Document Number: HSP 325 Current Rev: 07/23/2015 PSM 6...
Transcript of Document Number: HSP 325 Current Rev: 07/23/2015 PSM 6...
Document Number: HSP – 325
PSM – 6
Revised By: Jake A. Valenti
Manager Approval: Hillary Garner
Current Rev: 07/23/2015
Revision No.: 9
Page 1 of 28
HEALTH AND SAFETY PROGRAM 325 – CONTRACTOR SAFETY MANAGEMENT
Printed controlled copy expires 24 hours after 2:19 PM on 8/10/2015.
1.0 PURPOSE
Axiall, Plaquemine, has developed this document to ensure the site achieves desired safety
performance by contractors, thus enhancing contractor employee protection. This document
provides guidelines to assure that contractors and their tiers of subcontractors are meeting or
exceeding Axiall’s expectations and requirements.
2.0 SCOPE
This document applies to all contractor companies performing work at Axiall, Plaquemine,
through contractual agreement, by service contract, purchase order, etc…, including, but not
limited to contractor personnel performing maintenance, repair, turnaround, renovation or
specialty work.
3.0 RESPONSIBILITIES
3.1 Procurement Department
3.1.1 Issue contracts for services to only those companies that have satisfied all
contractor qualification requirements for Axiall, Plaquemine.
3.1.2 Issue contracts, purchase orders to contractors that have A or B company
grade in ISNetworld.
3.1.3 Retain copies of all required contract documents for PSM audit purposes.
3.1.4 Inform all contractors that a condition of performing work at the Plaquemine
Complex is to adhere to the site safety requirements.
3.2 Authorized Axiall Representative
3.2.1 Ensure contractor has acceptable ISNetworld company grade before
requesting them to the site.
3.2.2 Invite contractor to attend the monthly contractor safety meeting held the
first Wednesday of every month at 1:00pm in the Rebecca room of the H&S
building.
3.2.3 Monitor contractor's work areas for compliance to all applicable regulations
and Axiall health and safety policies and procedures.
3.2.4 Participate in inspections of Contractor work areas and ensure closure on
inspection findings.
3.2.5 Obtain contact information for contractors’ home office, corporate health and
safety contact, job superintendent and site health and safety representative.
3.2.6 Review all contractor chemical inventories and SDS and send all new
chemicals through “New Chemical Approval” process.
3.2.7 Complete “Post Job Evaluation” for all jobs performed by a contractor.
3.2.8 Notify Health and Safety of any contractor incident as soon as possible.
Document Number: HSP – 325
PSM – 6
Revised By: Jake A. Valenti
Manager Approval: Hillary Garner
Current Rev: 07/23/2015
Revision No.: 9
Page 2 of 28
HEALTH AND SAFETY PROGRAM 325 – CONTRACTOR SAFETY MANAGEMENT
Printed controlled copy expires 24 hours after 2:19 PM on 8/10/2015.
3.2.9 Send incident report/investigation report to Health and Safety upon receiving
the report.
3.2.10 Send following HSP’s to site contractor representative as applicable. Any
procedures sent to the contractor must be stamped/marked as “Date: Good
for Duration of Job.” 3.2.10.1.1 HSP – 103 “Plant Entry Requirements”
3.2.10.1.2 HSP – 106 “ General Safety Rules”
3.2.10.1.3 HSP – 200 “Safe Work Permitting”
3.2.10.1.4 HSP – 202 “Confined Space Entry Permitting”
3.2.10.1.5 HSP – 307 “Line Breaking”
3.2.10.1.6 HSP – 317 “Control of Hazardous Energy”
3.2.10.1.7 HSP – 318 “Excavation Safety”
3.2.10.1.8 HSP – 319 “Fall Protection”
3.2.10.1.9 HSP – 325 “Contractor Safety Management”
3.2.10.1.10 HSP- 302 “Signs, Signals, &Barricades”
3.2.10.1.11 HSP – Any other applicable HSP’s
3.3 Health & Safety Department (H&S)
3.3.1 Monitor ISNetworld grades for all connected contractors; work with ISN and
the contractor to maintain an acceptable grade.
3.3.2 Evaluate contractor health and safety requirements to ensure full compliance
with requirements of this policy during the qualification process. This will be
accomplished within ISNetworld.
3.3.3 Review annually contractor's (Evergreen) safety performance and verify
implementation through field inspections and surveillance.
3.3.4 Make Axiall Health and Safety Procedures available via ISNetworld.
3.3.5 Track any post-job evaluation action items to completion.
3.4 Operations Supervision
3.4.1 Axiall operations and maintenance supervision will meet as often as
necessary with contractor employers to discuss safe work practices and
contractor safety performance.
3.5 Security
3.5.1 Ensure contractor company has A or B ISNetworld company grade; if not
deny gate entry.
3.5.2 Ensure that contractors wear temporary badge and appropriate safety
equipment (e.g. hard hat, safety glasses, and NIOSH approved acid gas escape
respirator (Honeywell (model 7902) preferred) prior to entry into the facility.
3.5.3 Ensure that all contractors have proper safety orientations prior to entering
plant for work.
Document Number: HSP – 325
PSM – 6
Revised By: Jake A. Valenti
Manager Approval: Hillary Garner
Current Rev: 07/23/2015
Revision No.: 9
Page 3 of 28
HEALTH AND SAFETY PROGRAM 325 – CONTRACTOR SAFETY MANAGEMENT
Printed controlled copy expires 24 hours after 2:19 PM on 8/10/2015.
3.5.4 Provide site-specific orientation for contractor personnel prior to allowing
work on site for emergency jobs via Health & Safety approval
3.5.5 Ensure that all contractor employees use the turnstiles or scanners when
entering and leaving the complex.
3.5.6 Periodically inspect vehicles upon entering and exiting the plant per Axiall’s
security plan.
3.6 Contractors and Subcontractors
3.6.1 Submit all qualification forms and subsequent documentation including the
health and safety program associated with pre-qualification process for the
contractor and any sub-contractors to be used to ISNetworld – all
subcontractors shall have their own ISNetworld account.
3.6.2 Ensure all employees and subcontractor employees complete the ARSC
Basic Plus safety orientation and Axiall site-specific orientation prior to
beginning work on site.
3.6.3 Immediately report injuries, illnesses or other significant safety issues to
Authorized Axiall Representative.
3.6.4 Conduct and document weekly safety inspections of the work site.
3.6.5 Conduct weekly safety meetings for all employees.
3.6.6 Turn in an incident investigation report to Authorized Axiall Representative
within twenty-four (24) hours following any incident, injury or near miss.
3.6.7 Conduct daily tailgate safety meetings.
3.6.8 Comply with all applicable federal regulations and Axiall safety policies and
procedures.
3.6.9 Participate in scheduled third-party or Axiall internal process safety
management (PSM) audits for contractors; this will include providing
requested documentation and following action items to closure.
3.6.10 Submit hours worked and acknowledge Axiall Health & Safety procedure
changes via Monthly Contractor Report sent via email by the H&S
department.
3.6.11 Attend post-job evaluation with Axiall representative, when invited.
4.0 CONTRACTOR TIERS
4.1 Requirements of Tiered Contractor Companies
*ALL ENTRY REQUIREMENTS OF AXIALL HSP-103 APPLY.
Document Number: HSP – 325
PSM – 6
Revised By: Jake A. Valenti
Manager Approval: Hillary Garner
Current Rev: 07/23/2015
Revision No.: 9
Page 4 of 28
HEALTH AND SAFETY PROGRAM 325 – CONTRACTOR SAFETY MANAGEMENT
Printed controlled copy expires 24 hours after 2:19 PM on 8/10/2015.
4.1.1 Tier 1 – Visitors/Deliveries/Vendors – these companies/individuals do
not perform work either on or adjacent to process equipment.
4.1.1.1.1 These companies or individuals do not require subscription
to ISNetworld.
4.1.1.1.2 Examples of these companies or individuals are: a
visitor of an Axiall employee or contractor employee, hot
shot delivery, training rep, Sales, Entergy & gas suppliers.
4.1.1.1.3 Valid visitor orientation required for entry (12AXLV).
4.1.2 Tier 2 – Non-Operational Contractors – these companies may perform
work either adjacent to process equipment or adjacent to the property
battery limits, but for no reason perform hands-on work on process
equipment.
4.1.2.1.1 These companies do require subscription to ISNetworld.
4.1.2.1.1.1 Exemption to ISNetworld is allowed by written approval from
H&S dept. – safety and insurance review still required.
4.1.2.1.2 Their work could require safe work permits from
operations. However, they would not perform any work on
process equipment.
4.1.2.1.3 Companies performing work inside laboratories are not
required to subscribe to ISNetworld; this excludes
construction or renovation to the building.
4.1.2.1.4 Examples of service companies are: Tire repairs,
windshield replacement, fencing, equipment rental,
engineering contractors, PSM consultants, landscaping,
and chemical service companies.
4.1.2.1.5 Valid Basic Orientation Plus/Refresher and Axiall site-
specific required for entry (12AXLPLQ).
4.1.3 Tier 3 – Operational Contractors – Operational Contractors – These
companies perform maintenance or repair, turnaround, major
renovation or specialty work either on or adjacent to process
equipment; this tier consists of nested and job-specific contractors.
4.1.3.1.1 These companies require subscription to ISNetworld.
4.1.3.1.2 Examples of service companies are: work on piping,
vessels, or other equipment, work on DCS, fire
maintenance provider, turnaround services.
4.1.3.1.3 Safe Work permits are required for most of their work.
4.1.3.1.4 Required to review and accept policies annually via
ISNetworld.
4.1.3.1.5 Valid Basic Orientation Plus/Refresher and Axiall site
specific orientation required for entry (12AXLPLQ).
5.0 PROCEDURE
5.1 Qualification
5.1.1 The following information will be utilized to measure a Contractor’s and
Document Number: HSP – 325
PSM – 6
Revised By: Jake A. Valenti
Manager Approval: Hillary Garner
Current Rev: 07/23/2015
Revision No.: 9
Page 5 of 28
HEALTH AND SAFETY PROGRAM 325 – CONTRACTOR SAFETY MANAGEMENT
Printed controlled copy expires 24 hours after 2:19 PM on 8/10/2015.
sub- contractor’s prior safety performance. Contractors and sub-contractors
that do not adequately meet an acceptable level of achievement will not be
allowed to perform work at Axiall, Plaquemine.
5.2 Required Qualification Submittals
5.2.1 Prior to or as part of the bid evaluation process all prospective contractors
shall submit the following information to their ISNetworld account for
review and acceptance by Axiall:
5.2.1.1 Answer the Management System Questionnaire (MSQ) within the
ISN account
5.2.1.2 OSHA 300 and 300A logs covering the past three years and the
current year to date for the company and local/regional office.
5.2.1.3 Workers Compensation Insurance Experience Modification Rate
(EMR) documentation from the contractor’s workers comp carrier for
the past three years.
5.2.1.4 A current copy of their Health and Safety Manual
5.3 Other Data
5.3.1 In addition, a review may be conducted of audit reports from former clients,
the Greater Baton Rouge Industry Alliance (GBRIA), and previous Axiall
projects.
5.4 Selection
5.4.1 Submittal Review
5.4.1.1 A complete review of the MSQ will be conducted by ISN
Review and Verification Service (RAVS) to ensure the
company meets our minimum criteria.
5.4.1.2 The three year average of the local/regional office incident
rate may not exceed the national average in the applicable
NAISC code, as published by the Bureau of Labor Statistics
(BLS).
5.4.1.3 The contractor’s EMR rate may not exceed 1.0 to be a
qualified contractor at Axiall, without an approved variance.
5.4.2 Pre-Bid Meetings
Based upon the size and scope of the project a pre-bid meeting may be
conducted and made available to all prospective contractors. During the pre-
bid meeting an Axiall representative will discuss the health and safety
Document Number: HSP – 325
PSM – 6
Revised By: Jake A. Valenti
Manager Approval: Hillary Garner
Current Rev: 07/23/2015
Revision No.: 9
Page 6 of 28
HEALTH AND SAFETY PROGRAM 325 – CONTRACTOR SAFETY MANAGEMENT
Printed controlled copy expires 24 hours after 2:19 PM on 8/10/2015.
requirements of this Contract and any unique expectations, based upon the
project scope.
5.4.3 Contract Language
To ensure Contractors are made aware of Axiall’s health and safety
requirements the contract language shall contain details of special issues
expected of contractors when working within the Plaquemine Complex (see
appendices).
5.5 Re-Qualification
5.5.1 Contractors must re-qualify annually or prior to issuing a new contract.
5.5.1.1 Re-Qualification includes:
5.5.1.1.1 Updated OSHA 300 logs
5.5.1.1.2 Update EMR documentation
5.5.1.1.3 Annual Sign off of Plaquemine Site Health and Safety
Manual
5.5.1.1.4 Same OSHA TRIR and EMR requirements as original
qualification.
5.5.1.1.5 Contractor updated Health and Safety Manual (if requested)
5.6 Pre-Job Start
5.6.1 Kick-Off Meetings
5.6.1.1 Following contract award a pre-construction meeting (kick-off)
will be held with the Contractor's management. The site
supervisor must attend the pre-construction meeting. Applicable
health and safety issues shall be discussed during the pre-
construction meeting.
5.6.1.2 During the pre-construction meeting an Axiall Safety
Representatives will be assigned to the project for coordination
with the Contractor.
5.6.1.3 All required submittals shall be received and approved prior to the
Contractor being released to proceed with mobilization and construction.
5.6.2 Orientation
All Contractor employees are required to attend Axiall Site-Specific
Orientation at an Alliance Safety Council or other ARSC council prior to
beginning work on-site. See Axiall HSP-103 “Plant Entry Requirements” for
Document Number: HSP – 325
PSM – 6
Revised By: Jake A. Valenti
Manager Approval: Hillary Garner
Current Rev: 07/23/2015
Revision No.: 9
Page 7 of 28
HEALTH AND SAFETY PROGRAM 325 – CONTRACTOR SAFETY MANAGEMENT
Printed controlled copy expires 24 hours after 2:19 PM on 8/10/2015.
specific details.
5.7 Work in Progress
5.7.1 Evaluation
Throughout the duration of the project, the authorized Axiall representative
for the contractor will perform occasional informal inspections and as
warranted, a formal inspection of the contract job. Findings from these visits
will be tracked by the Authorized Axiall Representative to ensure mitigation
or elimination.
5.8 Post Evaluation
5.8.1 Following completion of a project completed by a contractor the authorized
Axiall representative will conduct a Post Job Evaluation of the Contractors
performance with the contractor (See Appendix B).
5.8.2 Service contracts will be reviewed on an annual basis.
6.0 RECORDKEEPING
6.1 Contractor Audits
6.1.1 Copies of all formal audits and inspections of a Contractors performance
shall be maintained in the Safety department & ISNetworld.
6.1.2 Axiall Health and Safety procedures shall be reviewed with both nested and
non-nested contractors annually. Nested contractors’ records will be
reviewed internally annually by Axiall. Non-nested may be reviewed
internally or by third party annually
6.2 Post Job Evaluation Form
6.2.1 The completed Post Job Evaluation Form will be maintained in the Project
files maintained by Engineering & ISNetworld.
7.0 PROGRAM REVIEW
7.1 This Program will be reviewed periodically. HS&S will ensure this review is
performed. The purpose is to assess compliance and to evaluate program effectiveness.
7.2 Following the review, the program will be revised to include any necessary changes.
Review results will be documented. All employees will be informed of any changes
Document Number: HSP – 325
PSM – 6
Revised By: Jake A. Valenti
Manager Approval: Hillary Garner
Current Rev: 07/23/2015
Revision No.: 9
Page 8 of 28
HEALTH AND SAFETY PROGRAM 325 – CONTRACTOR SAFETY MANAGEMENT
Printed controlled copy expires 24 hours after 2:19 PM on 8/10/2015.
made in the plan.
7.3 Department Managers will be informed of review results.
8.0 REFERENCES
8.1 29 CFR 1910.119 (h) - Process Safety Management
9.0 APPENDICES
Appendix A - Statement of Contractor Health and Safety Requirements and Policies
Appendix B - Post Job Evaluation
Printed controlled copy expires 24 hours after 2:19 PM on 8/10/2015.
APPENDIX A
STATEMENT OF CONTRACTOR
HEALTH AND SAFETY
REQUIREMENTS AND POLICIES
STATEMENT OF CONTRACTOR HEALTH AND
SAFETY REQUIREMENTS AND POLICIES
Axiall Corporation requires that Contractors take all reasonable precautions in the performance
of their work to protect the health and safety of their employees and of personnel in the
surrounding work areas. The special safety requirements listed herein shall not relieve the
Contractor from complying with the Occupational Safety and Health Act (OSHA) or any other
regulatory or contractual requirement, and are noted only to highlight special areas of concern.
1.0 Pre-Construction
1.1. Following contract award a pre-construction meeting (kick-off) will be held with the
Contractor's management. Applicable health and safety issues will be discussed
during the pre-construction meeting.
1.2. During the pre-construction meeting an authorized Axiall representative will be
assigned to the project for coordination with the Contractor. All required submittals
contained herein would go to the assigned representative, unless noted otherwise.
1.3. All required submittals would be received and approved prior to the Contractor being
released to proceed with mobilization and construction.
2.0 Safety Program
2.1. In the qualification process and anytime requested thereafter, the Contractor will
submit, for Axiall review and acceptance, a written Safety Program consistent with
OSHA regulations, Axiall safety requirements and specific to the tasks to be
performed. The Program at a minimum will contain the following:
2.2. Safety Policy Statement, signed by the principal officer of the company, which
describes the organization’s health and safety goals.
2.3. Name, qualifications and duties of the Safety Representative
2.4. Hazard Communication Program
2.5. Respiratory Protection Program
2.6. Fall Protection Plan
2.7. Training Program including; Employee orientation, hazard communication, personal
protective equipment, confined space entry, and control of hazardous energy.
2.8. Name, qualifications of excavation competent person (if applicable)
2.9. Name and training certification of First Aid designee
2.10. Process by which the Project will be internally inspected for health and safety
deficiencies
2.11. Safety meeting program
2.12. Disciplinary action program
2.13. Analysis of hazards anticipated with job tasks.
2.14. List of critical lifts to be performed during the project
2.15. Emergency response plan
2.16. Axiall Safety will promptly review the Program.
3.0 Hazard Communication
3.1. Axiall maintains Safety Data Sheets (SDS) for hazardous chemicals used on site.
SDSs are available to contractor personnel upon request. Request may be made in
any control room or to your Axiall representative.
3.1.1. The Contractor and all tier contractors will comply with OSHA 29CFR
1910.1200 Hazard Communication and Axiall requirements, which include:
3.1.2. Developing and implementing a written hazard communication program for
the site (To be included in the Safety Program).
3.1.3. Training employees in handling all hazardous materials.
3.1.4. Maintaining a list of all hazardous materials present in the workplace.
3.1.5. Maintaining Safety Data Sheets for each hazardous material onsite.
3.2. The Contractor will submit a copy of the hazardous material inventory and all
associated SDS to authorized Axiall representative for review and acceptance, prior to
the materials being brought onsite. The authorized Axiall representative will review
all SDS and send all new chemicals through the new chemical approval process.
4.0 Safety Representative
4.1. The Contractor will assign a Safety Representative to each project. The safety
representative will be on site full time when the project crew size is 25 or greater or
otherwise requested by the Axiall Representative. The safety representative
responsibilities will include, as a minimum, the following:
4.2. Authority to take immediate action to correct safety violations and, if necessary, stop
work;
4.3. Conduct weekly safety meetings with project employees;
4.4. Conduct weekly safety inspections and document findings;
4.5. Conduct daily tailgate safety meetings.
5.0 Medical First Aid
5.1. When the contract work force exceeds five (5) personnel, the Contractor will
provide at least one (1) employee trained in Basic First Aid and CPR to be
onsite during project work hours.
5.2. The Contractor will maintain a first aid kit of adequate size for the number of
employees working on the project.
5.3. Axiall maintains a Medical Emergency Response Team (MERT) available on all
shifts. In the event of a medical emergency, notify Axiall personnel for assistance
from the MERT. (See Section 28. Emergency Response for notification methods)
6.0 Orientations
6.1. Before beginning work on site, each Contract and/or sub-tier contract employee will
attend:
6.1.1. A general safety orientation presented by any member of ARSC (Association
of Reciprocal Safety Councils) located throughout the Gulf Coast area. The
Safety Council of Baton Rouge is a member of ARSC. The card will read
“ARSC”.
6.1.2. An Axiall General Plant and specific production-units orientation. The
orientation is conducted Monday thru Friday at 6:30 am to 4:00 pm at the
Alliance Safety Council. The card will read “12AXLPLQ” on the back.
6.2 A proof of the ARSC Orientation and the plant and unit specific (12AXLPLQ)
must be presented at the main security center prior to coming on site.
7.0 Training
7.1. OSHA requires training for all personnel working within an industrial facility.
7.2. The Contractor will ensure that required safety training is carried out before
personnel start work and continues throughout all phases of the work.
7.3. Additional training for specific tasks may also be required. The Contractor will
be responsible to ensure employees meet all required regulatory training.
7.4. Contractors must provide copies of certifications upon request for all work
requiring certifications per regulations such as crane operators or welders to
Axiall representative.
8.0 Communication Requirements
8.1. In order to ensure the safety and well being of all personnel entering this Axiall
complex it is important that contractors are capable of comprehending all plant
warning signs as well as verbal and written instructions. For this reason, personnel
must posses a minimum level of proficiency in the English language to be allowed
access into the plant. This minimum level will be gauged by requiring successful
completion of all orientation documentation and tests without assistance or
“coaching” from others.
9.0 Contractor Evaluation
9.1. Throughout the duration of the project, Axiall will perform occasional inspections of
the contract job. Findings from these visits will be presented to the Contractor for
corrective action. In addition a report regarding the observations and correction of
deficiencies will be placed in the contract file for use in future evaluation of the
Contractor.
10.0 Inspections
10.1. The Contractor will conduct weekly or more frequent if regulatory, safety
inspections of the work site and document findings.
10.2. Prompt action is required by the Contractor to correct noted unsafe practices or
unsafe conditions.
11.0 Safety Violations
11.1. In the event of violations or unsafe practices involving imminent danger to
personnel, immediate action will be taken to stop work and correct the hazardous
situation. If violations continue or corrective actions are not taken after a reasonable
period of time, Axiall's option of terminating the contract will be enforced.
11.2. Violation of safety requirements by Contractor employees will result in
appropriate disciplinary action. Axiall may determine it to be necessary for an
employee to be ejected from the plant premises and have their badge and orientation
card removed.
12.0 Reporting Injuries
12.1. The Contractor will, within 1 hour, verbally notify their Axiall Project Contact
and the Safety Department of all injuries, illnesses, or near-miss incidents. The
Contractor will investigate each injury, illness or incident. The Contractor will
submit written documentation of the incident and investigation to the authorized
Axiall representative within twenty-four hours of the injury or incident.
12.2. A Contractor’s Monthly Report must be submitted to the Axiall Safety
Department for each month in which the Contractor performed work on site. The
report should detail only Contractor numbers for personnel on an Axiall project.
This will be sent to you electronically from our H&S department.
13.0 Control of Hazardous Energy Sources
13.1. The Contractor will be responsible to ensure that the project and associated
personnel comply with the requirements of OSHA 29CFR 1910.147 and the Axiall
Health and Safety Manual procedure for the control of hazardous energy sources,
HSP-317, “Control of Hazardous Energy.”
13.2. For lockout/tagout, the contractor will provide personal blue locks for each
employee involved in lockout with the company’s name and employee’s name. Also
yellow locks for supervisors must be provided with the same information.
14.0 Confined Space Entry
14.1. The Contractor will be responsible to ensure that the project and associated
personnel comply with the requirements of OSHA 29CFR 1910.146 and Axiall’s
Health and Safety Manual procedure, HSP-202 “Confined Space Entries” for entry
into confined spaces.
14.2. A confined space entry permit issued by Axiall Operations is required prior to
entry into any confined space.
14.3. Excavations greater than 4 feet in depth will be considered a confined space.
15.0 Excavations
15.1. All excavation work will be conducted in accordance with OSHA 29CFR 1926
Subpart P “Excavations” and the Axiall’s Health and Safety Manual procedure, HSP
318 “Excavation Safety”.
15.2. All excavations must be inspected daily and when conditions change by a
“Competent Person” prior to entry, by personnel. The name and qualifications of
this competent person must be submitted to Axiall for review and acceptance.
15.3. An Excavation Permit must be obtained and reviewed prior to the start of
excavation activities at Axiall.
16.0 Permits
16.1. To provide for maximum personnel safety, any Contract work performed in the
plant must be “permitted” by the Supervision in charge of the area involved. The
following permits are utilized to communicate safety requirements for activities:
16.2. Safe Work Permit
16.2.1. Required for all work performed on site. Issued by Department Supervision
responsible for the unit in which work will be performed.
16.3. Hot Work
16.3.1. Required for all activities within an operating unit which may produce sparks
or flames. Contained within the Safe Work Permit. Issued by Department
Supervision responsible for the unit in which work will be performed.
16.4. Vehicle Entry
16.4.1. Required for all vehicles and other internal combustion engine equipment
taken into an operating unit. Contained within the Safe Work Permit. Issued
by Department Supervision responsible for the unit in which work will be
performed.
16.5. Confined space entry permit
16.5.1. Required for entry into any confined space. Issued by Department
Supervision responsible for the unit in which work will be performed.
16.6. Excavation permit
16.6.1. Required for all excavation work performed on site. Issued by Engineering
Department.
17.0 Protective Clothing
17.1. Contractor personnel will wear hard hats, industrial quality work shoes, and safety
glasses with side shields while within the plant site, except in offices, gang shacks,
and control rooms. Signs or permits for specific exposure areas may prescribe
additional personal protective equipment. Always follow these instructions. Safety
glasses, including all components (frames, lenses, and side shields) will conform to
ANSI Standard Z87.1. Slip-on, flimsy plastic side shields are not permitted.
17.2. All personnel, as determined by the activities to be performed, will wear
appropriate clothing. Shirts with sleeves, over the shoulders, and long pants are
required at a minimum. Flame retardant clothing (FRC) is required in all process
units and where otherwise noted by the requirements of a safe work permit.
17.3. All employees will have (on their person) an emergency escape respirator for
chlorine gas at all times while on site. The escape respirator must be maintained
sealed in a clear plastic bag for protection from deterioration.
17.4. Before any employee starts work requiring use of respiratory protective
equipment, the Contractor will comply with OSHA Section 29CFR 1910.134
17.5. No one whose work involves wearing a tight fitting respirator will be allowed in
the area with facial hair that would prevent a positive face to full-face mask seal.
This includes beards, sideburns, or an elongated mustache.
18.0 Fall Protection
18.1. Employees working on elevated surfaces four (4) feet or more above a lower
level will be protected from falling.
18.2. Fall protection systems must comply with the requirements of OSHA 29CFR
1926 Subpart M - “Fall Protection”.
18.3. Personnel fall arrest systems will consist of a full-body harness with shock
absorbing lanyard. All snap hooks will be the locking type. The use of body belts for
fall arrest is prohibited.
19.0 Housekeeping
19.1. Housekeeping is to be an ongoing process throughout the day and not performed
only at the completion of the day's work.
19.2. During the course of construction, alteration, or repairs, all debris will be kept
cleared from work areas, passageways, and stairs in and around buildings or other
structures.
19.3. The spillage of oil or any other foreign substance onto the ground or into plant
sumps, trenches or ditches is strictly prohibited. Any spill or release must be
immediately reported to the unit or authorized Axiall representative. Contractor will
provide metal containers for the collection and separation of waste, trash, and other
refuse.
20.0 Signs, Barriers and Flagging
20.1. The Contractor will furnish, erect, maintain, and dismantle all barriers required for
its work.
20.2. As a minimum, flagging will be installed around the perimeter of the jobsite and
storage areas. Signs will meet OSHA specifications and will identify all hazards.
20.3. Barricades or flagging are required:
20.3.1. Around all work areas
20.3.2. Around crane swing area and counterweight swing radius of all equipment
20.3.3. To define outer limits of high noise areas.
20.3.4. To define areas of overhead work
20.3.5. Around excavations
20.3.6. For road closures
20.4. Provide flashing yellow lights if barricades on road closures are left overnight.
Notify the authorized Axiall representative at least 48 hours before closing off any
road.
21.0 Construction Equipment
21.1. Contractor and all subcontractors will comply with all provisions of OSHA and
Axiall’s Health and Safety Manual in the operation, control, and inspection of major
equipment. In addition, Axiall reserves the right to inspect major equipment prior to
use on site to determine if there are obvious defects that would prevent operation of
the equipment on site.
21.2. Rigging from the buckets or booms of backhoes, front end loaders, dozers, etc., to
lay pipe, erect steel, pick and carry, etc., will not be permitted unless a properly
installed and tested lifting eye or lug has been attached to the bucket or boom by the
manufacturer, and lifting capacities and configurations are specified in the
manufacturer's operating manual.
21.3. All vehicles or construction equipment having the view to the rear obstructed will
be equipped with audible backup alarms. In congested areas, a flagman may also be
required.
21.4. Before conducting any work from a platform suspended from a crane the
Contractor will submit details of its proposed work platform and rigging method for
Axiall approval. All Cranes used in the hoisting of personnel must be equipped with
anti-two-block devices.
21.5. Prior to using cranes for any work, the Contractor will present to the authorized
Axiall representative a copy of the Annual Inspection Certificate. Cranes will be
restricted to 90% of the capacity shown on the manufacturer's capacity chart when
operating in the stability or tipping portion of the chart. When operating in the
structural integrity area of the chart, the capacity shown on the chart is acceptable.
21.6. Prior to making a critical lift, the Contractor will submit a rigging preplan to the
authorized Axiall representative for review and acceptance. Submittal will be made
no later than 5 working days before the lift is scheduled to be made. The rigging
preplan will include:
21.6.1. Manufacturer, model, and capacity of the crane(s)
21.6.2. Capacity charts
21.6.3. Working radius
21.6.4. Boom length
21.6.5. Weight of load including rigging
21.6.6. How the weight was determined
21.6.7. Size and capacity of rigging hardware (slings, shackles, etc)
21.6.8. Drawing showing the rig and load layout and extent of movement.
21.7. A lift will be considered critical when any of the following conditions exist:
21.7.1. The load exceeds 75% of the crane capacity as the crane is configured to
perform the lift.
21.7.2. Lifts involving more than one crane to handle a common load.
21.7.3. The crane or lifting device is used in an application that deviates from the
manufacturer's recommendations including, but not limited to:
21.7.3.1. Boom configuration not per boom make-up chart
21.7.3.2. Moving a crane with longer boom than recommended
21.7.3.3. Exceeding capacities for restrictions shown on the load chart
21.7.3.4. Lifts are made over process equipment.
22.0 Motor Vehicle Operation
22.1. Observe the speed limits and all posted traffic signs. Maximum plant speed is 15
mph.
22.2. All vehicles must be equipped with seat belts which will be used by both the
driver and passengers while operating the vehicle on Axiall property.
22.3. Equipment will not be fueled while the engine is running. This includes engine
driven equipment such as air compressors, welding rigs, etc.
22.4. Motor vehicles are to be driven to the side of the road and shut down immediately
upon sounding of the plant emergency alarm system. Vehicles' occupants will
evacuate on foot in a cross wind manner to the nearest shelter location. Do not
attempt to restart vehicles until the "All Clear" has been sounded.
22.5. Drivers will sound the vehicle horn prior to backing up unless vehicle is equipped
with a back up alarm.
22.6. Vehicles must not be left running unattended.
22.7. Vehicles may carry only the maximum number of persons it was designed to
accommodate. Passengers may only be transported if they are riding in the cab of
pickup trucks that have adequate seat belts for the number of passengers.
23.0 Electrical
23.1. Contractor will provide ground fault circuit interrupter protection for all cord sets,
receptacles, and electrical tools including connections to generators and equipment
connected by cord and plug for use by employees.
23.2. All Contractor equipment must be maintained outside the minimum clearance
distances for overhead lines, as listed in Table 1 of ASME/ANSI B30.5-1989 “Mobile
and Locomotive Cranes”.
23.3. All electrical equipment and lines will be considered energized until Axiall
electrical authorities verify that it is not.
23.4. All portable equipment shall be ground while in use (i.e. portable generators, etc..
and other equipment, such as during fuel transfers.
24.0 Tool Inspection
24.1. All Contractor-furnished portable tools and equipment (including personal
protective equipment) will be pre-inspected by qualified Contractor personnel.
Equipment will be maintained in safe working order and is subject to Axiall
inspection at any time while on the plant site. Tools and equipment found to be
defective will be tagged and removed from site daily and not returned until all
deficiencies are repaired. Axiall retains the right to prohibit, or restrict, the use of
tools and equipment determined to be in unsafe working condition.
25.0 Fire Protection
25.1. Smoking of tobacco products or use of electronic smoking devices, as defined in
HSP-109, will be permitted only in areas designated by Axiall. Smoking by a
Contractor employee in any non-designated area will be considered cause for
immediate discharge from the plant premises.
25.2. Storage and use of flammable materials will be subject to Axiall approval. Only
safety cabinets and cans that meet OSHA requirements will be used for storing and
dispensing flammable liquids.
25.3. The Contractor will provide a trained and dedicated fire watch for all hot work
activities, as required by the Hot Work Permit.
25.4. Contractor will furnish a sufficient number of fire extinguishers to protect its
work area. Extinguishers will be inspected and sealed.
25.5. Plant fire extinguishers are for emergency use only and may not be removed from
their storage location for fire watch use.
25.6. Oily rags will be kept in fireproof metal containers with self- closing lids, or an
approved equivalent container.
25.7. Any plastic, tarpaulin, or other material used to construct a hut, tent, or similar
protective structure, will be flame retardant.
26.0 Emergency Response
26.1. Axiall has an extensive system for emergency response. Contractors are trained
in the plant emergency response system during General Site Orientation.
26.2. It is Axiall’s policy that in the event of an emergency all personnel should
immediately take shelter and await further direction. It is critical that Contractors
identify their nearest shelter location to be utilized during an emergency.
26.3. The Contractor must designate a competent employee to serve as their Monitor.
During an emergency, the Monitor will take role of their employees and report to the
Main Security Office for accountability purposes.
26.4. To report an emergency condition dial “333" from any in-plant phone from a
“non-plant” phone line dial 685-2500.
27.0 Drug and Alcohol Free
27.1. It is Axiall’s position that all contract employees be drug and alcohol free while
they are on our property and/or equipment and in any way performing a service for
Axiall.
27.2. It is imperative that your employees be drug and alcohol free to insure the
efficient operation of our facilities, as well as conform to the law, and most
importantly, provide for safety and protection of all employees as well as the general
public.
27.3. It is required that each contractor inform his employees of our position regarding
controlled substances, and the contractor’s responsibility to enforce this with his own
employees.
27.4. When a contractor is involved in any of the following, an alcohol and drug test is
required within 24 hours:
27.4.1. OSHA recordable
27.4.2. Vehicle incident
27.4.3. Near Miss where the behavior of the employee or employees contributed to
the incident.
28.0 Drummed and Containerized Material
28.1. All contractors will be charged with the responsibility of handling all drummed and
other containerized material including: receiving, storing, and disposing of all
material received in drums as part of your work. Contractors will be responsible for
labeling and handling the containers in accordance with all applicable laws and
regulations. The contractor additionally will be responsible for clean-up and disposal
of any material that is spilled.
29.0 Temporary Buildings and/or Tents
29.1. All temporary buildings, including but not limited to blast resistant modules or
otherwise known as a c-can, tents, sheds, etc. that are intended to be occupied when
on Axiall property shall be reviewed by the Emergency Response Supervisor and a
Louisiana State Fire Marshals’ Request for Exemption shall be completed and
submitted the Louisiana State Fire Marshal by the Emergency Response Supervisor
before the building can be mobilized.
29.1.1. The Request for exemption (highlighted fields) shall be completed by the
building owner and the form submitted to the Emergency Response Supervisor for
payment request and submission to the Louisiana State Fire Marshals’ office for
approval.
29.1.1.1. No building (i.e. tent, trailer, shack, c-can, etc…) shall not be
mobilized to Axiall without the Request for Exemption being sent to the
Fire Marshal for review AND granted.
29.1.2. See Appendix C for the Request for Exemption, Interpretive Memorandums
2000-11, Exemption Request Form for Temporary Construction Buildings at Job
Site, 2002-01, for temporary buildings, and 2002-02, for tents and canopies in
industrial facilities.
Appendix B
*This form can be completed electronically in ISNetworld. **For login access to ISNetworld: Jake Valenti (225) 685-2617 [email protected]
APPENDIX C
Louisiana State Fire Marshals’
Request for Exemption – (2000-11)
and
Interpretive Memos (2002-01 & 2002-02)