DIN8782_OEE_OPI
Transcript of DIN8782_OEE_OPI
Performance Ratingof Production Facilities
2
Contents
� Scope of rating
� Losses in production
� General time model
� DIN 8782
� OEE
� OPI
� Example
� Perspective of filling line manufacturer
3
Scope of rating
� Depending on the perspective of the person asking for a certain figure the
scope of rating differs tremendously:
4
Scope of rating
� Based on the perspective and the sector of industry many terms and figures
are determined, e.g.:
� Efficiency
� Effectiveness
� Utilization factor
� Availability
� Performance efficiency
� Overall Equipment Effectiveness
� Overall Performance Indicator
� …
5
Losses in production
Reasons for losses in production can be split up generally:
Not scheduled time
Unscheduled time
Scheduled downtime
Prod. changeover
Breakdown
Reduced speed
Rejects
Weekend, public holiday, ...
No order, No activity (NoNa)
Training, maintenance, overhaul, cleaning, ...
Clearing production, set up of machines, ...
- Machine breakdowns (malfunction)
- NON-machine breakdowns (maloperation of personnel,missing utilities, poor quality of material to be processed, ...)
Reduced speed of master machine due to lack of product
Faulty fill height / label position, damaged packaging, ...
6
General time model
Unscheduled
Scheduled downtime
Product changeover
Breakdown
Reduced speed
Rejects
Total time (Kalenderzeit)
Manned time (geplante Personalzeit)Not
scheduled
Loading time (Arbeitszeit)
Available production time (Betriebszeit)
Operating time (Laufzeit)
Production time
Eff. Prod. time
Source: Dr.-Ing. T. Voigt
7
DIN 8782 (Beverage industry)
Scheduled downtime
Product changeover
Breakdown(NON- machine)
Working time(Arbeitszeit)
Operating time(Betriebszeit)
General running time(Allgemeine Laufzeit)
Effective running time
- Breakdown(machine)
- Red. speed
Utilization factor of filling line
Efficiency of filling line
Rejects(master)
8
Overall Equipment Effectiveness (OEE)
Original OEE:
Extended OEE:
9
Overall Equipment Effectiveness (OEE)
Source: Dr.-Ing. T. Voigt
10
Extended Overall Equipment Effectiveness
Source: Dr.-Ing. T. Voigt
11
Overall performance Indicator (OPI)
12
Overall performance Indicator (OPI)
Source: Dr.-Ing. T. Voigt
13
Comparison of indicators (Example)
Gantt chart of 1 week
Not scheduled time
Unscheduled time
Scheduled downtime
Prod. changeover
Breakdown
Reduced speed
Rejects
2880
450
560
960
120
160
470
Production 4480
Status Min.
Source: Dr.-Ing. T. Voigt
14
Comparison of indicators (Example)
* No distinction between machineand non-machine breakdowns
Source: Dr.-Ing. T. Voigt
15
Conclusion
Qualification of index:
� DIN 8782:
� Tender documents, acceptance test of filling line (line efficiency)
� OEE:
� Convenient index for ongoing technical controlling by owner/operator
� OPI:
� Comprehensive concept for benchmark of different production facilities
applied by owner/operator
16
Perspective of filling line manufacturer
� Guarantee of filling line efficiency according to DIN 8782
� This index allows a clear distinction of performance reducing impacts
(responsibility of the manufacturer and owner/opperator is clearly
defined for the beverage industry; e.g. splitting up of breakdown
reasons)
� Performance Optimization Service (POS)
� This service detects and eliminates bottlenecks and weak spots at
production facility by analysing intralogistics (storage facilities, material
handling, loading processes, etc.)
� POS is performed by an task related team of experts using latest
analysis and simulation tools
Thank you very muchfor your attention!