DGR EA Follow-Up Monitoring Program - Sub Domain Site Geologic... · in a long-term management...
Transcript of DGR EA Follow-Up Monitoring Program - Sub Domain Site Geologic... · in a long-term management...
DGR EA Follow-up Monitoring Program March 2011 Prepared by: Nuclear Waste Management Organization NWMO DGR-TR-2011-10
DGR EA Follow-up Monitoring Program March 2011 Prepared by: Nuclear Waste Management Organization NWMO DGR-TR-2011-10
EA Follow-Up Monitoring Program - ii - March 2011
This page has been left blank intentionally
EA Follow-Up Monitoring Program - iii - March 2011
Document History
Title: DGR EA Follow-Up Monitoring Program
Report Number: NWMO DGR-TR-2011-10
Revision: R000 Date: March 2011
Nuclear Waste Management Organization
Prepared by: J. Jacyk
Reviewed by: D. Barker, R. Heystee
Approved by: A. Castellan, I. Pritchard
EA Follow-Up Monitoring Program - iv - March 2011
THIS PAGE HAS BEEN LEFT BLANK INTENTIONALLY
EA Follow-Up Monitoring Program - v - March 2011
EXECUTIVE SUMMARY
Ontario Power Generation (OPG) is undergoing a multi-year planning and regulatory approvals process for a deep geologic repository (DGR) for the long-term management of low and intermediate level waste (L&ILW). As part of the regulatory approvals process for the DGR Project, an environmental assessment (EA) of the long-term management of L&ILW has been conducted and is documented in the Environmental Impact Statement (EIS) (OPG 2011a). This follow-up monitoring program has been prepared to support the EIS.
The EA follow-up monitoring program is designed to ensure that the predictions of effects are validated during the implementation of the project. If the effects are adverse, then further mitigation and contingency procedures will be considered. This follow-up monitoring program addresses the site preparation and construction, and operations phases of the project.
This report focuses on the EA follow-up monitoring program, which is summarized in Tables 3a and 3b. However, because of the interconnected nature of the environmental monitoring framework, the components of three other programs are also discussed where appropriate to provide a complete picture of the environmental monitoring for the DGR project as a whole. A summary of these components is presented in Table 1. The environmental monitoring framework encompasses four groups of monitoring activities:
1. EA follow-up monitoring (Tables 3a and 3b). 2. Environmental Management Plan (EMP) monitoring (Tables 4a and 4b). 3. Radiological regulatory monitoring (Tables 5a and 5b). 4. Conventional regulatory monitoring (e.g., provincial requirements, federal permits and
Certificates of Approval) (Table 6).
Because the detailed project design has not been finalized, some of the activities may become irrelevant or redundant, and additional items may be required as the project progresses. Input received from regulators will also be incorporated into the applicable monitoring programs which will be updated accordingly. In addition to the four groups of monitoring activities, additional baseline monitoring (Table 2) will be conducted prior to and during construction in order to acquire information and data with which future monitoring results can be compared.
The EIS (OPG 2011a) identifies a number of residual adverse effects: decreased flow in the North Railway Ditch; increased flow in the drainage ditch at Interconnecting Road during the site preparation and construction and operations phases; loss of a small quantity of eastern white cedar; loss of a small portion of habitat for redbelly dace, creek chub, variable leaf pondweed and burrowing crayfish within the DGR Project footprint; degradation in air quality during the site preparation and construction, and operations phases; increase in noise levels at Baie du Doré during site preparation and construction; exposure to acrolein in air during the site preparation and construction phase; and a diminished quality or value of activities undertaken by Aboriginal peoples at the Aboriginal Burial site located at the Bruce nuclear site resulting from changed aesthetics and increased noise and dust during the site preparation and construction and operations phases.
Although each of these effects was assessed to be not significant, monitoring programs are planned to confirm these predictions and assess the effectiveness of the mitigation measures. Monitoring programs are also planned to verify predictions that the DGR Project will not result in adverse effects to the environment.
EA Follow-Up Monitoring Program - vi - March 2011
Summary tables for each of the monitoring programs are provided. Activities are presented separately for each of the two project phases: site preparation and construction; and operations. The tables include a brief description of the activity, the objective of the monitoring, the relevant EA statement, the type of monitoring, the relevant criteria, and the frequency and location of the activity.
An assessment of the annual performance (i.e., effectiveness of the sampling) of the EA follow-up monitoring program will be completed in conjunction with the preparation of the annual report for the site preparation and construction phase follow-up monitoring, as well as during the operation phase.
A program evaluation of the core components of the EA follow-up monitoring program will be conducted once every five years, or once during each project phase, as a minimum to ensure that the program remains effective and relevant.
EA Follow-Up Monitoring Program - vii - March 2011
THIS PAGE HAS BEEN LEFT BLANK INTENTIONALLY
EA Follow-Up Monitoring Program - viii - March 2011
TABLE OF CONTENTS
Page
EXECUTIVE SUMMARY .............................................................................................................. v
1. INTRODUCTION ............................................................................................................... 1
1.1 DESCRIPTION OF THE PROJECT ...................................................................... 1
1.2 PROJECT SCHEDULE ......................................................................................... 1
1.3 PURPOSE OF THE EA FOLLOW-UP MONITORING PROGRAM ...................... 1
1.4 ENVIRONMENTAL MONITORING FRAMEWORK .............................................. 2
1.5 EA FOLLOW-UP MONITORING ........................................................................... 2
1.6 ENVIRONMENTAL MANAGEMENT PLAN MONITORING ................................. 3
1.7 RADIOLOGICAL REGULATORY MONITORING ................................................. 3
1.8 CONVENTIONAL REGULATORY MONITORING................................................ 4
1.9 REPORT STRUCTURE ......................................................................................... 4
2. SURFACE WATER MONITORING .................................................................................. 5
2.1 SAMPLING ............................................................................................................ 5
2.2 VISUAL INSPECTION ........................................................................................... 6
2.3 FLOW RATE MEASUREMENTS .......................................................................... 7
2.4 REGULATORY REQUIREMENTS ........................................................................ 7
3. GROUNDWATER MONITORING ..................................................................................... 8
3.1 GROUNDWATER QUALITY ................................................................................. 8
3.2 HYDRAULIC HEAD MONITORING ...................................................................... 9
3.3 ZONE OF INFLUENCE AND SHAFT DRAWDOWN ............................................ 9
3.4 DEWATERING VOLUMES ................................................................................... 9
3.5 GEOSCIENTIFIC DATA VERIFICATION PLAN ................................................. 10
3.6 REGULATORY REQUIREMENTS ...................................................................... 10
4. SOIL QUALITY MONITORING ....................................................................................... 11
4.1 REGULATORY REQUIREMENTS ...................................................................... 11
5. TERRESTRIAL SPECIES MONITORING ...................................................................... 12
EA Follow-Up Monitoring Program - ix - March 2011
5.1 REGULATORY REQUIREMENTS ...................................................................... 12
6. AQUATIC SPECIES MONITORING ............................................................................... 13
6.1 REGULATORY REQUIREMENTS ...................................................................... 13
7. ATMOSPHERIC MONITORING ..................................................................................... 14
7.1 UNDERGROUND AIR MONITORING PROGRAM ............................................. 14
7.2 SURFACE AIR MONITORING PROGRAM ........................................................ 14
7.3 NOISE MONITORING ......................................................................................... 15
7.4 VIBRATIONS MONITORING .............................................................................. 15
7.5 REGULATORY REQUIREMENTS ...................................................................... 16
8. RADIOLOGICAL MONITORING .................................................................................... 17
8.1 RADIOLOGICAL ANALYSIS OF AIR ................................................................. 17
8.2 RADIOLOGICAL ANALYSIS OF GROUNDWATER .......................................... 17
8.3 RADIOLOGICAL ANALYSIS OF SURFACE WATER ....................................... 17
8.4 WORKER DOSE AND CONTAMINATION CONTROL ...................................... 18
8.5 REGULATORY REQUIREMENTS ...................................................................... 18
9. MALFUNCTION AND ACCIDENTS PREVENTION FOLLOW-UP ................................ 19
9.1 REGULATORY REQUIREMENTS ...................................................................... 19
10. SOCIO-ECONOMIC FOLLOW-UP ................................................................................. 20
10.1 REGULATORY REQUIREMENTS ...................................................................... 20
11. ABORIGINAL INTERESTS FOLLOW-UP ...................................................................... 21
11.1 REGULATORY REQUIREMENTS ...................................................................... 21
12. DETAILED SAMPLING PLAN ........................................................................................ 22
13. CONTINGENCY PROCEDURES ................................................................................... 23
13.1 SURFACE WATER ............................................................................................. 23
13.2 GROUNDWATER ................................................................................................ 24
13.3 TERRESTRIAL ENVIRONMENT ........................................................................ 25
13.4 AQUATIC ENVIRONMENT ................................................................................. 25
13.5 ATMOSPHERIC ENVIRONMENT ....................................................................... 25
EA Follow-Up Monitoring Program - x - March 2011
13.6 ABORIGINAL INTERESTS ................................................................................. 26
13.7 SOCIO-ECONOMIC ENVIRONMENT ................................................................. 26
13.8 SPILLS ................................................................................................................ 26
14. BASELINE STUDIES AND PRE-CONSTRUCTION FOLLOW-UP ................................ 27
15. RECORD KEEPING AND REPORTING ........................................................................ 28
15.1 EA FOLLOW-UP REPORTS ............................................................................... 28
15.2 EMP MONITORING REPORT ............................................................................. 28
15.3 RADIOLOGICAL REGULATORY MONITORING REPORTS ............................ 28
15.4 CONVENTIONAL REGULATORY MONITORING REPORTS ........................... 28
16. PROGRAM ASSESSMENT ............................................................................................ 29
17. REFERENCES ................................................................................................................ 30
APPENDIX A: Environmental Monitoring Summary Tables
EA Follow-Up Monitoring Program - 1 - March 2011
1. INTRODUCTION
Ontario Power Generation (OPG) is undergoing a multi-year planning and regulatory approvals process for a deep geologic repository (DGR) for the long-term management of low and intermediate level waste (L&ILW). Currently, the L&ILW produced as a result of the operation of OPG’s nuclear reactors is stored centrally at OPG’s Western Waste Management Facility (WWMF) located on the Bruce nuclear site. Although current storage practices are safe and could be continued safely for many decades, OPG’s long-term plan is to manage these wastes in a long-term management facility. Throughout this report, OPG’s proposal is referred to as the “DGR Project”.
As part of the regulatory approvals process for the DGR Project, an environmental assessment (EA) of the long-term management of L&ILW has been conducted and is documented in the Environmental Impact Statement (EIS) (OPG 2011a). This follow-up monitoring program has been prepared to support the EIS. The guidelines for the EIS for the DGR Project require that the proponent include a framework on which effects monitoring and follow-up actions will be based for the life of the project, should it proceed. The environmental monitoring framework, which includes EA follow-up monitoring, has been prepared to address the site preparation and construction, and operations phases of the project. A separate environmental assessment is expected to be required for the decommissioning phase and a follow-up monitoring program will be provided as part of that process.
1.1 Description of the Project
The DGR Project includes the site preparation, construction, operation, decommissioning, and abandonment and long-term performance of above- and below-ground facilities for the long-term management of OPG’s L&ILW. Details of the project design are provided in the Preliminary Safety Report (PSR) (OPG 2011b) and Section 4 of the EIS.
1.2 Project Schedule
The construction schedule start date is dependent on the EA review period. Once the EIS review is completed by the joint review panel, the panel will render a licensing decision for a licence to Prepare Site and Construct under the Nuclear Safety and Control Act (NSCA 1997).
The site preparation and construction phase of the project is expected to last five to seven years. The operations phase will follow and is expected to last 40 to 45 years. This timeframe includes a monitoring period subsequent to the final waste emplacement.
1.3 Purpose of the EA Follow-up Monitoring Program
The purpose of the EA follow-up monitoring program is to:
Verify the predictions and assessments of the environmental effects of the project; and Confirm the effectiveness of the mitigation measures.
The EA follow-up monitoring program is designed to ensure that the predictions of effects are validated during the implementation of the project. If the effects are adverse, then further mitigation or regulatory action may be necessary to protect the environment. This follow-up monitoring program addresses the site preparation and construction, and operations phases of the project.
EA Follow-Up Monitoring Program - 2 - March 2011
The EA follow-up monitoring program will be carried-out in accordance with CSA N288.4-10 Environmental Monitoring Programs at Class I Nuclear facilities and Uranium Mines and Mills (CSA 2010), CNSC G-296 Developing Environmental Protection Policies, Programs and Procedures at Class I Nuclear Facilities and Uranium Mines and Mills (CNSC 2006a), and CNSC S-296 Environmental Protection Policies, Programs and Procedures at Class I Nuclear Facilities and Uranium Mines and Mills (2006b).
1.4 Environmental Monitoring Framework
The environmental monitoring framework was developed in accordance with CSA N288.4-10, CNSC S-296 and CNSC G-296 and encompasses four groups of monitoring activities:
1. EA follow-up monitoring (Tables 3a and 3b). 2. Environmental Management Plan (EMP) monitoring (Tables 4a, 4b and 4c). 3. Radiological regulatory monitoring (Tables 5a and 5b). 4. Conventional regulatory monitoring (e.g., provincial and federal requirements, permits and
approvals) (Table 6).
The following sections present a preliminary description of the activities that will be included in each of the four groups within the framework. Because the detailed project design has not been finalized, some of the activities may become irrelevant or redundant, and additional items may be required as the project progresses. Input received from regulators will also be incorporated into the applicable monitoring programs which will be updated accordingly. In addition to the four groups of monitoring activities, some baseline monitoring (Table 2) will be conducted prior to and during construction in order to acquire information and data with which future monitoring results can be compared.
The objective of the environmental monitoring framework is to ensure that the predictions made in the EA are confirmed, anticipated licensing and legislative requirements are adhered to and best management practice is employed, while minimizing the duplication and overlap of monitoring activities and reporting. A summary of the environmental monitoring components of each of the programs is presented in Table 1.
1.5 EA Follow-up Monitoring
An EA follow-up monitoring activity is further defined in this framework as:
Having a finite duration; and Having an effect or lack of effect that can be monitored or measured.
Though there may be some overlap with another monitoring program, the EA follow-up monitoring program is intended to capture elements that would otherwise not be required (either by licensing or legislation), but satisfy the requirement to confirm an effect (or lack-of), a prediction, an assumption used in assessing the effects, or the effectiveness of a mitigation measure identified in the EIS.
The EIS identified a number of residual adverse effects in the site preparation and construction phase, and the operations phase including:
Decrease in flow in the North Railway Ditch during the site preparation and construction, and operations phases;
EA Follow-Up Monitoring Program - 3 - March 2011
Increase in flow in the drainage ditch at Interconnecting Road during the site preparation and construction, and operations phases;
Loss of a small quantity of eastern white cedar in the site preparation and construction phase;
Loss of small portion of habitat for redbelly dace, creek chub, variable leaf pondweed and burrowing crayfish within the DGR Project footprint in the site preparation and construction phase;
Increase in concentrations of indicators of air quality during the site preparation and construction and operations phases;
Increase in noise levels at Baie du Doré during the site preparation and construction phase; Exposure to acrolein in air during the site preparation and construction of the project; and Diminished quality or value of activities undertaken by Aboriginal peoples at the Aboriginal
Burial site located at the Bruce nuclear site resulting from changed aesthetics and increased noise and dust.
Although each of these effects was assessed to be not significant, monitoring programs will be conducted to confirm these predictions and assess the effectiveness of the mitigation measures. Monitoring programs will also be conducted to verify predictions that the DGR Project will not result in adverse effects to the environment.
All EA follow-up monitoring activities are designed to satisfy a specific statement in the EIS and are expected to be discontinued when the requirement has been satisfied or at the end of a predetermined duration. In some cases, a particular monitoring activity may continue as a best management practice under the EMP, but the reporting requirement as part of the EA follow-up will be discontinued. Results of the activities identified in the EA follow-up monitoring program will be provided to the CNSC and CEAA in an annual EA-follow-up monitoring report, as described in Section 15. Reporting requirements for the other three components of the environmental monitoring framework are also discussed in Section 15.
1.6 Environmental Management Plan Monitoring
The purpose of the EMP monitoring is to confirm that the environmental protection measures inherent in the project design are functioning as designed and to ensure that best management practices are employed, in order to minimize the risk of unforeseen and accident-related environmental effects. The majority of EMP monitoring activities involve visual inspections and record keeping that may also be required for permitting or licensing. Once licensing requirements and permitting requirements have been determined, some of these activities may be transferred from the EMP into the appropriate regulatory monitoring program. The activities included in the EMP monitoring program are not necessarily ‘measurable’ activities, e.g., visual inspections, procedural confirmations, records checks.
The duration of the EMP activities are generally ongoing and specific to the phase of the project. An annual EMP monitoring report will summarize the results and effectiveness of the EMP.
1.7 Radiological Regulatory Monitoring
The environmental monitoring described under the radiological regulatory monitoring program characterizes those activities that have typically been required in the CNSC licence for OPG waste facilities. As these activities are likely to be a requirement of the licence itself, they are not duplicated under the EA follow-up monitoring program even if they will also serve to confirm
EA Follow-Up Monitoring Program - 4 - March 2011
predictions or effectiveness of mitigation measures presented in the EIS. This grouping of activities is limited to those that can be characterized as environmental monitoring and does not represent a complete list of the typical radiological regulatory requirements for monitoring and/or reporting. The monitoring activities described in Tables 5a and 5b are expected to be ongoing, with a re-evaluation of the monitoring requirements at each licensing phase or at the time of licence renewal.
Included in the radiological regulatory monitoring tables are the radiological monitoring activities that are expected to be reported to the CNSC in the quarterly operation report. The activities align with the current monitoring program at the Western Waste Management Facility (WWMF).
1.8 Conventional Regulatory Monitoring
Conventional regulatory monitoring activities are those that are required by federal or provincial legislation, including those required for a permit or certificate of approval, with the exception of those required for follow-up monitoring under CEAA or those required under licensing (radiological regulatory requirements). Since permit approvals will be obtained once the project design is finalized, the activities presented in this section are an indication of the general scope of the monitoring required, with the understanding that additional details will be provided in the permit applications, and eventually the permits themselves.
1.9 Report Structure
The following sections focus on the EA Follow-up monitoring program, which is summarized in Tables 3a and 3b. However, because of the interconnected nature of the environmental monitoring framework, the components of the three other programs are also discussed where appropriate to provide a complete picture of the environmental monitoring for the DGR project as a whole.
EA Follow-Up Monitoring Program - 5 - March 2011
2. SURFACE WATER MONITORING
Based on the assessment provided in the Hydrology and Surface Water Quality Technical Support Document (TSD) (NWMO 2011a), no adverse effects are predicted for surface water quality provided that the in-design mitigation measures function as expected. Two adverse effects of the DGR Project on hydrology and surface water quantity and flow were identified:
A 31% reduction in surface water quantity and flow in the North Railway Ditch; and A 114% and a 61% increase in surface water quantity and flow in the drainage ditch at
Interconnecting Road for site preparation and construction, and operations, respectively.
However, the magnitudes of these two effects are not expected to be significant.
Additionally, no adverse effect to water quality was predicted provided that the stormwater discharge meets the Certificate of Approval (C of A) criteria.
To verify the assumptions used in predicting the effects, to confirm the predicted effects, and to verify that mitigation is effective, a surface water follow-up monitoring program will include a surface water sampling program, flow rate measurements and a visual inspection program. It is described in the following sections.
2.1 Sampling
Results of a preliminary leachate testing and characterization study (Golder 2011) identified several contaminants of potential concern (COPCs): aluminum, ammonia, boron, cobalt, thallium, vanadium, nitrate, and chloride (salinity). Note that the COPC concentrations in the study would be indicative of COPC concentrations in leachate from the rock pile, and is not representative of the water quality in the pond which is expected to meet the C of A discharge criteria and the relevant Provincial Water Quality Objectives (PWQO) (MOEE 1994a). In order to verify that this prediction is accurate, an EA follow-up sampling program for surface water quality will be undertaken for the COPCs (Tables 3a and 3b).
Surface water samples will be collected from three locations:
The discharge point of the stormwater management pond during site preparation and construction, and operations;
The discharge point of the shaft sump water during site preparation and construction, and operations (at the stormceptor); and
The perimeter drainage ditch near the WRMA, at a location to be determined.
Total dissolved solids (TDS) and electrical conductivity will also be monitored as they are representative of dissolved metals and salinity. Nitrate will be evaluated by analyzing samples for Total Kjeldahl Nitrogen (TKN), and un-ionized ammonia will be calculated based on the total ammonia concentrations, pH and temperature.
Monitoring results for each water quality parameter analyzed will be compared with the relevant discharge criterion. The discharge criteria are based on the PWQO. As a value is not provided in guidance documents for TDS and TKN, a discharge criterion will be determined based on the receiving water body (Lake Huron) background concentrations and an assimilative capacity study (see Table 2) that will be completed as part of an application for a Ministry of Environment (MOE) Certificate of Approval for Industrial Sewage Works (C of A (Sewage)). The
EA Follow-Up Monitoring Program - 6 - March 2011
determination of background values will be based on the number of analyses and period of record and the variability of the data. The 75th percentile of the entire data set (including outliers) will be used to determine the background values. The chloride concentration criterion is based on the “Priority Substances List Assessment Report Road Salt” (CEPA 2001) toxicity values.
The sampling and analysis protocol will adhere to the MOE publication “Protocol for the Sampling and Analysis of Industrial/Municipal Wastewater” (MOE 1999), as amended from time to time by more recently published editions and the publication “Standard Methods for the Examination of Water and Wastewater” (APHA 2005). All samples will be analyzed at a Standards Council of Canada (SCC) and/or Canadian Association of Laboratory Accreditation Inc. (CALA) accredited laboratory.
The sample frequency, duration, parameters and locations are outlined in Tables 3a and 3b.
In addition, regulatory monitoring (see Table 6) will be required for total suspended solids (TSS). In the absence of a parameter-specific PWQO for TSS, values were based on MOE guidance documents B-1-5 Deriving Receiving-Water Based, point-source effluent requirements for Ontario Waters, (MOEE 1994b) and Procedure F-5-1 Determination of Treatment Requirements for Municipal and Private Sewage Treatment Works Discharging to Surface Waters (MOE F-5-1).
2.2 Visual Inspection
A visual inspection of the SWMP will be conducted weekly during the site preparation and construction phase (Table 3a) and monthly during operations (Table 3b). The inspection will ensure that the pond is free of floating and settleable solids and does not contain oil or any other substance in amounts sufficient to create a visible sheen, foam or discoloration. Monthly inspections will be conducted during operations as part of the EMP (see Tables 4a and 4b), and will no longer be required under the EA follow-up Monitoring Program. This activity may also be a requirement of the C of A, and may be transferred from the EMP monitoring program to the conventional regulatory monitoring requirements program (Table 6)
Additionally, the EMP will include a visual inspection of the stormwater management system (including the drainage pipes, swales, run-off area and ditches) conducted weekly during site preparation and construction, and monthly during operations to:
Ensure they do not have extreme erosion wear; Ensure that sediment control materials are kept on hand for emergency response and for
repair and maintenance purposes; and Ensure that the pond is free of floating and settleable solids and does not contain oil or any
other substance in amounts sufficient to create a visible sheen, foam or discoloration or other deleterious substance.
The EMP will also include semi-annual records checks for the stormwater interceptor maintenance program to ensure that the stormwater interceptors are routinely maintained and inspected as per the manufacturer’s recommended schedule.
EA Follow-Up Monitoring Program - 7 - March 2011
2.3 Flow Rate Measurements
The stormwater management pond (SWMP) discharge volume will be measured weekly, averaged monthly and recorded as part of the conventional regulatory monitoring program (Table 6). The method of measurement will be confirmed in the application for a C of A, but may consist of a water level monitoring installation in the pond near the SWMP outlet. The outlet structure could be calibrated so that the discharge flow rates can be determined based on the water level in the pond.
The flow rates will be recorded and compared with the predicted increase in flow in the drainage ditch at Interconnecting Road calculated in the Hydrology and Surface Water Quality TSD (Table 3a). The purpose of this monitoring is to confirm the assumptions used to predict an increase in flow rates of 114% over the existing annual mean flow. As described in the Hydrology and Surface Water Quality TSD, the calculations were based on change in drainage area and not on measured flow rates. The EA follow-up monitoring program will compare flow rates to the baseline values to confirm that the increase in flow in the drainage ditch at Interconnecting Road is similar to or, less than, the predicted increase of 114%. Baseline flow rate values will be recorded (see Table 2) for one year prior to the site preparation and construction phase. Since the highest flows are predicted for the site preparation and construction phase, the follow-up monitoring will be concluded after three years of monitoring. Provided the increase in flow is within the bounds of the EA predictions, the SWMP discharge flow rates will continue to be monitored only if required under the regulatory monitoring program (see Table 6).
Similarly, quarterly (seasonal) flow monitoring of the North Railway Ditch will be conducted at the south eastern Project Area boundary to ensure that there are no significant changes to stream flow at Stream C as a result of the project (see Table 3a). Flow will also be measured during or immediately following two major storm events each year to confirm that the effect of reduced flow in the North Railway Ditch is not significant, as predicted in the Hydrology and Surface Water Quality TSD. Though the flow is predicted to decrease by 31% during site preparation and construction, the effect was assessed as ‘not significant’. Flow data will be collected for one year prior to the start of site preparation and construction (Table 2) and for a minimum of three years after the start of site preparation and construction (Table 3a) to confirm the assumptions made in the EA.
2.4 Regulatory Requirements
A C of A for the stormwater collection system will be required in accordance with Section 53 of the Ontario Water Resources Act (OWRA 1990). Specific monitoring activities and discharge requirements will likely be included as a condition of the C of A.
EA Follow-Up Monitoring Program - 8 - March 2011
3. GROUNDWATER MONITORING
No likely adverse effects on either groundwater flow or quality were identified in the Geology TSD (NMWO 2011b). However, groundwater quality and flow monitoring will be conducted prior to and during site preparation and construction and operations to establish a baseline (see Table 2), to confirm the assumptions made in the EA, and to confirm that there are no adverse effects during the site preparation and construction and operations phases as a result of the WRMA, the SWMP and shaft excavation and dewatering.
EA follow-up monitoring will include hydraulic head and groundwater quality monitoring. The purpose of this monitoring is to confirm the predictions used in the EIS to assess the effects of shaft and repository excavation on the groundwater and solute transport VECs and the water quality VECs, as described in the Geology TSD. The details of the monitoring are provided in Table 3a. If the monitoring results fall within the predictions of the EIS during the site preparation and construction phase, the groundwater monitoring will be transferred to the EMP monitoring program (Table 4b).
No likely adverse effects to the marsh in the northeast portion are predicted, based on the assumptions made in the Geology TSD to estimate the zone of influence during shaft dewatering in the site preparation and construction phase. These assumptions will be verified during the shaft pilot hole and pilot grouting studies prior to construction (Table 2).
Dewatering volumes will also be recorded as part of the conventional regulatory monitoring program (Table 6).
3.1 Groundwater Quality
A sampling program was developed to establish a baseline for the DGR site groundwater quality. The sampling program includes a network of groundwater wells with ongoing quarterly monitoring (see Table 2) and comprises:
Four DGR-series wells (deep and intermediate geology Valued Ecosystem Components (VECs));
Three US-series wells (intermediate and shallow geology VECs); and Eight new shallow groundwater wells, beginning in 2012 (shallow geology VECs).
Sample analysis includes major ions, general chemistry (e.g. pH, temperature, electrical conductivity), trace elements, and petroleum hydrocarbons.
The shallow groundwater monitoring well network of eight wells will be installed and baseline monitoring will be conducted to align with the current groundwater quality monitoring program in some of the US and DGR-series wells (for a description of these wells, refer to the Geology TSD). The network will comprise upgradient and downgradient wells, and will serve as an early detection network of on-site (leachate from the WRMA or SWMP) or off-site groundwater contamination migrating on or through the DGR site. The upgradient wells will be located in areas unaffected by site activities. The well network will also be capable of detecting changes resulting from the SWMP and changes to the water table near the marsh in the northeast portion of the Project Area.
Monitoring of all the wells (shallow groundwater, US-series and DGR-series) will continue through the site preparation and construction phase as part of the EA follow-up monitoring
EA Follow-Up Monitoring Program - 9 - March 2011
program (Table 3a). The EA follow-up groundwater monitoring will be capable of detecting spatial and temporal changes in groundwater quality within the uppermost aquifer beneath the DGR surface structures. In the event that contaminants would be released from any of the DGR facilities into the subsurface environment, it is in this aquifer than any lateral migration of contaminants would first occur.
All samples will be analyzed at a Standards Council of Canada (SCC) and/or Canadian Association of Laboratory Accreditation Inc. (CALA) accredited laboratory. Data will be assessed with an emphasis on identifying abrupt and gradual changes in groundwater quality that potentially indicate impacts from DGR construction and operation. Consideration will be given to the influence of adjacent areas using baseline data collected in advance of facility operation, and using information collected from background wells.
The program will be re-evaluated at the end of the site preparation and construction phase. The program, if continued, will be continued as part of the EMP monitoring program (Table 4b) and will be re-evaluated every 5 years.
3.2 Hydraulic Head Monitoring
EA follow-up monitoring will also include hydraulic head monitoring in some of the existing US and DGR-series wells and the new shallow groundwater wells during site preparation and construction (Table 3a). The monitoring program will begin prior to the site preparation and construction phase to establish a baseline and seasonal variability (Table 2). Hydraulic head monitoring during site preparation and construction will be compared to the baseline monitoring results and will detect any perturbations to the local groundwater system as a result of shaft dewatering. Similar to the groundwater quality monitoring, the program will be re-evaluated at the end of the site preparation and construction phase. The program, if continued, will be continued as part of the EMP monitoring program (Table 4b) and will be re-evaluated every 5 years.
Hydraulic head monitoring may also be a requirement of an MOE Permit to Take Water (PTTW), as summarized in Table 6.
3.3 Zone of Influence and Shaft Drawdown
During the shaft pilot hole investigations and grouting feasibility study (see B-GW-1, Table 2), the groundwater regime in the shafts area will be characterized using a variety of field test methods, and may include: hydraulic conductivity tests, slug tests, and pump tests. The results of this work will be used to calculate the amount of dewatering that will be required during shaft sinking. A key objective of the grouting feasibility study will be to confirm an assumption in the EA that grouting will reduce the effective (bulk) hydraulic conductivities in the top 200 m (i.e. to less than 10-7 to 10-8 m/s). The results of the aforementioned investigations, coupled with modelling, will be used to establish the zone of influence (ZOI) and drawdown characteristics during shaft dewatering. For the purpose of the EA follow-up monitoring program, dewatering refers to the removal of ingress water into the shafts during shaft sinking.
3.4 Dewatering Volumes
Water volumes will be monitored daily during dewatering and total daily flow volumes will be recorded as part of the regulatory monitoring program to confirm that the daily water takings are below the limit in the PTTW, but will also serve to confirm the effectiveness of the advance
EA Follow-Up Monitoring Program - 10 - March 2011
grouting or freezing (Table 6). It is expected that a PTTW will only be required during the site preparation and construction phase, due to the low hydraulic conductivities of the rock and the shaft design itself.
3.5 Geoscientific Data Verification Plan
The Geoscientific Data Verification Plan (NWMO 2011c) provides details of testing and investigations confirming that the geologic/hydrogeologic setting underneath the Bruce nuclear site provides excellent isolation and protection from the repository wastes, as stated in the Gelogly TSD.
3.6 Regulatory Requirements
All new wells will be installed, maintained and monitored in accordance with O. Reg. 903 Wells (Reg. 903).
A PTTW will be required in accordance with Section 34 of the Ontario Water Resources Act and O. Reg. 387/04 – Water Taking (Reg. 387). Water taking will be done in accordance with the regulation and permit requirements, including annual reporting to the Ontario MOE of dewatered volumes by March 31 of every year.
EA Follow-Up Monitoring Program - 11 - March 2011
4. SOIL QUALITY MONITORING
There is no adverse effect predicted for soil quality in the Geology TSD (NWMO 2011b), except in the case of a malfunction or accident (e.g., fuel spill). In case of a spill, depending on the volume and nature of the contaminant released, a subsurface investigation and sampling program may be designed and implemented to determine the presence and extent of contamination. Therefore, soil sampling will be undertaken prior to the site preparation and construction phase in order to establish a baseline (Table 2) with which future soil investigation results can be compared.
Appropriate remediation measures will be implemented if necessary, taking into account the nature of the contaminant, the extent of contamination and the results of any post-spill subsurface investigation. This contingency procedure is addressed in Section 13.
4.1 Regulatory Requirements
Analytical soil quality results from any investigation will be compared with baseline conditions or Table 3 of Soil, Ground Water and Sediment Standards for Use Under Part XV.1 of the Environmental Protection Act (MOE 2009) for a non-potable groundwater condition, as appropriate.
Soil sampling may be required in response to a spill, as defined in Ontario Regulation 675 Classification and Exemption of Spills and Reporting of Discharges (Reg. 675).
EA Follow-Up Monitoring Program - 12 - March 2011
5. TERRESTRIAL SPECIES MONITORING
The residual adverse effect of the DGR Project on eastern white cedar identified in the Terrestrial Environment TSD (NWMO 2011d) is predicted to be ‘not significant’. Monitoring will be conducted for the eastern white cedar communities and wildlife habitat use adjacent to the areas which will be cleared during the site preparation and construction phase. This monitoring will consist of a one-time inspection after the completion of surface facility construction to confirm the significance of the predicted effect, as summarized in Table 3a.
The loss of some of individual white tailed deer and wild turkey as a result of vehicles strikes is predicted in the Terrestrial Environment TSD, though it was not assessed as an adverse effect as there are no changes expected at the population level of either species. In order to confirm that there is no adverse effect, vehicle strikes will be monitored in the follow-up monitoring program and reported as part of the existing Bruce nuclear site reporting program for one year to confirm EA predictions. Vehicle traffic is predicted to peak in the first year of the site preparation and construction phase. Provided the results confirm the EA predictions in the first year, this activity will be discontinued under the EA follow-up monitoring program and will be transferred to the EMP monitoring program (Tables 4a and 4b).
5.1 Regulatory Requirements
All work will be carried out in compliance with the Species at Risk Act (SARA) (SARA 2002), The Fish and Wildlife Conservation Act (FWCA 1997), Migratory Birds Convention Act (MBCA 1994), and the Ontario Endangered Species Act (ESA 2007).
It is expected that OPG will be subject to a number of additional permitting requirements (e.g., Development, Interface with Wetlands, and Alterations to Shorelines and Watercourses) The DGR Project will also required a Tree Cutting Permit from Bruce County.
EA Follow-Up Monitoring Program - 13 - March 2011
6. AQUATIC SPECIES MONITORING
A minor loss of burrowing crayfish habitat is predicted in the Aquatic Environment TSD (NWMO 2011e); however there is alternate suitable habitat for crayfish in most of the moist, low-lying portions of the Project Area.
The aquatic species EA Follow-up monitoring program will include visual inspections, surface water level monitoring, and groundwater well monitoring, as described in Tables 3a and 3b. Visual inspections will be conducted to:
Verify re-growth of riparian vegetation in disturbed areas (ditches); Identify bank stability deficiencies; Verify the presence of crayfish chimneys in the Project Area; and Monitor the marsh for confirmation that excavation does not dewater and affect marsh
habitat.
A staff gauge will be installed in the marsh identified in the northeast portion of the Project Area. Staff gauge readings (water levels) will be measured during dewatering to monitor any drying effect attributable to dewatering activities. Variations outside of seasonal norms will trigger further mitigation (see Section 13.4). Water levels will also be monitored for one year prior to site preparation and construction to establish a baseline (Table 2), as well as post-dewatering until the marsh has been deemed to have fully recovered (should an impact be observed). Groundwater levels will also be monitored in the shallow groundwater well closest to the marsh (see Section 3) to determine water table fluctuations.
During construction of the rail bed crossing, weekly visual inspections will be conducted as part of the EMP monitoring program to confirm that best management practices are undertaken and that regular maintenance of the ditches is completed. The details of the EMP monitoring program are provided in Tables 4a, 4b and 4c.
Monitoring of re-growth of vegetation following construction of the rail bed crossing may be a condition of the In Water Work Permit.
6.1 Regulatory Requirements
All work will be conducted in accordance with Section 35 of the federal Fisheries Act (FA 1985) and Ontario Regulation 169 (Reg.169) under the Conservation Authorities Act (CAA 1990).
Timing of the construction of the rail bed crossing should take place according to the Department of Fisheries and Oceans (DFO) Operational Statement-Timing Windows to ensure that critical life history stages such as spawning activities are protected by restricting the conduct of works or undertakings in and around water at certain times. It is the OMNR that determines the timing windows for a particular watercourse. The South Railway Ditch contains a warm water fish community and the warm water timing window generally begins July 1 and ends March 31. However, in order to minimize the risk for sediment generation and high flow periods, the Saugeen Valley Conservation Authority has recommended an in-water work timing window of July 1 to September 30. In-water work will be scheduled accordingly.
All work will be conducted in accordance with the SARA, and the provincial Endangered Species Act.
EA Follow-Up Monitoring Program - 14 - March 2011
7. ATMOSPHERIC MONITORING
A residual adverse effect is predicted on air quality during the site preparation and construction phase and the operations phase in the Atmospheric TSD (NWMO 2011f). The effect was assessed as “may not be significant”. Monitoring will be conducted in the site preparation and construction phase to ensure that the effect does not exceed the predictions in the assessment. The continuation of the program will be re-evaluated at the end of every year.
A residual adverse effect for noise was also predicted, but was assessed as ‘not significant’. Monitoring will be conducted for noise to confirm the assessment predictions.
In the Human Health Assessment in the EIS, a residual adverse effect was identified for acrolein as a result of air emissions.
Additional monitoring will be conducted to confirm the assumptions used in the assessment and to confirm that no significant effects result from the project. The atmospheric monitoring program comprises follow-up monitoring programs at surface for ambient air emissions, noise emissions and ground vibrations. EMP monitoring includes underground air monitoring. Emissions monitoring at the vent exhaust may be required as part of a C of A (Air) (Table 6).
The atmospheric EA follow-up monitoring program including the tasks, frequency and relevant triggers and criteria is summarized in Tables 3a and 3b. The EMP monitoring program is summarized in Tables 4a and 4b.
7.1 Underground Air Monitoring Program
Air quality of the underground DGR will be monitored under the EMP to ensure that the health and safety of personnel within the DGR is not compromised during underground construction and operations. The monitoring system will verify:
Levels of noxious gases do not exceed regulatory limits; Levels of explosive gases do not exceed explosive limits; Temperature and humidity of the DGR remain acceptable for both personnel health and
infrastructure integrity; and Airflows remain adequate in active work areas.
Air monitoring equipment will be installed. Airflow, CO and NO2 measurements will be monitored at underground locations, to be determined. Explosive gas monitors will also be installed to monitor a range of potential gases, including methane and hydrogen. Instrumentation measuring airflow, temperature, relative humidity, etc. will be installed and measurements will be monitored remotely on surface at the main control room and will also be available to be monitored underground.
7.2 Surface Air Monitoring Program
Continuous air quality monitors will be installed at the start of the site preparation and construction phase at a secure location in the Project Area near the main access road between the construction activities and the property boundary. Several air quality parameters will be monitored: NOx, PM10, and PM2.5. The monitoring results will be compared with the baseline results and predictions documented in the Atmospheric Environment TSD to confirm that the assessment predictions were reasonable and the integrated mitigation measures are effective.
EA Follow-Up Monitoring Program - 15 - March 2011
Continuous sampling will be carried out for a minimum of one year beginning at the start of site preparation and construction, which is the bounding year of the assessment. Continuation of the program will depend on the monitoring results and the data quality. The monitoring program including the tasks, frequency and predicted values and criteria is summarized in Table 3a.
Visual inspections for dust emissions will be conducted daily during site preparation and construction, and operations, at the shafts, access roads within the WRMA, and waste rock pile.
Provided the monitoring values do not exceed the predicted values in the Atmospheric Environment TSD, the significance of the effect will be consistent with the assessment. The predicted values are provided in Table 3a.
There are no current, accurate field methods for measuring acrolein at the levels predicted. However, because acrolein, like NOx is predominantly associated with vehicle emissions, the NOx monitoring will serve as an indicator of the accuracy of the EA predictions for acrolein. For example, if the NOx emissions monitored during the first year of site preparation and construction (the bounding year) are significantly lower than those predicted in the EA, this will serve as an indicator that acrolein is also lower than predicted. Given the relatively low hazard quotient associated with acrolein in the human health assessment of the EA, combined with the conservatism built into the assessment and the temporary nature of the effect, this approach is considered adequate in monitoring the potential effect related to acrolein.
7.3 Noise Monitoring
Integrated sound level meters will be stationed at the three noise receptor locations monitored during the EA field studies (R1, R2, and R3) during the site preparation and construction phase. The results will be compared with the baseline results and predictions documented in the Atmospheric Environment TSD to determine that the assessment predictions were reasonable and the integrated mitigation measures are effective.
During operations, exhaust fans will be maintained in accordance with manufacturer’s specifications. The maintenance records will be verified annually as part of the EMP monitoring program (Table 4b).
7.4 Vibrations monitoring
As a minimum, blasting preparation, design and implementation will take place in accordance with the appropriate requirements, for example the Noise Pollution Control (NPC) publication 119 Model Municipal Noise Control By-law (MOE 1978). In addition the following monitoring and follow-up activities will also occur (Table 3a):
The initial series of regular production blasts shall be monitored at several locations at varying distances from each blast to characterize the site specific ground vibration attenuation rates. This will entail establishing monitoring stations between the blast site and adjacent receptors during the initial series of shaft blasts. The site specific attenuation data developed during this monitoring period will then be used to better define ground vibration effects at the closest sensitive receptors.
Subsequent routine monitoring of all blasting operations will be carried out in the vicinity of the closest receptors to the blasting operations. As excavation continues within the shaft and underground development, the actual monitoring locations will be routinely and
EA Follow-Up Monitoring Program - 16 - March 2011
regularly reviewed so that the closest receptors are always being monitored for ground vibration effects.
The program may be discontinued based on consistently low vibration measurements once the shaft is advanced below 180 mBGS.
A communications program may be implemented to keep neighbours informed of the status of activity, as appropriate. During blasting near surface, blasting should take place during daylight hours.
7.5 Regulatory Requirements
Most industrial processes, equipment or modifications to industrial processes and equipment require A C of A (Air). A C of A for the ventilation shaft exhaust may be required in accordance with Section 9 of the EPA (EPA 1990). Regardless of compliance with Section 9, every facility is also required to meet the air quality standards, as stated in Ontario Regulation 419/05 (Reg 419).
Underground air quality monitoring for noxious gases will confirm compliance with Ontario Regulation 854 Mines and Mining Plants (Reg 854).
Annual reporting may be required in accordance with Ontario Regulation 127 Airborne Contaminant Discharge Monitoring and Reporting Regulation (Reg. 127) and the National Pollution Release Inventory (NPRI) as legislated in Sections 46 to 50 of the Canadian Environmental Protection Act (CEPA 1999). The regulatory monitoring is summarized in Table 6.
EA Follow-Up Monitoring Program - 17 - March 2011
8. RADIOLOGICAL MONITORING
No residual adverse effects were predicted in the Radiation and Radioactivity TSD (NWMO 2011g). However, monitoring is required as a licensing condition and the results will confirm the assumptions used in the assessment and that no adverse effects result from the DGR project. Note that all radiological monitoring is conducted under the radiological regulatory monitoring program (Tables 5a and 5b).
The radiological monitoring program comprises monitoring of air, surface water, groundwater and workers. The comprehensive radiological monitoring program will be implemented as described in the PSR. The monitoring activities described in this section are limited to those that are applicable to environmental media. These activities are summarized in Tables 5a and 5b.
8.1 Radiological Analysis of Air
During site preparation and construction (shaft sinking and excavation of emplacement rooms), and operations, air monitoring underground for radon will ensure that worker exposure to radon is limited. During operations, radioactivity (tritium, particulate and carbon-14) will also be monitored in the vent exhaust air.
In addition, an external radiation monitoring program will be carried out during the site preparation and construction, and operations phases.
8.2 Radiological Analysis of Groundwater
Radiological analysis will be carried out for samples collected from newly-built monitoring wells described in Section 3.1 to monitor any changes to groundwater radionuclide concentrations in the DGR Project Area, namely tritium and gross beta levels. Wells will be sampled quarterly during site preparation and construction, and operations. This program will be consistent with the existing WWMF monitoring program.
8.3 Radiological Analysis of Surface Water
Water samples collected from surface water will be analyzed to determine radionuclide concentrations in surface water during the site preparation and construction phase and the operations phase. Samples will be collected monthly from the SWMP and from the marsh during site preparation and construction to monitor the potential effect resulting from the operations at the WWMF and other nuclear facilities in the Local Study Area and to establish a baseline for the operations phase. Samples will be analyzed for tritium and gross beta. During operations, samples will be collected and analyzed monthly for tritium and gross beta. The operations phase sampling can be coordinated with the existing monitoring program at the WWMF.
Samples from the sump discharge will be collected weekly and averaged monthly for tritium and gross beta beginning one year prior to operations (to establish a baseline).
A sample will also be collected from the sump discharge and from the SWMP quarterly and analyzed for C-14 beginning one year prior to operations, to establish a baseline for the operations phase. During operations, samples will be collected and analyzed annually. Sample locations, frequency and criteria are summarized in Tables 5a and 5b.
EA Follow-Up Monitoring Program - 18 - March 2011
8.4 Worker Dose and Contamination Control
A routine survey program will be conducted to ensure that the DGR remains in compliance with the requirements of the Radiation Protection Requirement (OPG 2001) and the OPG Radiation Protection Procedures.
Quarterly dose accumulation in workers will be monitored, consistent with current practice at the WWMF.
8.5 Regulatory Requirements
The radiation protection program described in the PSR and the EA follow-up monitoring program will comply with the radiation protection program requirements of the following Acts and regulations as applied to licensed OPG facilities and licensed OPG activities:
Nuclear Safety and Control Act; General Nuclear Safety and Control Regulations (SOR/2000-202); Radiation Protection Regulations (SOR/2000-203); Class I Nuclear Facilities Regulations (SOR/2000-204); Nuclear Substances and Radiation Devices Regulations (SOR/2000-207); and Occupational Health and Safety Act (Ontario) (OHSA1990).
EA Follow-Up Monitoring Program - 19 - March 2011
9. MALFUNCTION AND ACCIDENTS PREVENTION FOLLOW-UP
In most cases, it is predicted that no adverse effects will occur unless there is an accident or malfunction. In order to prevent malfunctions and accidents from occurring, the EMP monitoring program will include an ongoing evaluation of site management practices.
The monitoring program includes visual inspections and records checks. It comprises verification that proper safety procedures and accident prevention programs are in place based on good industry management practice, such as:
Equipment is properly maintained; Proper environmental training is in place; and Emergency equipment and procedures are tested.
The malfunctions and accidents prevention monitoring program consists of a checklist of good industry management practice (Table 4c) that will be verified in the field.
9.1 Regulatory Requirements
All spills, as defined by Ontario Regulation 675 Classification and Exemption of Spills and Reporting of Discharges (Reg. 675), will be reported in accordance with Sections 15 and 92 of the Ontario Environmental Protection Act (EPA 1990).
EA Follow-Up Monitoring Program - 20 - March 2011
10. SOCIO-ECONOMIC FOLLOW-UP
No residual adverse effects were identified in the Socio-economic Environment TSD (NWMO 2011h). However, given the central role that public attitudes play in determining whether or not socio-economic effects occur and their magnitude, EA follow-up monitoring of public attitudes toward the DGR Project and communication of the results to the public is warranted.
Public attitude research (PAR) will be undertaken to provide directly comparable results to the 2009 PAR, in terms of questions and approach to sampling. At a minimum, the research will be undertaken once during the site preparation and construction phase and subsequent to any accidents or malfunctions of the DGR or associated operations, resulting in a release of radioactive contamination to the environment. During the operations phase, the PAR can be integrated with the PAR for ongoing WWMF operations.
The socio-economic follow-up monitoring program, including the tasks, frequency and relevant criteria, is summarized in Table 3a.
10.1 Regulatory Requirements
In the event a burial site is discovered in the project area, work will proceed in accordance with The Cemeteries Act (CA 1990). The act prohibits the disturbance of a burial site or artefacts associated with the human remains except on instruction of the Coroner or pursuant to a site disposition agreement.
EA Follow-Up Monitoring Program - 21 - March 2011
11. ABORIGINAL INTERESTS FOLLOW-UP
There may be a diminishment of the quality or value of activities undertaken by Aboriginal peoples at the Aboriginal burial site located at the Bruce nuclear site. No follow-up monitoring is required at this time. Activities at the site, based on past experience have been infrequent and the diminishment of activities, if it occurred would be a result of dust and noise, each of which are intermittent. Air quality monitoring is discussed in Section 7.
11.1 Regulatory Requirements
There are no regulatory requirements that are applicable to the aboriginal interests follow-up monitoring program.
EA Follow-Up Monitoring Program - 22 - March 2011
12. DETAILED SAMPLING PLAN
A detailed sampling plan will be developed for each of the field programs summarized in Tables 2 and 3. The programs will include a statistical evaluation of the adequacy of existing baseline data to provide a benchmark against which to test for project effects, and the need for any additional pre-construction or pre-operational monitoring to establish a firmer project baseline.
The sampling plan will also include a statistical evaluation to support the sampling schedule. The evaluation will address the length of time needed to detect effects given estimated baseline variability, likely environmental effect size and the desired level of statistical confidence in the results (Type 1 and Type 2 errors). The statistical evaluation will be completed in accordance with CSA N288.4-10 and US EPA QA/G-9S.
EA Follow-Up Monitoring Program - 23 - March 2011
13. CONTINGENCY PROCEDURES
13.1 Surface Water
If exceedances of the discharge criteria are detected, the SWMP outlet will be closed. Treatment will be applied as appropriate. SWMP water will be tested prior to release to confirm that the treatment is effective and that the discharge criteria are achieved. Daily samples will be collected and analyzed for the first week. Provided there are no exceedances, sampling will revert to the normal frequency. The type of treatment will depend on the parameters that exceed the discharge criteria.
In the event that total suspended solids concentrations exceed the discharge criteria, additional mitigation measures such as additional sediment, erosion and dust control measures can be implemented where appropriate (e.g., additional silt fencing, sediment logs, check dams). This may also be an effective contingency plan to reduce concentrations of some heavy metals such as iron and aluminum which are typically particle-bound.
In the event that a noticeable oil sheen, foam or deleterious substance is noted, the discharge will be closed until the substances can be skimmed off the surface.
The shales that are excavated during shaft sinking have the potential to generate leachate with relatively high salinity. These rocks (about 40,000 m3) will be reused on-site (e.g. as berm material with a soil cap). In the unlikely event that this relatively small amount of the shale material generates leachate with unacceptable levels of salinity, the leachate could be collected and treated.
There are several methods to treat salinity. Some of these methods can also be used to decrease metal and nutrient concentrations. Common treatment applications are listed below:
Membrane treatment, which uses chemically-formed microscopic pores to filter out dissolved ions.
Ion exchange, which uses columns of resins or zeolites to replace, or exchange, unwanted ions. This treatment can be used to remove nitrate as well.
Reverse osmosis, which uses mechanical pressures to force pure water through a semi-permeable membrane, removing dissolved ions.
Distillation, which involves boiling water to produce a vapour. The vapour contacts a cool surface where it condenses as a liquid. Dissolved components remain in the boiling solution, resulting in a vapour comprising only water.
Metals can be treated through chemical precipitation. Metals can form a number of insoluble compounds with hydroxide, carbonate and sulphide anions. The treated water will typically be directed into sedimentation ponds or mechanical thickeners so that the precipitated metals suspended in the water can precipitate and settle out.
Ammonia can be removed through several treatment technologies:
Ion exchange. Breakpoint chlorination which involves the addition of sodium hypochlorite or chlorine in
specific quantities to maximize the oxidation of ammonia to nitrogen gas and nitrate.
EA Follow-Up Monitoring Program - 24 - March 2011
Alkaline stripping, which involves the injection of air into alkaline waters to produce ammonium and ammonia gas, at proportions that are dependent on the temperature and pH.
Nitrification, which involves the biological oxidation of ammonia to, eventually, nitrate. Activated sludge and bio-films are generally used to provide a substrate for the bacteria and produce ideal conditions for the reactions.
Natural degradation, which, depending on the conditions within the stormwater retention pond (i.e. amount of sunlight, temperature, pH, residence time), results in ammonia degradation naturally to nitrate.
Nitrate can be removed by:
Ion exchange; Reverse osmosis; and Denitrification, which involves the conversion of nitrate into free nitrogen through biological
processes.
The retention pond will designed so that it is never dry and will have body of water that is permanently stored in the pond. It will be designed to retain runoff from 6-hour, 25-mm rainfall event on a 23 Ha area for a period of 24 hours. This time is required remove any sediment from the run-off before discharge. The run-off will be controlled by directing flow through a discharge pipe equipped with a valve that could be closed, as required, to stop flow. The final holding capacity of the pond will be confirmed during detailed design.
There will also be a weir at the discharge end of pond with crest set at a higher elevation than the discharge pipe. Assuming that there would be no control structure (e.g. a gate) in this weir, then the weir crest elevation sets maximum volume of run-off water that can be contained in pond if the aforementioned pipe valve is closed. This volume will be confirmed in the detailed design.
13.2 Groundwater
Based on historical monitoring results at the Bruce nuclear site, seasonal variablility in groundwater pathways is not expected in this area. Any such variability, if present, would be detected by the monitoring well network and additional monitoring points installed as required to ensure downgradient detection capability.
Groundwater levels and quality results will be compared with baseline data to determine whether there is an adverse effect of the DGR on groundwater. If an adverse effect is detected, the groundwater monitoring program may be modified to determine the extent of the effect. If a contaminant plume is detected and is attributable to the DGR, depending on the contaminant, hydrogeological conditions and the plume characteristics, remediation may be considered. Groundwater quality results will also be compared to Table 3 of Soil, Ground Water and Sediment Standards for Use Under Part XV.1 of the Environmental Protection Act (MOE 2004) for a non-potable groundwater condition.
Shaft sinking will be conducted using advance grouting or freezing, hence dewatering will be minimized, however a PTTW will be required in case the water taking exceeds 50,000 L/day, as described in Section 3.6. The maximum daily volume for dewatering will be determined in the permit application. If daily water taking records exceed the maximum daily volume in the
EA Follow-Up Monitoring Program - 25 - March 2011
PTTW, dewatering will be halted until mitigation measures can be implemented (e.g., additional grouting).
13.3 Terrestrial Environment
Should a rare or endangered species or its critical habitat be encountered during site preparation and construction, appropriate measures will be implemented to avoid destruction, injury or interference with the species, its residence and/or its habitat (e.g., through siting, timing or design changes). If the foregoing cannot be avoided, work will cease and the local Ontario Ministry of Natural Resources (OMNR) office will be contacted for advice regarding mitigation measures.
13.4 Aquatic Environment
Corrective actions may be required in the event that monitoring results are not consistent with predictions. Examples of mitigation measures include replanting or stabilization of ditches and pond(s), or temporary supply of surface water to the marsh to offset any ongoing dewatering effects.
During construction of the rail bed crossing, the section of South Railway Ditch where the culvert will be placed will be isolated and dewatered. Prior to dewatering the work area, any fish identified in the isolated area will be salvaged and relocated so as to avoid any fish or other aquatic life (frogs, turtles) during construction.
Should a rare or endangered species or its critical habitat be encountered during site preparation and construction, appropriate measures will be implemented to avoid destruction, injury or interference with the species, its residence and/or its habitat (e.g., through siting, timing or design changes). If the foregoing cannot be avoided, work will cease and the local Ontario Ministry of Natural Resources (OMNR) office will be contacted for advice regarding mitigation measures.
If the surface water monitoring program and groundwater level monitoring program, when compared to daily precipitation data, indicate that the wetland water levels may be dropping as a direct result of the shaft dewatering, mitigation measures will be implemented (e.g., a temporary water supply to the marsh).
13.5 Atmospheric Environment
If a visible dust plume is observed, watering will be implemented in non-frozen ground conditions. On-site vehicles and equipment will be equipped and maintained on-site to water roadways as required.
The air modeling in the Atmospheric Environment TSD assumed that all vehicles and equipment engines would meet Tier 2 emission standards. If the air quality monitoring results are higher than predicted, equipment could be replaced with equipment that meets Tier 3 standards or better.
Fisheries and Oceans Canada (DFO) has established a set of guidelines for the use of explosives in or near Canadian fisheries waters in the document Guidelines for the Use of Explosives In or Near Canadian Fisheries Waters (Wright et. al. 1998). These guidelines set out that “No explosive may be used that produces or is likely to produce, a peak particle velocity
EA Follow-Up Monitoring Program - 26 - March 2011
greater than 13 mm/s in a spawning bed during egg incubation”. If the monitoring program detects exceedances of this peak particle velocity and spawning is observed, a mitigation plan will be prepared outlining additional procedures for protecting fish and their habitat, as described in the guidelines. This would allow blasting to continue while meeting the guideline ground vibration limit set out by the Department of Fisheries and Oceans.
If the predicted peak ground vibration levels calculated in the Atmospheric Environment TSD are exceeded, the allowable maximum explosive weight could also be reduced.
13.6 Aboriginal Interests
In the unlikely event during development of the DGR Project, archaeological remains are encountered, all activity in the vicinity of the recovery will be suspended and the Ministry of Culture review officer will be notified immediately.
In the event that human remains are encountered at any time during development of the DGR Project, all activity in the vicinity of the discovery will be suspended and the Ministry of Culture review officer, the Registrar of Cemeteries (Ministry of Government Services), the South Bruce detachment of the Ontario Provincial Police and the local coroner will be contacted immediately.
13.7 Socio-Economic Environment
Similar to Section 13.6, in the unlikely event that artefacts are encountered that may be associated with a cultural or heritage resource, the construction activities will be curtailed until further assessment (i.e., a stage 3 or 4 archaeological assessment) can be undertaken to protect the resource from further disturbance and conserve its cultural heritage values.
13.8 Spills
To mitigate the effects of spills, appropriately equipped and trained on-site spills response teams will be available at all times as part of emergency response programs. For example a spill of diesel fuel would be mitigated by quickly assessing the situation for any immediate health and safety risks to the spills response team, on-site workers and the public by controlling the source of the spill and notifying the appropriate regulatory agencies, deploying containment booms to surround and contain the spill and finally by implementing an effective clean-up program that would likely involve the use of specialized equipment to pump the diesel fuel into secure containers. A spill to one of the on-site ditches would be collected, and directed via the stormwater management ditches to the stormwater management pond where it can be held until it is determined that it is suitable for discharge.
EA Follow-Up Monitoring Program - 27 - March 2011
14. BASELINE STUDIES AND PRE-CONSTRUCTION FOLLOW-UP
In some cases, the available baseline data may not be adequate to perform a statistically significant comparison to the measured data, or insufficient information is available to fully address the adequacy of mitigation measures. Some areas that require further study have been identified, and are summarized in Table 2.
Once the sampling protocols for each type of program (e.g., surface water quality, groundwater quality), are developed, the available baseline data will be evaluated using several factors commonly used to select appropriate background values: the number of analyses and the program duration; variability of the data set; the validity and integrity of the recorded values; the potential risk or hazard of each parameter; and the potential for bioaccumulation. Seasonal and diurnal fluctuations will also be considered. If the background data sets are deemed inadequate, further baseline studies may be conducted prior to start of the site preparation and construction phase.
EA Follow-Up Monitoring Program - 28 - March 2011
15. RECORD KEEPING AND REPORTING
Reports will be prepared and retained documenting the results of each of the monitoring programs. Each report will be prepared in accordance with CSA 288.4-10 and will include, in addition to the monitoring results:
A summary and assessment of the field and laboratory QA/QC results, including any non-conformances;
A summary of any program audit or review results and subsequent corrective actions; and A summary of any proposed modifications to the monitoring program.
Regulatory monitoring reports will be prepared as specified by the governing authority.
15.1 EA Follow-up Reports
An EA Follow-up Monitoring Report will be prepared annually and submitted to the CEAA and the CNSC. The annual report will provide conclusions regarding the accuracy of the effects predictions and recommendations to add, discontinue or refine monitoring activities or mitigation measures for the following year. Annual reports will be prepared until all EA follow-up monitoring activities have been satisfactorily concluded, with the approval of the CNSC and the CEAA.
15.2 EMP Monitoring Report
Documentation of all monitoring events, including analytical results and mitigation actions will be recorded, documented and incorporated as described in the DGR Environmental Management Plan (NWMO 2011j) to ensure that all regulatory reporting requirements are met, and that the results of the EA are carried over through the life of the project. Reporting will continue through the site preparation and construction phase and the operations phase. These reports will be retained by OPG.
15.3 Radiological Regulatory Monitoring Reports
The radiological regulatory requirements monitoring activities summarized in Tables 5a and 5b will also be subject to the DGR operations reporting to the CNSC as specified in the licence.
15.4 Conventional Regulatory Monitoring Reports
Summary reports will be prepared as required by the associated permit or approval. It is anticipated that the following reports will be required:
Monitoring Report – Certificate of Approval (Air); Monitoring Report – Certificate of Approval for Industrial Sewage Works; and Report – Permit to Take Water.
The reporting frequency and duration will be determined by the governing authority upon issuance of the permit/approval.
Regulatory monitoring and reporting may also be required as part of the in-water works associated with the construction of the rail bed crossing.
EA Follow-Up Monitoring Program - 29 - March 2011
16. PROGRAM ASSESSMENT
An assessment of the annual performance of the EA follow-up monitoring program will be completed in conjunction with the preparation of the annual report for the site preparation and construction phase follow-up monitoring, as well as during the operations phase.
The annual assessment will identify the effectiveness of the existing follow-up monitoring program design and identify any problems and gaps. It will be conducted by the person(s) responsible for the operation of the Environmental Management System (EMS). All aspects of the program assessment will be documented and incorporated into the EMP records.
A program evaluation of the core components of the EA follow-up and EMP programs will be conducted once every five years, and once during each project phase, at a minimum in accordance with CSA N288.4-10. Examples of core components are the study design, sampling and analytical procedures, interpretation, QA/QC, reporting, annual reviews and audits. The evaluation will be performed by a person with no direct responsibility for the follow-up program or EMS.
EA Follow-Up Monitoring Program - 30 - March 2011
17. REFERENCES
(APHA 2005) “Standard methods for the examination of water and wastewater”, American Public Health Association, 2005.
(CA 1990) Cemeteries Act (Revised) R.S.O. 1990, CHAPTER C.4.
http://www.e-laws.gov.on.ca/html/statutes/english/elaws_statutes_90c04_e.htm
(CAA 1990) Conservation Authorities Act, R.S.O 1990, Chap C.27.
www.e-laws.gov.on.ca/Download?dID=30181
(CEPA 2001) Canadian Environmental Protection Act, s.c. 1999. c. 33, “Priority Substances List Assessment Report Road Salt” 2001.
http://www.hc-sc.gc.ca/ewh-semt/alt_formats/hecs-sesc/pdf/pubs/contaminants/psl2-lsp2/road_salt_sels_voirie/road_salt_sels_voirie-eng.pdf
(CEPA 1999) Canadian Environmental Protection Act, s.c. 1999. c. 33.
http://laws.justice.gc.ca/PDF/Statute/C/C-15.31.pdf
(CNSC 2006a) “Developing Environmental Protection Policies, Programs and Procedures at Class I Nuclear Facilities and Uranium Mines and Mills”, Canadian Nuclear Safety Commission, G-296, March 2006.
http://nuclearsafety.gc.ca/pubs_catalogue/uploads/G-296_E.pdf
(CNSC 2006b) “Environmental Protection Policies, Programs and Procedures at Class I Nuclear Facilities and Uranium Mines and Mills”, Canadian Nuclear Safety Commission, S-296, March 2006.
http://nuclearsafety.gc.ca/pubs_catalogue/uploads/S-296_E.pdf
(CSA 2010) “Environmental Monitoring Programs at Class I Nuclear Facilities and Uranium Mines and Mills”, Canadian Standards Association, N288.4-10, May 2010.
(EPA 1990) Environmental Protection Act (Ontario), R.S.O. 1990 c E.19.
http://www.e-laws.gov.on.ca/html/statutes/english/elaws_statutes_90e19_e.htm
(ESA 2007) Endangered Species Act (Ontario), S.O. 2007, c.6.
http://www.e-laws.gov.on.ca/html/statutes/english/elaws_statutes_07e06_e.htm
(FWCA 1997 ) Fish and Wildlife Conservation Act, S.O. 1997, CHAPTER 41.
http://www.e-laws.gov.on.ca/html/statutes/english/elaws_statutes_97f41_e.htm
(FA 1985 ) Fisheries Act R.S., 1985, c. F-14.
http://laws.justice.gc.ca/eng/F-14/page-1.html
(Golder 2011) “Technical Memorandum – Results of Geochemical Testing of Rock Samples From the Deep Geologic Repository (DGR)”, Golder Associates, February 2011.
EA Follow-Up Monitoring Program - 31 - March 2011
(MBCA 1994 ) Migratory Birds Convention Act, 1994, c. 22.
http://laws.justice.gc.ca/en/M-7.01/
(MOE 1978) “Model Municipal Control By-law, Noise Pollution Control Publication 119”, Ministry of the Environment, 1978.
(MOE 1999) “Protocol for the sampling and analysis of industrial/municipal wastewater”, The Ministry of the Environment, January 1999.
http://www.ene.gov.on.ca/envision/gp/2724e01.pdf
(MOE 2004) “Soil, Ground Water and Sediment Standards for Use Under Part XV.1 of the Environmental Protection Act”, Ministry of the Environment, March, 2004.
http://www.ene.gov.on.ca/envision/gp/4697e.pdf
(MOEE 1994a) “Provincial Water Quality Objectives”, Ministry of the Environment and Energy, July 1994.
http://www.ene.gov.on.ca/envision/gp/3303e.htm
(MOEE 1994b) “Procedure B1-5 PIBS #3302 Deriving Receiving-water based, point-source effluent requirements for Ontario Waters”, Ministry of the Environment, July 1994.
http://www.ene.gov.on.ca/envision/gp/B1-5.pdf
(MOE F-5-1) “Procedure F-1-5 Determination of Treatment Requirements for Municipal and Private Sewage Treatment Works Discharging to Surface Waters”, Ministry of the Environment.
http://www.ene.gov.on.ca/envision/gp/F5-1.pdf
(NSCA 1997) Nuclear Safety and Control Act, 1997, c. 9.
http://laws.justice.gc.ca/eng/N-28.3/page-1.html
(NWMO 2011a) “Hydrology and Surface Water Quality Technical Support Document”, Nuclear Waste Management Organization, NWMO-TR-2011-04, March 2011.
(NWMO 2011b) “Geology Technical Support Document”, Nuclear Waste Management Organization, NWMO-TR-2011-03, March 2011.
(NWMO 2011c) “Geoscientific Verification Data Plan”, Nuclear Waste Management Organization, DGR-TR-2011-38, March 2011.
http://www.e-laws.gov.on.ca/html/statutes/english/elaws_statutes_90o01_e.htm
(NWMO 2011d) “Terrestrial Environment Technical Support Document”, Nuclear Waste Management Organization, NWMO-TR-2011-05, March 2011.
(NWMO 2011e) “Aquatic Environment Technical Support Document”, Nuclear Waste Management Organization, NWMO-TR-2011-01, March 2011.
(NWMO 2011f) “Atmospheric Environment Technical Support Document”, Nuclear Waste Management Organization, NWMO-TR-2011-02, March 2011.
(NWMO 2011g) “Radiation and Radioactivity Technical Support Document”, Nuclear Waste Management Organization, NWMO-TR-2011-06, March 2011.
EA Follow-Up Monitoring Program - 32 - March 2011
(NWMO 2011h) “Socio-economic Environment Technical Support Document” Nuclear Waste Management Organization, NWMO-TR-2011-08, March 2011.
(NWMO 2011i) “Aboriginal Interests Technical Support Document”, Nuclear Waste Management Organization, NWMO-TR-2011-09, March 2011.
(NWMO 2011j) “Environmental Management Plan”, Nuclear Waste Management Organization, DGR-PLAN-07002-0001.
(NWMO 2011h) “Radon Assessment”, Nuclear Waste Management Organization, DGR-TR-2011-34, March 2011.
(NSCA 1997) Nuclear Safety and Control Act, 1997, c. 9.
http://laws.justice.gc.ca/eng/N-28.3/page-1.html
(OHSA 1990) Occupational Health and Safety Act (Ontario), R.S.O. 1990 c O.1.
http://www.e-laws.gov.on.ca/html/statutes/english/elaws_statutes_90o01_e.htm
(OPG 2001) “Radiation Protection Requirements”, Ontario Power Generation, N-RPP-03415.1-10001-R07), June 2001.
(OPG 2011a) “Environmental Impact Statement”, Ontario Power Generation, 00216-REP-07701-00001 R000, March 2011.
(OPG 2011b) “Preliminary Safety Report”, Ontario Power Generation, 00216-SR-01320-00001 R000, March 2011.
(OWRA 1990) Water Resources Act (Ontario) R.S.O. 1990, c. 0.40.
http://www.e-laws.gov.on.ca/html/statutes/english/elaws_statutes_90o40_e.htm
(Reg. 127) Environmental Protection Act (Ontario) - Airborne Contaminant Discharge Monitoring and Reporting, Regulation 127/01.
http://www.e-laws.gov.on.ca/html/regs/english/elaws_regs_010127_e.htm
(Reg. 169) Conservation Authorities Act, R.S.O 1990, Chap C.27 (Ontario) - Regulation 169/06 Saugeen Valley Conservation Authority: Regulation of Development, Interference With Wetlands and Alterations to Shorelines and Watercourses.
http://www.e-laws.gov.on.ca/html/regs/english/elaws_regs_060169_e.htm
(Reg. 387) Ontario Water Resource Act Regulation 387/04 - Water Taking.
http://www.e-laws.gov.on.ca/html/regs/english/elaws_regs_040387_e.htm
(Reg. 419) Environmental Protection Act (Ontario) – Ontario Regulation 419/05 Air Pollution – Local Air Quality.
http://www.e-laws.gov.on.ca/html/regs/english/elaws_regs_050419_e.htm
(Reg. 675) Environmental Protection Act (Ontario) – Classification and Exemptions of Spills and Reporting of Discharged, Ontario Regulation 675/98.
http://www.e-laws.gov.on.ca/html/regs/english/elaws_regs_980675_e.htm
EA Follow-Up Monitoring Program - 33 - March 2011
(Reg. 854) Occupational Health and Safety Act (Ontario) – Mines and Mining Plants Regulations R.R.O. 1990, Regulation 854.
http://www.e-laws.gov.on.ca/html/regs/english/elaws_regs_900854_e.htm
(Reg. 903) Water Resources Act (Ontario) – Wells R.R.O. 1990.
http://www.e-laws.gov.on.ca/html/regs/english/elaws_regs_900903_e.htm
(SARA 2002) Species at Risk Act, S.O. 2007, c.6.
http://laws.justice.gc.ca/en/S-15.3/FullText.html
(SOR/2000-203) Radiation Protection Regulations, SOR/2000-203.
http://laws.justice.gc.ca/eng/SOR-2000-203/page-1.html
(SOR/2000-202) General Nuclear Safety and Control Regulations, SOR/2000-202.
http://laws.justice.gc.ca/en/n-28.3/sor-2000-202
(SOR/2000-204) Class I Nuclear Facility Regulations, SOR/2000-204.
http://laws.justice.gc.ca/eng/SOR-2000-204/page-1.html
(SOR/2000-207) Nuclear Substances and Radiation Devices Regulations, SOR/2000-207.
http://laws.justice.gc.ca/en/N-28.3/SOR-2000-207/
(Wright et. al. 1998)
“Guidelines for the Use of Explosives In or Near Canadian Fisheries Waters”, D.G. Wright and G.E. Hopky, Canadian Technical Report of Fisheries and Aquatic Sciences 2107, 1998. http://www.dfo-mpo.gc.ca/canwaters-eauxcan/infocentre/guidelines-conseils/guides/explosguide/pdf/explos_e.pdf
EA Follow-Up Monitoring Program - 34 - March 2011
APPENDIX
EA Follow-Up Monitoring Program - A 1 - March 2011
APPENDIX A: Environmental Monitoring Summary Tables
EA Follow-Up Monitoring Program - A 2 - March 2011
This page has been left blank intentionally
EA
Fol
low
-Up
Mon
itorin
g P
rogr
am
- A
3 -
M
arch
201
1
Tab
le 1
. P
rop
ose
d M
on
ito
rin
g S
um
mar
ized
by
Cat
ego
ry
En
viro
nm
ent
Co
mp
on
ent
Bas
elin
e E
A F
ollo
w-u
p
En
viro
nm
enta
l Man
agem
ent
Pla
n
Rad
iolo
gic
al R
egu
lato
ry
Mo
nit
ori
ng
Req
uir
eme
nts
C
on
ven
tio
nal
Reg
ula
tory
Mo
nit
ori
ng
R
equ
irem
en
ts
Sur
face
Wat
er
Qua
ntity
and
Flo
w
C
ondu
ct c
hann
el c
hara
cter
izat
ion
and
capa
city
stu
dy o
f the
dra
inag
e di
tch
alon
g In
terc
onne
ctin
g R
d. (
B-S
W-2
)
Col
lect
flow
dat
a ne
ar th
e dr
aina
ge d
itch
and
Nor
th R
ailw
ay D
itch
(B-S
W-3
and
B-
SW
-4)
M
onito
r flo
w n
ear
SW
MP
out
let (
C-E
A-
SW
3 an
d O
-EA
-SW
3)
M
onito
r flo
w in
Nor
th R
ailw
ay D
itch
(C-
EA
-SW
4)
Not
req
uire
d N
ot r
equi
red
M
onito
r S
WM
P d
isch
arge
flow
(C
-RE
G-S
W3)
Sur
face
Wat
er
Qua
lity
C
olle
ct r
ecei
ving
wat
er b
ody
base
line
surf
ace
wat
er s
ampl
es fr
om th
e dr
aina
ge
ditc
h an
d fr
om M
acP
hers
on B
ay (
B-S
W-1
)
Con
duct
an
assi
mila
tive
capa
city
stu
dy
and
rece
ivin
g w
ater
ass
essm
ent o
f M
acP
hers
on B
ay (
B-S
W-6
)
Mon
itor
stor
mw
ater
rad
ioac
tivity
(B
-R
AD
-3/ C
-LIC
-RA
D3)
C
olle
ct s
urfa
ce w
ater
sam
ples
for
CO
PC
s (C
-EA
-SW
1 an
d O
-EA
-SW
1)
C
ondu
ct S
WM
P v
isua
l effl
uent
mon
itorin
g (C
-EA
-SW
2 an
d O
-EA
-SW
2)
C
ondu
ct o
pera
tion
and
mai
nten
ance
in
spec
tion
for
stor
mw
ater
man
agem
ent
syst
em (
C-E
MP
-SW
1, c
ontin
uatio
n of
C-
EA
-SW
2; a
nd O
-EM
P-S
W1)
Con
duct
vis
ual i
nspe
ctio
n of
sto
rmw
ater
m
anag
emen
t sys
tem
(C
-EM
P-S
W2
and
O-
EM
P-S
W2)
Ver
ify s
torm
inte
rcep
tor
insp
ectio
n an
d m
aint
enan
ce p
rogr
am r
ecor
ds (
C-E
MP
-S
W3
and
O-E
MP
-SW
3)
R
adio
logi
cal s
torm
wat
er
mon
itorin
g of
rad
ioac
tivity
in
stor
mw
ater
man
agem
ent s
yste
m
(O-L
IC-R
AD
3, c
ontin
uatio
n of
B-
RA
D-3
/C-L
IC-R
AD
3)
R
adio
logi
cal s
ump
wat
er
mon
itorin
g (C
-LIC
-RA
D5
and
O-
LIC
-RA
D5)
C
olle
ct S
urfa
ce W
ater
Man
agem
ent S
yste
m
sam
ples
(ex
pect
ed to
be
limite
d to
TS
S)
(C-R
EG
-S
W1)
Con
duct
SW
MP
vis
ual e
fflue
nt m
onito
ring
(C-
RE
G-S
W2;
will
ove
rlap
with
C-E
A-S
W2
(3 y
ears
) an
d O
-EA
-SW
2 (1
yea
r)
Gro
undw
ater
Q
ualit
y
Mon
itor
shal
low
sub
surf
ace
and
bedr
ock
grou
ndw
ater
qua
lity
(B-G
W-1
and
B-G
W-
2)
M
onito
r gr
ound
wat
er r
adio
activ
ity (
B-
RA
D-2
/C-L
IC-R
AD
2)
M
onito
r sh
allo
w s
ubsu
rfac
e gr
ound
wat
er
qual
ity (
C-E
A-G
W2)
Mon
itor
shal
low
sub
surf
ace
grou
ndw
ater
qu
ality
(O
-EM
P-G
W2,
con
tinua
tion
of C
-E
A-G
W2)
R
adio
logi
cal g
roun
dwat
er
mon
itorin
g to
det
erm
ine
chan
ges
in le
vel o
f gro
undw
ater
co
ntam
inat
ion
(O-L
IC-R
AD
2,
cont
inua
tion
of B
-RA
D-2
/C-L
IC-
RA
D2)
Id
entif
y an
d m
onito
r an
y po
tent
ially
co
ntam
inat
ed g
roun
dwat
er in
res
pons
e to
a s
pill
(C-R
EG
-GW
1)
Gro
undw
ater
Flo
w
(Hyd
raul
ic H
ead)
Mon
itor
shal
low
sub
surf
ace
and
bedr
ock
hydr
aulic
hea
d (B
-GW
-1 a
nd B
-GW
-2)
E
stab
lish
shaf
t dra
wdo
wn
char
acte
ristic
s (B
-GW
-3)
M
onito
r sh
allo
w b
edro
ck g
roun
dwat
er
hydr
aulic
hea
d (C
-EA
-GW
1)
M
onito
r sh
allo
w s
ubsu
rfac
e gr
ound
wat
er
hydr
aulic
hea
d (C
-EA
-GW
3)
M
onito
r sh
allo
w b
edro
ck g
roun
dwat
er
hydr
aulic
hea
d (O
-EM
P-G
W1,
con
tinua
tion
of C
-EA
-GW
1)
M
onito
r sh
allo
w s
ubsu
rfac
e hy
drau
lic h
ead
(O-E
MP
-GW
3, c
ontin
uatio
n of
C-E
A-G
W3)
Not
req
uire
d
Mea
sure
flow
, dew
ater
ing
disc
harg
e (C
-RE
G-
GW
2)
M
onito
r sh
allo
w s
ubsu
rfac
e hy
drau
lic h
ead
to
estim
ate
grou
ndw
ater
flow
and
ZO
I (C
-RE
G-
GW
3; w
ill o
verla
p w
ith O
-EM
P-G
W3
and
C-E
A-
GW
3)
Soi
l Qua
lity
C
olle
ct b
asel
ine
soil
sam
ples
(B
-SW
-1)
N
one
prop
osed
Non
e pr
opos
ed, e
xcep
t in
case
of
mal
func
tion
or a
ccid
ent;
(C-E
MP
-SQ
1)
Not
req
uire
d N
ot r
equi
red
Ter
rest
rial H
abita
t N
ot r
equi
red
R
ecor
d w
hite
tail
deer
and
wild
turk
ey
vehi
cle
strik
es (
C-E
A-T
ER
1)
M
onito
r pl
ant s
peci
es c
omm
uniti
es a
nd
wild
life
habi
tat u
se a
djac
ent t
o th
e ar
eas
whi
ch h
ave
been
cle
ared
(C
-EA
-TE
R2)
R
ecor
d w
hite
tail
deer
and
wild
turk
ey
vehi
cle
strik
es (
C-E
MP
-TE
R1,
con
tinua
tion
of C
-EA
-TE
R1;
and
O-E
MP
-TE
R1)
Not
req
uire
d N
ot r
equi
red
Aqu
atic
Hab
itat
M
onito
r st
aff g
auge
and
mar
sh w
ater
le
vel (
B-S
W-5
)
M
onito
r re
-gro
wth
of r
ipar
ian
vege
tatio
n at
rai
l bed
cro
ssin
g fo
llow
ing
rem
oval
, not
e an
y de
ficie
ncie
s in
ban
k st
abili
ty (
C-E
A-
AQ
1)
M
onito
r ba
nk s
tabi
lity
of n
ew d
itche
s an
d st
orm
wat
er m
anag
emen
t pon
d, a
nd
reve
geta
tion
(C-E
A-A
Q2)
Mon
itor
staf
f gau
ge w
ater
leve
ls (
C-E
A-
AQ
3)
M
onito
r gr
ound
wat
er le
vels
nea
r m
arsh
(C
-EA
-AQ
4)
O
bser
ve a
nd d
ocum
ent b
urro
win
g cr
ayfis
h ac
tivity
(C
-EA
-AQ
5 an
d O
-EA
-A
Q5)
C
ondu
ct s
ite in
spec
tions
: o
del
eter
ious
sub
stan
ces
(C-E
MP
-AQ
1)
o s
edim
ent a
nd e
rosi
on c
ontr
ol
mea
sure
s(C
-EM
P-A
Q2)
o
on-
site
mac
hine
ry(C
-EM
P-A
Q3)
o
flu
id le
aks
(C-E
MP
-AQ
4)
o v
ehic
le m
aint
enan
ce (
C-E
MP
-AQ
5)
o c
onfir
m o
nsite
spi
ll ki
t is
acce
ssib
le (
C-
EM
P-A
Q6)
o
det
erm
ine
if di
tch
mai
nten
ance
is
requ
ired
(C-E
MP
-AQ
7 an
d O
-EM
P-
AQ
7)
Not
req
uire
d
Mon
itor
re-g
row
th o
f rip
aria
n ve
geta
tion
follo
win
g re
mov
al, n
ote
any
defic
ienc
ies
in b
ank
stab
ility
(C
-RE
G-A
Q1;
will
ove
rlap
with
C-E
A-A
Q1)
EA
Fol
low
-Up
Mon
itorin
g P
rogr
am
- A
4 -
M
arch
201
1
Tab
le 1
. P
rop
ose
d M
on
ito
rin
g S
um
mar
ized
by
Cat
ego
ry
En
viro
nm
ent
Co
mp
on
ent
Bas
elin
e E
A F
ollo
w-u
p
En
viro
nm
enta
l Man
agem
ent
Pla
n
Rad
iolo
gic
al R
egu
lato
ry
Mo
nit
ori
ng
Req
uir
eme
nts
C
on
ven
tio
nal
Reg
ula
tory
Mo
nit
ori
ng
R
equ
irem
en
ts
Air
Qua
lity
Not
req
uire
d
Mon
itor
air
qual
ity, N
Ox
and
PM
(C
-EA
-A
TM
1)
M
onito
r ai
r qu
ality
(du
st)
(C-E
A-A
TM
2)
C
ondu
ct v
ehic
le in
spec
tions
(C
-EM
P-
AT
M1
and
O-E
MP
-AT
M1)
Mon
itor
unde
rgro
und
air
qual
ity: a
irflo
w,
NO
x, C
O2
(C-E
MP
-AT
M2
and
O-E
MP
-A
TM
2)
M
onito
r un
derg
roun
d ai
r qu
ality
: exp
losi
ve
gas
(C-E
MP
-AT
M3
and
O-E
MP
-AT
M3)
Mon
itor
unde
rgro
und
air
qual
ity:
tem
pera
ture
and
hum
idity
(C
-EM
P-A
TM
4 an
d O
-EM
P-A
TM
4)
C
ondu
ct v
entil
atio
n in
spec
tion
(O-E
MP
-A
TM
5)
R
adio
logi
cal a
ir m
onito
ring
(C-
LIC
-RA
D1
and
O-L
IC-R
AD
1)
E
xter
nal r
adia
tion
mon
itorin
g pr
ogra
m, f
ence
-mou
nted
TLD
s (C
-LIC
-RA
D4
and
O-L
IC-R
AD
4)
R
adia
tion
and
cont
amin
atio
n co
ntro
l mon
itorin
g (O
-LIC
-RA
D6)
1
Qua
rter
ly d
ose
accu
mul
atio
n (O
-LI
C-R
AD
7)1
S
ubm
it ai
r qu
ality
em
issi
ons
repo
rts
(C-R
EG
-A
TM
1)
M
onito
r/m
odel
air
emis
sion
s (C
-RE
G-A
TM
2)
Noi
se
Not
req
uire
d
Mon
itorin
g no
ise
(C-E
A-A
TM
3)
Not
req
uire
d N
ot r
equi
red
Not
req
uire
d
Vib
ratio
n N
ot r
equi
red
M
onito
ring
vibr
atio
ns (
C-E
A-A
TM
4)
Id
entif
icat
ion
of s
paw
ning
dep
ress
ions
in
the
Nor
th R
ailw
ay D
itch
(C-E
A-A
TM
5)
Not
req
uire
d N
ot r
equi
red
Not
req
uire
d
Soc
io-E
cono
mic
N
ot r
equi
red
C
ondu
ct p
ublic
atti
tude
res
earc
h (P
AR
) (C
-EA
-SE
1)
Not
req
uire
d N
ot r
equi
red
Not
req
uire
d
Notes:
() Activity ID from Tables 2 through
6.
1This m
onitoring activity includes all pathways of radiological contamination but assumes that air would be the primary pathway.
EA
Fol
low
-Up
Mon
itorin
g P
rogr
am
- A
5 -
M
arch
201
1
Tab
le 2
. B
asel
ine
Mo
nit
ori
ng
Pro
gra
m
Act
ivit
y ID
B
asel
ine
Mo
nit
ori
ng
A
ctiv
ity
Ob
ject
ive
Sch
edu
le
Fre
qu
enc
y L
oca
tio
n
Typ
e o
f M
on
ito
rin
g
Su
rfac
e W
ater
B-S
W-1
C
olle
ct r
ecei
ving
wat
er b
ody
base
line
surf
ace
wat
er
sam
ples
from
the
drai
nage
di
tch
and
from
Mac
Phe
rson
B
ay
Est
ablis
h ba
selin
e fo
r su
rfac
e w
ater
sa
mpl
ing
prog
ram
an
d fo
r C
of A
pe
rmit
appl
icat
ions
Beg
inni
ng o
ne y
ear
prio
r to
site
pre
para
tion
and
cons
truc
tion
Qua
rter
ly
The
dra
inag
e di
tch*
at
Inte
rcon
nect
ing
Rd.
Lake
Hur
on
(Mac
Phe
rson
B
ay)
at th
e di
tch
outle
t.
EA
follo
w-u
p m
onito
ring
prog
ram
and
regu
lato
ry m
onito
ring
( C
of
A a
nd P
TT
W)
B-S
W-2
C
ondu
ct c
hann
el
char
acte
rizat
ion
and
capa
city
st
udy
of th
e D
rain
age
Ditc
h al
ong
Inte
rcon
nect
ing
Rd.
Det
erm
ine
if up
grad
es a
re
nece
ssar
y to
the
exis
ting
ditc
h to
ac
com
mod
ate
the
pred
icte
d in
crea
se
in fl
ow
2012
1
time
The
dra
inag
e di
tch
betw
een
Inte
rcon
nect
ing
Rd
and
Lake
H
uron
(M
acP
hers
on
Bay
)
EA
follo
w-u
p m
onito
ring
prog
ram
B-S
W-3
C
olle
ct fl
ow d
ata
near
the
SW
MP
out
let a
t the
Dra
inag
e D
itch
Est
ablis
h ba
selin
e fo
r flo
w
mea
sure
men
ts;
conf
irm fl
ow
assu
mpt
ions
in th
e E
A
Beg
inni
ng o
ne y
ear
prio
r to
site
pre
para
tion
and
cons
truc
tion
Qua
rter
ly a
nd
afte
r 2
stor
m
even
ts
Dra
inag
e D
itch
at
Inte
rcon
nect
ing
Rd
EA
follo
w-u
p m
onito
ring
prog
ram
B-S
W-4
C
olle
ct fl
ow d
ata
for
the
Nor
th
Rai
lway
Ditc
h at
the
sout
h ea
ster
n P
roje
ct A
rea
boun
dary
Est
ablis
h ba
selin
e fo
r flo
w
mea
sure
men
ts;
conf
irm fl
ow
assu
mpt
ions
in th
e E
A
Beg
inni
ng o
ne y
ear
prio
r to
site
pre
para
tion
and
cons
truc
tion
Qua
rter
ly a
nd
afte
r 2
stor
m
even
ts
Nor
th R
ailw
ay
Ditc
h at
Str
eam
C
EA
follo
w-u
p m
onito
ring
prog
ram
EA
Fol
low
-Up
Mon
itorin
g P
rogr
am
- A
6 -
M
arch
201
1
Tab
le 2
. B
asel
ine
Mo
nit
ori
ng
Pro
gra
m
Act
ivit
y ID
B
asel
ine
Mo
nit
ori
ng
A
ctiv
ity
Ob
ject
ive
Sch
edu
le
Fre
qu
enc
y L
oca
tio
n
Typ
e o
f M
on
ito
rin
g
B-S
W-5
M
onito
r st
aff g
auge
and
m
arsh
wat
er le
vel
Est
ablis
h ba
selin
e m
arsh
wat
er le
vels
B
egin
ning
one
yea
r pr
ior
to s
ite p
repa
ratio
n an
d co
nstr
uctio
n
Mon
thly
M
arsh
in
nort
heas
t cor
ner
of th
e P
roje
ct
Are
a
EA
follo
w-u
p m
onito
ring
prog
ram
and
reg
ulat
ory
mon
itorin
g pr
ogra
m
(PT
TW
)
B-S
W-6
C
ondu
ct a
n as
sim
ilativ
e ca
paci
ty s
tudy
and
rec
eivi
ng
wat
er a
sses
smen
t of
Mac
Phe
rson
Bay
Det
erm
ine
rele
ase
crite
ria fo
r C
of A
. 20
12
One
tim
e D
esk-
top
stu
dy
Reg
ulat
ory
mon
itorin
g pr
ogra
m(C
of A
)
Gro
un
dw
ater
B-G
W-1
M
onito
r sh
allo
w b
edro
ck
grou
ndw
ater
qua
lity
and
hydr
aulic
hea
d
Det
erm
ine
base
line
hydr
ogeo
logi
cal
cond
ition
s
On-
goin
g Q
uart
erly
m
onito
ring
4
DG
R s
erie
s w
ells
3 U
S s
erie
s w
ells
EA
follo
w-u
p m
onito
ring
prog
ram
B-G
W-2
M
onito
r sh
allo
w s
ubsu
rfac
e gr
ound
wat
er q
ualit
y an
d hy
drau
lic h
ead
Det
erm
ine
base
line
grou
ndw
ater
co
nditi
ons
2011
Q
uart
erly
m
onito
ring
8 ne
w w
ells
E
A fo
llow
-up
mon
itorin
g pr
ogra
m
B-G
W-3
E
stab
lish
shaf
t dra
wdo
wn
char
acte
ristic
s
Con
firm
hyd
raul
ic
cond
uctiv
ities
.
Mod
el e
ffect
s of
dr
awdo
wn
and
grou
nd p
re-
trea
tmen
t.
Pum
p te
st to
co
nfirm
dra
wdo
wn
char
acte
ristic
s.
2011
to 2
013
One
tim
e pr
ogra
m
Ven
t sha
ft lo
catio
n E
A fo
llow
-up
mon
itorin
g pr
ogra
m
Rad
iolo
gic
al
B-S
Q-1
S
oil s
ampl
ing
E
stab
lish
base
line
cond
ition
s S
tart
201
1 O
ne ti
me
prog
ram
R
epre
sent
ativ
e lo
catio
ns
EM
P
EA
Fol
low
-Up
Mon
itorin
g P
rogr
am
- A
7 -
M
arch
201
1
Tab
le 2
. B
asel
ine
Mo
nit
ori
ng
Pro
gra
m
Act
ivit
y ID
B
asel
ine
Mo
nit
ori
ng
A
ctiv
ity
Ob
ject
ive
Sch
edu
le
Fre
qu
enc
y L
oca
tio
n
Typ
e o
f M
on
ito
rin
g
Rad
iolo
gic
al
B-R
AD
-2
Gro
undw
ater
mon
itorin
g to
de
term
ine
chan
ges
in le
vel o
f gr
ound
wat
er c
onta
min
atio
n
Est
ablis
h ba
selin
e co
nditi
ons
Sta
rt 2
011
See
Tab
le 5
a R
adio
logi
cal r
egul
ator
y
requ
irem
ent m
onito
ring
B-R
AD
-3
Sto
rmw
ater
mon
itorin
g of
ra
dioa
ctiv
ity in
sto
rmw
ater
m
anag
emen
t sys
tem
Ver
ify p
redi
cted
ef
fect
s B
egin
ning
one
yea
r pr
ior
to o
pera
tions
S
ee T
able
5a
Rad
iolo
gica
l reg
ulat
ory
re
quire
men
t mon
itorin
g
Not
e:
*D
rain
age
ditc
h is
nor
ma
lly d
ry; t
here
fore
sa
mpl
e co
llect
ion
ma
y n
ot b
e po
ssib
le
EA
Fol
low
-Up
Mon
itorin
g P
rogr
am
- A
8 -
M
arch
201
1
Th
is p
age
has
bee
n le
ft b
lan
k in
ten
tio
nal
ly
EA
Fol
low
-Up
Mon
itorin
g P
rogr
am
- A
9 -
M
arch
201
1
Tab
le 3
a. E
A F
ollo
w-u
p M
on
ito
rin
g P
rog
ram
– S
ite
Pre
par
atio
n a
nd
Co
nst
ruct
ion
Ph
ase
Act
ivit
y ID
M
on
ito
rin
g A
ctiv
ity
Ob
ject
ive
EA
Sta
tem
en
t T
ype
of
Mo
nit
ori
ng
C
rite
ria
F
req
uen
cy
Du
rati
on
L
oca
tio
n
Su
rfac
e W
ater
C-E
A-S
W1
Col
lect
Sur
face
Wat
er
Man
agem
ent S
yste
m
sam
ples
Con
firm
pr
edic
tion
D
isch
arge
from
the
SW
MP
is
expe
cted
to m
eet t
he d
isch
arge
cr
iteria
; the
refo
re, n
o re
sidu
al
adve
rse
effe
cts
on s
urfa
ce w
ater
qu
ality
are
exp
ecte
d fr
om th
e D
GR
pr
ojec
t.
Sam
plin
g E
vent
:
TK
N
TD
S
Fre
e A
mm
onia
Alu
min
um
Bor
on
Cob
alt
Tha
llium
Van
adiu
m
pH
Tem
pera
ture
Chl
orid
e
Ele
ctric
al
Con
duct
ivity
Dis
char
ge c
riter
ia:
TB
D1
TB
D1
0.0
20 m
g/L
0.07
52 mg/
L
0.2
mg/
L
0.00
09 m
g/L
0.00
03 m
g/L
0.00
6 m
g/L
6.5-
8.5
TB
D1
200
mg/
L3
TB
D
Onc
e pr
ior
to in
itial
di
scha
rge,
dai
ly d
urin
g fir
st w
eek
of d
isch
arge
, w
eekl
y th
erea
fter
for
1 m
onth
. (ex
cept
sum
p di
scha
rge)
Afte
r in
itial
per
iod
is o
ver,
qu
arte
rly.
Onc
e sh
aft d
ewat
erin
g ha
s co
mm
ence
d, d
aily
du
ring
first
wee
k of
de
wat
erin
g, w
eekl
y th
erea
fter
for
1 m
onth
(s
haft
sum
p lo
catio
n on
ly).
Afte
r in
itial
per
iod
is o
ver,
qua
rter
ly (
to b
e in
tegr
ated
into
the
disc
harg
e an
d pe
rimet
er
ditc
h sa
mpl
ing
prog
ram
).
Site
pre
para
tion
and
cons
truc
tion
1 S
WM
P d
isch
arge
sam
ple
1 pe
rimet
er d
rain
age
ditc
h lo
catio
n, T
BD
4
1 at
sha
ft su
mp
disc
harg
e po
int
(at s
urfa
ce, p
ost-
trea
tmen
t)4
C-E
A-S
W2
Mon
itor
SW
MP
effl
uent
to
ens
ure
efflu
ent f
rom
po
nd is
free
of f
loat
ing
and
settl
eabl
e so
lids
and
does
not
con
tain
oil
or a
ny o
ther
sub
stan
ce
in a
mou
nts
suffi
cien
t to
crea
te a
vis
ible
film
, sh
een,
foam
or
disc
olor
atio
n or
any
ot
her
dele
terio
us
subs
tanc
e
Con
firm
pr
edic
tion
Dis
char
ge fr
om th
e S
WM
P is
ex
pect
ed to
mee
t the
dis
char
ge
crite
ria; t
here
fore
, no
resi
dual
ad
vers
e ef
fect
s on
sur
face
wat
er
qual
ity a
re e
xpec
ted
from
the
DG
R
proj
ect.
Vis
ual i
nspe
ctio
n N
o ob
serv
ed fl
oatin
g an
d se
ttlea
ble
solid
s.
No
oil o
r ot
her
subs
tanc
es th
at c
reat
e a
shee
n, fo
am o
r di
scol
orat
ion
of th
e re
ceiv
ing
wat
er.
Wee
kly
once
SW
MP
st
arts
dis
char
ging
.
Site
pre
para
tion
and
cons
truc
tion
SW
MP
dis
char
ge
C-E
A-S
W3
Mon
itor
flow
nea
r S
WM
P o
utle
t to
drai
nage
ditc
h at
In
terc
onne
ctin
g R
oad
Con
firm
effe
ct
A 1
14 %
incr
ease
in s
urfa
ce
quan
tity
and
flow
in th
e dr
aina
ge
ditc
h at
Inte
rcon
nect
ing
Roa
d is
pr
edic
ted
resu
lting
in a
res
idua
l ad
vers
e ef
fect
.
Flo
w m
easu
rem
ent
Con
firm
ass
umpt
ions
in
EA
use
d to
pre
dict
an
d ad
vers
e ef
fect
(m
easu
red
as p
erce
nt
chan
ge fr
om m
ean
annu
al fl
ow)
in fl
ow to
th
e dr
aina
ge d
itch.
Wee
kly
flow
m
easu
rem
ents
, av
erag
ed m
onth
ly
3 ye
ars
SW
MP
dis
char
ge
EA
Fol
low
-Up
Mon
itorin
g P
rogr
am
- A
10
- M
arch
201
1
Tab
le 3
a. E
A F
ollo
w-u
p M
on
ito
rin
g P
rog
ram
– S
ite
Pre
par
atio
n a
nd
Co
nst
ruct
ion
Ph
ase
Act
ivit
y ID
M
on
ito
rin
g A
ctiv
ity
Ob
ject
ive
EA
Sta
tem
en
t T
ype
of
Mo
nit
ori
ng
C
rite
ria
F
req
uen
cy
Du
rati
on
L
oca
tio
n
C-E
A-S
W4
Mon
itor
flow
in N
orth
R
ailw
ay D
itch
at th
e so
uth
east
ern
proj
ect
boun
dary
Con
firm
effe
ct
A 3
1 %
dec
reas
e in
sur
face
qu
antit
y an
d flo
w in
the
Nor
th
Rai
lway
Ditc
h is
pre
dict
ed r
esul
ting
in a
res
idua
l adv
erse
effe
ct.
Vis
ual i
nspe
ctio
n C
onfir
m a
ssum
ptio
ns
in E
A u
sed
to p
redi
ct
and
adve
rse
effe
ct
(mea
sure
d as
per
cent
ch
ange
from
mea
n an
nual
flow
) in
flow
to
the
Dra
inag
e D
itch.
Qua
rter
ly a
nd d
urin
g 2
maj
or s
torm
eve
nts
per
year
.
3 y
ears
Str
eam
C a
t Nor
th R
ailw
ay
Ditc
h di
scha
rge
Gro
un
dw
ater
C-E
A-G
W1
Mon
itor
shal
low
be
droc
k gr
ound
wat
er
hydr
aulic
hea
d
Sub
stan
tiate
zon
e of
influ
ence
and
dr
awdo
wn
pred
ictio
ns a
nd to
de
term
ine
whe
ther
inflo
w
rate
s w
ill e
xcee
d 50
,000
L/d
ay.
Gro
und
trea
tmen
t ove
r th
e le
ngth
of
the
shaf
t thr
ough
the
over
burd
en s
oils
and
upp
er 1
80 m
of
bed
rock
will
min
imiz
e th
e am
ount
of d
ewat
erin
g.
Sha
llow
and
in
term
edia
te
bedr
ock
grou
ndw
ater
m
onito
ring
Per
mit
to T
ake
Wat
er
App
licat
ion
(reg
ulat
ory
requ
irem
ent (
OW
RA
19
90).
Qua
rter
ly m
onito
ring
of
wat
er le
vels
thro
ugho
ut
cons
truc
tion.
The
pr
ogra
m c
ontin
uatio
n w
ill
be r
e-ev
alua
ted
afte
r 5
year
s.
Con
tinua
tion
of th
e pr
ogra
m w
ill
be r
e-ev
alua
ted
at th
e en
d of
th
e si
te p
repa
ratio
n an
d co
nstr
uctio
n ph
ase.
4 D
GR
ser
ies
wel
ls
3 U
S s
erie
s w
ells
C-E
A-G
W2
Mon
itor
shal
low
su
bsur
face
gro
undw
ater
qu
ality
Con
firm
pr
edic
tions
of
Geo
synt
hesi
s pr
ogra
m u
sed
in
the
EA
.
Est
ablis
h se
ason
al fl
uctu
atio
ns.
Ear
ly d
etec
tion
netw
ork
to id
entif
y co
ntam
inat
ion.
Gro
undw
ater
sa
mpl
ing
prog
ram
C
ompl
ianc
e w
ith
regu
lato
ry s
tand
ards
M
OE
Tab
le 3
MO
E
2004
) or
bas
elin
e.
Qua
rter
ly m
onito
ring
Con
tinua
tion
of th
e pr
ogra
m w
ill
be r
e-ev
alua
ted
at th
e en
d of
th
e si
te p
repa
ratio
n an
d co
nstr
uctio
n ph
ase.
8 ne
w w
ells
C-E
A-G
W3
Mon
itor
shal
low
su
bsur
face
gro
undw
ater
hy
drau
lic h
ead
Con
firm
pr
edic
tions
of
Geo
synt
hesi
s pr
ogra
m u
sed
in
the
EA
, su
bsta
ntia
te z
one
of in
fluen
ce a
nd
draw
dow
n pr
edic
tions
and
to
dete
rmin
e w
heth
er in
flow
ra
tes
will
exc
eed
50,0
00 L
/day
.
Zon
e of
influ
ence
is e
stim
ated
at
54 m
. W
ater
leve
l m
onito
ring
prog
ram
A
brup
t or
grad
ual
chan
ge in
gro
undw
ater
flo
w.
Qua
rter
ly m
onito
ring
C
ontin
uatio
n of
the
prog
ram
will
be
re-
eval
uate
d at
the
end
of
the
site
pre
para
tion
and
cons
truc
tion
phas
e.
8 ne
w w
ells
Ter
rest
rial
C-E
A-T
ER
1 R
ecor
d w
hite
tail
deer
an
d w
ild tu
rkey
veh
icle
st
rike
s
Con
firm
pr
edic
tions
W
hile
a fe
w in
divi
dual
s co
uld
be
lost
bec
ause
of p
roje
ct-r
elat
ed
vehi
cle
strik
es, i
t will
hav
e a
negl
igib
le e
ffect
upo
n th
e lo
cal
popu
latio
n.
Rep
ortin
g N
o si
gnifi
cant
cha
nge
at a
pop
ulat
ion
leve
l O
n-go
ing
1 ye
ar
DG
R P
roje
ct A
rea,
to b
e re
port
ed u
nder
the
Bru
ce
nucl
ear
site
pro
gram
EA
Fol
low
-Up
Mon
itorin
g P
rogr
am
- A
11
- M
arch
201
1
Tab
le 3
a. E
A F
ollo
w-u
p M
on
ito
rin
g P
rog
ram
– S
ite
Pre
par
atio
n a
nd
Co
nst
ruct
ion
Ph
ase
Act
ivit
y ID
M
on
ito
rin
g A
ctiv
ity
Ob
ject
ive
EA
Sta
tem
en
t T
ype
of
Mo
nit
ori
ng
C
rite
ria
F
req
uen
cy
Du
rati
on
L
oca
tio
n
C-E
A-T
ER
2 M
onito
r pl
ant s
peci
es
com
mun
ities
and
w
ildlif
e ha
bita
t use
ad
jace
nt to
the
area
s w
hich
hav
e be
en
clea
red
durin
g th
e si
te
prep
arat
ion
and
cons
truc
tion
phas
e.
Con
firm
effe
ct
As
the
miti
gatio
n m
easu
res
will
not
su
ffici
ently
red
uce
or e
limin
ate
the
effe
ct, t
here
is a
res
idua
l adv
erse
ef
fect
of t
he D
GR
Pro
ject
on
east
ern
whi
te c
edar
.
Vis
ual i
nspe
ctio
n P
rese
nce
of s
uita
ble
habi
tat
One
tim
e af
ter
cons
truc
tion
of s
urfa
ce
stru
ctu
res
Sin
gle
even
t La
nd a
djac
ent t
o cl
earin
g w
ithin
th
e P
roje
ct A
rea
Aq
uat
ic
C-E
A-A
Q1
Mon
itor
re-g
row
th o
f rip
aria
n ve
geta
tion
follo
win
g re
mov
al, n
ote
any
defic
ienc
ies
in b
ank
stab
ility
Con
firm
effe
ct
sign
ifica
nce,
co
nfirm
miti
gatio
n
The
re is
a r
esid
ual h
abita
t los
s in
th
e so
uth
railw
ay d
itch
for
Red
be
lly d
ace,
Cre
ek c
hubb
and
va
riabl
e le
af p
ondw
eed
from
the
acce
ss r
oad
cros
sing
. V
eget
ate
any
dist
urbe
d ar
eas
by p
lant
ing
and
seed
ing
pref
erab
ly w
ith n
ativ
e tr
ees,
shr
ubs
or g
rass
es a
nd c
over
su
ch a
reas
with
mul
ch to
pre
vent
er
osio
n an
d to
hel
p se
eds
germ
inat
e. If
ther
e is
insu
ffici
ent
time
rem
aini
ng in
the
grow
ing
seas
on, t
he s
ite s
houl
d be
st
abili
zed
(e.g
., co
ver
expo
sed
area
s w
ith e
rosi
on c
ontr
ol b
lank
ets
to k
eep
the
soil
in p
lace
and
pr
even
t ero
sion
) an
d ve
geta
ted
the
follo
win
g sp
ring)
.
Vis
ual i
nspe
ctio
n H
ealth
y es
tabl
ishe
d ve
geta
tion.
No
defic
ienc
ies
in
bank
sta
bilit
y.
Ann
ually
afte
r co
nstr
uctio
n of
rai
l bed
cr
ossi
ng
3 gr
owin
g se
ason
s Lo
catio
n: d
istu
rbed
are
as; a
t rai
l be
d cr
ossi
ng
C-E
A-A
Q2
Mon
itor
bank
sta
bilit
y of
an
d of
new
ditc
hes
and
stor
mw
ater
m
anag
emen
t pon
d, a
nd
reve
geta
tion
of n
ew
ditc
hes
Con
firm
miti
gatio
n N
o lik
ely
adve
rse
effe
ct id
entif
ied
to S
potta
il sh
iner
, ben
thic
in
vert
ebra
tes,
lake
whi
tefis
h,
Sm
allm
outh
bas
s (L
ake
Hur
on
VE
Cs)
, pro
vide
d in
-des
ign
miti
gatio
n is
effe
ctiv
e.
Vis
ual i
nspe
ctio
n H
ealth
y es
tabl
ishe
d ve
geta
tion.
No
defic
ienc
ies
in
bank
sta
bilit
y.
One
tim
e af
ter
cons
truc
tion
of d
rain
age
ditc
hes
and
stor
mw
ater
m
anag
emen
t pon
d.
1 gr
owin
g se
ason
N
ew d
itche
s an
d S
WM
P
C-E
A-A
Q3
Mon
itor
the
mar
sh o
n-si
te fo
r co
nfirm
atio
n th
at
exca
vatio
n do
es n
ot
dew
ater
and
affe
ct
mar
sh h
abita
t and
cr
ayfis
h.
Con
firm
effe
ct
The
re is
a r
esid
ual l
oss
of
burr
owin
g cr
awfis
h ha
bita
t with
in
the
Pro
ject
Are
a as
a r
esul
t of l
and
clea
ring
activ
ities
and
con
stru
ctio
n of
sur
face
faci
litie
s. P
roje
ct d
esig
n av
oide
d th
e m
arsh
in th
e no
rthe
ast
port
ion
of th
e P
roje
ct a
rea
whe
re
ther
e is
kno
wn
cray
fish
habi
tat.
Mon
itor
staf
f gau
ge
wat
er le
vels
D
rop
in w
ater
leve
l ou
tsid
e se
ason
al
/bas
elin
e no
rms
and
devi
atio
n fr
om
prec
ipita
tion
even
t pa
ttern
s.
Fre
quen
cy w
ill d
epen
d on
po
rosi
ty o
f roc
k an
d ef
fect
iven
ess
of m
itiga
tion
to s
top
grou
ndw
ater
dra
w
dow
n (g
rout
ing
exca
vatio
n).
Sug
gest
ed
wee
kly.
Site
pre
para
tion
and
cons
truc
tion
phas
e.
Pro
gram
will
be
disc
ontin
ued
if th
ere
is n
ot o
bser
ved
effe
ct a
t th
e en
d of
the
phas
e.
1 re
pres
enta
tive
loca
tion
with
in
the
mar
sh to
be
dete
rmin
ed
EA
Fol
low
-Up
Mon
itorin
g P
rogr
am
- A
12
- M
arch
201
1
Tab
le 3
a. E
A F
ollo
w-u
p M
on
ito
rin
g P
rog
ram
– S
ite
Pre
par
atio
n a
nd
Co
nst
ruct
ion
Ph
ase
Act
ivit
y ID
M
on
ito
rin
g A
ctiv
ity
Ob
ject
ive
EA
Sta
tem
en
t T
ype
of
Mo
nit
ori
ng
C
rite
ria
F
req
uen
cy
Du
rati
on
L
oca
tio
n
C-E
A-A
Q4
Mon
itor
the
mar
sh o
n-si
te fo
r co
nfirm
atio
n th
at
exca
vatio
n do
es n
ot
dew
ater
and
affe
ct
mar
sh h
abita
t and
cr
ayfis
h.
Con
firm
effe
ct
The
re is
a r
esid
ual l
oss
of
burr
owin
g cr
awfis
h ha
bita
t with
in
the
Pro
ject
Are
a as
a r
esul
t of l
and
clea
ring
activ
ities
and
con
stru
ctio
n of
sur
face
faci
litie
s. P
roje
ct d
esig
n av
oide
d th
e m
arsh
in th
e no
rthe
ast
port
ion
of th
e P
roje
ct a
rea
whe
re
ther
e is
kno
wn
cray
fish
habi
tat.
Gro
undw
ater
leve
l D
rop
in w
ater
leve
l ou
tsid
e se
ason
al
/bas
elin
e no
rms
and
devi
atio
n fr
om
prec
ipita
tion
even
t pa
ttern
s.
Mon
thly
dur
ing
dew
ater
ing
Fro
m th
e st
art o
f sha
ft de
wat
erin
g un
til th
e co
mpl
etio
n of
exc
avat
ion
of th
e to
p 20
0 m
of
the
shaf
ts, o
r un
til th
e w
ater
ta
ble
reco
vers
from
dew
ater
ing-
rela
ted
effe
cts.
Gro
undw
ater
wel
l clo
sest
to th
e m
arsh
inst
alle
d as
par
t of
mon
itorin
g ac
tivity
C-E
MP
-GW
3
C-E
A-A
Q5
Obs
erve
and
doc
umen
t bu
rrow
ing
cray
fish
activ
ity
Con
firm
effe
ct
The
re is
a r
esid
ual l
oss
of
burr
owin
g cr
awfis
h ha
bita
t with
in
the
Pro
ject
Are
a as
a r
esul
t of l
and
clea
ring
activ
ities
and
con
stru
ctio
n of
sur
face
faci
litie
s. P
roje
ct d
esig
n av
oide
d th
e m
arsh
in th
e no
rthe
ast
port
ion
of th
e P
roje
ct a
rea
whe
re
ther
e is
kno
wn
cray
fish
habi
tat.
Cra
yfis
h C
him
ney
Sur
vey
Pre
senc
e of
cra
yfis
h ch
imne
ys
Ann
ually
B
egin
ning
afte
r co
nstr
uctio
n of
th
e ra
il be
d cr
ossi
ng fo
r th
ree
year
s.
Pro
ject
Are
a
Atm
osp
her
ic
C-E
A-A
TM
1 M
onito
r ai
r qu
ality
C
onfir
m
pred
ictio
ns,
miti
gatio
n an
d ef
fect
A r
esid
ual a
dver
se e
ffect
of t
he
DG
R P
roje
ct o
n ai
r qu
ality
was
as
sess
ed a
s ‘m
ay b
e si
gnifi
cant
”.
Dia
tom
aceo
us
TE
OM
ana
lyze
r) fo
r:
PM
10
PM
2.5
Con
tinuo
us N
Ox
anal
yzer
s
EIS
max
imum
pr
edic
tions
(ug
/m3 ):
24-h
our
PM
10: 7
5.3
24 h
our
PM
2.5:
45.
7
1-ho
ur N
O2:
321
.7
Ann
ual N
O2:
18.5
Con
tinuo
us m
onito
rs, l
og
hour
ly a
vera
ged
reco
rdin
gs.
Dat
a w
ill b
e do
wnl
oade
d qu
arte
rly.
Site
pre
para
tion
and
cons
truc
tion
phas
e.
Con
tinua
tion
of th
e pr
ogra
m to
be
re-
eval
uate
d at
the
end
of
each
yea
r.
The
mon
itorin
g eq
uipm
ent (
to
be s
et u
p in
a s
ecur
e lo
catio
n ne
ar th
e M
ain
Acc
ess
Roa
d;
betw
een
the
cons
truc
tion
activ
ities
and
the
prop
erty
bo
unda
ry).
C-E
A-A
TM
2 M
onito
r ai
r qu
ality
–
dust
em
issi
ons
Con
firm
effe
ct
A r
esid
ual a
dver
se e
ffect
of t
he
DG
R P
roje
ct o
n ai
r qu
ality
was
as
sess
ed a
s ‘m
ay b
e si
gnifi
cant
.
Vis
ual i
nspe
ctio
ns
for
dust
em
issi
ons
No
visi
ble
dust
plu
me
Dai
ly
Site
pre
para
tion
and
cons
truc
tion
phas
e A
t sha
fts, a
cces
s ro
ads
with
in
the
WR
MA
, was
te r
ock
pile
.
C-E
A-A
TM
3 M
onito
r no
ise
C
onfir
m
pred
ictio
ns,
miti
gatio
n an
d ef
fect
.
An
adve
rse
nois
e ef
fect
is
iden
tifie
d th
roug
h th
e no
ise
leve
l in
dica
tor.
Inte
grat
ing
soun
d le
vel m
eter
EIS
max
imum
pr
edic
tions
:
R1:
38
dBa
R2:
42
dBa
R3:
37
dBa
Noi
se m
onito
ring
cam
paig
n of
suf
ficie
nt
dura
tion
to c
onfir
m
cons
truc
tion
nois
e pr
edic
tions
pre
sent
ed in
th
e as
sess
men
t.
Mea
sure
men
ts s
houl
d be
co
ntin
uous
for
a pe
riod
of
at le
ast 4
8 ho
urs.
Site
pre
para
tion
and
cons
truc
tion
phas
e.
Con
tinua
tion
of th
e pr
ogra
m to
be
re-
eval
uate
d at
the
end
of
each
yea
r.
Noi
se m
onito
ring
loca
tions
R1,
R
2 an
d R
3 (B
aie
du D
ore,
In
verh
uron
Par
k an
d ad
jace
nt to
In
verh
uron
Par
k).
EA
Fol
low
-Up
Mon
itorin
g P
rogr
am
- A
13
- M
arch
201
1
Tab
le 3
a. E
A F
ollo
w-u
p M
on
ito
rin
g P
rog
ram
– S
ite
Pre
par
atio
n a
nd
Co
nst
ruct
ion
Ph
ase
Act
ivit
y ID
M
on
ito
rin
g A
ctiv
ity
Ob
ject
ive
EA
Sta
tem
en
t T
ype
of
Mo
nit
ori
ng
C
rite
ria
F
req
uen
cy
Du
rati
on
L
oca
tio
n
C-E
A-A
TM
4 M
onito
r gr
ound
vi
brat
ions
C
onfir
m
pred
ictio
n It
shou
ld b
e re
cogn
ized
that
thes
e pr
edic
ted
peak
gro
und
vibr
atio
n le
vels
are
bas
ed o
n em
piric
al d
ata
and
shou
ld b
e co
nfirm
ed o
nce
blas
ting
has
com
men
ced.
13
mm
/s
Onc
e at
the
star
t of
blas
ting.
Wee
kly
durin
g bl
astin
g of
th
e to
p 10
0 m
, mon
thly
th
erea
fter.
Pro
gram
may
be
disc
ontin
ued
base
d on
co
nsis
tent
ly lo
w v
ibra
tion
mea
sure
men
ts o
nce
shaf
t is
adv
ance
d be
low
100
m
.
See
Fre
quen
cy
Sev
eral
loca
tions
, TB
D.
C-E
A-A
TM
5 Id
entif
icat
ion
of
spaw
ning
dep
ress
ions
in
the
Nor
th R
ailw
ay
Ditc
h
Con
firm
pr
edic
tion
Wor
king
on
the
assu
mpt
ion
of a
m
axim
um v
ibra
tion
limit
of 1
3 m
m/s
allo
ws
the
calc
ulat
ion
of
theo
retic
al m
axim
um c
harg
e w
eigh
ts. F
or a
rec
epto
r at
150
m
away
from
the
blas
t sou
rce,
the
max
imum
cha
rge
wei
ght p
er d
elay
w
ould
be
250
kg to
mai
ntai
n th
e 13
m
m/s
vib
ratio
n lim
it
Vis
ual i
nspe
ctio
n N
o sp
awni
ng
depr
essi
ons
in th
e N
orth
Rai
lway
Ditc
hes.
Onc
e at
the
begi
nnin
g of
ve
nt s
haft
colla
r de
velo
pmen
t.
One
tim
e ev
ent
With
in 1
50 m
of t
he v
ent s
haft
So
cio
Eco
no
mic
C-E
A-S
E1
Con
duct
pub
lic a
ttitu
de
rese
arch
(P
AR
)
Con
firm
ben
efic
ial
effe
ct
Ben
efic
ial e
ffect
as
a re
sult
of
incr
ease
d po
pula
tion,
incr
ease
d ed
ucat
iona
l opp
ortu
nitie
s
Sur
vey
Pro
vide
com
para
ble
resu
lts to
200
9 P
AR
A
t a m
inim
um:
O
nce
durin
g th
e si
te
prep
arat
ion
and
cons
truc
tion
phas
e;
and
S
ubse
quen
t to
any
acci
dent
s or
m
alfu
nctio
ns o
f the
D
GR
or
asso
ciat
ed
oper
atio
ns, r
esul
ting
in
a re
leas
e of
rad
ioac
tive
cont
amin
atio
n to
the
envi
ronm
ent.
To
be c
oord
inat
ed w
ith
othe
r O
PG
PA
Rs.
See
Fre
quen
cy
Kin
card
ine
and
five
surr
ound
ing
mun
icip
aliti
es
Ab
ori
gin
al In
tere
sts
Not
es:
N/A
= N
ot a
pplic
able
T
BD
= T
o be
det
erm
ined
1W
ill b
e ba
sed
on th
e b
asel
ine
stu
dies
2B
ased
on
pH v
alu
es .6
.5 a
nd <
9.0,
in c
lay
free
sam
ple
s 3B
ased
on
the
toxi
city
val
ues
iden
tifie
d in
the
“Prio
rity
Sub
stan
ces
Lis
t Ass
essm
ent R
epo
rt fo
r R
oad
Sal
ts”.
(C
EP
A 2
001)
4P
urpo
se o
f th
ese
loca
tions
is to
hel
p id
entif
y th
e so
urce
of
pote
ntia
l con
tam
inat
ion,
an
d w
ill n
ot n
eed
to c
ompl
y w
ith th
e di
sch
arge
crit
eria
EA
Fol
low
-Up
Mon
itorin
g P
rogr
am
- A
14
- M
arch
201
1
T
able
3b
: E
A F
ollo
w-u
p M
on
ito
rin
g P
rog
ram
– O
per
atio
ns
Ph
ase
Act
ivit
y ID
M
on
ito
rin
g A
ctiv
ity
Ob
ject
ive
EA
Sta
tem
en
t T
ype
of
Mo
nit
ori
ng
C
rite
ria
F
req
uen
cy
Du
rati
on
L
oca
tio
n
Su
rfac
e W
ater
O-E
A-S
W1
(con
tinua
tion
of C
-EA
-S
W1)
Col
lect
Sur
face
Wat
er
Man
agem
ent S
yste
m
sam
ples
Con
firm
pre
dict
ion
D
isch
arge
from
the
SW
MP
is e
xpec
ted
to
mee
t the
dis
char
ge
crite
ria; t
here
fore
, no
resi
dual
adv
erse
ef
fect
s on
sur
face
w
ater
qua
lity
are
expe
cted
from
the
DG
R p
roje
ct.
Sam
plin
g E
vent
:
TK
N
TD
S
Fre
e A
mm
onia
Alu
min
um
Bor
on
Cob
alt
Tha
llium
Van
adiu
m
pH
Tem
pera
ture
Chl
orid
e
Ele
ctric
al
cond
uctiv
ity
Dis
char
ge c
riter
ia:
TB
D1
TB
D1
0.02
0 m
g/L
0.07
52 mg/
L
0.2
mg/
L
0.00
09 m
g/L
0.00
03 m
g/L
0.00
6 m
g/L
6.5-
8.5
TB
D1
200
mg/
L3
TB
D1
Qua
rter
ly fo
r on
e ye
ar
1 ye
ar
1 S
WM
P d
isch
arge
sam
ple
1 pe
rimet
er d
rain
age
ditc
h lo
catio
n, T
BD
4
1 at
sha
ft su
mp
disc
harg
e po
int
(at s
urfa
ce, p
ost-
trea
tmen
t)4
O-E
A-S
W2
(con
tinua
tion
of C
-EA
-S
W2)
Mon
itor
SW
MP
ef
fluen
t, to
ens
ure
efflu
ent f
rom
pon
d is
fr
ee o
f flo
atin
g an
d se
ttlea
ble
solid
s an
d do
es n
ot c
onta
in o
il or
an
y ot
her
subs
tanc
e in
am
ount
s su
ffici
ent t
o cr
eate
a v
isib
le fi
lm,
shee
n, fo
am o
r di
scol
orat
ion
or a
ny
othe
r de
lete
rious
su
bsta
nce
Con
firm
pre
dict
ion
Dis
char
ge fr
om th
e S
WM
P is
exp
ecte
d to
m
eet t
he d
isch
arge
cr
iteria
; the
refo
re, n
o re
sidu
al a
dver
se
effe
cts
on s
urfa
ce
wat
er q
ualit
y ar
e ex
pect
ed fr
om th
e D
GR
pro
ject
.
Vis
ual i
nspe
ctio
n N
o ob
serv
ed fl
oatin
g an
d se
ttlea
ble
solid
s.
No
oil o
r ot
her
subs
tanc
es th
at c
reat
e a
shee
n, fo
am o
r di
scol
orat
ion
of th
e re
ceiv
ing
wat
er.
Mon
thly
1 ye
ar
SW
MP
dis
char
ge
O-E
A-S
W3
(con
tinua
tion
of C
– E
A-
SW
3
Mon
itor
flow
at S
WM
P
disc
harg
e C
onfir
m e
ffect
A
114
% in
crea
se in
su
rfac
e qu
antit
y an
d flo
w in
the
Dra
inag
e D
itch
at
Inte
rcon
nect
ing
Roa
d is
pre
dict
ed r
esul
ting
in a
res
idua
l adv
erse
ef
fect
.
Flo
w m
easu
rem
ent
Con
firm
ass
umpt
ions
in
EA
use
d to
pre
dict
and
ad
vers
e ef
fect
(m
easu
red
as p
erce
nt
chan
ge fr
om m
ean
annu
al fl
ow)
in fl
ow to
th
e D
rain
age
Ditc
h.
Wee
kly
flow
m
easu
rem
ents
, av
erag
ed m
onth
ly
1 ye
ar
SW
MP
dis
char
ge
EA
Fol
low
-Up
Mon
itorin
g P
rogr
am
- A
15
- M
arch
201
1
T
able
3b
: E
A F
ollo
w-u
p M
on
ito
rin
g P
rog
ram
– O
per
atio
ns
Ph
ase
Act
ivit
y ID
M
on
ito
rin
g A
ctiv
ity
Ob
ject
ive
EA
Sta
tem
en
t T
ype
of
Mo
nit
ori
ng
C
rite
ria
F
req
uen
cy
Du
rati
on
L
oca
tio
n
Aq
uat
ic
O-E
A-A
Q5
(con
tinua
tion
of C
-EA
-A
Q5)
Obs
erve
and
do
cum
ent b
urro
win
g cr
ayfis
h ac
tivity
Con
firm
effe
ct
The
re is
a r
esid
ual
loss
of b
urro
win
g cr
awfis
h ha
bita
t w
ithin
the
Pro
ject
A
rea
as a
res
ult o
f la
nd c
lear
ing
activ
ities
and
co
nstr
uctio
n of
su
rfac
e fa
cilit
ies.
P
roje
ct d
esig
n av
oide
d th
e m
arsh
in
the
nort
heas
t por
tion
of th
e P
roje
ct a
rea
whe
re th
ere
is k
now
n cr
ayfis
h ha
bita
t.
Cra
yfis
h C
him
ney
Sur
vey
Pre
senc
e of
cra
yfis
h ch
imne
ys
Ann
ually
M
ay e
xten
d 2
year
s in
to
oper
atio
ns, d
epen
ding
on
whe
n th
e ra
il be
d cr
ossi
ng is
co
nstr
ucte
d (s
ee C
-EA
-AQ
5 in
T
able
3a)
.
Pro
ject
Are
a
Atm
osp
her
ic
P
rovi
ded
mon
itorin
g re
sults
are
not
in e
xces
s of
the
EIS
pre
dict
ions
dur
ing
cons
truc
tion,
no
non-
radi
olog
ical
mon
itorin
g is
re
quire
d fo
r th
e E
A F
ollo
w-u
p M
onito
ring
Pro
gram
. Oth
er a
tmos
pher
ic
mon
itorin
g is
incl
uded
in th
e E
MP
and
the
radi
olog
ical
reg
ulat
ory
requ
irem
ent m
onito
ring.
Rad
iati
on
an
d R
adio
acti
vity
S
ee T
able
s 5a
and
5b
Not
es:
TB
D =
To
be d
eter
min
ed
1W
ill b
e ba
sed
on th
e b
asel
ine
stu
dies
2B
ased
on
pH v
alu
es .6
.5 a
nd <
9.0,
in c
lay
free
sam
ple
s 3B
ased
on
the
toxi
city
val
ues
iden
tifie
d in
the
“Prio
rity
Sub
stan
ces
Lis
t Ass
essm
ent R
epo
rt fo
r R
oad
Sal
ts”.
(C
EP
A 2
001)
4P
urpo
se o
f th
ese
loca
tions
is to
hel
p id
entif
y th
e so
urce
of
pote
ntia
l con
tam
inat
ion,
an
d w
ill n
ot n
eed
to c
ompl
y w
ith th
e di
sch
arge
crit
eria
EA
Fol
low
-Up
Mon
itorin
g P
rogr
am
- A
16
- M
arch
201
1
Tab
le 4
a. E
nvi
ron
men
tal M
anag
emen
t P
lan
Mo
nit
ori
ng
Pro
gra
m –
Sit
e P
rep
arat
ion
an
d C
on
stru
ctio
n P
has
e
Act
ivit
y ID
M
on
ito
rin
g A
ctiv
ity
Ob
ject
ive
EA
Sta
tem
en
t T
ype
of
Mo
nit
ori
ng
C
rite
ria
F
req
uen
cy
Lo
cati
on
Su
rfac
e W
ater
C-E
MP
-SW
1
Ope
ratio
n an
d M
aint
enan
ce in
spec
tion
to e
nsur
e th
at th
e st
orm
wat
er
man
agem
ent s
yste
m
and
run-
off a
reas
do
not
have
ext
rem
e er
osio
n w
ear.
Ens
ure
that
sed
imen
t co
ntro
l mat
eria
ls a
re
kept
on
hand
for
emer
genc
y re
spon
se
and
for
repa
ir an
d m
aint
enan
ce p
urpo
ses.
Con
firm
miti
gatio
n
No
resi
dual
adv
erse
effe
cts
on
surf
ace
wat
er q
ualit
y ar
e ex
pect
ed
from
the
DG
R p
roje
ct p
rovi
ded
in-
desi
gn m
itiga
tion
is e
ffect
ive.
Vis
ual I
nspe
ctio
n F
ree
of d
ebris
and
er
osio
n W
eekl
y
Sto
rmw
ater
man
agem
ent
syst
em
C-E
MP
-SW
2 (c
ontin
uatio
n of
C-
EA
-SW
2)
Mon
itor
for
accu
mul
atio
n of
se
dim
ent,
shee
n,
disc
olor
atio
n on
the
surf
ace,
fuel
odo
ur,
float
ing
debr
is a
nd
visi
ble
film
s or
any
oth
er
dele
terio
us s
ubst
ance
Con
firm
miti
gatio
n N
o re
sidu
al a
dver
se e
ffect
s on
su
rfac
e w
ater
qua
lity
are
expe
cted
fr
om th
e D
GR
pro
ject
pro
vide
d in
-de
sign
miti
gatio
n is
effe
ctiv
e.
Vis
ual i
nspe
ctio
n O
il an
d G
reas
e (P
WQ
O):
No
accu
mul
atio
n of
se
dim
ent a
nd fl
oatin
g de
bris
and
vis
ible
fil
ms.
PW
QO
Tab
le 1
, G
ener
al N
arra
tive
Obj
ectiv
es
No
depo
sit o
f de
lete
rious
sub
stan
ces
Wee
kly
Dra
inag
e sw
ales
and
per
imet
er
ditc
hes
C-E
MP
-SW
3 E
nsur
e th
at s
torm
in
terc
epto
r in
spec
tion
and
mai
nten
ance
pr
ogra
m is
in p
lace
Con
firm
miti
gatio
n N
o re
sidu
al a
dver
se e
ffect
s on
su
rfac
e w
ater
qua
lity
are
expe
cted
fr
om th
e D
GR
pro
ject
pro
vide
d in
-de
sign
miti
gatio
n is
effe
ctiv
e.
Rec
ords
che
ck
Insp
ectio
n an
d m
aint
enan
ce
freq
uenc
y m
eet
man
ufac
ture
r’s
spec
ifica
tions
Sem
i-ann
ually
N
/A
So
il Q
ual
ity
C-E
MP
-SQ
1 M
onito
ring
for
cont
amin
atio
n of
soi
l.
Con
firm
no
effe
ct
No
dire
ct o
r in
dire
ct li
kely
en
viro
nmen
tal e
ffect
s w
ere
iden
tifie
d fo
r th
e so
il qu
ality
VE
C.
Soi
l sam
plin
g an
d su
bsur
face
in
vest
igat
ion
prog
ram
.
Com
plia
nce
with
re
gula
tory
sta
ndar
ds
MO
E T
able
3 (
MO
E
2004
) or
res
tore
to
base
line
Pre
limin
ary
inve
stig
atio
n pr
ior
to s
ite p
repa
ratio
n an
d as
req
uire
d
As
need
ed a
nd w
here
nee
ded
in
resp
onse
to a
mal
func
tion
or
acci
dent
Ter
rest
rial
C-E
MP
-TE
R1
(con
tinua
tion
of C
-E
MP
-TE
R1)
Rec
ord
whi
te ta
il de
er,
wild
turk
ey v
ehic
le
strik
es
Con
firm
pr
edic
tions
W
hile
a
few
in
divi
dual
s co
uld
be
lost
be
caus
e of
pr
ojec
t-re
late
d ve
hicl
e st
rikes
, it
will
ha
ve
a ne
glig
ible
ef
fect
up
on
the
loca
l po
pula
tion.
Rep
ortin
g S
igni
fican
t ch
ange
at
a po
pula
tion
leve
l O
n-go
ing,
be
ginn
ing
in
year
2 o
f si
te p
repa
ratio
n an
d co
nstr
uctio
n.
DG
R
Pro
ject
A
rea,
to
be
re
port
ed
unde
r th
e B
ruce
nu
clea
r si
te p
rogr
am
EA
Fol
low
-Up
Mon
itorin
g P
rogr
am
- A
17
- M
arch
201
1
Tab
le 4
a. E
nvi
ron
men
tal M
anag
emen
t P
lan
Mo
nit
ori
ng
Pro
gra
m –
Sit
e P
rep
arat
ion
an
d C
on
stru
ctio
n P
has
e
Act
ivit
y ID
M
on
ito
rin
g A
ctiv
ity
Ob
ject
ive
EA
Sta
tem
en
t T
ype
of
Mo
nit
ori
ng
C
rite
ria
F
req
uen
cy
Lo
cati
on
Aq
uat
ic
C-E
MP
-AQ
1 C
ondu
ct s
ite in
spec
tion
– de
lete
rious
su
bsta
nces
Con
firm
miti
gatio
n U
se m
easu
res
to p
reve
nt
dele
terio
us s
ubst
ance
s su
ch a
s ne
w c
oncr
ete
(i.e.
, it i
s pr
ecas
t, cu
red
and
drie
d be
fore
use
nea
r th
e w
ater
cour
se),
gro
ut, p
aint
and
pr
eser
vativ
es fr
om e
nter
ing
the
wat
erco
urse
.
Vis
ual i
nspe
ctio
n N
o de
lete
rious
m
ater
ials
W
eekl
y du
ring
cons
truc
tion
of r
ail b
ed
cros
sing
and
ong
oing
in
cide
ntal
obs
erva
tions
Rai
l bed
cro
ssin
g
C-E
MP
-AQ
2 C
ondu
ct s
edim
ent a
nd
eros
ion
cont
rol m
easu
re
insp
ectio
n
Con
firm
miti
gatio
n In
stal
l effe
ctiv
e se
dim
ent a
nd
eros
ion
cont
rol m
easu
res
befo
re
star
ting
wor
k to
pre
vent
si
lt/se
dim
ent l
aden
run
off f
rom
di
rect
ly e
nter
ing
the
wat
er in
the
sout
h R
ailw
ay D
itch.
Insp
ect t
hem
re
gula
rly d
urin
g th
e co
urse
of
cons
truc
tion
and
mak
e al
l ne
cess
ary
repa
irs if
any
dam
age
occu
rs.
Vis
ual i
nspe
ctio
n E
ffect
ive
sedi
men
t an
eros
ion
cont
rol
mea
sure
s
Wee
kly
durin
g co
nstr
uctio
n of
rai
l bed
cr
ossi
ng a
nd o
ngoi
ng
inci
dent
al o
bser
vatio
ns
Rai
l bed
cro
ssin
g
C-E
MP
-AQ
3 C
ondu
ct s
ite in
spec
tion
– on
– s
ite m
achi
nery
C
onfir
m m
itiga
tion
Ope
ratio
n of
mac
hine
ry o
n la
nd
and
in a
man
ner
that
min
imiz
es
dist
urba
nce
to th
e ba
nks
of th
e so
uth
Rai
lway
Ditc
h.
Vis
ual i
nspe
ctio
n M
achi
nery
on
land
and
ba
nk d
istu
rban
ce
min
imiz
ed
Wee
kly
durin
g co
nstr
uctio
n of
rai
l bed
cr
ossi
ng a
nd o
ngoi
ng
inci
dent
al o
bser
vatio
ns
Rai
l bed
cro
ssin
g
C-E
MP
-AQ
4 C
ondu
ct s
ite in
spec
tion
– flu
id le
aks
Con
firm
miti
gatio
n M
achi
nery
is to
arr
ive
on s
ite in
a
clea
n co
nditi
on a
nd is
to b
e m
aint
aine
d fr
ee o
f flu
id le
aks.
Vis
ual i
nspe
ctio
n M
achi
nery
is fr
ee o
f flu
id le
aks
Wee
kly
durin
g co
nstr
uctio
n of
rai
l bed
cr
ossi
ng a
nd o
ngoi
ng
inci
dent
al o
bser
vatio
ns
Rai
l bed
cro
ssin
g
C-E
MP
-AQ
5 C
ondu
ct s
ite in
spec
tion
– ve
hicl
e m
aint
enan
ce
Con
firm
miti
gatio
n W
ash,
ref
uel a
nd s
ervi
ce
mac
hine
ry a
nd s
tore
fuel
and
oth
er
mat
eria
ls fo
r th
e m
achi
nery
aw
ay
from
the
wat
er to
pre
vent
any
de
lete
rious
sub
stan
ce fr
om
ente
ring
the
wat
er.
Vis
ual i
nspe
ctio
n
No
fuel
sto
rage
or
mai
nten
ance
act
iviti
es
near
wat
er.
Wee
kly
durin
g co
nstr
uctio
n of
rai
l bed
cr
ossi
ng a
nd o
ngoi
ng
inci
dent
al o
bser
vatio
ns
Rai
l bed
cro
ssin
g
C-E
MP
-AQ
6 C
ondu
ct s
ite in
spec
tion
– co
nfirm
ons
ite s
pill
kit
is a
cces
sibl
e
Con
firm
miti
gatio
n K
eep
an e
mer
genc
y sp
ill k
it on
site
in
cas
e of
flui
d le
aks
or s
pills
from
m
achi
nery
.
Vis
ual i
nspe
ctio
n S
pill
kit i
s ac
cess
ible
. W
eekl
y du
ring
cons
truc
tion
of r
ail b
ed
cros
sing
and
ong
oing
in
cide
ntal
obs
erva
tions
Rai
l bed
cro
ssin
g
C-E
MP
-AQ
7 C
ondu
ct s
ite in
spec
tion
– de
term
ine
if di
tch
mai
nten
ance
is r
equi
red
Con
firm
miti
gatio
n T
he r
egul
ar m
aint
enan
ce o
f the
di
tche
s w
ill in
clud
e dr
edgi
ng to
ex
trac
t pla
nt m
ater
ials
from
the
ditc
hes
to p
erm
it ef
ficie
nt fl
ow.
Vis
ual i
nspe
ctio
n M
inim
al p
lant
mat
eria
ls
Ann
ually
, dur
ing
the
grow
ing
seas
on
Sto
rmw
ater
man
agem
ent
syst
em
EA
Fol
low
-Up
Mon
itorin
g P
rogr
am
- A
18
- M
arch
201
1
Tab
le 4
a. E
nvi
ron
men
tal M
anag
emen
t P
lan
Mo
nit
ori
ng
Pro
gra
m –
Sit
e P
rep
arat
ion
an
d C
on
stru
ctio
n P
has
e
Act
ivit
y ID
M
on
ito
rin
g A
ctiv
ity
Ob
ject
ive
EA
Sta
tem
en
t T
ype
of
Mo
nit
ori
ng
C
rite
ria
F
req
uen
cy
Lo
cati
on
Atm
osp
her
ic
C-E
MP
-AT
M1
Con
duct
veh
icle
in
spec
tions
Con
firm
air
and
nois
e qu
ality
pr
edic
tions
Mai
ntai
n on
-site
veh
icle
s an
d eq
uipm
ent.
R
ecor
ds c
heck
E
quip
men
t is
m
aint
aine
d is
as
per
man
ufac
ture
r’s
spec
ifica
tion
Ann
ually
.
All
cons
truc
tion
vehi
cles
, in
desi
gnat
ed v
ehic
le m
aint
enan
ce
bays
/are
as.
C-E
MP
-AT
M2
Mon
itor
unde
rgro
und
air
qual
ity
Con
firm
as
sum
ptio
n N
o lik
ely
adve
rse
effe
ct id
entif
ied.
A
ir m
onito
ring
stat
ion
cont
rolle
d re
mot
ely
at s
urfa
ce:
CO
NO
2
airf
low
Min
es a
nd M
inin
g P
lant
s R
egul
atio
n (R
eg
854)
On-
goin
g du
ring
unde
rgro
und
cons
truc
tion
In
take
at M
ain
Sha
ft an
d un
derg
roun
d lo
catio
ns, T
BD
C-E
MP
-AT
M3
Mon
itor
unde
rgro
und
air
qual
ity (
expl
osiv
e ga
s)
Con
firm
as
sum
ptio
n N
o lik
ely
adve
rse
effe
ct id
entif
ied.
E
xplo
sive
gas
m
onito
r, in
clud
ing:
met
hane
hydr
ogen
Min
es a
nd M
inin
g P
lant
s R
egul
atio
n (R
eg
854)
Ong
oing
dur
ing
unde
rgro
und
cons
truc
tion
U
nder
grou
nd lo
catio
ns, T
BD
C-E
MP
-AT
M4
Mon
itor
unde
rgro
und
air
qual
ity (
tem
pera
ture
and
hu
mid
ity)
Con
firm
as
sum
ptio
n N
o lik
ely
adve
rse
effe
ct id
entif
ied.
W
et b
ulb
Tem
pera
ture
Dry
bul
b T
empe
ratu
re
Hum
idity
Min
es a
nd M
inin
g P
lant
s R
egul
atio
n (R
eg
854)
Ong
oing
dur
ing
unde
rgro
und
cons
truc
tion
In
take
at M
ain
Sha
ft an
d un
derg
roun
d lo
catio
ns, T
BD
.
Rad
iolo
gic
al
See
Tab
le 5
a
EA
Fol
low
-Up
Mon
itorin
g P
rogr
am
- A
19
- M
arch
201
1
Tab
le 4
b.
En
viro
nm
enta
l Man
agem
ent
Pla
n M
on
ito
rin
g P
rog
ram
– O
per
atio
ns
Act
ivit
y ID
M
on
ito
rin
g A
ctiv
ity
Ob
ject
ive
EA
Sta
tem
en
t T
ype
of
Mo
nit
ori
ng
C
rite
ria
F
req
uen
cy
Lo
cati
on
Su
rfac
e W
ater
O-E
MP
-SW
1
(con
tinua
tion
of C
-EM
P-
SW
1)
Con
duct
ope
ratio
n an
d m
aint
enan
ce in
spec
tion
to
ensu
re th
at th
e st
orm
wat
er
man
agem
ent s
yste
m a
nd
run-
off a
reas
do
not h
ave
extr
eme
eros
ion
wea
r.
Ens
ure
that
sed
imen
t co
ntro
l mat
eria
ls a
re k
ept
on h
and
for
emer
genc
y re
spon
se a
nd fo
r re
pair
and
mai
nten
ance
pu
rpos
es.
Con
firm
miti
gatio
n
No
resi
dual
adv
erse
ef
fect
s on
sur
face
wat
er
qual
ity a
re e
xpec
ted
from
the
DG
R p
roje
ct
prov
ided
in-d
esig
n m
itiga
tion
is e
ffect
ive.
Vis
ual I
nspe
ctio
n F
ree
of d
ebris
and
ero
sion
M
onth
ly d
urin
g op
erat
ions
S
torm
wat
er m
anag
emen
t sys
tem
O-E
MP
-SW
2
(con
tinua
tion
of C
-EM
P-
SW
2)
Mon
itor
for
accu
mul
atio
n of
se
dim
ent,
shee
n,
disc
olor
atio
n on
the
surf
ace,
fuel
odo
ur, f
loat
ing
debr
is a
nd v
isib
le fi
lms
or
any
othe
r de
lete
rious
su
bsta
nce
Con
firm
miti
gatio
n N
o re
sidu
al a
dver
se
effe
cts
on s
urfa
ce w
ater
qu
ality
are
exp
ecte
d fr
om th
e D
GR
pro
ject
pr
ovid
ed in
-des
ign
miti
gatio
n is
effe
ctiv
e.
Vis
ual i
nspe
ctio
n O
il an
d G
reas
e (P
WQ
O):
N
o ac
cum
ulat
ion
of
sedi
men
t and
floa
ting
debr
is a
nd v
isib
le fi
lms.
PW
QO
Tab
le 1
, Gen
eral
N
arra
tive
Obj
ectiv
es
No
depo
sit o
f del
eter
ious
su
bsta
nces
Mon
thly
S
torm
wat
er m
anag
emen
t sys
tem
O-E
MP
-SW
3 (c
ontin
uatio
n of
C-E
MP
-S
W3)
Ens
ure
that
sto
rm
inte
rcep
tor
insp
ectio
n an
d m
aint
enan
ce p
rogr
am is
in
plac
e an
d up
to d
ate
Con
firm
miti
gatio
n N
o re
sidu
al a
dver
se
effe
cts
on s
urfa
ce w
ater
qu
ality
are
exp
ecte
d fr
om th
e D
GR
pro
ject
pr
ovid
ed in
-des
ign
miti
gatio
n is
effe
ctiv
e.
Rec
ords
che
ck
Insp
ectio
n an
d m
aint
enan
ce fr
eque
ncy
mee
t man
ufac
ture
r’s
spec
ifica
tions
and
are
up
to d
ate
Sem
i-ann
ually
N
/A
Gro
un
dw
ater
O-E
MP
-GW
1
(a c
ontin
uatio
n of
C-E
A-
GW
1)
Mon
itor
shal
low
bed
rock
gr
ound
wat
er h
ydra
ulic
he
ad
Sub
stan
tiate
zon
e of
in
fluen
ce a
nd
draw
dow
n pr
edic
tions
and
to
dete
rmin
e w
heth
er
inflo
w r
ates
will
ex
ceed
50,
000
L/da
y.
Gro
und
trea
tmen
t ov
er
the
leng
th o
f the
sha
ft th
roug
h th
e ov
erbu
rden
so
ils a
nd u
pper
180
m
of b
edro
ck w
ill
min
imiz
e th
e am
ount
of
dew
ater
ing
Sha
llow
and
in
term
edia
te b
edro
ck
grou
ndw
ater
m
onito
ring
Per
mit
to T
ake
Wat
er
App
licat
ion
(reg
ulat
ory
requ
irem
ent (
OW
RA
199
0)
Qua
rter
ly m
onito
ring
4 D
GR
ser
ies
wel
ls
3 U
S s
erie
s w
ells
O-E
MP
-GW
2 (a
co
ntin
uatio
n of
(C
-EA
-G
W2)
Mon
itor
shal
low
sub
surf
ace
grou
ndw
ater
qua
lity
C
onfir
m p
redi
ctio
ns
of G
eosy
nthe
sis
prog
ram
use
d in
the
EA
.
Est
ablis
h se
ason
al
fluct
uatio
ns.
Ear
ly
dete
ctio
n ne
twor
k to
id
entif
y co
ntam
inat
ion.
Gro
undw
ater
sa
mpl
ing
prog
ram
C
ompl
ianc
e w
ith
regu
lato
ry s
tand
ards
MO
E
Tab
le 3
MO
E 2
004)
or
base
line
cond
ition
s
Qua
rter
ly m
onito
ring
8 ne
w w
ells
EA
Fol
low
-Up
Mon
itorin
g P
rogr
am
- A
20
- M
arch
201
1
Tab
le 4
b.
En
viro
nm
enta
l Man
agem
ent
Pla
n M
on
ito
rin
g P
rog
ram
– O
per
atio
ns
Act
ivit
y ID
M
on
ito
rin
g A
ctiv
ity
Ob
ject
ive
EA
Sta
tem
en
t T
ype
of
Mo
nit
ori
ng
C
rite
ria
F
req
uen
cy
Lo
cati
on
O-E
MP
-GW
3 (a
co
ntin
uatio
n of
C-E
A-
GW
3)
Mon
itorin
g sh
allo
w
subs
urfa
ce h
ydra
ulic
hea
d C
onfir
m p
redi
ctio
ns
of G
eosy
nthe
sis
prog
ram
use
d in
the
EA
, sub
stan
tiate
zo
ne o
f inf
luen
ce
and
draw
dow
n pr
edic
tions
and
to
dete
rmin
e w
heth
er
inflo
w r
ates
will
ex
ceed
50,
000
L/da
y
Zon
e of
influ
ence
is
estim
ated
at 5
4 m
. W
ater
leve
l mon
itorin
g pr
ogra
m
Abr
upt o
r gr
adua
l cha
nge
in g
roun
dwat
er fl
ow.
Qua
rter
ly m
onito
ring
8
new
wel
ls
Ter
rest
rial
O-E
MP
-TE
R1
(con
tinua
tion
of C
-EM
P-
TE
R1)
Rec
ord
whi
te ta
il de
er, w
ild
turk
ey v
ehic
le s
trik
es
Con
firm
pre
dict
ions
W
hile
a fe
w in
divi
dual
s co
uld
be lo
st b
ecau
se
of p
roje
ct-r
elat
ed
vehi
cle
strik
es, i
t will
ha
ve a
neg
ligib
le e
ffect
up
on th
e lo
cal
popu
latio
n
Rep
ortin
g S
igni
fican
t cha
nge
at a
po
pula
tion
leve
l O
n-go
ing
DG
R P
roje
ct A
rea,
to b
e re
port
ed u
nder
th
e B
ruce
nuc
lear
site
pro
gram
.
Aq
uat
ic
C-E
MP
-AQ
7 (c
ontin
uatio
n of
C-E
MP
-A
Q7)
Con
duct
site
insp
ectio
n –
ditc
h m
aint
enan
ce
Con
firm
miti
gatio
n T
he r
egul
ar
mai
nten
ance
of t
he
ditc
hes
will
incl
ude
dred
ging
to e
xtra
ct
plan
t mat
eria
ls fr
om th
e di
tche
s to
per
mit
effic
ient
flow
.
Vis
ual i
nspe
ctio
n M
inim
al p
lant
mat
eria
ls
Ann
ually
, dur
ing
the
grow
ing
seas
on
Sto
rmw
ater
man
agem
ent s
yste
m
Atm
osp
her
ic
O-E
MP
-AT
M1
(con
tinua
tion
of C
-EM
P-
AT
M1)
Con
duct
veh
icle
in
spec
tions
Con
firm
air
and
nois
e qu
ality
pr
edic
tions
Mai
ntai
n on
-site
ve
hicl
es a
nd
equi
pmen
t.
Rec
ords
che
ck
Equ
ipm
ent i
s m
aint
aine
d as
per
man
ufac
ture
r’s
spec
ifica
tion
Ann
ually
.
All
cons
truc
tion
vehi
cles
, in
desi
gnat
ed
vehi
cle
mai
nten
ance
bay
s/ar
eas.
O-E
MP
-AT
M2
(con
tinua
tion
of C
-EM
P-
AT
M2)
Mon
itor
unde
rgro
und
air
qual
ity
Con
firm
ass
umpt
ion
No
likel
y ad
vers
e ef
fect
id
entif
ied.
A
ir m
onito
ring
stat
ion
cont
rolle
d re
mot
ely
at
surf
ace:
CO
NO
2
airf
low
Min
es a
nd M
inin
g P
lant
s R
egul
atio
n (R
eg 8
54)
On-
goin
g du
ring
oper
atio
ns
Inta
ke a
t Mai
n S
haft
and
unde
rgro
und
loca
tions
, TB
D.
O-E
MP
-AT
M3
(con
tinua
tion
of C
-EM
P-
AT
M3)
Mon
itor
unde
rgro
und
air
qual
ity (
expl
osiv
e ga
s)
Con
firm
ass
umpt
ion
No
likel
y ad
vers
e ef
fect
id
entif
ied.
E
xplo
sive
gas
mon
itor,
in
clud
ing:
met
hane
hydr
ogen
Min
es a
nd M
inin
g P
lant
s R
egul
atio
n (R
eg 8
54)
On-
goin
g du
ring
oper
atio
ns
Und
ergr
ound
loca
tions
, TB
D.
O-E
MP
-AT
M4
(con
tinua
tion
of C
-EM
P-
AT
M4)
Mon
itor
unde
rgro
und
air
qual
ity (
tem
pera
ture
and
hu
mid
ity)
Con
firm
ass
umpt
ion
No
likel
y ad
vers
e ef
fect
id
entif
ied.
W
et b
ulb
Tem
pera
ture
Dry
bul
b T
empe
ratu
re
Hum
idity
Min
es a
nd M
inin
g P
lant
s R
egul
atio
n (R
eg 8
54)
On-
goin
g du
ring
oper
atio
ns
Inta
ke a
t Mai
n S
haft
and
unde
rgro
und
loca
tions
, TB
D.
EA
Fol
low
-Up
Mon
itorin
g P
rogr
am
- A
21
- M
arch
201
1
Tab
le 4
b.
En
viro
nm
enta
l Man
agem
ent
Pla
n M
on
ito
rin
g P
rog
ram
– O
per
atio
ns
Act
ivit
y ID
M
on
ito
rin
g A
ctiv
ity
Ob
ject
ive
EA
Sta
tem
en
t T
ype
of
Mo
nit
ori
ng
C
rite
ria
F
req
uen
cy
Lo
cati
on
O-E
MP
-AT
M5
Con
duct
ven
tilat
ion
insp
ectio
n C
onfir
m m
itiga
tion
Mai
ntai
n fr
esh
air
and
retu
rn a
ir ra
ise
fans
. R
ecor
ds c
heck
F
ans
mai
ntai
ned
in g
ood
wor
king
ord
er,
mai
nten
ance
con
duct
ed
and
reco
rded
as
per
man
ufac
ture
r’s
inst
ruct
ions
.
Ann
ual r
ecor
ds c
heck
N
/A
Rad
iati
on
an
d R
adio
acti
vity
See
Tab
le 5
b
EA
Fol
low
-Up
Mon
itorin
g P
rogr
am
- A
22
- M
arch
201
1
Th
is p
age
has
bee
n le
ft b
lan
k in
ten
tio
nal
ly
EA Follow-Up Monitoring Program - A 23 - March 2011
Table 4c. Environmental Management Plan Monitoring Program - Accident Prevention Checklist
Activity ID Task Activity Type Frequency
C-EMP-MA1 Verify that all work is carried out in compliance with all applicable air emissions regulations and by-laws. Vehicles/machinery to be in good repair, equipped with emission controls as applicable and operated within regulatory requirements.
Visual inspection and records check
Quarterly during site preparation and construction
C-EMP-MA3 Verify that storing, mixing and cleaning operations are carried out away from surface water bodies.
Visual inspection
Quarterly during site preparation and construction
C-EMP-MA4 Verify that all activities including maintenance procedures are controlled to prevent the entry of petroleum products, debris, rubble, concrete, uncured cement leachate, or other deleterious substances into surface water bodies.
Visual inspection
Quarterly during site preparation and construction
C-EMP-MA5 Verify that hazardous substances (including fuel) are stored, handled and applied in a manner to prevent release to surface water. A spill response kit to be on site in the event of a spill.
Immediately contain and clean up any spills in accordance with provincial regulatory requirements. Report spill to the Ontario Spills Actions Centre (1-800-268-6060).
Visual inspection
Quarterly during site preparation and construction
C-EMP-MA6 Verify that construction machinery and equipment arrive on-site in a clean condition, are maintained free of fluid leaks, and are equipped with appropriate silencers.
Visual inspection, records inspection
As equipment is received on site
C-EMP-MA7 Verify that on-site vehicles are properly maintained. Visual inspection, records inspection
Quarterly during site preparation and construction
C-EMP-MA8 Ensure a tight project footprint is maintained. Visual inspection
Quarterly during site preparation and construction
C-EMP-MA9 Verify that washing or refuelling is taking place in the designated area.
Visual inspection
Quarterly during site preparation and construction and operations
C-EMP-MA11
Verify that work areas are clearly defined and identified.
Visual inspection
Quarterly during site preparation and construction and operations
C-EMP-MA12
Verify that workers are wearing protective gear (e.g. safety work boots, hard hats, safety goggles, safety vests etc.) in accordance with the Occupational Health and Safety Act and regulations.
Visual inspection
Quarterly during site preparation and construction and operations
EA Follow-Up Monitoring Program - A 24 - March 2011
Table 4c. Environmental Management Plan Monitoring Program - Accident Prevention Checklist
Activity ID Task Activity Type Frequency
C-EMP-MA13
Verify that access to work areas for fire and emergency vehicles is maintained.
Visual inspection
Quarterly during site preparation and construction and operations
C-EMP-MA14
Verify that all work areas and machinery are stabilized and made safe and secure at the end of each workday to prevent accidents from occurring to people and the environment.
Visual inspection
Quarterly during site preparation and construction and operations
C-EMP-MA15
Verify that appropriate training and operating procedures are in place, and that training is current/up-to-date.
Records check Annually during site preparation and construction and operations
C-EMP-MA16
Verify that suitable fire detection and suppression equipment such as automatic fire suppression systems on diesel transfer equipment is in place and follows a routine testing schedule.
Visual inspection and records check
Quarterly during site preparation and construction and operations
C-EMP-MA17
Verify that drills for emergency assembly in underground refuge stations are practiced.
Records check Once per year
C-EMP-MA18
Verify contamination and dose rate monitoring programs are in place and are properly recorded.
Visual inspection and records check
Quarterly during operations
C-EMP-MA19
Verify that combustible materials and ignition sources are kept to a minimum.
Visual inspection
Quarterly during site preparation and construction and operations
C-EMP-MA20
Verify that waste generated in the building is be disposed of in accordance with applicable legislation (i.e. Ontario Regulation 347, as amended).
Records check Quarterly during site preparation and construction and operations
EA
Fol
low
-Up
Mon
itorin
g P
rogr
am
- A
25
- M
arch
201
1
Tab
le 5
a. R
adio
log
ical
Reg
ula
tory
Mo
nit
ori
ng
Pro
gra
m –
Sit
e P
rep
arat
ion
an
d C
on
stru
ctio
n
Act
ivit
y ID
M
on
ito
rin
g
Act
ivit
y O
bje
ctiv
e T
ype
of
Mo
nit
ori
ng
C
rite
ria
F
req
uen
cy
Lo
cati
on
Rad
iolo
gic
al
C-L
IC-R
AD
1 A
ir m
onito
ring
Con
firm
no
effe
ct, c
onfir
m
effe
ctiv
enes
s of
miti
gatio
n
Air
mon
itorin
g:
Rad
on
Rad
on <
150
B
q/m
3 (N
WM
O
2011
h)
1 sa
mpl
e pe
r m
onth
/loca
tion
durin
g un
derg
roun
d co
nstr
uctio
n.
Con
tinua
tion
of th
e pr
ogra
m w
ill b
e re
-ev
alua
ted
base
d on
the
resu
lts.
DG
R P
roje
ct S
ite;
TB
D
C-L
IC-R
AD
2 G
roun
dwat
er
mon
itorin
g to
de
term
ine
chan
ges
in le
vel
of g
roun
dwat
er
cont
amin
atio
n
Ver
ify
pred
icte
d ef
fect
s
Gro
undw
ater
sa
mpl
e:
Trit
ium
Gro
ss b
eta
Est
ablis
h B
asel
ine
Qua
rter
ly
8 ne
w m
onito
ring
wel
ls
C-L
IC-R
AD
3 S
torm
wat
er
mon
itorin
g of
ra
dioa
ctiv
ity in
st
orm
wat
er
man
agem
ent
syst
em
Ver
ify
pred
icte
d ef
fect
s
Gra
b sa
mpl
e:
Trit
ium
Gro
ss B
eta
Car
bon-
14
Est
ablis
h B
asel
ine
(Bq/
L)
Trit
ium
and
Gro
ss B
eta:
m
onth
ly, b
egin
ning
one
ye
ar p
rior
to o
pera
tions
: C
onsi
sten
t with
the
exis
ting
WW
MF
ra
diol
ogic
al m
onito
ring
prog
ram
. C
arbo
n-14
, qu
arte
rly b
egin
ning
one
ye
ar p
rior
to o
pera
tions
.
1 sa
mpl
e fr
om
SW
MP
, 1 fr
om
mar
sh
C-L
IC -
RA
D4
Ext
erna
l ra
diat
ion
mon
itorin
g pr
ogra
m
Ver
ify
pred
ictio
ns
Ave
rage
gam
ma
dose
rat
e.
The
rmol
umin
esce
nt
Dos
imet
ers
(TLD
) m
ount
ed o
n th
e fe
nces
0.5
uGy/
h C
hang
ed a
nd a
naly
zed
quar
terly
. C
onsi
sten
t with
th
e ex
istin
g W
WM
F
radi
olog
ical
mon
itorin
g pr
ogra
m
Exi
stin
g W
WM
F
nort
h fe
ncel
ine
TLD
s
EA
Fol
low
-Up
Mon
itorin
g P
rogr
am
- A
26
- M
arch
201
1
Tab
le 5
a. R
adio
log
ical
Reg
ula
tory
Mo
nit
ori
ng
Pro
gra
m –
Sit
e P
rep
arat
ion
an
d C
on
stru
ctio
n
Act
ivit
y ID
M
on
ito
rin
g
Act
ivit
y O
bje
ctiv
e T
ype
of
Mo
nit
ori
ng
C
rite
ria
F
req
uen
cy
Lo
cati
on
C-L
IC-R
AD
5
Sum
p w
ater
m
onito
ring
V
erify
pr
edic
ted
effe
cts
Gra
b sa
mpl
e:
Trit
ium
Gro
ss B
eta
Car
bon-
14
WW
MF
DR
L fo
r T
ritiu
m a
nd G
ross
B
eta
in s
urfa
ce
wat
er (
1.7
5E+
14
and
9.63
E+
09
Bq/
mo,
re
spec
tivel
y)
Car
bon-
14, T
BD
Trit
ium
and
Gro
ss B
eta:
w
eekl
y sa
mpl
es a
vera
ged
mon
thly
, beg
inni
ng o
ne-
year
prio
r to
ope
ratio
ns.
Con
sist
ent w
ith th
e ex
istin
g W
WM
F
radi
olog
ical
mon
itorin
g pr
ogra
m.
Car
bon-
14: q
uart
erly
be
ginn
ing
one
year
prio
r to
op
erat
ions
.
1 sa
mpl
e fr
om
stor
mce
ptor
at s
ump
disc
harg
e
Not
es:
TB
D =
To
be d
eter
min
ed
EA
Fol
low
-Up
Mon
itorin
g P
rogr
am
- A
27
- M
arch
201
1
Tab
le 5
b. R
adio
log
ical
Reg
ula
tory
Req
uir
eme
nts
Mo
nit
ori
ng
Pro
gra
m –
Op
erat
ion
s
Act
ivit
y ID
M
on
ito
rin
g
Act
ivit
y O
bje
ctiv
e T
ype
of
Mo
nit
ori
ng
C
rite
ria
F
req
uen
cy
Lo
cati
on
Rad
iati
on
an
d R
adio
acti
vity
O-L
IC-R
AD
1 (c
ontin
uatio
n of
C-L
IC-
RA
D1)
Air
mon
itorin
g C
onfir
m
miti
gatio
n;
verif
y pr
edic
ted
effe
cts
Air
mon
itorin
g:
rado
n, tr
itium
, pa
rtic
ulat
e an
d ca
rbon
-14
Rad
on <
150
Bq/
m3
(NW
MO
20
11b)
.
Trit
ium
, pa
rtic
ulat
e an
d ca
rbon
-14
will
be
com
pare
d to
th
e sa
me
DR
Ls
as th
e W
WM
F
(2.6
7E+
15,
5.62
E+
10 a
nd
8.19
E+
13
Bq/
wee
k re
spec
tivel
y).
Rad
on:
TB
D b
ased
on
resu
lts (
See
C-
LIC
-RA
D1)
Trit
ium
, pa
rtic
ulat
e an
d ca
rbon
-14:
co
ntin
uous
, an
alyz
ed w
eekl
y
Sel
ecte
d un
derg
roun
d lo
catio
ns fo
r R
adon
, TB
D.
Ven
t exh
aust
and
WP
RB
ex
haus
t for
triti
um, p
artic
ulat
e an
d ca
rbon
-14.
O-
LIC
-R
AD
2 (c
ontin
uatio
n of
C-L
IC-
RA
D2)
Gro
undw
ater
m
onito
ring
to
dete
rmin
e ch
ange
s in
le
vel o
f gro
undw
ater
co
ntam
inat
ion
Ver
ify
pred
icte
d ef
fect
s
Gro
undw
ater
sa
mpl
ing:
triti
um
and
gros
s be
ta
Com
pare
d to
ba
selin
e
Con
sist
ent w
ith
the
exis
ting
WW
MF
ra
diol
ogic
al
mon
itorin
g pr
ogra
m
Qua
rter
ly
8 ne
wly
built
mon
itorin
g w
ells
O-
LIC
-R
AD
3 (c
ontin
uatio
n of
C-L
IC-
RA
D3)
Sto
rmw
ater
m
onito
ring
of
radi
oact
ivity
in
stor
mw
ater
m
anag
emen
t sys
tem
.
Ver
ify
pred
icte
d ef
fect
s
Gra
b sa
mpl
e:
Trit
ium
Gro
ss B
eta
C-1
4
Bas
elin
e (B
q/L)
Con
sist
ent w
ith
the
exis
ting
WW
MF
ra
diol
ogic
al
mon
itorin
g pr
ogra
m
Trit
ium
and
G
ross
Bet
a:
mon
thly
.
Car
bon-
14:
annu
ally
.
1 sa
mpl
e fr
om S
WM
P, 1
from
m
arsh
EA
Fol
low
-Up
Mon
itorin
g P
rogr
am
- A
28
- M
arch
201
1
Tab
le 5
b. R
adio
log
ical
Reg
ula
tory
Req
uir
eme
nts
Mo
nit
ori
ng
Pro
gra
m –
Op
erat
ion
s
Act
ivit
y ID
M
on
ito
rin
g
Act
ivit
y O
bje
ctiv
e T
ype
of
Mo
nit
ori
ng
C
rite
ria
F
req
uen
cy
Lo
cati
on
O-
LIC
-R
AD
4 (c
ontin
uatio
n of
C-L
IC-
RA
D4)
Ext
erna
l rad
iatio
n m
onito
ring
prog
ram
V
erify
pr
edic
tions
A
vera
ge g
amm
a do
se r
ate
The
rmol
umin
esce
nt
Dos
imet
ers
(TLD
) m
ount
ed o
n th
e fe
nces
0.5u
Gy/
h
Cha
nged
and
an
alyz
ed
quar
terly
. C
onsi
sten
t with
th
e ex
istin
g W
WM
F
radi
olog
ical
m
onito
ring
prog
ram
.
DG
R fe
nce
line,
the
num
ber
of
sam
ple
loca
tions
TB
D.
O-L
IC-R
AD
5
(con
tinua
tion
of C
-LIC
-R
AD
5)
Sum
p w
ater
m
onito
ring
V
erify
pr
edic
ted
effe
cts
Trit
ium
Gro
ss B
eta
Car
bon-
14
WW
MF
DR
L fo
r T
ritiu
m a
nd
Gro
ss B
eta
in
surf
ace
wat
er
(1.7
5E+
14 a
nd
9.63
E+
09
Bq/
mo,
re
spec
tivel
y).
Con
sist
ent w
ith
the
exis
ting
WW
MF
ra
diol
ogic
al
mon
itorin
g pr
ogra
m.
Car
bon-
14:
TB
D.
Trit
ium
and
gro
ss
beta
:
wee
kly
sam
ples
av
erag
ed
mon
thly
, be
ginn
ing
one-
year
prio
r to
op
erat
ions
.
Car
bon-
14:
annu
ally
.
1 sa
mpl
e fr
om s
torm
cept
or a
t su
mp
disc
harg
e
EA
Fol
low
-Up
Mon
itorin
g P
rogr
am
- A
29
- M
arch
201
1
Tab
le 5
b. R
adio
log
ical
Reg
ula
tory
Req
uir
eme
nts
Mo
nit
ori
ng
Pro
gra
m –
Op
erat
ion
s
Act
ivit
y ID
M
on
ito
rin
g
Act
ivit
y O
bje
ctiv
e T
ype
of
Mo
nit
ori
ng
C
rite
ria
F
req
uen
cy
Lo
cati
on
O-L
IC-R
AD
6 R
adia
tion
and
cont
amin
atio
n co
ntro
l
Rou
tine
Sur
vey
Pro
gram
C
ompl
ianc
e w
ith th
e re
quire
men
ts o
f th
e R
adia
tion
Pro
tect
ion
Req
uire
men
ts
(OP
G 2
001)
.
Con
sist
ent w
ith
the
exis
ting
WW
MF
ra
diol
ogic
al
mon
itorin
g pr
ogra
m.
To
be s
peci
fied
in
the
oper
atio
ns
licen
ce
appl
icat
ion
To
be s
peci
fied
in th
e op
erat
ing
licen
ce a
pplic
atio
n
O-L
IC-R
AD
7 Q
uart
erly
dos
e ac
cum
ulat
ion
W
hole
bod
y do
se
and
skin
bet
a do
se
acco
rdin
g to
wor
k gr
oup.
Com
plia
nce
with
the
requ
irem
ents
of
the
Rad
iatio
n P
rote
ctio
n R
equi
rem
ents
(O
PG
200
1).
Con
sist
ent w
ith
the
exis
ting
WW
MF
ra
diol
ogic
al
mon
itorin
g pr
ogra
m.
To
be s
peci
fied
in
the
oper
atin
g lic
ence
ap
plic
atio
n
To
be s
peci
fied
in th
e op
erat
ing
licen
ce a
pplic
atio
n
Not
es:
TB
D –
To
be d
eter
min
ed
EA
Fol
low
-Up
Mon
itorin
g P
rogr
am
- A
30
- M
arch
201
1
Th
is p
age
has
bee
n le
ft b
lan
k in
ten
tio
nal
ly
EA
Fol
low
-Up
Mon
itorin
g P
rogr
am
- A
31
- M
arch
201
1
Tab
le 6
. C
on
ven
tio
nal
Reg
ula
tory
Mo
nit
ori
ng
Pro
gra
m
Act
ivit
y ID
M
on
ito
rin
g A
ctiv
ity
Ob
ject
ive
Reg
ula
tory
Bo
dy
Typ
e o
f M
on
ito
rin
g
Cri
teri
a
Fre
qu
enc
y L
oca
tio
n
Req
uir
eme
nt
Su
rfac
e W
ater
C-R
EG
-S
W1
Col
lect
Sur
face
Wat
er
Man
agem
ent S
yste
m s
ampl
es
Com
ply
with
S
ectio
n 53
of
the
Ont
ario
W
ater
R
eso
urce
s A
ct
MO
E
Sam
plin
g E
vent
:
TS
S
40 m
g/L
(MO
E 1
994b
an
d M
OE
F-5
-1)
Qua
rter
ly
1 S
WM
P
disc
harg
e sa
mpl
e
Com
ply
with
co
nditi
ons
of C
of A
C-R
EG
-S
W2
Mon
itor
effl
uent
– e
nsur
e ef
fluen
t fro
m p
ond
is fr
ee o
f flo
atin
g an
d se
ttlea
ble
solid
s an
d do
es n
ot c
onta
in o
il or
an
y ot
her
subs
tanc
e in
am
ount
s su
ffici
ent t
o cr
eate
a
visi
ble
film
, she
en, f
oam
or
disc
olor
atio
n or
any
oth
er
dele
terio
us s
ubst
ance
Com
ply
with
S
ectio
n 53
of
the
Ont
ario
W
ater
R
eso
urce
s A
ct
MO
E
Vis
ual i
nspe
ctio
n N
o ob
serv
ed fl
oatin
g an
d se
ttlea
ble
solid
s.
No
oil o
r ot
her
subs
tanc
es th
at c
reat
e a
shee
n, fo
am o
r di
scol
orat
ion
of th
e re
ceiv
ing
wat
er.
Mon
thly
.
SW
MP
di
scha
rge
Com
ply
with
co
nditi
ons
of C
of A
C-R
EG
-S
W3
Mon
itor
flow
C
ompl
y w
ith
Sec
tion
53
of th
e O
ntar
io
Wat
er
Res
our
ces
Act
MO
E
Flo
w m
easu
rem
ent
W
eekl
y flo
w
mea
sure
men
ts ,
aver
aged
mon
thly
SW
MP
di
scha
rge
Com
ply
with
co
nditi
ons
of C
of A
Gro
un
dw
ater
C-R
EG
-G
W1
Iden
tify
and
mon
itor
any
pote
ntia
lly c
onta
min
ated
gr
ound
wat
er in
res
pons
e to
a
spill
.
Com
ply
with
O
ntar
io
Reg
ulat
ion
675.
MO
E
Gro
undw
ater
sam
plin
g pr
ogra
m
Com
plia
nce
with
re
gula
tory
sta
ndar
ds
MO
E T
able
3 (
MO
E
2004
) or
bas
elin
e co
nditi
ons
As
need
ed
Whe
re n
eede
d in
res
pons
e to
m
alfu
nctio
n or
ac
cide
nt
Ont
ario
Reg
ulat
ion
675
C-R
EG
-G
W2
Mea
sure
flow
C
ompl
y w
ith
Sec
tion
34
of th
e O
ntar
io
Wat
er
Res
our
ces
Act
MO
E
Flo
w m
onito
ring
Dai
ly ta
king
s lim
it as
sp
ecifi
ed in
the
PT
TW
D
aily
dur
ing
dew
ater
ing
for
dura
tion
of s
ite
prep
arat
ion
and
cons
truc
tion
or a
s sp
ecifi
ed in
the
PT
TW
.
Ann
ual R
epor
ting
to th
e M
OE
.
At p
oint
of
disc
harg
e at
su
rfac
e
PT
TW
C-R
EG
-G
W3
Mon
itor
shal
low
sub
surf
ace
hydr
aulic
hea
d to
est
imat
e gr
ound
wat
er fl
ow a
nd Z
OI
Com
ply
with
S
ectio
n 34
of
the
Ont
ario
W
ater
R
eso
urce
s A
ct
MO
E
Wat
er le
vel m
onito
ring
prog
ram
A
brup
t or
grad
ual
chan
ge in
gro
undw
ater
flo
w
Qua
rter
ly m
onito
ring
for
dura
tion
of s
ite
prep
arat
ion
and
cons
truc
tion
or a
s sp
ecifi
ed in
the
PT
TW
8 ne
w w
ells
P
TT
W
EA
Fol
low
-Up
Mon
itorin
g P
rogr
am
- A
32
- M
arch
201
1
Tab
le 6
. C
on
ven
tio
nal
Reg
ula
tory
Mo
nit
ori
ng
Pro
gra
m
Act
ivit
y ID
M
on
ito
rin
g A
ctiv
ity
Ob
ject
ive
Reg
ula
tory
Bo
dy
Typ
e o
f M
on
ito
rin
g
Cri
teri
a
Fre
qu
enc
y L
oca
tio
n
Req
uir
eme
nt
Aq
uat
ic
C-R
EG
-A
Q1
Mon
itor
re-g
row
th o
f rip
aria
n ve
geta
tion
follo
win
g re
mov
al,
note
any
def
icie
ncie
s in
ban
k st
abili
ty
Con
firm
ef
fect
si
gnifi
canc
e,
conf
irm
miti
gatio
n
MN
R
Vis
ual i
nspe
ctio
n H
ealth
y es
tabl
ishe
d ve
geta
tion.
No
defic
ienc
ies
in b
ank
stab
ility
.
Ann
ually
afte
r si
te
prep
arat
ion
and
cons
truc
tion
of a
cces
s ro
ad c
ross
ing.
For
a
min
imum
of 2
gro
win
g se
ason
s. I
f no
dist
ress
ed
vege
tatio
n or
ban
k in
stab
ility
is n
oted
, pr
ogra
m m
ay b
e di
scon
tinue
d.
Loca
tion:
di
stur
bed
area
s;
at a
cces
s ro
ad
cros
sing
In w
ater
wor
k pe
rmit,
Fis
herie
s A
ct v
ia S
auge
en
Val
ley
Con
serv
atio
n A
utho
rity
Atm
osp
her
ic
C-R
EG
-A
TM
1 R
epor
t air
emis
sion
s
Com
ply
with
O
ntar
io
Reg
ulat
ion
127
MO
E
Mod
ellin
g O
.Reg
127
A
nnua
lly
Onl
ine
Rep
ort
NP
RI/R
eg 1
27
Rep
ortin
g
C-R
EG
A
TM
-2
Mon
itor/
mod
el a
ir qu
ality
em
issi
ons
C
ompl
y w
ith
Ont
ario
R
egul
atio
n 41
9
MO
E
Mod
ellin
g an
d/or
mon
itorin
g O
. Reg
419
A
nnua
lly
Ven
t exh
aust
C
of A
(A
ir)
Rad
iolo
gic
al
See
Tab
les
5a a
nd 5
b
Not
es:
P
TT
W –
Per
mit
to T
ake
Wat
er
M
OE
– O
nta
rio M
inis
try
of th
e E
nviro
nmen
t
C o
f A –
Cer
tific
ate
of a
ppro
val
M
NR
– M
inis
try
of N
atur
al R
esou
rces
NP
RI –
Nat
iona
l Pol
luta
nt R
elea
se In
vent
ory
Z
OI –
Zon
e of
influ
ence