Discharge by Performance
-
Upload
azhari-ahmad -
Category
Documents
-
view
28 -
download
1
description
Transcript of Discharge by Performance
DISCHARGE OF CONTRACT BY PERFORMANCE
Discharge of contract
• Meaning
> Contract is terminated
> Parties are released / discharged from contractual obligations
• NOTE:
Dispute arise where X demand performance of contract, but Y claimed he was discharged from contractual obligation to perform
GENERAL RULE1. Each party to the contract has contractual
obligations to perform. Eg
a. Sale Agreement :
> Seller deliver the goods according to the terms / specification stated.
> Buyer’s obligation is the payment when
contract is performed
b. Employment agreement: When does Employer’s duty to pay salary
arise?
2. Order of performance
Question of who is to perform 1st
Sec 53 : when the order of performance of
contract for reciprocal promise is fixed by
the contract, they shall be performed in that
order
>>> Question of construction of terms on WHO is the 1st person to perform the contract
Mars Equity Sdn Bhd v Tis ‘Ata ‘ashar Sdn Bhd [2006] 4 MLJ 302 CA
• Facts:
2 agreements made simultaneously ie SPA on land, Resp to transfer land title &Timber agreemt , App to apply for licence.
• Issues: i) What is the order of the agreemt?
ii) Relevant remedy?
Held
1. Order n sequence: S 53 Contract Act; look at nature of transaction
2. Only registered owner of land can apply for licence. Vendor (R) has breached primary obligation.
Common law positionRule:
1.Parties to contract must perform their
contractual obligations as per the terms.
2. Performance of entire / lump sum contract
i. must be exact, complete & precise
>> pre-condition to payment
ii. Agreement ends when each party fulfills his contractual obligations
Case: Sumpter v Hedges
Consequence of non compliance
• Deviation / non performance = breach of contract.
>> Party in breach is not entitled to payment.
Reason: Contract was not fully performed as per the terms
>> Where non performance is inexcusable,
contract breaker faced a claim of breach of
contract
>> Effect: Injured party is entitled to terminate all future obligations under contract
Case: Re Moore v Landauer
Cutter v Powell [ 1795]Employment contract as 2nd mate from Jamaica toLiverpool. Term: Salary to be paid upon reaching the port. Sailor however died en route. Claim by sailor’s widow for his salary.Held: Widow was not entitled to claim his salaryi. Entire contract / Lump sum contract. ii. Right to payment was dependent on completion of the
journey.iii. Deceased did not complete his task or perform the
contract in its entirety. Right to payment is dependent upon completion of duties
Note: strict application of common law principle
Re Moore v LandauerB ordered goods to be packed 30 cans perbox. B rejected goods delivered & refused topay. 50% were packed 24 cans per box. Ssued B for breach of contract. Defence: S had not performed the terms of contractHeld: No discharge of contract by performancei. Breach of term ie condition by Seller. ii. Seller was not entitled to payment. Did not
perform the contract according to the termsiii. Buyer was entitled to repudiate the contract &
reject the goods
Sumpter v Hedges [1898]
• Agreement to buildhouses & stables on D’s land for 565 pound. Pl did part of the work only & abandoned the work. Dthen completed the work.
• Issue: Was the Pl entitled to claim the value of the work done by him , ie 333 pounds?
• Held: NO
Bolton v Mahadeva [ 1972] HL
Claim by contractor for payment [ 800pounds ] for installation of central heating system. System was found ineffective. Held: Claim failed. 1.Pl did not perform his contractual
obligation2.Pl could get nothing
Effect of judgements
• Strict application of complete & precise performance of entire contracts
Criticism:
> unjust enrichment for Paying party
who had benefitted from the contract
EXCEPTION 1 : Payment can be claimed if
Substantial Performance of Contract byPerforming PartyCase: Bolton v Mahadeva [ 1972] HL
RD: Paying party to pay if there was substantial performance by contract breaker
Contract breaker is entitled to contract price , subject to counter claim for cost to remedy defect (eg cost of hiring another contractor) if he canshow that he has substantially performed his obligations
Hoenig v Isaacs [ 1952] per Denning LJ
• “ when a contract provides for for a specific sum to be paid on completion of specified work, the courts lean against a construction …which would deprive the contractor of any payment simply because there are some defects. The promise to complete the work is…construed as a term of contract, but not a condition…”
M’sian positionKunchi Rahman v Goh Bros (1978)
FACTS
Contract worth $71000 was made with Pl to
supply & lay pipes between Mak Mandin & Prai
for $ 16580. Work was not completed despite
reminders given. D incurred expenses. Another
contractor was hired to complete the work.
Claim for payment was made by Pl. Def
counterclaimed for damages
Issues
> Was Contractor entitled to the contract sum? How much?
> Was the contract substantially performed?
Note:
English law was followed. Ratio decidendi of
Bolton v Mahadeva was applied
Held
• Agreement was an entire contract. Pl had substantially performed / completed the contract. Entitled to claim balance of payment [ $11,000]
• Def was also entitled to counterclaim for the defects & cost to complete the contract [ ie $ 22,000]. Damages awarded will diminish / reduce amount claimed by Pl. Amount after adjustment : $6047
• Pl’s claim was dismissed
EXCEPTION 2
Divisible Contracts :
> Obligations broken down into smaller units eg
i. building contracts ---payment according to percentage of work done
ii. Employment contract----salary paid at intervals eg on daily or weekly basis
Divisible Contracts
Difference from entire contract
> Separate payment for performance by
instalment
Question : How much to pay ?
• Tong Aik v Eastern Mineral (1963 )
EXCEPTION 3
Prevention of Performance of Contracts• Unfair to disallow claims for portion of work done• Party who prevent performance of contract
committed breach of contract• Performing party allowed to sue payment on
quantum meruit: basis
Planche v Colburn [1831]
EXCEPTION 4Acceptance of partial performance• Inference of new contract. Implied contract to
pay for work done• No entitlement to original contract price. Right
to payment on quantum meruit• Innocent party’s option to accept or reject
incomplete / partial performance of contract
Case: Sumpter v Hedges
Smith Construction Co Ltd v Phit Kiritvana [ 1955]
Time for performance of contract
• Contract must be performed at the time agreed by the parties
• Effect of non compliance with stipulation / term of contract?
>> No standard / uniform principles.
>> See the terms of contract
“Time is of the essence”.
1 Where time of performance is crucial, the parties should make express mention in the contract, ie make time “ of the essence”
IMPLICATION>> Important term of contract ; >> compliance with the date is mandatory2. In absence of such provision, reference is made
to industry practiceRight to terminate the contract ?>> Yes
Contracts Act 1950
• Sec 56(1)
Contract…becomes voidable at the option of the promisee, if the intention of the parties was that time should be of the essence of the contract
Note:
Term on time “of the essence of the
contract” is thus a condition / important term
of contract
Sec 56 (2) : reasonable time to complete
• Where time is not of the essence, performance is within reasonable time
• Meaning of reasonable time?
Case
Penang Devmt Corporation v Khoo Chin
Boo
>> Question of fact
Time is of the essence : S56• What is the intention of parties?
• Effect of breach of term: Contract is voidable
Examplesi. Sale of goods• S11 SOGA, 1957: Stipulation / term as to time
of payment is not deemed as of the essence.• Stipulation as to time of delivery of goods
Case: Himatsing v Joitaram
ii. Sale of land :
Generally , time is not important, unless it is specified that time is of the essence
• Jamshed Khodaram Irani v Burjoji [1913] PC
Jamshed Khodaram Irani v Burjoji [1913] PC
In relation to land,
• completion is to take place within a reasonable time, notwithstanding the specific time named.[ General rule]
• one looks at the intention of the parties
• In equity , time is not of the essence of the contract
• Equity will infer an intention that time should be of the essence from what has passed between the parties prior to the signing of the contract
[ note: parties to specify in the agreement if want to make time as an important element/ condition of a contract ! ]
Sim Chio Huat v Wong Ted Fui [1983] FC
• Building contract with App, a housing developer
• Term that time was of the essence. No term or provision on extension, or alterations & additional works.
• App was unable to complete & deliver the houses within the stated time.
• Claim for price of extra work done at Resp’s instruction & expenses incurred
Issues:
• Relevance of additional work given by Resp?
• Was the extra time to perform the work = a waiver of the term that time is of the essence?
Decision: Salleh Abas FJ
• 1. Stipulated time for delivery was essential condition of the agreement. Failure to fulfill it entitled Resp to exercise the option of terminating / rescinding OR continue with the contract
• 2.Resp did not repudiate the contract, but had allowed time to pass ie acquiescence in the work continuuing & ordering extra work to be done ,
continue
where there was no such provision in the agreement ,means he had waived his right to rescind the contract & the right to treat himself as discharged
3. The term / stipulation as to time ceased to be of the essence of the agreement.
reason: Acquiescence in the continuance of the work
Extension of time: What is the legal implication?
CONSIDER:
1.Was the term that “ time is of the essence” no longer applicable?
2. Was there a waiver of that term?
Extension of time: What is the legal implication?
3. If the performing party breached the contract [ ie did not complete the contract despite the new time extended ] , can the parties rely on the original date of performance?
4. Must there be insistence on time being of the essence of contract [ for the new time / date] ?
Loke Yuen Cheng v Vimtex [ 1998] 4 CLJ 352
Issue: Whether mere grant of extension of time is a waiver of express term that time is of the essence?
Facts: SPA of land made on14/08/1992. Terms of contract: 1.10% deposit2.Completion before 14/11/19923. Time is of the essence4.Vendor to grant extension of time of 2 mths …to enable Purchaser to pay balance of price
Loke Yuen Cheng v Vimtex> Time of payment was extended to 13/1/93. > P did not pay the money on 13 / 1/ 93.> V rescinded agreement on 14/01/1993 & forfeited deposit. P sent a cheque a few days later. P later claimed specific performance of contract ie the
land be transferred to him.Held: P’s application was rejected1.Time was of the essence. P had breached the
term. Non compliance by P2. V was entitled to forfeit the deposit
Yeow Kim Pong Realty v Ng Kim Pong [ 1962] PC
1.Sale of land . Purchaser failed to pay on the date specified.
2.Supplementary agreement: V agreed to give P extension of time provided that certain conditions were fulfilled; otherwise extensionof time would be withdrawn . P failed to pay. V forfeited the deposit n terminated the contract
Held: The Rt Hon LMD De Silva
• Question whether time is of the essence is one to be determined by ascertaining the real intention of the parties.
• Sec 56[3] does not place a limitation upon the freedom of parties when one of them failed to perform the promise. The contract could be reaffirmed in its original or varied form and subject to such conditions as may be agreed…
CORRUGATED CARTON PRODUCTS SDN BHD v. KONG LONG HUAT REALTY
SDN BHD [2004] 3 CLJ 1 FC Issues: - • Whether termination proper • Whether purchaser entitled as of right for
extension of time to make payment
FACTS
• App [P] entered into a sale and purchase agreement dated 11 October 1989 with the Resp [V] to purchase land at the agreed price of RM550,000. At the time of execution of the agreement, App had paid Resp RM50,000.
• By cl. 3(a) App was to pay the balance of RM500,000 on or before 9 January 1990.
• 3(a)Completion of the sale and purchase of the said property shall take place within a period of Ninety (90) days from the date of this Agreement (hereinafter referred to as "the Completion Date"). Provided always and it is hereby agreed by and between the parties hereto that the Vendor shall grant to the Purchasers an extension of a further thirty (30) days in respect of the Completion Date but upon payment of interest on the outstanding balance of the purchase price at the rate of eight point five per centum (8.5%) per annum calculated on a daily basis during the period of extension
HELD Abdul Malek Ahmad FCJ
• Read in its entirety, it was clear beyond doubt that the completion date was ninety days after the execution of the agreement. But a further extension of thirty days shall be given by the respondent upon payment of interest on the outstanding balance of the purchase price
• notification for the extension was essential before the expiry of the initial period and a written undertaking to pay
• With no interest paid by the appellant for the extension period and without any notification that an extension was needed despite the exchange of correspondence during the crucial period before and after the expiry of the initial period of three months, how was the respondent to know that the appellant needed an extension to complete the agreement?
• Resp [V] is entitled to have the deposit forfeited in accordance with clause 9.
Sik Hong Photo Sdn Bhd v Ch’ng Beng Choo [2010] 3 MLJ 633 CA
1.Sale and purchase of property
2.Specified mandatory date of completion of sale
Issues:
a.Whether time was of essence
b.Whether purchaser could rescind sale and purchase agreement for default of completion date : Contracts Act 1950 s 56(1)
Held Low Hop Bing JCA 1.The essence of time in the SPA came
under s 56(1) of the Act and the failure of
consideration was within the ambit of s 40 of
the Act.
2. Section 40 must be read together with
Sec 56(1) when determining whether Def
as a promisor had committed a breach of
such a nature that went to the root of the
contract ie a fundamental breach.
Low Hop Bing JCA
• That fundamental breach entitled Madam
Ng to rescind the contract and to have the
parties restored to a position where they
would stand as if the SPA had never been
made ie the return of the property by way of
restitutio in integrum to Madam Ng, and,
upon her death, to her estate
Soon Yee Ling & Anor v Lim Ah Hun [2011] 1 MLJ 735
FC, [2011] 1 MLJ 819 CA
1. Agreement dated 11 April 2000 ('the SPA') whereby Respondent agreed to buy the lands at RM1,600,992.20 & redeem the land charged to the banks.
2. Deposit of RM264,992 was paid , & balance sum of RM1,336,000
.
3. He applied to Bank for a loan of RM800,000. It was approved on 26 June 2000. However, until 21 July 2000, ie the date of the termination of the agreement, the lands had not been redeemed by Resp
4. Under cl 22 of the SPA, time shall be of essence of the agreement
Issues(i) whether the App [V] were entitled to terminate
the SPA and to forfeit the deposit for the non-compliance by the Resp [P] of the condition to redeem the property within the time stipulated
[YES]
(i) whether the Resp was entitled to insist on the App continuing with the SPA when the respondent himself failed to redeem the property within the stipulated time.
[ NO]
Held Arifin Zakaria CJ (Malaya)
• Appeal allowed
• the respondent's failure to pay the redemption sum in accordance with section 2 of the Fourth Schedule tantamount to a failure to pay the balance of the purchase price. That certainly constituted a breach of the SPA
• the parties to the SPA has agreed that time shall be of the essence of the agreement (see cl 22 of the SPA). Resp promised to pay the redemption sum on or before 11 July 2000 and failed to do so at or before the specified time. Therefore, under s 56(1), the agreement, or so much of it as has not been performed, becomes voidable at the option of the appellants.
THE END