DITS Project – M. Houry 27 th of april Y07 DITS PROJECT SCHEDULE.

6
DITS Project – M. Houry 27 th of april Y07 DITS PROJECT DITS PROJECT SCHEDULE SCHEDULE

Transcript of DITS Project – M. Houry 27 th of april Y07 DITS PROJECT SCHEDULE.

Page 1: DITS Project – M. Houry 27 th of april Y07 DITS PROJECT SCHEDULE.

DITS Project – M. Houry 27th of april Y07

DITS PROJECT DITS PROJECT SCHEDULESCHEDULE

Page 2: DITS Project – M. Houry 27 th of april Y07 DITS PROJECT SCHEDULE.

DITS Project – M. Houry 27th of april Y07

A Project Management Office has been established in the DITS A Project Management Office has been established in the DITS project organizationproject organization

DITS project organization.

The PMO provides a help in terms of : Schedule, Human ress., Risk, Cost, Communication, Reviewing Management

Mean Goals : Built ONE Work-Plan based on Work-Packages What you must do Periodic progression measurements

Analysis of shifts & risks anticipation Appropriate corrections or treatments

Project LeaderE. Tsitrone

Deputy Project LeaderC. Brosset

General BoardCoEx (DRFC)CCAT (DRFC)

…..

Advisory BoardEuropean Experts

EU PWI TF, CNRS, ....

WP1 – Particle Balance ExperimentsWorkPackage Leader

B. Pégourié (DRFC)

WP2 - TPL DismantlingWorkPackage Leader

F. Samaille (DRFC)

WP3 – TPL analysisWorkPackage Leader

C. Brosset (DRFC)

WP4 – Satellite ProgrammesWorkPackage Leader

E. Tsitrone (DRFC)

Erosion RedepositionE. Gauthier

IRR. Reichle

CFPJ. Schlosser

Test SATIRJ. Schlosser

DétritiationH. Roche

Management TeamProject Time & Ressource Management (M. Houry)

Project Risk, Cost & Quality Management (L. Jourd’Heuil)Project Safety Management (K. Zunino)

Management TeamProject Time & Res. Management

Project Risk, Cost & Quality ManagementProject Safety Management

Page 3: DITS Project – M. Houry 27 th of april Y07 DITS PROJECT SCHEDULE.

DITS Project – M. Houry 27th of april Y07

The DITS schedule is made of 6 Work-Packages

WP0 - Management Time, cost, human resources, quality, risk, safety, communication, reviews

WP1 – Particle balance experiments D2 Plasma experiments for TPL loading

WP2 – TPL Dismantling Extraction – Operations – Mounting

WP3 – ANALYSIS Preparations and analysis on the TPL, fingers, tiles and samples

WP4 – SATELLITE PROGRAMS IR program (R. Reichle) PFC (J. Schlosser) Detritiation (H. Roche) DUST (S. Rosanvallon)

WP5 – CO ACTIVITIES Acoustic sensors (X. Courtois)

Tore Supra Summer Shut-down

Tore Supra Experimental program

Page 4: DITS Project – M. Houry 27 th of april Y07 DITS PROJECT SCHEDULE.

DITS Project – M. Houry 27th of april Y07

Work Package 1 & 2 : TPL loading and Dismantling

Sept.MaiMaiMay JuinJuinJune Juil.Juil.July. AoûtAoûtAug.

Removing ICRH(Q1) & TPL(Q6A)

TPL Loading : 24/05 to 07/06

Fingers exchangeSpare Fingers validation

Qualification tests

TPL & ICRH installing

3D Cartography Meas.

WP1

WP2

WP3

Tore Supra Summer Shut-down for maintenance operationsTore Supra Summer Shut-down for maintenance operations

Page 5: DITS Project – M. Houry 27 th of april Y07 DITS PROJECT SCHEDULE.

DITS Project – M. Houry 27th of april Y07

WP3 : Analysis

3D Cartography on fingers

TPL back in TS

Assembly - tests 18/07

April May June July Aug. Sept.

3D cartography measurements

Structure

22/06

Optics04/07

3D Cartography on sector 02/08 24/08

Page 6: DITS Project – M. Houry 27 th of april Y07 DITS PROJECT SCHEDULE.

DITS Project – M. Houry 27th of april Y07

WP3 : Preparation for analysis WP3 : Preparation for analysis Fingers – Tiles extraction – Samples cuttingFingers – Tiles extraction – Samples cutting

Aug. Sept. Oct.

Samples characterization

Fingers activity controlSafety authority agreement 13/09

Tiles dismantling

26/09

Tiles cutting Samples 11/10

3D Cartography

Ready for analysis

22/10