DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and...

37
PROJECT NAME: Item No./Description: 104(2) Embankment, Common Borrow Unit of Measurement: cu.m. Output per hour: Quantity: A. Labor a. Const. Foreman b. Unskilled Labor P B. Equipment, (2014 ACEL Rates) a. Motorized Road Grader (140 hp), G170A b. Vibratory Roller (10 mt), SD100C c. Water Truck/Pump (16000 L) P C. D. E. Materials a. Common Borrow (with 25% Shrinkage Factor) P F. Direct Cost (C + E) G. Overhead, Contingencies and Miscellaneous 12% per D.O. 197, s. 2016 H. Contractor's Profit(CP) 8% per D.O. 197, s. 2016 I. Value Added Tax (VAT 5% per D.O. 197, s. 2016 J. Total Unit Cost 5,582.00 Designation 1 242,593.72 206,087.44 68,379.50 2 13.96 342.24 9,551.92 Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy. Vitali, Zamboanga City, 50.00 No. of Persons Amount Compacted Volume 13.96 1 17,384.00 Amount No. of Days DETAILED UNIT PRICE ANALYSIS 14,768.00 13.96 611.92 8,539.34 1 3,130,804.25 6,977.50 cu.m. 448.70 Sub-total for B 517,060.66 Sub-total for A 18,091.26 Name and Capacity No. of Equipment No. of Days Daily Rate 3.49 19,600.00 Total (A+B) 535,151.92 Output/day 400.00 cu.m./day Name and Specifications Quantity Unit Unit Cost Amount Sub-total for E 3,130,804.25 1 13.96 3,665,956.17 439,914.74 293,276.49 219,957.37 827.50 Daily Rate

Transcript of DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and...

Page 1: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

PROJECT NAME:

Item No./Description: 104(2) Embankment, Common Borrow

Unit of Measurement: cu.m.

Output per hour:

Quantity:

A. Labor

a. Const. Foreman

b. Unskilled Labor

P

B. Equipment, (2014 ACEL Rates)

a. Motorized Road Grader (140 hp), G170A

b. Vibratory Roller (10 mt), SD100C

c. Water Truck/Pump (16000 L)

P

C.

D.

E. Materials

a. Common Borrow

(with 25% Shrinkage Factor)

P

F. Direct Cost (C + E)

G. Overhead, Contingencies and Miscellaneous 12% per D.O. 197, s. 2016

H. Contractor's Profit(CP) 8% per D.O. 197, s. 2016

I. Value Added Tax (VAT) 5% per D.O. 197, s. 2016

J. Total Unit Cost

5,582.00

Designation

1 242,593.72

206,087.44

68,379.50

2 13.96 342.24 9,551.92

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy.

Vitali, Zamboanga City,

50.00

No. of Persons Amount

Compacted Volume

13.96

1

17,384.00

Amount

No. of Days

DETAILED UNIT PRICE ANALYSIS

14,768.00

13.96 611.92 8,539.34

1

3,130,804.25 6,977.50 cu.m. 448.70

Sub-total for B 517,060.66

Sub-total for A 18,091.26

Name and CapacityNo. of

EquipmentNo. of Days Daily Rate

3.49 19,600.00

Total (A+B) 535,151.92

Output/day 400.00 cu.m./day

Name and Specifications Quantity Unit Unit Cost Amount

Sub-total for E 3,130,804.25

1 13.96

3,665,956.17

439,914.74

293,276.49

219,957.37

827.50

Daily Rate

Page 2: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

PROJECT NAME:

Item No./Description: 200 Aggregate Subbase Course

Unit of Measurement: cu.m.

Output per hour:

Quantity:

A. Labor

a. Const. Foreman

b. Unskilled Labor

P

B. Equipment, (2014 ACEL Rates)

a. Motorized Road Grader (140 hp), G710A

b.

c.

P

C.

D.

E. Materials

a. Aggregate Subbase Course

P

F. Direct Cost (C + E)

G. Overhead, Contingencies and Miscellaneous 12% per D.O. 197, s. 2016

H. Contractor's Profit(CP) 8% per D.O. 197, s. 2016

I. Value Added Tax (VAT) 5% per D.O. 197, s. 2016

J. Total Unit Cost

1.44 342.24 982.23

1 1.44 611.92 878.11

2

No. of Persons No. of Days Daily Rate Amount

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy.

Vitali, Zamboanga City,

50.00

574.00

Designation

DETAILED UNIT PRICE ANALYSIS

Sub-total for A 1,860.33

Name and CapacityNo. of

EquipmentNo. of Days Daily Rate Amount

1 1.44 17,384.00 24,946.04

Vibratory Roller (10 mt), SD100DC 1 1.44 14,768.00 21,192.08

Water Truck/Pump (16000 L) 1 0.36 19,600.00 7,031.50

Sub-total for B 53,169.62

Total (A+B) 55,029.95

Output/day 400.00 cu.m./day

Name and Specifications Quantity Unit Unit Cost Amount

660.10 cu.m. 1,042.10 687,890.21

(w/ 15% Shrinkage Factor)

Sub-total for E 687,890.21

742,920.16

89,150.42

59,433.61

44,575.21

1,630.80

0.30 m. thk., Compacted Volume

Page 3: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

PROJECT NAME:

Item No./Description: 300(1) Gravel Surface Course

Unit of Measurement: cu.m.

Output per hour:

Quantity:

A. Labor

a. Const. Foreman

b. Unskilled Labor

P

B. Equipment, (2014 ACEL Rates)

a. Motorized Road Grader (140 hp), G710A

b.

c.

P

C.

D.

E. Materials

a. Uncrushed Aggregate Surface Course

P

F. Direct Cost (C + E)

G. Overhead, Contingencies and Miscellaneous 12% per D.O. 197, s. 2016

H. Contractor's Profit(CP) 8% per D.O. 197, s. 2016

I. Value Added Tax (VAT) 5% per D.O. 197, s. 2016

J. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy.

Vitali, Zamboanga City,

50.00

55.00

Designation No. of Persons No. of Days Daily Rate Amount

0.15 m. thk.

1 0.14 611.92 84.14

2 0.14 342.24 94.12

Sub-total for A 178.26

Name and CapacityNo. of

EquipmentNo. of Days Daily Rate Amount

1 0.14 17,384.00 2,390.30

Vibratory Roller (10 mt), SD100DC 1 0.14 14,768.00 2,030.60

Water Truck/Pump (16000 L) 1 0.03 19,600.00 673.75

Sub-total for B 5,094.65

Total (A+B) 5,272.91

Output/day 400.00 cu.m./day

Name and Specifications Quantity Unit Unit Cost Amount

63.25 cu.m. 1,097.10 69,391.58

(w/ 15% Shrinkage Factor)

Sub-total for E 69,391.58

74,664.48

8,959.74

5,973.16

4,479.87

1,710.50

Page 4: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

PROJECT NAME:

Item No./Description: 311(1)e1 Portland Cement Concrete Pavement, 0.28 m. thk.

Unit of Measurement: sq.m.

Output per hour:

Quantity:

A. Labor

a. Const. Foreman

b. Skilled Labor

c. Unskilled Labor

P

B. Equipment, (2014 ACEL Rates)

a. Transit Mixer (5 cu.m.)

b.

c.

d.

e.

f. Water truck/Pump (16000 L)

g. Concrete Saw (7.5 hp), 14" Blade Ø

h. Bar Cutter, Single Phase

Minor Tools 5% of Labor

P

C.

D.

E. Materials

a. Reinforcing Steel Bar

b.

c. Asphalt Sealant

d.

e.

f.

g.

h.

i.

j.

P

F. Direct Cost (C + E)

G. Overhead, Contingencies and Miscellaneous 12% per D.O. 197, s. 2016

H. Contractor's Profit(CP) 8% per D.O. 197, s. 2016

I. Value Added Tax (VAT) 5% per D.O. 197, s. 2016

J. Total Unit Cost

960.00

Designation No. of Persons No. of Days Daily Rate Amount

0.28 m. thk.

1 2.09 611.92 1,277.05

4 2.09 443.20 3,699.76

12 2.09 342.24 8,570.88

Sub-total for A 13,547.69

Name and CapacityNo. of

EquipmentNo. of Days Daily Rate Amount

4 2.09 10,544.00 88,019.48

Concrete Vibrator 2 2.09 730.00 3,046.96

Concrete Batch Plant (30 cu.m.) 1 2.09 14,076.00 29,376.00

Payloader (1.50 cu.m.), LX80-2C 1 2.09 13,864.00 28,933.57

Concrete Screeder (5.5 hp) 1 2.09 4,360.00 9,099.13

1 2.09 19,600.00 40,904.35

1 2.09 261.04 544.78

1 0.21 1,758.00 366.89

677.38

Sub-total for B 200,968.53

Total (A+B) 214,516.22

Output/day 460.00 sq.m./day

Name and Specifications Quantity Unit Unit Cost Amount

480.00 kg. 38.00 18,240.00

Curing Compound 278.40 L 35.00 9,744.00

163.20 L 100.00 16,320.00

Steel Forms (Rental) 441.60 m 60.00 26,496.00

Sand 147.84 cu.m. 1,504.50 222,425.28

Gravel 268.80 cu.m. 1,504.50 404,409.60

Cement 2,553.60 bag 273.00 697,132.80

Concrete Saw (Diamond Blade 14" Ø) 0.14 pc. 8,000.00 1,152.00

Pipe Sleeve, 2" Ø 7.49 m. 101.67 761.28

Grease/Tar 7.49 L 112.50 842.40

Sub-total for E 1,397,523.36

1,612,039.58

193,444.75

128,963.17

96,722.37

2,115.80

DETAILED UNIT PRICE ANALYSIS

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy.

Vitali, Zamboanga City,

57.50

Page 5: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

PROJECT NAME:

Item No./Description: 103(2)a Bridge Excavation Above Ordinary Water Level

Unit of Measurement: cu.m.

Output per hour:

Quantity:

A. Labor

a. Const. Foreman

b. Skilled Labor

c. Unskilled Labor

P

B. Equipment, (2014 ACEL Rates)

a. Backhoe (0.80 cu.m.)

b.

Minor Tools 10% of Labor

P

C.

D.

E. Materials

P

F. Direct Cost (C + E)

G. Overhead, Contingencies and Miscellaneous 12% per D.O. 197, s. 2016

H. Contractor's Profit(CP) 8% per D.O. 197, s. 2016

I. Value Added Tax (VAT) 5% per D.O. 197, s. 2016

J. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy.

Vitali, Zamboanga City,

20.00

428.72

Designation No. of Persons No. of Days Daily Rate Amount

1 2.68 611.92 1,639.64

1 2.68 443.20 1,187.55

2 2.68 342.24 1,834.06

Sub-total for A 4,661.26

Name and CapacityNo. of

EquipmentNo. of Days Daily Rate Amount

1 2.68 12,296.00 32,947.13

Dump Truck (12 cu.yd.) 2 2.68 11,360.00 60,878.24

466.13

Sub-total for B 94,291.50

Total (A+B) 98,952.76

Output/day 160.00 sq.m./day

Name and Specifications Quantity Unit Unit Cost Amount

98,952.76

290.82

Sub-total for E -

11,874.33

7,916.22

5,937.17

Page 6: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

PROJECT NAME:

Item No./Description: 103(2)b Bridge Excavation Below Ordinary Water Level

Unit of Measurement: cu.m.

Output per hour:

Quantity:

A. Labor

a. Const. Foreman

b. Skilled Labor

c. Unskilled Labor

P

B. Equipment, (2014 ACEL Rates)

a. Backhoe (0.80 cu.m.)

b.

Minor Tools 10% of Labor

P

C.

D.

E. Materials

P

F. Direct Cost (C + E)

G. Overhead, Contingencies and Miscellaneous 12% per D.O. 197, s. 2016

H. Contractor's Profit(CP) 8% per D.O. 197, s. 2016

I. Value Added Tax (VAT) 5% per D.O. 197, s. 2016

J. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy.

Vitali, Zamboanga City,

20.00

686.00

Designation No. of Persons No. of Days Daily Rate Amount

1 4.29 611.92 2,623.61

1 4.29 443.20 1,900.22

2 4.29 342.24 2,934.71

Sub-total for A

Name and CapacityNo. of

EquipmentNo. of Days Daily Rate Amount

1 4.29 12,296.00 52,719.10

Dump Truck (12 cu.yd.) 2 4.29 11,360.00 97,412.00

745.85

Sub-total for B

Total (A+B) 158,335.49

Output/day 160.00

Name and Specifications Quantity Unit Unit Cost Amount

Sub-total for E

12,666.84

9,500.13

290.82

7,458.54

150,876.95

sq.m./day

158,335.49

-

19,000.26

Page 7: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

PROJECT NAME:

Item No./Description: 400(4)a Precast Concrete Piles, Furnished

Unit of Measurement: ln.m.

Output per hour:

Quantity:

A. Labor

a. Const. Foreman

b. Skilled Labor

c. Unskilled Labor

Formworks

a. Skilled Labor

b. Unskilled Labor

P

B. Equipment, (2014 ACEL Rates)

a. Concrete Vibrator

b.

c. Bar Bender

d.

Minor Tools 10% of Labor

P

C.

D.

E. Materials

a. Ready Mix Concrete

b.

c. #16 G.I. Tie Wire (2% of RSB)

d.

e.

f.

Casting Bed

a.

b.

c. Base Course (Crushed, Grading A)

P

F. Direct Cost (C + E)

G. Overhead, Contingencies and Miscellaneous 12% per D.O. 197, s. 2016

H. Contractor's Profit(CP) 8% per D.O. 197, s. 2016

I. Value Added Tax (VAT) 5% per D.O. 197, s. 2016

J. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy.

Vitali, Zamboanga City,

8.75

16.00 meters/pile1,596.00

Designation No. of Persons No. of Days Daily Rate Amount

1 22.80 611.92 13,951.78

4 22.80 443.20 40,419.84

8 22.80 342.24 62,424.58

Sub-total for A

Name and CapacityNo. of

EquipmentNo. of Days Daily Rate Amount

Plate Compactor 1 4.56 984.00 4,487.04

25,645.44

47.88

266.53

1 4.56 730.00 3,328.80

342.24

1 9.12 2,812.00

4

Bar Cutter 1 9.12

Sub-total for B

Total (A+B)

8

16,032.96

68.40 443.20 121,259.52

187,273.73

Output/day 70.00

1,758.00

68.40

92,027.18

sq.m./day

Name and Specifications Quantity Unit Unit Cost Amount

517,356.62

4,530.00 1,207,389.96

Reinforcing Steel Bar 76,608.00 kg. 38.00 2,911,104.00

cu.m.

kg. 78.00 119,508.48

Forms 24,471.47 bd.ft. 37.00 905,444.32

Plywood Marine 427.73 pc. 880.00 376,400.64

Sub-total for E

cu.m. 1,042.10 49,895.75

Assorted CWN (1 kg./100 bd.ft. of Lumber)

Ready Mix Concrete

42,532.94

425,329.44

268.13 kg. 50.00 13,406.40

1,532.16

47.88 cu.m. 4,200.00 201,096.00

Coco Lumber 2,394.00 bd.ft. 15.00 35,910.00

5,820,155.54

6,337,512.17

760,501.46

507,000.97

380,250.73

5,003.30

Page 8: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

PROJECT NAME:

Item No./Description: 400(6) Structural Steel Sheet Piles, Furnished

Unit of Measurement: ln.m.

Output per hour:

Quantity:

A. Labor

a. Const. Foreman

b. Skilled Labor

c. Unskilled Labor

P

B. Equipment, (2014 ACEL Rates)

a. Truck Mounted Crane (45 T)

P

C.

D.

E. Materials

a. Steel Sheet Piles KSP II (deliverd at site)

P

F. Direct Cost (C + E)

G. Overhead, Contingencies and Miscellaneous 12% per D.O. 197, s. 2016

H. Contractor's Profit(CP) 8% per D.O. 197, s. 2016

I. Value Added Tax (VAT) 5% per D.O. 197, s. 2016

J. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy.

Vitali, Zamboanga City,

48.00 6.00 m./pile; width = 0.40 m. for Scour

Protection & Cofferdam1,008.00

Designation No. of Persons No. of Days Daily Rate Amount

1 2.63 611.92 1,606.29

2 2.63 443.20 2,326.80

2 2.63 342.24 1,796.76

Sub-total for A 5,729.85

Name and CapacityNo. of

EquipmentNo. of Days Daily Rate Amount

1 2.63 20,848.00 54,726.00

Sub-total for B 54,726.00

Total (A+B) 60,455.85

Output/day 384.00 ln.m./day

Name and Specifications Quantity Unit Unit Cost Amount

48,384.00 kg. 50.00 2,419,200.00

Sub-total for E 2,419,200.00

2,479,655.85

297,558.70

198,372.47

148,779.35

3,099.57

Page 9: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

PROJECT NAME:

Item No./Description: 400(12) Structural Steel Sheet Piles, Driven

Unit of Measurement: ln.m.

Output per hour:

Quantity:

A. Labor

a. Const. Foreman

b. Skilled Labor

c. Unskilled Labor

P

B. Equipment, (2014 ACEL Rates)

a. Truck Mounted Crane (45 T)

b.

c. Gen. Set (876-1000 KVA)

d.

e.

P

C.

D.

E. Materials

a. Welding Rod (1 kg./2000 kg. of Steel Sheet Pile)

b.

P

F. Direct Cost (C + E)

G. Overhead, Contingencies and Miscellaneous 12% per D.O. 197, s. 2016

H. Contractor's Profit(CP) 8% per D.O. 197, s. 2016

I. Value Added Tax (VAT) 5% per D.O. 197, s. 2016

J. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy.

Vitali, Zamboanga City,

10.00 6.00 m./pile; width = 0.40 m. for Scour

Protection & Cofferdam1,008.00

Designation No. of Persons No. of Days Daily Rate Amount

1 12.60 611.92 7,710.19

6 12.60 443.20 33,505.92

6 12.60 342.24 25,873.34

Sub-total for A 67,089.46

Name and CapacityNo. of

EquipmentNo. of Days Daily Rate Amount

1 12.60 20,848.00 262,684.80

Vibro Hammer 1 12.60 16,984.00 213,998.40

1 12.60 10,373.36 130,704.34

Welding Machine 1 12.60 2,968.00 37,396.80

6.30 363.60 2,290.68

Sub-total for B 647,075.02

Total (A+B) 714,164.47

Cutting Outfit 1

Output/day 80.00 ln.m./day

Name and Specifications Quantity Unit Unit Cost Amount

24.19 kg. 150.00 3,628.80

Oxy/Acetylene (1 set/5000 kg. of Steel Sheet Pile) 9.68 set 2,500.00 24,192.00

Sub-total for E 27,820.80

741,985.27

89,038.23

59,358.82

44,519.12

927.48

Page 10: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

PROJECT NAME:

Item No./Description: 400(14) Precast Concrete Piles, Driven

Unit of Measurement: ln.m.

Output per hour:

Quantity:

A. Labor

a. Const. Foreman

b. Leadman

c. Skilled Labor

d. Unskilled Labor

P

B. Equipment, (2014 ACEL Rates)

a. Truck Mounted Crane (45 T)

b.

c. Drop Hammer

d.

e.

f. Air Compressor (103 Hp)

Minor Tools 10% of Labor

P

C.

D.

E. Materials

a. Coco Log

b.

c. Nail/Spike (1 kg./100 bd.ft. of Lumber)

d.

P

F. Direct Cost (C + E)

G. Overhead, Contingencies and Miscellaneous 12% per D.O. 197, s. 2016

H. Contractor's Profit(CP) 8% per D.O. 197, s. 2016

I. Value Added Tax (VAT) 5% per D.O. 197, s. 2016

J. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy.

Vitali, Zamboanga City,

4.80

15.00 m./pile1,520.00

Designation No. of Persons No. of Days Daily Rate Amount

1 39.58 611.92 24,221.83

10 39.58 443.20 175,433.33

2 39.58

10 39.58 342.24 135,470.00

Sub-total for A 379,566.17

Name and CapacityNo. of

EquipmentNo. of Days Daily Rate Amount

2 20.98 20,848.00 874,747.33

Diesel Hammer (K25 or equivalent) 2 10.69 9,992.00 213,579.00

2 5.15 1,600.00 16,466.67

Cutting Outfit 2 7.92 363.60 5,757.00

Jack Hammer 4 7.92 1,200.00 38,000.00

2

Sub-total for B 1,270,783.33

Total (A+B) 1,650,349.50

Output/day 38.40 ln.m./day

Name and Specifications Quantity Unit Unit Cost Amount

1,520.00 m. 350.00 532,000.00

Good Lumber (Falsework) 24,320.00 bd.ft. 37.00 899,840.00

243.20 kg. 68.00 16,537.60

Oxygen/Acytelene 15.20 set 2,500.00 38,000.00

7.92 7,720.00 122,233.33

Sub-total for E 1,486,377.60

3,136,727.10

376,407.25

250,938.17

188,203.63

2,600.18

561.36 44,441.00

Page 11: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

PROJECT NAME:

Item No./Description: 400(16) Test Piles, Furnished and Driven (400 mm. x 400 mm.)

Unit of Measurement: ln.m.

Output per hour:

Quantity:

A. Labor

a. Const. Foreman

b. Skilled Labor

c. Unskilled Labor

P

B. Equipment, (2014 ACEL Rates)

a. Truck Mounted Crane (45 T)

b.

c. Drop Hammer

d.

e.

f. Air Compressor (103 Hp)

Minor Tools 10% of Labor

P

C.

D.

E. Materials

a. Coco Log

b.

c. Nail/Spike (1 kg./100 bd.ft. of Lumber)

d.

e.

P

F. Direct Cost (C + E)

G. Overhead, Contingencies and Miscellaneous 12% per D.O. 197, s. 2016

H. Contractor's Profit(CP) 8% per D.O. 197, s. 2016

I. Value Added Tax (VAT) 5% per D.O. 197, s. 2016

J. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

84.00

Designation No. of Persons No. of Days Daily Rate Amount

1 1.75 611.92 1,070.86

6 1.75 443.20 4,653.60

6 1.75 342.24 3,593.52

Sub-total for A 9,317.98

Name and CapacityNo. of

EquipmentNo. of Days Daily Rate Amount

1 0.93 20,848.00 19,336.52

Diesel Hammer (K25 or equivalent) 1 0.47 9,992.00 4,721.22

1 0.23 1,600.00 364.00

Cutting Outfit 1 0.35 363.60 127.26

Jack Hammer 2 0.35 1,200.00 840.00

1 0.35 7,720.00 2,702.00

Sub-total for B 28,091.00

Total (A+B) 37,408.98

Output/day 48.00 ln.m./day

Name and Specifications Quantity Unit Unit Cost Amount

142.80 m. 350.00 49,980.00

Lumber (Falsework) 1,344.00 bd.ft. 37.00 49,728.00

13.44 kg. 68.00 913.92

Oxygen/Acytelene 4.20 set 2,500.00 10,500.00

Fabricated R.C. Pile 84.00 m. 2,520.00 211,680.00

Sub-total for E 322,801.92

360,210.90

43,225.31

28,816.87

21,612.65

5,403.16

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy.

Vitali, Zamboanga City,

6.00

16 m./pile

Page 12: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

PROJECT NAME:

Item No./Description: 401(2) Concrete Railing

Unit of Measurement: ln.m.

Output per hour:

Quantity:

A. Labor

a. Const. Foreman

b. Skilled Labor

c. Unskilled Labor

P

B. Equipment, (2014 ACEL Rates)

a. Concrete Vibrator

b.

c. Bar Bender

d.

Minor Tools 10% of Labor

P

C.

D.

E. Materials

a. Ready Mix Concrete

b.

c. Plywood 1/2" x 4' x 8'

d.

e.

f.

g.

P

F. Direct Cost (C + E)

G. Overhead, Contingencies and Miscellaneous 12% per D.O. 197, s. 2016

H. Contractor's Profit(CP) 8% per D.O. 197, s. 2016

I. Value Added Tax (VAT) 5% per D.O. 197, s. 2016

J. Total Unit Cost

101.00

Designation No. of Persons No. of Days Daily Rate Amount

1 20.20 611.92 12,360.78

2 20.20 443.20 17,905.28

4 20.20 342.24 27,652.99

Sub-total for A 57,919.06

Daily Rate Amount

1 5.05 730.00 3,686.50

Bar Cutter 1 2.53 1,758.00 4,438.95

1 2.53 2,812.00 7,100.30

Cutting Outfit 1 0.51 363.60 183.62

5,791.91

ln.m./day

Name and Specifications Quantity Unit Unit Cost Amount

Sub-total for B 21,201.27

Total (A+B)

79,152.69

Reinforcing Stee Bar 2,504.80 kg. 38.00

79,120.33

Output/day 5.00

95,182.40

4,530.00

750.00 45,450.00

17.47 cu.m.

60.60 pc.

Name and CapacityNo. of

EquipmentNo. of Days

50.10 kg. 78.00 3,907.49

Lumber 2,626.00 bd.ft. 37.00 97,162.00

Assorted CWN (1 kg./100 bd.ft. of Lumber) 26.26 kg. 50.00 1,313.00

Tie Wire (2% of RSB)

Oxy/Acetylene (1 set/5000 kg. of steel) 0.51 set 2,500.00 1,262.50

Sub-total for E 323,430.08

5,021.92

DETAILED UNIT PRICE ANALYSIS

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy.

Vitali, Zamboanga City,

0.63

48,306.05

32,204.03

24,153.02

402,550.41

Page 13: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

PROJECT NAME:

Item No./Description: 402(1) Timber Structures for Craneway

Unit of Measurement: span

Output per hour:

Quantity:

A. Labor

a. Const. Foreman

b. Skilled Labor

c. Unskilled Labor

P

B. Equipment, (2014 ACEL Rates)

a. Truck Mounted Crane

b.

c. Cargo Truck

Minor Tools 10% of Labor

P

C.

D.

E. Materials

a. Coco Trunks

b.

c. 25 mm. dia. x 400 mm. Machine Bolt w/

d.

P

F. Direct Cost (C + E)

G. Overhead, Contingencies and Miscellaneous 12% per D.O. 197, s. 2016

H. Contractor's Profit(CP) 8% per D.O. 197, s. 2016

I. Value Added Tax (VAT) 5% per D.O. 197, s. 2016

J. Total Unit Cost

Amount

1 41.00 611.92

DETAILED UNIT PRICE ANALYSIS

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy.

Vitali, Zamboanga City,

7.00 meters/span8.00

Designation No. of Persons No. of Days Daily Rate

25,088.72

6 41.00 443.20 109,027.20

6 41.00 342.24 84,191.04

Sub-total for A 218,306.96

Name and CapacityNo. of

EquipmentNo. of Days Daily Rate Amount

1 41.00 20,848.00 854,768.00

Drop Hammer 1 3.40 1,600.00 5,444.80

1 3.40 9,696.00 32,995.49

21,830.70

Sub-total for B 915,038.98

Total (A+B) 1,133,345.94

Output/day - span/day

Name and Specifications Quantity Unit Unit Cost Amount

350.00 pc. 950.00 332,500.00

Coco Lumber - Floor Planks and Running Board 30,000.00 bd.ft. 15.00 450,000.00

200.00 kg. 150.00 30,000.00

standard nuts and washer

25 mm. dia. Steel Bar 1,200.00 kg. 44.00 52,800.00

Sub-total for E 865,300.00

1,998,645.94

239,837.51

159,891.68

119,918.76

314,786.74

Page 14: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

PROJECT NAME:

Item No./Description: 404a Reinforcing Steel, Grade 40

Unit of Measurement: kg.

Output per hour:

Quantity:

A. Labor

a. Const. Foreman

b. Skilled Labor

c. Unskilled Labor

P

B. Equipment, (2014 ACEL Rates)

a. Service Crane (25 T, 145 Hp)

b.

c. Bar Cutter

d. Bar Bender

P

C.

D.

E. Materials

a. Tie Wire (2% of RSB)

b.

(with 5% wastage)

P

F. Direct Cost (C + E)

G. Overhead, Contingencies and Miscellaneous 12% per D.O. 197, s. 2016

H. Contractor's Profit(CP) 8% per D.O. 197, s. 2016

I. Value Added Tax (VAT) 5% per D.O. 197, s. 2016

J. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy.

Vitali, Zamboanga City,

180.00

3,356.80

Designation No. of Persons No. of Days Daily Rate Amount

1 2.33 611.92 1,426.45

2 2.33 443.20 2,066.30

8 2.33 342.24 6,382.40

Sub-total for A 9,875.15

Name and CapacityNo. of

EquipmentNo. of Days Daily Rate Amount

1 0.35 11,072.00 3,871.51

Cargo Truck (10 T, 270 Hp) 1 0.35 9,696.00 3,390.37

1 1.17 1,758.00 2,049.05

1 1.17 2,812.00 3,277.54

Sub-total for B 12,588.47

Quantity Unit Unit Cost Amount

3,524.64 kg. 38.00 133,936.32

Total (A+B) 22,463.61

Output/day 1,440.00 kg./day

Name and Specifications

70.49 kg. 78.00 5,498.44

Reinforcing Steel Bar, Grade 40

Sub-total for E 139,434.76

161,898.37

19,427.80

12,951.87

9,713.90

60.77

Page 15: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

PROJECT NAME:

Item No./Description: 404b Reinforcing Steel, Grade 60

Unit of Measurement: kg.

Output per hour:

Quantity:

A. Labor

a. Const. Foreman

b. Leadman

c. Skilled Labor

d. Unskilled Labor

P

B. Equipment, (2014 ACEL Rates)

a. Service Crane (25 T, 145 Hp)

b.

c. Bar Cutter

d. Bar Bender

P

C.

D.

E. Materials

a. Tie Wire (2% of RSB)

b.

(with 5% wastage)

P

F. Direct Cost (C + E)

G. Overhead, Contingencies and Miscellaneous 12% per D.O. 197, s. 2016

H. Contractor's Profit(CP) 8% per D.O. 197, s. 2016

I. Value Added Tax (VAT) 5% per D.O. 197, s. 2016

J. Total Unit Cost

4,842,952.39

581,154.29

387,436.19

290,577.14

64.72

use double gang of labor and equipment

Sub-total for E 4,114,331.59

1,979.95 kg. 78.00 154,435.93

Reinforcing Steel Bar, Grade 60 98,997.39 kg. 40.00 3,959,895.66

Total (A+B) 728,620.80

Output/day 2,560.00 kg./day

Name and Specifications Quantity Unit Unit Cost Amount

Sub-total for B 397,772.11

2 18.41 1,758.00 64,746.06

2 18.41 2,812.00 103,564.24

2 5.52 11,072.00 122,332.49

Cargo Truck (10 T, 270 Hp) 2 5.52 9,696.00 107,129.32

Sub-total for A 330,848.69

Name and CapacityNo. of

EquipmentNo. of Days Daily Rate Amount

16 36.83 342.24 201,671.83

4 36.83 443.20 65,291.14

2 36.83 561.36 41,349.09

Designation No. of Persons No. of Days Daily Rate Amount

1 36.83 611.92 22,536.64

94,283.23

DETAILED UNIT PRICE ANALYSIS

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy.

Vitali, Zamboanga City,

320.00

Page 16: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

PROJECT NAME:

Item No./Description: 405(1)b2 Structural Concrete, Class "A"

Unit of Measurement: cu.m.

Output per hour:

Quantity:

A. Labor

a. Const. Foreman

b. Leadman

c. Skilled Labor

d. Unskilled Labor

Installation & Removal of Formworks/Falsework

a. Const. Foreman

b. Leadman

c. Skilled Labor

d. Unskilled Labor

P

B. Equipment, (2014 ACEL Rates)

a. Transit Mixer (5 cu.m.)

b.

c. Batching Plant (30 cu.m.)

d. Payloader (1.50 cu.m.), LX80-2C

e. Water Truck (1000 gal.)

f. Crane w/ Bucket

P

C.

D.

E. Materials

a. Lumber, Coco

b.

c. Assorted CWN (1 kg./100 bd.ft. of Lumber)

d.

e.

f.

g.

P

F. Direct Cost (C + E)

G. Overhead, Contingencies and Miscellaneous 12% per D.O. 197, s. 2016

H. Contractor's Profit(CP) 8% per D.O. 197, s. 2016

I. Value Added Tax (VAT) 5% per D.O. 197, s. 2016

J. Total Unit Cost

use triple gang of labor and equipment

2.58 561.36 4,341.42

3 51.56

12,431.46

12 51.56 443.20 274,207.84

6,104,242.07

732,509.05

488,339.37

366,254.52

3

3 1.29 20,848.00 80,616.61

Sub-total for E 4,846,431.78

Gravel 618.70 cu.m. 1,504.50 930,834.15

Curing Compound 618.70 lit. 35.00 21,654.50

Cement 6,496.35 bag 273.00 1,773,503.55

Sand 309.35 cu.m. 1,504.50 465,417.08

Plywood (1/2" x 4' x 8') 928.05 pc. 750.00 696,037.50

618.70 kg. 50.00 30,935.00

Name and Specifications Quantity Unit Unit Cost Amount

61,870.00 bd.ft. 15.00 928,050.00

Sub-total for B 400,933.07

Total (A+B) 1,257,810.29

Output/day 240.00 cu.m./day

3 1.29 13,864.00 53,610.36

3 0.64 19,600.00 37,895.38

Concrete Vibrator 6 2.58 730.00 11,291.28

3 1.29 14,076.00 54,430.13

Name and CapacityNo. of

EquipmentNo. of Days Daily Rate Amount

6 2.58 10,544.00 163,089.32

Sub-total for A 856,877.23

611.92 31,549.58

24 51.56 342.24 423,487.78

561.36 86,828.36

1 51.56

12 2.58 443.20 13,710.39

24 2.58 342.24 21,174.39

Designation No. of Persons No. of Days Daily Rate Amount

1 2.58 611.92 1,577.48

DETAILED UNIT PRICE ANALYSIS

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy.

Vitali, Zamboanga City,

30.00

618.70

Page 17: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

PROJECT NAME:

Item No./Description: 406(1)a4 Prestressed Concrete AASHTO Girder (Type IV-B)

Unit of Measurement: ln.m.

Output per hour:

Quantity:

A. Labor

a. Const. Foreman

b. Skilled Labor

c. Unskilled Labor

P

B. Equipment, (2014 ACEL Rates)

a. Truck Mounted Crane w/ Bucket (45 T)

b.

c. Bar Cutter

d. Bar Bender

e. Cutting Outfit

f. Concrete Vibrator

g. Plate Compactor

P

C.

D.

E. Materials

a. Prestressed Concrete AASHTO Girder

P

F. Direct Cost (C + E)

G. Overhead, Contingencies and Miscellaneous 12% per D.O. 197, s. 2016

H. Contractor's Profit(CP) 8% per D.O. 197, s. 2016

I. Value Added Tax (VAT) 5% per D.O. 197, s. 2016

J. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy.

Vitali, Zamboanga City,

35.00 Prestressed Concrete AASHTO Girder (Type

IV-B)202.00

Designation No. of Persons No. of Days Daily Rate Amount

1 60.60 611.92 37,082.35

8 60.60 443.20 214,863.36

6 60.60 342.24 124,438.46

Sub-total for A 376,384.18

Name and CapacityNo. of

EquipmentNo. of Days Daily Rate Amount

1 25.25 20,848.00 526,412.00

Stressing (Jack) Machine 1 2.16 80,000.00 173,142.86

1 7.94 1,758.00 13,950.99

1 7.94 2,812.00 22,315.23

1 0.46 363.60 167.88

3 8.66 730.00 18,959.14

Sub-total for B 757,432.69

Total (A+B) 1,133,816.87

Output/day 280.00 ln.m./day

Name and Specifications Quantity Unit Unit Cost Amount

202.00 ln.m. 24,000.00 4,848,000.00

Type IVB

Sub-total for E 4,848,000.00

358,909.01

37,312.32

984.00 2,484.60 1 2.53

5,981,816.87

717,818.02

478,545.35

Page 18: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

PROJECT NAME:

Item No./Description: 407(8) Lean Concrete

Unit of Measurement: cu.m.

Output per hour:

Quantity:

A. Labor

a. Const. Foreman

b. Skilled Labor

c. Unskilled Labor

P

B. Equipment, (2014 ACEL Rates)

a. One Bagger Mixer

b.

c. Water Truck

P

C.

D.

E. Materials

a. Portland Cement

b.

c. Gravel

P

F. Direct Cost (C + E)

G. Overhead, Contingencies and Miscellaneous 12% per D.O. 197, s. 2016

H. Contractor's Profit(CP) 8% per D.O. 197, s. 2016

I. Value Added Tax (VAT) 5% per D.O. 197, s. 2016

J. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy.

Vitali, Zamboanga City,

1.40

17.01

Designation No. of Persons No. of Days Daily Rate Amount

1 1.52 611.92 929.35

1 1.52 443.20 673.11

2 1.52 342.24 1,039.55

Sub-total for A 2,642.02

Name and CapacityNo. of

EquipmentNo. of Days Daily Rate Amount

1 1.52 1,376.00 2,089.80

Concrete Vibrator 1 1.52 730.00 1,108.69

1 0.15 19,600.00 2,976.75

Sub-total for B 6,175.24

Total (A+B) 8,817.26

Output/day 11.20 kg./day

Name and Specifications Quantity Unit Unit Cost Amount

161.60 bag 273.00 44,115.44

Sand 8.51 cu.m. 1,504.50 12,795.77

17.01 cu.m. 1,504.50 25,591.55

Sub-total for E 82,502.75

91,320.01

10,958.40

7,305.60

5,479.20

6,764.45

Page 19: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

PROJECT NAME:

Item No./Description: 412 Elastomeric Bearing Pad

Unit of Measurement: each

Output per hour:

Quantity:

A. Labor

a. Const. Foreman

b. Unskilled Labor

P

B. Equipment, (2014 ACEL Rates)

a. Wood/Steel Ladder

P

C.

D.

E. Materials

a. Elastomeric Bearing Pad

Miscellaneous 10% of Labor

P

F. Direct Cost (C + E)

G. Overhead, Contingencies and Miscellaneous 12% per D.O. 197, s. 2016

H. Contractor's Profit(CP) 8% per D.O. 197, s. 2016

I. Value Added Tax (VAT) 5% per D.O. 197, s. 2016

J. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy.

Vitali, Zamboanga City,

1.00

24.00

Designation No. of Persons No. of Days Daily Rate Amount

1 0.48 611.92 293.72

2 0.48 342.24 328.55

Sub-total for A 622.27

Name and CapacityNo. of

EquipmentNo. of Days Daily Rate Amount

1 3.00 800.00 2,400.00

Sub-total for B 2,400.00

Total (A+B) 3,022.27

Output/day 8.00 kg./day

Name and Specifications Quantity Unit Unit Cost Amount

24.00 each 16,150.00 387,600.00

62.23

Sub-total for E 387,662.23

390,684.50

46,882.14

31,254.76

23,441.07

20,510.94

Page 20: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

PROJECT NAME:

Item No./Description: 414 Forms and Falsework

Unit of Measurement: L.S.

Output per hour:

Quantity:

A. Labor

a. Const. Foreman

b. Skilled Labor

c. Unskilled Labor

P

B. Equipment, (2014 ACEL Rates)

a. Cutting Outfit

Minor Tools 10% of Labor

P

C.

D.

E. Materials

a. 63 mm. dia. G.I. Pipes

b. 63 mm. dia. C-Clamps

c. #16 G.I. Tie Wire

d.

P

F. Direct Cost (C + E)

G. Overhead, Contingencies and Miscellaneous 12% per D.O. 197, s. 2016

H. Contractor's Profit(CP) 8% per D.O. 197, s. 2016

I. Value Added Tax (VAT) 5% per D.O. 197, s. 2016

J. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy.

Vitali, Zamboanga City,

1.00

Designation No. of Persons No. of Days Daily Rate Amount

1 15.00 611.92 9,178.80

6 15.00 443.20 39,888.00

6 15.00 342.24 30,801.60

Sub-total for A 79,868.40

Name and CapacityNo. of

EquipmentNo. of Days Daily Rate Amount

1 5.00 363.60 1,818.00

7,986.84

1,508,000.00

Sub-total for B 9,804.84

Total (A+B) 89,673.24

Output/day -

78.00 2,340.00

Name and Specifications Quantity Unit Unit Cost Amount

800.00 pc. 1,885.00

2,000.00 pc. 54.00 108,000.00

30.00 kg.

Oxy/Acetylene 3.00 set 2,500.00 7,500.00

1,625,840.00

1,715,513.24

205,861.59

137,241.06

102,930.79

2,161,546.68

Sub-total for E

Page 21: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

PROJECT NAME:

Item No./Description: 505(5) Grouted Riprap, Class A

Unit of Measurement: cu.m.

Output per hour:

Quantity:

A. Labor

a. Const. Foreman

b. Leadman

c. Skilled Labor

d. Unskilled Labor

P

B. Equipment, (2014 ACEL Rates)

a. One Bagger Mixer

b.

Minor Tools 5% of Labor

P

C.

D.

E. Materials

a. Cement

b. Sand

c. Gravel

d.

e.

f.

Miscellaneous 1% of Materials Cost

P

F. Direct Cost (C + E)

G. Overhead, Contingencies and Miscellaneous 12% per D.O. 197, s. 2016

H. Contractor's Profit(CP) 8% per D.O. 197, s. 2016

I. Value Added Tax (VAT) 5% per D.O. 197, s. 2016

J. Total Unit Cost

6 21.34

use triple gang of labor and equipment

DETAILED UNIT PRICE ANALYSIS

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy.

Vitali, Zamboanga City,

3.75

443.20 56,748.21

Daily Rate Amount

611.92

21.34

13,058.58

640.21

Designation No. of Persons No. of Days

21.34

1 21.34

For Slope Protection & Headwall apron

3

342.24 175,284.38 24

561.36 35,938.83

281,030.00

Name and CapacityNo. of

EquipmentNo. of Days Daily Rate Amount

Sub-total for A

3 21.34 1,376.00 88,092.90

Water Truck/Pump (16000 L) 3 1.07 19,600.00 62,740.58

14,051.50

Unit Cost Amount

Sub-total for B 164,884.98

1,504.50 240,798.99

Total (A+B) 445,914.97

Output/day 30.00 cu.m./day

Name and Specifications Quantity Unit

192.06 m.

1,920.63 bag 273.00 524,331.99

160.05 cu.m.

9.60 cu.m. 1,504.50 14,447.94

Weep Holes (PVC) 101.67 19,526.41

Filter Cloth 9.60 sq.m. 160.00 1,536.50

Boulders (15 - 25 kg.) 672.22 cu.m. 1,703.50 1,145,127.62

19,457.69

Sub-total for E 1,965,227.14

144,668.53

4,745.38

2,411,142.11

289,337.05

192,891.37

Page 22: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

PROJECT NAME:

Item No./Description: 612(1) Reflectorized Thermoplastic Pavement Markings (White)

Unit of Measurement: sq.m.

Output per hour:

Quantity:

A. Labor

a. Const. Foreman

b. Skilled Labor

c. Unskilled Labor

P

B. Equipment, (2014 ACEL Rates)

a. Cargo Truck/Delivery Truck (2-5 mt)

b.

c.

Minor Tools 10% of Labor

P

C.

D.

E. Materials

a. Thermoplastic Paint (White)

b.

c. Primer

d.

e.

f.

Miscellaneous 5% of Materials Cost

P

F. Direct Cost (C + E)

G. Overhead, Contingencies and Miscellaneous 12% per D.O. 197, s. 2016

H. Contractor's Profit(CP) 8% per D.O. 197, s. 2016

I. Value Added Tax (VAT) 5% per D.O. 197, s. 2016

J. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy.

Vitali, Zamboanga City,

25.00

100.00

Designation No. of Persons No. of Days Daily Rate Amount

1 0.50 611.92 305.96

For Center Lines (Separation) & Edge Lines

2 0.50 443.20 443.20

6 0.50 342.24 1,026.72

Sub-total for A 1,775.88

Name and CapacityNo. of

EquipmentNo. of Days Daily Rate Amount

1 0.50 6,264.00 3,132.00

Applicator Machine 1 0.50 750.00 375.00

Kneading Machine 1 0.50 1,500.00 750.00

177.59

1,585.00 51,512.50

Sub-total for B 4,434.59

Total (A+B) 6,210.47

Output/day 200.00 sq.m./day

L 160.00 1,920.00

Name and Specifications Quantity Unit Unit Cost Amount

32.50 bag

0.20 cyl. 828.00 165.60

Glass Beads 3.30 bag 2,500.00 8,250.00

12.00

3,180.16

LPG (50 kg) 0.40 cyl. 3,450.00 1,380.00

LPG (12 kg)

Calsumine 12.50 kg. 30.00 375.00

5,839.50

919.72

66,783.26

8,759.25

4,379.62

Sub-total for E

72,993.72

Page 23: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

PROJECT NAME:

Item No./Description: A.1.1(3) Construction of Field Office for the Engineer

Unit of Measurement: L.S.

Output per hour:

Quantity:

A. Labor

a. Const. Foreman

b. Mason

c. Carpenter

d. Laborer

P

B. Equipment, (2014 ACEL Rates)

a. One Bagger Mixer

b.

Minor Tools 10% of Labor

P

C.

D.

E. Materials

I. Earthworks (Excavation, Embankment, Bedding)

a. Gravel Bedding

b. Selected Fill

c. Soil Poisoning

II. Concrete Works (Footing, Columns, Beams & Slab on Grade)

a. Portland Cement

b. Crushed Gravel

c. Washed Sand

III. Reinforcing Bars(Footing Columns, Beams, & Slabs on Grade)

a. Deformed Round Bar, Grade 40

b. No. 16 GI Tie Wire

IV. Formworks (Columns & Beams)

a. Coco Lumber

b. Ordinary Plywood, 1/4"x4'x8'

c. CWN, Assorted

V. Masonry Works (masonry walls & plastering)

a. CHB 6" thk

b. Portland Cement

c. Washed Sand

d. 10mm dia. X 6m RSB

e. No. 16 GI Tie Wire

VI. Doors and Windows

a.

b. W-1, Jalousie window, 1.4m x 1.2m

c. W-2, Jalousie window, 2.8m x 1.2m

P

P

F. Direct Cost (C + E)

G. Overhead, Contingencies and Miscellaneous 12% per D.O. 197, s. 2016

H. Contractor's Profit(CP) 8% per D.O. 197, s. 2016

I. Value Added Tax (VAT) 5% per D.O. 197, s. 2016

J. Total Unit Cost

175,478.77

D-1, Hollow Core Flush Type swing door,

complete w/ accessories, 0.90mx2.1m

1,848.00

10,400.00

12,285.00

12,036.00

2,470.00

195.00

1,560.00

6,000.00

6,930.00

250.00

78.00

4,487.00

4,750.00

24,570.00

31,594.50

27,081.00

16,530.00

50.00

16.00

273.00

1,504.50

38.00

38.00

78.00

15.00

385.00

448.70

1,900.00

273.00

1,504.50

1,504.50

bd.ft.

pc.

kg.

pc.

bag

cu.m.

cu.m.

L

bag

cu.m.

cu.m.

kg.

10.00

2.50

90.00

21.00

18.00

435.00

65.00

2.50

kg.

kg.

Sub-total for E

5.00

650.00

2.00 set

2.00 set

45.00

8.00

467,757.14

371,235.83

324,379.70

1,848.00 3,696.00

20.00 kg.

Sub-total for E (I + II + III)

- L.S./day

Name and Specifications Quantity Amount

3.50

2.00 set

Unit Unit Cost

400.00

18.00

Sub-total for B 4,259.65

Total (A+B) 46,856.13

Output/day

5,265.75

1,765.26 3,530.52

44,548.30

29,698.87

22,274.15

4,259.65

cu.m. 1,504.50

924.00

1 1.00 -

- 6.00

Sub-total for A 42,596.48

Name and CapacityNo. of

EquipmentNo. of Days Daily Rate Amount

Water Truck

1

3 8.00 443.20 10,636.80

6 8.00 342.24 16,427.52

1 8.00 611.92 4,895.36

3 8.00 443.20 10,636.80

For Government Field Office

DETAILED UNIT PRICE ANALYSIS

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy.

Vitali, Zamboanga City,

1.00

Designation No. of Persons No. of Days Daily Rate Amount

Page 24: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

PROJECT NAME:

Item No./Description: A.1.1(3) Construction of Field Office for the Engineer

Unit of Measurement: L.S.

Output per hour:

Quantity:

A. Labor

a. Const. Foreman

b. Mason

c. Carpenter

d. Laborer

P

B. Equipment, (2014 ACEL Rates)

a. One Bagger Mixer

b.

Minor Tools 10% of Labor

P

C.

D.

E. Materials

VII. Steel Works

a. 65 x 65 x 6mm. L

b. 50 x 50 x 6mm. L

c. 50 x 50 x 4mm. L

d. Purlins C- 150 x 50 x 3mm.

e. 16mm dia. Cross bracing

f. 16mm dia. Turn buckle

g. 12mm thk base plate

h. 10mm thk batten plate

i. 10mm dia. Sag rod

j. 20mm dia. X 350 mm anchor bolts

k. Welding Rod

l. Primer, Zinc Cromate

VIII Roofing Works

a. Pre-painted GI Roofing Sheet long span

b. Pre-painted ridge roll ga 24, 0.60m width

c. Pre-painted flashing, ga. 24

d. Teckscrew 11/2"

e. Roof Sealant

IX. Carpentry Works

a. Rough Lumber, sun dried tanguile

b. Plywood, ordinary 1/4" x 4' x 8'

c. Finishing Nails

d. Common Wire Nails

e. Wood Preservative Brown

P

F. Direct Cost (C + E)

G. Overhead, Contingencies and Miscellaneous 12% per D.O. 197, s. 2016

H. Contractor's Profit(CP) 8% per D.O. 197, s. 2016

I. Value Added Tax (VAT) 5% per D.O. 197, s. 2016

J. Total Unit Cost

1,000.00

5.00

10.00

5.00

kg.

kg.

kg.

gal.

ln.m.

kg.

350.00

35.00

10.00

5.00

2.00

Sub-total for E 104,707.68

16,800.00 48.00

90.00 450.00

kg. 50.00

500.00 bd.ft. 37.00 18,500.00

30.00 pc.

500.00

398.00 1,990.00 L

pc. 1.25 1,250.00

350.00 10,500.00

2.00 L 242.84 485.68

10.00 ln.m. 189.00 1,890.00

189.00 378.00

531.00 2,655.00

55.00 sq.m. 420.00 23,100.00

10.00 pc. 36.00 360.00

15.00 kg. 149.00 2,235.00

15.00 kg 47.00 705.00

38.00 380.00

20.00 pc. 118.00 2,360.00

25.00 kg. 47.00 1,175.00

18.00 kg. 48.00 864.00

38.00 1,330.00

250.00 kg. 48.00 12,000.00

100.00 kg. 48.00 4,800.00

Total (A+B) -

Output/day - L.S./day

Name and Specifications Quantity Unit Unit Cost Amount

Sub-total for B -

Water Truck 1 1.00 19,600.00

-

Name and CapacityNo. of

EquipmentNo. of Days Daily Rate Amount

1 5.00 1,376.00

Sub-total for A -

3 16.00 443.20

6 16.00 342.24

611.92

3 16.00 443.20

1.00

Designation No. of Persons No. of Days Daily Rate Amount

1 16.00

DETAILED UNIT PRICE ANALYSIS

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy.

Vitali, Zamboanga City,

For Government Field Office

Page 25: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

PROJECT NAME:

Item No./Description: A.1.1(3) Construction of Field Office for the Engineer

Unit of Measurement: L.S.

Output per hour:

Quantity:

A. Labor

P

B. Equipment, (2014 ACEL Rates)

P

C.

D.

E. Materials

X. Electrical Works

a. 2 x 40w Flourescent lighting fixtures

b. Porcelain Ceiling Outlet w/ female socket

c. Duplex Convinience outlet

d. two gang switch

e. 3.5mm2 thw

f. 8.00mm2 thw

g. 15mm dia. PVC pipe

h. 15mm dia. PVC Coupling

i. 15mm dia. PVC Elbow

j. 15mm dia. PVC Clamp

k. 20mm dia. RSC Pipe

l. 20mm dia. RSC Coupling

m. 20mm dia. RSC elbow

n. 20mm dia. RSC Clamp

o. 20mm dia. Service entrance cap

p. wire holder

q. utility box

r. octagonal box

s. electrical tape (big)

t. panel board (side main w/ braches)

XI. Plumbing Works

a. Water Closet (include. Fitting & Accessories)

b. Lavatory (include fitting & Accessories)

c. 1/2" GI Pipe S-40

d. 1/2" Water Faucet

e. 1/2" Assorted Connector

f. 4" PVC series 1000

g. 2" PVC series 1000

h. 4" PVC assorted Connector

i. 2" PVC assorted Connector

P

F. Direct Cost (C + E)

G. Overhead, Contingencies and Miscellaneous 12% per D.O. 197, s. 2016

H. Contractor's Profit(CP) 8% per D.O. 197, s. 2016

I. Value Added Tax (VAT) 5% per D.O. 197, s. 2016

J. Total Unit Cost

305.00

7,353.00

6,615.00

7,353.00

6,615.00

642.00

332.00

152.00

640.00

1.00

1.00

2.00

2.00

8.00

set

321.00

166.00

19.00 pc

pc

pc

pc

pc

462.00

8.00

set

pc

pc

1.00

448.00

305.00

77.00

56.00

Sub-total for E 44,193.25

1,627.00 3,254.00

640.00

1.00

6.00

217.00 7.00 pc

2.00 set

7.00 pc 32.00 224.00

8.00 pc 34.00 272.00

31.00

2.00 pc 100.00 200.00

2.00 pc 50.00 100.00

30.00 90.00 3.00 pc

10.00 pc 18.00 180.00

4.00 pc 240.00 960.00

3.00 pc 36.00 108.00

25.00 pc 26.00 650.00

55.00 pc 8.00 440.00

20.00 pc 73.00 1,460.00

25.00 pc 16.00 400.00

3.00 roll 3,600.00 10,800.00

25.00 m 69.33 1,733.25

100.00

3.00 pc 170.00 510.00

3.00 pc 132.00 396.00

pc

Name and Specifications Quantity Unit Unit Cost Amount

5.00 set 1,030.00 5,150.00

Sub-total for B -

Total (A+B) -

Output/day - L.S./day

DETAILED UNIT PRICE ANALYSIS

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy.

Vitali, Zamboanga City,

Daily Rate

For Government Field Office

Amount

1.00

Designation No. of Persons No. of Days

50.00

Name and CapacityNo. of

EquipmentNo. of Days Daily Rate Amount

2.00

Sub-total for A -

Page 26: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

PROJECT NAME:

Item No./Description: A.1.1(11)

Unit of Measurement: L.S.

Output per hour:

Quantity:

A. Labor

P

B. Equipment, (2014 ACEL Rates)

P

C.

D.

E. Materials

Office Equipment/Facilities & Supplies

Electric Desk Fan

Folding Beds, Good Quality

pillows w/ pillow cases, fitted sheets and blanket

Double burner gas stove (Gasul)

10 cups Rice Cooker

Aluminum Cookware

Plate, Glass, Spoon and fork

6 seater dinning table

Monoblock w/ Backrest chair

Plastic Pail & Basin

White Board

Bond Paper (Long)

Bond Paper (Short)

Yellow Pad

White Board Marker

Sign Pen (assorted color)

Ballpen (assorted color)

Mechanical Pencil

Pencil Lead, No. 5

Puncher

Staple Pad w/ wire

Cutter Blade

Scotch Tape

Brown Envelope

Folder, Long

Folder, Short

Data File Folder

Laptop

50 m. Tape

Lighting/Water Fixtures

a. Electrical Bill

b. Water Bill

c. LPG (11 kg)

P

F. Direct Cost (C + E)

G. Overhead, Contingencies and Miscellaneous per D.O. 197, s. 2016

H. Contractor's Profit(CP) 8% per D.O. 197, s. 2016

I. Value Added Tax (VAT) 5% per D.O. 197, s. 2016

J. Total Unit Cost

2.00

6.00

unit

each

5,000.00

2.00

1.00

Name and Specifications Quantity Unit

1,370.00

5,400.00

10,000.00

1,370.00

2,700.00

870.00

3,500.00

13,062.01

8,816.85

185,153.92

10.53 mos. 1,000.00 10,533.33

Sub-total for E 163,275.06

163,275.06

-

each

box

8.00 dozen 70.00 560.00

125.00 1,000.00

8.00 dozen

8.00 roll 45.00 360.00

8.00 pc.

8.00

box 240.00 960.00

1.00 unit 250.00 250.00

dozen

4.00 unit 275.00 1,100.00

4.00

4.00 box 180.00 720.00

6.00 unit 350.00 2,100.00

10.00 pc. 75.00 750.00

2.00 dozen 580.00 1,160.00

20.00 ream 270.00 5,400.00

4.00 pad 35.00 140.00

1.00 Unit 3,000.00 3,000.00

20.00 ream 300.00 6,000.00

2.00 dozen 2,500.00 5,000.00

2.00 pc. 250.00 500.00

1.00 dozen 2,000.00 2,000.00

1.00 each 2,800.00 2,800.00

10.53 mos. 1,500.00 15,800.00

mos.

1.00 unit 3,700.00 3,700.00

1.00

Unit Cost Amount

10.53

42,000.00

unit 2,500.00 2,500.00

1.00 set 3,500.00

Sub-total for B -

Total (A+B) -

Output/day - L.S./day

3,000.00 31,600.00

85.00 680.00

85.00 680.00

145.00

1.00

DETAILED UNIT PRICE ANALYSIS

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy.

Vitali, Zamboanga City,

Designation No. of Persons No. of Days Daily Rate Amount

Name and CapacityNo. of

EquipmentNo. of Days Daily Rate

Sub-total for A

Amount

-

1.00 set 42,000.00

Provision of Furnitures/Fixtures, Equipment and Appliances for the Field Office for the Field

Engineer

1.00 set 841.73 841.73

Page 27: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

PROJECT NAME:

Item No./Description: B.5 Project Billboard/Signboard

Unit of Measurement: each

Output per hour:

Quantity:

A. Labor

a. Const. Foreman

b. Skilled Labor

c. Unskilled Labor

P

B. Equipment, (2014 ACEL Rates)

P

C.

D.

E. Materials

a.

b. Tarpaulin (4' x 8')

c. Assorted Lumber

d. Assorted CW Nails

P

F. Direct Cost (C + E)

G. Overhead, Contingencies and Miscellaneous 12% per D.O. 197, s. 2016

H. Contractor's Profit(CP) 8% per D.O. 197, s. 2016

I. Value Added Tax (VAT) 5% per D.O. 197, s. 2016

J. Total Unit Cost 6,463.30

Ordinary Plywood 1/2" thk. x 4' x 8' 2.00 pc. 690.00 1,380.00

Sub-total for E 6,780.00

10,259.20

1,231.10

820.74

615.55

100.00 bd.ft. 37.00 3,700.00

2.00 kg. 50.00 100.00

Name and Specifications Quantity Unit Unit Cost Amount

2.00 pc. 800.00 1,600.00

Sub-total for B -

Total (A+B) 3,479.20

Output/day - each/day

Sub-total for A 3,479.20

Name and CapacityNo. of

EquipmentNo. of Days Daily Rate Amount

2 2.00 342.24 1,368.96

1 2.00 611.92 1,223.84

1 2.00 443.20 886.40

Designation No. of Persons No. of Days Daily Rate Amount

Per D.O. 141, s. 2016

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy.

Vitali, Zamboanga City,

2.00

DETAILED UNIT PRICE ANALYSIS

Page 28: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

PROJECT NAME:

Item No./Description: B.7 Occupation Safety and Health Program

Unit of Measurement: month

Output per hour:

Quantity:

A. Labor

a. Safety Practioner

b. First Aider

C. Flagman ( 2 per shift )

P

B. Equipment, (2014 ACEL Rates)

a. Warning Signs and Barricades

P

C.

D.

E. Materials

a.

b. Working Gloves (Maong Material)

c. Rain Coats (Reinforced, Hip Lenth)

d. Safety Hats

P

F. Direct Cost (C + E)

G. Overhead, Contingencies and Miscellaneous per D.O. 197, s. 2016

H. Contractor's Profit(CP) 8% per D.O. 197, s. 2016

I. Value Added Tax (VAT) 5% per D.O. 197, s. 2016

J. Total Unit Cost 104,260.47

30,000.00

Sub-total for E 26,160.00

968,439.36

-

77,475.15

52,295.73

18.00 pc. 100.00 1,800.00

24.00 pc, 600.00 14,400.00

Rubber Boots (Long w/ steel toe, Black) 24.00 pair 400.00 9,600.00

24.00 pair 15.00 360.00

Total (A+B) 942,279.36

Output/day - L.S./day

Name and Specifications Quantity Unit Unit Cost Amount

Sub-total for B 30,000.00

Name and CapacityNo. of

EquipmentNo. of Days Daily Rate Amount

Sub-total for A 912,279.36

1 158.00 443.20 70,025.60

6 316.00 342.24 648,887.04

Designation No. of Persons No. of Days Daily Rate Amount

1 316.00 611.92 193,366.72

DETAILED UNIT PRICE ANALYSIS

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy.

Vitali, Zamboanga City,

10.53

Page 29: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

PROJECT NAME:

Item No./Description: A.1.2(5) Operation and Maintenance of 4x4 Pick Up Type Service Vehicle for the Engineer

Unit of Measurement: month

Output per hour:

Quantity:

A. Labor

a. Driver

P

B. Equipment, (2014 ACEL Rates)

P

C.

D.

E. Materials

a.

b. Spare Parts

c. Engine Oil & Lubricants

d.

P

F. Direct Cost (C + E)

G. Overhead, Contingencies and Miscellaneous per D.O. 197, s. 2016

H. Contractor's Profit(CP) per D.O. 197, s. 2016

I. Value Added Tax (VAT) 5% per D.O. 197, s. 2016

J. Total Unit Cost

453,647.59

-

-

22,682.38

Sub-total for E 320,236.70

45,235.51

1.00 L.S. 29,378.70 29,378.70

Miscellaneous 1.00 L.S. 45,000.00 45,000.00

Diesel 6,318.00 L 31.00 195,858.00

1.00 L.S. 50,000.00 50,000.00

Total (A+B) 133,410.89

Output/day - L.S./day

Name and Specifications Quantity Unit Unit Cost Amount

Sub-total for B -

Sub-total for A 133,410.89

Name and CapacityNo. of

EquipmentNo. of Months Monthly Rate Amount

1 316 422.32 133,410.89

10.53

Designation No. of Persons No. of Days Daily Rate Amount

DETAILED UNIT PRICE ANALYSIS

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy.

Vitali, Zamboanga City,

Page 30: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

PROJECT NAME:

Item No./Description: B.9 Mobilization & Demobilization

Unit of Measurement: L.S.

Output per hour:

Quantity:

A. Labor

P

B. Equipment, (2014 ACEL Rates)

a. Low Bed Trailer

b. Water Truck

c. Backhoe

d. Payloader

e. Dumptruck

P

C.

D.

E. Materials

P

F. Direct Cost (C + E)

G. Overhead, Contingencies and Miscellaneous per D.O. 197, s. 2016

H. Contractor's Profit(CP) per D.O. 197, s. 2016

I. Value Added Tax (VAT) 5% per D.O. 197, s. 2016

J. Total Unit Cost

412,617.00

-

-

20,630.85

433,247.85

Sub-total for E -

Name and Specifications Quantity Unit Unit Cost Amount

Sub-total for B 412,617.00

Total (A+B) 412,617.00

Output/day - L.S./day

Name and CapacityNo. of

EquipmentNo. of Days Daily Rate Amount

1 3.00 34,043.00 102,129.00

Sub-total for A -

Designation No. of Persons No. of Days Daily Rate Amount

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy.

Vitali, Zamboanga City,

1.00

DETAILED UNIT PRICE ANALYSIS

136,320.00 3.00

1

2

1

4

3.00

3.00

3.00

19,600.00

12,296.00

13,864.00

11,360.00

58,800.00

73,776.00

41,592.00

Page 31: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

PROJECT NAME:

Item No./Description: B.4(1) Construction Survey & Staking

Unit of Measurement: km.

Output per hour:

Quantity:

A. Labor

For Field Works

a. Geodetic Engineer

b. Skilled Laborer

c. Laborer

For Office Works

a. Geodetic Engineer

b. Skilled Laborer

P

B. Equipment, (2014 ACEL Rates)

a. Total Station w/ complete accessories

Minor Tools 10% of Labor

P

C.

D.

E. Materials

a.

b. Blue Printing

Miscellaneous 5% of Materials Cost

P

F. Direct Cost (C + E)

G. Overhead, Contingencies and Miscellaneous 12% per D.O. 197, s. 2016

H. Contractor's Profit(CP) 8% per D.O. 197, s. 2016

I. Value Added Tax (VAT) 5% per D.O. 197, s. 2016

J. Total Unit Cost 102,153.07

Sub-total for E 9,975.00

16,214.77

1,945.77

1,297.18

972.89

475.00

Standard Stake Plan (800 mm x 910 mm) 20.00 pc 400.00 8,000.00

100.00 pc 15.00 1,500.00

Total (A+B) 6,239.77

Output/day 0.32 km./day

Name and Specifications Quantity Unit Unit Cost Amount

Sub-total for B 1,021.80

521.80

1 0.63 800.00 500.00

Sub-total for A 5,217.98

Name and CapacityNo. of

EquipmentNo. of Days Daily Rate Amount

1 1.88 833.31 1,562.46

2 1.88 443.20 1,662.00

3 0.63 342.24 641.70

1 0.63 833.31 520.82

3 0.63 443.20 831.00

0.04

0.200

Designation No. of Persons No. of Days Daily Rate Amount

DETAILED UNIT PRICE ANALYSIS

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy.

Vitali, Zamboanga City,

Page 32: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

PROJECT NAME:

Item No./Description: 403(1) Structural Steel, Furnished, Fabricated and Erected

Unit of Measurement: kg.

Output per hour:

Quantity:

A. Labor

a. Const. Foreman

b. Leadman

c. Skilled Labor

d. Unskilled Labor

P

B. Equipment, (2014 ACEL Rates)

a. Truck Mounted Crane

b.

c. Welding Machine

d. Generator Set (1401 - 1500 KW)

e. Cutting Outfit

Minor Tools 10% of Labor

P

C.

D.

E. Materials

a. Structural Steel (imported)

Structural Steel Support

b. 1 - I Beam x 10.0 m.

c.

d.

e.

f. Oxy/Acetylene (1 kg./5000 kg. of Steel)

P

F. Direct Cost (C + E)

G. Overhead, Contingencies and Miscellaneous 12% per D.O. 22 s 2015

H. Contractor's Profit(CP) 8% per D.O. 22 s 2015

I. Value Added Tax (VAT) 5% per D.O. 22 s 2015

J. Total Unit Cost

DETAILED UNIT PRICE ANALYSIS

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy.

Vitali, Zamboanga City,

245.25

1,207.00

Designation No. of Persons No. of Days Daily Rate Amount

1 0.62 611.92 376.45

1 0.62 561.36 345.34

4 0.62 443.20 1,090.61

8 0.62 342.24 1,684.34

Sub-total for A 3,496.73

Name and CapacityNo. of

EquipmentNo. of Days Daily Rate Amount

1 0.62 20,848.00 12,825.45

Drop Hammer 1 0.49 1,600.00 787.44

1 0.43 2,968.00 1,278.12

1 0.43 21,902.16 9,431.77

2 0.43 363.60 313.16

349.67

Sub-total for B 24,985.61

Total (A+B) 28,482.34

Output/day 1,962.00 kg./day

Name and Specifications Quantity Unit Unit Cost Amount

1,207.00 kg. 162.93 196,656.51

(including fabrication, galvanization, pre-trial,

assembly, hauling & erection cast)

78.46 kg. 50.00 3,922.75

2 - Tubular Pipe 0.35 mm Ø x 10.0 m. 0.99 m. 950.75 941.00

4 - RSB 30 mm. Ø x 12.0 m. 19.31 kg. 38.00 733.86

Welding Rod (1 kg./2000 kg. of Steel) 0.60 kg. 150.00 90.53

0.24 set 2,500.00 603.50

241.59

Sub-total for E 202,948.14

231,430.48

27,771.66

18,514.44

13,885.83

Page 33: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

Bureau : DPWH

Region : IX

District/City : Zamboanga City

Date :

NAME OF PROJECT : Appropriation : P

Source of Funds :

Issued Obligated Authority :

LOCATION: Released :

Cal. Days to Complete :

PROJECT CATEGORY : Desirable Starting Date :

Mode of Implementation : by contract

PROJECT DESCRIPTION : Limits: Length:

Scope of Work : Bridge

Road Width : 6.70 m. m.

Roadbed Width : 12.00 m.

Subbase Course : 0.30 m. thk. m.

Surface Course : 0.15 m. thk.

m.

Approaches Net Length: ln.m.

Bridge Length: ln.m.

MINIMUM EQUIPMENT REQUIREMENT : TECHNICAL PERSONNEL REQUIRED :

Diesel Hammer

Truck Mounted Crane Drop Hammer

Gen. Set (876 - 1000 KVA) Jack Hammer

Gen. Set (1401 - 1500 KW) Service Crane

Welding Machine Air Compressor

PART A - FACILITIES FOR THE ENGINEER

PART B - OTHER GENERAL REQUIREMENTS

A.1.2(5)Operation and Maintenance of 4x4 Pick Up Type Service

Vehicle for the Engineer0.98 month 10.53

1.00 Mobilization & Demobilization 0.89

0.20

2.00

968,439.36

1.00

UNIT COST

371,235.83

1

1

Laborers (Unskilled)

1

2

1 20

NATIONAL ROAD

Transti Mixer

1

2 Foreman

51.34

Abutment A 1864+935.79

1864+987.13

8

Laborers (Skilled)

upon approval

QUANTITY

L.S.B.9

B.7 Occupation Safety and Health Program 2.10 month 10.53

0.04

Project Billboard/Signboard

Construction Survey & Staking

0.02 each

B.4(1)

163,275.06

A.1.1(3) Construction of Field Office for the Engineer 1.00

km.

371,235.83

A.1.1(11) 0.35

L.S.

Stressing (Jack) Machine

Water Tank

Batching Plant

Payloader 4

Cargo Truck

Plate Compactor2

1

1

DESCRIPTION% OF

TOTALUNIT

2 Bar BenderRoad Roller

Water Truck

One Bagger Mixer

2

ITEM NO.

Backhoe 3 Concrete Cutter

Road Grader 2 Bar Cutter

Bulldozer 2 Concrete Vibrator 3 Geometric Surveyor 1

Dump Truck 12 1

75.79

51.34

72.87

148.66

1865+060.00End of Proj.

No.

316

4 Concrete Screeder 1 Materials Engineer 1

1864+860.00Beg. of Proj.

Abutment B

Water Pump

B.5

Mason

Zamboanga City

91,940.45

60,000,000.00

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City

Road, Brgy. Vitali, Zamboanga City,

CY-2017 GAA

Description No.

0.80

Republic of the Philippines

Department of Public Works and Highways

PROGRAM OF WORK

(For all types of Project)

December 8, 2016

Description No. Description

Calendar Days

81,073.86

453,647.59 43,081.44

163,275.06

10,259.20

16,214.77

Materials Lab. Tech.

Carpenter

1

ESTIMATED COST OF PROPOSED WORK

Provision of Furnitures/Fixtures, Equipment and

Appliances for the Field Office for the Field Engineer

12

1

Kneading Machine

30

1

Crane with Bucket

412,617.00

DIRECT COST

TOTAL

1

412,617.00

5,129.60

1 Project Engineer

L.S.

Safety Practitioner 1

2

1

1

1

Applicator Machine 1

1

1

1

1

Page 34: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

UNIT COSTQUANTITYDESCRIPTION

% OF

TOTALUNITITEM NO.

DIRECT COST

TOTAL

PART C - EARTHWORKS

PART D - SUBBASE AND BASE COURSE

PART E - SURFACE COURSES

PART F - BRIDGE CONSTRUCTION

P

1,715,513.24 414 Forms and Falsework 3.71 L.S. 1.00 1,715,513.24

5,368.61

412 Elastomeric Bearing Pad 0.85 each 24.00 390,684.50 16,278.52

407(8) Lean Concrete 0.20 cu.m. 17.01 91,320.01

9,866.24

406(1)a4 Prestressed Concrete AASHTO Girder (Type IV-B) 12.94 ln.m. 202.00 5,981,816.87 29,612.95

405(1)b2 Structural Concrete, Class "A" 13.21 cu.m. 618.70 6,104,242.07

48.23

404b Reinforcing Steel, Grade 60 10.48 kg. 94,283.23 4,842,952.39 51.37

404a Reinforcing Steel, Grade 40 0.35 kg. 3,356.80 161,898.37

3,985.65

402(1) Timber Structures for Craneway 4.33 span 1,998,645.94 249,830.74

401(2) Concrete Railing 0.87 ln.m. 101.00 402,550.41

8.00

300(1) Gravel Surface Course

Bridge Excavation Above Ordinary Water Level cu.m.

104(2)

Portland Cement Concrete Pavement, 0.28 m. thk.

cu.m.

cu.m.

Aggregate Subbase Course

428.72

505(5) Grouted Riprap, Class A 5.22 cu.m. 640.21 2,411,142.11

55.00

5,582.00

1,679.21 1,612,039.58

3,665,956.17

736.10

1,294.29

656.75

742,920.16

158,335.49

6,337,512.17 3,970.87

74,664.48

98,952.76 230.81

960.00

1,357.54

T O T A L

3.49 sq.m.

100.00

0.21103(2)a

311(1)e1

1.61

0.16

103(2)b Bridge Excavation Below Ordinary Water Level

Embankment, Common Borrow

200

46,209,838.85

cu.m. 574.00

400(12)

13.71 ln.m. 1,596.00

7.93

230.81 0.34 cu.m. 686.00

2,459.98 400(6) Structural Steel Sheet Piles, Furnished 5.37 ln.m. 1,008.00 2,479,655.85

741,985.27

360,210.90 0.78 ln.m. 84.00

Structural Steel Sheet Piles, Driven 1.61

3,766.17

4,288.23

400(14) Precast Concrete Piles, Driven 6.79 ln.m. 1,520.00 3,136,727.10 2,063.64

400(16)

231,430.48

729.94

PART G - DRAINAGE AND SLOPE PROTECTION STRUCTURES

612(1) Reflectorized Thermoplastic Pavement Markings (White) 0.16 sq.m. 100.00 72,993.72

PART H - MISCELLANEOUS STRUCTURES

403(1) Structural Steel, Furnished, Fabricated and Erected 0.50 kg. 1,207.00

Test Piles, Furnished and Driven (400 mm. x 400 mm.)

400(4)a Precast Concrete Piles, Furnished

1,008.00 ln.m.

191.74

Page 35: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

NAME OF PROJECT :

I. ESTIMATED COST

A. DIRECT COST

A.1. Labor

A.2. Equipment Expenses

A.3. Materials

P

B. INDIRECT COST (Per D.O. # 197, s. 2016)

B.1. Overhead, Contingency & Misc.

(12 % Max. of D.C.)

B.2. Profit (8 % Max. of D.C.)

C. VAT (5% of D.C. and I.C. Per D.O. # 197, s. 2016)

P

II. ESTIMATED GOVERNMENT EXPENDITURES

1. Engineering and Administrative Overhead (3.5%)

2. Detailed Engineering (1%)

3. Reserved for the Payment of RROW

4. Physical Reserved

P

Checked :

Submitted : Recommending Approval :

Approved :

JORGE U. SEBASTIAN, JR., CESO III

Regional Director

LEONCIO B. SOLAMILLO CAYAMOMBAO D. DIA

Chief, Construction Division OIC - Assistant Regional Director

Engineer II Engineer II

Prepared :

ELWICK P. ACUÑA JERALD R. BARRERA

TOTAL ESTIMATED PROJECT COST 100.00 60,000,000.00

0.00 114.63

3.50 2,100,000.00

4.60 2,757,137.40

SUBTOTAL (CONTRACT COST) 96.50 57,899,885.37

6.05 3,627,485.94

8.84 5,305,423.18

SUB-TOTAL (DIRECT COST) 77.02 46,209,838.85

10.47 6,279,714.73

59.47 35,680,663.44

7.08 4,249,460.68

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy. Vitali, Zamboanga City,

Zamboanga City

BREAKDOWN OF ESTIMATED EXPENDITURES % OF TOTAL AMOUNT

Page 36: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

Beg. Of Proj. - Abutment A to

Abutment A - Abutment B toAbutment B - End of Proj. to

Approaches Net Length 148.66 Ln.m.Bridges Net Length 51.34 Ln.m. Contract Duration : 316 CD

OCM PROFIT % VALUE

(9) (10) (11) (12) (13)

(5) x (8) 5%[(5) + (9)] (9) + (10) (5) + (11) (12) / (3)

PART A - FACILITIES FOR THE ENGINEER

A.1.1(3) Construction of Field Office for the Engineer 1.00 L.S. 371,235.83 12.00 8.00 20.00 74,247.17 22,274.15 96,521.32 467,757.14 467,757.14

A.1.1(11) Provision of Furnitures/Fixtures, Equipment and

Appliances for the Field Office for the Field Engineer 1.00 L.S. 163,275.06 - 8.00 8.00 13,062.01 8,816.85 21,878.86 185,153.92 185,153.92

A.1.2(5) Operation and Maintenance of 4x4 Pick Up Type Service

Vehicle for the Engineer 10.53 month 453,647.59 - - - - 22,682.38 22,682.38 476,329.97 45,235.51

TOTAL OF PART A 988,158.48 87,309.17 53,773.38 141,082.55 1,129,241.03

B.4(1) Construction Survey & Staking 0.20 km. 16,214.77 12.00 8.00 20.00 3,242.95 972.89 4,215.84 20,430.61 102,153.07

B.5 Project Billboard/Signboard 2.00 each 10,259.20 12.00 8.00 20.00 2,051.84 615.55 2,667.39 12,926.59 6,463.30

B.7 Occupation Safety and Health Program 10.53 month 968,439.36 - 8.00 8.00 77,475.15 52,295.73 129,770.87 1,098,210.23 104,260.47

B.9 Mobilization & Demobilization 1.00 L.S. 412,617.00 - - - - 20,630.85 20,630.85 433,247.85 433,247.85

TOTAL OF PART B 1,407,530.33 82,769.94 74,515.01 157,284.96 1,564,815.29

104(2) Embankment, Common Borrow 5,582.00 cu.m. 3,665,956.17 12.00 8.00 20.00 733,191.23 219,957.37 953,148.60 4,619,104.78 827.50

TOTAL OF PART C 3,665,956.17 733,191.23 219,957.37 953,148.60 4,619,104.78

200 Aggregate Subbase Course 574.00 cu.m. 742,920.16 12.00 8.00 20.00 148,584.03 44,575.21 193,159.24 936,079.41 1,630.80

TOTAL OF PART D 742,920.16 148,584.03 44,575.21 193,159.24 936,079.41

300(1) Gravel Surface Course 55.00 cu.m. 74,664.48 12.00 8.00 20.00 14,932.90 4,479.87 19,412.76 94,077.24 1,710.50

311(1)e1 Portland Cement Concrete Pavement, 0.28 m. thk. 960.00 sq.m. 1,612,039.58 12.00 8.00 20.00 322,407.92 96,722.37 419,130.29 2,031,169.87 2,115.80

TOTAL OF PART E 1,686,704.06 337,340.81 101,202.24 438,543.05 2,125,247.11

103(2)a Bridge Excavation Above Ordinary Water Level 428.72 cu.m. 98,952.76 12.00 8.00 20.00 19,790.55 5,937.17 25,727.72 124,680.47 290.82

103(2)b Bridge Excavation Below Ordinary Water Level 686.00 cu.m. 158,335.49 12.00 8.00 20.00 31,667.10 9,500.13 41,167.23 199,502.72 290.82

400(4)a Precast Concrete Piles, Furnished 1,596.00 ln.m. 6,337,512.17 12.00 8.00 20.00 1,267,502.43 380,250.73 1,647,753.16 7,985,265.33 5,003.30

400(6) Structural Steel Sheet Piles, Furnished 1,008.00 ln.m. 2,479,655.85 12.00 8.00 20.00 495,931.17 148,779.35 644,710.52 3,124,366.37 3,099.57

400(12) Structural Steel Sheet Piles, Driven 1,008.00 ln.m. 741,985.27 12.00 8.00 20.00 148,397.05 44,519.12 192,916.17 934,901.44 927.48

400(14) Precast Concrete Piles, Driven 1,520.00 ln.m. 3,136,727.10 12.00 8.00 20.00 627,345.42 188,203.63 815,549.05 3,952,276.15 2,600.18

400(16) Test Piles, Furnished and Driven (400 mm. x 400 mm.) 84.00 ln.m. 360,210.90 12.00 8.00 20.00 72,042.18 21,612.65 93,654.83 453,865.73 5,403.16

401(2) Concrete Railing 101.00 ln.m. 402,550.41 12.00 8.00 20.00 80,510.08 24,153.02 104,663.11 507,213.51 5,021.92

402(1) Timber Structures for Craneway 8.00 span 1,998,645.94 12.00 8.00 20.00 399,729.19 119,918.76 519,647.95 2,518,293.89 314,786.74

403(1) Structural Steel, Furnished, Fabricated and Erected 1,207.00 kg. 231,430.48 12.00 8.00 20.00 46,286.10 13,885.83 60,171.92 291,602.40 241.59

404a Reinforcing Steel, Grade 40 3,356.80 kg. 161,898.37 12.00 8.00 20.00 32,379.67 9,713.90 42,093.58 203,991.95 60.77

404b Reinforcing Steel, Grade 60 94,283.23 kg. 4,842,952.39 12.00 8.00 20.00 968,590.48 290,577.14 1,259,167.62 6,102,120.01 64.72

405(1)b2 Structural Concrete, Class "A" 618.70 cu.m. 6,104,242.07 12.00 8.00 20.00 1,220,848.41 366,254.52 1,587,102.94 7,691,345.01 12,431.46

406(1)a4 Prestressed Concrete AASHTO Girder (Type IV-B) 202.00 ln.m. 5,981,816.87 12.00 8.00 20.00 1,196,363.37 358,909.01 1,555,272.39 7,537,089.26 37,312.32

407(8) Lean Concrete 17.01 cu.m. 91,320.01 12.00 8.00 20.00 18,264.00 5,479.20 23,743.20 115,063.21 6,764.45

412 Elastomeric Bearing Pad 24.00 each 390,684.50 12.00 8.00 20.00 78,136.90 23,441.07 101,577.97 492,262.47 20,510.94

414 Forms and Falsework 1.00 L.S. 1,715,513.24 12.00 8.00 20.00 343,102.65 102,930.79 446,033.44 2,161,546.68 2,161,546.68

TOTAL OF PART F 35,234,433.81 7,046,886.76 2,114,066.03 9,160,952.79 44,395,386.60

(1) (2) (3) (4) (5) (8)

APPROVED BUDGET FOR THE CONTRACT

Widening of Vitali Bridge and Approaches along Zamboanga City - Pagadian City Road, Brgy. Vitali, Zamboanga City,

ITEM NO. DESCRIPTION QUANTITY UNITESTIMATED DIRECT

COSTUNIT COST

1,864,987.13

1864+860.00

MARK-UPS IN % TOTAL MARK-UPSVAT

TOTAL INDIRECT

COSTTOTAL COST

1865+060.00

1864+935.79

1864+935.79 1864+987.13

PART B - OTHER GENERAL REQUIREMENTS

PART C - EARTHWORKS

PART D - SUBBASE AND BASE COURSE

PART E - SURFACE COURSES

(7)

PART F - BRIDGE CONSTRUCTION

(6)

Page 37: DETAILED UNIT PRICE ANALYSIS€¦ · DETAILED UNIT PRICE ANALYSIS Sub-total for A 1,860.33 Name and Capacity No. of Equipment No. of Days Daily Rate Amount 1 1.44 17,384.00 24,946.04

OCM PROFIT % VALUE

(9) (10) (11) (12) (13)

(5) x (8) 5%[(5) + (9)] (9) + (10) (5) + (11) (12) / (3)(1) (2) (3) (4) (5) (8)

ITEM NO. DESCRIPTION QUANTITY UNITESTIMATED DIRECT

COSTUNIT COST

MARK-UPS IN % TOTAL MARK-UPSVAT

TOTAL INDIRECT

COSTTOTAL COST

(7)(6)

505(5) Grouted Riprap, Class A 640.21 cu.m. 2,411,142.11 12.00 8.00 20.00 482,228.42 144,668.53 626,896.95 3,038,039.06 4,745.38

TOTAL OF PART G 2,411,142.11 482,228.42 144,668.53 626,896.95 3,038,039.06

612(1) Reflectorized Thermoplastic Pavement Markings (White) 100.00 sq.m. 72,993.72 12.00 8.00 20.00 14,598.74 4,379.62 18,978.37 91,972.09 919.72

TOTAL OF PART H 72,993.72 14,598.74 4,379.62 18,978.37 91,972.09

TOTAL 46,209,838.85 8,932,909.12 2,757,137.40 11,690,046.52 57,899,885.37

Prepared by : Submitted by : Recommending Approval: Approved by :

Head, BAC Technical Working Group Chief, Construction Division OIC - Assistant. Regional Director

PART G - DRAINAGE AND SLOPE PROTECTION STRUCTURES

Regional Director

BELEN A. SAPALLEDA LEONCIO B. SOLAMILLO CAYAMOMBAO D. DIA JORGE U. SEBASTIAN, JR., CESO III

PART H - MISCELLANEOUS STRUCTURES