Transcript of DIAMOND MINING PROJECT, PANNA(M.P.)
A VOCATION TRAINING REPORT ON UNDERGROUND COAL MINES S.E.C.L. CHURCHA (R.O.)
A VOCATION TRAINING REPORTONDIAMOND MINING PROJECT,PANNA (M.P.)
PRESENTED BY:-ASHISH KU.VISHWAKARMA
CONTENTS1. INTRODUCTION2. HOW TO REACH MINE3. MINE PROFILE4. geology5. SURVEY 6. MINE PLAN7. unit operation of mines 8. processing plant 9. civil work10. environmental work11. SAFETY FEATURE12. accidental case13. reference
INTRODUCTION
DIAMOND MINING PROJECT MAJHGAWAN, PANNA IS A PROJECT OF NATIONAL MINERAL DEVELOPMENT CORPORATION (NMDC)
HOW TO REACH THE MINES
MINE PROFILE
year OF OPENING NUMBER OF BENCHESLEASeHOLD AREARL OF SURFACERL OF BOTTOMWIDTH OF BENCHESHEIGHT OF BENCHESDEPTH OF MINESINCIDENCE OF DIAMONDTYPE OF DIAMONDBLASTING PATTERNEXPLOSIVE USEDPER BLASTING COAL PRODUCEDTYPE OF MACHINE USED
GEOLOGYMain intact-Type of DepositType of materialOverburdenSuper group
SURVEYRL.BENCHESDEPTHINSTRUMENT USED SHAFT INFORMATION
MINE PLANTailing dump Stock pilesScale of mine planMining leaseOther neccesary things
UNIT OPERATION OF MINESDRILLLINGBLASTINGLOADINGHAULING
DRILLING
Drill machine.Depth of drilling.Burden & spacing.Diameter of holes.Time required for one hole.
BLASTINGTypes of explosive used.
Stemming.
Connection
LOADINGShovel 1.No of shovel 2.Capacity of shovel 3. Operation Loader 1.No of loader 2.Capacity of shovel 3.Operation
HAULINGDUMPER 1.No of dumper 2.Capacity of dumper 3. Types of brake
PROCESSING PLANT
CIVIL WORK
ENVIRONMENTAL WORK Panna tiger reserveThree test are conducted 1.Ground water monitoring 2.water quality 3.Environmental quality monitoring a.Noise b.Surface water quality c.Ambient air quality
ACCIDENTAL ANALYSISS.N YEAR FATAL SERIOUS REPORTABLE01.2011 - - -02.2012 - - -03.2013 - - -04.2014 - - -05.2015 - - -06.2016 - - -