MICE Detector Systems

Beam Monitors Upstream

Ready. However, RAL engineering has expressed concern about cable runs and the electronics rack. Some work may have to be done during shutdown. Also would like to do source studies during shutdown

Downstream MAPMTs showed evidence of sparking. If during the shutdown we

can do some tests to verify this, then we might want to pull the monitor to remove the tubes

CKOV Ready. Again some re-cabling issues.

TOF0/1

Page 3: Detector Systems For May/June Run MICE Video Meeting April 24, 2008.

MICE Detector Systems II

Calorimeter KL detector & RC crossing trigger counters with mechanical

equipment for supporting and movement installed HV cables (46 units) 16 m long Twisted pair cables (42 units) 48 m long for temporary position close to

TOF1 Twisted pair cables (42 units) 24 m long for final downstream position Coax cables (4 units) for trigger counters SY 527 HV mainframe power supply 144 channels of HV boards (A734 type) (KL, RCTC, TOF0 and TOF1 require

114 chs). Available power multi-socket but UK power plug needed ! PC for HV manual setting and monitoring 12 FADC modules, plus 3 FADCs (120 chs) and 2 FTDCs (64 chs) that

should have been already installed by Jean-Sebastien in the Mice Control Room

Spares : coax and twist-pairs cables, PMTs and VDs Tooling and spares for (small) electrical and mechanical interventions in

a 120x60x40 metallic piece of furniture

Tracker Will be in R8