Transcript of Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but...
![Page 1: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/1.jpg)
RISK MANAGEMENT IN
SOFTWARE DEVELOPMENT
Dillon Hasselmann
![Page 2: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/2.jpg)
“When a project is successful, it is not because there are no problems, but
that the problems were overcome”
![Page 3: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/3.jpg)
Roadmap
What is a Risk? Elements of Risk Management
Risk IdentificationRisk AnalysisRisk Treatment
Responsible Risk Analysis
![Page 4: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/4.jpg)
What is Risk?
![Page 5: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/5.jpg)
What is a Risk?
A risk is “The likelihood of an event, hazard, threat, or situation occurring and its undesirable consequences”IEEE Standard 1540-2001
![Page 6: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/6.jpg)
Characteristics
UncertaintyProbability of occurrence
Associated LossWhat happens when it materializes?
ManageableHuman intervention can have an influence
![Page 7: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/7.jpg)
What is Risk Management?
Main Goal: Identify and respond to potential problems with enough time to avoid a crisis
![Page 8: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/8.jpg)
How is it Done?
Identify risk factors
Analyze factors to estimate probability and possible impact(s)
Develop treatment options to deal with risks if they should become problems
Monitor risks on an ongoing basis
![Page 9: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/9.jpg)
Issues in Managing Risk
Process is complexNot everyone knows probability
Limited insight“Crystal balls rarely found on sale”
Projects are just trying to get completedDevelopers don’t want to deal with problems
which haven’t materialized“Pay to fix” problems mentality
![Page 10: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/10.jpg)
Issues in Managing Risk
Culture of OrganizationFocus on optimization over dealing with
issuesRisk denialTroublemakers
![Page 11: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/11.jpg)
Common Risks and Preventions
Costly late fix to a productEarly verification and design work
Tons of bugs and defectsCode reviews and testing
Poor communication among the developersStatus reports and group meetings
![Page 12: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/12.jpg)
Risk vs. Project Management
Project management deals with common risks found over the years which are present on nearly every project
Risk management deals with risks which are unique to a specific project
![Page 13: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/13.jpg)
Elements of Risk Management
![Page 14: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/14.jpg)
Elements of Risk Management
Risk IdentificationWhat are the risks and impacts?
Risk AnalysisPlans for dealing with risks
Risk Mitigation/TreatmentActually dealing with the problem
![Page 15: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/15.jpg)
Risk Identification
![Page 16: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/16.jpg)
Risk Identification Organized approach to determine actual risks
to a project
NOT: Dreaming up crazy schemes which will almost never occurWhat if the sun blows up tomorrow?
At the same time, do not ignore severe risks just because they’re too severe and no one would know what to doWhat if a runaway truck hits our senior engineer?
![Page 17: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/17.jpg)
How do we go About Finding Risks?
2 paradigmsDirect: find root cause and then work
towards impacted areas
Indirect: Look at areas of impact and work backwards to possible root causes
![Page 18: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/18.jpg)
Another Approach
Where do we look for risks?Traditional or folk knowledgeLearn from othersCommon senseResults of tests
![Page 19: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/19.jpg)
Common Risk Factors
Organization Estimation Monitoring Development Methodology Tools Reliability Personnel
![Page 20: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/20.jpg)
Types of Risks
Cost
Schedule
Requirements
Quality
Operational
![Page 21: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/21.jpg)
Schedule Risks
Make an activity network
From http://syque.com/improvement/Activity%20Network.htm
![Page 22: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/22.jpg)
Cost Risks
Bad estimates
Requirements creep
Uncertain requirements
Unreasonable budgets
![Page 23: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/23.jpg)
Requirements Risks
Incorrect requirements
Inconsistent requirements
Very difficult requirements
Unverifiable requirements
Unclear requirements
![Page 24: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/24.jpg)
Quality Risks Unreliable: Frequently breaks
Unusable: Too much effort to use
Unmaintainable: Hard to find and fix errors
Non-Portable: Only works in 1 environment
Non-Expandable: Can’t add new functionality
![Page 25: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/25.jpg)
Operational Risks
Main cause: Development environment different from operating environmentProduct satisfies requirements, but doesn’t
satisfy customer
![Page 26: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/26.jpg)
Many risks belong to more than one category!
What if we have to add more developers half-way through the project?
Cost? Salary and benefits
Schedule?Training
Quality? Unfamiliar with requirements
![Page 27: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/27.jpg)
Risk Analysis
![Page 28: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/28.jpg)
Risk Analysis
Primary goal is to uncover the cause and effects of risks and develop possible means to mitigate the problem should the risk become one
Subset of Risk Identification- sometimes you do both steps at the same time
![Page 29: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/29.jpg)
Risk Exposure RE = probability * cost
Note that these are estimates!
Attempt to assign a monetary value to a risk
Generally, do not spend more than the calculated exposure to prevent the risk
From Hasker: Prioritize the risks that have high probability, high cost, then
high probability low cost. These are much more likely to have an impact on your
project
![Page 30: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/30.jpg)
How is Risk Analysis Carried Out? One way- A risk list
Easy way to keep track of problems that might creep up
But does not list any possible solutionsBetter than nothing
Better Option- Risk Action ListSame as risk list, but with possible solutions
![Page 31: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/31.jpg)
How is Risk Analysis Carried Out?
A more ideal alternative: watch list or risk registryTrigger eventActions taken to avoid a problemPerson(s) responsible for taking action
Goal: Assess the impacts of risks
![Page 32: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/32.jpg)
Watch ListTrigger Event Action Taken Responsible
Person(s)
Code does not compile
Conduct code reviews to find the errors
Bob
Engineers unfamiliar with implementation language
Training by a certain date
Team leader
Budget overrun Talk with executive board to receive additional funding
Jack, Jill
Note that these can be sorted in order of priority
![Page 33: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/33.jpg)
Treatment
![Page 34: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/34.jpg)
Risk Treatment
Risks which have become (or about to become) problems are dealt with
This separates the men from the boys - does the team crumble when things go wrong? Or work together to solve the problem?
How is it different from risk analysis?Analysis: Brainstorming possible solutionsTreatment: Carrying out a solution
![Page 35: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/35.jpg)
Five Techniques
Risk Avoidance
Risk Acceptance
Problem Control and Prevention
Risk Transfer
Refinement of Knowledge
![Page 36: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/36.jpg)
Risk Avoidance
Select lower risk requirement over one with higher risk
Advantages?Easy to doIn some cases, eliminates the risk completely
Disadvantage?May not satisfy what the customer wants
![Page 37: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/37.jpg)
Risk Acceptance Accept the consequences of the risk/problem
Hoping that the problem won’t destroy the project Advantage?
Don’t have to change requirementsThere could be other benefits from doing the project
a specific way Disadvantage?
What if the problem is much worse than anticipated
“I am aware of the risk yet I choose to accept it because of potential benefits”
![Page 38: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/38.jpg)
Problem Control and Prevention
Aware of the risk, but measures are taken to reduce the chances of it surfacing as a problem and its impact
Essentially alternate solutions to problems
Disadvantage?Requires the development of a plan and the
effort to track its progress
![Page 39: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/39.jpg)
Risk Transfer
Transfer responsibilities of one task over to someone (or something) else
Advantages?Give the job to someone who can do it
Disadvantages?You may lose control over a portion of your
project
![Page 40: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/40.jpg)
Refinement of Knowledge Ongoing activity to reduce uncertainty
Not a “true” risk handling method
TechniquesPrototypingModelingBenchmarkingStudying
![Page 41: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/41.jpg)
Treatment ExamplesRisk Avoidance Acceptance Control Transfer Knowledge
Refinement
Getting shot by someone with a gun
Don’t live in states without gun control laws
Assume someone else will get shot instead
Wear a bulletproof vest
Health Insurance
Learn self defense
Memory Leaks
Use Java Hope that the memory leaks don’t destroy the program
Use leakwatcher.h to search for memory leaks
Have someone else code portion of project
Learn about pointer management
Take CS 263
![Page 42: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/42.jpg)
Other Issues
How do you know if your project was a failure?Not as easy as “we didn’t finish”
What if our product isn’t used?Satisfies requirements, but…
Possible solution?Responsible risk analysis
![Page 43: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/43.jpg)
Responsible Risk Analysis
![Page 44: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/44.jpg)
Responsible Risk Analysis The focus is on the stake holders
Anyone who interacts or is otherwise involved with the product
Think in terms of user interaction instead of “does it work”?
What type of software is being developed?Business?Commercial?Medical?
![Page 45: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/45.jpg)
Example: Traffic Controller Direct traffic approaching a bridge to
least crowded lanes
How is it judged to be successful?Does it cause accidents?Did it speed up traffic flow?Was it done on time?Did it stay within the budget?
![Page 46: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/46.jpg)
Example: Traffic Controller Despite being judged “successful”, the
project ended up being a failure
During periods under excessive load, the system would get out of synch and crashRequired a reboot periodically
Acknowledged by developerBut never fixed to satisfy time/budget
constraints
![Page 47: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/47.jpg)
Quantitative vs. Qualitative
Most developers focus on quantitativeMost are universal among projectsEngineers are taught to recognize theseMost of us are very mathematically inclined
Professor at Carnegie Mellon Institute of Software Engineering defines good software as “usable, reliable, defect free, cost effective, and maintainable”
“Tunnel vision” of only seeing quantitative
![Page 48: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/48.jpg)
But What About Qualitative? These may or may not affect if your project gets
finished
May have much more severe consequences if overlookedCan cause death!
Example: Aegis Radar SystemSuccessful in terms of budget, schedule, requirementsTerrible user interface blamed for a missile hitting a
commercial aircraft
![Page 49: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/49.jpg)
References Barki, H., Rivard, S., & Talbot, J. (1993). Toward an Assessment of
Software Development Risk. Journal Of Management Information Systems, 10(2), 203-225.
Christensen, M. (2001). The Project Manager's Guide to Software
Engineering's Best Practices. Washington: IEEE.
Gotterbarn, D., & Rogerson, S. (2005). RESPONSIBLE RISK ANALYSIS
FOR SOFTWARE DEVELOPMENT: CREATING THE SOFTWARE DEVELOPMENT IMPACT STATEMENT. Communications Of AIS, 2005(15), 730-750.
Karolak, D. (1998). Software Engineering Risk Management. Washington: IEEE.
Pennington, R., & Tuttle, B. (2007). The Effects of Information Overload on Software Project Risk Assessment. Decision Sciences, 38(3), 489-526.
![Page 50: Dillon Hasselmann. “When a project is successful, it is not because there are no problems, but that the problems were overcome”](https://reader035.fdocuments.us/reader035/viewer/2022062320/56649d995503460f94a837e0/html5/thumbnails/50.jpg)
Do You Have Any Questions?