Distribution List - ER:

1. AGM (PE-Electrical) NTPC(Darlipalli, North Karanpura, Nabinagar-I &II) EOC Complex, A-8A, Sec-24, Noida, UP-201301 Email:[email protected]; [email protected] Ph: 9650991067

2. Principal Chief Engineer cum Secretary Power Department Government of Sikkim Kazi Road, Gangtok, Sikkim

Email: [email protected]; [email protected] Mob: 9733032266

3. General Manager Monnet Ispat & Energy Limited 11, Monnet House, Masjid Moth, Grater Kailash, Part-II, New Delhi – 110 048 Email : [email protected]

Mobile : +91 9560509283

4. Director, Madhya Bharat Power Corporation Ltd 1

st Floor, Vanijya Bhawan,

Devendra Nagar Square, Jail Road, Raipur-492001 Mobile: 9810432623

Phone : 0771- 2214210 Email : [email protected]; [email protected]; [email protected]

5. Director & SPV Head Lanco Babandh Power Pvt. Ltd. Plot No. 397, Phase-III Udyog Vihar, Gurgaon-122 016 Phone : 0124-4691101 Mobile : 8800090621 Email : [email protected]

[email protected]

6. Director, Sikkim Hydro Power Ventures Ltd, 5th Floor, Orbit Plaza, New Prabhadevi Road, Prabhadevi, Mumbai- 400025 Email: [email protected]; [email protected] Mob: 7709042956

7. Sr. Manager Nabinagar Power Generation Co. 1

st Floor, Vidyut Bhavan-II,

Bailey Road, Patna-800021 Email: [email protected] Mob: 0612- 2504010

8. SPV Head, Lanco Teesta Hydro Power Limited Plot No. 397, Udyog Vihar – Phase III, Gurgaon – 122016 Email : [email protected] Phone : 0124-4741475 Mobile : 9599934386

9. Chairman Orissa Power Generation Corporation Ltd. (OPGC) Zone-A, 7th Floor, Fortune Towers Chandrasekharpur, Bhubaneswar – 751023 Odisha Ph : 0674-2303765- 66, 09338715428 Fax : 0674-2303755-56 Email : [email protected]; [email protected]

10. Chief Operating Officer KVK Nilachal Power Pvt Limited 6-3-1109/3, 3

rd Floor, Navabharath Chambers,

Raj Bhavan Road, Somajiguda Hyderabad: 500 082 Contact No: 040 66225111 Email:[email protected]; [email protected] [email protected]; [email protected] Mob: 8790944466

11. CEO Sneha Kinetic Power Projects Pvt. Ltd. Sonam Complex, Jeevan Theng Marg Development Area, Near Little Pixel International School, Gangtok, Sikkim-737 101 Email : [email protected]

Mob: 9958355966

12. President, Hydro Gati Infrastructure Bhasmey Power Pvt. Ltd. 14/19/2 Old Delhi Gurgaon Road, Opp. Heera Public School, Samalkha, New Delhi - 110037. Email: [email protected]

13. Sr. Vice President Teestavalley Power Transmission Ltd 2nd Floor, Vijaya Building 17, Barakhamba Road, New Delhi-110001 Email: [email protected] Mob: 9958008265

Minutes of 18th

JCC of Eastern Region held on 28.09.2018

Page 1 of 29

Minutes of 18th Joint Co-ordination Committee meeting of Generation Projects granted Connectivity/LTA

in Eastern Region (ER) held on 28.09.2018 at POWERGRID, Gurgaon

1. The 18th Joint Co-ordination Committee meeting of generation projects in Eastern Region was held at POWERGRID Office, Gurgaon on 28th Sep, 2018. The list of participants of the meeting is enclosed at Annexure-I.

2. After welcoming the participants, it was informed that Minutes of the 17th Meeting of the Joint Co-ordination Committee in Eastern Region held on 29.06.2017, were issued vide letter ref. no. C/CTU/ER/OA/18JCC dated 10.09.2018. As no observations/comments were received on the minutes, the minutes were confirmed as circulated. CTU informed following regulatory provision compliance by all applicants/ grantee:

a) It was re-iterated that JCC forum has been created for co-ordination purposes to attempt matching of generation schedules with the associated transmission system and accordingly, the information given by generation developers/applicants is being taken into cognizance for co-ordination purpose which can be achieved only if the applicant/generation developers provide realistic schedule & other status of generation project /dedicated line. However, for any substantial issue, same may be submitted through official correspondence addressed to CTU, by clarifying the nature of issue to be dealt therein, as per the Regulatory framework. It was further informed that some letters are being sent by LTA customers related to relinquishment which are not clear in the content; therefore it was advised that such communication should strictly follow CERC Regulatory provisions (Regulation 18) specifically regarding notice, mentioning the relinquishment quantum, date of relinquishment and consent for payment of applicable relinquishment charges for which an advisory is also available at www.powergridindia.com >> CTU Open Access.

b) It is pertinent to mention that the BPTAs/LTAAs executed with the generation project developers/companies monitored hereunder provides that if any of the developers fail to construct the generating station/dedicated transmission line or makes an exit or abandons its project, then POWERGRID shall have the right to collect the transmission charges and/or damages as the case may be in accordance with the CERC Regulations, Orders etc. Further, as per the BPTAs/LTAAs, the construction phase bank guarantee submitted by the project developers/LTA customers is also en-cashable in case of adverse progress of individual generations project(s)/unit(s) assessed during the Joint Coordination Committee meetings. It was also informed that in light of a number of recent CERC orders, wherein the Hon’ble Commission has emphasized upon stricter implementation of the various Regulations, Procedures and statutory Agreements, CTU shall assess the progress of various generation projects and take necessary action in terms of the applicable provisions/ clauses of the Regulations/Procedure/Agreements.

c) CTU emphasized that generation developers should ensure completion of their dedicated transmission lines to match with the commissioning of transmission network in order to avoid bottling up of power. It was further stated that interim arrangements through LILO of existing lines were provided only as a contingency measure and the generation developers need to implement

Minutes of 18th

JCC of Eastern Region held on 28.09.2018

Page 2 of 29

the final dedicated transmission system expeditiously as the matter has been very seriously looked into by Hon’ble CERC in Petition no. 34/MP/2014 & 112/TT/2013.

d) Recently in number of cases, generation developers have submitted online additional details in respect of Connectivity (CON-4) only when the generation projects are on the verge of commissioning. Thus, a very short period of time is available for processing and issuance of Connection Offer (CON-5) and subsequent signing of Connection Agreement. As per the CERC Connectivity Regulations/ Detailed Procedure, 2009, the CON-4 details are to be furnished to CTU at least 2 (two) years prior to physical interconnection which may be noted by all the applicants.

e) All information exchanged, discussions/decisions taken in the JCC meeting shall be subject to the CERC Regulations and Detailed procedure made therein.

f) It was noted that some of the generation developers/ applicants had been repetitively not attending the JCC Meetings. All such generation developers/ applicants were requested to attend the future meetings so as to have a better co-ordination. Further, it was also stated that the matter regarding limited participation of the generation developers/ applicants shall be brought to the notice of Hon’ble CERC.

g) All those generation projects that have achieved COD and their respective dedicated transmission lines have also been commissioned, may not be required to attend JCC as the coordination work has already been over. Therefore they are not being called for further JCC meetings (Details of all such generation projects as per Table T1 (i)-(v)).

h) Regarding execution of TSA, it was informed that under the applicable provisions of CERC (Sharing of Inter State Transmission Charges and Losses) Regulations, 2010 and CERC Orders pronounced thereupon, TSA notified under Regulation 13 is the ‘default transmission agreement’ and mandatorily applies to all DICs.

i) It was clarified that in terms of the recent CERC Orders and directions, the liability to pay transmission charges shall commence irrespective of opening of LC and signing of TSA. In default thereof, necessary action in terms of CERC Regulations including curtailment of STOA may be taken. Regardless of the said CERC Orders, all DICs are duty bound to establish payment security mechanism (LC) under Regulation 12 (8) of CERC (Sharing of Inter State Transmission Charges and Losses) Regulations, 2010.

j) Further, it was also brought to the attention of all applicants/ grantees that CERC has pronounced Order in Petition No. 229/RC/2015 wherein inter alia it has been reemphasized that all Designated ISTS Customers (DICs) of ISTS are bound to establish payment security mechanism (LC) and pay transmission charges from the date of commissioning of associated transmission system or scheduled date under BPTA, whichever is later. In case of default in payment of transmission charges and/or maintaining LC, the DICs TSA shall be liable for termination/suspension and shall thus be disabled from injecting/drawing from the ISTS.

Minutes of 18th

JCC of Eastern Region held on 28.09.2018

Page 3 of 29

k) All the LTA customers are advised to clear the consultancy payment liabilities at the earliest towards implementation of bays for termination of dedicated/connectivity lines as deposit work for timely implementation of the same. In case of failure, the generation developers/applicants alone shall be responsible towards any delay in implementation of the bays.

l) A no. of LTA customers are yet to sign the Transmission Service Agreement (TSA) in accordance with CERC Sharing Regulations. It is once again advised that the LTA customers shall sign the TSA at the earliest. List of the generation developers who are yet to sign the TSA is enclosed herewith at Annexure- II.

m) Thereafter, the LTA Customers were requested to update the progress of their generation projects and the discussions are summarised below:

Status of the Generation Projects

HIGH CAPACITY POWER TRANSMISSION CORRIDOR – I

(Phase-I IPPs in Odisha & associated Transmission System)

Sl. No

LTOA / LTA Applicant

LTOA/LTA Quantum

(MW)

Target Beneficiaries Firm

beneficiary

Comm. schedule

(as per 17th

JCC)

Comm. schedule

(as per 18th

JCC)

Dedicated / Connectivity line

& Status Remarks

NR WR ER SR

1.

Monnet Power Company Ltd.

(MPCL) (2x525 MW)

900 300 225 225 150

Not attended

No specific schedule

mentioned

Not attended

Last JCC attended:

12

th JCC held

on 27.03.2017

400kV Monet TPS-Angul Pool

D/c line

(Status as per 17

th JCC)

No specific schedule

mentioned

The developer consistently not attending the JCC meeting since 13

th JCC held on

16.06.2017. Further, no status report has been submitted for 18

th JCC meeting.

Status as per 17

th JCC held on

29.06.2018 is as below: MPCL vide email dated 29.06.2018 informed that MPCL has gone to NCLT as per the NCLT order dated 23.02.2018.

Construction Phase BG of Rs. 45 Cr has been encashed on 26.10.2017 on account of poor progress of the generation

Minutes of 18th

JCC of Eastern Region held on 28.09.2018

Page 4 of 29

Sl. No

LTOA / LTA Applicant

LTOA/LTA Quantum

(MW)

Target Beneficiaries Firm

beneficiary

Comm. schedule

(as per 17th

JCC)

Comm. schedule

(as per 18th

JCC)

Dedicated / Connectivity line

& Status Remarks

NR WR ER SR

project.

PPA for power transfer of 400MW has been signed with West Bengal.

2.

Lanco Babandh

Power Pvt Ltd. (2x660 MW)

1600

800

650

950

150

0 0

Not attended

As per status report dated 27.06.2018:

The project has achieved 60%

overall progress

Uncertain

400kV Lanco TPS -Angul Pool

D/c line + 765/400 kV,

2x1500 MVA ICT along with

associated bays at Angul Pool:

Revalidation of

section – 68 applied

Representative informed in the meeting that the project has achieved 60% overall progress. However, the commissioning has been delayed due to occurrence of force majeure events which has led to cost and time overrun, for which the Company has filed petition with Hon’ble CERC for time extension for commissioning and the matter is being adjudicated.

The promoter and EPC contractor M/s Lanco Infratech Limited (LITL) was admitted to National Company Law Tribunal (NCLT) in Aug. 2017 for Corporate Insolvency Resolution Process (CIRP) process initiated by LITL lenders, at present the work is suspended. LBPL vide letter no. IBPL/OW/010/06092018 informed that their endeavor is for resolution in order to complete the project.

LTA Customer is yet to open LC despite several reminders.

Generation developer has filed

Minutes of 18th

JCC of Eastern Region held on 28.09.2018

Page 5 of 29

Sl. No

LTOA / LTA Applicant

LTOA/LTA Quantum

(MW)

Target Beneficiaries Firm

beneficiary

Comm. schedule

(as per 17th

JCC)

Comm. schedule

(as per 18th

JCC)

Dedicated / Connectivity line

& Status Remarks

NR WR ER SR

Petition No. 38/MP/2016 in Hon’ble CERC for keeping its LTA on abeyance on account of alleged force majeure condition.

Construction Phase BG of Rs. 40 Cr has been encashed on 26.10.2017 on account of poor progress of the generation project. Relinquishment charges are not applicable for relinquished 800MW as per CERC order dated 08.06.2013 in petition no. 118/MP/2012. PPAs for power transfer of 424MW to UP and 350MW to Rajasthan have been signed.

HIGH CAPACITY POWER TRANSMISSION CORRIDOR – III

(Phase-I IPPs in Sikkim)

In 18th ER JCC meeting held on 28.09.2018, Teesta Valley Power Transmission Limited (TPTL) informed that commissioning of 400 kV Teesta-III Kishanganj D/c line is expected by 30.11.2018. With commissioning of this line, the entire LTA system associated with Ph-I and Ph-II IPPs of Sikkim will be commissioned. Accordingly, LTA will be made effective w.e.f. 01.12.2018 subject to commissioning of aforementioned transmission system for all the LTA/LTOA applicants (i.e. PTC India Limited, DANS Energy Pvt. Ltd, Shiga Energy Pvt Ltd, Lanco Teesta Hydro Power Ltd, Gati Infrastructure Pvt. Ltd (Chuzachen), Madhya Bharat Power Corporation Limited, Gati Infrastructure Bhasmey Power Pvt. Ltd).

Minutes of 18th

JCC of Eastern Region held on 28.09.2018

Page 6 of 29

Sl. No.

LTOA / LTA Applicant

LTOA/LTA Quantum

(MW)

Target Beneficiaries Firm beneficiary

Comm. schedule

(as per 17th

JCC)

Comm. schedule

(as per 18th

JCC)

Dedicated / Connectivity line

& Status Remarks

NR WR ER

1.

Lanco Teesta Hydro Power

Ltd, (Teesta-VI) (4x125 MW)

500 0 500 0

U1 - U4: Previously

communicated COD Sep-2020, will get extended as all construction activity on hold,

Uncertain

220 kV Teesta VI- Rangpo D/c Twin Moose Conductor

line under construction

Status: Approvals under section-68 and 164 of Electricity Act, 2003 has been obtained from MoP.

MoEF (Shillong) in-principally approved diversion of forest land for the transmission line. Lanco Teesta Hydro Power Ltd. & Lanco Infratech Ltd.(EPC Contractor) has been referred to liquidation under IBC 2016.

Appropriate action as per BPTA/Regulations as well as insolvency/ bankruptcy laws may be taken.

Project work is not going on as of now.

Representative was informed that LTA will be made effective w.e.f. 01.12.2018 subject to commissioning of 400 kV Teesta-III - Kishanganj D/c line.

2.

Madhya Bharat Power Corporation

Ltd. (Rongnichu) (2x48 MW)

96 56 40 0 Nil U1: 31.03.2020

U2: 31.03.2020

U1: 31.03.2020

U2: 31.03.2020

220kV Rongnichu-Rangpo D/c

Zebra conductor line (7.3 km) :

Nov’18

Representative informed that 25 out of 30 foundations completed, 19 tower erections completed, stringing yet to be started.

Tunnel excavation works have been completed.

Supplementary agreement for bay construction has been signed.

Main plant package has been awarded to CG Electric on 28.02.2017.

Minutes of 18th

JCC of Eastern Region held on 28.09.2018

Page 7 of 29

Sl. No.

LTOA / LTA Applicant

LTOA/LTA Quantum

(MW)

Target Beneficiaries Firm beneficiary

Comm. schedule

(as per 17th

JCC)

Comm. schedule

(as per 18th

JCC)

Dedicated / Connectivity line

& Status Remarks

NR WR ER

Applicant is again advised to sign TSA at the earliest.

Representative was informed that LTA will be made effective w.e.f. 01.12.2018 subject to commissioning of 400 kV Teesta-III - Kishanganj D/c line.

3.

Gati Infrastructure

Bhasmey Power Pvt.

Ltd. (Bhasmey)

(2x25.5 MW)

51 36 15 0 U1: Jun’21

U2: Jul’21 Not attended

132 kV Bhasmey- Rangpo D/c line –

(Under scope of Govt of Sikkim)

The developer neither attended the meeting nor submitted the status update. Status as per 17

th JCC held on

29.06.2018 is as below: Representative informed that there is no further progress in the project due to financial constraints and only 36% project work has been completed. Also informed that dedicated line is under the scope of Govt. of Sikkim and the work is yet to be started.

Representative informed that PPA of 30MW has been signed with West Bengal. In response, CTU informed that LTOA had been granted for NR & WR, thus, introduction of new region (ER) shall require filling of fresh application, as per CERC Connectivity Regulations/ Detailed Procedure, 2009. The same was noted by the developer.

Minutes of 18th

JCC of Eastern Region held on 28.09.2018

Page 8 of 29

Sl. No.

LTOA / LTA Applicant

LTOA/LTA Quantum

(MW)

Target Beneficiaries Firm beneficiary

Comm. schedule

(as per 17th

JCC)

Comm. schedule

(as per 18th

JCC)

Dedicated / Connectivity line

& Status Remarks

NR WR ER LTA will be made effective w.e.f. 01.12.2018 subject to commissioning of 400 kV Teesta-III - Kishanganj D/c line.

PPA for power transfer of 30MW has been signed with West Bengal.

Minutes of 18th

JCC of Eastern Region held on 28.09.2018

Page 9 of 29

(Phase-II IPPs in Odisha)

Sl. No.

LTOA / LTA Applicant

LTOA/LTA Quantum

(MW)

Target Beneficiaries Firm

beneficiary

Comm. schedule

(as per 17th

JCC)

Comm. schedule

(as per 18th

JCC)

Dedicated / Connectivity line & Status

Remarks

NR WR ER SR

1. NTPC Ltd. (Darlipalli)

(2x800 MW) 793.5 0 0 0 0

Bihar: 154.13 MW WB: 283.75

MW Jharkhand: 102.11 MW

Sikkim: 15.29 MW

Unallocated: 237.98 MW

U1: Dec’18

U2: Jun’19

Status sent through email

dated 28.09.2018 U1: Feb’19 U2: Sep’19

765 kV Darlipalli-Jharsuguda D/c line:

Line completed & charged in May’17

Representative did not attend the meeting. However, sent the status report through email dated 28.09.2018.

2. GRIDCO Ltd

(Darlipalli) 748 0 0 0 0

Odisha: 748 MW

3.

Orissa Power Generation Company

Ltd. (2x660 MW)

600 200 200 0 200 Nil

Not attended

As per status report dated 27.06.2018:

U1: Sep’18

U2: Oct’18

Not attended

400 kV OPGC - Jharsuguda D/c line with Triple snowbird conductor

:

Charged from Jharsuguda end

(Implemented under TBCB)

The developer neither attended the meeting nor submitted the status update. Status as per 16

th JCC meeting

held on 28.03.2018 is as below: The developer has not attended the meeting, however, sent the status report though email dated 04.04.2018. “Signing of PPA with beneficiaries is under progress.” Applicant is again advised to sign TSA at the earliest.

Minutes of 18th

JCC of Eastern Region held on 28.09.2018

Page 10 of 29

(Phase-II IPPs in Sikkim)

Sl. No.

LTOA / LTA Applicant

LTOA/LTA Quantum

(MW)

Target Beneficiaries Firm beneficiary

Comm. schedule (as per 17

th JCC)

Comm. schedule (as per 18

th JCC)

Dedicated / Connectivity line & Status

Remarks

NR WR ER SR

1.

Sneha Kinetic Power Projects Ltd

(Dikchu) (2x48 MW)

96 0

48 0

48 0

0 0 Nil U1&2: Mar’17

(Commissioned) Commissioned

132 kV Dikchu- Dikchu Pool D/c Moose conductor/

HTLS line:

400kV Interim arrangement through LILO of one ckt of Teesta-III to Rangpo D/c line at Dikchu (implemented by M/s Sneha Kinetic) –Commissioned

Representative informed that the issue regarding implementation of 132 kV Dikchu – Dikchu Pool D/c line is being taken up with Govt of Sikkim and CEA.

It was informed that upon commissioning of Rangpo-Dikchu Pool D/c line, the 400 kV interim arrangements are liable to be discontinued. Accordingly, Dikchu was requested to finalise the issue regarding dedicated transmission line with Govt of Sikkim at the earliest.

LTA has been revoked on account of non-signing of LTA Agreement vide CTU letter dated 08.03.2016

Minutes of 18th

JCC of Eastern Region held on 28.09.2018

Page 11 of 29

Other Generation Projects – Granted LTA

Sl. No.

LTOA / LTA Applicant

LTOA/LTA Quantum

(MW)

Target Beneficiaries Firm beneficiary

Comm. schedule

(as per 17th

JCC)

Comm. schedule

(as per 18th

JCC)

Dedicated / Connectivity line &

Status Remarks

NR WR ER SR

1 Nabinagar-II (3x660 MW)

1866.15 196.98

0 1529.

21 0

Bihar: 1463.23 MW Jharkhand: 56.55 MW

Sikkim: 9.43 MW

UP: 196.98 MW

U1: Sep’18 U2: Mar’19 U3: May’20

Status sent through email dated 28.09.2018

U1: Jan’19 U2: Sep’19 U3: Aug’20

400 kV Nabinagar-II-Gaya D/c line test

charged on 10.03.2018.

Representative did not attend the meeting. However, sent the status through email dated 28.09.2018.

2

NTPC Ltd (North

Karanpura) (3x660 MW)

1856.25 0 0 1577.

81 0

Bihar: 645 MW

Jharkhand: 468.75 MW

Odisha: 371.25 WB :

92.81 MW Unallocated: 278.44 MW

U1: Oct’19 U2: Apr’20 U3: Oct’20

Status sent through email dated 28.09.2018

U1: Oct’19 U2: Apr’20 U3: Oct’20

400 kV North Karanpura – Chandwa (Jharkhand) Pooling Station D/c line (Quad): Sep’17 (As per SPV transfer) (Under TBCB, monitored by CEA)

Representative did not attend the meeting. However, sent the status through email dated 28.09.2018.

Availability of LTA transmission system is extremely critical for meeting NTPC’s requirement of start-up power from Dec’18.

LTA transmission lines were under scope of M/s NKTL (under TBCB). Not taken up by Transmission licensee. However, M/s NKTL has submitted termination notice of TSA on 13.04.2018 due to non-availability of NOC from Ministry of Coal. NTPC has taken up the matter with MoP for expediting the interim arrangement.

2. Sikkim Hydro

Power Ventures Ltd-

66 40 26 0 0 NIL U1: Dec’19 U1: Dec’19 132 kV Rangit II – Legship Pool D/c line (along with 2 nos. of 132

Tripartite LTA agreement not signed by Govt of Sikkim. A meeting was held among

Minutes of 18th

JCC of Eastern Region held on 28.09.2018

Page 12 of 29

Sl. No.

LTOA / LTA Applicant

LTOA/LTA Quantum

(MW)

Target Beneficiaries Firm beneficiary

Comm. schedule

(as per 17th

JCC)

Comm. schedule

(as per 18th

JCC)

Dedicated / Connectivity line &

Status Remarks

NR WR ER SR (2x33 MW) U2: Dec’19 U2: Dec’19 kV line bays at legship

pool): applicant vide email dated 05.07.2018 informed that prior approval under section 68 for route survey is pending with Govt of Sikkim.

MoP, CTU and Govt of Sikkim on 06.01.2018 wherein Govt of Sikkim requested POWERGRID to resend the LTA agreement for signing. Accordingly, LTA agreement was sent to Govt of Sikkim and the same is yet to be signed.

Govt of Sikkim vide email dated 12.07.2018 informed that the expected commissioning schedule of 2 nos of 132 kV line bays at New Rangpo is Sep’18.

3.

K V K Nilachal

Power Pvt. Ltd

(3x350 MW)

560 140 140 140 140 Not attended Not attended

LILO of one ckt of 400kV Baripada- Mendhasal

D/c line – matching with Gen. Proj

The developer neither attended the meeting nor submitted the status update.

The status as per 10th JCC

held on 30.09.2016 is as below:

PIL has been disposed of in favor of Generation developer. However, work could not be taken up on account of tying up of finances.

Applicant to sign TSA at the earliest.

PPA for power transfer of 263MW has been signed with Odisha.

Minutes of 18th

JCC of Eastern Region held on 28.09.2018

Page 13 of 29

List of Generation Projects for which coordination not required in view of commissioning of projects along with the dedicated lines, or relinquishment of LTA

HIGH CAPACITY POWER TRANSMISSION CORRIDOR – I

(Phase-I IPPs in Odisha & associated Transmission System) Table T 1 (i)

Sl. No.

LTOA / LTA Applicant

LTOA/ LTA Quantum

(MW)

Target Beneficiaries Firm beneficiary

Status Dedicated /

Connectivity line & Status

Remarks NR WR ER SR

1.

GMR Kamalanga Energy Ltd (3x350 MW)

800

647

600

387 75

0

0

260 0

200 0

312MW -Haryana

260MW - Bihar

(Both are operational)

Commissioned

400kV GMR TPS-Angul Pool D/c (Quad) line-commissioned in Dec’14;

GMR TPS- Meramundali 400 kV S/c - commissioned in Mar’15

Petition No: 41/MP/2016 for relinquishment of 153MW filed before CERC & the matter is already decided. Matter in appeal before APTEL in Appeal No: 43/18.

LC is yet to be modified as per CERC approved format.

2.

Navabharat Power Pvt.

Ltd

(3x350 MW)

720 0

465 0

255 0

0 0 Nil Abandoned

400kV Navabharat

TPS-Angul Pool D/c line: Abandoned

Developer has applied for relinquishment of entire 720 MW and CERC vide order dated 12.04.2017 in Petition No: 317/MP/2013 has decided that the relinquishment charges shall be as per Petition No: 92/MP/2015. Appeal has been filed by Navabharat.

3.

Jindal India Thermal

Power Ltd (2x600 MW)

1044 0

834 0

210 0

0 0 Nil Commissioned

400kV Jindal TPS-Angul Pool 1

st D/c

line - Commissioned

400kV Jindal TPS-Angul Pool 2

nd D/c

line – To be awarded shortly.

Appeal No DFR 4400/17 before APTEL filed by JITPL.

Matter already decided vide CERC order dated 20.09.2017 in Petition No: 55/MP/2015 that relinquishment charges of

Minutes of 18th

JCC of Eastern Region held on 28.09.2018

Page 14 of 29

Sl. No.

LTOA / LTA Applicant

LTOA/ LTA Quantum

(MW)

Target Beneficiaries Firm beneficiary

Status Dedicated /

Connectivity line & Status

Remarks NR WR ER SR

entire 1044 MW to be decided in 92/MP/2015.

4. Sterlite

Energy Ltd (4x600 MW)

400 0

200 0

200 0

0 0 Nil Commissioned

400kV Sterlite-Jharsuguda Pool

D/c line: Commissioned on

06.11.2017

Petition No. 003/MP/2016 has been filed before CERC for relinquishment of entire LTA quantum.

5.

Ind Barath Energy

(Utkal) Ltd. (IBEUL)

(2x350 MW)

616 0

266

116 0

350

0

0

0

500 0

Nil

As per status report dated 25.06.2018:

U1: COD

(20.07.2016)

U2: Ready for BLU

400kV Ind Barath-Jharsuguda Pool D/c line: Completed.

(Due to OPGC’s new MGR corridor

infringement; diversion is required which is held up for financial constraints

and ROW land problem with MCL and private land

owners).

Construction Phase BG of Rs. 30.8 Cr. has been encashed on 25.10.2017 on account of failure to comply with CERC directions, non-establishment of requisite LC and default on payment.

Petition No. 127/MP/2016 filed by IBEUL is pending before CERC. As on date, IBEUL is bound by directions passed in said petition for payment of transmission charges.

TSA termination notice has been issued on 18.06.2018 with notice period of 30 days, upon expiry of which IBEUL shall cease to be DIC and therefore, IBEUL will be ineligible to inject power into ISTS through any form of access including STOA, MTOA, and LTA as directed by CERC in order dated 08.03.2018 in Petition No: 229/RC/2015.

LTA has been revoked on

Minutes of 18th

JCC of Eastern Region held on 28.09.2018

Page 15 of 29

Sl. No.

LTOA / LTA Applicant

LTOA/ LTA Quantum

(MW)

Target Beneficiaries Firm beneficiary

Status Dedicated /

Connectivity line & Status

Remarks NR WR ER SR

account of termination of TSA vide CTU’s letter dated 18.07.2018.

HIGH CAPACITY POWER TRANSMISSION CORRIDOR – II

(Phase-I IPPs in Jharkhand & associated Transmission System) Table T 1 (ii)

Sl. No.

LTOA / LTA Applicant

LTOA/LTA Quantum

(MW)

Target Beneficiaries Firm beneficiary

Status Dedicated /

Connectivity line & Status

Remarks

NR WR ER SR

1.

Adhunik Power & Natural

Resources Limited

(2x270 MW)

450 200

200

0

50 0

200

100

0

100

Tamil Nadu: 100 MW &

West Bengal: 100 MW;

(Operational)

Commissioned 400kV Adhunik TPS-Jamshedpur D/c line-

Commissioned

Applicant has filed a petition No: 167/MP/2016 before CERC for relinquishment for 250 MW (NR: 200 MW, WR: 50 MW) of LTOA and return of BG for 450 MW. Vide ROP dated 19.01.2017, CERC vide order dated 27.02.2018 has accepted relinquishment of 250MW subject to payment of applicable relinquishment charges as per CERC directions in Petition No: 92/MP/2015.

2.

Corporate Power Limited

Ph-I (2x270 MW)

480 240 240 0 0 Project uncertain 400kV Corporate TPS -Ranchi D/c line: Not taken up

Developer had earlier confirmed in the Special JCC held on 07.07.2015 that project is uncertain due to de-allocation of Coal Blocks and requested for relinquishment of entire LTA.

CBG encashed.

3.

Corporate Power Limited

Ph-II (2x270 MW)

480 240 240 0 0

Project uncertain

400kV Corporate TPS-Jharkhand Pooling Station D/c line: Not taken up

Minutes of 18th

JCC of Eastern Region held on 28.09.2018

Page 16 of 29

Sl. No.

LTOA / LTA Applicant

LTOA/LTA Quantum

(MW)

Target Beneficiaries Firm beneficiary

Status Dedicated /

Connectivity line & Status

Remarks

NR WR ER SR

Matter is sub-judice.

4.

Essar Power (Jharkhand) Ltd. (2x600

MW)

1100 0

400 0

400 0

300 0

0 Nil U1 : Nov’18 U2 : Jan’19

400kV Essar TPS - Jharkhand Pooling Station D/c line (Quad) : Commissioning matching with generation projects

Entire 1100 MW LTOA was relinquished w.e.f. 12.04.2017 subject to directions in Petition No: 21/MP/2017 filed by EPJL for relinquishment of 1100 MW LTOA and payment of applicable relinquishment charges as per CERC directions in Petition No: 92/MP/2015.

5.

WBSEDCL (1000 MW

State surplus)

1000 600 400 0 0 - LTA operationalized from 01.10.2017.

HIGH CAPACITY POWER TRANSMISSION CORRIDOR – III

(Phase-I IPPs in Sikkim) Table T 1 (iii)

Sl. No.

LTOA / LTA Applicant

LTOA/LTA Quantum

(MW)

Target Beneficiaries Firm beneficiary

Status Dedicated /

Connectivity line & Status

Remarks NR WR ER SR

1

DANS Energy Pvt.

Ltd. (Jorethang)

(2x48)

96 48 48 0 0 Commissioned

220kV Jorethang - New Melli D/c line- commissioned in Nov’16

SPS has been commissioned. LTA will be made effective w.e.f. 01.12.2018 subject to commissioning of 400 kV Teesta-III - Kishanganj D/c line.

2

PTC /Teesta Urja Ltd.

(Teesta-III) (6x200 MW)

1200 840 0 144 0

Punjab: 340 MW

Haryana: 200 MW

U1-U6: Feb’17 (Commissioned)

400kV Teesta III - Kishanganj D/c (Quad) line (being implemented by TPTL): COD of

Part LTA of 174 MW has been operationalized w.e.f. 12.05.2018. Further, entire LTA will be made effective

Minutes of 18th

JCC of Eastern Region held on 28.09.2018

Page 17 of 29

Sl. No.

LTOA / LTA Applicant

LTOA/LTA Quantum

(MW)

Target Beneficiaries Firm beneficiary

Status Dedicated /

Connectivity line & Status

Remarks NR WR ER SR

UP: 200 MW Rajasthan: 100 MW

Sikkim: 144 MW

Teesta-III to Rangpo Ckt 2 declared on 16.01.2017 and COD of Teesta-III – Dikchu declared on 13.04.2017, Dikchu - Rangpo portion completed but not commissioned due to Church in ROW. Balance portion upto Kishanganj expected to be commissioned by Jun’18.

w.e.f. 01.12.2018 subject to commissioning of 400 kV Teesta-III - Kishanganj D/c line.

3

JAL Power Corporation (Rangit-IV) (3x40 MW)

120 0

16 0

16 0

88 0

Nil

Not attended

As per status report dated 04.04.2018:

No specific schedule

mentioned

(Three and a half year for completion after

restart of work)

220kV Rangit IV - New Melli D/c line:

No specific schedule

mentioned

(2 years after restart of work)

The developer has not attended the meeting, however, sent the status report though emails dated 28.03.2018 and 04.04.2018. Status is as below: Rangit Stage-IV HE Project has not been abandoned. Lead leader viz M/s Power Finance corp. are in the process of identifying new promoter. Dedicated line awarded in Nov’12. Route survey & design of towers has been completed. Further work could not be done due to funds constraint. Due to funds constraints, work on project is held up since Oct’13. In spite of best

Minutes of 18th

JCC of Eastern Region held on 28.09.2018

Page 18 of 29

Sl. No.

LTOA / LTA Applicant

LTOA/LTA Quantum

(MW)

Target Beneficiaries Firm beneficiary

Status Dedicated /

Connectivity line & Status

Remarks NR WR ER SR

efforts additional equity could not be tied up matching with revised cost. Since infusion of equity is expected to take some time and uncertain as of now, no commitment can be given regarding restart/COD of the project at this stage. PFC has agreed to give loan as per revised cost after enhancement of equity by the State Govt. Commitment for COD can be given after tie-up of additional equity matching with the revised cost.

Entire 120 MW LTOA was relinquished w.e.f. 01.01.2018 subject to payment of applicable relinquishment charges as per CERC directions in Petition No: 92/MP/2015.

4

Gati Infrastructure

Ltd (Chuzachen) (2x55 MW)

99 99 0 0 Commissioned

(May’13)

132kV Chuzachen-Rangpo D/c Zebra Conductor line:

Line Completed

Representative informed that Line completed, however bay works at Rangpo substation is likely to be completed by Govt of Sikkim by Nov’18. LTA will be made effective w.e.f. 01.12.2018 subject to commissioning of 400 kV Teesta-III - Kishanganj D/c line.

Minutes of 18th

JCC of Eastern Region held on 28.09.2018

Page 19 of 29

(Phase-II IPPs in Odisha)

Table T 1 (iv)

Sl. No.

LTOA / LTA Applicant

LTOA/LTA Quantum

(MW)

Target Beneficiaries Firm beneficiary

Status Dedicated / Connectivity

line & Status Remarks

NR WR ER SR

1.

GMR Kamalanga Energy Ltd

(1x350 MW)

220 0

0 220 0

0 0 Nil Abandoned

400kV GMR TPS-Angul Pool D/c (Quad) line with

bays at both ends: Commissioned

Applicant has filed a petition No: 137/MP/2016 before CERC for relinquishment of 220 MW LTA as the project has been abandoned.

CERC vide ROP dated 6.10.2016 has accepted relinquishment of 220MW subject to payment of applicable relinquishment charges as per CERC directions in Petition No: 92/MP/2015.

2. Sterlite

Energy Ltd (4x600 MW)

1000 0

400 0

400 0

200 0

0 Nil Commissioned

400kV Sterlite-Jharsuguda Pool 2

nd D/c line:

Requirement of 2nd

dedicated line was reviewed in the 12

th ER

Connectivity /LTA meeting held on 01.09.2017 and it was agreed that with the relinquishment of 1000MW LTA, the same may not be required.

Applicant has filed a petition No: 303/MP/2015 before CERC for relinquishment of 1000 MW LTA.

CERC vide ROP dated 08.03.2016 has accepted relinquishment of 1000MW LTA subject to payment of applicable relinquishment charges as per CERC directions in Petition No: 92/MP/2015.

Minutes of 18th

JCC of Eastern Region held on 28.09.2018

Page 20 of 29

(Phase-II IPPs in Sikkim) Table T 1 (v)

Sl. No.

LTOA / LTA Applicant

LTOA/LTA Quantum

(MW)

Target Beneficiaries Firm beneficiary

Status Dedicated / Connectivity line &

Status Remarks

NR WR ER SR

1.

Shiga Energy Pvt. Ltd.

(Tashiding) (2x48.5 MW)

97 48.5 48.5 0 0 Nil Commissioned

220kV Tashiding -Legship D/c line – completed in Dec’16

Also Legship Pool - New Melli of Sikkim has been charged on 12.10.2017.

At present Tashiding project is connected through LILO of Tashiding – Legship Pool – New Melli 220 kV D/c line with one circuit of New Melli – Rangpo 220 kV D/c line.

LTA will be made effective w.e.f. 01.12.2018 subject to commissioning of 400 kV Teesta-III - Kishanganj D/c line.

Minutes of 18th

JCC of Eastern Region held on 28.09.2018

Page 21 of 29

Status of the Associated Transmission System

HIGH CAPACITY POWER TRANSMISSION CORRIDOR – I (Phase-I IPPs in Odisha & associated Transmission System)

All the elements of HCPTC-I have been commissioned. The details of elements are as follows:

Transmission System under the Scope of POWERGRID:

Transmission System for Phase-1 generation projects in Odisha - Part-A

Sl. No. Scope of Transmission System

1 765kV Angul Pooling Station – Jharsuguda Pooling Station 2xS/c line

2 LILO of 400kV Rourkela – Raigarh D/c at Jharsuguda Pooling station

3 LILO of 400kV Meramundali – Jeypore S/c line at Angul pooling station

4 LILO of 400kV one ckt of Talcher - Meramundali D/c line at Angul pooling station

5 Establishment of 2x1500 MVA, 765/400kV Pooling Station at Jharsuguda

6 Establishment of 4x1500MVA, 765/400kV Pooling Station at Angul

Transmission System for Phase-1 generation projects in Odisha - Part-B

Sl. No. Scope of Transmission System

1 Establishment of 765kV switching station at Dharamjaygarh / near Korba

2 LILO of 765kV Ranchi – WR Pooling near Sipat S/c line at Dharamjaygarh / near Korba

3 765kV Jharsuguda Pooling Station – Dharamjaygarh / near Korba (WR) D/c

4 Establishment of 765/400kV Pooling Station at Jabalpur

5 765kV Dharamjaygarh / near Korba – Jabalpur Pooling Station D/c line

6 400 kV Jabalpur Pooling Station – Jabalpur D/c (high capacity) line

Minutes of 18th

JCC of Eastern Region held on 28.09.2018

Page 22 of 29

Transmission System for Phase-1 generation projects in Odisha - Part-C

Sl. No. Scope of Transmission System

1 765kV Jabalpur Pooling Station – Bina D/c line

2 765kV Bina – Gwalior S/c (3rd circuit)

3 765kV Gwalior - Jaipur S/c line (2nd circuit)

4 765kV Jaipur - Bhiwani S/c line (1st circuit)

Transmission System under the Scope of Private Sector:

Sl. No. Scope of Transmission System

1 Establishment of 2x1500MVA, 765/400kV Bhopal Pooling Station

2 765kV Jabalpur Pool – Bhopal – Indore S/c

3 400kV Bhopal New substation – Bhopal (M.P.) D/c (high capacity)

Minutes of 18th

JCC of Eastern Region held on 28.09.2018

Page 23 of 29

HIGH CAPACITY POWER TRANSMISSION CORRIDOR – II (Phase-I IPPs in Jharkhand & associated Transmission System)

All the elements of HCPTC-II have been commissioned. The details of elements are as follows:

Transmission System under the Scope of POWERGRID:

Transmission System for Phase-I Generation Projects in Jharkhand & West Bengal : Part-A-1

Sl. No. Scope of Transmission System

1 Establishment of 400kV GIS Pooling Station (Jharkhand Pool) near Essar and Corporate generation projects.

2 400 kV Ranchi - Gaya D/c (Quad) line via pooling station proposed near Essar / Corporate generation projects

Transmission System for Phase-I Generation Projects in Jharkhand & West Bengal : Part-A-2

Sl. No. Scope of Transmission System

1 Ranchi New (765/400kV S/s) - Dharamjaygarh / near Korba 765kV S/c

2 2x1500 MVA, 765/400 kV New GIS substation at Varanasi

3 Gaya - Varanasi 765kV S/c

4 Varanasi - Balia 765 kV S/c line

Transmission System for Phase-I Generation Projects in Jharkhand & West Bengal : Part-B

Sl. No. Scope of Transmission System

1 New 2x1500 MVA, 765/400 kV substation at Kanpur

2 Varanasi – Kanpur 765 kV D/c

3 Kanpur – Jhatikra 765 kV S/c

4 Kanpur (765/400kV) – Kanpur (Existing) 400kV D/C (Quad)

5

400kV connectivity for new 765/400kV S/s at Varanasi

Varanasi – Sarnath (UPPCL) 400kV D/c (quad)

LILO of Sasaram – Allahabad 400kV line at Varanasi

Opening of LILO of one ckt of Sasaram – Allahabad 400kV D/c line at Sarnath

Transmission System under the Scope of Private Sector:

Sl. No. Scope of Transmission System

1 Dharamjaygarh – Jabalpur 765kV D/C line (2nd

line)

Minutes of 18th

JCC of Eastern Region held on 28.09.2018

Page 24 of 29

HIGH CAPACITY POWER TRANSMISSION CORRIDOR – III (Phase-I IPPs in Sikkim)

Transmission System under the Scope of POWERGRID:

Transfer of power from generation projects in Sikkim to NR/WR: Part-A

All the elements of Part-A and B of HCPTC-III have been commissioned. The details of elements are as follows:

Sl No Scope of Transmission System

1. Establishment of New 2x500 MVA, 400/220 kV sub-station at Kishanganj

2. LILO of New Siliguri – New Purnea 400kV D/c line (quad) at Kishanganj

3. LILO of Siliguri – Dalkhola 220kV D/c line at Kishanganj

Transfer of power from generation projects in Sikkim to NR/WR: Part-B

Sl No Scope of Transmission System

1. Establishment of 16x105MVA, 1 ph, 400/220kV and 3x100MVA 220/132kV, Gas Insulated Substation at Rangpo

2. Establishment of 220kV Gas Insulated switching station at New Melli

3. LILO of one circuit of Teesta III – Kishanganj 400kV D/c line (quad, Teesta III – Kishanganj 400kV D/c line under JV route) at Rangpo (with Twin HTLS)

4. Rangpo – New Melli 220kV D/c line (with Single HTLS conductor)

5. LILO of Gangtok – Rangit 132 kV S/c line & Gangtok- Melli 132 kV S/c line at Rangpo

6. LILO of Teesta V – Siliguri 400kV D/c line at Rangpo

7. Kishanganj – Patna 400kV D/c (quad) line

Transfer of power from generation projects in Sikkim to NR/WR: Part-B1

Sl No

Scope of Transmission System Status

(as per 17th

JCC) Status

(as per 18th

JCC) Remarks

1. LILO of 2

nd ckt of Teesta – III – Kishanganj 400 kV

D/c (Quad) line

Award placed in Dec’17 and completion schedule is 30 months i.e. Jun’20.

12 km line length, 34 out of 35 locations in forest. Expected to be completed by June’20

Minutes of 18th

JCC of Eastern Region held on 28.09.2018

Page 25 of 29

Transmission System under the Scope of TPTL (ISTS licensee):

Sl. No.

Scope of Transmission System Status (as per 17

th JCC)

Status (as per 18

th JCC)

Remarks

1 Teesta-III – Kishanganj 400kV D/c (Quad) line

Dikchu – Rangpo S/c expected on 30.06.2018 Rangpo – Kishanganj D/c 400 kV line: 30.09.2018

Dikchu – Rangpo S/c commissioned on 30.06.2018 Rangpo – Kishanganj D/c 400 kV line: 30.11.2018

585 Out of 590 tower foundations completed;

581 erection completed, balance 9; 193.17 Km. Stringing completed, balance 20.33kM yet to be

stringed.

Minutes of 18th

JCC of Eastern Region held on 28.09.2018

Page 26 of 29

Status of other Associated Transmission System Phase-II IPPs in Odisha & associated Transmission System

Transmission System under the Scope of POWERGRID:

Sl. No.

Scope of Transmission System Status (as per 17th JCC)

Status (as per 18th JCC)

Remarks

1 Angul-Jharsuguda (Sundargarh)-Dharamjaygarh 765 kV D/c (2nd

) line Sep’18 Dec’18

2 Addition of 2x1500MVA, 765/400 kV ICTs at Jharsuguda (Sundargarh)

Apr’19 Apr’19

3 Split bus arrangement at 400 kV and 765 kV bus at Jharsuguda (Sundargarh) substations.

Apr’19 Apr’19

4 LILO of both circuits of Rourkela-Raigarh 400 kV D/c (2

nd) at

Jharsuguda (Sundergarh) substation

Commissioned in Jan’18

Commissioned in Jan’18

Transmission System under the Scope of TBCB (Sterlite):

Sl. No.

Scope of Transmission System Status (as per 17th JCC)

Status (as per 18th JCC)

Remarks

1 Jharsuguda (Sundargarh) – Raipur Pool 765 kV D/c

Aug’19 (As per SPV

transfer)

Aug’19 (As per SPV

transfer)

Completion of associated bays: Aug’19 (CMG may verify)

Minutes of 18th

JCC of Eastern Region held on 28.09.2018

Page 27 of 29

(North Karanpura STPP) Transmission System under the Scope of TBCB:

Sl. No.

Scope of Transmission System Status (as per 17th

JCC)

Status (as per 18th

JCC)

Remarks

1 400 kV North Karanpura – Gaya D/c line with quad moose conductor

Sep’19 (As per SPV

transfer)

Sep’19 (As per SPV

transfer)

TBCB line is being monitored by CEA.

2 400 kV North Karanpura – Chandwa (Jharkhand) Pooling Station D/c line with quad moose conductor

Sep’17 (As per SPV

transfer)

Sep’17 (As per SPV

transfer)

TBCB line is being monitored by CEA. Line construction delayed substantially as coal field encountered. Action is being taken up by CEA/MoP.

Transmission System under the Scope of POWERGRID:

Sl. No.

Scope of Transmission System Status (as per 17th

JCC)

Status (as per 18th

JCC)

Remarks

1 2 no 400 kV D/c line bays at Gaya for termination of North Karanpura-Gaya 400 kV D/c line

Sep’19 Sep’19 Associated transmission line (under TBCB) delayed substantially.

2 2 nos of 400 kV D/c line bays at under construction Chandwa (Jharkhand) Pooling Station for termination of North Karanpura – Chandwa 400 kV D/c line

Jun’18 Dec’18

(Nabinagar-II STPP)

Sl. No.

Scope of Transmission System Status (as per 17th

JCC)

Status (as per 18th

JCC)

Remarks

1 400 kV Nabinagar II-Gaya D/c line Test charged on

10.03.2018. Test charged

on 10.03.2018.

2 400 kV Nabinagar II-Patna D/c line Jun’19 Jun’19

Minutes of 18th

JCC of Eastern Region held on 28.09.2018

Page 28 of 29

Annexure-I List of Participants in the 18th Joint Co-ordination committee Meeting of IPPs granted LTA in ER held on 28.09.2018

Sl. No. Name Designation Organisation Email

1 D S Barik Manager (Law) Sikkim Hydro Power Pvt Ltd. [email protected]

2 K Chakraborty GM (E&M) Madhya Bharat Power Corpn Ltd. [email protected]

3 Sunny Kumar Singh Asst Manager Sneha Kinetic Power Project Pvt. Ltd. [email protected]

4 Chinmay Biduri Engg Teesta Valley Power Transmission Limited [email protected]

5 Prasenjit Majhi Dy. Manager Lanco Teesta Hydro Power Ltd. [email protected]

6 Harpreet Singh Walia General manager Lanco Babandh [email protected]

7 Ashok pal General Manager (CTU-Plg) POWERGRID [email protected]

8 Laxmi Kant Chief Manager (CTU-Plg) POWERGRID [email protected]

9 Swapnil Verma Sr. Law Officer (CTU-Plg) POWERGRID [email protected]

10 Dwaipayan Sen Engineer (CTU-Plg) POWERGRID [email protected]

Minutes of 18th

JCC of Eastern Region held on 28.09.2018

Page 29 of 29

Annexure-II

The following applicants/DICs are requested to sign the Transmission Service Agreement

Sl. No. LTOA / LTA Applicant

LTOA/ LTA Quantum (MW)

Target Beneficiaries

NR WR ER SR

1. Essar Power (Jharkhand) Ltd. (2x600 MW) 1100 400 400 300 0

2. Lanco Teesta Hydro Power Ltd. (Teesta-VI) (4x125 MW) 500 0 500 0 0

3. Madhya Bharat Power Corpn Ltd. (Rongnichu) (2x48 MW) 96 56 40 0 0

4. Orissa Power Generation Company Ltd. 600 200 200 0 200

5. Monnet Power Company Ltd. 900 300 225 225 150

6. KVK Nilachal Power Pvt. Ltd. 560 140 140 140 140

7. Navbharat Power Pvt. Ltd 720 465 255 0 0

8. Sterlite Energy Ltd. 400 200 200 0 0

9. Gati Infrastructure Ltd. (Bhasmey) 51 36 15 0 0

Sl. No. Name of the DIC Remarks

1. Energy & Power Dept. Govt. of Sikkim TSA not signed