Diecraft Australia
-
Upload
mahdi-hossain -
Category
Education
-
view
113 -
download
1
Transcript of Diecraft Australia
DIECRAFT AUSTRALIA PTY. LTD.: A CASE STUDY
Prepared by:
Md. Rezwanur Rahman Majumdar Id#110304
Md. Rafsan Jani Id#110313
Mahdi Hossain Id#110335
OUTLINE
• Diecraft at a Glance
• Market & Competition
• Product Offerings
• Order Processing
• Engineering Design Process
• Manufacturing Process
• Final Assembly Cell
• Plant Loading
• Production Scheduling
• Findouts from emergency meeting
• Solutions
DIECRAFT AT A GLANCE
6, Radford Rd, Reservoir VIC, 3073, Australia
DIECRAFT AT A GLANCE
Founded by John Rabin in 1953, known as Rabin Engineering
Producing High Quality Moulds for the Plastic Industry & Others since 1961
Purchased by Tupperware in 1963; named as Diecraft Australia; Moved to Reservoir; Continued producing high quality till now
MARKET & COMPETITION
Tupperware: The Major Customer
Tupperware accounted for more than 90% turnover by supplying over 14
countriesStiff competition from
Korea, Portugal & Japan
Competitors have faster turnaround times and lower
prices to the customers
PRODUCT OFFERINGS
Moulds
New mould
Standard Non Standard
Conversion
PRODUCT OFFERINGS (CONT.)
Lead time: 15 weeks for a standard mould and 17 weeks for a non-standard mould.
Annual production capacity:
130-150 moulds, which included 20-30 conversions.
Less expensive soft steel moulds, easier and faster to make but low quality.
ORDER PROCESSING
Bidding Process.
Request For Quote(RFQ)
Detail Drawings And Due Date
Inclusion of Mould Concept by Customer
Company.
RFQ Forwarded To Sales Engineer
Kick-off Meeting
Tentative Schedule
ENGINEERING DESIGN PROCESS:
Time requirement for a detailed design:100 and 300 hours.
Physical requirements: Bolster plates, hot runner, cores, cavities and strippers.
CAD:Detailed design in computer aided design(CAD).
Programming:Writing the codes for computer-numerically-controlled(CNC) machines.
Engineering
MANUFACTURING PROCESS
Job shop type of operation
Two shift productionThe Bolster cell & unit cells manufactured in parallel
Three stages in machining operation:• Turning, milling, drilling• Heat treatment by vendors• Finishing operation, demanding close tolerance
and precision machining, on EDM machines.
Sent to Quality Assurance Section for verification
FINAL ASSEMBLY CELL
Responsible for fitting the bolster plates and
units components
Sent to test center, put the mold into
action
Sample of final plastic product sent for
customer approval,
After approval, mold shipped to customer.
Assembly operation might take 50-1000
hours.
Total manufacturing process might require
1700 hours on average, including
300 hours of design.
PLANT LOADING
Capacity 125 moulds per year Detailed plan for the next 14-15 weeks Driven primarily by delivery commitments, processing requirements, assumptions related to complement of labour and machine resources available.
Recognizing potential mismatch between available capacity and proposed work load.
PRODUCTION SCHEDULING
Details scheduling involves: Disintegration of tasks Assigning tasks to workers Scheduling of overtime Subcontracting some tasks
Top concerns: Utilization of workers and satisfactory performance with due date
commitments
Reducing lead times Recording & updating done in real time and reviewed weekly
FINDOUTS FROM EMERGENCY MEETINGRequests for engineering changes during mould processing increase completion time
Holding a job waiting for customer clearance
Adding more permanent skilled labour may increase cost
Lump order creates domino effects and causes inordinate delays.
SOLUTIONS
Customer should adhere to the initial design submitted.
All the engineering change requests while product processing must include extension of product delivery date.
Customer should be informed about before the date of clearance
Hiring a few number of labour additionally
Increasing work shift to three
And to have a maximum order acceptance limit in each quarter.
THANK YOU