Determinants of Completion of Government Funded Urban ...€¦ · 20 Determinants of Completion of...
Transcript of Determinants of Completion of Government Funded Urban ...€¦ · 20 Determinants of Completion of...
20
Determinants of Completion of Government Funded
Urban Construction Projects In Nairobi City County,
Kenya
Hawa Ibrahim HASSAN1 & Dr. Wario GUYO
2
1M.Sc Scholar Project Management, Jomo Kenyatta University of Agriculture and Technology,
Kenya 2Lecturer, Jomo Kenyatta University of Agriculture and Technology, Kenya
`
ABSTRACT
In Kenya like other countries construction industry is one of major industry contributing significantly
to the socio-economic development growth. The general objective of this study was to examine the
determinants influencing project completion of government funded projects in Nairobi, Kenya. The
specific objectives of this study were to examine; project cost; project procurement procedures;
project Kenya designs and specifications and project contractors‟ experience on project completion of
the government funded urban projects. The study adopted descriptive survey and study population and
sample of 68 was considered for this study. A census sampling technique method was used and data
collected through the use of questionnaires. On the other hand, secondary data was obtained from
published documents such as journals, periodicals, magazines and reports to supplement the primary
data. The study variables were regressed at 5% level of significance and 95% confidence level to
determine strength and direction of the their relationship. The analysis showed that project
procurement procedures had the strongest positive (Pearson correlation coefficient =.703) influence
on project completion of government funded projects. In addition, project design specifications,
project contractors experience and project cost are positively correlated to project completion of
government funded urban projects (Pearson correlation coefficient =.644, .493 and .532) The study
recommends that that training on project contractors experience is crucial for project completion of
government funded urban construction projects. There is need to enhance project design specification
and project procurement procedures through the tendering systems, and monitoring and evaluation to
reduce the project cost especially on the material cost, labour cost, equipment cost, control cost
overruns and deficiencies on cost estimates on implementation of projects to enhance performance of
the projects. Additionally, very little has been undertaken to explore the determinants studied on
completion of government urban funded projects thus the researcher call for further studies to be
undertaken on other factors and areas also in Kenya for generalization of the findings of this study.
Keywords: project procurement, urban funded projects, project contractors experience
INTRODUCTION
Construction has become an important player in the economy of many countries, especially developed
countries. As mentioned by Olawale (2010), this industry contributes to the GDP and employment
rate of many nations and for this reason it is considered vital for the economic development of any
nation. The role the construction industry plays in socio-economic development is significant. It
provides the basis upon which other sectors can grow by constructing the physical facilities required
for the production and distribution of goods and services. The construction industry has a significant
multiplier effect on the economy as a whole (Morris, 2008).
Delays and cost overruns in construction sector investments can raise the capital-output ratio in the
sector and elsewhere bringing down the efficacy of investments (Morris, 2008). Thus, successful
management of processes employed in acquisition of these assets is to a large extent, determined by
the amount of resources expended, time taken and quality when compared to similar projects.
International Journal of Innovative Development & Policy Studies 5(1):20-42, Jan.-Mar., 2017
© SEAHI PUBLICATIONS, 2017 www.seahipaj.org ISSN: 2354-2926
21
Infrastructure includes the capital required to produce economic services from utilities (like
electricity, telecommunication, and water) and transport (roads, bridges, seaport, and airports) and is
central to promoting economic activity (Chan, Scott & Chan, 2004). Individuals, private firms or
public entities are continually engaging in acquisition of physical assets in various forms such as,
residential, commercial buildings, hospital, schools/institutions, and development infrastructure like
water, roads, electricity and telecommunication. These assets represent major capital investment
motivated by market demands or perceived needs. To remain competitive in profit or non-profit
engagements, these entities focus on processes and procedures that offer value and competitive
advantage. Understanding the customer needs and appropriately deploying the available resources in
meeting customer expectations offer competitive edge over competitors in product and service
provision. Thus, efficient and effective resource management through appropriate use of tools and
techniques in asset acquisition is critical. Customers are demanding for better quality product through
efficient and timely deliveries at low price. It is therefore important, that time, cost, and quality of
constructed facilities are efficiently managed in the entire project life cycle for effective service or
product delivery.
Lin-lin et al., (2014) conducted a study on understanding of government funded projects in China's
infrastructure and construction projects. They established that the development of public projects
practices in China remains relatively slow despite the urgent need to promote this mechanism for
solving socio-economic and environmental disputes in PIC projects. Thus, a four-step strategic plan is
suggested to be established to overcome main barriers for the implementation of public participation
and promote its development in China.
Ektewan and Ogunlana (2006) did a study on public hearings in Thailand's infrastructure projects.
They found that the projects had moderate to low effectiveness primarily because the participation
and management performance aspects did not meet the participants' expectations. The relationships of
evaluation and satisfaction indices were examined. The hearing participants focus both on the process
and outcome of hearings
In Kenya like other countries construction industry is one of major industry contributing significantly
to the socio-economic development growth. Achieving project completion on time, within budget, at
specified quality standards, and most importantly without unprecedented cost escalations is major
criterion of success of project. Generally, a project is considered successful if the project is completed
within a stated cost or budget and time. Although the government of Kenya sets aside huge sums of
money to be spent in construction sector, the industry is facing a lot of challenges such as the
expenditure exceeding the budget, delay to complete the project in time, the building defects and
over-reliance on foreign workers (RoK,2012).
The construction infrastructure has been given the highest priority to ensure that the main projects
under the economic pillar are implemented, for example according to the Ministry of Roads Service
Charter (2008), there is a need for improvement of roads to a motorable condition because the road
transport (mode of transport) carries about 80% of all cargoes and passengers in the country. Due to
the importance of roads in socio-economic development of the country, the government has in the
recent past steadily increased budget allocation to the road sub-sector. However, road projects in
Kenya have been facing various challenges, which include delay in completion, cost overruns,
demolition of residential and businesses houses and abortive works (Maina, 2013).
Statement of the Problem
The construction industry in Kenya is plays a very major role in the country„s economic development
through its contribution to gross domestic product (GDP), gross domestic capital formation (GDCF),
creation of employment and production of capital facilities and assets required for production in other
sectors, as creating demand for their products (UNCHS, 2006). According to Ahmed et al., (2012), the
urban construction project is bound to fail due to slow rate in completion. This according to UNCHS,
(2006), can result to losses of over 19.82%. Construction sector is purely a project based work and in
management of project, the most critical thing is in time completion.
The delays in project completion are a common problem in the construction industry not only with an
immeasurable cost to society but also with debilitating effects on the contracting parties. The concept
of delay in the substantial completion of construction projects is a global phenomenon. For instance,
while evaluating the progress and reports of 28 highway projects constructed during the period 1996-
1999 in Jordan, Battaineh (2006) observed that the average ratio of actual completion time to the
Hassan & Guyo…..Int. J. Innovative Development & Policy Studies 5(1):20-42, 2016
Ok
22
planned contract duration is 160.5% for road works. Seboru (2006), further citing other scholars also
states that the time frame for major road projects worldwide to reach construction start stage have
been observed to range from 10-30 years.Similarly, a study by United Nations Commission for Trade
and Development (UNCTAD), (2001) on African construction industry‟s turmoils and their
implications for New Partnership for Africa‟s Development (NEPAD) identified costly project delays
as a major problem and identifies poor project time, quality and cost performance as a major issue.
There is, therefore, a need to address the unpredictability of the successful completion of construction
projects in terms of delivery time, cost and to the standard of quality expected. While several studies
(Musa, 2009: Karimi, 2008;Tulakhaba 2008, Mwandali, 2006) have been done focusing on different
aspects of project completions and further appreciating the crisis in every project in terms of
completion, all empirical evidences are in short of the actual factors that influences the completion
itself. Hence this study seeks to investigate the determinants of completion of government funded
urban construction projects in Nairobi City County, Kenya.
Objectives of the Study
The general objective of the study was to establish the determinants influencing completion of
government funded urban construction projects in Nairobi City County, Kenya.
The specific objectives of the study were to;
i. Establish the influence of project cost on completion of government funded urban
construction projects in Nairobi City County, Kenya.
ii. Assess the influence of project design specifications on completion of government funded
urban construction projects in Nairobi City County, Kenya.
iii. Determine the influence of project procurement procedures on completion of government
funded urban construction projects in Nairobi City County, Kenya.
iv. Establish the project contractors experience on completion of government funded urban
construction projects in Nairobi City County, Kenya.
Research Questions
The study sought to answer the following questions;
i. How does project cost affect completion of government funded urban construction projects in
Nairobi City County, Kenya?
ii. Do project design specifications affect completion of government funded urban construction
projects in Nairobi City County, Kenya?
iii. To what extent does project procurement procedures affect completion of government funded
urban construction projects in Nairobi City County, Kenya?
iv. Dow does project contractors experience on completion of government funded urban
construction projects in Nairobi City County, Kenya?
LITERATURE REVIEW Theoretical Review
The Study will be guided by the theory of constraints, complexity theory, knowledge based theory and
resource based theory.
Knowledge-based Theory
Knowledge-based Theory of Project Management states that there is no explicit theory of project
management and as a result there is a general theory to underpin the discipline and is found in theories
of management, planning, control and projects (Koskela & Ballard, 2002). There is „embryonic‟
theory contained in literature, particularly his books (Turner, 2006). In response, it is noted that
explicit theory is lacking (Sauer & Reich, 2007). Knowledge-based project management is the
systematic and optimal arrangement and coordination of knowledge and knowledge configurations
over a period of time to achieve specific objectives within certain constraints. This includes but not
limited to include but not limited to project cost management, project risk management, and project
integration management (Onions, 2007). The above theory instigated the first research question; To
what extent does project cost affect completion of government funded urban construction projects in
Kenya?
Hassan & Guyo…..Int. J. Innovative Development & Policy Studies 5(1):20-42, 2016
Ok
23
Complexity Theory
The second theory is the Complexity Theory. A prominent author in the field of complexity is Terry
Williams who shares the view of other scholars on complexity but extends it by one additional
dimension of cost estimates. In addition to the two components of complexity, vis-à-vis the number of
factors and the interdependency of these factors, he introduces the third factor which is uncertainty.
Since uncertainty adds to the complexity of a project, cost estimates therefore can be viewed as a
constituent dimension of project complexity that can be as a result of various factors (Williams,
2008The above theory instigated the second research question; Does project design specifications
affect completion of government funded urban construction projects in Kenya?
Resource Based Theory
Resource-based theory has been developed to understand how organizations achieve sustainable
competitive advantages (Barney, 1986). The theory focuses on the idea of costly-to-copy attributes of
the firm as sources of business returns and the means to achieve superior performance and
competitive advantage (Conner, 1991; Hamel & Prahalad, 1996). One of the objectives of the theory
is to help managers to appreciate why competences can be perceived as a firms‟ most valuable asset
and, at the same time, to understand how those assets can be used to improve business performance. A
resource-based view of the firm accepts that attributes related to past experiences, organizational
culture and competences are critical for the success of the firm (Hamel and Prahalad, 1996). The core
premise of the resource-based view is that organizational resources and capabilities can vary
significantly across firms, and that these differences can be stable (Barney, 1986). The above theory
instigated the third research question; How does project procurement procedures affect completion of
government funded urban construction projects in Kenya?
Theory of Constraints
Goldratt Eliyah (1984) started the Theory of Constraints (TOC), and based this management theory
that every system has at least one constraint limiting it from getting more of what it strives for. If this
were not true, then the system would produce infinite output. These constraints determine the output
of a system whether they are acknowledged or not. Therefore, it is in a manager's best interest to
identify and reduce the system constraints within the organization. The TOC is both descriptive and
prescriptive in nature; it not only describes the cause of system constraints, but also provides guidance
on how to resolve them. This theory refers to systems in organizations as chains. The above theory
instigated the fourth research question: To what extent does project contractor‟s experience affect
completion of government funded urban construction projects in Kenya?
Hassan & Guyo…..Int. J. Innovative Development & Policy Studies 5(1):20-42, 2016
Ok
24
Conceptual Framework
In the study, the conceptual framework will look at the determinants influencing completion of
government funded urban construction projects in Kenya. The conceptual framework for the study is
shown in figure 1;
Independent Variables Dependent Variable
Figure 1: Conceptual Framework
Project Completion In Government
Funded Urban Construction
Projects
Finish in time
Within Budget
As per specifications
Sustainable
Project Cost
Investment cost
Material cost
Equipment cost
Labour cost
Project Design Specifications
Design information
Use of computer aided designs
Revision of designs
Timely issuance of designs
Quality assurance
Project Procurement Procedures
Bidding documents
Procurement drawings
Approval of procurement stages
Tendering systems
Procurement standardization
Project Contractors’ Experience
Knowledge & cognitive skills
Technical skills
Management skills
Training
Hassan & Guyo…..Int. J. Innovative Development & Policy Studies 5(1):20-42, 2016
Ok
25
RESEARCH METHODOLOGY The study was descriptive in nature as it is deemed appropriate because it involved use of written
questionnaires administered to respondents. Yin (2003) recommends descriptive design as it allows
the researcher to describe, record, analyze and report conditions that exit or existed. Since this study
sought to establish the determinants influencing project completion in government funded urban
construction projects in Kenya, descriptive research design was the best design.
The target population comprised of the personnel implementing the government funded urban
construction projects in Nairobi area.
According to the records available in Nairobi county Council (2014), the major construction projects
in the last 10 years implemented in Nairobi area can be divided into roads, housing and water projects.
To get in depth analysis for the study, the research used the project team who comprised of client of
the project, work contractor, design consultant and project manager for each project as unit of
analysis. Since the unit of analysis in each project is 4, the total study population was 17 x 4 = 68. The
major construction projects in the last 10 years in the categories were as follows;
Sample and Sampling Technique
The sample of the study was 17 x 4 = 68. According to NCC (2014), there are 17 projects that are
being implemented. In every project, there will be 4 members of project team that is client of the
project, work contractor, design consultant and project manager. The sample size is manageable and
small enough for data collection, therefore study will adopt census sampling technique. It is also
supported by Neuman (2006) who argue that taking a census of the population is applicable if it
provides enough information and sufficient for the study. Census sampling technique is procedure of
gathering information about the entire population if it is small and reasonable and manageable
(Babbie, 2009).
Data collection Method
The study will collect both primary and secondary data during the study. Primary data will be
collected using questionnaires to be given to the project teams (clients, contactors, project managers
and design consultants).These respondents will be specifically targeted for their ability to provide
pertinent information to the study. The questionnaire will contain both structured and unstructured
questions. This is because of their simplicity in the administration and scoring of items as well as data
analysis (Babbie, 2009). From the data collected, out of the 68 questionnaires administered, 41
questionnaires were fully completed and returned making a response percent of 60.29%. Secondary data was be gathered from existing credible and recognized source. The secondary data
will comprise of materials that are desirable, current, accurate, sufficient and relevant and will be
collected from library text books, internet and magazines and personnel file in the projects.
Pilot Study
A pilot study was undertaken on at least 7 respondents to test the reliability and validity of the
questionnaire. Reliability is the extents to which a research instrument yields findings that are
consistent each time it is administered to same subjects (Mugenda and Mugenda, 2003).The
measurement of reliability provides consistency in the measurement variables(Kumar,2000)). Internal
consistency reliability is the most commonly used psychometric measure assessing survey instruments
and scales (Zhang, 2000 The Cronbach‟s alpha results ranged between 0. 709 and 0.778 and
therefore the construct were acceptable.
Data Analysis and Presentation
Quantitative data will be analyzed by employing descriptive statistics and inferential analysis using
statistical package for social science (SPSS) version 22. This technique gives simple summaries about
the sample data and present quantitative descriptions in a manageable form, (Orodho, 2003). Together
with simple graphics analysis, descriptive statistics form the basis of virtually every quantitative
analysis to data, (Kothari, 2005).
The researcher further adopted multiple regression model at 5% level of significance to establish the
strength and direction of the relationship between the independent variables (project cost, project
design specifications, project procurement procedures and project contractors‟ experience) and the
dependent variable (Completion of government funded urban construction projects). The project
completion of government funded urban construction projects was regressed against four variables
Hassan & Guyo…..Int. J. Innovative Development & Policy Studies 5(1):20-42, 2016
Ok
26
namely project cost, project design specifications, project procurement procedures and project
contractors‟ experience. The equation was expressed as follows:
Y = β0+ β1X1+ β2X2+ β3X3+ β4X4 + ε,
Where;
Y= Completion of government funded urban construction projects, β0= constant (coefficient of
intercept),
X1= Project cost; X2= Project design specifications; X3= Project procurement procedures;
X4= Project contractors‟ experience; ε = error term; β1…β4= regression coefficient of four variables.
The findings were also presented using tables, charts and graphs for further analysis and to facilitate
comparison. This generated quantitative reports through tabulations, percentages, and measure of
central tendency. Descriptive statistics such as measures of central tendency and dispersion along with
percentages were used to organize and summarize numerical data whose results are presented in
tables, pie charts, column and bar graphs for easy interpretation of the findings.
FINDINGS AND DISCUSSIONS Table 1: Pearson Correlations on determinants of project completion in government funded urban
construction projects in Kenya
Dimensions Project
contractors
experience
Project design
specifications
Project procurement
procedure
Project
cost
Project
contractors
experience
1 .722** .333** .453**
Project design
specifications
- 1 .676** .564**
Project
procurement
procedure
- - 1 .654**
Project cost - - - 1
* Correlation is significant at the 0.05 level (2-tailed)
Project Contractors Experience
Project Contractors Experience Measure On Project Success
The research sought out to establish whether the project contractors experience influence project
success of the government funded urban construction projects in Kenya. The findings as indicated in
Figure 2, a simple majority (58.54%) of the respondents agreed that project contractors experience
influence project completion in government funded urban construction projects whereas 41.46%
posited that were of contrary opinion. This implies that project contractors experience is an important
factor which influence project completion in government funded urban construction project. The
findings of the study are in agreement with literature review by Manchweka (2006) who observed that
project contractors experience plays an important role on completion of urban projects in the
developing countries. Thus lack of contractors experience affected completion of projects in Nairobi
County.
Figure 2: Project Contractors Experience Measure A Project Success
Contractors Knowledge and Cognitive Skills On Project Completion
The study sought out to establish whether the project contractors skills could enhance completion of
government funded urban construction projects in the study area. The findings as indicated in Figure
Hassan & Guyo…..Int. J. Innovative Development & Policy Studies 5(1):20-42, 2016
Ok
27
3, a simple majority (63.41%) of the respondents agreed that project contractors experience influence
project completion in government funded urban construction projects whereas 36.58% posited that
were of contrary opinion. This reveals that project contractor‟s skill is an important factor which
influence project completion in government funded urban construction project in Nairobi county.
Lack of contractors knowledge and cognitive skills in many projects established within the county
hinder the decision making and it is of crucial importance that the project organization and project
management are meticulously set up and operated in ways that minimize the risk of cost estimates.
The findings of the study are in line with Flyvbjerg et al, (2008) who observed that many projects fail
to be completed in time due lack of enough skills from the contractors. Thus lack of contractors‟
skills prolonged completion of urban construction projects in Nairobi County.
Figure 3: Contractors Knowledge and Cognitive Skills On Project Completion
Contractors Technical Skills On Project Completion
The study sought out to find out whether the project contractor‟s technical skills influence project
completion of the government funded urban construction projects in Kenya. The findings as indicated
in Figure 3 a simple majority (73.17%) of the respondents agreed that project contractors technical
skills influence project completion in government funded urban construction projects whereas 26.83%
of the respondents were of contrary opinion. It can be deduced that project contractor‟s technical
skills enhance project completion in government funded urban construction projects in the study area.
The contractors responsible for the projects do not have adequate technical skills thus affecting
project completion. The findings of the study corroborates with literature review by Chan &
Kumararswamy (2007) who observed that may government funded projects fail to be completed in
time and within budget as a result of lack of adequate technical skills in the creation of long
implementation phases.
Figure 4: Contractors Technical Skills On Project Completion Continuous Training On Projection Completion
The study sought out to establish whether the project contractors received continuous training as they
implemented various project in the study area. The study results as indicated in Figure 5, majority
(78.08%) of the respondents disagreed that they were receiving continuous training as they
Hassan & Guyo…..Int. J. Innovative Development & Policy Studies 5(1):20-42, 2016
Ok
28
implemented the projects whereas 21.92% of the respondents were of contrary opinion. It can be
deduced from the study findings that project contractors did not receive continuous training thus it
hindered project completion of government funded projects in the study area. Continuous training
especially on project management and new technology was not available hindering effective
completion of government funded urban construction projects. The findings of the study are in
agreement with the findings of Karimi (2008) who observed that continuous training especially on
adequate planning at the early stages of a project is crucial for minimizing delays and cost overruns.
Variations in designs and contract documents usually lead to a change in contract price or contract
schedule thus affecting project completion.
Figure 5: Contractors Technical Skills On Project Completion
Cost Escalations On Project Completion
The research sought out to establish whether due to lack of the project contractor‟s experience led to
project cost escalations therefore hindering project completion of government funded urban
constructions projects in the study area. The findings as indicated in Figure 6, a simple majority
(53.66%) of the respondents agreed that lack of the project contractor‟s experience led to project cost
escalations therefore hindering project completion of government funded urban constructions projects
in the study area whereas 46.34% of the respondents were of contrary opinion. This implies that
project contractors experience on project costing influenced completion of government funded
projects in the study area. Cost escalations resulted from inadequate experience in many of the
government funded projects. He findings of the study are in tandem with literature review by Muller
& Jugdev (2012) who states that cost escalations are common in projects when contractors do not
enough experience in the construction process.
Figure 6: Project Cost Escalations On Project Completion Project Design Specifications
Project Design On Project Completion
The research sought out to establish whether project design influenced project completion of
government funded urban constructions projects in the study area. The findings as indicated in Table
2, majority (78.05%) of the respondents agreed Project design influenced project completion of
government funded urban constructions projects in the study area whereas 21.95% of the respondents
were of contrary opinion. This implies that project design has an effect on the completion of
government funded projects in the study area. Project designs adversely impact on project completion
Hassan & Guyo…..Int. J. Innovative Development & Policy Studies 5(1):20-42, 2016
Ok
29
of the established projects in the study. The findings of the study are in agreement with literature
review by Aiyetan et al (2008) who observed that project completion is dependent on the performance
of the design team. The designers are the key players in the construction industry whose services are
needed from the conception stage of the project to its completion. The performance of the designers is
therefore important because any decision made at the inception of the project will affect project
completion.
Table 2: Project Design on Project Completion
Opinion Frequency Percentage
Yes 32 78.05
No 9 21.95
Total 41 100
Use Of Computer Aided Sign On Project Completion
The research sought out to establish whether use of computer aided sign influenced project
completion of government funded urban constructions projects in the study area. The findings as
indicated in Table 3, a simple majority (73.17%) of the respondents agreed use of computer aided sign
influenced project completion of government funded urban constructions projects in the study area
whereas 26.83% of the respondents were of contrary opinion. This can be deduced that use of
computer aided sign influenced project completion of government funded urban constructions projects
in the study area. Lack of technology especially on the usage of computer aided design adversely
impact on project completion of the established projects in the study. The findings of the study are in
agreement with literature review by Aiyetan et al (2008) who observed that project completion is
dependent on the usage of computer aided design to a great extent. The designers are the key players
in the construction industry whose services are needed from the conception stage of the project to its
completion.
Table 3: Use of computer aided sign on project completion
Opinion Frequency Percentage
Used 30 73.17
Not used 11 26.83
Total 41 100
Revision Of Designs On Project Completion
The research sought out to establish whether there revision of designs influenced completion of
ongoing projects in the study area. The study results as indicated in Figure 7, a simple majority
(53.66%) of the respondents agreed there was a common tendency of revising designs of the ongoing
projects and affected their completion whereas 46.34% of the respondents were of contrary opinion.
This can be deduced that revision of the designs of the ongoing projects was common thus hindering
completion of government funded urban constructions projects in the study area. The study results are
in agreement with literature review by Karimi (2008) who states that adequate planning at the early
stages of a project is crucial for minimizing delays and cost overruns.Variations in designs and
contract documents usually lead to a change in contract price or contract schedule. Typically, change
orders and variations present problems to all parties involved in the construction process. Usually,
these design changes require additional time and cost inputs which ultimately overruns hindering
project completion.
Hassan & Guyo…..Int. J. Innovative Development & Policy Studies 5(1):20-42, 2016
Ok
30
Figure 6: Revision Of Designs On Project Completion
Timely issuance of designs on project completion
The research sought out to establish whether timely issuance of designs influenced completion of
government construction projects in the study area. The findings as indicated in Figure 7, a majority
(66.66%) of the respondents stated that there was delay of issuance of project designs thus affecting
their completion whereas 33.34% of the respondents were of contrary opinion. This implies that
project designs were delayed during the commencement of the projects thus affecting their completion
in the study area. There is a common tendency in many projects established to have a delay on
issuance of the project designs leading to untimely project completion. The study results are in
tandem with findings of Muller & Jugdev (2012) who observed that untimely issuance of designs that
are imposed when construction is underway, usually lead to reworks, overruns and delays in project
completion Rework and demolition are potential effects of changes in construction, depending on the
timing of the occurrence of the changes can ultimately lead to overruns.
Figure 7: Timely Issuance Of Designs On Project Completion Availability Of Expertise On Project Completion
The research sought out to establish availability of project designers‟ influenced completion of the
projects in the study area. The findings as indicated in Figure 8, a simple majority (56%) of the
respondents stated that there was a shortage of project designers and affected completion of the
projects in the study area whereas 44% of the respondents were of contrary opinion. This implies that
lack of availability of project designers was an impediment on completion of the projects in the study
area. The study findings conforms with literature review by Aridity et al (2002) who observed that
availability of expertise on project design specifications is a major problem in developing countries.
Some are not only hard to predict but also difficult to manage. The inherent contractors‟ expertise
during preparation, planning, authorization and evaluation procedures for large infrastructure projects
creates obstacles to the implementation of such projects (CEU, 2008).
Hassan & Guyo…..Int. J. Innovative Development & Policy Studies 5(1):20-42, 2016
Ok
31
Figure 8: Availability Of Expertise On Project Completion
Design Changes On Project Completion
The research sought out to establish whether there was changes on design in the course of
implementation of the projects and if it affected completion of the projects. According to the study
results as illustrated in Table 4, a simple majority (70.73%) of the respondents stated that there a
common occurrence of changes being made on the agreed designs in the course of implementation of
the projects and it affected completion of the projects in the study area whereas 29.27% of the
respondents were of contrary opinion. This implies that design changes was an impediment on
completion of the projects in the study area. The study results are in agreement with literature review
by Karimi (2008) who states that adequate planning at the early stages of a project is crucial for
minimizing delays and cost overruns. Variations in designs and contract documents usually lead to a
change in contract price or contract schedule. Typically, change orders and variations present
problems to all parties involved in the construction process. Usually, these design changes require
additional time and cost an input which ultimately overruns hindering project completion.
Table 4: Design Changes On Project Completion
Opinion Frequency Percentage
Yes 29 70.73
No 12 29.27
Total 41 100
Project Procurement Procedures
Project Procurement Procedures On Project Completion
The research sought out to establish whether project procurement procedures influenced project
completion of government funded urban constructions projects in the study area. The findings as
indicated in Figure 9, a simple majority (80.49%) of the respondents agreed project procurement
pprocedures influenced project completion of government funded urban constructions projects in the
study area whereas 19.51% of the respondents were of contrary opinion. This implies that pproject
pprocurements pprocedures has influence on the completion of government funded projects in the
study area. The bureaucracies in the procurement process leads to delay of projects implementation in
the study area. The findings are in line with findings of to Kagiri &Wainaina (2007) who observed
that procurement procedures for many projects delay completion of projects
Figure 9: Project Procurement Procedures On Project Completion
Procurement Guidelines and Standardization On Project Completion
The research sought out to establish whether procurement guidelines and standardization influenced
project completion of government funded urban constructions projects in the study area. The findings
as indicated in Figure 10, a simple majority (73.17%) of the respondents agreed procurement
Hassan & Guyo…..Int. J. Innovative Development & Policy Studies 5(1):20-42, 2016
Ok
32
guidelines and standardization affected project completion of government funded urban constructions
projects in the study area whereas 26.83% of the respondents were of contrary opinion. This can be
deduced that procurement guidelines and standardization play an important role on completion of
government funded urban constructions projects in the study area. The findings of the study conforms
with Kagiri & Wainaina (2007) who states that financiers require the recipient to follow specific rules
(i.e., procurement guidelines) for identifying the contractor who constructs the road and to set up
specific financial management systems to oversee the use of funds. These specific rules and
guidelines are meant to ensure that resources are used efficiently and economically, but at the same
time can lead to fragmentation and complexity
Figure 10: Procurement Guidelines and Standardization On Project Completion
Procurement Delays On Project Completion
The research sought out to establish whether procurement delays affected completion of ongoing
projects in the study area. The findings as indicated in Table 5, simple majority (53.66%) of the
respondents agreed there were common procurement delays and it affected project completion
whereas 46.34% of the respondents were of contrary opinion. This implies that projects were not
completed as expected due recurring procurement delays. The study findings are in agreement with
literature review by Rundquist (2008) who states that procurement as the acquisition of goods,
services and/or infrastructure at the best possible total cost of ownership in the right quantity and
quality, at the right time, in the right place for the direct benefit or use of governments, corporations
or individuals, generally via a contract greatly influence project completion. It is evident from the
discussions above that procurement is an important aspect of the project implementation and has
many parties involved namely development partners, government, implementing agencies and
contractors. Procurement delays can therefore arise on the projects from various parties involved. The
contractors are responsible for the procurement of materials and equipment in all the contracts. For
multi-contract projects, where the engineer had dual role of designer and supervisor on the civil
contracts, many factors interplay leading to delays. On some contracts, there are delays by contractors
in releasing of procurement drawings, delays in provision of design information from supply
contractors to the engineer‟s designers to prepare procurement drawings. Delays are also experienced
in the tendering system, preparation of the bidding documents, and approval by the development
partners on the documentation submitted as it has to meet the set standards. The several approval
stages in procurement can also lead to delays especially in high-value contracts as they have to go the
highest levels for approval.
Table 5: Procurement Delays on Project Completion
Opinion Frequency Percentage
Yes 22 53.66
No 19 46.34
Total 41 100
Tendering Systems On Project Completion
The research sought out to establish effectiveness of tendering systems affected completion of the
projects in the study area. The findings as indicated in Table 5, majority (82.93%) of the respondents
stated that there was ineffectiveness of tendering systems thus affecting project completion whereas
Hassan & Guyo…..Int. J. Innovative Development & Policy Studies 5(1):20-42, 2016
Ok
33
17.07% of the respondents were of contrary opinion. This implies that ineffectiveness of tendering
systems is an impediment on completion of the projects. It is evident from the discussions above that
tendering systems are important aspect of the project implementation and has many parties involved
namely development partners, government, implementing agencies and contractors thus affecting
project completion in the study area. The study conforms with findings of Rundquist (2008) who
observed that the tendering systems delays are also experienced in the preparation of the bidding
documents, approval by the development partners on the documentation submitted as it has to meet
the set standards. The several approval stages in procurement can also lead to delays especially in
high-value contracts as they have to go the highest levels for approval thus affecting project
completion.
Table 6: Tendering Systems On Project Completion
Opinion Frequency Percentage
Yes 7 17.07
No 34 82.93
Total 41 100
Procurement Stages On Project Completion
The research sought out to whether procurement stages influenced completion of the projects in the
study area. The findings as indicated in Figure 11, majority (87.81%) of the respondents stated that
there was bureaucracy on every procurement stage and affected completion of the projects in time
whereas 12.19% of the respondents were of contrary opinion. This reveals that bureaucracy on
procurement stages had effects on completion of the projects in the study area. The study findings are
in agreement with literature review by Rundquist (2008) who states that procurement stages as the
acquisition of goods, services and/or infrastructure at the best possible total cost of ownership in the
right quantity and quality, at the right time, in the right place for the direct benefit or use of
governments, corporations or individuals, generally via a contract greatly influence project
completion.
Figure 11: Procurement Stages On Project Completion
Procurement Policy On Project Completion
The research sought out to establish whether procurement policy influenced completion of the
projects. According to the study results as illustrated in Figure 12, a simple majority (68.29%) of the
respondents stated that procurement policy facilitated completion of government urban construction
projects in the study area whereas 31.71% of the respondents were of contrary opinion. This implies
that government procurement policy plays an important role towards completion of the projects in the
study area. The study findings are in agreement with literature review by Rundquist (2008) who states
that procurement policy on the acquisition of goods, services and/or infrastructure at the best possible
total cost of ownership in the right quantity and quality, at the right time, in the right place for the
direct benefit or use of governments, corporations or individuals, generally via a contract greatly
influence project completion. For multi-contract projects, where the engineer had dual role of designer
and supervisor on the civil contracts, many factors interplay leading to delays. On some contracts,
there are delays by contractors in releasing of procurement drawings, delays in provision of design
information from supply contractors to the engineer‟s designers to prepare procurement drawings
which require a proper procurement policy.
Hassan & Guyo…..Int. J. Innovative Development & Policy Studies 5(1):20-42, 2016
Ok
34
Figure 12: Procurement Policy On Project Completion
Procurement Feedback System and Reporting On Project Completion
The research sought out to establish whether effective procurement system and reporting influenced
completion of the projects. According to the study results as illustrated in Figure 4.17, a simple
majority (71.29%) of the respondents stated that there were ineffective Procurement feedback system
and reporting which hindered completion of government urban construction projects in the study area
whereas 28.71% of the respondents were of contrary opinion. This implies that ineffective
procurement feedback system and reporting did affect completion of urban government funded
projects in the study area. The study findings are in agreement with literature review by Rundquist
(2008) who states that procurement feedback systems are necessary for procurement purposes.
Figure 13: Procurement Feedback System and Reporting On Project Completion
Project Cost
Project Cost On Project Completion
The research sought out to establish whether project cost influenced project completion of
government funded urban constructions projects in the study area. The findings as indicated in Figure
14, a simple majority (92.68%) of the respondents agreed project cost influenced project completion
of government funded urban constructions projects in the study area whereas 7.32% of the
respondents were of contrary opinion. This implies that project cost has an effect on the completion of
government funded projects in the study area. The study established that many projects had issues
with cost estimation. The study findings corroborates with the Kuen, Zailani and Fernando (2009)
who stated that cost is one of the primary measures of a project‟s success. This is true, especially for
public projects in developing countries like Kenya, because public construction projects in these
countries are executed with lack of proper cost projections on most government funded projects.
Hassan & Guyo…..Int. J. Innovative Development & Policy Studies 5(1):20-42, 2016
Ok
35
.
Figure 14: Project Cost On Project Completion
Material Cost On Project Completion
The research sought out to establish whether material cost influenced project completion of
government funded urban constructions projects in the study area. The findings as indicated in Table
7, a simple majority (73.17%) of the respondents agreed material cost influenced project completion
of government funded urban constructions projects in the study area whereas 26.83% of the
respondents were of contrary opinion. This can be deduced that material cost played a major role on
project completion of government funded urban constructions projects in the study area. The study
findings are in line with a study made in Turkey by Arditi, et al, (2005), the important sources for cost
overruns were found to be inflationary pressures, increases in material prices difficulties in obtaining
construction materials, construction delays, deficiencies in material cost estimates prepared by public
agencies and unexpected sub soil conditions were the most important sources for cost overruns that
affected successful completion of projects.
Table 7: Material Cost On Project Completion
Opinion Frequency Percentage
Yes 30 73.17
No 11 26.83
Total 41 100
Labour Cost On Project Completion
The research sought out to establish whether labour cost influenced completion of projects in the
study area. The findings as indicated in Figure 15, simple majority (51.21%) of the respondents
agreed there was a common tendency of revising designs of the ongoing projects and affected their
completion whereas 48.79% of the respondents were of contrary opinion. This can be deduced that
labour cost can hinder completion of government funded urban constructions projects in the study
area. The study findings are in line with a study made in Turkey by Arditi, et al, (2005), the important
sources for cost overruns were found to be inflationary pressures, increases in workmen wages
difficulties in obtaining construction expert wages, deficiencies in labour cost estimates prepared by
public agencies and unexpected sub soil conditions were the most important sources for cost overruns
that affected successful completion of projects.
Hassan & Guyo…..Int. J. Innovative Development & Policy Studies 5(1):20-42, 2016
Ok
36
Figure 15: Labour Cost On Project Completion
Equipment Cost On Project Completion
The research sought out to establish whether equipment cost affect completion of the projects in the
study area. The findings as indicated in Table 16, majority (58.54%) of the respondents stated that
equipment cost affect completion thus affecting their completion whereas 41.46% of the respondents
were of contrary opinion. This implies that equipment costs were delayed during the commencement
of the projects thus affecting their completion in the study area. The study findings are in line with a
study by Mono, (2013) who observed that the important sources for cost overruns were found to be
inflationary pressures, increases in material prices difficulties in obtaining construction materials,
construction delays, deficiencies in material and equipment cost estimates prepared by public agencies
were the most important sources for cost overruns that affected successful completion of projects.
Table 8: Equipment Cost On Project Completion
Opinion Frequency Percentage
Yes 24 58.54
No 17 41.46
Total 41 100
Project Completion
Project Completion In Time
The research sought out to establish whether the government funded urban constructions projects
were completed in the study area. The findings as indicated in Figure 16, a simple majority (92.68%)
of the respondents stated completion of government funded urban constructions projects in the study
area was not on time whereas 7.32% of the respondents were of contrary opinion. This implies that
most of government funded projects in the study area were not completed in time
Figure 16: Project Completion In Time
Project Completion As Per Specification
The research sought out to establish whether the government funded urban constructions projects
were completed as per the specification in the study area. The findings as indicated in Table 9,
majority (80.49%) of the respondents stated completion of government funded urban constructions
projects in the study area were not completed as per the specification whereas 19.51% of the
Hassan & Guyo…..Int. J. Innovative Development & Policy Studies 5(1):20-42, 2016
Ok
37
respondents were of contrary opinion. This implies that most of government funded projects in the
study area were completed as per the specification.
Table 9: Project Completion In Time
Opinion Frequency Percentage
Yes 8 19.51
No 33 80.49
Total 41 100
Project Completion Within The Budget
The research sought out to establish whether the government funded urban constructions projects
were completed as per the specified budget in the study area. The findings as indicated in Figure 17,
majority (95.12%) of the respondents stated completion of government funded urban constructions
projects in the study area were not completed within the specified budget whereas 4.88% of the
respondents were of contrary opinion. This implies that most of government funded projects in the
study area were not completed within the allocated budget.
Figure 17: Project Completion Within The Budget
Multiple Regression Analysis
According to Green & Salkind (2003) regression analysis is a statistics process of estimating the
relationship between variables. Regression analysis helps in generating equation that describes the
statistics relationship between one or more predictor variables and the response variable. Since there
are four variables against one dependent variable, multiple regression analysis was used to establish
their relationship at 5% level of significance. Further, the multiple regression analysis is
mathematically expressed as shown below: a multivariate regression model was applied to determine
the relative importance of each of the four variables with respect to the project completion of
government urban funded projects .The results are shown in Table 9.
Table 9: Model summary
Model R R2 Adjusted R
2 Std. Error of
the Estimate
1 .811a .642 .618 .876
a. Predictors: (Constant), project contractors experience, project cost, project design specifications and project
procurement procedures
R is the correlation coefficient which shows the relationship between the study variables, from the
findings shown in the Table 9 is notable that there extists strong positive relationship between the
study variables as shown by 0.811. The coefficient of determination (R2 ) explains the extent to which
changes in the dependent variable can be explained by the change in the independent variables or the
percentage of variation in the dependent variable (project completion of government urban funded
projects) that is explained by all four independent variables (project contractors experience, project cost,
project design specifications and project procurement procedures).According to the four independent
variables studied, they explain only 64.20% of the project completion of government urban funded
projects. This implies that these variables are very significant therefore need to be considered in any
effort to enhance project completion of government urban funded projects in Kenya. The study
therefore identifies variables as critical determinants of project completion of government urban funded
Hassan & Guyo…..Int. J. Innovative Development & Policy Studies 5(1):20-42, 2016
Ok
38
projects. Further, it means that other factors not studied in this research contribute 35.80% of project
completion of government urban funded projects. Therefore, a further study should be conducted to
investigate the other factors that contribute 35.80% which influence project completion of government
urban funded projects.
Analysis of Variance (ANOVA)
Table 10: Analysis of Variancea
Model Sum of
Squares
Df Mean Square F Sig.
1 Regression 86.880 4 21.720 32.2494 .001b
Residual 24.247 36 .6735
Total 109.901 40
a. Dependent Variable: Project completion of government urban funded projects
b. Predictors: (Constant), project contractors experience, project cost, project design
specifications and project procurement procedures
c. Critical value = 17.673
From the Table 10, the study established the regression model had a significance of 0.001 which is an
indication that the data was ideal for making a conclusion on the population parameters as the value of
significance (p-value) was less than 5%. The F-calculated value was greater than the critical value
(32.2494 > 17.673) an indication that project contractors experience, project cost, project design
specifications and project procurement procedures and all enhance Project completion of government
urban funded projects and this shows that the overall model was significant
Regression Coefficients
Table 11: Regression Coefficientsa
Model Unstandardized
Coefficients
Standardized
Coefficients
T Sig.
B Std.
Error
Beta
1 (Constant) 65.008 2.065 2.309 .001
Project contractors experience .644 .885 .502 2.455 .013
Project design specifications .493 .556 .555 3.266 .037
Project procurement
procedures
.703 .487 .405 2.011 .011
Project cost .532 .356 .609 2.069 .019
a. Dependent Variable: Project completion of government urban funded projects
The general form of the equation was to predict project completion of government urban funded
projects from project contractors experience, project cost, project design specifications and project
procurement procedures is: Y = β0 + β1X1 + β2X2 + β3X3 + β4X4 + ε Where Y= Project completion
of government urban funded projects; β0 = Constant Term; β1, β2, and β3 = Beta coefficients; X1=
project contractors experience; X2= project design specifications ; X3= project procurement
procedures; X4 = project cost and ε = Error term. The model equation would be; Y=65.008 + 0.644X1
+ 0.493X2 + 0.703X3 + 0.532X4. The Project completion of government urban funded projects =
65.008 + (0.644 x project contractors experience) + (0.493 x project design specifications) + (0.703 x
project procurement procedures) + (0.532 x project cost). From above regression equation; the study
found out that when all independent variables (project contractors‟ experience, project cost, project
design specification and project procurement procedures) are kept constant at zero the Project
completion of government urban funded projects will be at 65.008. At one unit change in project
contractors experience will lead to 0.644 increases in Project completion of government urban funded
projects. Also a one unit change in project design specifications will lead to 0.493 increases in the
Project completion of government urban funded projects. Further, a one unit change in project
procurement procedures will lead to 0.703 increases in the new Project completion of government
Hassan & Guyo…..Int. J. Innovative Development & Policy Studies 5(1):20-42, 2016
Ok
39
urban funded projects and one unit change in project cost will lead to 0.532 increases in Project
completion of government urban funded projects.
This concludes that knowledge application contributes more to Project completion of government
urban funded projects. To test for the statistical significance of each of the independent variables, it
was necessary to test at 5% level of significance and 95% level of confidence of the p-values and
from the Table 4.10 the project contractors experience had a 0.013; project procurement procedures
showed a 0.011 level of significance, project design specification showed a 0.037 level of
significance and project cost had a 0.019 level of significance. Therefore, the most significant factor
was project procurement procedures.
CONCLUSIONS
The study established that project cost affects completion of the government funded urban
construction projects. The study revealed that inadequate funds on investment materials, equipment
and labour adversely affected completion of the projects. Further, the study revealed that the variable
statistically, moderately, positively and significantly correlated to project completion of the
government funded projects in the county
Additionally, the study found out project designs such as inadequate design information, use of
computer aided designs, revision of designs, timely issuance of designs and lack of quality assurance
in designs to some extent affect completion of the projects. The study revealed that the variable
statistically, strongly and significantly correlated to project completion of the government funded
projects in the county
Further, the study revealed that project procurement procedures influenced completion of the urban
construction projects. The lack of bidding documents, procurement drawings, approval of
procurement stages, tendering systems and procurement standardization affected completion of the
projects. The Pearson correlation coefficient statistically, strongly and significantly correlated to
project completion of the government funded projects in the county
Finally, project contractors experience in terms of technical skills, management skills due to lack of
enough trainings was found out to be a major impediment towards completion of the projects. The
Pearson correlation coefficient statistically, strongly and significantly correlated to project completion
of the government funded projects in the county
RECOMMENDATIONS
The study recommends that that project contractors experience is crucial for project completion of
government funded urban construction projects. There is need to enhance the contractor‟s knowledge
and a cognitive skill through the contractor‟s continuous training. The cost escalations due to
contractors experience and bankruptcy of the contractor during implementation period should be
established. The contractors experience during preparation, planning, authorization and evaluation
procedures influenced completion of the government funded urban projects should also be established
to avoid delays of the projects.
The project design specification should be enhanced to improve project completion in government
funded urban construction projects. The timing of issuance of designs, availability of expertise on
designing, the design efficiencies reduce to redesign and rework or poor quality of products thus
improving completion of the government funded urban projects in Nairobi county
The project procurement procedures through the tendering systems, approval of procurement stages,
the government procurement policy on implementation of projects and monitoring of the procurement
system and reporting should be monitored and evaluated to reduce the project cost especially on the
material cost, labour cost, equipment cost, control cost overruns and deficiencies on cost estimates,
financial management of project funds and monitoring and evaluation of funds, government capital
investment cost on implementation of projects to enhance performance of the projects.
REFERENCES Adan, I. H. (2012). Influence of stakeholders role on performance of constituencies development fund projects a case of
Isiolo North Constituency, Kenya. Available at: http://researchkenya.or.ke/node/18866
Ahmed S, Azher S, Castillo M, Kappagantula, P. (2012) Construction Delays in Florida; An Empirical Study, Florida.
Aiyetan, O.A., Smallwood, J.J. & Shakantu, W. (2008). Influences on construction project delivery time performance. In the
proceeding of Third Built Environment conference, Cape Town, South Africa
Hassan & Guyo…..Int. J. Innovative Development & Policy Studies 5(1):20-42, 2016
Ok
40
Al-Kharashi, A. & Skitmore, M. (2009). Causes of delays in Saudi Arabian public sector construction projects. Construction
Management and Economics, 27(1), 3-23.
Ardity, D., Akan, T., & Gurdamar, S. (2009). Adherence to cost estimates in public projects: International Journal of
Project Management.
Babbie, E. (2009). Survey research methods (2nd ed.). Belmont: Wodsworth.
Barney, J. (1986). Strategic factor markets: Expectations, luck, and business strategy. Management Science, 32, 1231-1241.
Battaineh R.K (2006) „Causes of Delay in Large Building Construction Projects‟, Journal of Management in Engineering,
Vol. 11, No. 2.
Binder, (2008). User Satisfaction and Sustainability of Drinking Water Schemes in Rural Communities of Nepal.
Bridget, S., and Lewin, C. (2005). Research Methods in the Social Sciences. London: Sage publications
Bordens, K. S., and Abbott, B.B. (2008). Research design methods: A process approaches (7th ed.). New York, NY:
McGraw-Hill.
Burke, R. (2004). Project Management Planning and Control Techniques. 4th edition, New Delhi India: Pearson Education.
Callahan, M. T., D. G. Quackenbush, and J. E. Rowings, (2006). “Construction Project scheduling”. USA: McGraw-Hill.
Chandran C. (2004). Research Methods: A qualitative Approach with Illustrations from Christian Ministries. Nairobi:
Daystar University.
Chan, M., & Kumaraswamy, M. (2007). A comparative study of causes of time overruns in Hong Kong construction
projects. International Journal of Project Management 15(1), pp. 55-63.
Chan, M., Scott, D. & Chan, L. (2004). Factors affecting the success of a construction project: Journal of Construction
Engineering and Management 130 pp. 153.
Conner, K.R. (1991). A historical comparison of resource-based theory and five schools of thought within the industrial
organization economics: Do we have a new theory of the firm? Journal of Management, 17, 121-154.
Cooper D R, Schindler PS (2005). Business Research Methods. (8th ed.). Mc Graw-Hill, New Delhi, India.
Creswell, J. W. (2003).Research design: Quantitative, qualitative, and mixed methods approaches (2nd Ed.). Thousand
Oaks, CA: Sage.
Creswell, J. W., (2002). Educational research: Planning, conducting, and evaluating quantitative and qualitative
approaches to research. New Jersey: Merrill/Pearson Education.
Cronbach, L. J. (1971). Test validation. In R. L. Thorndike (Ed.). Educational Measurement (2nd Ed.). Washington, D. C.:
American Council on Education
Damodaran, L. (2011). User involvement in the systems design process: a practical guide for users, Behaviour &
Information Technology, 15(6), 363-377
Ektewan, M. & Ogunlana, S.O. (2006). Public hearings in Thailand's infrastructure projects: effective participations?,
Engineering, Construction and Architectural Management, 13(4), 343 – 363
Flyvbjerg, B. (2005), Policy and Planning of Large Infrastructure Project Problems, Causes, Cures. World Bank Policy
Research Working Paper 3781, Cambridge University Press, Cambridge.
Flyvbjerg, B., Holm, S., & Buhl, L. (2004). What Causes Cost Overrun in Transport Infrastructure Projects?: Transport
Reviews, 24 (1), 3-18.
Fudge, N. & Wolfe, C.D.A. (2008). Assessing the promise of user involvement in health service development: ethnographic
study. BMJ, 336, 313
Ghazala, M. & Vijayendra R. (2011) Evaluating Community Based and Community Driven Development: A critical review
of the Evidence. Working Paper, Development research Group, World Bank.
Goldratt, Eli M.. (1984). Essays on the Theory of Constraints. [Great Barrington, MA]: North River Press. ISBN 0-88427-
159-5.
Hamel, G., & Prahalad, C.K. (1996). Competing for the Future. Boston: Harvard Business School Press.
Kvaye, M., & Anderson, R. (2000). Continuous improvement: The ten essential criteria.The International Journal of Quality
& Reliability Management, 16(5), 485.
Kagiri, D., & Wainaina, G. (2009). Time and Cost Overruns in Power Projects in Kenya: A Case Study of Kenya Electricity
Generating Company Limited, Nairobi. (2004). Solving Tough Problems: An Open Way of Talking, Listening, and
Creating New Realities. Berrett-Koehler Publishers.
Kaliba, C. Muya, M. & Mumba, K. (2009), Cost Escalation and Schedule Delaying Building Construction Projects in
Zambia, International Journal of Project Management, Vol. 27, Issue 5, pp 522-531.
Karimi, R.B.(2008), “Factors which are Critical in Project Cost Overruns: A Case Study of Ministry of Water Resources
Projects”, Unpublished MBA Thesis, University of Nairobi.
Kog, C., & Loh, K. (2012). Critical Success Factors for Different Components of Construction Projects. Journal of
Construction Engineering and Management 138(4), pp. 520-528.
Koskela, Howell ., & Ballard, G. (2002). Should project management be based on theories of economics or production?:
Building Research and Information, Vol. 34, No. 2
Kothari, C. R. (2004). Research methodology: Methods and techniques. New Delhi: New Age International (P) Limited
Publishers.
Kuen, C.W., Zailani, S., & Fernando, Y. (2009). Critical factors influencing the project success amongst manufacturing
companies in Malaysia. African Journal of Business management, 3(1), 16-27.
Kumar, C. (2000). Research Methods.(2ndedn.). New York: Harper and Row.
Lin-lin, X., Yang, Y. Hu, Y. & Chan, A.P.C. (2014). Understanding project stakeholders‟ perceptions of public participation
in China's infrastructure and construction projects: Social effects, benefits, forms, and barriers", Engineering,
Construction and Architectural Management, 21(2), 224 – 240
Maina, B. M. (2013). Influence of stakeholders’ participation on the success of the economic stimulus programme: a case of
education projects in Nakuru County, Kenya. Retrievedfrom
Hassan & Guyo…..Int. J. Innovative Development & Policy Studies 5(1):20-42, 2016
Ok
41
Maltz, A.C., Shenhar, A.J. & Reilly, R.R. (2003). Beyond the balanced scorecard: Refining the search for organizational
success measures, Long Range Planning, Vol. 36, No. 2,pp.187-204.
Malkat, M & Byung-Gyoo, K. (2012). An Investigation on the Stakeholders of Construction Projects in Dubai and Adjacent
Regions. Available at: www.ipedr.com vol45 016-ICMTS2012-M00008.pdf
Marchewka, J.T. (2006). Information Technology Project Management: Providing Measurable Organizational Value, 2nd
ed., Wiley, New York, NY.
McGrew, J.F., Bilotta, J.G. (2007) The effectiveness of risk management: measuring what did not happen, Manage Decision,
38(4) 293-300.
Mono, O.R. (2013).Determinants of successful delivery of housing construction Projects in the Ministry of Housing in
Nairobi, Kenya. Retrieved from: http://ir-library.ku.ac.ke/handle/123456789/6213
Morris, G., & Hough, H. (2008). The Anatomy of Major Projects: A Study of the Reality of Project Management. Chichester;
New York: Wiley, pp. 502-511.
Mugenda, O.M and Mugenda, A.G (2003) Research Methods, Quantitative & Qualitative Approaches. Acts Press: Nairobi
Müller, R., & Jugdev, K. (2012). Critical success factors in projects Pinto, Slevin, and Prescott – the elucidation of project
success. International Journal of Managing Projects In Business, 5(4), 757-775.
Musa, G. H., (2009)“Determination of Factors Influencing Projects Delays in Water Projects in Kenya: The Case of
Government Funded Projects”, Unpublished MBA Thesis University Of Nairobi.
Mwandali, D., (2006) “Analysis of Major Factors that Affect Projects Management: A Case of Kenya Railways Projects”,
Unpublished MBA Thesis, University of Nairobi.
Nana Agyeman (2010), Delays in building construction projects in Ghana.
Nyandika Fred(2014); Influence of stakeholders' participation on performance of road projects at Kenya National
Highways Authority ; A Research Project Submitted in Partial fulfillment for the award of degree of master of
science in project management of Jomo Kenyatta University of Agriculture and Technology
National Tax Payers Association (2010), Utilization of Government Revenue: Government Printers, Nairobi
Neuman, W.L. 2006. Social Research Methods: Qualitative and Quantitative Approaches. Pearsons Education Inc. Boston.
USA
Nunnally, J. C. (1978). Psychometric theory (2nd ed.). New York: McGraw-Hill.
O‟Brien, S., & Ibbs, C. (2005). The Paradox of using Tacit and Explicit Knowledge Strategies to face Dilemmas:
Management Decision, Vol. 43 No. 1, pp. 102-112.
Olawale, A., & Sun, M. (2010). Cost and Time Control of Construction Projects: Inhibiting Factors and Mitigating Measures
in Practice. Construction Management and Economics 28(5), pp. 509-526.
Olima,H.A. (2011). The Dynamics and Implications of Sustaining Urban Spatial Segregation in Kenya: Experiences from
Nairobi Metropolis. Paper presented at the International Seminar on Segregation in the City Held at Lincoln
Institute of Land Policy in Cambridge, MA, USA, July 25-28, 2001.
Onchoke, N. K. (2013). Factors influencing performance of community development projects in Kenya: a case of Kisii
Central District. Available at: http://ir-library.ku.ac.ke/handle/123456789/6205
Ondieki, W. M. (2011). Factors influencing stakeholders' participation in monitoring and evaluation of Local Authority
transfer fund projects in Kisii municipality, Kenya. Available at
http://erepository.uonbi.ac.ke:8080/handle/123456789/3906
Onions, W. (2007). A Knowledge Based Theory of Project Management: McGraw-Hill, pp 61-72.
Ophiyandri, T., Amaratunga, D., Pathirage, C. & Keraminiyage, K. (2013). Critical success factors for community-based
post-disaster housing reconstruction projects in the pre-construction stage in Indonesia, International Journal of
Disaster Resilience in the Built Environment, 4(2), 236 – 24
Republic of Kenya.(2014). Kenya National Bureau of Statistics.Economic Survey 2014.Nairobi: Government Printer.
Rundquist, J. (2008) World Class or Good Enough: the Choice of partner when Outsourcing New Product
Development in medium sized firms. International Journal of Innovation and Technology Management 5:
429‐451.
Sambasivan M. and Yau W.S., (2007). Causes and effects of delays in Malaysian construction industry. International
Journal of Project Management 25: pp. 517 -526.
Sauer, C. & Reich, H. (2007). What do we want from a Theory of Project Management?: International Journal of Project
Management, A response to Rodney Turner”, Guest editorial, Vol.25, pp 1-2.
Saunders, M., Lewis, P., &Thornhill, A. (2007).Research Methods for Business Students.(4thedn.). Harlow: Financial Times
Prentice Hall.
Schumpeter, J.A. (1950). American Institutions and Economic Progress.New York: Harper & Brothers.
Sekaran, U. (2003). Research Methods for Business: A Skill Building Approach. (4thedn.). USA: John Wiley & Sons
Publishers.
Seboru, M. A. (2006). An investigation into factors causing delays in road construction projects in Kenya, unpublished MA
Project, Faculty of Architecture, design and Development, University of Nairobi
Serdar S. Durmusoglu, (2009). The role of top management team's information technology (IT) infrastructure view on new
product development: Conceptualizing IT infrastructure capability as a mediator. European Journal of Innovation
Management, 12(3), 364 – 385
Tabish, S., & Jha, K. (2012). Success Traits for a Construction Project. Journal of Construction Engineering &
Management,138(10), 1131-1138.
Talukhaba, A.A, (2008). “Time and Cost Performance of Construction Projects”, Unpublished M.A. Thesis, University of
Nairobi.
Turner, R. ( ). Towards a Theory of Project Management: The Nature of the Project: International Journal of Project
Management, Vol 24, p.1-3.
Hassan & Guyo…..Int. J. Innovative Development & Policy Studies 5(1):20-42, 2016
Ok
42
Williams,T. (2008), "A review of inventory management research in major logistics journals: themes and future
directions", International Journal of Logistics Management, Vol. 19 No.2, pp.212-32.
Yin, R. K., (2003), Case Study Research: Design and Methods, (3rd edition). Sage Publications, London
Young, N. (2009). Understanding the Research Process and Methods. An Introduction to Research Methods. Las Vegas:
Acts Press.
Zhang, Z.H. (2000). Implementation of Total Quality Management: An Empirical Study of Chinese Manufacturing
Firms.Unpublished doctoral dissertation, University of Groningen, Groningen, Netherlands.
Zou, P. X.W., Zhang,G., and Wang, J. (2006). Identifying key risks in construction projects: life cycle and stakeholder
perspectives. www.prress.net/papers/Zou_risks-construAccessed 4/9/2012
Hassan & Guyo…..Int. J. Innovative Development & Policy Studies 5(1):20-42, 2016
Ok