Dfr for Air-conditioning at Kp-4

download Dfr for Air-conditioning at Kp-4

of 23

Transcript of Dfr for Air-conditioning at Kp-4

  • 8/18/2019 Dfr for Air-conditioning at Kp-4

    1/23

     

    DETAILED FEASIBILITY REPORT

    ON THE INSTALLATION OF

    GEO-THERMAL HEAT SINK

    SYSTEM AT

    KNOWLEDGE PARK-IV.

  • 8/18/2019 Dfr for Air-conditioning at Kp-4

    2/23

     

    EXISTING STRUCTURE OF KNOWLEDGE PARK-IV BUILDING WITH B+G+4

  • 8/18/2019 Dfr for Air-conditioning at Kp-4

    3/23

    1

    2

    3

    1

    2

    3

    4  Heat Exchange thru Infiltration

    Heat Gain from Human

    Heat Gain from Electrical Equipments

    2-External Heat Gain Heat Gain from Wall

    Heat Gain from Window

     Heat Gain from Area

    Heat Gain from Lighting

    DESIGN CONSIDERATIONS

    There are several methods available to calculate the cooling load of a commercial building, such as :

    1) Total Equivalent Temperature Difference/Time Average (TETD/TA)

    2) Cooling Load Temperature Difference/Cooling Load Factor (CLTD/CLF)

    3) Transfer Function Method (TFM)

    4) Heat Balance (HB) & Radiant Time Series (RTS)

    5) Manual J Method for Residential Applications & Manual N for Commercial Buildings: These methods are simplified

    versions, jointly developed by Air conditioning contractors of America (ACCA) and the Air conditioning and

    Refrigeration Institute (ARI).

    These different methods may yield different results for the same input data. This is primarily due to the way; each

    method handles the solar effect and building dynamics. But in true sense all the above approaches attempt to consider the

    fundamental principle that heat flow rates are not instantaneously converted to loads and heat addition or extraction incident

    upon the building do not immediately result in a change in temperature. Thermally heavy buildings can effectively delay the

    cooling or heating load for several hours.

    Most designers use the TETD and CLTD methods because these methods are simple to use, give component loads

    and tend to predict load on conservative side.

    For strictly manual cooling loads calculation method, the most practical to use is the CLTD/CLF method.

    Here in the cooling load calculation for KNOWLEDGE PARK - IV, we have considered this same method.

    1-Internal Heat Gain 

  • 8/18/2019 Dfr for Air-conditioning at Kp-4

    4/23

     

    Q = U * A * (CLTD)

    Q = HEAT GAINED IN BTU'S

    DBT = DRY BULB TEMPERATURE.

    U = Thermal transmittance for roof or wall or glass. See 1997 ASHRAE Fundamentals, Chapter 24 or 2001 ASHRAEFundamentals, chapter 25.

     A = area of wall or glass calculated from building plans

    CLTD = Cooling Load Temperature Difference for roof, wall or glass. Refer 1997 ASHRAE Fundamentals, Chapter 28,

    tables 30, 31, 32, 33 and 34.

    CLTD correlated = CLTD + (78-tr) + (tm-85)

    Design Consideration:

    INSIDE TEMPERATURE = 64.4 F or 18 °C

    OUTSIDE TEMEPRATURE = 113 F or 45 °C

    tr =64.4 F (room temperature)

    tm = 88.7 F (mean temperature = (tr+to)/2))

    DESIGN CONSIDERATIONS

  • 8/18/2019 Dfr for Air-conditioning at Kp-4

    5/23

    TOTAL BUILT-UP AREA = 4390.31 sqft 

     AIR-CONDITIONING REQUIRED IN THE TOTAL BUILT-UP AREA = 55,995 sqft 

    CAFETERIA IN TERRACE

    OPEN AREA FOR OUTDOOR UNITS APPROX TONNAGE REQUIRED = 48.97 

    SECOND FLOOR APPROX TONNAGE REQUIRED = 89.77

    THIRD FLOOR APPROX TONNAGE REQUIRED = 88.41

    TOTAL BUILT-UP AREA = 11287.13 sqft 

    TOTAL BUILT-UP AREA = 11287.13 sqft 

    FIRST FLOOR APPROX TONNAGE REQUIRED = 85.04

    TOTAL BUILT-UP AREA = 11287.13 sqft 

    BASEMENT APPROX TONNAGE REQUIRED = 64.78 

    GROUND FLOOR

    PANEL ROOM

     APPROX TONNAGE REQUIRED = 57.60 

    TOTAL BUILT-UP AREA = 8871.86 sqft 

    TOTAL BUILT-UP AREA = 8871.86 sqft

    (excluding panel room)

  • 8/18/2019 Dfr for Air-conditioning at Kp-4

    6/23

    TOTAL ADDITIONAL AREA = 3110.7 sqft per floor (Approx.)

    EXISTING STRUCTURE

    ADDITIONAL AREA

    HEAT LOAD FOR THIS ADDITIONAL AREA WILL DEPEND UPON INTERNAL SEATING PLAN (EITHER

    CABINS OR OPEN AREA INCLUDING WORK STATIONS & CUBICLES)

  • 8/18/2019 Dfr for Air-conditioning at Kp-4

    7/23

    CONVENTIONAL HVAC SYSTEM

    The Conventional HVAC system used for air conditioning system removes heat from inside

    of the building and transfers it to the outside via the condenser to keep your inside

    environment cool in the summer. This type of system typically pairs a chiller with a cooling

    tower. Like the condenser used in our home’s central AC system, the chiller is a machine

    that removes heat from the building. A piped water loop runs through the building, picking

    up heat along the way, which is circulated though the chiller to be cooled —in a continuous

    loop called the chilled water loop. The heat removed by the chiller is rejected to the

    outside through a different piped water loop (called the condenser loop). This condenser

    water loop runs through a cooling tower, which uses evaporative cooling to cool this piped

    water—typically by 10 degrees Fahrenheit—which is circulated back to the chiller in a

    continuous loop.

    Evaporative cooling is the same cooling process our body uses, i.e., as perspiration

    evaporates, it pulls heat away from our body. Just like the perspiration on our skin, the

    evaporated water carries heat and is lost to the atmosphere. This lost water must be addedback into the system, or "made up."

  • 8/18/2019 Dfr for Air-conditioning at Kp-4

    8/23

    VRF SYSTEM (VARIABLE REFRIGERENT FLOW SYSTEM)

    A split system air-conditioner or heat pump incorporating a single refrigerant circuit, with

    one or more outdoor units, at least one variable speed compressor or an alternative

    compressor combination for varying the capacity of the system by three or more steps,

    multiple indoor fan coil units, each of which is individually metered and individuallycontrolled by a proprietary control device and common communications network. The

    system shall be capable of operating either as an air conditioner or a heat pump. Variable

    refrigerant flow implies three or more steps of control on common, inter-connecting

    piping. One outdoor unit can serve multiple indoor units connected by refrigerant piping.

    The systems use R-410A refrigerant, which is applicable for LEED. The combination of the

    more efficient refrigerant, variable refrigerant volume, inverter driven compressor, and DC

    fan and compressor motors provide high coefficients of performance (COP), even at low

    temperatures.

    VRFs are typically installed with an Air conditioner inverter which adds a DC inverter to the

    compressor in order to support variable motor speed and thus variable refrigerant flow

    rather than simply on/off operation. By operating at varying speeds, VRF units work only at

    the needed rate allowing for substantial energy savings at partial-load conditions. Heat

    recovery VRF technology allows individual indoor units to heat or cool as required, while

    the compressor load benefits from the internal heat recovery. Energy savings of up to 55%

    are predicted over comparable unitary equipment. This also results in greater control of

    the building's interior temperature by the building's occupants.

    https://en.wikipedia.org/wiki/Air_conditioner_inverterhttps://en.wikipedia.org/wiki/Inverter_compressorhttps://en.wikipedia.org/wiki/Refrigeranthttps://en.wikipedia.org/wiki/Gas_compressorhttps://en.wikipedia.org/wiki/Gas_compressorhttps://en.wikipedia.org/wiki/Refrigeranthttps://en.wikipedia.org/wiki/Inverter_compressorhttps://en.wikipedia.org/wiki/Air_conditioner_inverter

  • 8/18/2019 Dfr for Air-conditioning at Kp-4

    9/23

     

    BASICALLY, THERE ARE TWO TYPES OF VRF SYSTEMS:

    1.  AIR SOURCED VRF SYSTEM (AS INSTALLED AT CHI-IV OFFICE OF NPCL)

    2.  WATER SOURCED VRF SYSTEM

    AIR SOURCED VRF SYSTEM -

    Air Sourced VRF systems provide heating and cooling by exchanging energy with theambient air, extracting energy from the air (outside atmosphere) in the heating

    mode and rejecting energy to the air (outside atmosphere) in the cooling mode.

  • 8/18/2019 Dfr for Air-conditioning at Kp-4

    10/23

    SEVERAL VENDORS ARE PRESENT IN THE MARKET WHICH ARE PROFICIENT IN THE

    AIR SOURCED VRF TECHNOLOGY LIKE:

    1.  MITSUBISHI

    2.  LG ( VRF UNITS INSTALLED AT CHI-IV ARE LG MAKE) 

    3.  DAIKIN

    4.  TOSHIBA

    5.  CARRIER

    6.  TRANE

    OUT OF THESE, WE HAVE EARLIER RAISED OUR ENQUIRIES TO:

    1.  MITSUBISHI

    2.  LG

    3.  DAIKIN

    WATER SOURCED VRF SYSTEM -

    Water-source VRF is similar to air-source VRF on the refrigeration side. Multiple

    indoor units can be connected to a compressor module where each module houses

    a single inverter driven compressor. The primary difference is the fact that the

    compressor module absorbs and rejects heat from or to a water-source heat sink

    instead of an air-source heat sink.

    Water sourced VRF systems will provide heat recovery between modules connected

    to a common hydronic loop. System then absorb or reject heat, from or to the

    building hydronic loop.

  • 8/18/2019 Dfr for Air-conditioning at Kp-4

    11/23

     

    VENDORS PRESENT IN THE MARKET WHICH ARE PROFICIENT IN THE WATER SOURCED VRF

    TECHNOLOGY LIKE:

    1.  MITSUBISHI

    2.  DAIKIN

    3.  LG

    We have not yet raised our formal enquiries for Water Sourced VRF system but asked for

    tentative price schedule for water source VRF.

    *Water Sourced VRF are 1.5-2 times costlier than Air-Sourced VRF system.

  • 8/18/2019 Dfr for Air-conditioning at Kp-4

    12/23

    WHY VRF NOT TRADITIONAL HVAC SYSTEM?

    1. ENERGY EFFICIENCY.  VRF systems use less energy for several reasons. The system is

    designed to provide exactly the amount of cooling needed for the current conditions,

    which means it runs less frequently and at a lower capacity. The VRF system is also

    designed to capture heat from the cooling process and reuse it in other areas that may

    need heating.

    2. QUIET OPERATION. In a VRF system, the noisier condensing unit is typically outside, and

    the indoor air handlers are smaller and quieter than a traditional split system.

    3. HEAT AND COOL SIMULTANEOUSLY (ZONING). The VRF system captures residual heat

    absorbed from the air during the cooling process, and redirects that heat to other parts of

    the building that need heat.

    VRF systems have a unique ability to extract heat out of areas requiring cooling and put it

    into zones requiring heating. Recent modelling of a typical medium sized commercial office

    building indicated the requirement for simultaneous heating and cooling to be about 1-2 %of the system’s operation.

    The need for this feature increases in colder climates & may form up to 10-15% of the

    system’s  operation. To some extent, differing preferences of occupants for warmer or

    cooler workspaces can also result in a demand for simultaneous heating and cooling, which

    is normally frowned upon, but can be economically catered for with the VRF system.

    Hence, it is possible to create zones where cooling or heating is required at same time and

    no cooling or heating when there is no occupancy in a single floor.

    The VRF zoning systems by the company permit an indoor unit to be serviced while other

    indoor units within the same piping system are still in operation, and the simple controls

    networks provide diagnostic information, making maintenance simpler

    4. CONSISTENT COMFORT. The VRF system’s compressor can detect the precise

    requirements of each zone, and send the precise amount of refrigerant needed to do the

     job. As a result, each area of your space is consistently comfortable with well-controlled

    humidity and no hot or cold spots.

    5. LESS DOWNTIME. Since the VRF system is designed to run only when needed and under

    partial-load conditions, there is less wear and tear on the parts. That means fewer

    breakdowns. Also, if something goes wrong with one air handler, often the others areunaffected. That means your whole space won’t be without air conditioning all at once.

    6. REQUIRES LESS SPACE. Since the air handlers are smaller and VRF systems don’t usually

    require ducts, they don’t require as much wall and ceiling space for the equipment. That

    means you get to keep those gorgeous high ceilings in your apartment. Ductwork is limited

    or not required at all, and the two-pipe system is extremely flexible. Mitsubishi Electric VRF

  • 8/18/2019 Dfr for Air-conditioning at Kp-4

    13/23

    zoning systems require only a 3-inch opening in the exterior of a building for the refrigerant

    lines and wiring to run through, connecting the indoor units to the outdoor units.

    7. MODERN CONTROLS. For residences, you can take advantage of mobile control

    technology that lets you adjust temperature settings for each zone from your mobile

    device. For commercial settings, the VRF system’s built-in controls may allow you to skip

    purchasing expensive building management software.

    GEO-THERMAL HEAT SINK SYSTEM -

    Commercial buildings that are centrally air-conditioned use an air-cooled or water-cooled

    heat exchanger to pump out heat inside the building into the atmosphere. The atmospheric

    temperature conditions contribute to the efficiencies of the air-conditioning systems. If the

    atmospheric temperatures are higher, efficiency of the air-conditioning system is lower and

    vice versa.

    Geothermal heat sink system uses the earth as heat sink instead of outside atmosphere in

    conventional systems. The earth temperatures in most cases are much lower than theatmospheric temperatures. With the lower temperatures the efficiencies of the air-

    conditioning systems are significantly higher.

    Geothermal works because the ground beneath our feet is warmer then the outside air in

    the winter and cooler in the summer. Inserting a series of small pipes into the ground

    allows heat to be transferred to and from enclosed area. In this process heat is not created,

    it is transported therefore no fuel is burned.

    Summer Operation: The indoor heat pump takes the hot air from the office building and

    removes the heat. This leaves behind cool air to be distributed through vents as air-

    conditioning. The removed heat from the air is rejected into the earth through the ground

    loop. In this case the water is warmer leaving the office area then when it returns since

    heat is rejected into it.

    Winter Operation: The underground pipes, called a ground loop, circulate water which

    absorbs the heat from the earth and returns it to the indoor heat pump. The heat pump

    extracts the heat from the liquid then distributes it throughout as warm air. With the heat

    removed, the water is re-circulated to collect more heat from the ground. In this case the

    loop water is warmer when it comes into the enclosed area than when it goes back into the

    earth since the heat is being removed.

    There are two primary types of loop systems available for use with geo-exchange /

    geothermal systems. These are:

  • 8/18/2019 Dfr for Air-conditioning at Kp-4

    14/23

    1.  CLOSED-LOOP SYSTEMS 

    HORIZONTAL 

    This type of installation is generally most cost-effective for residential installations,

    particularly for new construction where sufficient land is available. It requires trenches at

    least four feet deep. The most common layouts either use two pipes, one buried at six feet,and the other at four feet, or two pipes placed side-by-side at five feet in the ground in a

    two-foot wide trench.

    VERTICAL 

    Large commercial buildings and schools often use vertical systems because the land area

    required for horizontal loops would be prohibitive. Vertical loops are also used where the

    soil is too shallow for trenching, and they minimize the disturbance to existing landscaping.

    For a vertical system, holes (approximately four inches in diameter) are drilled about 20

    feet apart and 100 to 400 feet deep. Into these holes go two pipes that are connected at

    the bottom with a U-bend to form a loop. The vertical loops are connected with horizontal

    pipe (i.e., manifold), placed in trenches, and connected to the heat pump in the building.

  • 8/18/2019 Dfr for Air-conditioning at Kp-4

    15/23

    2.  OPEN-LOOP SYSTEM - (SYSTEM OFFERED BY GIBBS FOR KP-4) 

    Actually system is an open loop system but due to the upstream and downstream water

    flow beneath aquifers, the system is converted in natural close loop system.

  • 8/18/2019 Dfr for Air-conditioning at Kp-4

    16/23

     

  • 8/18/2019 Dfr for Air-conditioning at Kp-4

    17/23

    Combining Two Technologies: Geothermal + VRF Zoning Systems- 

    Water-source VRF zoning systems combine the efficiency benefits of a geothermal system

    with the sophistication of VRF zoning systems. This technology takes advantage of an

    INVERTER-driven compressor, coupled with a closed geothermal loop, instead of utilizing

    air as a heat exchange medium.

  • 8/18/2019 Dfr for Air-conditioning at Kp-4

    18/23

    WATER SOURCED VRF PAIRED WITH CONVENTIONAL COOLING TOWER SYSTEM -

  • 8/18/2019 Dfr for Air-conditioning at Kp-4

    19/23

    WATER SOURCED VRF PAIRED WITH GEO-THERMAL HEAT SINK SYSTEM – 

  • 8/18/2019 Dfr for Air-conditioning at Kp-4

    20/23

    PROS & CONS OF WATER SOURCE VRF ZONING SYSTEM PAIRED WITH GEO-THERMAL SYSTEM:  

    PROS: 

    1.  Upto 15-20% Energy savings compared to traditional HVAC (Chiller & Cooling

    Tower). Energy saving as a result of lower Entering Cooling Water Temperature

    (ECWT) in the water sourced VRF since ground offers a much lower temperature

    compared to ambient environment.

    2.  System offered by M/s. GIBBS is not an actual closed loop system but converted into

    a Natural Closed loop system using upstream & downstream water flow beneath

    aquifers. Hence, does not require any make-up water upto Heat-Exchanger as

    compared to traditional HVAC (Chiller & Cooling Towers)

    3.  Flexible installation - Installation is possible in tight spaces because the two-pipe 

    design of the VRF system requires less space than ducted systems. Moreover, both

    injection field and production field are below ground. Hence, space above ground

    can be used for other purposes.

    4. 

    Application variety - Water-source VRF zoning condenser units can be connected to an array of indoor unit styles to accommodate the specific needs of the space. The

    configuration of the below-ground loop system can be customized to accommodate

    the building’s surroundings.

    5.  Clean energy source. Water-source VRF zoning systems use the clean and  

    sustainable energy stored in the earth to cool and heat buildings, a more

    environmentally friendly and efficient source of energy than non-renewable fossil

    fuels. Reduction in Carbon Footprints by 30%. The combined system can provide

    upto 10 LEED points for Green building certification.

    6.  System efficiency. The INVERTER-driven compressor varies the speed of the motor’s 

    rotation, allowing it to precisely meet each zone’s load requirement while reducingoverall power consumption. Geothermal VRF zoning systems are also able to take

    advantage of stable ground temperatures for even greater efficiencies.

    CONS: 

    1.  Earlier we were working on Air-Source VRF unit for whole Knowledge Park-IV building.

    Geo-Thermal heat exchange system cannot work with Air-Source VRF system. If we want

    to implement Geo-Thermal heat exchange system, we need move from Air-Source VRF

    system to Water Source VRF system which is major issue for us. Initial cost of water source

    VRF system approximately 2 times that of air source VRF system. Apart from this,

    installation and commissioning cost of water source VRF system is 15-20% higher as itincludes additional Piping and Instrumentation job (water circuit).

    2.  Installing a geothermal system is expensive. The major disadvantage of geothermal

    heat pumps is increased upfront initial costs, which are in average two to three times

    higher than conventional systems. This really becomes a disadvantage if the system is

    not installed properly. Thousands of heating and cooling systems are installed each year

    that do not produce the intended energy savings due to improper installation

    techniques. The costing will depend on the soil conditions, plot size, system

  • 8/18/2019 Dfr for Air-conditioning at Kp-4

    21/23

    configuration, site accessibility and the amount of digging and drilling required. Even so,

    a geothermal system will cost about 40 percent more than a traditional HVAC system.

    3.  Almost 50-60% of the total project cost involves Ground Thermal Analysis, Modeling

    and Sensitivity Analysis for the designing of primary and secondary loops. These

    processes are done by highly accredited professionals. Hence, sizing, design and

    installation require pro-expertise for the most efficient system. There are very few

    installers involved in erection and commissioning of water sourced VRF system in

    combination with Geo-thermal system with natural closed loop system.

    4.  Heavy drilling and digging is required on earth surface  which is quite a tedious

     job. However, vertical installations are typically much more expensive than

    horizontal installations because of the cost of drilling several hundred feet

    underground.

    5.  Most of the Water Source VRF units have factory installed stainless steel plate heat

    exchangers. In order to protect these heat exchangers, it is recommended to use

    closed geothermal water loops. Should open geothermal systems be used, an

    intermediate heat exchanger should be installed to isolate VRF units from

    contaminants in the water system. Open geothermal loops may contain minerals,

    biological contaminants, corrosive agents, or other substances which can cause

    scale, fouling or corrosion, that could degrade performance or shorten the life of the

    heat exchanger and unit.

    Hence, an intermediate heat exchanger will be necessary which will add up extra cost.

    6.  De-mineralized or RO water will be required as a makeup water for the primary

    loop between Water Sourced VRF unit and intermediate heat exchanger. Since, we

    are planning to construct Ion-Exchange plant for drinking water supply in the building

    with capacity 300-400 LPH. Hence, we have to increase our plant capacity which will

    again add up extra cost.

  • 8/18/2019 Dfr for Air-conditioning at Kp-4

    22/23

    7.  There will be a huge piping and instrumentation job required at both sides  (VRF outdoor units as well as Geo-thermal Exchanger side). Hence, a separatemaintenance team including a Mechanical Engineer & Fitter will be required in

    each shift as there will be every time occupancy in the building (Central ControlRoom or Load Dispatch Centre) which will again add up extra cost. (Piping &Instrumentation drawing for such a system is shown below in the diagram) 

    8.  One of the reasons to not consider Traditional HVAC system (Chiller & Cooling Tower)

    and to consider Air-Sourced VRF system was low maintenance and minimal Piping &Instrumentation (PI) job. Though there will be less maintenance required in Geo-

    Thermal system but the same is not true in case of water source VRF coupled with

    Geo-Thermal system.

    9.  There are very less references available in India for Water source VRF system

    coupled with Geo-Thermal system. Hence, operational issues or problems are not

    known.

    10. Almost 10-year payback period. This cost includes extra CAPEX*  for installing water

    source VRF + Geo-Thermal Heat Sink system. Return of Investment can be achieved

    thru OPEX.

    Extra CAPEX*

    Cost of Air Source VRF system = Rs. X  

    Cost of Water Source VRF System = Rs. 2X  

    Cost of Geothermal System = Rs. Y  

    Total cost of Water Source VRF coupled with Geo-Thermal system = Rs. (2X+Y) 

    Complete ROI calculation is also available in the next attachment.

  • 8/18/2019 Dfr for Air-conditioning at Kp-4

    23/23

    11. Of course Geo-Thermal system is an efficient system leading to energy saving but on the

    other hand Air-Source VRF system which is typically installed with an Air conditioner

    inverter which adds a DC inverter to the compressor in order to support variable motor

    speed and thus variable refrigerant flow rather than simply on/off operation. By operating

    at varying speeds, VRF units work only at the needed rate allowing for substantial energy

    savings at partial-load conditions. Heat recovery VRF technology allows individual indoor

    units to heat or cool as required, while the compressor load benefits from the internal heatrecovery. Energy savings of up to 55% are predicted over comparable unitary equipment

    in case of AIR Source VRF.

    12. Geo-Thermal system can provide upto 10 LEED points under innovation category for Green

    Building Certification. On the other hand, the Air-Sourced VRF systems use R-410A

    refrigerant, which is applicable for LEED. The combination of the more efficient refrigerant,

    variable refrigerant volume, inverter driven compressor, and DC fan and compressor motors

    provide high coefficients of performance (COP), even at low temperatures.

    13. While if we talk about only Water source VRF system and not Geo-Thermal system, we are

    totally dependent on water for primary loop between VRF unit and intermediate heat

    exchanger. If there occurs any sort of obstacle in the primary water circuit then whole Air-Conditioning system will be compromised. While, in case of Air-Source VRF there is no such

    requirement of water circuit. Each unit can be separately taken OFFLINE for maintenance

    without disturbing existing unit.

    14. If we take the reference from recent visit to ISB, Mohali :

    They have installed 3 nos. water cooled chillers each of 300 TR. At a time only 2 chillers are

    working while 3rd is a standby.

    a. Chiller 1 – 300 TR (Heat Exchange done thru Cooling Towers)

    b. Chiller 2 – 300 TR (Heat Exchange done thru Cooling Towers)

    c. Chiller 3 – 300 TR (Heat Exchange done thru Geo-Thermal Heat Sink System)

    Looking at the benefits of only Geo-Thermal system, ISB management can easily dismantle

    existing cooling towers and can sync their other 2 chillers with Geo-Thermal system but

    they have not done yet.

    Of course, M/s. GIBBS makes out a case that they were called for design, engineering,

    supply, erection & commissioning of Geo-Thermal Heat Sink system at the very later stage

    of the construction of ISB, Mohali project but the fact cannot be denied that ISB facility is

    not fully dependent on Geo-Thermal Heat sink system.

    Since, Geo-thermal heat sink system technology is new in India, ISB team doesn’t want to

    take any sort of risk.