~ RE F I NE Rf A BAL BOA REFERENCE DOCUMENTS FOR REFINERiA BALBOA EXECUTION PROJECT OWNER I CONTRACTOR DIVI ION OF RESPONSIBILITIES Approved by: Date Sign: For mato [dd-rnrn-afio] Reviewed by : Date Sign: A.M. CALERO Formato [dd-rnrn-afio] Prepared by : Date Sign: A.M. CALERO Formato [dd-rnrn-afio] August, 2008

Transcript of Division of Responsabilities

Page 1: Division of Responsabilities

8/4/2019 Division of Responsabilities

http://slidepdf.com/reader/full/division-of-responsabilities 1/9

~

R E F I N E R fA B A L B O A

REFERENCE DOCUMENTS FORREFINERiA BALBOA EXECUTION PROJECT

OWNER I CONTRACTOR DIVISION OF

RESPONSIBILITIES

Approved by: Date Sign:

Formato [dd-rnrn-afio]

Reviewed by: Date Sign:

A.M. CALERO Formato [dd-rnrn-afio]

Prepared by: Date Sign:

A.M. CALERO Formato [dd-rnrn-afio]

August, 2008

Page 2: Division of Responsabilities

8/4/2019 Division of Responsabilities

http://slidepdf.com/reader/full/division-of-responsabilities 2/9

DIVISION OF RESPONSABILITIES

CONTENT

DISTRIBUTION LIST 3

REVISION STATUS 3

LIST OF ABBREVIATIONS 4

1.0 DEFINITIONS 5

DESCRIPTION 5

2.0 PROJECT SERVICES 5

3.0 MOBILIZATION & SITE SERVICES 7

4.0 EPC 7

5.0 QUALITY ASSURANCE AND QUALITY CONTROL 8

6.0 SAFETY, HEALTH & ENVIRONMENT (SHE) 9

7.0 MISCELLANEOUS SUPPLlES 9

Grupo Alfonso Gallardo. Refinerfa Balboa, S. A

REFERENCE DOCUMENTS FOR REFINERiA BALBOA EXECUTION PROJECT Rev. O. August 2008 Page 2 of 9

Page 3: Division of Responsabilities

8/4/2019 Division of Responsabilities

http://slidepdf.com/reader/full/division-of-responsabilities 3/9

DIVISION OF RESPONSABILITIES

This document is one of a series of Business Controls to be adopted by Refinerfa Balboa S.A as

reference for REFINERfA BALBOA EXECUTION PROJECT.

Comment and feedback from users of this document is encouraged, by means of a Proposal for

Modification for this document.

Copyright

Copyright @ 2001, Refineria Balboa S.A

This document is the property of Refinerfa Balboa, S.A. Circulation is

restricted to Refinerfa Balboa S.A and its designated associates,

contractors and consultants. It must not be copied or used for any purpose

other than which it is supplied, without the express written authority of

RBSA.

Except where provided for purposes of contractual requirements, RBSA

disclaims any responsibility or liability for any use or misuse of thedocument by any person and makes no warranty as to the accuracy or

suitability of the information to any third party.

Symbols:

Denote a reference document

DISTRIBUTION LIST

Copy I English Spanish I User LocationNumber

IIIEF: Electronic distribution

P: Hard Copy (Paper) distribution.

REVISION STATUS

IssueDate of Next I Change Details Prep. Sign I App. SignRev. Rev. Description

0

August August I First IssueOriginal I008 2012 IssueI I

I IThe organization of PMC must review and adapt this document to incorporate as complement into

the information to be provided to FEED/EPC CONTRACTORS for REFINERfA BALBOA

EXECUTION PROJECT. These documents establish the scope of work and requirements that

contractors should be considered for during the development phases of ENGINEERING,

PROCUREMENT, CONSTRUCTION, PRE-COMMISSIONING, COMMISSIONING, START-UP,

NORMAL OPERATION Period and PERFORMANCE TESTS, according EPC CONTRACTS.

Grupo Alfonso Gallardo. Refinerfa Balboa, S. A

REFERENCE DOCUMENTS FOR REFINERiA BALBOA EXECUTION PROJECT Rev. O . August 2008 Page 3 of 9

Page 4: Division of Responsabilities

8/4/2019 Division of Responsabilities

http://slidepdf.com/reader/full/division-of-responsabilities 4/9

DIVISION OF RESPONSABILITIES

LIST OF ABBREVIATIONS

C Contractor

RB OWNER

E Engineering

P Procurement

Ct Construction

Cm Commissioning

SU Start-Up

NO Normal Operation Period

PT Performance Tests

Grupo Alfonso Gallardo. Refinerfa Balboa, S. A

REFERENCE DOCUMENTS FOR REFINERiA BALBOA EXECUTION PROJECT Rev. O. August 2008 Page 4of9

Page 5: Division of Responsabilities

8/4/2019 Division of Responsabilities

http://slidepdf.com/reader/full/division-of-responsabilities 5/9

DIVISION OF RESPONSABILITIES

1.0 DEFINITIONS

ENGINEERING

Engineering, Design and Coordination work including preparation of purchase specifications,

evaluation of bids and review and approval of vendor drawings.

MATERIAL & SERVICES SUPPLY

The supply of an item, system or service and accountability for all associated costs. This includes

responsibilities such as manufacture and associated studies, soliciting bids and procurement

where applicable, scheduling, ordering, quality control, and inspecting

SITEWORK & ERECTION

Responsible for the unloading at site, proper erection installation, cleaning, testing and other work

and services.

COMMISSIONING, START-UP, NORMAL OPERATION PERIOD AND PERFORMANCE TESTS

The provision of technical advisors (TA's) for erection commissioning, start-up, normal operation

period and performance testing of equipment supplied and the overall management, direction

and execution of the facilities commissioning, start-up, normal operation period and performance

testing activities

DIVISION OF RESPONSABILITIES

DESCRIPTION E P Ct I Cm I SU I NO I PT NOTES

2.0 PROJECT SERVICES

2 . 1 PROJECT MANAGEMENT C C C C C C C

2 . 2 PROJECT CONTROLS C C C C C C C

2 . 3 INSURANCES

A Employer C C C C C C C

B General-Civil C C C C C C C

C Vehicles-Civil C C C C C C C

D Construction All Risk C/RB C/RB C/RB C/RB C/RB

2 . 4 FINANCIAL INSTRUMENTS

A Performance Bond C C C C C C C

B Labor Bond C C C C C C C

2 . 5 DETAILED DESIGN

ABasic Engineering Val idat ion by

CContractor

BMain Contractor Offices, Computers,

C COffice Services

B Surveys & Studies

1 IDetailed Site Surveys C

Grupo Alfonso Gallardo. Refinerfa Balboa, S. A

REFERENCE DOCUMENTS FOR REFINERiA BALBOA EXECUTION PROJECT Rev. O. August 2008 Page 5 of 9

Page 6: Division of Responsabilities

8/4/2019 Division of Responsabilities

http://slidepdf.com/reader/full/division-of-responsabilities 6/9

DIVISION OF RESPONSABILITIES

2 Soil Studies C

C Design

1

Calculations, Studies,

CDescriptions

2Drawings, Diagrams, Indexes,

CLists, Details

3 Data Sheets and Specifications C

4 As Built Drawings C

5 Data / Project Books C

6Operating and Maintenance

CManuals & Catalogs

7Vendor and Subcontractor

C C C C C C CDrawings & Specs

0 Purchasing Support by Engineering

1 Bills of Material C

2RFQ & Tech Evaluation for

CI purchase orders

3RFQ & Tech Evaluation for

CSubcontracts

4Review & Approval of Vendor

CDrawings

5 Support to Expediting C

6 Support to Inspection Services C

2.6PURCHASING CONTRACTING,

LOGISTICS, PERMITS

AVendor and Subcontracts Approved

RB RB RB RB RB RB RBContractor may propose

List alternates for approval

BRequisi tioning / Commercial Bid

C C C C C CEvaluations / Order Placement

C Supplier and Subcontractor Payments C C C C C C

0Expediting of Suppl iers and

C C C C C CSubcontractors

EInland Transportation for Foreign

CPurchases (Country of Origin)

FOcean/Air Freight for Foreign

CPurchases

GPre-Shipment Inspection for Foreign

N/APurchases

Applies in case of off-

H CAU List and Customs Clearance C shore equipment and

material by Contractor

I Duties RB

J Permits by Contractor C C C C C C

KPermits - Land, Affectation of Natural

RB RB RB RB RBResources

L Permits - Construction, Hot Work C C C C C

M Access to Site RB RB RB RB RB

NRight of Way/Clearance for All Plant

C C C C C CEquip and Material to Site

0Transportation from Port of Import to

C C C C C CSite

P

Unloading and Receiving Equipment

C C C C Cand Material (at s ite)

Grupo Alfonso Gallardo. Refinerfa Balboa, S. A

REFERENCE DOCUMENTS FOR REFINERiA BALBOA EXECUTION PROJECT Rev.O.August2008 Page 6 of 9

Page 7: Division of Responsabilities

8/4/2019 Division of Responsabilities

http://slidepdf.com/reader/full/division-of-responsabilities 7/9

DIVISION OF RESPONSABILITIES

QReceiving, Inspecting, Checking &

C C C C CInventory (Including OS&D}

RAll Req'd Indoor/Outdoor Storage of

C C C C C CEquip' & Material

S Local Registration Fees, License, Etc. C C C C C C

TTransport of Damaged/Defective

C C C C C CMaterial for Rep,air

2 . 7 TAXES

A Sales & Use Taxes C C C C C C

B Value Added Taxes (IVA) C C C C C C

C Corporate Taxes C C C C C C

0 Municipal Taxes C C C C C C C

2 . 8 TRAINING OF OWNER PERSONNEL

A Training Manual C C C C C

B Training Facility and Materials C C C C C

COwner O&M Personnel salaries,

RB RB RB RB RBTransportat ion & Living Expenses

2 . 9 FACTORY TEST REPORTS C C C C C C

2 . 1 0 WARRANTY SERVICES C C C C C C

3.0 MOBILIZATION & SITE SERVICES

3 . 1 CONSTRUCTION PLAN, UTILITIES PLAN C C C C C C

3 . 2 SITE SECURITY & SUPERVISION C C C C C C

3 . 3 SITE MEDICAL SERVICES C C C C C C

3 . 4 CONSTRUCTION TOOLS & EQUIPMENT C C C C C C

3 . 5 SITE SANITARY FACILITIES C C C C C C

3 . 6 SITE TEMPORARY FACILITIES C C C C C C

3 . 7 OWNER OFFICES AT SITE C C C C C C

3 . 8 SITE MEALS C C C C C C

3 . 9 SITE MOBILIZATION & DEMOBILIZATION C C C C C I C

3 . 1 0 SITE FUELS & LUBRICANTS FOR C C C C C CCONSTRUCTION EQUIPMENT

3 . 1 1SITE CLEANLINESS, DUST CONTROL,

C C C C CGARBAGE & DEBRIS

4.0 EPC

4.1SITE FACILITIES, OTHERS - LABOR &

MATERIAL

ASite Preparation including Clearing/Grubbing,

C C C C C C CEarthwork

B Site Improvements C C C C C C C

C Underground Drainage C C C C C C C

0 Foundations C C C C C C C

Grupo Alfonso Gallardo. Refinerfa Balboa, S. A

REFERENCE DOCUMENTS FOR REFINERiA BALBOA EXECUTION PROJECT Rev.Q,August2QQ8 Page 7 of 9

Page 8: Division of Responsabilities

8/4/2019 Division of Responsabilities

http://slidepdf.com/reader/full/division-of-responsabilities 8/9

DIVISION OF RESPONSABILITIES

EMiscellaneous Steel, ladders, platforms,

C C C C C C Csupports

F Erection C C C C C C C

G Piping Systems C C C C C C C

HElectrical Systems incl Grounding, Cathodic

C C C C C C CProtection, Lighting

I Painting C C C C C C C

J Fire-Fighting System C C C C C C C

4 . 2 CONSTRUCTION SUPERVISION C C C C C

PRECOMMISSIONING, COMMISSIONING,

4 . 3 START-UP (SU), NORMAL OPERATION C C C C C

AND PERFORMANCE TESTS

A Fuel

B Operators C C C C C

C Supervision C C C C C

D Craft Labor C C C C C

E Electrical Power C RB RB RB RB

FStandard and Special Test Instruction, Tools, &

C C C C CEquipment

G Instrumentation Calibration C C C C C

HPrecommissioning, Commissioning, SU, NO,

C C C C CPT Consumables

IConstruction, Precommissioning and

C C C C CCommissioning, SU, NO, PT Spares

J Documentation, Tests, Data, & Reports C C C C C

K Equipment & System Walk down and Turnover C C C C C

L Punch List Creation and Maintenance C C C C C

4 . 4 TESTING

A Procedures C C C

B Fuel C C C

C Operators C RB RB RB RB

D Supervision & Craft Labor Support C C C C C

5.0 QUALITY ASSURANCE AND QUALITY CONTROL

A Quality Assurance/Quality Control Plans C C C C C C C

BVendor Shop Inspection for Purchased

CMaterials, Equip, Services

C Positive Materials Identification C C

D Control of Special Processes C C C C C C

E Test Control C C C C C C

FUse, Control and Calibration of Tools,

C C C C C CMeasurement Devices, Equip

Grupo Alfonso Gallardo. Refinerfa Balboa, S. A

REFERENCE DOCUMENTS FOR REFINERiA BALBOA EXECUTION PROJECT Rev.O.August2008 Page 8 of 9

Page 9: Division of Responsabilities

8/4/2019 Division of Responsabilities

http://slidepdf.com/reader/full/division-of-responsabilities 9/9

DIVISION OF RESPONSABILITIES

G Nonconformance and Corrective Action C C C C C C C

H Documentation C C C C C C C

IQuality Audits C C C C C C C

6.0 SAFETY, HEALTH & ENVIRONMENT (SHE)

A SHE Plan C C C C C C C

B SHE Procedures C C C C C C C

C SHE Execution C C C C C C C

0 SHE Audits C C C C C C C

E SHE Documentation C C C C C C C

7.0 MISCELLANEOUS SUPPLIES

A Site Vehicles C C C C C

B Chemicals and Gases (Initial Fill) C C C C C

C Oils and Greases (Initial Fill) C C C C C

0 Other Consumables C C C C C

Grupo Alfonso Gallardo. Refinerfa Balboa, S. A

REFERENCE DOCUMENTS FOR REFINERiA BALBOA EXECUTION PROJECT Rev. o . August 2008 Page 9 of 9