    PILOT PROJECT 3:

    Detention Storage Cum Rainwater Harvesting System at DID

    Headquarters, Kuala Lumpur

    THE HEADQUARTERS OF DEPARTMENT OF

    IRRIGATION AND DRAINAGE(DID), KUALA LUMPUR

    Underground storage

    tank underconstruction

    MAIN COMPONENT OF RAINWATERHARVESTING SYSTEM

    Gutter

    Catchments area(roof)

    Downspouts

    and piping Underground Storage Tank

    Underground

    storage tank

    1

  • 7/28/2019 DID's HQ Complex Rwhs

    2/5

    DEPARTMENT OF IRRIGATION

    AND DRAINAGE (DID)

    HEAD-QUARTERS COMPLEX

    Storage tank

    Roof as catchments area

    Undergroundstorage tank

    DID HEAD-QUARTERS COMPLEX

    Consists of a block

    of 4-storied which

    is the standard

    office building with

    flat roof

    Roof of this

    building is attached

    via central gutter

    (size of 600 mm in

    depth)

    60% of the water

    collected will flow

    into central gutter

    Collected water

    will discharge to

    the perimeter drain

    at ground level

    Rainwater flow

    into two of 150

    mm rainwater

    downpipe.

    Downpipe

    Roof as catchments area

    2

  • 7/28/2019 DID's HQ Complex Rwhs

    3/5

    The system uses

    a header tank on

    the roof of the

    building

    The water is

    store in

    underground

    storage tank

    Rainwater from downpipe

    Header tank

    Underground

    storage tank

    Tankinstallation

    Toilet flushing

    Main component of

    rainwater harvesting system

    Catchments system

    Filtering system

    pump

    Header tank

    Internal plumbingConveyance system

    Storage tank

    3

  • 7/28/2019 DID's HQ Complex Rwhs

    4/5

    Components of rainwater harvesting

    system distribution network

    Internal Plumbing (Diagrammatic)

    Toilet flush

    External

    Installation ofInstallation of

    Detention Storage Cum Rainwater Harvesting SystemDetention Storage Cum Rainwater Harvesting System

    at DID Headquarters, Kuala Lumpurat DID Headquarters, Kuala Lumpur

    JPSJPS HqHq. Building Roof Area:. Building Roof Area: 1,688.85 m1,688.85 m22 (calculated)(calculated)

    Total JPSTotal JPS HqHq. staff:. staff: 250 (est.)250 (est.)

    Average water use per person:Average water use per person: 25 liters/day.25 liters/day.

    Total water use per day:Total water use per day: 250 x 25 = 6,250 liters/day.250 x 25 = 6,250 liters/day.

    storage tank size:storage tank size:

    (Say 3 days water storage):(Say 3 days water storage): 6,250 x 3 = 18,750 lit6,250 x 3 = 18,750 lit

    Water for plants (25m.sq):Water for plants (25m.sq): 6.3 litres/m6.3 litres/m22/day(est.)/day(est.)

    4

  • 7/28/2019 DID's HQ Complex Rwhs

    5/5

    Installation ofInstallation of

    Detention Storage Cum Rainwater Harvesting SystemDetention Storage Cum Rainwater Harvesting System

    at DID Headquarters, Kuala Lumpurat DID Headquarters, Kuala Lumpur

    Tank Size (m3) Reliability (%)

    40 57.53

    50 60.74

    60 63.64

    70 66.31

    80 67.95

    90 69.67

    100 70.93

    110 72.02

    120 72.98

    Tank Size Vs Reliability

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    0 20 40 60 80 100 120 140

    Tank Size (cu. m)

    Reliabilty(%)

    Reliability (%)

    Installation ofInstallation of

    Detention Storage Cum Rainwater Harvesting SystemDetention Storage Cum Rainwater Harvesting System

    at DID Headquarters, Kuala Lumpurat DID Headquarters, Kuala Lumpur

    To determine the critical storm duration for Detention Storage Size RequiredCs = 1

    td (min) I (mm/h) Runoff Coeff Area (m2) Qd (l/s)

    Qbefore

    (PSD)

    T= 10 yr c d SSR (m3)

    5 380 0.91 1688 162.2 41.1 124.94 6.09 40.81

    10 263 0.91 1688 112.3 41.1 237.61 17.61 52.04

    15 208 0.91 1688 88.8 41.1 340.61 33.39 57.46

    20 175 0.91 1688 74.5 41.1 434.88 53.05 60.14

    25 152 0.91 1688 64.7 41.1 520.94 76.33 61.26

    30 135 0.91 1688 57.5 41.1 599.14 103.09 61.40

    35 122 0.91 1688 51.9 41.1 669.75 133.20 60.88

    40 111 0.91 1688 47.5 41.1 732.95 166.59 59.92

    45 103 0.91 1688 43.8 41.1 788.90 203.18 58.66

    50 95 0.91 1688 40.7 41.1 837.74 242.93 57.20

    55 89 0.91 1688 38.0 41.1 879.56 285.77 55.61

    60 84 0.91 1688 35.8 41.1 914.46 331.67 53.94

    65 79 0.91 1688 33.8 41.1 942.52 380.60 52.25

    Site S torage Requirement (SSR) = 0.06(Qdtd-c -d)

    c= 0.675PSDtd(1-0.392PSD/Qd)

    d= 0.117tdPSD2/Qd

    5