DIGITAL MIGRATION JOURNEY
PRESENTATION TO THE CTO CONFERENCE
13 February 2012
DTT MIGRATION MAP: SENTECH’s Location: ACTIVITIES
2
DTT Regulations
BDM Policy
Frequency Plan
Channel Licensing
Radio Stations
TV Channels
Service Information
for EPG
Interactive Content
Playout Coding and Multiplexing
Contribution Linking
Transmitter Network
STB Control System
DVB-T2 Standard Approval
Revise MHEG Profile
EPG User Interface
Revise STB Standard
for DVB-T2
Manufacture STBs
Conformance Testing
Trademark Certification
Wholesale Distribution
STB subsidy
Consumer Messaging
Marketing Channels Retail
FTA Platform
Brand
Installations
On-ground support
Go-Live
Award STB RFP
Platform Management
DoC Direct All Broadcasters FTA Broadcasters
SENTECH USAASA SAPO
STB Manufacturers
ICASA
SABS
CPE Installers Retailers All
Customer Contracts
Acknowledgement: SABC
DTT MIGRATION MAP: SENTECH’s Location: ACTIVITIES
3
DTT Regulations
BDM Policy
Frequency Plan
Channel Licensing
Radio Stations
TV Channels
Service Information
for EPG
Interactive Content
Playout Coding and Multiplexing
Contribution Linking
Transmitter Network
STB Control System
DVB-T2 Standard Approval
Revise MHEG Profile
EPG User Interface
Revise STB Standard
for DVB-T2
Manufacture STBs
Conformance Testing
Trademark Certification
Wholesale Distribution
CPE subsidy
Consumer Messaging
Marketing Channels Retail
FTA Platform
Brand
Installations
On-ground support
Go-Live
Award STB RFP
Platform Management
Activities that SENTECH is directly responsible for
Activities that SENTECH is directly participating in
Activities that SENTECH is indirectly participating in
Customer Contracts
SENTECH DTT MIGRATION MAP: Internal Activities: DESCRIPTION
4
Content
Contribution Links
Multiplexing
STB Control
SMS
EPG Applications
Satellite Uplink
Satellite Space
Satellite Reception
PIE Transmitter Combiner &
Feeder Cables
Antenna
Civil Mechanical Electrical
Security Monitoring Operational Readiness
SITE x 183
New Upgrade Optimize New/Upgrade New/Upgrade
New
New
New/Upgrade
New
New New Upgrade/New
Upgrade Upgrade
Upgrade
New
Broadcasters’ responsibility
SENTECH DTT MIGRATION MAP: Internal Activities: STATUS
5
Contribution Links
Multiplexing
STB Control
Satellite Uplink
Satellite Space
Satellite Reception
PIE Transmitter Combiner &
Feeder Cables
Antenna
Civil Mechanical Electrical
Security Monitoring Operational Readiness
SITE x 183
New Upgrade Optimize New/Upgrade New/Upgrade
New
New
New/Upgrade
New
New New Upgrade/New
Upgrade Upgrade
Upgrade
New
On going and under higher levels of risk management
On going and on track
DIGITAL TERRESTRIAL TELEVISION (DTT): Provincial Rollout for Financial Year 2012/2013
6
DIGITAL TERRESTRIAL TELEVISION (DTT): Provincial Rollout for Financial Year 2013/2014
7
CUSTOMER ENGAGEMENTS: Coverage Example: SABC
8
SABC 3 DTT Mux 1 Population Covered 37 580 832 43 970 922
% of Total Population 75.2 87.9 % Change 17%
Geographic Coverage (km²) 377 770 789 020
% of Total RSA Area 29.7 62.1 % Change 109%
Number of sites 104 183
SABC 2 DTT Mux 1 Population Covered 41 268 816 43 970 922
% of Total Population 82.5 87.9 % Change 7%
Geographic Coverage (km²) 742 390 789 020
% of Total RSA Area 58.4 62.1 % Change 6%
Number of sites 179 183
SABC 1 DTT Mux 1 Population Covered 40 711 270 43 970 922
% of Total Population 81.4 87.9 % Change 8%
Geographic Coverage (km²) 581 940 789 020
% of Total RSA Area 45.8 62.1 % Change 36%
Number of sites 146 183
All SABC channels will be transmitted from the same sites, with varying degrees of increases in both population and geographic coverage.
Analogue TV DTT
We are in discussion with the other two commercial broadcasters in finalizing their coverage areas. We do note however that there are some regulatory
issues that have to be dealt with due to the nature of DTT, the manner of the current allocations on the multiplexors and considerations for maximizing the
utilization of spectrum resources (including geographically) and ensuring the continued viability of the investments that are being made by the company in
the distribution network.
STATUS UPDATE: Citizen Support: Technical
9
Only 4 million of 12 million TV owning households are used to the complex
home environment that will come with digital terrestrial television;
The remaining 8 million households will need support as they get used to the
increased complexity in the homes;
SENTECH has been asked by the DTT Project Office to assist in the
establishment of a contact center that will provide citizen support on all matters
technical, including but not limited to matters related to signal reception and the
general increased technical complexity of the home environment . The work is
at an initial stage but the center should be in production by the time STBs arrive
into the mass market.
The Home DTT Migration
Content support
Logistic support
Technical support
4 FTA channels
1 power cable
1 remote control
1 indoor signal cable
Picture Quality:
Grades A, B or C
20 FTA channels
2 power cables
2 signal cables
2 remote controls
New outdoor aerial
STB : a new device
Picture Quality:
Grades A or Nothing
Images sourced from the Internet. Copyright belongs to respective owners.
STATUS UPDATE: Towards the September 2012 Technical Launch
10
The soft launch of terrestrial reception can be at any of the
green places shown above. Simultaneously, the soft launch of satellite reception can be at
any of the white places shown above. The core of the SKA area
already does not have coverage and the demonstration/soft
launch can confirm non-interfering reception of the digital
broadcasting services.
DTH Demonstration: SKA Core
DTT Demonstration
SENTECH SOC Limited
Provincial Project Status Per Site - Gauteng
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 12
Sites 1. Pretoria 2. Sunnyside 3. Welverdiend 4. Pretoria North 5. Menlo Park 6. Helderkruin 7. Johannesburg 8. Heidelberg 9. Linmeyer 10. Mondeor 11. Mulbarton 12. Bez Valley
Provincial Project Status Per Site – Free State
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 13
1. Kroonstad (83%) 100% Building
92% Electrical
96% Mechanical
58% Transmitter
100% Combiner
0% PIE
0% Commissioning (29/11/12)
PIE Prototype delivered. PIE shipped to site 23/12.
73%
Provincial Project Status Per Site – Free State
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 14
2. Suidrand (82%) 100% Building
44% Electrical
96% Mechanical
58% Transmitter
100% Combiner
0% Commissioning (14/12/12)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11. To be deployed by 14/12
73%
Provincial Project Status Per Site – Free State
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 15
3. Bethlehem (90%) 100% Building
92% Electrical
58% Transmitter
100% Combiner
0% PIE
100% Antenna Replacement
0% Commissioning (14/12/12)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11. To be deployed by 14/12
73%
Provincial Project Status Per Site – Free State
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 16
4. Senekal (74%) 100% Building
89% Electrical
58% Transmitter
100% Combiner
0% PIE
0% Commissioning (14/12/12)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11. To be deployed by 14/12
73%
Provincial Project Status Per Site – Free State
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 17
5. Boesmanskop (74%) 100% Building
89% Electrical
58% Transmitter
100% Combiner
0% PIE
0% Commissioning (14/12/12)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11. To be deployed by 14/12
73%
Provincial Project Status Per Site – Free State
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 18
6. Dewetsdorp (70%) 75% Civils
100% Electrical
0% Combiner
0% Commissioning (14/12/12)
Site Acquisition Awaiting municipality approval. Continuing work at risk PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11. To be deployed by 14/12
73%
Provincial Project Status Per Site – Free State
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 19
7. Ficksburg Town (16%) 100% Building
0% Electrical
17% Mechanical
50% Transmitter
0% Combiner
0% Commissioning (14/12/12)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11. To be deployed by 14/12
73%
Provincial Project Status Per Site – Free State
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 20
8. Ladybrand (75%) 100% Building
90% Electrical
9% Transmitter
100% Combiner
0% Commissioning (14/12/12)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11. To be deployed by 14/12
73%
Provincial Project Status Per Site – Free State
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 21
9. Petrus Steyn (82%) 100% Building
88% Electrical
58% Transmitter
100% Combiner
0% PIE
0% Commissioning (14/12/12)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11. To be deployed by 14/12
73%
Provincial Project Status Per Site – Free State
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 22
10. Springfontein (66%) 100% Building
50% Electrical
78% Mechanical
17% Transmitter
100% Combiner
0% PIE
0% Commissioning (14/12/12)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11. To be deployed by 14/12
73%
Provincial Project Status Per Site – Free State
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 23
11. Witsieshoek (66%) 100% Building
87% Electrical
22% Mechanical
17% Transmitter
0% Combiner
0% PIE
0% Commissioning (14/12/12)
Site Acquisition Awaiting municipality approval. Continuing work at risk Power Escalation to Eskom in place. Mitigation plan in place with SBG. Impact – Cost. PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11. To be deployed by 14/12
73%
Provincial Project Status Per Site - Limpopo
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 24
1. Tzaneen (87%) 100% Electrosys
88% Building
100% HVAC
96% Electrical
9% Transmitter
71% Combiner
0% PIE
0% Commissioning (22/01/13)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
39%
Provincial Project Status Per Site - Limpopo
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 25
2. Dzamba (51%) 51% STG
88% Electrical
35% Mechanical
0% Transmitter
0% Combiner
0% Commissioning (13/02/13)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
39%
Provincial Project Status Per Site - Limpopo
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 26
3. Gaba (18%) 15% Building
37% STG
15% Electrical
11% Mechanical
0% Transmitter
0% Combiner
0% PIE
0% Move old equipment
0% Commissioning (29/03/13)
Site Issues Communication issues with local chief resolved. Lessons learnt to be applied to all future sites. Power Escalation to Eskom in place. Mitigation plan in place with SBG. Impact – Cost. PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
Recovery plan in place for lost time due to site issues Mitigation plan for power issues in hand
39%
Provincial Project Status Per Site - Limpopo
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 27
4. Malamba (44%) 0% Container
60% STG
92% Electrical
0% Mechanical
20% Transmitter
0% Combiner
0% Commissioning (31/01/13)
39%
Provincial Project Status Per Site - Limpopo
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 28
5. Nylstroom (77%) 55% STG
99% Electrical
100% Mechanical
100% Transmitter
100% Combiner
100% Commissioning (21/01/13)
39%
Provincial Project Status Per Site - Limpopo
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 29
6. Sibasa (22%) 42% Building
20% Electrical
0% Mechanical
0% Transmitter
0% Combiner
0% Move old equipment
0% PIE
0% Commissioning (27/03/13)
Recovery plan in place for lost time due to site issues Mitigation plan for power issues in hand
Site Issues Communication issues with local chief resolved. Lessons learnt to be applied to all future sites. Power Escalation to Eskom in place. Mitigation plan in place with SBG. Impact – Cost. PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
39%
Provincial Project Status Per Site - Limpopo
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 30
7. Tolwe (15%) 20% Building
24% Electrical
0% Mechanical
0% Transmitter
0% Combiner
0% Move old equipment
0% PIE
0% Commissioning (20/03/13)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
39%
Provincial Project Status Per Site - Limpopo
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 31
8. Tsamavudzi (11%) 10% Building
21% Electrical
0% Mechanical
0% Transmitter
0% Combiner
0% Move old equipment
0% PIE
0% Commissioning (29/03/13)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
39%
Provincial Project Status Per Site - Mpumalanga
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 32
1. Davel (46%) 73% Building
37% Electrical
0% Mechanical
58% STG
0% Transmitter
0% PIE
100% Combiner
0% Sat Dishes
0% Commissioning (14/12/12)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
22%
Provincial Project Status Per Site - Mpumalanga
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 33
2. Carolina (28%) 10% Building
51% Electrical
11% Mechanical
53% STG
0% Transmitter
0% PIE
0% Combiner
0% Commissioning (14/12/12)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11. STG and Electrical Delay in control panels = delay in electrical works. Catch up in January
22%
Provincial Project Status Per Site - Mpumalanga
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 34
3. Dullstroom (35%) 100% Building
11% Electrical
53% STG
0% Transmitter
0% PIE
100% Combiner
0% Commissioning (25/01/13)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
22%
Provincial Project Status Per Site - Mpumalanga
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 35
4. Mbuzini (17%) 11% Building
0% Electrical
53% STG
0% Mechanical
0% Transmitter
0% PIE
0% Combiner
0% Commissioning (29/03/13))
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
22%
Provincial Project Status Per Site - Mpumalanga
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 36
5. Piet Retief (25%) 22% Building
18% Electrical
53% STG
13% Mechanical
0% Transmitter
0% PIE
0% Combiner
0% Commissioning (08/03/12)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
22%
Provincial Project Status Per Site - Mpumalanga
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 37
6. Volksrust (37%) 99% Building
13% Electrical
53% STG
10% Mechanical
0% Transmitter
0% PIE
0% Combiner
0% Commissioning (28/02/13))
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11. STG and Electrical Delay in control panels = delay in electrical works. Catch up in January
22%
Provincial Project Status Per Site - Mpumalanga
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 38
7. Hetorspruit (23%) 99% Building
13% Electrical
53% STG
10% Mechanical
0% Transmitter
0% PIE
0% Combiner
0% Commissioning (28/02/13))
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
22%
Provincial Project Status Per Site - Mpumalanga
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 39
8. Standerton (1%) 50% Planning
0% Building
0% Electrical
0% Mechanical
0% Transmitter
0% Combiner
0% Commissioning (18/02/13))
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
22%
Provincial Project Status Per Site - Mpumalanga
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 40
9. Lydenburg (0%) 0% Building
0% Electrical
0% Mechanical
0% Transmitter
0% Combiner
0% Commissioning (11/02/13))
22%
Provincial Project Status Per Site - Mpumalanga
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 41
10. Sabie (0%) 0% Building
0% Electrical
0% Mechanical
0% Transmitter
0% Combiner
0% Commissioning (11/02/13))
22%
Provincial Project Status Per Site – KZN
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 42
1. Verulam (12%) 100% Electrical
100% Mechanical
100% Antenna
2% Transmitter
100% Combiner
0% Commissioning (06/12/12))
40%
Provincial Project Status Per Site – KZN
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 43
2. Donnybrook (6%) 5% Building
3% Electrical
0% Mechanical
0% Transmitter
100% Combiner
0% PIE
0% Commissioning (06/02/13))
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
40%
Provincial Project Status Per Site – KZN
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 44
3. Pietermaritzburg (99%) 100% CMEE
100% VSAT Terminal
100% Building
100% Electrical
100% Mechanical
100% Transmitter
83% Combiner
96% PIE
0% Commissioning (12/12/12))
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
40%
Provincial Project Status Per Site – KZN
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 45
4. Vryheid (23%) 2% Building
2% Electrical
100% Mechanical
0% Transmitter
0% Combiner
0% PIE
0% Commissioning (28602/13))
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
40%
Provincial Project Status Per Site – KZN
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 46
5. Eshowe (80%) 100% Building
83% Electrical
100% Mechanical
0% Transmitter
100% Combiner
0% PIE
100% Antenna Replacement
0% Commissioning (14/12/12))
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
40%
Provincial Project Status Per Site – KZN
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 47
6. Greytown (34%) 6% Building
2% Electrical
100% Mechanical
0% Transmitter
0% Combiner
0% PIE
0% Commissioning (14/12/12))
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
40%
Provincial Project Status Per Site – KZN
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 48
7. Mooirivier (20%) 100% Building
2% Electrical
0% Transmitter
0% Combiner
0% PIE
0% Commissioning (25/12/12)))
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
40%
Provincial Project Status Per Site – KZN
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 49
8. Ubombo (48%) 100% Building
42% Electrical
0% Transmitter
0% Combiner
0% PIE
0% Commissioning (18/12/12)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
40%
Provincial Project Status Per Site – KZN
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 50
9. Empangeni (11%) 100% Building
5% Electrical
25% Mechanical
0% Transmitter
0% Combiner
0% Monitoring
0% Commissioning (18/12/12)
40%
Provincial Project Status Per Site – KZN
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 51
10. Estcourt (56%) 100% Building
21% Electrical
100% Mechanical
0% Transmitter
0% Combiner
0% Commissioning (29/01/13)
40%
Provincial Project Status Per Site – KZN
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 52
11. Greytown Dorp (0%) 0% Transmitter
0% Combiner
0% Commissioning (14/12/12)
40%
Provincial Project Status Per Site – KZN
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 53
12. Howick (41%) 100% Building
5% Electrical
100% Mechanical
0% Transmitter
0% Combiner
0% Monitoring
0% Commissioning (05/02/13)
40%
Provincial Project Status Per Site – KZN
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 54
13. Kokstad (42%) 100% Building
5% Electrical
100% Mechanical
0% Transmitter
0% Combiner
0% Monitoring
0% Commissioning (19/02/13)
40%
Provincial Project Status Per Site – KZN
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 55
14. Ladysmith (8%) 100% Building
5% Electrical
14% Mechanical
0% Transmitter
0% Combiner
0% Monitoring
0% Commissioning (23/01/13)
40%
Provincial Project Status Per Site – KZN
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 56
15. Loskop (11%) 100% Building
6% Electrical
16% Mechanical
0% Transmitter
0% Combiner
0% Commissioning (01/02/13)
40%
Provincial Project Status Per Site – KZN
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 57
16. Louwsberg (24%) 100% Building
4% Electrical
0% Transmitter
0% Combiner
0% PIE
0% Commissioning (26/12/12)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
40%
Provincial Project Status Per Site – KZN
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 58
17. Matatiele (32%) 100% Building
15% Electrical
25% Mechanical
0% Transmitter
0% Combiner
0% Monitoring
0% Commissioning (21/12/12)
40%
Provincial Project Status Per Site – KZN
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 59
18. Newcastle (63%) 100% Building
86% Electrical
82% Mechanical
0% Transmitter
0% Combiner
0% Commissioning (19/02/13)
40%
Provincial Project Status Per Site – KZN
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 60
19. Nongoma (24%) 78% Building
4% Electrical
18% Mechanical
0% Transmitter
0% Combiner
0% Monitoring
0% Commissioning (28/02/13)
40%
Provincial Project Status Per Site – KZN
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 61
20. Nqutu (15%) 21% Building
15% Electrical
3% Mechanical
0% Transmitter
0% Combiner
0% PIE
0% Commissioning (25/03/13)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
40%
Provincial Project Status Per Site – KZN
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 62
21. Pongola (15%) 100% Building
21% Electrical
14% Mechanical
0% Transmitter
0% Combiner
0% Commissioning (19/02/13)
40%
Provincial Project Status Per Site – KZN
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 63
22. Qudeni (15%) 21% Building
3% Electrical
15% Mechanical
0% Transmitter
0% Combiner
0% PIE
0% Commissioning (27/03/13)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
40%
Provincial Project Status Per Site – EC
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 64
1. Aliwal North (7%) 100% Planning
0% Building
0% Electrical
53% STG
0% Mechanical
0% Transmitter
0% Combiner
0% PIE
0% Commissioning (28/02/13)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
6%
Provincial Project Status Per Site – EC
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 65
2. Butterworth (8%) 100% Planning
0% Building
0% Electrical
53% STG
0% Mechanical
0% Transmitter
0% Combiner
0% PIE
0% Commissioning (28/02/13)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
6%
Provincial Project Status Per Site – EC
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 66
3. Suurberg (1%) 100% Planning
0% Building
0% Electrical
0% Mechanical
0% Transmitter
0% Combiner
0% PIE
0% Commissioning (20/02/13)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
6%
Provincial Project Status Per Site – EC
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 67
4. Mount Ayliff (2%) 2% Building
2% Electrical
2% Mechanical
0% Transmitter
0% Combiner
0% PIE
0% Commissioning (28/02/13)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
6%
Provincial Project Status Per Site – EC
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 68
5. King Williams Town (1%) 100% Planning
0% Building
0% Electrical
0% Mechanical
0% Transmitter
0% Combiner
0% PIE
0% Commissioning (29/03/13)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
6%
Provincial Project Status Per Site – EC
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 69
6. Queenstown (9%) 100% Planning
0% Building
0% Electrical
20% STG
0% Mechanical
0% Transmitter
0% Combiner
0% PIE
0% Feeder & U-Link
0% Commissioning (29/03/13)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
6%
Provincial Project Status Per Site – EC
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 70
7. Umtata (16%) 0% Planning
22% Building
0% Electrical
53% STG
0% Mechanical
0% Transmitter
0% Combiner
0% PIE
0% Commissioning (26/03/13)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
6%
Provincial Project Status Per Site – EC
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 71
8. Kirkwood (5%) 82% Planning
0% Site Acquisition
0% Building
0% Electrical
53% STG
0% Mechanical
0% Transmitter
0% Combiner
0% PIE
0% Commissioning (28/02/13)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11. New Site Evaluation of new site proposal curretnly in progress
6%
Provincial Project Status Per Site – EC
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 72
9. Kareedouw (1%) 100% Planning
0% Building
0% Electrical
0% Mechanical
0% Transmitter
0% Combiner
0% PIE
0% Commissioning (29/03/13)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
6%
Provincial Project Status Per Site – EC
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 73
10. Port St Johns (0%) 0% Planning
0% Building
0% Electrical
0% Mechanical
0% Transmitter
0% Combiner
0% Commissioning (14/02/13)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
6%
Provincial Project Status Per Site – North West
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 74
1. Schweizer Reneke (84%) 97% Building
98% Electrical
89% STG
97% Mechanical
100% Transmitter
100% Combiner
0% PIE
0% Commissioning (14/12/12)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11. To be deployed by 14/12
60%
Provincial Project Status Per Site – North West
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 75
2. Christiana (34%) 13% Building
16% Electrical
89% STG
12% Mechanical
0% Transmitter
100% Combiner
0% PIE
0% Commissioning (07/03/13)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
60%
Provincial Project Status Per Site – WC
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 76
1. George (40%) 100% Electrosys
100% Building
6% Electrical
86% Mechanical
0% Transmitter
0% Combiner
0% PIE
0% Commissioning (18/03/13)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
54%
Provincial Project Status Per Site – WC
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 77
2. Piketberg (38%) 100% Electrosys
14% Building
31% Electrical
37% Mechanical
0% Transmitter
0% Combiner
0% PIE
0% Feeder & U-Link
0% Commissioning (18/03/13)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
54%
Provincial Project Status Per Site – WC
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 78
3. Grabouw (79%) 100% Antennas
77% Building
58% Electrical
79% Mechanical
0% Transmitter
91% Combiner
99% Linking
0% Commissioning (18/03/13)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
54%
Provincial Project Status Per Site – WC
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 79
4. Kleinmond (26%) 86% Building
16% Electrical
36% HVAC
0% Transmitter
91% Combiner
0% Linking
0% Commissioning (28/02/13)
54%
Provincial Project Status Per Site – WC
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 80
5. Knysna (16%) 1% Electrical
100% Mechanical
32% STG
0% Transmitter
0% Combiner
0% Linking
0% Commissioning (18/03/13)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
54%
Provincial Project Status Per Site – WC
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 81
6. Montagu (18%) 86% Building
8% Electrical
31% Mechanical
0% Transmitter
0% Combiner
0% Monitoring
0% Commissioning (29/03/13)
PIE Prototype delivered. PIE shipped to sites at 4 per week from 26/11.
54%
Provincial Project Status Per Site – NC
SENTECH SOC LIMITED | Corporate Plan_MTEF 2012 - 2015 82
No sites form part of the 80%
0%