DMP Formwork PanelSystem
Table of Contents
General Instructions 2
Elementary Safety Warnings 2
DMP Panel In Detail 4
Adaptability 6
Connecting Panels 7
Bracing the panels 8
Vertical stacking of panels 9
Form-tie system 10
With DMP outside corner 11
Stripping corners & shaft formwork 12
Plumbing accessories 13
Pouring platforms with single brackets 14
Gael Form Refurbishment Service 17
Product Listing 18
2
• This User Guide is reference
for those who will be working
with the DMP Panel system. It
contains information on how to
set up this system, and on its
correct utilization.
• The functional/technical
instructions, safety warnings
and loading data must all be
strictly observed and complied
with. Failure to comply with
these requirements may cause
accidents, injury and damage.
• The customer must ensure that
the User Guide is available to all
users and that they have been
made aware of it and can easily
access it.
• Always observe all industrial
safety regulations and other
safety rules applying to the
application and utilization of
our products in the country
and/or region in which you are
operating.
• All materials must be inspected
by the customer before use to
ensure that they are in perfect
condition. Any components
that are damaged, deformed,
or weakened due to wear,
corrosion or fatigue, must not
be used.
• DMP Formwork panels,
products and systems must be
set up in the correct manner to
ensure all loads are transferred
as per intended use.
• The stability of all components
and assemblies must be
ensured during all phases of the
construction work.
• Provide safe access for those
using the formwork.
• Do not exceed the permitted
fresh-concrete pressures.
Excessively high pouring rates
lead to formwork overload,
cause greater deflection and
risk causing breakage.
• Do not strike the formwork
until the concrete has reached
sufficient strength and have
been given the order for the
formwork to be struck.
• When stripping the gang-form,
never use the crane to break
concrete cohesion. Use suitable
tools such as timber wedges or
a special pry-bar.
• When striking the formwork,
do not endanger the stability
of any part of the structure, or
of any scaffolding, platforms or
formwork that is still in place.
• Observe all regulations applying
to the handling of formwork and
scaffolding.
• Remove any loose parts or
secure them in place.
• All components must be
stored safely.
General Instructions Compliant Utilisation
Elementary Safety Warnings
3
Wall Formwork
Permitted pressure of the fresh concrete: 80kN/m2
• The DMP Panel System is the
ideal framed formwork for
large-area forming using the
crane.
• The high load-bearing capacity
and long lifespan of the DMP
Panel make it highly economical
for all wall-forming tasks.
• The panels can be joined
together at any point around the
frame, quickly and safely, using
the DMP Uni Formwork clamp
or the Adjustable clamp.
• The DMP panels have such
rigidity, you only need 2
form-ties per 2.70 m of panel
height. Any fitting-gaps left
between the panels are very
easy to close. The system
has numerous options for the
optimum length adjustment in
each case.
• DMP Panel System provides
solutions for corners, stop-end
column formwork and wall
junctions.
• Comprehensive range of panel
sizes available.
• Bespoke sizes can also be
manufactured to customer
specifications.
4
Clean concrete surfaces with the thermoplastic sheet
The sheet consists of a combination of a traditional
plywood core and innovative thermoplastic coating.
This combination of materials ensures high numbers
of repeat uses, with superb concrete results every
time.
• High quality concrete finish.
• Less touching-up needed.
• Less cleaning work - the thermoplastic sheet
can also be cleaned using a high-pressure spray
cleaner.
• ●No breaking away of plywood chips, and less water
is absorbed through nail-holes.
• Screwed-on from the rear, so no screw marks are
visible.
DMP Panel In Detail
5
• DMP panel.
• DMP wedge clamp.
• DMP universal waling.
• Diameter 25 m
• 32 mm
• 42 mm
Handy setting recess (insertion point for a pry-bar.)
The integrated handles make the formwork
easier to relocate.
Tie-rods are very easy to insert through the large,
conical form-tie sleeves.
Tie-rods 20.0mm may also be used (up to 80 kN/ m2).
Only 2 form-ties are needed for every 2.70 m of
panel height.
Quick Assembly of waling Components
Form-tie sleeves
Setting recess
Handles
6
A 12.3cm
B DMP wedge clamp
C Squared timber
D Formwork sheet
E DMP Panel
Timber make up
The DMP panel system also allows for simple timber
make ups. The universal waling and wedge clamp
make it simple to join the panels to squared timbers
and ply sheets.
With universal adjustable clampSelf-aligning inter-panel connections and make up
The multifunction clamp jaw profile gives a
continuous clamping pressure on the panel profile;
meaning no additional bracing is required when
stacking panels up to 4m.
Joining the panels using the universal adjustable
clamp provides additional bracing of the gang-form
(as the clamp bears directly onto the profile).
More functions Inter-panel joints
Schematic representationAdaptability
• When used with the DMP panel system
permitted tensile force: 15.0 kN
permitted shear force: 9.0 kN
permitted moment: 0.9 kNm
Universal adjustable clamp:
Make up to 15 cm
7
The universal formwork clamp & universal adjustable clamp
• Create fast, self-aligning and tension-proof joints.
• Have no loose parts.
• Are hard wearing for site use.
• Can be fixed using only a hammer.
Quick panel connectionsWith universal formwork clamp
The continuous profile in the panel frame means that
panels can be clamped together at any point.
Connecting Panels
• When used with the DMP panel system
permitted tensile force: 15.0 kN
permitted shear force: 6.0 kN
permitted moment: 0.5 kNm
Universal formwork clamp:
Height of Panel Number of Clamps
1.35 m 2
2.70 m 3
3.30 m 3
Upright Panels
Height of Panel Number of Clamps
0.30 m 1
0.45 m 1
0.60 m 2
0.90 m 2
1.35 m 2
Horizontal Panels
8
DMP universal waling
When used with DMP panel system
Permitted moment (for vertical stacking of panels): 5.0
kNm.
Due to the max. tensile load of 14 kN in the waling
profile, even stiffer components such as multi-purpose
walings Ws10 Uni Waling are also subject to: Permitted
moment 5.0 kNm.
With closures, the universal walings bring the gang-
forms firmly into alignment and transfer the form-tie
forces to the framed panels. Using additional universal
walings gives gangforms better rigidity, especially in
higher vertically stacked configurations. This makes
it possible to pick up and set down large gang-forms
by crane without any problems. The additional universal
walings are also useful for transferring the loads from
platforms.
Note: Instead of the universal waling, it is also possible to
use a Multi-purpose waling.
Bracing the panelsDMP universal waling
How to attach using the universal wedge clamp
A DMP universal waling
B Universal wedge clamp
A DMP universal waling
C DMP Universal fixing bolt
D GF Plate
Using the DMP universal fixing bolt and Super- plate
9
Formwork heights up to 4.05 m
On each inter-panel joint, 2 multi-function clamps are attached for each
panel (max. 1.35 m).
Formwork heights up to 5.40 m
On each inter-panel joint, 1 universal waling and 2 Universal adjustment
clamps are attached for each panel (max. 1.35 m).
Formwork heights up to 8.10 m
On each inter-panel joint, 1 universal waling and 2 universal adjustment
clamps are attached for each panel (max. 1.35 m).
Positions of the interconnecting and form-tie components and accessories needed for:• Lifting and setting down
• Crane-handling
• Platform loads
• Pouring
Rules for vertical stacking of panelsWith universal adjustment clamp
Vertical stacking of panels
permitted tensile force: 15.0 kN
permitted shear force: 6.0 kN
permitted moment: 0.5 kNm
Universal formwork clamp:
permitted tensile force: 15.0 kN
permitted shear force: 9.0 kN
permitted moment: 0.9 kNm
Values apply only when mounted on profile
Universal adjustment clamp:
With universal formwork clamp.
A Form-tie 15.0 mm
+ plate 15.0
B Universal Formwork
Clamp
C Universal Adjustment
Clamp
D DMP universal waling
E DMP wedge clamp
10
A Tie-rod 20.0mm
B GF Plate 20.0
C Plastic tube 32mm
D Universal cone 32mm
A Tie-rod 15.0mm
B GF Plate 15.00
C Plastic tube 22mm
D Universal cone 22mm
The “Plastic tubes 22 mm” that are left behind in the
concrete are sealed off with Plugs 22 mm.
In general:
Fix a form-tie in every form-tie sleeve that is not
covered over by a super-plate.
Always tie in the bigger (wider) of the two panels.
For exceptions, see the sections headed “Length
adjustment using closures” and “Vertical stacking
of panels”.
Form-tie system 15mm
Form-tie system 20.0
For high formwork pressures of up to 80 kN/m2,
use the Form-tie system 20.0 mm.
Seal off uneeded form-tie sleeves with
Universal plugs.
Form-tie systemPlacing form-ties in the frame profile
Permitted load with safety factor
of 1.6: 120 kN
Permitted load to DIN 18216: 90 kN
Tie-rod 15.0mm:
Permitted load, allowing a 1.6:
1 factor of safety: 220 kN
Permitted load to DIN 18216: 150 kN
Tie-rod 20.0mm:
Only use approved tie-rodsNever weld or heat tie-rods.!
11
The DMP outside corner is an easy way of forming corners.
With DMP outside corner
A DMP panel
B DMP outside corner
C DMP wedge bolt
D DMP tensioning wedge
a) 40 cm
b) 30 cm
A DMP outside corner
B DMP inside corner
C DMP Universal Formwork Clamp
D DMP Universal Adjustable Clamp
E DMP Universal waling
F DMP wedge clamp
G Fitting timber
H DMP panel 0.60m
Height of outisde corner Number of Clamps
1.35 m 4
2.70 m 8
3.30 m 10
Number of universal formwork clamps needed:
b
For concrete pressures of over 60 kN/m2 or wall
thicknesses of over 40 cm, wedge bolts and
tensioning wedges must be used instead of
quick-acting clamps.
12
Shaft formwork with Stripping corner
The DMP stripping corner is
manufactured specifically for use
with shaft formwork. With the
DMP stripping corner, the entire
DMP formwork unit is detached
from the wall, in one piece, and
repositioned with the aid of a
DMP lifting hook and a
four-part lifting tackle.
Vertically stacking the Stripping corner:• Pull out the coupling bolt (A).
• Manoeuvre the Stripping corner (B) into place so that it is flush with
the one below it.
• Push the coupling bolt (A) back in.
• Bolt the Stripping corners together with 2 hex- agonal bolts M16x45 (C).
Mounting the DMP stripping spindle:• ●Place the spindle (A) on the push-rod (C).
• ●Position the nut (D) between the holes in the push-rod and bolt in
place with the fastening clamp (B).
Operating the spindle:• ●Stripping = Turn the nut anti-clockwise.
• ●Erecting = Turn the nut clockwise.
In order to obtain the full available stripping- play, make sure that the DMP universal formwork clamp are mounted at staggered heights (i.e. not opposite one another).
Stripping corners & shaft formwork
Height of the Stripping Number of Clamps
1.35 m 4
2.70 m 6
3.30 m 8
Number of DMP universal formwork clamp needed:
A DMP stripping corner
B DMP stripping spindle
Product features:
• No negative impression in the
concrete.
• Formwork erection and stripping
function integrated in the inside
corner.
• Using the Stripping spindle.
• With no need for the crane.
• The entire shaft formwork is
repositioned in one piece.
13
Formwork height (M)
Panel strut Europrop 20 550/ Adjustable plumbing strut340 540
4. 1*
5. 1
6. 1 1
7. 1 2
8. 1 1
Max. anchoring load: 153.5 kN
Number of struts per 2.70m width of gang-form
Fixing to the ground
Anchor the plumbing
accessories in such a way
as to resist tensile and
compressive forces.
A ø 26 mmB ø18 mmC ø 28 mmD ø 18 mmE Slotted hole
ø 18x38mmF ø 35 mm
* Up to a height of 3.30 m, the spacing of the props
can be extended to 4.05 m apart.
The values given here apply up to a height of 8 m
above the surrounding ground. For heights of more
than 8 m, the correct spacing of the props must be
calculated as required by the higher wind loads.
Plumbing accessories
IMPORTANT NOTE: The formwork elements must be held stable in every phase of the construction work! Please observe all applicable safety regulations.
!
Connection in the waling profile
NOTE: Every gang-form must be supported by
at least 2 panel struts.
Example: Where the formwork height is 7.20 m,
the following are needed for every 5.40 m wide
gang-form:
• 2 Panel struts 340
• 4 Panel struts 540
Follow the manufacturer’s applicable
fitting instructions.
Required load-bearing capacity of alternative dowels: min. 13.5 kNPanel struts, Europrop
20 550 and Adjustable plumbing struts
Secure the elements against wind loads, and make it
easier to plumb and align the formwork.
14
The DMP brackets 90 and/or DMP GF platforms
enable you to assemble pouring platforms that can
easily be mounted by hand.
Preconditions for use:Only fix the pouring platform onto formwork
constructions that are sufficiently stable to transfer
the expected loads.
Shore the formwork in a windproof manner when
erecting it and when it is temporarily placed in the
standing position.
Ensure that the formwork gang has sufficient stiffness.
Observe all applicable safety regulations.
DMP bracket 90
With the DMP bracket 90, pouring platforms
with a platform width of 90 cm can
be assembled.
b) 87 cmh) 103 cm
Pouring platforms with single brackets
Permitted live load: 1.5 kN/m2 (150 kg/m2)
Load Class 2 to EN 12811-1:2003 Max.
influence width: 2.00 m
15
Using Scaffolding tubes
Tools: Fork spanner 22 for mounting the
couplers and scaffolding tubes.
A Scaffold tube connector
B Scaffolding tube 48.3mm
C Screw-on couplers 48mm 50
D Hexagon screw M14x70 + hexagon nut M14
(not included in scope of supply)
Deck-boards and guard- rail boards:
Per 1 metre length of platform, 0.9 m2 of deck-
boards and 0.6 m2 of guard-rail boards are
needed (in-situ).
Plank thicknesses for support centres of up to
2.50 m:
• Deck-boards min. 20/5 cm.
• Guard-rail boards min. 20/3 cm.
Fastening the deck-boards:
With 5 square bolts M 10x120 per bracket (not
included in scope of supply).
16
A DMP bracket 90
B Spring cotter
C Wedge bolt
POSSIBLE WAYS OF FIXING
In the frame profile
In the cross profile
In the cross profile on horizontal panels
C
A
B
B
A
17
Gael Form Refurbishment ServiceSo that your formwork is in “top form” for its next assignment
Inspecting, cleaning and
maintaining your DMP framed
formwork - all tasks that Gael
Forms Reconditioning Service
will be pleased to take off your
hands. Its highly qualified staff and
special equipment will quickly get
your formwork back in top form -
quickly and economically.
The advantage for you: You always have formwork
that is ready for use, and also
extend the service life of your
equipment.
What’s more: It is only with well-
maintained formwork that you
will achieve the desired quality of
concrete surface.
In our modern plants, your
formwork will be carefully
cleaned using energy-saving
and environmentally sound
technology.
The panels are then inspected for
damage and dimensional accuracy
and overhauled where necessary.
Any damaged form-facing is
repaired, or - if necessary replaced.
19
21
23
25
www.gaelform.comwww.gaelform.com
300321
ABOUT US
Gael Form is a leading international manufacturer and distributor of high-quality new and used formwork solutions used within the global construction industry.
We proudly operate from a 20-acre state-of-the art facility, where our products are manufactured and shipped globally to 3 continents and are used across a wide variety of infrastructure projects such as high-rise buildings, stadiums, bridges, tunnels, airports, seaports, mines and power plants.
At Gael Form Ltd, we pride ourselves on being a Guaranteed Irish company. This means that all of our formwork panel products and systems are manufactured in Ireland. All products are rigorously tested and certified to industry standards.
HEAD OFFICEBallivor,
Co. Meath,C15 HK09.
P:+353 (0) 46 954 6210
UK OFFICEUnit 2, Beckingham Business Park,
Beckingam Street, Tolleshunt Major,
CM9 8LZ, United Kingdom. P: +44 (0)1621 868 329