Development of A Traffic Monitoring Program Using Emme 3 Based on A San Joaquin COG Travel Demand Model Jia Hao Wu, Ph.D., Joy Bhattacharya, P.E. and Chris Kinzel. P.E. TJKM Transportation Consultants, Pleasanton, California, USA 20 th International Emme Users’ Conference Montreal, October 18 to 20, 2006

Transcript of Development of A Traffic Monitoring Program Using Emme 3 Based on A San Joaquin COG Travel Demand...

Page 1: Development of A Traffic Monitoring Program Using Emme 3 Based on A San Joaquin COG Travel Demand Model Jia Hao Wu, Ph.D., Joy Bhattacharya, P.E. and Chris.

Development of A Traffic Monitoring Program Using Emme 3 Based on A San Joaquin COG Travel Demand Model

Jia Hao Wu, Ph.D., Joy Bhattacharya, P.E. and Chris Kinzel. P.E. TJKM Transportation Consultants, Pleasanton, California, USA

20th International Emme Users’ Conference

Montreal, October 18 to 20, 2006

Page 2: Development of A Traffic Monitoring Program Using Emme 3 Based on A San Joaquin COG Travel Demand Model Jia Hao Wu, Ph.D., Joy Bhattacharya, P.E. and Chris.

OutlineCity of Lathrop BackgroundObjectivesEmme 3 ImplementationResultsConclusions

Page 3: Development of A Traffic Monitoring Program Using Emme 3 Based on A San Joaquin COG Travel Demand Model Jia Hao Wu, Ph.D., Joy Bhattacharya, P.E. and Chris.

1.5 hours from San FranciscoPopulation: 12,500Buildout Population: 70,000Fastest Growing in CaliforniaMost Comprehensive EIRNew Development Pop: 50,000

Page 4: Development of A Traffic Monitoring Program Using Emme 3 Based on A San Joaquin COG Travel Demand Model Jia Hao Wu, Ph.D., Joy Bhattacharya, P.E. and Chris.

New DevelopmentsRiver Islands at Lathrop

11,000 residential units 17,000 new jobs

Mossdale South and West Villages 2,500 residential units27 acres services and 1 million square feet of retail/office

Central Lathrop Specific Plan6,800 residential units4.5 million square feet of offices

We developed traffic models for all of these new developments for environment impact studies.

Page 5: Development of A Traffic Monitoring Program Using Emme 3 Based on A San Joaquin COG Travel Demand Model Jia Hao Wu, Ph.D., Joy Bhattacharya, P.E. and Chris.

Traffic Monitoring ProgramDetermine the circulation needs for traffic circulation improvements Satisfy the conditions of approval for new developments Identify any intersection level of servicesDetermine mitigation measuresUpdate on an annual basisYears: 2006,2008,2010 and 2012

Page 6: Development of A Traffic Monitoring Program Using Emme 3 Based on A San Joaquin COG Travel Demand Model Jia Hao Wu, Ph.D., Joy Bhattacharya, P.E. and Chris.

Level of ServiceLevel of Service (LOS) is a qualitative index of the performance of an intersection in the transportation system  LOS is based on 2000 Highway Capacity Manual published by the Transportation Research Board

Page 7: Development of A Traffic Monitoring Program Using Emme 3 Based on A San Joaquin COG Travel Demand Model Jia Hao Wu, Ph.D., Joy Bhattacharya, P.E. and Chris.

We developed traffic models for all of these new developments for environment impact studies

Three Highway Interchanges

Page 8: Development of A Traffic Monitoring Program Using Emme 3 Based on A San Joaquin COG Travel Demand Model Jia Hao Wu, Ph.D., Joy Bhattacharya, P.E. and Chris.

Intersection Lane Geometry – Existing (Year 2006) Conditions

Page 9: Development of A Traffic Monitoring Program Using Emme 3 Based on A San Joaquin COG Travel Demand Model Jia Hao Wu, Ph.D., Joy Bhattacharya, P.E. and Chris.

Turn Volumes AM and PM – Existing (Year 2006) Conditions

Page 10: Development of A Traffic Monitoring Program Using Emme 3 Based on A San Joaquin COG Travel Demand Model Jia Hao Wu, Ph.D., Joy Bhattacharya, P.E. and Chris.

Level of Service – Existing (Year 2006) Conditions

Page 11: Development of A Traffic Monitoring Program Using Emme 3 Based on A San Joaquin COG Travel Demand Model Jia Hao Wu, Ph.D., Joy Bhattacharya, P.E. and Chris.

Demand Forecasting ProcessSan Joaquin Council Governments Travel Demand Forecasting Model was used in CUBE/TP+Emme 3 was used for a detailed analysis, since it was used for the model calibration at the turning movement levelTurn counts at the study intersections were entered into Emme 3 for the model calibrationThe difference method was used Road network and land use data were updated

Page 12: Development of A Traffic Monitoring Program Using Emme 3 Based on A San Joaquin COG Travel Demand Model Jia Hao Wu, Ph.D., Joy Bhattacharya, P.E. and Chris.

City of Lathrop General Plan as A Background

Page 13: Development of A Traffic Monitoring Program Using Emme 3 Based on A San Joaquin COG Travel Demand Model Jia Hao Wu, Ph.D., Joy Bhattacharya, P.E. and Chris.

River Island Development Plan

Page 14: Development of A Traffic Monitoring Program Using Emme 3 Based on A San Joaquin COG Travel Demand Model Jia Hao Wu, Ph.D., Joy Bhattacharya, P.E. and Chris.

Dwelling Units Employments

Page 15: Development of A Traffic Monitoring Program Using Emme 3 Based on A San Joaquin COG Travel Demand Model Jia Hao Wu, Ph.D., Joy Bhattacharya, P.E. and Chris.

Year 2012 Peak Hour Turning Movement Volumes

Page 16: Development of A Traffic Monitoring Program Using Emme 3 Based on A San Joaquin COG Travel Demand Model Jia Hao Wu, Ph.D., Joy Bhattacharya, P.E. and Chris.

Lane Geometry

Page 17: Development of A Traffic Monitoring Program Using Emme 3 Based on A San Joaquin COG Travel Demand Model Jia Hao Wu, Ph.D., Joy Bhattacharya, P.E. and Chris.

Recommended Roadway Phasing

Page 18: Development of A Traffic Monitoring Program Using Emme 3 Based on A San Joaquin COG Travel Demand Model Jia Hao Wu, Ph.D., Joy Bhattacharya, P.E. and Chris.

RecommendationsRecommendations for Existing Conditions Recommendations for 2008 (Two-year look) Recommendations for 2010 (Four-year look)Recommendations for 2012 (Six-year look)

Page 19: Development of A Traffic Monitoring Program Using Emme 3 Based on A San Joaquin COG Travel Demand Model Jia Hao Wu, Ph.D., Joy Bhattacharya, P.E. and Chris.

Conclusions

Emme 3 was used for the monitoring programs Worked with SynchroA wish list for display results in Emme 3 with many symbols and LOS