Develop Pavement Design Catalog - vaasphalt · 1. VDOT - Reformat draft catalog options showing...
Transcript of Develop Pavement Design Catalog - vaasphalt · 1. VDOT - Reformat draft catalog options showing...
VDOT Pavement Policy Task Group TOPICS/PURPOSE
Develop VDOT Alternate Bid Policy
• When to Include
• Comparable Pavement Designs
• Use of Price Adjustment/Escalation Clauses
Develop Pavement Design Catalog
• New Pavements
• Rehabilitation Alternate Bid Designs
Dispute Resolution Panel
VDOT Pavement Policy Task Group Members
VDOT
• Garrett Moore, Chief Engineer
• Mohammad Mirshahi, Deputy Chief Engineer
• Jose Gomez, Director VCTIR
• Andy Babish, State Materials Engineer
Industry
• Richard Schreck, Virginia Asphalt Association
• Bob Long, VA Chapter American Concrete Pavement Assn
• Jeff Southard, VA Transportation Construction Alliance
• Ed Dalrymple, Old Dominion Highway Contractors Assn
FHWA
• Tom Jennings, Director of Project Delivery, VA Division
VDOT Pavement Policy Task Group March 21, 2014 Meeting
Bob Long pitched AC Index “unfair” to concrete
industry and should be eliminated. Supporting
documents supplied were:
• “Development and Use of Price Adjustment
Contract Provisions”, TRB AASHTO Study
• FHWA Technical Advisory “Price Indexing in
Transportation Construction Contracts”
• NCHRP Report 703, “Guide for Pavement-Type
Selection”
• ACPA’s Perspectives document, “Material Price
Adjustment Clauses”
VDOT Pavement Policy Task Group March 21, 2014 Meeting
Decision and debate on inclusion of Price
Adjustment put on “back burner” by Chief
Engineer until greenfield design catalog and
rehabilitation catalog developed.
Discussion/rebuttal from Asphalt Industry
postponed as well.
Moved forward with presentation of draft
greenfield pavement design catalog developed
by Materials Division.
Rehabilitation alternative designs will be
addressed after green field.
Five Sections
Section A: Asphalt with Agg Base
Section B: Asphalt with CTA Base
Section C: Joint Plain Concrete with Agg Base
Section D: Jointed Plain Concrete with CTA Base
Section E: Composite Pavement with CTA Base
(Asphalt on Continuously Reinforced
Concrete)
VDOT Pavement Design Catalog DRAFT
Three Traffic Levels
• 500-750 AADTT (6”)
• 750-1000 AADTT (6.5”)
• 1000-1250 AADTT (7.0)
Five Subgrade Strengths
• Impacts Asphalt Base
Thickness
• Middle thickness show
Primary Road Designs
• Reduce Asphalt Base 1”
Section A: Asphalt with Agg Base
AADTT = Annual Average Daily Truck Traffic in Design Lane
2” SMA 12.5 2” SMA 19.0
6” - 7” BM 25.0
8.0” Aggregate Base 21B
12.0” Open Graded Stone Base Layer
SUBGRADE
Geotextile Fabric
10” - 11” Asphalt
One Traffic Level
• 1250 – 2000 AADTT
• Section A maxed at 1250
Five Subgrade Strengths • Impacts Asphalt Base
Thickness
• Middle thickness show
Primary Road Designs • Reduce BM 25.0 1”
Section B: Asphalt with CTA Base
AADTT = Annual Average Daily Truck Traffic in Design Lane
2” SMA 12.5
2” SMA 19.0
7” BM 25.0
6.0” CTA
SUBGRADE
2” OGDL
13” Asphalt
Three Traffic Levels
• 500-750 AADTT (9.5”)
• 750-1000 AADTT (10.0”)
• 1000-1250 AADTT (10.5”)
Three Subgrade Strengths
• Impacts JPCP Thickness
• Middle thickness show
Shoulder Design
• Tied PCC on Interstate
• Full-depth asphalt on Primary
• JPCP +.5” on Primary designs due asphalt shoulders
Section C: JPCP with Agg Base
AADTT = Annual Average Daily Truck Traffic in Design Lane
12.0” Open Graded Stone Base Layer
9.5 – 10.5” JPCP
8.0” Aggregate Base 21B
SUBGRADE
Geotextile Fabric
Three Traffic Level
• 1250 – 1500 AADTT (11.0”)
• 1500 – 1750 AADTT (11.0”*)
• 1500 – 2000 AADTT (11.5”)
Three Subgrade Strengths
• Impacts JPCP Thickness
• Middle thickness show
Shoulder Design
• Tied PCC on Interstate
• Full-depth asphalt on Primary
• JPCP + .5” on Primary designs due asphalt shoulders
Section D: JPCP with CTA Base
AADTT = Annual Average Daily Truck Traffic in Design Lane
6.0” CTA
SUBGRADE
2” OGDL
11.0” – 11.5” JPCP
Five Traffic Levels
• 200-2500 AADTT (9”)
• 2500-3000 AADTT (10”)
• 3000-4000 AADTT (10”)
• 4000-5000 AADTT (11”)
• 5000-6000 AADTT (11”)
Three Subgrade Strengths
• Impacts CRCP Thickness
• Middle thickness show
Primary Road Designs
• Reduce Asphalt Base 1”
Section E: Composite with CTA
Base
AADTT = Annual Average Daily Truck Traffic in Design Lane
6.0” CTA
SUBGRADE
2” OGDL
9.0” – 11.0” CRCP
2” SMA 12.5 2” SMA 19.0
VDOT Pavement Design Catalog DRAFT
AADTT HMA/AGG Subbase
HMA/CTA Subbase
JPCP/AGG Subbase
JPCP/CTA Subbase
CRCP/SMAComposite
500-750 10” - 9.5” - -
750-1000 10.5” - 10” - -
1000-1250 11” - 10.5” - -
1250-1500 - 11” + 2” - 11” -
1500-1750 - 11” + 2” - 11” -
1750-2000 - 11” + 2” - 11.5” -
2000-2500 - - - - 9” + 4”
2500-3000 - - - - 10” + 4”
3000-4000 - - - - 10” + 4”
4000-5000 - - - - 11” + 4”
5000-6000 - - - - 11” + 4”
NO Asphalt Pavement options proposed above 2000 AADTT!
2” SMA 12.5 2” SMA 19.0
6” - 7” BM 25.0
8.0” Aggregate Base 21B
12.0” Open Graded Stone Base Layer
SUBGRADE
Geotextile Fabric
9.5 – 10.5” JPCP
8.0” Aggregate Base 21B
SUBGRADE
Geotextile Fabric
Section A vs. Section C
12.0” Open Graded Stone Base Layer
Section B vs. Section D
7” BM 25.0
6.0” CTA
SUBGRADE
2” OGDL
2” SMA 12.5 2” SMA 19.0
6.0” CTA
SUBGRADE
2” OGDL
11.0” – 11.5” JPCP
13” Asphalt
Section E vs. ?
6.0” CTA
SUBGRADE
2” OGDL
9.0” – 11.0” CRCP
2” SMA 12.5 2” SMA 19.0
NO Asphalt Pavement options proposed above 2000 AADTT!
SUBGRADE
VDOT Pavement Policy Task Group Post Meeting Notes – General Remarks
“Rehab type projects are brunt of VDOT work today
and for some time to come in the future.”
“VDOT as an Agency cannot afford the remove and
replace option for our existing pavements.”
“For major rehab of our pavements we need
flexibility and options to balance with funding.”
“We may consider a composite option if indeed we
get to a remove/replace option as the best solution
for a project.”
“VDOT wants economical solutions but comfortable
with some conservatism…no arguing over and inch
of material.”
VDOT Pavement Policy Task Group Post Meeting Notes – General Remarks
“The unit of measure issue (tons of HMA vs. CY of
concrete is resolved)….Resolution: HMA = tons,
HCC = CY.”
“Commodity price adjustment is unresolved at this
time and was tabled for now and will be addressed
toward end of process after we have worked
through some of the other issues such as catalog
designs.”
“Intent is to gather a bigger picture of the impacts of
this specific issue on the global context of the final
product of this process..”
Task Group Action Items
1. VDOT - Reformat draft catalog options showing
comparable sections on one sheet for ease of
comparison by Tuesday, April 1.
• Review/ensure traffic criteria consistent for comparable
options.
• Provide reformatted draft catalog to industry for comment.
2. Each industry to provide comments regarding the
proposed catalog sections A-D.
3. Each industry to provide a composite alternative
to proposed catalog section E.
4. Each industry to provide a proposed full Flexible
and/or Rigid Pavement design for Section E
conditions (i.e. AADTT and Subgrade RM)
ACPA Virginia 97% Button and
“Balanced Paving Program” Pitch