Dewatering - An Overview

download Dewatering - An Overview

of 4

Transcript of Dewatering - An Overview

  • 7/29/2019 Dewatering - An Overview

    1/4

    BUILDING

    CONSTRUCTION

    During construction, excavations must be kept

    free of standing water. Such water may come

    from :

    -PRECIPITATION

    IT MAY COME FROM GROUND-WATER SEEPAGE

    originating from any

    of a number of sources, such as

    -surface water percolating through the Soil

    -underground streams,

    -perched water moving over impervious soilstrata

    -adjacent permanently saturated soil areas

    where the excavation extends below the water

    table.

    DEWATERING

    The most common method of dewatering is to run water by pumping as it accumulates in pits, called sumps, created at low points

    in the excavation.

    This can be done either by pumping water from the surrounding soil to depress the water table below the level of the bottom of theexcavation or by erecting a watertight barrier, such as a slurry wall, around the excavation

    Most excavations require some form of

    dewatering, or extraction of water from

    the excavation or surrounding soil.

    ATUL ANAND JHA

    TAUSEEF AHMED

    B.ARCH. III A

  • 7/29/2019 Dewatering - An Overview

    2/4

    Well points are commonly used to depress the water table. These are vertical

    sections of pipe with screened openings at the bottom that keep out soil particles

    while allowing water to enter.

    Closely spaced well points are driven into the soil around the entire perimeter of

    the excavation. These are connected to horizontal header pipes leading to pumps

    that continually draw water from the system and discharge it away from the

    building site. Once pumping has drawn down the water table in the area of the

    excavation, work can continue in the dry.

    For excavations deeper than the 20 feet (6 m) or so that cannot be drained by

    a suction pump stationed at ground level, two rings of well points may be

    required, the inner ring being driven to a deeper level than the outer ring, or

    a single ring of deep wells with submersible force pumps may have to be

    installed.

  • 7/29/2019 Dewatering - An Overview

    3/4

    In some cases, well points may not be practical:

    they may have insufficient capacity to ensure that an

    excavation remains dry;

    restrictions on the disposal of groundwater may limit

    their use;

    reliability due to power outages may be a concern; or

    lowering of the water table may have serious adverse

    effects on neighboring buildings by causingconsolidation and settling of soil under their

    foundations or by exposing untreated wood

    foundation piles, previously protected by total

    immersion in water, to decay.

    In these cases, a watertight barrier wall may be used as

    an alternative (Figure 2.26).

    Slurry walls and soil mixed walls can make excellent

    watertight barriers.

    Sheet piling can also work, but it tends to leak at the

    joints.

    Soil freezing is also possible. In this method, an array

    of vertical pipes similar to well points is used to

    continuously circulate coolant at temperatures low

    enough to freeze the soil around an excavation area,

    resulting in a temporary but reliable barrier to

    groundwater.Watertight barriers must resist the hydrostatic pressure

    of the surrounding water, which increases with depth, so

    for deeper excavations, a system of bracing or tiebacks is

    required. A watertight barrier also works only if it

    reaches into a stratum of impermeable soil such as clay.

    Otherwise, water can flow beneath the barrier and rise

    up into the excavation.

    Slurry wall and tieback construction used

    to support historic buildings around a

    deep excavation for a station of the Paris

    Metro.

  • 7/29/2019 Dewatering - An Overview

    4/4

    Installing tiebacks. (a) Drilling

    through a slurry wall for atieback. The ends of

    hundreds of completed tiebacks

    protrude from the wall.