and a demonstrated capacity to
implement the proposed sub-project) and IAs (Technical Sectoral Departments). Small
local private contractors/NGOs/ CDAs will be contracted for execution of contracts.
Line Ministries/ Governorates will endorse the proposed sub-projects and facilitate
implementation at the local level. Technical directorates within the Governorates will
provide guidance on sectoral issues and ensure that budgetary allocations are made for
proper operation and maintenance of completed sub-projects. These technical directorates
will also be responsible (as IAs) for implementing infrastructure sub-projects.
NGOs/ Community Development Associations (CDAs). NGOs are registered, large,
experienced development associations with a track record in implementing community
driven development projects. (CDAs) are groups of citizens from the community with a
common interest, which organize into legally constituted civil associations. Both NGOs
and CDAs will identify, prepare, implement, supervise, operate and maintain their sub-
projects, assisted by technical specialists.
68. Project Oversight: The Board of Directors of the SFD is responsible for project oversight.
The Board is chaired by the Prime Minister and includes ministers, experts in development,
private sector representatives, and academia. SFD‟s Managing Director will be responsible for
general project coordination and implementation, and the General Manager of the Human and
Community Development Group will be responsible for day-to-day project management.
9 This will be applied only for central level ministerial sub-projects that would involve technical or geographical
coverage requirements to be implemented at that level.
16
69. SFD Roles and Responsibilities: Key SFD duties will include: (a) preparing the sub-project
pipeline in accordance with guidelines and eligibility criteria defined in the Operations Manual;
(b) assessing the degree of labor intensity of the proposed sub-projects, (c) assessing the degree
of community participation in identifying and executing sub-projects and the quality of the skills
upgrading activities proposed; (d) supervising the activities of the SAs and the IAs; (e)
overseeing the procurement arrangements to ensure that implementing partners are adhering to
the agreed procedures; (f) ensuring that SAs are actually carrying out the capacity building
activities for the implementing partners (including training on sub-project implementation,
contracting, operation and maintenance, and financial management); (g) monitoring performance
through the Management Information System (MIS) and reporting quarterly on progress; and (h)
developing an impact evaluation process to provide information on project outcomes.
Alternatives Considered and Reasons for Rejection
70. The Bank was asked to consider the use of a Development Policy Loan (DPL). A DPL
would be more appropriate for an operation that aims to support the adoption of appropriate
policy reforms having a medium- to long-term impact on the unemployment problem in Egypt.
The proposed Project, on the other hand, is designed to deliver support urgently to improve
short-term employment opportunities that would be responsive to the immediate needs of the
Government.
71. The Bank was also asked to consider small and medium enterprise programs. The Bank is
already undertaking such support through the Enhancing Access to Finance for Micro- and
Small-Enterprises (MSEs) Project (US$300 million), which is being implemented by SFD. The
objective of the project is to contribute to a sustainable improvement in inclusive (region and
gender) access to finance for MSEs on a commercial basis. There are two components to the
project, the first component being a line of credit for microfinance channeled through banks,
Non-Governmental Organizations (NGOs) and potential Microfinance Institutions (MFIs).
Finally, this support would not be in compliance with the request from the Government to
prepare a project under the Bank‟s guidelines for “Rapid Response to Crises and Emergency
Operations.”
72. Support to design a broader safety net assistance program. One option considered was
having a project design which addresses different aspects of the safety net, including reform of
subsidies, cash transfers under the Ministry of Social Affairs, and public workfare and
community development under the SFD. This would not be feasible within the context of an
emergency operation, because such a project would be more complex in design and therefore
would take longer to prepare and would involve several agencies. The proposed Project will
make an important contribution to the Government‟s safety net reform by strengthening one of
the key safety net instruments, the SFD, and making it more efficient and effective. The subsidy
issue will continue to be pursued through macroeconomic policy dialogue
73. Support for labor-intensive public works implemented by line ministries. While such
programs could be implemented relatively quickly, they were rejected for the following reasons:
(i) any short term response to the crisis should be consistent with the longer term vision for
17
Egypt, and given that in the long run the private sector has to be the engine of employment
generation, hiring more people into an already too large public sector would be inconsistent with
the vision, so an approach using private contractors and NGOs is better; (ii) the labor intensity of
ministry-run programs is too low; and (iii) ministry programs do not correspond as well to local
needs as programs with a more demand-driven approach.
74. Due to the emergency nature of the proposed Project, supervision will be carried out on a
regular basis from the Bank‟s field office in Cairo. In addition, procurement and financial
management specialists will carry out a minimum of two missions per year. An environmental
specialist will be included in the project supervision team. The Project will be supported by
operations staff in World Bank Headquarters.
75. The proposed Project is expected to close on December 31, 2015. It will be implemented
over three years.
F. Key Risks and Mitigating Measures
76. The overall risk rating for the Project is Substantial. The Project has been prepared and will
be implemented in a country and political environment that is still in transition. The Country,
Governance, Fraud and Corruption risks are rated „Substantial‟. Mitigating measures to address
these risks include, inter alia: (i) a project design that focuses on poor areas where the risk of
major disruptions to project activities is lower; (ii) selection of the SFD as Implementing
Agency. The SFD has considerable prior experience with implementing Bank-financed projects,
and is familiar with Bank policies and procedures; and (iii) fiduciary safeguards in place for the
Project to ensure effective oversight of the flow of funds and procurement procedures. The
Procurement Risk Rating is „High‟ because of gaps in capacity to carry out procurement,
especially at the local levels. Mitigating measures in place under the Project include: (i) hiring
an experienced Procurement Advisor to help build procurement capacity and monitor conformity
with procedures used for selection of consulting services; and (ii) updating the SFD Procurement
Manual to ensure clear definitions of roles and responsibilities and consistent application of
procedures. The project risks, their ratings, and mitigating measures are detailed in the
Operational Risk Assessment Framework in Annex 4.
G. Terms and Conditions for Project Financing
77. The amount of the loan is US$200 million. The Borrower completed the Loan Choice
Worksheet during negotiations and the parties agreed on an IBRD Variable Spread Loan with a
29 year maturity and a 7 year grace period with commitment linked level repayment pattern.
Conditions for sub-project financing are detailed in the Schedule to the Project Agreement.
18
Annex 1: Detailed Description of Project Components
ARAB REPUBLIC OF EGYPT
Emergency Labor Intensive Investment Project
I. Proposed Development Objective(s)
1. The objectives of the Project are: (i) to create short-term employment opportunities for
unemployed unskilled and semi-skilled workers; and (ii) to provide access to basic infrastructure
services to the target population in poor areas in the Borrower‟s territory.
II. Preliminary Description
2. The Project will be three years in length, and will be financed by a US$200 million loan. It
will be implemented by SFD following World Bank policies and procedures.
Component 1: Employment-Intensive Sub-projects (US$198.0 million)
3. This component will support two types of sub-projects: (i) small-scale local infrastructure
works sub-projects; and (ii) community-level labor-intensive sub-projects for provision of social
services.
4. Labor Intensity. The component will support employment-intensive sub-projects that will
apply a labor intensity percentage of an overall average of 40 percent, higher than that currently
being achieved in Egypt.
5. Small Scale Local Infrastructure Public Works Sub-projects. Eligible sub-projects could
include, but are not limited to: canal weed reduction, Nile River bank protection, upgrading the
conditions of rural housing, pavement of rural roads, and school rehabilitation. These sub-
projects could be demand-driven, requested by the local government at the governorate level, or
supply driven, requested by a central ministry based on needs.
6. Demand Driven Community Service Sub-projects. These would support the provision of
demand driven community services. Social service sub-projects tend to employ unemployed
females, so this type of sub-project would increase the percentage of targeting of women under
the Project. Sub-projects could include labor intensive interventions such as community services,
early childhood education services, employment intensive population services, outreach for
health and nutrition services, solid waste collection, and youth engagement sub-projects, mainly
in rural and urban areas.
7. Youth Employment. In addition to those specific sub-projects that will be targeted for youth
employment in rural and urban settings, it is anticipated that the youth beneficiaries of the sub-
projects funded under this component would be high, reaching 60 percent as projected by project
estimates.
19
Component 2: Implementation Support (US$2.0 million)
8. This component will finance the following:
9. Public Information, Communication, and Social Accountability. The component will
support the design and implementation of a communication and social mobilization strategy and
detailed action plan. The objective of the communication strategy will be to: (i) promote the
benefits of labor intensive projects; (ii) raise public awareness about the availability of the
potential employment opportunities that would be created by the Project; (iii) address areas of
concern raised as the project is implemented; and (iv) create channels for feedback from the
beneficiaries and civil society that would improve implementation. The communication strategy
and plan will be prepared during the first year of project implementation. The strategy will
propose key messages to be disseminated through communication/media channels, and training.
10. In addition, the component will support the design and implementation of a grievance and
transparency mechanism that would allow citizens to provide feedback to the SFD about project
implementation and allow potential beneficiaries who have not been included in the program to
seek redress.
11. Technical Verification, Quality Assurance, and Audits. Periodic technical verification will
be carried out on a semi-annual basis during the life of the Project, using an Independent
Verification Expert (IVE) and NGOs. The IVE will verify: (i) the intermediate sectoral
outcomes; and (ii) the output indicators. Quality assurance firms will assess: (i) the quality of
the works; (ii) whether sub-projects are operated and maintained in accordance with SFD‟s
maintenance manuals; (iii) compliance with the Operations Manual; and (iv) compliance with
environmental and social safeguards for community infrastructure sub-projects as well as client
satisfaction rates for community social services sub-projects.
12. Project Management. The Project will be implemented by the SFD using fiduciary
management systems that will be in compliance with World Bank regulations and procedures.
13. Project Monitoring & Evaluation. Monitoring will be carried out by the SFD‟s internal
monitoring system using the SFD management information system (MIS). The Project will
finance support to conduct mid-term, end-of-project, and impact evaluations that will assist the
Government of Egypt in its potential for scale-up as an essential part of Egypt‟s social safety net
program. Evaluations will be carried out through independent consulting firms.
20
Annex 2: Results Framework and Monitoring
EGYPT: Emergency Labor Intensive Investment Project
Results Framework Project Development Objective (PDO): (i) To create short-term employment opportunities for unemployed unskilled and semi-skilled workers; and (ii) to provide access to basic
infrastructure services to the target population, in poor areas in the Borrower’s territory.
PDO Level Results Indicators
Co
re
Unit of
Measure Baseline
Cumulative Target Values Frequency
Data Source/
Methodology
Responsibility
for Data
Collection
Description
(indicator
definition etc.) YR 1 YR 2 YR3 YR 4 YR5
Indicator One:
No. of direct job opportunities
created through the project.
Number
0
50,000
120,000
194,800
Every 6
months
SFD MIS
SFD
Number of job
opportunities
calculated a 4
month cycle per
job created
based on
number
person/days
employment
created
Indicator Two:
No. of indirect job opportunities
created through the project.
Number
0
17,000
40,000
64,000
Every 6
months
SFD MIS
SFD
This is an
average factor of
1.5 times of
direct job
opportunities
calculated for
community
infrastructure
subprojects at
any given time
Indicator Three:
Percentage of direct job
opportunities created through the
project, gender disaggregated
Number
0
25% of
direct job
opportuniti
es for
females
25% of
direct job
opportuniti
es for
females
25% of
direct job
opportunit
ies for
females
Every 6
months
SFD MIS
SFD
Extent of female
participation in
jobs created
Indicator Four:
Percentage of direct job
opportunities created through the
project, age disaggregated
Number
0
50% of
direct job
opportuniti
es for youth
55% of
direct job
opportuniti
es for youth
60% of
direct job
opportunit
ies for
youth
Every 6
months
SFD MIS
SFD
Extend of youth
below age of 30
participation in
jobs created
21
INTERMEDIATE RESULTS
Intermediate Results
Intermediate Result indicator
One:
A- Percentage of Quality
subprojects completed
as measured by– Client
Satisfaction
Percent
0
65
70
75
MTR and
End of
Project
Evaluation
Through
client
satisfaction
surveys by an
independent
agency
Independent
agency/SFD
Percentage of
client satisfaction rates of services
provided at
subproject level
Intermediate Result indicator
One:
B- Percentage of
subprojects completed
with high– Technical
Quality
Percent
0
60
70
75
MTR and
End of
Project
Evaluation
Through
technical
surveys by an
independent
agency
Independent
agency/SFD
Percentage of
infrastructure
subprojects
achieving satisfactory levels
of quality
Intermediate Result indicator
Two:
Labor intensity of subprojects
Percent
22-36
30
35
40
Every 6
months
SFD MIS
SFD
Percentage of
wages paid from total subprojects
costs.
Intermediate Result indicator
Three:
Number of person/days of
employment created
Number
0
5 million
12 million
19.48
million
Every 6
months
SFD MIS
SFD
No. of working
days of employment
created by the
subprojects
Intermediate Result indicator
Four:
Wages paid to workers
(disaggregated by gender)
Number
20 million 40 million 79.2
million
Every 6
months
SFD MIS
SFD
Amount paid in
USD to workers in
subprojects
Intermediate Result indicator
Four:
Kilometers of canals cleaned
Number
0
0
10,200
10,200
Every 6
months
SFD MIS
SFD
The same number of 10,200 km will
be cleaned each
year.
Intermediate Result indicator
Five:
Kilometers of River Nile bank
protected
Number
0
11
30
47
Every 6
months
SFD MIS
SFD
No Kilometers
of River Nile
bank protected
cumulative
Intermediate Result indicator Six:
Number of houses of the poor
rehabilitated
Number
0
2,400
4,960
7,591
Every 6
months
SFD MIS
SFD
Number of
houses of the
poor
rehabilitated
cumulative
Intermediate Result indicator
Seven:
Number
0
66.5
88.5
122
Every 6
SFD MIS
SFD
Number of
Kilometers of
22
Kilometers of rural roads
upgraded
months rural roads
upgraded
cumulative
Intermediate Result indicator
Eight:
Number of classrooms in schools
and kindergartens rehabilitated
Number
0
2,000
5,000
12,000
classroom
s in 710
schools
and 500
KGs
Every 6
months
SFD MIS
SFD
Number of
classrooms in
schools and
kindergartens
rehabilitated
cumulative
23
Annex 3: Summary of Estimated Project Costs
ARAB REPUBLIC OF EGYPT
Emergency Labor Intensive Investment Project
Components Cost Summary
(US$ million)
%
Foreign
Exchange
% Total
Base
Costs
Local
Components
Foreign
Total
Comp-1: Labor Intensive Sub-
projects 196.57
196.57
0
98.3
Comp-2: Implementation
Support 1.25
0.75
2.0
40
1.0
Total BASELINE COSTS
Physical Contingencies
0.79
0.79
100
0.4
Price Contingencies
0.64
0.64
100
0.3
Total PROJECT COSTS 197.82
2.18
200.0
1.1
Expenditure Accounts Cost Summary
(US$ million)
%
Foreign
Exchange
Expenditure Accounts
Local
Foreign
Total
A. Sub-projects to SFD
196.57
196.57
0
B. Consultants‟ Services,
Training, Audit
1.25
0.75
2.0
40
Total BASELINE COSTS
Physical Contingencies
0.79
0.79
100
Price Contingencies
0.64
0.64
100
Total PROJECT COSTS
197.82
2.18
200
1.1
24
Annex 4: Operational Risk Assessment Framework (ORAF)
ARAB REPUBLIC OF EGYPT
Emergency Labor Intensive Investment Project
Project Stakeholder Risks Rating M
Description: SFD as an institution is supported by the
government and the donor community, and is known as an
effective poverty reduction instrument. Job creation is the top
priority. Local government is the focal point for identification of
sub-projects, and there may be the possibility of bias in
targeting.
Risk Management: The project will follow standard mechanisms for targeting, combining
geographic targeting, self-targeting, and community targeting.
Resp: SFD/ Human &
Community
Development Sector
Stage: Implementation Due Date : By
Effectiveness Status: Ongoing
At the local level, there may be bias in the identification of sub-
projects to be funded.
Risk Management: The majority of sub-projects were identified during project preparation to
avoid bias in sub-projects identification.
Resp: SFD/ Human &
Community
Development Sector
Stage: Appraisal Due Date : April 13,
2012
Status:
Completed
Implementing Agency Risks (including fiduciary)
Capacity Rating: S
Description: Lack of sufficient capacity for project
management, given that SFD has not been managing PWP for
many years. Insufficient procurement and FM capacity,
including a challenging public financial management
environment, and insufficient levels of transparency at the
country and sector levels. Lack of implementing capacity at the
local levels. SFD did at one time have an active public works
program, which the WB supported, but the program closed in
the 1990s due to diminished demand. The staffing, procedures
and other arrangements used during that period may no longer
be in place. However, capacity under the ongoing WB
microcredit project indicates that project management and
fiduciary capacity are adequate.
Risk Management: Support from the project, under Component 2, in the form of TA to build
project management capacity, including in the areas of project management, procurement and
financial management.
Resp: SFD/ Human &
Community
Development Sector
Stage: Appraisal Due Date : April 13,
2012
Status:
Completed
Procurement risk is considered „High‟ because: (i) there are
gaps in procurement capacity, especially at the local level; and
(ii) all procurement for goods will be carried out using
Shopping procedures.
Financial Management risk is considered “Substantial” because:
(i) the project is complex with decentralized implementation
arrangements with the SAs and NGOs at the governorate level
Risk Management: Procurement: Mitigation measures include: (i) hire experienced Procurement
Advisor; (ii) update Procurement Manual with complete annexes to ensure clear definitions of roles
and responsibilities, and consistent application of procedures; (iii) reinforce capacity of regional
offices through Procurement Advisor to monitor conformity with procedures used by SAs and IAs;
and (iv) provide capacity building on development of Procurement Manual and Annexes.
Financial Management: Mitigation measures include: (i) the Operations Manual clarifies the
roles/responsibilities of the different implementation layers; (ii) per the framework agreements with
the Sponsoring Agencies (SAs), the PIUs in the ministries, governorates or NGOs will be
25
managing the funds; (ii) there is weak capacity and oversight at
the decentralized level; and (iii) the PFM diagnostics on Egypt
during the past year have indicated that the PFM risk in Egypt is
Substantial, with stagnant PFM reform agenda..
responsible for sending monthly technical and financial reports to the SFD ROs in order to be
entitled to request future tranches; (iii) SFD procedures have been amended to capture the FM
arrangements and disbursement requirements of the project; (iv) the SFD Internal Audit
Department has established a risk based audit strategy which is acceptable to the Bank; (v) the SFD
will track continuously the amounts actually disbursed, through the SFD Finance Department, and
not only the amounts transferred to the SA.
Resp: SFD/ Financial
Management and
Procurement
Departments
Stage: Implementation
Due Date : Three
months after
effectiveness
Status: Ongoing
Risk Management: The project will support the establishment of a web-based grievance system
with text messaging capability to allow reporting of irregularities, complainants, and feedback.
Resp: SFD/ Human &
Community
Development Sector
Stage: Implementation
Due Date: Within six
months of project
signing
Status: Ongoing
Governance Rating S
Description: Project implementation will involve multiple
agencies at different levels, and this could complicate the
implementation process, especially since the project is a Rapid
Response operation.
Roles and responsibilities of the different agencies and levels
(central, Governorate, municipality) may not be sufficiently
clear.
Lags in decision-making.
Too few qualified staff at local level to implement a large PWP.
SFD has a long and positive history of implementing similar
projects.
Risk Management: TA support under the project could be used to help build up the capacity at the
local level. Also, the Project Operations Manual will detail the roles and responsibilities of all the
players.
Resp: SFD/ Human &
Community
Development Sector
Stage: Implementation Due Date : Six months
after effectiveness Status: Ongoing
Project Risks
Design Rating: S
Description: The project is complex in nature, with weak
capacity of the implementing partners, including Community
Development Associations (CDAs) and NGOs.
While envisaged PWP activities are straight forward, the project
would provide support for the adoption of several targeting
mechanisms, some of which are new. Inequitable or skewed
targeting of the poor for participation in the public works sub-
Risk Management: The project includes funding to build and strengthen capacity of the SFD and
the implementing partners, including fiduciary functions. For example, all CDAs and NGOs will
be required to have a Project Implementation Unit (PIU) which includes a full time project
manager, an accountant and a procurement specialist.
The project includes funding to build capacity of the SFD to use available and tested targeting
mechanisms.
26
projects. Egypt does not have a scalable targeted social
protection system to adequately protect the poor if a crisis
emerges. Enhanced targeting measures are needed.
Resp: SFD/ Human
& Community
Development Sector
Stage: Effectiveness Due Date : By
Effectiveness Status: Ongoing
Social & Environmental Rating: L
Description: Social – Social risks are minimal or non-existent.
This project would directly benefit unskilled, impoverished and
largely rural population.
Environmental - there may be some negative environmental
impacts resulting from implementing some sub-projects though
potentially minor and not significant. SFD has experience in
implementing EMP as per World Bank policies and guidelines.
It also has environmental focal points and qualified
environmental consultants.
Risk Management: An Environmental and Social Screening and Assessment Framework
(ESSAF) has been developed to ensure environmental due diligence for all the sub-projects funded
by this project. It is intended to ensure that, for all activities financed by the project, all efforts are
made to avoid and minimize environmental and social impacts.
Resp: SFD/ Human &
Community
Development Sector
Stage: Appraisal Due Date : April 2,
2012 Status: Done
Delivery Monitoring & Sustainability Rating: M
Description: The M&E system currently in place may not be
adequate to effectively measure project results, including
outputs and outcomes. This risk is considered Moderate as the
SFD has developed M&E systems to monitor previous WB-
financed projects.
There is a risk to sustainability if the Government will not
provide sufficient funding for O&M costs related to the public
works activities after the project closes, even though covering
these O&M costs is a requirement as part of the initial sub-
project agreement with the local government authorities.
Risk Management: The SFD MIS system has been upgraded (with EU support) and enables users
to receive real time monitoring of the entire subproject cycle. The MIS was also modified to
enable it to collect and report on project specific outputs and outcomes in disaggregated manner.
The proposed project will also include support to continue strengthening the SFD M&E function
for project monitoring.
As the project is addressing country shocks, it is not meant to be financially sustainable. However,
capacity development of the SFD as an institution that will be capable of implementing this
program in a scalable manner is an essential element of the program‟s sustainability and resources
are devoted under the project towards that end.
Resp: SFD/ Financial
Department
Stage: Implementation
Due Date : By six
months from project
signing
Status: Ongoing
Overall Risk Following Review
Implementation Risk Rating: S
Comments: Given that the overall risk is rated as S, the project team will intensify
its supervision efforts during implementation including planning additional
missions during the first year of implementation, and including sectoral and
fiduciary Bank team members to ensure the compliance of the SFD to the
application of the mitigation measures outlined above.
27
Annex 5: Financial Management and Disbursement Arrangements
ARAB REPUBLIC OF EGYPT
Emergency Labor Intensive Investment Project
A. Executive Summary and Conclusions:
1. An assessment of the Financial Management (FM) arrangements for the proposed Project
was undertaken in March 2012 to assess the capacity of the Project‟s implementing entity and
assist in determining the required FM arrangements for project implementation. A detailed FM
capacity assessment of the SFD was conducted and its outcome is found to be satisfactory to the
Bank.
2. The Project‟s implementation arrangements were discussed at length with an evaluation
of all FM options to be applied during implementation and their impact on the various
stakeholders under the Project. The project activities will be implemented by the SFD which has
the overall responsibility for project oversight, coordination, and implementation. While
Component 2 of the Project will finance project implementation support disbursed directly by the
SFD, Component 1of the Project will provide grants to Sponsoring Agencies (SAs) for the
carrying out of sub-projects consisting of small-scale infrastructure public works and community
services. To facilitate the carrying out of Component 1of the Project, the SFD will sign Grant
Agreements with the SAs in accordance with eligibility criteria and procedures acceptable to the
Bank, for sub-projects selected, implemented and evaluated in accordance with the principles
and procedures of the Project‟s Operations Manual.
3. At the country level, the FM risk is considered as substantial due to the stagnant Public
Financial Management (PFM) reform agenda for several years. The main challenges affecting
the FM risk at the country level, as assessed by the 2009 PEFA report and the 2008 CFAA, are:
(a) weak intricate internal control system, (b) absence of a Government Financial Management
Information System (GFMIS); (c) lack of transparency; and (d) weak regulatory framework and
capacity of the Egyptian Supreme Audit Institute. The current political and post revolution
changes in the country represent an opportunity for tackling the PFM reform agenda provided
that the Government becomes more engaged in the PFM reform.
4. At the project level, the FM risk is considered substantial before mitigating measures due
to the complex implementation and oversight arrangements and the capacity at the decentralized
level.
5. To mitigate the FM risks, the following mitigating measures have been agreed upon:
(i) The SFD will benefit from its experience with World Bank-financed projects and most
recently the Enhancing Access to Finance for Micro and Small Enterprises Project during
the preparation of which the Bank worked closely with the SFD team to improve the
SFD‟s internal control procedures, including updating the FM Manual and the Internal
Audit risk-based approach strategy.
(ii) The Operations Manual has been revised to clarify the relations/responsibilities of the
different layers of implementation.
28
(iii)The SFD‟s Internal Audit Department (IAD) will play a major role in assessing the
capacity of decentralized implementing agencies before advancing the project funds.
(iv) The SFD has an acceptable automated accounting system which is Oracle based. The
SFD will create a new unique code for this project and this action is expected to be
concluded within one month from project effectiveness.
(v) The SFD will contract with an IVE, based on terms of reference (TOR) acceptable to the
Bank, to assess and verify that: (i) project outcomes have been met; (ii) the quality of
works undertaken in carrying out sub-projects is acceptable; and (iii) sub-projects are
implemented and maintained in accordance with the requirements of the Maintenance
Manuals, the ESSAF and the Operations Manual.
(vi) The SFD will contract with an independent external auditor based on TORs acceptable to
the Bank, for the purpose of carrying out an external audit of the Project‟s financial
statements which will include an extended scope to audit the SA implementation of sub-
projects and their compliance with the agreed FM system and internal control procedures.
6. The SFD has prior experience with Bank-financed projects. The most recent project, SFD
III, closed in February 2006 with satisfactory FM performance and audit compliance rate. The
SFD is currently implementing the Enhancing Access to Finance for Micro and Small
Enterprises Project, a US$300 million operation with satisfactory FM performance.
FM Arrangements:
Roles and Responsibilities
7. The SFD: The SFD will be responsible for maintaining the project‟s FM arrangements,
including providing oversight of sub-projects implementation and monitoring the SAs‟
compliance with the Operations Manual, including financial and internal control procedures. The
SFD will be responsible for budgeting, recording and reporting financial activities under the
umbrella of the Project, requesting transfer of funds from the World Bank and transferring funds
to the PIU/NGO. The SFD will contract with an independent external auditor based on TORs
acceptable to the Bank, for the purpose of carrying out an external audit of the Project‟s
Financial Statements.
8. The SFD Internal Audit (IAD): As per the existing IAD risk-based strategy, the IAD
will be responsible for evaluating all PIUs and NGOs interested in implementing sub-projects
under this Project. The IAD has representatives stationed in their Regional Offices (ROs) who
will be responsible for carrying out the detailed assessments. The Bank reviewed the IAD‟s
strategy, including their process of assessing the capacity of PIUs/NGOs to implement sub-
projects and found the IAD strategy and the IAD capacity assessment process to be acceptable.
Subsequent to the IAD‟s assessment and approval, the SFD will sign a Grant Agreement with the
SA. The IAD, through conducting field visits, will follow up on the project implementation
throughout the project‟s life.
9. The Sponsoring Agencies (SA) (PIUs/NGOs): The SA, in coordination with the IA, is
responsible for implementation of sub-grants including the issuance of bidding documents, the
selection process, supervision of implementation, the verification of technical acceptability of
29
implemented activities, and the issuance of payments to beneficiaries. Each SA will open and
manage a separate bank account denominated in Egyptian Pounds, at an acceptable bank, for the
sole purpose of managing the sub-grants received from the SFD under this Project. Each SA will
follow acceptable FM systems and control procedures as agreed upon and as per the Operations
Manual. The SAs will prepare monthly bank reconciliation and submit monthly financial and
technical packages to the SFD office. The PIUs under the Ministries and Governorates are
subject to the Central Accountancy Office (CAO) regular audit and the NGOs are legally
required to have their annual financial statements audited by an independent external auditor. In
addition, SAs will be subject to the annual external audits and regular audits by the SFD‟s IA
Department.
Staffing:
10. The SFD Finance Department‟s structure is considered to be adequate in terms of
staffing, capacity and previous experience in conducting project financial transactions. The staff
capacity is considered to be adequate to carry out the additional workload of the Project. There
are 100 employees in the Finance and Administration Group, both at the main office and the
SFD‟s regional offices. SFD has prior experience with Bank-financed projects, has achieved
satisfactory FM performance and has received unqualified audit reports in the past.10
Accounting, Recording and Reporting:
11. The SFD will record all project-related transactions using accrual basis and will maintain
the accounting records. Original supporting documents for sub-projects will be kept at the SA
level.
12. The SFD bookkeeping is automated through the Oracle accounting system, which is
centralized in the SFD‟s Main Office. The regional offices have the ability to access the SFD
MIS for the purposes of recording and reporting activities. The SFD accounting system is
considered acceptable and SFD staff members are familiar with World Bank requirements,
having been engaged previously with several Bank-financed projects. While the system was
found to be generally acceptable by the Bank, it was agreed that the SFD‟s IT team will establish
a separate module/code in the Oracle system for the sole purpose of recording and reporting on
all project related transactions. The SFD‟s accounting system is capable of generating quarterly
Interim Financial Reports (IFRs) and annual Project Financial Statements (PFS) which are
required under the Loan Agreement. The format and content of the project reports has been
discussed and agreed with the SFD Finance and IT Departments during project appraisal.
13. The Grant Agreement with the SA will obligate the PIUs to report on technical and
financial progress on a monthly basis to the SFD. With regard to contracting with PIUs to
implement sub-grants, the PIUs will be given access to SFD‟s MIS system to execute the
recording and reporting activities. When contracting with NGOs, the SFD‟s regional offices will
be responsible for the recording and reporting on the SFD system on behalf of the NGOs. Each
sub-project agreement between the SFD and the SA is given a unique code in the SFD automated
accounting system against the financing donor (i.e., The World Bank).
10
Please refer to Annex 2 for the SFD Finance Department organizational structure
30
14. Contracts will be kept at the SFD Headquarters while supporting documents for the sub-
projects will be kept at the PIU/NGO level where the supporting documents will also be required
to be scanned and sent to the SFD‟s regional offices as part of the disbursement process. The
Grant Agreement with the PIUs will state that the SFD IA Department and the independent
external auditor will be granted access to examine the original project documents supporting
actual disbursements.
15. The SFD will keep track of the amounts actually disbursed and not only the amounts
transferred to the PIUs/NGOs. The amounts actually disbursed to the contractors/suppliers
should represent the basis for documentation of expenditures and requesting future advances.
Flow of Funds and Internal Controls:
16. To facilitate the flow of funds (provided the advancing of loan proceeds to a Designated
Account is permitted by the Bank), a segregated USD Designated Account (DA) will be opened
and managed by the SFD for the sole purpose of managing the project funds. The project‟s
design allows SFD to request advances to the DA for an amount equal to two quarters (6 months)
of the Project‟s cash forecast as presented in the quarterly unaudited IFRs (i.e., IFR based
disbursement). Other disbursement methods such as reimbursement, direct payment and special
commitments will be available.
17. A monthly bank reconciliation of the DA will be prepared by the SFD Financial Internal
Control Department and will be prepared by Financial Officer and reviewed by the Internal
Control Department Senior Manager.
18. In addition, each SA will open and manage a separate bank account denominated in
Egyptian Pounds, at an acceptable bank, for the sole purpose of managing the sub-grants
received from the SFD under this Project. Each SA will issue a disbursement request to the SFD
regional office based on a 6-month disbursement forecast requesting the advance payment and
later subsequently advanced after documenting initial advances.
19. The SFD‟s regional office will forward the requests for funds to the Human and
Community Development Department (HCD). The HCD will fill out a disbursement form with
all project information (i.e., code, name, responsible department, sub-project start date, sub-
project duration, sub-project developmental objective, financing source, project value, total
number of tranches according to the contract, previous tranches and their respective amount,
remaining amount, SA bank name, bank account number). The form is signed by the responsible
sub-project officer, and approved by the HCD Head of the Department and HCD Sector Head.
The form is then reviewed and signed by the Monitoring and Evaluation Department. The form
is forwarded to the Finance Department where it is reviewed, approved and authorized for
payment. The form is signed by the Internal Control Department representative and the Head of
Operations. The Finance Department issues a letter to the bank to transfer the requested and
approved advance or replenishment to the SA from the SFD DA opened for the World Bank
31
project to the SA bank account. The letter is signed by the Internal Control Manager and the
Internal Control Senior Manager.11
20. The same procedures apply for subsequent tranches. The following documents are
attached with the disbursement request from the SA to the SFD‟s regional office:
- The sub-project‟s disbursements to date.
- Technical report on the sub-project‟s achievements to date.
- Sub-project‟s cash forecast and planned activities.
21. The project disbursement plan and the budgetary process, which is conducted by the SFD
Finance Department, is based on the signed contracts with the PIUs, and accordingly, the project
disbursements forecast is registered on the system, will be updated periodically and will be used
to reflect the variances upon IFRs submission. It is necessary that variance analysis be prepared
with each IFR submission explaining variances that exceed 15 percent between actual and
planned figures of the previous six months/quarter. Also, the IFR package will include DA
Reconciliation Statement, Sources and Uses of Funds by Component and by Category, a List of
Payments against contracts subject to the Bank‟s prior review, and a List of Payments against
contracts not subject to the Bank‟s prior review.
22. The Borrower is responsible to bear all risks associated with foreign exchange
fluctuations when making transfers from the DA which is denominated in US Dollars to the sub-
accounts denominated in Egyptian Pounds. At the end of the Project, any unused balance in
Egyptian Pounds should be converted to US Dollars and deposited in the DA.
Report-Based Disbursement
23. Under the report-based disbursement method, a forecast of expenditures will be agreed
between the SFD and the Bank, covering up to two calendar quarters. Thereafter, aggregate
disbursement requests not exceeding this forecast amount are transferred by the Bank into the
Designated Account upon demand by the SFD. Disbursements will be made against Withdrawal
Applications supported by IFRs. The Designated Account would be used in accordance with the
Bank‟s Disbursement Guidelines. The SFD will be responsible for administration of the
Designated Account and all disbursement related transactions.
24. Under Component 2 of this project, the capacity of the SFD staff in the regional offices
will be enhanced through workshops conducted by external consultants. In order to ensure proper
controls are applied over disbursements pertaining to the workshops, the workshop agendas, list
of participants, venues, costs, etc., will be reviewed by the TTL and given a No Objection prior
to taking place.
25. The following is an illustration of the flow of funds cycle:
11
On the SFD automated system, the related Journal Voucher is prepared by the Finance Officer, reviewed by the
Finance Manager and approved by the Internal Control Department Senior Manager and the Sector Director,
Finance and Operation.
32
26. SFD‟s Operations Manual was amended to capture the financial management
arrangements and disbursement requirements of the Project which were found acceptable to the
Bank. This entailed updating the SFD FM Manual to reflect activities under the envisaged
Project, and included new disbursement voucher forms as annexes to the existing FM manual.
The FM manual was reviewed by the Bank and found acceptable. The FM manual is now dated
March 15, 2012. As per the IAD strategy, all SFD Departments should notify the IAD of any
changes made to their respective policies and procedures prior to implementation to provide
opportunity for the IAD to review and advise on whether such changes might weaken the system
of internal controls.
Internal Audit Arrangements:
27. The SFD IAD. The SFD‟s IAD includes over 40 internal auditors at the HQ and
governorate levels or regional offices. The IAD, with its current capacity, is responsible for
conducting audit field work and related reporting for all SFD projects throughout Egypt.
IBRD
SFD HQ DA
Sponsoring Agencies (PIU or
NGOs)
Suppliers
Contractors
Service Providers/
Consultants
Delivery of Sub-projects and Services to Beneficiaries and
Responsible Authorities
33
28. The SFD IAD has established a risk based audit strategy which was reviewed, and found
acceptable, by the Bank. The audit strategy covers the IAD and the independent external auditor
involvement in evaluating the grant recipient and follow up on activities being implemented. It
was agreed with the Head of the IA that a capacity assessment of each PIU/NGO would be
carried out before signing the SA grant agreement by the IAD representative stationed in the
SFD regional office. Upon the IA clearance, the agreement will be signed accordingly and the
IAD will update its annual audit plan to include the approved PIU/NGO in their work program.
29. The IAD audit plan is prepared annually and revised on a quarterly basis. The planned
number of IAD visits and the associated scope of supervision is based on the results of the field
work of the Internal Auditor and the noted observations on the PIU/NGO performance. The IAD
plan establishes proper segregation of duties between the teams responsible for capacity
assessment of PIU/NGO and those responsible for follow up on implementation activities.
30. Following the transfer of the first tranche, the IA representative from HQ visits the PIU to
ensure that all of the financial arrangements stipulated in the SA grant agreement are followed.
Any noted observations are reported in the IAD report and followed up on by the IAD until
resolution. The final tranche is not transferred to the PIU until all IAD noted observations are
resolved.
31. The SFD IAD and the Project‟s External Auditor will be granted access to examine the
original supporting documentation. Meanwhile, the SA will send monthly reports to the SFD
regional office. As per the existing SFD IAD strategy and Program, the IAD will conduct regular
field visits by using the IAD‟s representatives stationed in the SFD‟s regional office throughout
the project life. The IAD staff will be responsible for documenting the outcome of the visits by
preparing and submitting to the Head of the Internal Audit a report documenting each visit. Also,
for NGOs, the two latest audited financial statements will be obtained to ensure that there is an
unqualified (clean) opinion on the NGO financial statements.
Transparency:
32. Allocation of funds under the umbrella of the Project was based on Egypt‟s geographical
poverty map which was prepared by the GoE and applied by the World Bank in the project
design in determining the targeted geographical areas. Signs and bulletin boards will be placed in
the field demonstrating that the Project is financed by the World Bank in collaboration with the
SFD.
33. Under the umbrella of the Project, a call for proposal will be announced in the local
newspaper and on the announcement board in the Governorates and the Intermediary Agencies.
The call for proposal will include the evaluation criteria, which address the eligibility of the
applicant, and the associated scoring sheet, which determines the ceiling of the granted funds.
Also, as is the common practice in all SFD projects, this information will be posted on the SFD
website (in Arabic).
34
34. The website provides comprehensive information about the SFD and its role, how to
obtain services under different programs offered by the SFD, and the SFD development partners.
HQ and RO contact information.
Complaints Handling and Grievances System:
35. At present, a limited grievance system is in place. The system is not web-based and does
not allow anonymous reporting of complaints. Rejected applicants can file a complaint with the
Head of the SFD regional office who investigates the complaint with the HCD representative in
the regional office. A formal justification for rejection must be provided and, if a resolution is
not reached. The matter is escalated to the SFD HQ. Alternatively, the complaint form can be
obtained from the SFD website.
36. The project design includes: (i) support for client satisfaction surveys, and (ii) a sub-
component which allow NGOs to conduct independent verification of sub-project
implementation. The Project aims to establish an effective web-based grievances system with
text messaging capability (SMS) to allow reporting of irregularities and complaints and
feedback.
External Audit Arrangements:
37. The SFD is subject to annual external audits by: (i) the Central Accountancy Office
(CAO) and (ii) independent external audit firms (currently KPMG). In addition, the SFD will
contract with an independent external auditor based on TORs acceptable to the Bank, for the
purpose of carrying out an external audit of the Project‟s Financial Statements. The SFD‟s
Entity and Project audit reports will be submitted to the Bank within six months from the end of
each calendar year.
38. The SFD will hire the Project‟s external auditor within three months after project
effectiveness. The Bank expects the Borrower to submit terms of reference for the project
external audit for the Bank‟s prior review and approval within 3 months of effectiveness. The
external auditor will conduct quarterly reviews on the project IFRs before submission to the
Bank.
39. The external audit report shall encompass all project activities and shall be in accordance
with internationally accepted auditing standards, e.g., International Standards on Auditing (ISA).
The annual audit report of the Project Accounts shall include a separate opinion as to whether the
IFRs submitted during such fiscal year, together with the procedures of internal controls involved
in their preparation, can be relied upon to support related Withdrawal Applications. Also, the
audit report shall include a separate opinion on the Fund Accountability Statement (i.e.,
Statement of Sources and Uses of Funds), Withdrawals from the World Bank Loan,
Disbursements Forecast and the DA Reconciliation Statement. In addition, the auditor will
provide a separate opinion on compliance with the Operations Manual and effectiveness of the
internal control system. In addition to the audit reports, the auditor will prepare a “management
letter” identifying any observations, comments and deficiencies in the system and controls that
the auditor considers pertinent and shall provide recommendations for their improvement. The
35
Project‟s external auditor TOR will be subject to the Bank‟s review, tailored to include the
auditing of sub-projects. The project auditor will use the SFD internal audit reports and other
external audit reports furnished to SFD to determine whether to use using the risk-based
approach as per SFD Audit Strategy. There are no overdue Audit Reports for projects previously
implemented (or currently implemented) by the SFD.
40. The table below summarizes the financial reporting arrangements required under the
Project.
Report Due Date Responsibility Sent
to:
Language Scope
Interim financial
Reports
45 days from end
of quarter
External Auditor Bank Arabic/English Review
Annual Project
financial
statements
6 months from end
of the fiscal year
External Auditor Bank Arabic/English Audit
Annual Entity
financial
Statements (SFD)
6 months from end
of the fiscal year
External Auditor Bank Arabic/English Audit
Supervision Plan:
41. After effectiveness, the Bank FMS will participate in Bank supervision missions. The
Bank supervision will follow a risk based approach. At least two supervision missions will be
carried out annually in addition to follow up visits as deemed necessary. The review and audit
reports of the interim and annual financial statements respectively, in addition to the
management letter, will be reviewed on a regular basis by the Bank FMS, and the results or any
issues which emerge will be pursued during supervision missions. Also, during the Bank's
supervision missions, the Project's financial management and disbursement arrangements will be
reviewed to ensure compliance with the Bank's requirements and to develop the financial
management rating for the Implementation Status Report (ISR).
Next actions:
Action Required By Whom When Status
Amend the existing automated
accounting system to record and report
on the new project activities
SFD IT
Department One month from
effectiveness
Pending
Amend the SFD Financial Manual to be
reflective of the envisaged project
financial activities and ensure consistent
implementation of control procedures.
SFD Finance
Department
March 15, 2012
Completed
Agree on the terms of reference for the
project‟s external auditor.
SFD Within 3 months
after effectiveness
Pending
36
Appendix 1
37
Appendix 2
38
Annex 6: Procurement Arrangements
ARAB REPUBLIC OF EGYPT
Emergency Labor Intensive Investment Project
General
1. The Country Procurement Assessment Report (CPAR) of 2003 concluded that Egypt‟s
Procurement Law (Law No. 89) and the Executive Statutes provide important concepts for public
procurement in Egypt and generally contain sound principles. However, the broad nature of their
principles and the absence of written guidelines for their application leave considerable room for
extensive discretionary power which can result in inconsistent decisions and loss of
transparency.
2. In addition, a follow-on sector specific assessment to the CPAR, an institutional procurement
capacity assessment in the water sector, was carried out in 2005 as part of the Public Expenditure
Review also issued at about the same time in early 2006. The assessment emphasized the
importance of developing the National Procurement Guidelines to avoid conflicting
interpretations of the above mentioned Law 89. The proposed guidelines should explain all steps
necessary for the efficient procurement of goods and works, as well as provide guidelines for the
selection of consultants (currently non-existent) based on qualitative criteria, as well as
guidelines on thresholds.
3. More recently, upon the request of the General Authority for Government Services, the Bank
has provided support through a legal Technical Assistance (TA) to modernize the Executive
Regulations in line with UNCITRAL Model Law to the extent that Law 89 allows. The revisions
are expected to be endorsed by the GoE shortly and rolled out nationally to all procuring
agencies in the country.
4. Procurement for the proposed Project will be carried out in accordance with the World
Bank‟s “Guidelines: Procurement under IBRD Loans and IDA Credits” dated January 2011;
“Guidelines: Selection and Employment of Consultants by World Bank Borrowers” dated
January 2011; the World Bank‟s Anti Corruption Guidelines (“Guidelines on Preventing and
Combating Corruption in Projects Financed by IBRD Loans and IDA Credits and Grants), and
the provisions stipulated in the Legal Agreement. The various items under different expenditure
categories are described in general below. For each contract to be financed by the Loan, the
different procurement methods or consultant selection methods, the need for pre-qualification,
estimated costs, prior review requirements, and time frame are agreed between the Borrower and
the Bank in the Procurement Plan. The Procurement Plan will be updated at least annually or as
required to reflect the actual project implementation needs and improvements in institutional
capacity.
5. Procurement of Works: Works procured under this Project will include: small value
contracts implemented by the SA, the beneficiary of SFD finance in the form of a Labor
Intensive (LI) Sponsoring Agency Grant Agreement. Civil works contracts will include canal
weed reduction and protection of river bank, rehabilitation of rural housing, upgrading of rural
roads, school rehabilitation, and solid waste collection. The maximum financing for a LI SA
39
Grant Agreement will be around US$2,000,000 and include small works in dispersed
communities, estimated to not exceed US$350,000. Large contracts will not arise at the SA/NGO
level due to the nature of the works involved and, therefore, ICB and NCB are not foreseen. Civil
works with an estimated contract value below US$500,000 would be awarded through local
shopping (small works procedures) as explained and agreed upon in the updated Operations
Manual. The Operations Manual will also include standard evaluation forms related to these
types of procurements.
6. Civil works with an estimated contract value more than US$500,000 will be procured at the
SFD central level through National Competitive Bidding (NCB) using the modified World Bank
standard bidding document in Arabic language which is currently being used by other World
Bank financed projects in the water sector in Egypt, with advertisement in two national
newspapers. NCB procedures shall comply with the requirements stipulated in the Financing
Agreement under Provisions for NCB.
7. Procurement of Goods: Goods procured under this Project will include: small value
contracts valued around US$100,000 or less implemented by the Sponsoring Agency SA/ NGOs,
the beneficiary of SFD finance in the form of a LI SA Grant Agreement. The procurement will
be done using the SFD updated procurement manual agreed upon with the Bank; this manual
includes in its annexes simplified local shopping procedures for contracts estimated less than
US$250,000 or equivalent. The manual also includes standard evaluation forms related to these
types of procurements.
8. Procurement of non-consulting services: Procurement of non consulting services under the
project may include printing services, translation services, transportation service, catering
services, hotel services, etc.
9. Selection of Consultants: All consulting service contracts under Component 2 for firms
would be procured at the SFD central level following the World Bank‟s procurement procedures
by using the Bank‟s Standard Request for Proposal (SRFP). Consulting services contracts would
mainly comprise hiring of an Independent Verification Expert, Evaluation, Communication,
Quality Assurance, Capacity Development, and Audits. Consulting service contracts above
US$500,000 will use QCBS and QBS.
10. Consulting service contracts below US$500,000 for selection of firms or NGOs may be
procured using selection based on Consultants‟ Qualification, Fixed Budget Selection, and Least
Cost Selection. Single Source Selection could be used in exceptional cases subject to approval by
the Bank. The SFD updated procurement manual will include annexes of standard simplified
RFP and contract forms as well as standard evaluation forms. Short lists of consultants for
services estimated to cost less than US$300,000 equivalent per contract may be composed
entirely of national consultants in accordance with the provisions of paragraph 2.7 of the
Consultant Guidelines. All individual consulting assignments will be selected on the basis of
comparison of qualifications in accordance with Section V of the Guidelines for Selection of
Consultants.
40
11. Capacity building activities to be financed by the Loan include workshops to train
beneficiaries on environmental and other aspects related to implementation of the LI sub-
projects. The procurement will be done in the form of a budget covering the expenses of the
workshops. This will include trainee travel expenses, their accommodation if necessary, rental
of space, consumables and remuneration for private facilitators.
Assessment of the Agency’s Capacity to Implement Procurement
12. The SFD has its main headquarters in Cairo, and is supported by 20 regional and 7 satellite
offices. The SFD Headquarters Office will be supported by a qualified procurement adviser who
has experience in World Bank procurement procedures. The regional and satellite offices are the
main point of contact between requesting agencies and the SFD: they provide advice to
communities, NGOs, and regional government on SFD procedures; receive completed
application forms; coordinate sub-project appraisal committees; and conduct field appraisals and
launch workshops through the SFD's Programs. The regional and satellite offices are linked to
the national offices through telephones, facsimiles, and internet connections.
13. The SFD is supported by the following units: (a) Management Information Systems (MIS);
(b) Credit Unit responsible for determining the credit worthiness of projects involving
intermediary agencies and/or beneficiaries for both the Community Development and Enterprise
Development Programs; (c) Projects and Planning Office (includes a monitoring targeting
evaluation and studies unit), with requisite skills to plan and review SFD activities, as well as
appraise and evaluate projects; (d) Legal mandated to prepare framework agreements and handle
related legal matters; (e) International Cooperation Affairs and Information for Public Relations
Department charged with managing and organizing marketing campaigns involving information
dissemination on the role of SFD as well as handling problems arising from poor
communication; and (f) IAD which reports directly to the Managing Director and the Board of
Directors. The SFD would have primary responsibility for monitoring physical and financial
progress of the works undertaken by the SA/NGO. The Governorate beneficiaries submit a
proposal outlining the works to be undertaken and to be considered for financing by the SFD.
The SFD reviews and approves the proposal for which an appraisal document is prepared
(detailing the scope of work, feasibility, sustainability, timetable, disbursement schedule, etc.).
Through the SFD's Programs, a Framework Agreement is signed with the SA/NGO which
describes the guidelines to be followed and each party‟s role in the implementation of the sub-
project. The SA/NGO then sub-contracts the work with a contractor and/or supplier. The SFD
will oversee and guide the SA/NGO based on the processes outlined in the SFD‟s updated
Program Operations Manual. The updated Operations Manual will form the cornerstone of the
Project launch workshop and subsequent activities. This Manual will provide consistent
procurement procedures for all project beneficiaries, and will be disseminated to all project
entities.
14. An updated assessment of the methodology and the applied procurement procedures of Egypt
SFD to implement and monitor procurement actions for the project were carried out by the Bank
following the simplified procedures, OP 8.00 Rapid Response for Crises, which is applicable to
this Project. The assessment reviewed the organizational structure, the applied procedures and
the matrix of responsibility for implementing the Project.
41
15. The key issues and risks concerning procurement for implementation of the Project have
been identified and include:
BD inconsistent with Bank‟s Guidelines.
Inconsistent application of rules and procedures by the different implementing
agencies;
Quality of selection process for NGOs yet to be improved.
Lack of standard BD, RFP, contract forms and evaluation forms;
Practice of pre/post award negotiations;
Unjustified re-bidding which may result in unnecessary delays in implementation;
Civil servants are paid out of the project proceeds.
A general practice across the country of negotiating prices with bidders or
accepting discount after bids opening.
16. The overall project risk for procurement is high.
17. The corrective measures which have been agreed are: (i) hiring of an experienced
procurement adviser for consulting services (disbursement condition); (ii) updating of the
procurement manual with complete annexes to ensure clear definitions of rules and
responsibilities and enable consistent application of these rules (completed March 2012); (iii)
reinforcement of the capacity of the regional offices by the procurement adviser to monitor
conform compliance to the application of procurement procedures by the SAs and IAs; and (v)
carrying out of appropriate capacity building for the procurement manual and annexes.
Prior Review:
18. For the first consulting services contracts related to the selection of NGOs per sector and all
consulting services contracts above US$200,000 under Component 1, and all consulting services
contracts under Component 2 and the first contract for works and goods regardless of their
values and their geographical location are subject to the Bank‟s prior review. The SFD regional
office would review the first three contracts for each governorate and issue a formal no-objection
letter to be documented for the Bank‟s post review. In addition, the SFD regional office would
randomly carry out post review for contracts implemented by all different IAs/NGOs on a
quarterly basis and send its findings and recommendations to the Bank. Rejection of all bids for
rebidding purposes is subject to the Bank‟s prior review.
42
Table 1
Procurement Plan
19. The Borrower, at appraisal, developed a procurement plan for project implementation which
provides the basis for the procurement methods. This plan was agreed upon between the
Borrower and the Project Team before negotiation. The Procurement Plan will be updated in
agreement with the Project Team annually or as required to reflect the actual project
implementation needs and improvements in institutional capacity.
20. The Programs of the SFD (CDP and PWP) being financed under the proposed Project have
no procurement unit. The Programs are responsible for preparing a Project Appraisal Document,
which is based on requests received from the Governorates/NGOs, and which outlines the scope
of works (the project and its subprojects), feasibility, sustainability terms and conditions
(criteria), project cost, disbursement schedule, and schedule of completion.
Frequency of Procurement Supervision
21. In addition to the prior review supervision to be carried out from the Bank office, the
capacity assessment of the IA has recommended two supervision missions to visit the field to
carry out post-review of procurement actions.
Prior Review
Thresholds
Proposed (USD
million)
Procurement Method Thresholds Proposed (USD million)
ICB NCB Shopping QCBS QBS CQS
Least
Cost SSS
Goods 0.1 ≥0.5 <0.25 <0.25
Works 0.35 ≥5 >0.5 <0. 5
Consulting
Services
Firms ≥ 0.2
Individual ≥ 0.1
default TBD <0.5 TBD TBD
Rebidding All
43
Annex 7: Implementation and Monitoring Arrangements
ARAB REPUBLIC OF EGYPT
Emergency Labor Intensive Investment Project
A. Project Implementation. The project implementation period is three years.
1. The Project will be implemented by the SFD. The SFD is a legally autonomous, permanent
and well established development organization with a long track record of providing support to
needy and underserved communities. The SFD has been implementing the public works program
for the last 20 years to provide immediate short-term employment opportunities.
2. The SFD has significant experience in interventions that provide services and employment to
the poor, and with an increasing focus on community participation, cooperation with NGOs, and
decentralization. Since 1992, about EGP 1.8 billion worth of projects have been implemented by
SFD in infrastructure under its HCD. Over the years, the most common sub-projects
implemented were water supply and sanitation projects, pavement of roads, cleaning of canals,
public buildings, and riverbank protection.
3. Project Oversight. The Board of Directors of the SFD, which is chaired by the Prime
Minister and includes the Ministers of Finance, Manpower and Migration, Information, Foreign
Trade and Industry, Transportation, the Chairman of the Public Authority for Investment and
Free Zones, SFD‟s Managing Director, and the Financial and Legal Advisor, is responsible for
project oversight. SFD‟s Managing Director will be responsible for general project coordination
and implementation and the General Manager of the Human and Community Development
Sector will be responsible for day-to-day project management responsibilities.
4. Project Management. The SFD will be the implementing agency for the proposed Project.
The SFD central office, based in Cairo with the support of its 27 regional offices (one in each
Governorate), will coordinate project activities with the various stakeholders.
5. SFD’s Roles and Responsibilities. Key SFD duties will include: (a) preparing the sub-
projects pipeline in accordance with guidelines and eligibility criteria defined in the Operations
Manual; (b) assessing the degree of labor intensity of the proposed sub-project, (c) assessing the
degree of community participation in identifying and executing sub-projects and the quality of
the skills upgrading activities proposed; (d) supervising the activities of the sponsoring agencies
and the intermediary agencies; (e) overseeing the procurement arrangements to ensure that
implementing partners are adhering to the agreed procedures; (f) ensuring that sponsoring
agencies are actually carrying out the capacity building activities for the implementing partners
(including training on sub-project implementation, contracting, operations and maintenance, and
financial management); (g) monitoring performance through the MIS and reporting quarterly on
progress; and (h) developing an impact evaluation process to provide information on project
outcomes.
44
Main Sub-project Partners
6. Line Ministries/Governorates and their technical directorates. Line Ministries are the
sectoral ministries at the national level that identify the types of technical subsectors to be funded
under this operation. Below the national level, the 27 governorates are the main focal points of
government development efforts. Associated with line ministries/governorates are technical
directorates (mudiriat) which represent line ministries within a particular governorate. Technical
directorates are responsible for the technical aspects of their sectors throughout the governorate.
Governorates and their technical directorates also assume the technical and financial
responsibility for operation and maintenance of most infrastructure investments.
7. NGOs/ Community Development Associations (CDAs). NGOs are registered large
experienced community development associations with a track record in implementing
community driven development projects. NGOs support the formation, capacity development,
and expansion of grass-roots CDAs at the village level. CDAs are groups of citizens from the
community with a common interest, who organize into legally constituted civil associations.
Both NGOs/CDAs will identify, prepare, implement, supervise, operate and maintain their sub-
projects, assisted both by technical specialists whom they contract directly and by technical
assistance and training made available through the Project.
B. Sub-project Cycle:
Priority setting for allocation of funds
8. Egypt poverty map information was used to prioritize allocation of funds for sub-projects
geographical areas.
Sub-project implementation
9. Community Infrastructure Sub-projects.
Identification of sub-projects
The sub-projects pipeline is identified by SFD regional offices in
collaboration with sectoral line ministries, technical directorates at the
governorate level, local authorities, and in consultation with the local
community.
Approvals by SFD
Once a group of sub-projects under a single framework agreement has been
identified, it is sent to the standing SFD appraisal committee at headquarters
for appraisal. Upon approval, the funds are allocated.
Signing of framework agreements (also known as Sponsoring Agencies
Grant Agreements)
A framework agreement is signed between SFD and the governorate or line
ministries (SA). Framework agreements define the scope of the sub-project,
45
preliminary sub-project list, and reporting requirements, in addition to the
roles and responsibilities of the technical directorates as IA (mudiriat). The
IA will represent line ministries within a particular governorate and will also
assume the technical and financial responsibility for operations and
maintenance of infrastructure investments.
Setting up a Project Implementation Unit (PIU) within the SA
Based on an assessment of the strengths of the SA, a PIU will be set up
within the SA. Personnel will include a full time project manager, an
accountant, and a procurement specialist.
Signing of sub-grant agreements between SA and IA (also known as
Intermediary Grant Agreements)
A sub-grant agreement is signed between the governorate/line ministries
(SA) and their technical directorates at the governorate level (mudiriat) (IA).
The sub-grant agreement defines the roles and responsibilities of the
technical directorates, contracting conditions, and procurement procedures.
Setting up required bank accounts
A bank account for the sub-project will be set up in the name of the
sponsoring agency, with signatory delegated to the PIU and other details
declared. Similarly, every intermediary agency (technical directorate) which
is expected to execute sub-projects will also set up bank accounts.
Preparing detailed designs and tender documents by IA
The IA is responsible for preparing the detailed designs, bills of quantities,
tender documents, and technical daily supervision.
Physical execution of sub-projects
Sub-projects will be implemented through contracting local private civil
works contractors in accordance with SFD‟s procurement manual and in
compliance with SFD‟s financial management manual.
Reporting on sub-project progress
Implementation progress of sub-projects is reported by the SA as per
reporting requirements defined in SFD‟s Operations Manual.
10. Community Subprojects.
Signing of Protocol with governorates
A memorandum of understanding (Protocol) is signed between SFD and the
governorates that will define the key sectors and activities to be funded. The
protocol will ensure the coordination between the governorate and the
NGOs/CDAs that will be selected for sub-project implementation.
Selection of NGOs/CDAs
46
NGOs/CDAs will be selected based on the qualifications of the organization,
past experience, and implementation and fund management capacity. A long
list of NGOs/CDAs will be identified per sector for each governorate. The
SFD has already a long list of qualified NGOs/CDA, which will be updated
during project implementation.
Identification of sub-projects
Qualified NGOs/CDAs per sector per geographic area will develop the
subprojects pipeline in partnership with SFD regional offices and in
collaboration and consultation with the local authorities.
Approvals by SFD
Grant agreements for sub-projects are identified and sent to the standing SFD
appraisal committee at headquarters for appraisal. Upon approval, the funds
are allocated to the NGO/CDA.
Signing of grant agreements for sub-project implementation (also known as
Sponsoring Agencies Grant Agreements)
An agreement is signed between SFD and the implementing NGO/CDA that
will define the scope of the sub-project, the roles and responsibilities of
NGO/CDA where applicable, reporting requirements, contracting conditions,
and procurement procedures.
Setting up a Project Implementation Unit (PIU) within the NGO/CDA
Based on an assessment of the strengths of the NGO/CDA, a PIU will be set
up within the SA. Personnel needed for the PIU will include a full time
project manager, an accountant, and a procurement specialist.
Setting up required bank accounts for the grant agreement
A bank account for the sub-project will be set up in the name of the
NGO/CDA, with signatory delegated to the PIU and other details declared.
Physical execution of sub-projects
Sub-projects will be implemented by the NGO/CDA through contracting
suppliers and consultants in accordance with SFD‟s procurement manual and
in compliance with SFD‟s financial management manual.
Reporting on sub-project progress
Implementation progress of the sub-projects is reported by the NGO/CDA as
per reporting requirements defined in SFD‟s Operations Manual.
The project will be managed in accordance with SFD’s Operations Manual which at all times
will need to be acceptable to the Bank.
47
Monitoring & Evaluation
11. Monitoring. The SFD will monitor the progress of the implementation of sub-projects using
its MIS which has been adapted to ensure that it will be able to respond to the reporting
requirements of the Bank and the Results Framework of the Project.
12. Reporting. The SFD will submit to the Bank semi-annual progress reports that provide
updates on the status of the project outcome, intermediate outcome, and output indicators. In
addition, the SFD will submit to the Bank a Mid Term Review Report and a Project Completion
Report.
13. Verification. The SFD, using the expertise of an IVE, will conduct community level
verification of the results of implementation of sub-projects, using NGOs to ensure social
accountability.
14. Evaluation. The SFD will conduct two evaluations, one at mid-term and another at the end
of the Project, using independent consultants who will provide inputs to the SFD Mid Term
Review and Completion Reports. Also, the SFD will plan to conduct an impact evaluation for
the project.
15. Quality Assurance. The SFD, through use of quality assurance firms or regional
universities, will conduct quality assurance activities that assess the technical quality of assets
maintained under the community infrastructure sub-projects as well as measuring the rate of
client satisfaction with the community social services sub-projects.
48
Project Cost Table
ACTIVITY
Total
US$ M
Implementation
Component 1 US$198.00 million
1 Rehabilitation of 7,500 poorest household units (45 sq m rural house) 47.50
2 Canal weed reduction (10,200 km < 2m width) 30.00
3 River Nile Bank Protection for 47km 22.00
4 Maintenance and pavement of Rural Roads between villages (6m width) 11.00
5 Rehabilitation of 16,000 classrooms in 710 Schools 35.00
6 Rehabilitation of 1,000 KG classrooms in 500 KGs 2.50
7 Employment Intensive Population Services 19.50
8 Community Solid Waste Collection 13.00
9 Youth Employment in rural areas 4.50
10 Youth Employment in urban areas 12.00
11 Technical Verification using Independent NGOs 1.00
Component 2 US$2.00 million
1 Communication and public information 0.50
2 Mid-Term Review and End of Project Evaluations 0.25
3 Financial audit of the project 0.15
4 Quality assurance & Independent Verification 0.50
5 Project Management operating cost, equipment, software, and supplies. 0.25
6 Individual consulting services 0.35
TOTAL 200.00
49
Project Pipeline
Project Type Geographic
Location
Project
Cost
(USD)
Million
Project
Cost (LE)
Million
Direct
Jobs
Direct Jobs for
Youth
Direct Jobs for
Females
Total No.
Man/Day
Total
Wages
(LE)
Million
Labor
Intensit
y %
Output
Unit
Total
Outpu
ts
Responsible
Agency
No. No. % No. %
1
Rehabilitation of 7,500
poorest household
units (45 sq m rural
house)
Poorest villages in
6 governorates
Ministry of
Housing 47.5 285.0 8,159 4,079 50.0% 0 0.0% 815,851
110.00 38.6% House 7591
2
Canal Weed Reduction
(10,200 km less than
2m width for 3 years)
Nationwide Ministry of
Irrigation 30.0 180.0 31,500 15,750 50.0% 0 0.0% 3,150,000
126.00 70.0% KM 10200
3 River Nile Bank
Protection for 47km Upper Egypt
Ministry of
Irrigation 22.0 131.9 13,464 6,732 50.0% 0 0.0% 1,346,400
62.83 47.6% KM 47
4 Rural Roads between
villages (6m width) 13 governorates
Local
Government 11.0 66.0 3,950 1,975 50.0% 0 0.0% 395,000
16.43 24.9% KM 100
5
Rehabilitation of
16,000 classrooms in
710 Schools
11 governorates Ministry of
Education 35.0 210.0 14,400 7,200 50.0% 0 0.0% 1,440,000
77.76 37.0%
Classro
om 16000
6
Rehabilitation of 1,000
KG classrooms in 250
KGs
11 governorates NGOs 1.3 7.8 530 265 50.0% 0 0.0% 53,000
2.86 36.7%
Classro
om 1000
7
Early Child Education
of 1,000 KG
classrooms in 250 KGs
11 governorates NGOs 1.2 7.2 4,000 2,400 60.0% 4,000 100.0
% 400,000
6.20 86.1%
Classro
om 1000
8 Employment Intensive
Population Services 16 governorates NGOs 19.5 117.0 47,736 28,642 60.0% 47,736
100.0
% 4,773,600
97.30 83.2% NGO 117
9 Solid Waste Collection 16 governorates NGOs 13.0 78.0 34,632 20,779 60.0% 0 0.0% 3,463,200
62.90 80.6% NGO 78
1
0
Youth Employment in
rural areas 15 governorates NGOs 4.5 27.0 10,287 10,287 100.0% 514 5.0% 1,028,700
19.50 72.2% NGO 27
1
1
Youth Emplyment in
urban areas
Urban
governorates NGOs 12.0 72.0 22,000 22,000 100.0% 1,100 5.0% 2,200,000
50.40 70.0% NGO 60
1
2
Technical Verification
using Independent
NGOs
All project
governorates NGOs 1.0 6.0 2,000 1,000 50.0% 100 5.0% 200,000
4.20 70.0% NGO 27
TOTAL
198
1,188
192,658
121,109 62.9%
53,450 27.7%
19,265,751
636.38 53.6%
50
Annex 8: Project Preparation and Appraisal Team Members
ARAB REPUBLIC OF EGYPT
Emergency Labor Intensive Investment Project
Name Title Unit
Alaa Mahmoud Hamed Abdel Hamid Sr. Health Specialist/Task Team Leader MNSHH
Hany Al-Saadni Sr. Water Resources Specialist MNSWA
Mahmoud Gamal El-Din Sr. Operations Officer MNSHE
Nehad Kamel Infrastructure Specialist MNSHD
Marc Van Imshoot Sr. Infrastructure Specialist ILO
Amal Mwafy Sr. Program Officer ILO
Dorothia Schmidt Sr. Employment Specialist ILO
Akram El-Shorbagi Sr. Financial Management Specialist MNAFM
Jamal Abdulla Abdulaziz Sr. Procurement Specialist MNAPR
Alaa Ahmed Sarhan Sr. Environmental Specialist MNSEN
Rebekka Grun Sr. Economist MNSSP
Wael Ahmed Elshabrawy Financial Management Analyst MNAFM
Adrien Andre Pinelli Operations Officer MNCO3
Mira Hong Operations Officer MNSSP
Amy Champion Operations Analyst MNSHH
Virginia Jackson Operations Advisor SASHD
Claudine Kader Senior Program Assistant MNSHD
Brigitte Franklin Program Assistant MNSHD
Emma Paulette Etori Program Assistant MNSHD
Mariam William Guirguis Team Assistant MNCO3
Raghada Abdel Hamid Team Assistant MNCO3
51
Annex 9: Environmental and Social Safeguards Framework
ARAB REPUBLIC OF EGYPT
Emergency Labor Intensive Investment Project
ENVIRONMENTAL AND SOCIAL SCREENING AND ASSESSMENT FRAMEWORK (ESSAF)
I. OBJECTIVES
1. The main objective of the Environmental and Social Screening and Assessment
Framework (ESSAF) is to provide general policies, guidelines, and procedures to be integrated
into the implementation of the World Bank-supported ELIIP which will be implemented by the
SFD. This Framework has been developed to identify the environmental requirements needed to
ensure that all sub-projects are in compliance with the national environmental protection laws,
regulations and guidelines in Egypt, and the World Bank‟s safeguards policies more specifically.
Furthermore, the ESSAF will provide clear guidance which will ascertain that all environmental
and social impacts are being addressed effectively for the successful appraisal, design, and
implementation of the sub-projects. More specifically, the ESSAF will:
a. Provide a standardized safeguard screening and assessment process that enables the SFD
to quickly and effectively assess the likely environmental impacts associated with any of
the sub-projects.
b. Provide some examples of the necessary mitigation measures (in line with best practices)
to counter such impacts.
c. Include the monitoring and evaluation indicators that are necessary for implementing the
ESSAF.
d. Provide guidance on the approach to be taken during consultation and disclosure
requirements.
II. GENERAL PRINCIPLES
2. While ensuring due diligence in managing potential environmental and social risks, one
has to recognize the emergency nature of the proposed Project which aims to provide assistance
towards creating or maintaining infrastructure using labor-intensive techniques. Given that, the
ESSAF is based on the following principles:
The proposed operation will support multiple sub-projects, the detailed designs of which
were not necessarily known at appraisal. To ensure effective application of the World
Bank‟s safeguard policies, the ESSAF provides guidance on the approach to be taken
during implementation for the selection and design of sub-projects and the planning of
mitigation measures;
The proposed Project supports only environmental category “B” or “C” sub-projects as
per the World Bank classification for safeguards;
52
No sub-projects will be eligible for funding that trigger OP 4.12. In particular, all works,
even if there are design changes, will be done on public land and will not result in
relocation or loss of shelter, loss of assets or access to assets, or loss of income sources or
means of livelihoods; and
No sub-projects that involve the use or pollution of international waterways will be
financed under this Project;
Sub-projects entailing weeding activities shall be manual weeding (i.e., by hand) and will
not involve the use of pesticides. As a result, the World Bank OP 4.09 is not triggered;
and
Consultation and disclosure requirements will be simplified to meet the special needs of
these operations. This ESSAF will be shared with and disclosed in the SFD and relevant
governorates in Egypt as well as in the World Bank InfoShop.
III. PROJECT DESCRIPTION
3. The objectives of the Project are: (i) to create short-term employment opportunities for
unemployed unskilled and semi-skilled workers; and (ii) to provide access to basic infrastructure
services to the target population in poor areas in the Borrower‟s territory. The Project comprises
the following components:
Component 1: Employment-Intensive Sub-projects (US$198 million)
This component will include provision of grants to sponsoring agencies to carry out, by
governorate and local authorities, sub-projects consisting of small-scale infrastructure public
works including, but not limited to, the following activities: canal cleaning and protection,
rehabilitation of schools, housing, and rural roads.
This component will also include provision of grants to NGOs to carry out, by communities, sub-
projects consisting of community services including, but not limited to, solid waste collection,
early childhood education services, outreach for maternal and child health, nutrition, population
services and youth employment in rural and urban settings.
Component 2: Implementation Support (US$2 million)
This component will include provision of project implementation support, including project
management, audits, public information and communication, technical verification and quality
assurance, monitoring and evaluation, and social accountability.
IV. POTENTIAL ENVIRONMENTAL IMPACTS
4. The sub-projects of the proposed Project are likely to result in a number of positive
environmental and socio-economic impacts. That is, all of the sub-projects are expected to
generate employment opportunities and improve income generation for many individuals as well
as improve the living conditions and livelihoods, especially for those representing the low- or
poorest segments of society in targeted areas and communities. For example, the improvement
53
of housing conditions and solid waste collection for the poor will lead to positive health and
environmental impacts.
5. However, despite the substantial positive environmental impacts that will result from the
implementation of the sub-projects, there may still be some negative environmental impacts,
though potentially minor and not significant.
V. APPLICABLE WORLD BANK SAFEGUARD POLICIES
6. This ESSAF has been developed specifically to ensure environmental and social due
diligence for all the sub-projects funded by this Project. It is intended to ensure that, for all
activities financed by the Project, all efforts are made to avoid and minimize environmental and
social impacts; and where they cannot be avoided, that these impacts are identified and the
necessary mitigation measures are developed and implemented following the relevant Egyptian
laws as well as the World Bank policies.
7. In addition, this Framework is to assist the SFD in screening all the sub-projects for their
likely environmental impacts, identifying documentation and preparation requirements.
8. World Bank BP/OP 4.01 Environmental Assessment. Most of the proposed sub-
projects are likely to focus on canal weed reduction and protection of river banks, rehabilitation
of rural housing, maintenance of rural roads, school rehabilitation, and solid waste collection.
Given the nature of the proposed sub-projects, this policy will be triggered. Individual sub-
projects will be screened and assigned the appropriate environmental categorization and
environmental due diligence will be conducted in accordance with OP 4.01.
9. Considering the nature and magnitude of potential environmental impacts from the
relatively limited scale and magnitude of reconstruction works, sub-projects classified as “B” or
“C” will be financed by the Project. Any sub-projects classified as category “A” will not be
eligible for funding under this operation.
VI. Approach to Address Environmental Safeguard Issues
10. In accordance with World Bank policy OP/BP 8.00, the ESSAF will guide the
environment social safeguard planning and compliance during implementation of sub-projects.
As sub-projects will be identified and proposed for financing in a continuous manner during the
project implementation period, screening for potential environmental and social impacts will be
conducted and mitigation and management measures will be developed in line with the agreed
ESSAF.
11. Environmental and social impact screening, mitigation and management measures
development and implementation will be carried out as per the following:
First: Screening for potential environmental and social safeguard impacts and determination
of safeguards Category according to Egyptian laws and regulations, and World Bank
policies;
Second: Review of safeguards screening by World Bank;
54
Third: Preparation of safeguards documents, consultation and disclosure;
Fourth: Review and clearance of the safeguard documents within the Government or/and by the
Bank; and
Fifth: Implementation of agreed actions; and supervision, monitoring, and evaluation
A. Screening for Potential Environmental and Social Safeguard Impacts and
Determination of Safeguards Category for Each Sub-project
12. Once sub-projects have been identified, the environmental safeguard specialists at SFD
will concurrently screen each sub-project to determine the applicable Egyptian laws and
regulations, the World Bank safeguards policies and guidelines and the corresponding safeguard
instruments (i.e., EIA, EMP) which need to be prepared and implemented. Annex 1 provides a
proposed checklist of the likely environmental impacts to be filled out for each sub-project or
group of sub-projects.
13. The results of the screening exercise will determine the categorization for each sub-
project.
Environmental Safeguards Screening
14. With respect to environmental screening of sub-projects, the Egyptian national
regulations and World Bank policies and guidelines are considered on the whole to be closely
related; both are impact-based and will require the SFD to identify and assess potential impacts
to environmental components such as water, air, land and natural habitats and biodiversity.
15. For specific screening according to World Bank policies, the SFD will use the screening
tool in Annex 1 to propose an environmental classification for each sub-project as follows:
Category B: A proposed sub-project may have some adverse environmental impacts, but
less adverse than those of Category A projects. These impacts are typically site-specific;
few if any of them are irreversible; and in most cases, mitigation measures can be readily
designed. The great majority of sub-projects for rehabilitation and reconstruction works
are likely to fall into this category.
Category C: A proposed sub-project is likely to have minimal or no adverse
environmental impacts.
Determination of Environmental Safeguards Documents for Sub-projects
16. The environmental safeguards documentation requirements for each sub-project will be
determined based on the screening procedures, as follows:
Category B: Sub-projects will require an EIA or simplified EIA (as required under the
Egyptian laws and regulations) and or an EMP (as per the World Bank policy) consisting,
at a minimum, of standard environmental codes of practices supplemented, if necessary,
with additional analysis. The sub-project specific EMP and/or standard environmental
55
codes of practices, including chance-finds of physical cultural resources, will be included
in all construction contracts/bidding documents.
Category C: Sub-projects that are rated Category C do not require environmental
safeguards documents, but will comply with the Egyptian regulatory requirements.
B. Review of Safeguards Screening by the World Bank
17. The SFD will prepare a safeguards screening summary for each sub-project in a format
specified in the Operations Manual. This will summarize: (a) the recommended categorization
according to World Bank policies; and (b) the proposed environmental safeguards
documentation requirements for the sub-project. The safeguards screening summary will be part
of the sub-project identification package that will be submitted to the Bank by the SFD.
18. The World Bank will review the screening of sub-projects on a selective basis to verify
that the screening tools and choice of documents are being applied appropriately and
consistently.
C. Preparation of Safeguards Documents, Consultation and Disclosure
19. This ESSAF will be shared with the SFD and will be disclosed in-country in both Arabic
and English by them in Egypt. The ESSAF will also be shared with the relevant ministries and
governorates (i.e., local authorities) that are implementing the sub-projects. Disclosure will also
be carried out through the World Bank‟s InfoShop. The other relevant specific safeguard
documents/mitigation plans prepared for the sub-projects will also be subsequently disclosed.
20. For Category B12
sub-projects, the SFD will consult the stakeholders and/or the project-
affected groups and local non-governmental organizations on the project's environmental and
social aspects, and will take their views into account. The SFD will initiate these consultations
as early as possible, and for meaningful consultations, will provide relevant material in a timely
manner prior to consultation, in Arabic and in a form that is comprehensible and accessible to the
groups being consulted.
21. Once the screening and documentation requirements are agreed by the Bank and
confirmed by the SFD, the SFD will develop the relevant safeguard documents and impact
mitigation measures.
22. The SFD are encouraged to liaise closely with the Bank if any issues arise that may
require clarification from the Bank on the application of World Bank policies.
23. Safeguards documents will be subject to consultation and disclosure in an accessible
place, in a timely manner, and in a form and language understandable to key stakeholders, prior
to the finalization of the said documents. Particular attention will be given to ensure that the
project stakeholders receive adequate time and ready access to draft documents before
consultation is carried out. This is essentially to ensure that the project stakeholders participate
12
As defined in World Bank Operational Policy 4.01, Environmental Assessment.
56
in and contribute to the sub-project planning and implementation, and thereby help minimize any
sub-project impacts while maximizing the benefits.
D. Review and Clearance of Safeguards Documents
24. Review and clearance of the environmental and social safeguards documents according to
national regulations is the responsibility of the SFD.
25. The requirements for review and clearance of the environmental documents by the World
Bank are as follows:
Category B: The Simplified EA (or EIA) and EMP for Category B sub-projects will not
be subject to World Bank review and clearance prior to approval of the sub-project.
However, these documents will be post-reviewed on a selective basis during supervision
missions.
Category C: No review required by the World Bank.
E. Implementation of Agreed Actions and Supervision, Monitoring and Evaluation
Implementation
26. Implementation of the safeguards measures during sub-project implementation is the
responsibility of sub-project field office staff.
Supervision
27. The SFD will supervise the implementation of the EMP. The World Bank task team will
regularly visit the sub-project areas throughout project implementation in order to:
Provide guidance and assist in the preparation of safeguards instruments;
Review the screening results, due diligence review report, and safeguard documents of
proposed sub-projects;
Supervise the implementation of the safeguards instruments to ensure they are
implemented in compliance with the Bank policy requirements.
Monitoring and Evaluation
28. The SFD will engage qualified and experienced consultants to carry out the monitoring
program to provide information on key environmental and social aspects of the sub-projects and
the effectiveness of the planned mitigation measures. This will enable the Government and the
Bank to evaluate the performance of the environmental program and allow corrective action to
be taken as needed. Annex 2 provides a checklist for environmental monitoring indicators for
typical sub-projects.
57
VII. RESPONSIBILITIES FOR SAFEGUARDS SCREENING AND MITIGATION
29. In the environmental and social mitigation planning process described above, the various
institutional roles and responsibilities are:
Environmental and social impact screening: the SFD, through its specialized staff comprising
the 32 Environmental Focal Points from regional offices and headquarters and/or qualified
consultants, will undertake environmental screening of each proposed sub-project, the findings
of which will be post-reviewed by the World Bank on a sample basis. The Environmental Focal
Points will also undertake social safeguards training.
Preparation of safeguards documents: individual sub-project proponents are responsible for
planning, design and implementation of individual sub-projects, including environmental and
social safeguard documents and mitigation measures, and will engage qualified consultants as
needed.
Supervision: the SFD with the assistance of its specialized staff comprising the 32
Environmental Focal Points and/or qualified consultants will guide, supervise and manage the
process of safeguard planning and implementation work.
Overall responsibility: the SFD will assume the overall responsibility for the planning and
implementation of safeguards documents under the Project. The World Bank will support the
process through periodic supervision and training.
Review and clearance of the safeguard documents: safeguards documents will be reviewed and
cleared as per the provisions of the Law No. 4 for 1994 and its Executive Regulations and also
its amendment, Law No. 9 for 2009.
World Bank review and clearance of the safeguards documents: the World Bank will carry out
sample post-reviews during supervision missions.
Safeguards documents implementation: the sub-project proponents will be responsible for the
implementation of the safeguard documents, under the direction and supervision of the SFD.
Supervision, monitoring and evaluation: the SFD through its environmental focal points and/or
qualified consultants will assume the overall responsibility for the supervision, monitoring, and
evaluation of the safeguard document implementation.
Environmental Safeguards Guidelines: For all sub-projects that are determined to be “Category
B” sub-projects according to the terms of the ESSAF, the SFD will develop Environmental
Safeguards Guidelines which will guide the specific regional office in the implementation of the
ESSAF. No “Category B” sub-projects should be carried out before such Environmental
Safeguards Guidelines are prepared. Category B sub-projects will be selectively post-reviewed.
In addition, the Bank will review the Environmental Safeguard Guidelines to ensure consistency
with the ESSAF.
58
VIII. CAPACITY-BUILDING AND MONITORING OF SAFEGUARDS FRAMEWORK
IMPLEMENTATION
30. As part of the capacity-building to be provided for implementation of the proposed
operation, the Environmental/Safeguards Focal Points at the SFD as well as the relevant staff of
the concerned governorates, NGOs, and other project stakeholders, will also receive training in
ESSAF‟s application.
59
Appendix 1
CHECKLIST OF LIKELY ENVIRONMENTAL AND SOCIAL IMPACTS OF SUB-PROJECTS
This Form is to be used by the Safeguards Focal Point at the SFD in screening Sub-project
Applications.
Note: One copy of this form and accompanying documentation to be kept in the SFD and one
copy to be sent to the task team leader of the World Bank.
Name of Sub-project:
Number of Sub-project:
Proposing Agency:
Sub-project Location:
Sub-project Objective:
Infrastructure to be rehabilitated:
Estimated Cost:
Proposed Date of Commencement of Work:
Technical Drawing/Specifications Reviewed (circle answer): Yes __ No __
No ISSUES
Yes
No
A.
Zoning and Land Use Planning
1. Will the sub-project affect land use zoning and planning or
conflict with prevalent land use patterns?
2. Will the sub-project involve significant land disturbance or site
clearance?
3. Will the sub-project land be subject to potential encroachment
by urban or industrial use or located in an area intended for
urban or industrial development?
B. Utilities and Facilities
4. Will the sub-project require the setting up of ancillary
production facilities?
5. Will the sub-project make significant demands on utilities and
services?
6. Will the sub-project require significant levels of accommodation
or service amenities to support the workforce during
construction (e.g., contractor will need more than 20 workers)?
60
C Water and Soil Contamination
7. Will the sub-project require large amounts of raw materials or
construction materials?
8. Will the sub-project generate large amounts of residual waste,
construction material waste or cause soil erosion?
9. Will the sub-project result in potential soil or water
contamination (e.g., from oil, grease and fuel from equipment
yards)?
10. Will the sub-project lead to contamination of ground and surface
waters by herbicides for vegetation control and chemicals (e.g.,
calcium chloride) for dust control?
11. Will the sub-project lead to an increase in suspended sediments
in streams affected by road cut erosion, decline in water quality
and increased sedimentation downstream?
12. Will the sub-project involve the use of chemicals or solvents?
13. Will the sub-project lead to the destruction of vegetation and
soil in the right-of-way, borrow pits, waste dumps, and
equipment yards?
14. Will the sub-project lead to the creation of stagnant water bodies
in borrow pits, quarries, etc., encouraging for mosquito breeding
and other disease vectors?
D.
Noise and Air Pollution Hazardous Substances
15. Will the sub-project increase the levels of harmful air
emissions?
16. Will the sub-project increase ambient noise levels?
17. Will the sub-project involve the storage, handling or transport of
hazardous substances?
E.
Fauna and Flora
18. Will the sub-project involve the disturbance or modification of
existing drainage channels (rivers, canals) or surface water
bodies (wetlands, marshes)?
19. Will the sub-project lead to the destruction or damage of
terrestrial or aquatic ecosystems or endangered species directly
or by induced development?
20. Will the sub-project lead to the disruption/destruction of wildlife
through interruption of migratory routes, disturbance of wildlife
habitats, and noise-related problems?
F.
Destruction/Disruption of Land and Vegetation
21. Will the sub-project lead to unplanned use of the infrastructure
being developed?
22. Will the sub-project lead to long-term or semi-permanent
destruction of soils in cleared areas not suited for agriculture?
23. Will the sub-project lead to the interruption of subsoil and
overland drainage patterns (in areas of cuts and fills)?
24. Will the sub-project lead to landslides, slumps, slips and other
mass movements in road cuts?
25. Will the sub-project lead to erosion of lands below the roadbed
receiving concentrated outflow carried by covered or open
drains?
26. Will the sub-project lead to long-term or semi-permanent
destruction of soils in cleared areas not suited for agriculture?
61
27. Will the sub-project lead to health hazards and interference of
plant growth adjacent to roads by dust raised and blown by
vehicles?
G.
International Waterways Issues
28 Does the sub-project use or otherwise affect an international or
trans-boundary waterway?
H.
Land Acquisition and Resettlement
29 Does the sub-project require land acquisition?
30 If so, will this land acquisition be involuntary?
31 If so, will this involuntary land acquisition lead to relocation or
loss of shelter?
32 If so, will this involuntary land acquisition lead to loss of assets
or access to assets?
If so, will this involuntary land acquisition lead to loss of
income sources or means of livelihood (whether or not the
affected persons must move to another location)?
33 Will the sub-project lead to the involuntary restriction of access
to legally designated parks and protected areas resulting in
adverse impacts on the livelihoods of the displaced persons?
Screening Tool Completed and Reviewed by:
Signed by Environmental Specialist in PMO:
Name: ______________________________________
Title and Date: ______________________________________
62
Appendix 2
CHECKLIST FOR ENVIRONMENTAL MONITORING INDICATORS FOR TYPICAL SUB-PROJECTS
School Sub-project:
Environmental Impact Monitoring Indicator Monitoring
Frequency
Air Pollution Noise
Odors
Dust
Smoke
Pollutants (i.e.CO, NOx. And SO2)
Asbestos
Paint containing lead
Annually
Water Pollution Electrical Conductivity
BOD – COD
E-Coli
Nitrates
Annually
Soil Pollution Oil
Wastewater
Solid Waste
Annually
Road Sub-project:
Environmental Impact Monitoring Indicator Monitoring Frequency
Air Pollution Increase in traffic
Noise
Odors
Dust
Smoke
Pollutants (i.e.CO, NOx. And SO2)
Asbestos
Paint containing lead
VOC
Annually
Different Forms of Visual
Pollution
Solid Waste
Construction Waste
Green Areas
Sewage System
Archeological Sites / Artifacts
Annually
Water Pollution EC
BOD-COD
E-Coli
Nitrates
Annually
Reduction or Migration of
Water Sources
Productivity of water source
Annually
Obstruction of Water
Collection
Obstruction of canals on the road
Dispersion of natural canals
Road erosion
Annually
63
Landslide, Erosion, and
Structural Instability of
Slopes
Falling rocks, soil, and debris on the road
Change in road width Annually
Population Emigration Census Annually
Tourism Support Determination of incoming tourists Semi-Annually
64
Appendix 3: Examples of Negative Environmental Impacts that may be associated with Sub-projects13
13
The table provides a summary of some of the negative environmental impacts that may be associated with the sub-projects different components though it is not intended to
provide an exhaustive list of all types of the sub-projects, their impacts, and their mitigation measures that shall be funded by the Project, rather, the table highlights the typical
impacts that can be expected in the types of sub-projects that shall be financed by the Project.
Sub-project Type
Potential Environmental and
Social Negative Impacts
During Project Construction
Best Management Practices and
Mitigation Measures
Potential Environmental and
Social Negative Impacts
During Project Operation
Best Management Practices and
Mitigation Measures
Water Supply and
Networks
Road, and
Irrigation Canals
Mismanagement of
construction and demolition /
rehabilitation waste
Disruption to biodiversity
(changes to fauna, flora, and
aquatic life)
Cut down of trees or
destruction of green areas
Increased air pollutant
emissions
Foul odors
Effluents to public water
systems
Alteration of current alignment
of streams
Obstruction of irrigation
intakes
Obstruction of flood water
course
Alteration of surface water
quality or quantity
Interference with existing
drainage networks
Alteration of direction / quality
of groundwater
Changes in soil (erosion /
fertility / salinity / pollution)
Gas emissions
Dust pollution
Change in local climate
Accidents may occur leading
to fire or personal injury
Monitoring of water
Regional water use plans
Proper drainage near wells and
pumping stations
Erosion control during
construction
Construction during dry season
Include odor-control technology
in design
Provide appropriate sized bins to
collect construction waste and
arrange for periodic pick up and
disposal
Restrict activities to areas where
biodiversity is not adversely
affected
Avoid cutting trees and
destruction of green areas, and if
necessary, re-vegetation should
be arranged and included in the
project
Control construction by fencing
site and spraying water over
working area to control dust
emissions
Consider project siting during the
design phase
Collect liquid effluents during
construction and avoid disposal
of untreated effluents into public
water systems
Careful design and appropriate
Disruption to biodiversity
(changes to fauna, flora,
and aquatic life)
Increased air pollutant
emissions
Foul odors
Changes in soil (erosion /
fertility / salinity / pollution)
Gas emissions
Change in local climate
Accidents may occur
leading to fire or personal
injury
Quality; operation, and
maintenance plan
Avoid harmful effects to
biodiversity during operation
Monitoring of water
Regional water use plans
Erosion control during
operation
Include odor-control technology
in operation
Use protective clothing and
masks for workers as
appropriate.
Train workers on health care
waste segregation and
occupational safety measures
65
selection of irrigation systems
Use protective clothing and
masks for workers as
appropriate.
Train workers on health care
waste segregation and
occupational safety measures
Waste
Management
None perceived
None
The garbage streams contain
all types of household and
other wastes, some of which
are hazardous.
Collection vehicles are not
covered during transport
leads to littering.
Collection workers usually
have no special training or
protection for handling these
wastes
Human scavengers at
dumping area may be
sorting through the waste.
Waste accumulating in
dumping areas may burn
spontaneously or by
individuals resulting in air
quality degradation from
smoke and dust.
Contamination of ground
water resources is of
concern at dumping areas.
Avoiding contamination of
close by water bodies through
random waste dumping.
Sound selection and siting of
dumping areas, studies are
crucial for this type of project
Train workers on waste
management and occupational
safety measures
Use protective clothing and
masks for workers as
appropriate
Vehicles must be covered
during transport.
Waste generated should be
collected frequently and storage
prohibited in streets.
Waste accumulated in dumping
areas should be covered to
avoid scavenging and
spontaneous burning
Health Care
Related
Mismanagement of demolition
/ rehabilitation waste
Disruption to biodiversity
(changes to fauna, flora, and
aquatic life)
Cut down of trees or
destruction of green areas
Changes in soil (erosion /
Adequate sanitation and disposal
system for waste
Avoid cutting trees and
destruction of green areas, and if
necessary, re-vegetation should
be arranged and included in the
project
Restrict noisy activities to certain
Indoor air pollution
Infectious waste may be
disposed of in mixed form
with municipal waste
Incinerators, if used, may
not be properly sited,
operated or maintained
leading to air pollution and
Control sources of indoor
pollution at source.
Provide for appropriate in door
ventilation either naturally by
using larger windows or
mechanically by using air
circulation fans and vents
Use different bags for
66
fertility / salinity / pollution)
Dust pollution
Accidents may occur leading
to fire or personal injury
Transportation and traffic
circulation
Increase traffic hazards to
motorists and pedestrians
Introduction of new diseases
Excessive exposure to existing
diseases
Attraction of pests and rodents
Generation of excess solid
wastes and litter
Transport, storage or disposal
of regulated hazardous wastes
Reduced aesthetic values /
visual pollution
Risk of impact on historical,
archaeological, touristic,
religious, or protected areas
and sites
Risk of impact on recreational
activities
Increased noise levels / noise
pollution
hours during the day to avoid
disturbance
Control construction by fencing
site and spraying water over
working area to control dust
emissions
Provide appropriate sized bins to
collect construction waste and
arrange for periodic pick up and
disposal
Consider project siting during the
design phase
Restrict activities to areas where
biodiversity is not adversely
affected
Use protective clothing and
masks for workers as
appropriate.
Train workers on health care
waste segregation and
occupational safety measures
Education in proper sanitation
and health practices
Careful management of
pesticides
Integrated pest management
programs
Provide glowing traffic signs and
build artificial humps near
construction area
Strict avoidance of construction
near archeological, historical, or
religious areas. If any potential
artifacts are discovered during
construction, work will be
temporarily halted in this area
Restrict noisy activities to certain
hours during the day to avoid
disturbance
hazardous working
conditions.
Accidents may occur
leading to fire or personal
injury
Disruption / congestion of
transportation and traffic
circulation
Increase traffic hazards to
motorists and pedestrians
Introduction of new diseases
Excessive exposure to
existing diseases
Attraction of pests and
rodents
Generation of excess solid
wastes and litter
Transport, storage or
disposal of regulated
hazardous wastes
Reduced aesthetic values /
visual pollution
Risk of impact on historical,
archaeological, touristic, or
protected areas and sites
Risk of impact on
recreational activities
municipal waste (black bags)
and infectious waste (red bags).
Get approval on incinerator
location before installation.
Maintain incinerator
periodically.
Use protective clothing and
masks for workers as
appropriate.
Train workers on health care
waste segregation and
occupational safety measures
Consultation with affected
communities
Employ local citizens in sub-
project area in sub-project
operation
Education in proper sanitation
and health practices
Avoidance of stagnant waters
Careful management of
pesticides
Integrated pest management
programs
Provide glowing traffic signs
and build artificial humps near
construction area
67
Annex 10: Economic and Financial Analysis
ARAB REPUBLIC OF EGYPT
Emergency Labor Investment Project
Rationale for public intervention
1. There is a strong rationale for government intervention to insure social risks, including
poverty, through safety nets such as the present workfare program.
2. First, the private market in this area usually fails, for three reasons:
(i) Information asymmetry. An individual will always know more about his/her own
inherent risk of poverty (hidden knowledge) and about actions that might increase that
risk (hidden action). A private insurer has little possibility to get this information and will
therefore try to „cream-skim‟ the market, i.e., select people with the „best‟ risks and leave
out those with „bad‟ risks. However, this is socially inefficient because of two other
market failures:
(ii) Coordination failure. Individual risks of poverty are different: one person may be hit
during the summer season, and another in the winter season; and they do not know of
each other, and neither does an individual insurer. If they pool their risks, insuring them
jointly will be more efficient. In fact, the more people with different risks who participate
in the insurance scheme, the more efficient it is – also if some are „bad‟ risks. This is
called risk-pooling.
(iii)Externality/ returns to scale. If risks are spread across a large number of people, the cost
of risk-bearing (risk-premium) can be nearly eliminated. For example, if two people share
the costs and benefits of an undertaking, both the costs and the benefits are halved, and
therefore the distance and variation between them are smaller (because costs are negative
benefits). This is called risk-spreading.
3. Second, workfare is a safety net for poverty and unemployment of the neediest and thereby
an instrument to promote greater equity.
Appraisal of costs and benefits of the program
Framework
4. Based on the methodology by Martin Ravallion14,
we estimate the share of the Government‟s
outlay which benefits the poor, i.e.
where
NW is the net wage to beneficiaries (gross wage W minus any costs of participating),
IB are the indirect benefits of the assets (infrastructure etc) created, and
14
Ravallion, M :”Appraising Workfare Programs”, World Bank Policy Research Working Paper 1955, 1998
68
G is the Government‟s budget for the program.
The above ratio can be decomposed as follows:
where
C is private co-financing;
W is the gross wage;
L are leakages of salaries to the non-poor.
Poor people‟s share of the social benefits of the assets created is denoted as
.
Calculations with real parameters
Targeting performance
5. If the workfare wage is low enough, it will self-select participants who do not have better
labor market options. The Egyptian official minimum wage is only EGP 35 (unchanged for 26
years) and therefore not a benchmark. A recent 2011 field trip recorded formal salaries for the
unskilled of EGP 700/month in cities and EGP 600 in rural areas. Most of these can be assumed
to come from the poorest quintile (20%) of the population. Labor Force Survey data from 2006
reports average salaries for the illiterate of EGP 540 and for illiterate informal sector workers of
EGP 420 in 2006. NGO-managed activities (2011) in rural areas pay EGP 350 for unskilled
workers and the Ministry of Water Resources and Irrigation pays maintenance workers only EGP
300 per month, probably on arrangements with a similar motivation as the ELIIP. – We therefore
assume EGP 350 as the outside wage option for the beneficiaries of the ELIIP, which will be
mainly unskilled workers from the poorest 20% in targeted rural areas. If the ELIIP pays EGP
300 or below, it is unlikely to be attractive to currently employed poor workers. For the
following calculations, we therefore assume a LIWP wage of EGP 300.
6. In addition, the LIWP is strictly targeted to very poor regions, namely Luxor, Aswan, Qena,
Sohag, Assiut, Fayoum, Al Sharqia, Kafr Al-Sheikh, Suez, and Beheira. Also, the positive list of
project types eligible under the LIWP will by their nature likely not appeal to people with access
to other work.
7. In conclusion, we assume that the LIWP will suffer no leakages to the non-target
population. L=0.
Net wage to beneficiaries
8. The net wage NW is the gross wage W minus the costs of participation. The costs of
participation include any foregone wage opportunities. Let us assume conservatively that a
beneficiary from the program‟s target population (i.e., an unskilled worker from the poorest
20%) will have a probability of finding work of 78%15
if he is not on the program. With the
NGO wage in rural areas at EGP 350, his expected foregone wage is EGP 273, i.e., a bit lower
than the set wage for the program.
15
Unemployment rate in most affected governorate, Luxor, 22%, ILO 2008.
69
9. The above are average calculations, concealing a distribution around the reservation wage
and employment rate with poorer as well as better expectations. Comparing the options, we can
presume it likely that many workers with less than average probability of finding a job and a
lower expected wage join the program. We also assume that the probability of finding a job does
not change through the time spent on the program, i.e. there will be enough spare time to look for
another job. Let‟s assume the actual LIWP participants face a 30% higher unemployment rate
than the average of the Luxor governorate (22%), i.e., 30%. With this in mind, the Costs C of
participation are 70% * EGP350 = EGP245. And the net wage NW is EGP 300 – EGP 245,
i.e., EGP 55.
Cost-effectiveness of the LIWP
10. The cost-effectiveness ratio is
as explained above. Let us start to fill it with data one
by one.
11. It is likely that the bulk of the indirect benefits IB will accrue in the future and will be zero as
a current value. So IB=0 for now.
12. From a previous similar program, the Social Fund for Development, we know that the wage
share of the overall costs
varies between 22% and 36% for de-centrally implemented, and
between 40% and 70% for centrally implemented activities. The pipeline of projects lined up for
the LIWP achieves a minimum of 50% wage share. We therefore assume for the purposes of this
calculation an intermediate wage share of 50%.
13. We also expect L to be =0 as explained above.
14. Scenario 1: Participants in the LIWP can find work outside the program with the
probability of the current employment rate of Luxor and an NGO wage
With W/G=50% and the NW=EGP 55, the current cost-effectiveness ratio will be
15. This means, under the LIWP it takes EGP 11 to transfer EGP 1 to the beneficiaries
today. This performance can be improved with a higher labor intensity (i.e., going above
50%). The B/G estimate is about 1/2 of Egypt‟s overall poverty rate of 22% (2009, post crisis).
The latter percentage would also be the share of the poor in a uniform, untargeted allocation of
the same budget across the population. So the LIWP unfortunately provides less current
immediate benefit to the poor than this alternative policy. The reason is the relatively low
unemployment rate (22% in the most affected governorate according to our latest information),
suggesting that beneficiaries would face relatively good chances of finding some work outside
LIWP.
16. As the unemployment figures available to us probably do not reflect the reality of the poor
unskilled, we also provide the results of a scenario assuming that workers cannot find work
outside the LIWP.
70
17. Scenario 2: participants in the LIWP cannot find work outside the program
In this case, NW=W and NW/W=1. W/G=50% as before. Then, the current cost-
effectiveness ratio will be
In this case, it only takes EGP 2 to transfer EGP 1 to the beneficiaries today.
18. The B/G estimate is now about 2 times Egypt‟s overall poverty rate of 22% (2009, post
crisis). We can see that under this scenario, the LIWP would provide more current immediate
benefit to the poor than a uniform, untargeted allocation of the same budget across the
population.
Adding in future indirect benefits (IB) to the poor
19. If we add in future IB, we have to examine the extent to which poor people will benefit from
the assets created under LIWP. Given that Upper Egypt will be targeted, we calculate two
scenarios, one for urban, one for rural Upper Egypt, whose poverty rates are 22% and 46%,
respectively.16
Scenario 1: Rural Upper Egypt
20. The poverty rate also implies that the ratio IB/SB is 46%. If all people use a new road
(100%), 46% of these people are poor, and this is the share of the benefit that goes to them.
21. In addition, if we assume that the projects under LIWP generate social benefits sufficient to
cover their costs, then SB/(G+C)=1.
22. Combining the above figures, and conservatively setting C=0, we obtain
23. In concrete terms, it takes EGP 1.04 to increase the incomes of the poor by EGP 1 in the
long term (EGP 1.8 if we use Scenario 1 of the net wage analysis). This is a very efficient
result and compares very positively to the Argentinean Trabajar workfare program, where
it cost EGP 2.5 to improve incomes by EGP 1.
24. Scenario 2: Urban Upper Egypt
Analogously to the above calculations, under this scenario
.
It takes EGP 1.4 to increase the incomes of the poor by EGP 1 in the long term (EGP 3.2 if
we use Scenario 1 of the net wage analysis). This ratio still compares favorably with the
Trabajar program.
16
Source: Staff estimates based on HIECS 2008/09. Number of poor includes extreme poor.
71
Annex 11: Documents in Project Files
ARAB REPUBLIC OF EGYPT
Emergency Labor Intensive Investment Project
International Organization for Migration (IOM) Cairo. Egyptian Migration to Libya. March
2011.
The World Bank. Social and Economic Development Group. Middle East and North Africa.
EGYPT - Poverty in Egypt 2008-09: Withstanding the Global Economic Crisis. January
2011.
The World Bank. Social and Economic Development Group. Middle East and North Africa.
EGYPT - EGYPT‟S FOOD SUBSIDIES: BENEFIT INCIDENCE AND LEAKAGES, July
2010.
The World Bank. Social Protection. Macro Crises and Safety Net Responses Experience of
Argentina, Mexico, Korea and Thailand and Lessons for East and Central Asia countries.
The World Bank. Social Protection Discussion Papers. Making Public Works Work. The
Design and Implementation of Public Works Programs. A Toolkit for Practitioners. April
2010.
The World Bank. Social and Economic Development Group. Middle East and North Africa.
EGYPT - UPPER EGYPT: PATHWAYS TO SHARED GROWTH. October 2009.
Ministry of Labor. International labor Organization. Egypt Youth Employment. National
Action Plan - 2010-2015. May 2009.
The World Bank. Social and Economic Development Group. Middle East and North Africa.
EGYPT - TOWARD A MORE EFFECTIVE SOCIAL POLICY: SUBSIDIES AND
SOCIAL SAFETY NET. December 2005.
International Labor Organization. Livelihood and Employment Creation. Labour-based
Infrastructure Projects. 2005
International labor Organization. Mitigating a Job Crisis. Innovations in Public Works
Programmes. Case Study. The Mahatma Ghandi National Rural Employment Guarantee Act
(NERGA), India.
International labor Organization. Employment-Intensive Infrastructure Programmes:
Capacity Building for Contracting in the Construction Sector. 1999
International labor Organization. Employment-Intensive Infrastructure Programmes: Labour
Policies and Practices. 1998
72
Annex 12: Statement of Loans and Credits
ARAB REPUBLIC OF EGYPT
Emergency Labor Intensive Investment Project
Original Amount in US$ Millions
Difference between
expected and actual
disbursements
Project ID FY Purpose IBRD IDA SF GEF Cancel. Undisb. Orig. Frm. Rev‟d
P120161 2011 EG-Integrated Sanitation & Sew. Infra. 2 200.00 0.00 0.00 0.00 0.00 200.00 0.00 0.00
P117745 2011 EG-Farm-level Irrigation Modernization 100.00 0.00 0.00 0.00 0.00 100.00 10.50 0.00
P101201 2010 EG-Cairo Airport Development Project-TB2
280.00 0.00 0.00 0.00 0.00 258.31 58.31 0.00
P112346 2010 EG-Affordable Mortgage Finance DPL 300.00 0.00 0.00 0.00 0.00 100.00 0.75 0.00
P113416 2010 EG-Wind Power Development 70.00 0.00 0.00 0.00 0.00 70.00 32.33 0.00
P116011 2010 EG-Enhancing Access to Finance for
SMEs
300.00 0.00 0.00 0.00 0.00 136.21 -63.87 0.00
P116194 2010 EG-Giza North Power Project 840.00 0.00 0.00 0.00 0.00 809.80 84.80 5.91 P080228 2010 EG-Health Insurance Systems
Development
75.00 0.00 0.00 0.00 0.00 75.00 13.83 0.00
P101103 2009 EGYPT-Railways Restructuring 600.00 0.00 0.00 0.00 0.00 591.64 181.80 3.38 P100047 2009 EG-Ain Sokhna Power 600.00 0.00 0.00 0.00 0.00 479.66 53.00 0.00
P095392 2008 EG-Natural Gas Connections Project 75.00 0.00 0.00 0.00 0.00 6.93 -12.07 0.00
P094311 2008 EG INTEGRATED SANITATION & SEWERAGE INFR
120.00 0.00 0.00 0.00 0.00 106.86 61.91 0.65
P090073 2006 EG-Second Pollution Abatement 20.00 0.00 0.00 0.00 0.00 8.73 8.73 1.58
P082952 2005 EG-Early Childhood Education Enhancement
20.00 0.00 0.00 0.00 0.00 8.65 -3.40 -0.02
P073977 2005 EG-INTEGRATED IRRIGATION IMPR.
& MGT
120.00 0.00 0.00 0.00 0.00 77.62 70.12 17.27
P045499 2000 EG-NATIONAL DRAINAGE II 80.00 0.00 0.00 0.00 0.00 28.43 -1.50 1.67
P050484 1999 EG Secondary Education Enhancement
Proj
0.00 50.00 0.00 0.00 0.00 7.79 3.87 4.50
Total: 3,800.00 50.00 0.00 0.00 0.00 3,065.63 499.11 34.94
Egypt, Arab Republic of
STATEMENT OF IFC‟s
Held and Disbursed Portfolio
In Millions of US Dollars
Committed Disbursed
IFC IFC
FY Approval Company Loan Equity Quasi Partic. Loan Equity Quasi Partic.
Total portfolio: 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Approvals Pending Commitment
FY Approval Company Loan Equity Quasi Partic.
Total pending commitment: 0.00 0.00 0.00 0.00
73
Annex 13: Country at a Glance
ARAB REPUBLIC OF EGYPT
Emergency Labor Intensive Investment Project
74
W e s t e r n
D e s e r t
L i b y a n P l a t e a u
Li
by
an
D
es
er
t
QattaraDepression
Ea
st e
rn
De
se
rt
A L WA D IA L J A D I D
MARSA MATRUH
ASWAN
QENA
SOHAG
ASSIUT
SOUTHERNSINAI
NORTHERNSINAI
SUEZ
EL FAYOUM
BENI SUEF
AL MINYA
AL BAHR
AL AHMAR
Luxor
Kom Ombo
Halaib
Siwa
Qara
Mut.
Ras Gharib
Taba
Abu Zenima
Qena
Suez
Aswan
Sohag
Assiut
Benha
Tanta
Damietta
El Tur
Zagizig
Al Minya
Ismailia
Damanhur
El-Kharga
Beni Suef
El Fayoum
El Mansura
Shibin el Kom
Kafr elSheikh
CAIRO
LakeNasser
Nile
River
G I Z A
Giza
1
89
1011
1213
2
3
4
5
6 7
HelwanHELWAN
Luxor
Kom Ombo
Halaib
Marsa 'Alam
Salum
Siwa
Qara
Mut.
Quseir.
Bir Seiyala
Ras Gharib
Taba
Abu Zenima
Giza
Marsa Matruh
Qena
Suez
Helwan
Aswan
Sohag
Assiut
Benha
Tanta
Damietta
El Tur
Zagizig
Al Minya
Ismailia
Damanhur
El'Arish
El-Kharga
Beni Suef
El Fayoum
Port SaidEl Mansura
Alexandria
Al Ghurdaqah
Shibin el Kom
Kafr elSheikh
CAIRO
A L WA D IA L J A D I D
MARSA MATRUH
ASWAN
QENA
SOUTHERNSINAI
NORTHERNSINAI
SUEZ
HELWAN
G I Z A
AL BAHR
AL AHMARASSIUT
EL FAYOUM
BENI SUEF
AL MINYA
SOHAG
1
89
1011
1213
2
3
4
5
6 7
S U D A N
SAUDIARABIA
JORDANISRAEL
LIBYA
WEST BANKAND GAZA
Aswan Dam
Nile
River
LakeNasser
Gulf of Suez
Gul
f of
A
qaba
Red
Sea
M e d i t e r r a n e a n S e a To Tel Aviv
To Port SudanTo
BerberTo
Dongola
To Jalu
To Darnah
W e s t e r n
D e s e r t
L i b y a n P l a t e a u
Li
by
an
D
es
er
t
QattaraDepression
Ea
st e
rn
De
se
rt
25°E 30°E
30°N
25°N
20°N
30°N
25°N
20°N
35°E
25°E 30°E 35°E
ARAB REPUBLICOF EGYPT
This map was produced by the Map Design Unit of The World Bank. The boundaries, colors, denominations and any other informationshown on this map do not imply, on the part of The World BankGroup, any judgment on the legal status of any territory, or anyendorsement or acceptance of such boundaries.
0 50 100 150
0 50 100 150 Miles
200 Kilometers
IBRD 33400R
MAY 2010
ARAB REPUBLIC OF EGYPTSELECTED CITIES AND TOWNS
GOVERNORATE CAPITALS
NATIONAL CAPITAL
RIVERS
MAIN ROADS
RAILROADS
GOVERNORATE BOUNDARIES
INTERNATIONAL BOUNDARIES
GOVERNORATES IN NILE DELTA:
1234567
KAFR EL SHEIKHDAMIETTAPORT SAIDALEXANDRIABEHEIRAGHARBIYADAGAHLIYA
MENOUFIYASHARGIYAHQALIUBIYAISMAILIACAIROGIZA
89
10111213