Detailed Project Report For Water Supply (Nanded – South)

Upgradation of Water Supply, Sewerage and Storm Water Drainage System for Nanded Waghala City

Municipal Corporation Maharashtra

TamilNadu Water Investment Company

Chennai

AUGUST 2006

Page 2: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Salient Features

1. Name of the town: Nanded (South)

2. Area: 20.42 Sq. km

3. Present Water Supply: Supply InstalledCapacity

CIDCO Treatment Plant: 10 Mld 12Mld

4. Present Per Capita Supply: 185 lpcd

5. Existing Source: Vishnupuri

Present Allocation: (1.5) MCM

6. Population: 2023 2038

2.89 lac 6.87 Lac

7. Proposed Per Capita Supply at consumer end: 135 lpcd

8. Gross Demand (Mld): 2023 2038

50.3 119.7

(Water availability at

source to be Checked)

9. Proposed Source: Vishnupuri Dam

10. Proposed Elevated Service Reservoirs: 7 Nos.

11. Proposed Transmission Pipe Length (km): 12.85 km for 2038

Rehabilitation of Work: .

Rehabilitation of Existing Water

Treatment Plant of 12 Mld

12. Estimated Cost of the Project: 39.98 Crore Rupees

13. Proposed Scheme: Exhibit No. 2, 3, 4

14. Proposed Water Treatment Plant with Mld

Clear Water Pump (Mld) 35

Page 3: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page1 of 5

CONTENTS

Sr. No. Title Page No.

1. Introduction

1.1 Background 1

1.2 Sources 1

1.3 Justification of Project 1

1.4 Project Area 2

1.5 Population 2

1.6 Authorization 3

2. Existing Water Supply System

2.1 Raw Water Pump House 1

2.2 Raw Water Transmission System 1

2.3 Water Qualities and Water Treatment Plant 2

2.4 Reservoirs 2

2.5 Water Distribution System 3

2.6 Electrical System 3

2.7 Mechanical System 4

3. System Planning Criteria

3.1 General 1

3.2 Population 1

3.3 Water Demand 1

3.4 Inlet Mains to Service Reservoirs and Trunk Mains 1

3.5 Local Distribution System 1

3.6 Hazen William C-Value 2

3.7 Peak Factor 2

3.8 Local Distribution Network Analysis 2

3.9 Residual Pressures in the Distribution System 3

3.10 Minimum Diameter of the pipes 3

3.11 Miscellaneous Considerations 3

Page 4: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page2 of 5

3.12 Structural Design Criteria for Elevated Service Reservoirs 4

3.13 Design Criteria for Electrical System 8

4. Pipe Material Selection Aspect

4.1 General 1

4.2 Pipe Material 1

4.3 Selection of Pipes 7

5. Proposed System

5.1 Source 1

5.2 Raw water conveyance from Vishnupuri 1

5.3 Treatment Plant at Asadvan Village 2

5.4 Proposed pumping Station 7

5.5 Proposed Transmission System 7

5.6 Service Reservoir 7

5.7 Distribution System 7

5.8 Proposed Rehabilitation 7

5.9 Proposed Rehabilitation for Electrical System 7

5.10 Proposed Rehabilitation for Mechanical System 9

5.11 Environmental and Social Impact Assessment 10

5.12 Summary of Proposed Works 13

6. Project Implementation Schedule

6.1 Implementation Schedule 1

7. Cost Estimate

7.1 Cost Basis for Proposed Work 1

7.2 Cost Basis for Water Supply System 1

8. Appendix 1-Population and Water Demand

9. Appendix 2- Implementation Schedule

10. Appendix 3-Alternatives for Transmission system

11 Appendix 4-Detailed Cost Estimates

12. Exhibits

Page 5: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page3 of 5

LIST OF FIGURES

Figure No. Title Page No.

III.1 Mass Curve Chapter 3

Page 13

III.2 Consumption Curve Chapter 3

Page 13

V.1 Schematic Flow Diagram for the proposed water treatment plant

at Kabranagar

Chapter 5

Page5

Page 6: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page4 of 5

LIST OF TABLES

Table No. Title Page No.

I.1 Present Water Supply

Chapter 1

Page 1

I.2 Adopted Population

Chapter 1

Page 2

II.1 Details of Raw Water Pumping mains

Chapter 2

Page 1

II.2 Details of Water Treatment Plant

Chapter 2

Page 2

III.1 Hazen William C-Values for different pipe materials

Chapter 3

Page 2

III.2 Assessed Mass Curve (Inflow/Outflow vs. Time)

Chapter 3

Page 12

IV.1 Characteristics of different types of pipe materials

Chapter 4

Page 4

IV.1a Analytical Results (Kabranagar )

Chapter 5

Page 3

IV.1 b Analytical Results (New Pump house)

Chapter 5

Page 4

IV.3 Possible Environmental and Social Issues in Urban Infrastructure

Projects

Chapter 5

Page 10

IV.4 Summary of Mitigation Measures

Chapter 5

Page 11

Page 7: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page5 of 5

LIST OF EXHIBITS

Exhibit No. Title

1 Map showing Location of Nanded city in Maharashtra State

2 Layout showing Transmission Main, Proposed Storages and Proposed zone

boundary

3 Layout of water distribution network for Asarjan, Fattejangpur ,Kavatha and

Vasarni

4 Layout of water distribution network for Asadvan and Waghala

5 Typical details of Valve Chamber

6 Typical shape of ESR for staging height of 15m

Page 8: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

ABBREVIATIONS

CDP

CI

CIDCO

CPHEEO

CWPH

CWPS

IL&FS

DI

DPR

DSR

ESR

LPCD

MBR

MJP

ML

Mld

MS

NWMC

OHT

RCC

TWIC

WTP

W + S

City Development Plan

Cast Iron

City and Industrial Development Corporation

Central Public Health & Environmental

Engineering Organisation.

Clear Water sump and pump house

Clear Water Pumping Station

Infrastructure Leasing & Financial Services

Ltd.

Ductile Iron

Detailed Project Report

District Schedule of Rates

Elevated Service Reservoir

Liters per Capita per Day

Master Balancing Reservoir

Maharashtra Jeevan Pradhikaran

Million Liters

Million Liters per Day

Mild Steel

Nanded-Waghala Municipal Corporation

Over Head Tanks

Reinforced Cement Concrete

Tamilnadu Water Investment Company

Water Treatment Plant

Working and Standby

Page 9: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page1 of 3

CHAPTER - I

INTRODUCTION

1.1 BACKGROUND

Nanded City is well connected by train as well as by road to Mumbai, Delhi, Hyderabad.The

River Godavari in Nanded almost bisects the city and it runs in a west to east direction.

Nanded (south) is the new added area to erstwhile Nanded Municipal Council forming

Nanded-Waghala Municipal Corporation. Nanded city is famed for its pilgrim, tourism

offerings and education facilities. Nanded ( South) has growth potential for planned

development of residential and educational facilities (Refer Exhibit-1 for location of Nanded

City in Maharashtra State)

Nanded Waghala City Municipal Corporation (NWMC) is the organization for development

of plans to prepare a long-term perspective plan for Water Supply, Sewerage and storm water

services in the city. Present water supply to the city as given in Table I.1 is 10 Mld for

population of 54,905 souls as per 2001 census. NWMC intends to implement water supply

scheme on priority to improve the water supply in the Nanded(South). NWMC therefore

invited Consultancy services from reputed consulting firm for preparation of long term

perspective plan & detailed project report for water supply scheme, which would form part of

perspective plan.

Table I.1: Present Water Supply

WTP Clear water available in

(Mld)

CIDCO 10 (12.6 Mld)

1.2 SOURCES

Raw Water Pumping Station (CIDCO jack well)

The source was first developed in the year 1985 for supply of 12 MLD. River Godavari is a

source of water for Nanded (South)Waghala Municipal Corporation. A Dam is constructed

across river Godavari at Vishnupuri. Jack well of 8.0 m diameter is located at distance of

about 500.0 m of dam on riverbank (North). A intake well is located at distance of 22.0 m in

river bed from the bank and connected to jack well by 600 mm diameter Reinforced Concrete

pipe.

1.3 JUSTIFICATION OF THE PROJECT

Nanded (South) obtains its daily supply of 12 Mld of water from river Godavari. The present

population in the NWMC area is 94000 souls and is projected to increase to 2.89 lakhs by the

year 2023. The present gross water demand is correspondingly expected to increase to about

44.0 Mld for the year 2023.

Nanded (North) is area heading towards the saturation. Hence Nanded (South) is

newly added area in Nanded Waghala City Municipal Corporation (NWCMC). Area

includes mainly six villages and CIDCO ( 1.91 sq.km.) area. Nanded ( South)

particularly has lack infrastructure facilities. New hospitals, institutions are coming

up in the area. In October 2008, a event of tri centenary function of Gur ta Gaddi

would be celebrated at Nanded. Obviously 25 lac pilgrims is expected to mark their

presence for the event.. As part of Infrastructure Development, Government of

Page 10: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page2 of 3

Maharashtra and NWMC are planning to upgrade the Water Supply system of

Nanded (South) on priority .

1.4 PROJECT AREA

The project area comprises of the Nanded (South) admeasuring 31.14 sq.km. The project area

is under the jurisdiction of Nanded Municipal Corporation. It comprises of Vasrani, Kautha,

Asarjan, Fatehjangpur and Asadvan. Though CIDCO area is part of project area, the water

supply in this area couldn’t review due to non availability of data

CLIMATE

The climate of the city is generally dry except during southwest monsoon season. The average

annual rainfall in the city is about 901 mm and temperature range is in between 46 0C

(maximum) to 18 0C(minimum).

GEOGRAPHY & TOPOGRAPHY

Nanded (South) situated on the bank of river Godavari at an altitude 489 m above mean sea

level. It is located approximately at the intersection of 18O30’ N latitude and 77

O10’ E

longitude. The total area of Nanded south and North City (NWMC) is 51.76 sq.km. The city

is divided in two parts i.e. Old Nanded Town (20.62) Sq kms located North of the Godavari

and Waghala area along with newly merged 6 villages (31.14 Sq. Kms) in the South. Nanded

South and North of Godavari slope towards the river. Ground levels vary from 405.0 m to

355.0 m near the river.

GEOLOGY

Nanded (South) Municipal Corporation area generally has sandy soil.

1.5 POPULATION

After formation of Nanded Waghala city Municipal Council, 2001is the first census taken

place for population. The total population of the project area was about 54000 soul in the year

2001. The present population is about 94000 souls.

Population projection has been given in City Development Plan (CDP) prepared by IL&FS.

The annual growth rate of 4% is considered in CDP by ILFS. The same annual growth rate is

considered to obtain the population for the year 2038. Following projected population has

been adopted.

Table I.2: Adopted Population

Year Populations

2001 54,905

2006 94,054

2023 289,334

2038 687951

Page 11: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page3 of 3

1.6 AUTHORISATION

Tamilnadu Water Investment Company (TWIC) has authorised TCE Consulting Engineers

Limited to review available Master Plan and D.P.R.. In absence of such information, a fresh

DPR are prepared for Nanded(South). A water supply augmentation project for Nanded

Municipal Corporation(South area) has been prioritized for the year 2023.

TCE wishes to thank TWIC for entrusting the task of review of Master plan & Detailed

project Report and also acknowledges the full co-operation offered by officials of NWMC for

collection of data and drawings required for the same. Also thanks are due to officials of

Maharashtra Jeevan Pradhikaran (MJP) for making available relevant data required for the

project.

Page 12: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page1 of 6

CHAPTER - II

EXISTING WATER SUPPLY SYSTEM

Nanded Waghala City Municipal Corporation (NWCMC) manages the water supply and

sewerage system for the Nanded (North) and Nanded (South) city in addition to its other

functions. River Godavari is identified as the surface water source. Nanded (South) comprises

of City and Industrial Development CIDCO, HUDCO area and six villages. In Nanded

(South) only CIDCO area (1.91sq. km) is covered with regular water supply schemes in the

year 1985. Rest of the area has got supply from local source. The details of the system for

CIDCO area is as follows:

CIDCO system consists of following components:

i) Raw Water Pump house (RWPH)

ii) Raw water transmission main (RWTM)

iii) Water Treatment Plant (WTP)

iv) Clear Water sump and pump house (CWPH)

2.1 RAW WATER PUMP HOUSE

There is one raw water pump houses in a system located at Vishnupuri

Raw Water Pump House (Jack well-CIDCO):

The jackwell was constructed in the year 1985 as part of water supply system for CIDCO area

of Nanded city. Pump house consists of jack wells of 8.0 m diameter. Jackwell is located at

500.0 m upstream of Vishnupuri dam on the right bank of Godavari River. Water is drawn

from inspection wells with opening of 600 mm fitted with mild steel wire mesh to protect the

entry of debris into jackwell. Bed of the river is 343.0m. Drawal is of water is at 340.0 m

through intake well at 41.5 m distance into bed from jackwell. Overall capacity of jack well is

for 12 Mld water supply. There are two pumps (1W+1S) in the jackwell with 100% stand by

arrangement. Jackwell has spare capacity to accommodate two more pumps.

2.2 RAW WATER TRANSMISSION SYSTEM

Raw water from the jack well is pumped to the inlet of water treatment plant. The details of

the raw water mains are as follows:

Table-II.1: Details of Raw Water pumping mains

Sr.

No.

Location

of

Jackwell

WTP Diameter

(mm)

Length

(meter) Material

1 Vishnupuri CIDCO WTP 450 4500 Cast Iron (CI)

Page 13: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page2 of 6

2.3 WATER QUALITY AND WATER TREATMENT PLANT (WTP):

Presently raw water is treated at various treatment plants. All the existing water treatment

plants are of conventional type having aeration, clarification and filtration as main units. All

the treatment plants are functioning to their design standards. The treated water quality is

within the limits of the CPHEEO drinking water standards. The capacity and their area of

coverage is given in table II.2. Civil structures of the WTP are in Reinforced Cement Concrete.

All treatment unit are Structurally in good condition. However the shutter of steel windows of

filter house and chemical are corroded condition and requires replacement. Size of windows

for filter house and chemical house is 2 nos.18.0mx2.0m and 2 nos.15.0mx2.0m respectively

Table II.2: Details of Water Treatment Plant

Sl.

No. Source

Allocated

Quantity

from the

source

(MLD)

Installed

Capacity

(MLD)

Current

Water

Drawl

(MLD)

Reservoirs

coverage

3 Vishnupuri 4.0 12.0 10.0 CIDCO township

Clear Water Pumping stations, Sump and pump house:

Treated water is then pumped directly to sump and from the sump; water is pumped to

elevated service reservoir. The clear water pump house is located within the water treatment

premises.

i) Clear water pump house at CIDCO water treatment plant

Sump and Pump house

There are two-sump and pump house in CIDCO area. They are in Reinforced Cement

Concrete material. Civil works are structurally in good condition. The sump and pump house

is within the ESR premises. The technical details of the same are not available. First sump

and pump house is at about 300-meter distance from WTP. Three pumps are housed in the

pump house with 2 working and 0 standby (under repair). Second sump and pump house is at

1.0 km distance from WTP. Four pumps are housed in the pump house with 2 pumps working

and two standbys. The details of the pumps aren’t available. Hence the details of pumps aren’t

given in this report.

Clear water Transmission System

Water from WTP sump is pumped to two sumps at different locations. Transmission system

is shown in Exhibit 2. Cast iron pipes are used in the transmission system.

Clear water from WTP is pumped to at sumps through 450 mm CI main with braches to

sumps of 250 mm diameter. Length of pumping main is 1.0 km approximately.

2.4 RESERVOIRS

There are two sumps and two Elevated Service Reservoirs in CIDCO area., Capacity of

sumps are 1.30 Ml and 1.20 Ml. and ESR capacity of related sumps at each location is 1.2 Ml.

Existing storage is about 40% of treatment capacity.

Page 14: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page3 of 6

2.5 WATER DISTRIBUTION SYSTEM

Details for distribution system are not available with NWCMC.

2.6 ELECTRICAL SYSTEM

Power Supply Arrangement

2.6.1 CIDCO Raw Water Pumping Station

Existing System

The pumping station gets 11kV supply from MIDC substation which is 5kM away and its not

a dedicated feeder.

The incoming 11kV line is terminated on a two pole structure consisting of CT-PT metering

set, disconnector and drop-out fuse with outgoing connected 1 nos 11kV / 0.433kV , 315kVA

transformer. The secondary of transformer is connected 250kVA Voltage stabilizer to correct

voltage fluctuations.

The MCC is having 1000A ACB as incomer and two numbers outgoing feeders for starter

panels of 160 kW Motors and SFU feeders for fixed capacitors.

Observation

They have voltage fluctuation problem so pump starting is a problem.

The MCC is totally in bad shape

There is no proper cable management system

The point wiring has been done using MS conduit and has completely rusted has to be totally

replaced

There is no proper lighting inside the machinery area.

2.6.2 CIDCO 12mld Water Treatment Plant And Clear Water Pumping Station

Existing System

The pumping station gets 11kV supply from Waghala substation which is 2.5kM away and its

not a dedicated feeder.

The incoming 11kV line is terminated on a two pole structure consisting of CT-PT metering

set, disconnector and drop-out fuse with outgoing connected 1 nos 11kV / 0.433kV , 150kVA

pole mounted transformer. The secondary of transformer is connected 125kVA Voltage

stabilizer to correct voltage fluctuations.

The CWPS MCC is having incomer 200A MOCB and SFU outgoing star-delta feeders to

45kW motors and on feeder to WTP.

The WTP has 5.5kW Floculator, 4.5 kW Clarifier bridge, 15kW Air compressor.

Observations

Page 15: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page4 of 6

They have voltage fluctuation problem so pump starting is a problem.

The CWPS MCC and WTP MCC is bad shape.

There is no chlorination system.

There is no proper cable management system

The point wiring has been done using MS conduit and has completely rusted has to be totally

replaced

There is no proper lighting inside the machinery area

2.6.3 CIDCO 35mld New Water Treatment Plant and Clear Water Pumping

Power Supply Arrangement

The location of 35mld WTP and Clear water pumping station is located 1 kM away from

existing WTP. The nearest substation is Waghala Grid Substation which is approximately

4kM away from proposed site, 11kV dedicated feeder will be installed from Waghala grid

substation to New WTP Site.

2.7 MECHANICAL SYSTEM

2.7.1 CIDCO RAW WATER PUMPING STATION

Existing System:

The pumps at this pumping station were installed and commissioned in 1985 and pump raw

water to CIDCO WTP. There are two pumps in the pump house (one working + one standby)

each having a capacity of 580 m3/hr and head of 52 mtr.

Individual pump delivery pipe is connected to discharge header inside the pump house. One

non-return valve and one manual sluice valve is provided on delivery pipe.

Pressure gauges are installed on the pump delivery but are not in working condition.

A 5 Ton manual Crane installed for the purpose of pumping unit maintenance.

Observations:

It is observed that the pumping units are very old and excessive heating is observed.

There is no level, flow measurement instrument provided.

2.7.2 CIDCO WATER TREATMENT PLANT

Existing System

The Raw water to the treatment plant is fed from CIDCO Raw Water Pumping Station. The

treatment scheme consists of a Cascade aerator, flash mixer, 2 no. Clariflocculator, three

Gravity sand filters. Also, the water treatment plant consists of Alum handling cum dosing

Page 16: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page5 of 6

system, Lime handling cum dosing system and Chlorine handling cum dosing system. This

WTP of 12 Mld was installed and commissioned in the year 1985-86.

The raw water inlet from the cascade aerator is through Parshall flume with flow meter. The

flow meter is not working.

Presently due to Algae problem, bleaching powder is dosed just after the Cascade Aerator.

Alum solution is added after the parshall flume in the WTP with a constant head dosing tank

located in the inlet channel just before the flash mixer. Flash mixer is provided for mixing

alum solution with raw water. The flash mixer is in working condition. Three tanks are

provided for preparation of alum solution with one mixer in each tank. The mixers are

corroded and need replacement. The piping and valves for the alum tanks are corroded and

need refurbishment/replacement.

Clariflocculator is provided for WTP for sedimentation. The clariflocculator are reported not

in proper working condition and breaks down frequently. The clarifier scrapers are partly

corroded.

Two tanks are provided for preparation of lime solution with one mixer in each tank. The

mixers are not in working condition. The piping and valves for the lime tanks are corroded.

Presently lime is not dosed.

The clarified water from the clariflocculator is then filtered by Three (3) gravity sand filters

each filter has an inlet isolation gate which are corroded and difficult to operate. The filter

bed valves are leaking badly. It is reported that pressure drop across the bed is very high due

to poor quality of sand media. The loss of head meter and rate of flow meter on the filter beds

are not working. The valves in the filter beds are not functioning properly and majority of the

valves are leaking from the gland and flange joints. The two Air blowers installed for back

wash of filters are in completely bad shape. One of them is not in service. Back wash is

carried out by water from the overhead backwash tank. Pure water is stored in the backwash

tank and used for backwashing of the filters.

Post-chlorination system though provided but is now completely out of service. Presently

chlorine is directly dosed from the cylinder into the pure water header. Safety kit items are not

in proper order.

Observations:

Most of the mechanical systems in the plant are non operational and thereby affect the quality

of water produced.

No proper chemical dosing is being carried out due to non existent measuring and control

system.

The chlorine is dosed in a crude way, thereby creating a very hazardous situation.

Filters are not properly backwashed, thereby reducing their output in terms of both quality

and quantity.

2.7.3 PURE WATER PUMPING STATION – CIDCO

Page 17: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page6 of 6

The pumping station is designed for a configuration of 1W+1S system with each pump

capable of pumping 6 Mld of pure water. Presently both the pumps are in operation. The

pumps are vertical turbine pumps. These pumps were installed in the year 1989.

Individual pump delivery pipe is connected to a main header discharge header inside the

pump house. One non-return valve and one manual sluice valve are provided on delivery

pipe.

Two horizontal centrifugal pumps of 26 m3/hr with a discharge head of 30 m are installed to

meet the requirement of engineering college.

A manually operated overhead hoist of 5T capacity is provided for handling of equipment

located in side the pump house.

Pressure gauges are installed on the pump suction and delivery. None of the pressure gauges

are in working condition.

No flow-measuring, level measuring instrument is provided in the system

Observations:

The pumps are quite old and break down frequently and need replacement.

Flow measuring and level measuring instrument need to be installed for proper monitoring of

water pumped and for protection of the pumps.

Page 18: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page1 of 13

CHAPTER – III

SYSTEM PLANNING CRITERIA

3.1 GENERAL

This Chapter discusses the basis for identifying Design Parameters to be used in the design of inlet

mains to service reservoirs and the components of distribution system covered under the project.

Design horizon has been considered on the basis of year of Gur-ta Gaddi on September, 2008.

Accordingly horizon year would be as 2023 and 2038.

3.2 POPULATION

Population figures would be used as given in City Development Plan (ILFS). The population for

the year 2038 is obtained by extending the graph given in CDP. The population for Nanded (South

of Godavari) for the year 2023 and 2038 are given in Appendix 1 Table1.

3.3 WATER DEMAND

Water demand projections are carried out with per capita rate of 135 lpcd at consumer end and

losses up ward for gross demand projections as per CPHEEO manual. Demand is given in

Appendix 1 Table-.3

3.4 INLET MAINS TO SERVICE RESERVOIRS AND TRUNK MAINS

Flow Rate

The inlet mains to service reservoirs and trunk mains will carry water for 22 hours. To cater for

emergencies, these mains are designed for 1.1 times the daily average flow. A minimum residual

head of 2.0 m is considered over the full level of the reservoir. The full supply levels of the

existing reservoirs proposed to be used in the system. The proposed reservoirs are marked on the

Exhibit-2. The inlet main system would be in the form of a tree network of pipelines supplying

water to various reservoirs. The design of the trunk system is done using Environmental

Protection Agency (EPA) net software. The inlet mains to the service reservoirs are designed to

cater projected flows for the year 2038 and are checked for intermediate (2023) flow conditions.

3.5 LOCAL DISTRIBUTION SYSTEM

Service Storage

Storage in the service reservoirs have to be provided considering balancing of inflows and

outflows and emergency including water for fire fighting. The service storage in the horizon year

2023 is worked out presuming a 22-hour water supply. A 22-hour consumption pattern based on

assessment of water consumption every hour under local conditions has been synthetically

developed and presented in Figure III.1. The cumulative inflow and outflow for a service reservoir

are depicted in Table-III.2. From this curve, the balancing storage works out to 33 percent of the

daily water supply. The total storage to be adopted for design is considered as 33 percent

including emergencies and fire fighting requirements. These figures are taken from sample studies

carried out under this assignment.

The existing storage and proposed reservoirs in NWCMC area is given in Appendix 1, Table 2.

The storage required for this satisfaction would be for about 8 hours or about 33 percent of supply,

which is for 6 hours of supply.

Page 19: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page2 of 13

3.6 HAZEN-WILLIAMS C-VALUE

In existing distribution system, Cast iron pipes have been widely used in the past. As the soil strata

is black cotton soil which is of corrosive nature, recently, internal mortar lined ductile iron pipes

have been laid in NWCMC area for trunk distribution mains and local distribution mains to take

care of corrosion of pipes.

Due to corrosion, carrying capacity of cast iron pipes reduces. The deterioration of C- value with

ages for cast iron pipes would be considered as in the table given below:

The design of transmission system is carried out by considering C value of 130 for Ductile Iron

(DI) and Mild Steel (MS).

Based on material and age of the pipe, following C-values would be adopted for design of

distribution system.

Table III.1: Hazen William C -Values for different pipe materials (Distribution Pipes)

Material

Age (years)

C value

Cast iron (CI) New 100

10 90

15 80

Ductile iron (DI) New & old 120

Mild steel (Mortar lined) New & old 120

Proposed pipes

All the proposed pipelines upto 750 mm is of DI material and pipelines above 750 mm are of

mortar lined MS pipes.

3.7 PEAK FACTOR

The peak factor with the twenty-two hours consumption pattern as shown in Fig.III.2-, which is

referred earlier, will be about 2.5. This peak factor would be used in the design.

3.8 LOCAL DISTRIBUTION NETWORK ANALYSIS

Distribution System

The proposed distribution zones are planned considering coverage of the existing distribution

network of the nearby existing reservoirs. In addition to this following points have been

considered while rezoning:

i. Geographical features and ground profile

ii. Population densities

iii. Location of existing reservoirs

iv. Availability of land to build additional reservoir at existing reservoir site and at new locations

v. Feasibility of laying additional mains

vi. Manmade barriers like railways, major roads etc.

Page 20: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page3 of 13

There is a large variation in demand for the year 2023 and 2038. Therefore laying of pipes now for

the year 2038 is not advisable. Hence water distribution would be design for the requirement for

the year 2023. However transmission system is designed for the year 2038 as it is to be laid once

on major roads.

3.9 RESIDUAL PRESSURES IN THE DISTRIBUTION SYSTEM

Presently the houses in the Nanded Waghala Municipal Corporation area are in the range of

Ground to Ground+1 Storied. Therefore system is designed for minimum residual pressure of 12

m at nodal points.

3.10 MINIMUM DIAMETER OF THE PIPE

The minimum proposed diameter of pipes considered in the analysis is 100 mm and no service

connections would be given from a pipe more than 200 mm dia. Wherever there is single pipeline

on a road of size above 200mm, a parallel line of 100 mm is proposed for giving consumer

connections.

3.11 MISCELLANEOUS CONSIDERATIONS

Bulk Flow Meters

After a careful study of the system’s requirements, bulk flow meters have been proposed at 12

strategic points in the system such as water treatment plants, service reservoirs and pumping

stations to monitor the quantum of water being handled at these places. Magnetic type full-bore

flow meters have been recommended

A provision is also made for bulk meter at existing stand post for measurement of flow. About 40

no 100 mm size meters are proposed in the system.

Pressure Gauges

Monitoring of the water supply system would include monitoring of the pressures and flows in the

field.

For monitoring pressures in the local distribution network in the field, it is proposed that pressure

points be made and kept ready at all important road junctions and at critical points as sudden dips

or humps. Whenever required, pressures could be monitored easily at these points.

In every zone about 5 points are anticipated. A total of 30 points are proposed.

Level Indicators

During studies conducted for identification of rehabilitation measures for service reservoirs in the

system it was noted that level indicators at many of these locations were either not in working

condition or missing. A provision is now made to have float type level indicators at all these

locations. Level indicators are proposed for all the new reservoirs.

Valves

For operation and maintenance of any intermittent supply system a minimum number of valves are

necessary. Ideally in a continuous supply system every branch should have a valve to enable

isolation of lines in stretches.

Now that NWCMC is planning for leak detection work on a large and continuous basis, the system

should have adequate number of valves to isolate the pockets.

Page 21: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page4 of 13

3.12 STRUCTURAL DESIGN CRITERIA FOR ELEVATED SERVICE RESERVOIRS

Standards And Codes

The following codes (latest edition) are applicable for the design of various structures.

a) IS 456: Code of Practice for Plain and Reinforced Concrete.

b) IS 800: Code of Practice for General Construction in steel.

c) IS 875: Code of Practice for Structural Safety of Buildings – Loading Standards.

d) IS 1893: Criteria for Earthquake resistant design of Structures. (Refer 4.4 also

e) IS 3370: Code of Practice for Concrete Structures for the Storage of Liquids (Part I to IV).

.

Geotechnical Data

Detailed geotechnical investigation is proposed to be carried out at the site. From the report of a

preliminary geotechnical investigation carried out earlier, the safe soil bearing capacity for the

design and cost estimating of the ESRs can be taken as 100 KN/sq m. The detailed report and the

recommendations of the geotechnical investigation agency, after review, regards Safe Bearing

capacity, type of foundation, ground water table and other related matters, will be followed in the

design of foundations.

Loads

The ESRs for this project would be designed for the following loads –

Dead Loads

Dead loads would include the weight of all permanent construction including walls, staging,

floors, finishes, roof and staircase

The dead loads of materials would be as per IS 875 Part 1. The minimum dead loads of frequently

used materials in the design of ESRs would be considered as follows:

(a) Weight of water: 9.81 kN/m3

(b) Weight of soil (irrespective of strata

available at site and type of soil used

for filling, etc.). However, for checking

stability against uplift actual weight of

soil as determined by field test would

be considered: 20.00 kN/m3

(c) Weight of plain concrete: 24.00 kN/m3

(d) Weight of reinforced concrete: 25.00 kN/m3

(e) Weight of plaster to masonry 18.00 N/m2 per mm thickness

surface:

Live Load

Live Load would include the superimposed loads due to the use/maintenance of the ESRs not

including dead, wind or earthquake load. The live loads would be as per IS 875 Part 2. The

minimum live loads on floors for different uses frequently required in design would be as follows:

(a) Live load on roofs 1.50 kN/m2

(b) Live load on all other floors,

Page 22: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page5 of 13

Walkways and platforms 5.00 kN/m2

(c) Live load on stairways 5.00 kN/m2

.

Wind Load

Wind load on ESRs would be as per IS: 875 (Part 3). Basic Wind Speed (Vb) for Nanded is 39

m/sec. For calculation of Design Wind Speed (Vz) the following coefficients would be adopted:

K1 = Probability Factor for a return period of 50 years = 1.0

Terrain, height and structure size factor (determined from Table 2 of IS: 875 Part 3)

Topography Factor =1.00 for sites on level ground. For sites on sloping grounds, K3 would be as

per Appendix C of IS 875 Part 3.

Vz = K1 * K2 * K3

and Design Wind Pressure

Pz = 0.06 Vz2

Where Pz = Design wind pressure in N/m2 at height Z

Seismic Load

Seismic loads would be computed according to IS 1893 -1984 for the ESRs.

As per IS 1893 – 2002, Nanded falls in Zone II of Seismic map of India. The importance factor to

be considered for design of ESRs would be taken as 1.5.

Combination of Load Cases

A judicious combination of the loads specified above keeping in view the probability of:

a) Their acting together and

b) Their disposition in relation to other loads and severity of stresses or deformations caused

by combinations of the various loads is necessary to ensure the required safety and

economy in the design of the ESRs.

Keeping the above aspect in view, the following load combinations, whichever combination

produces the most unfavorable effect in the ESRs, foundation or structural member concerned will

be adopted.

a) DL

b) DL + LL

c) DL + WL/EL

d) DL + LL + WL/EL

Where DL = dead load

LL = live load

WL = wind load and

EL = seismic load

DESIGN REQUIREMENTS FOR RCC ELEVATED SERVICE RESERVOIRS (ESRs)

i. All non-water retaining concrete members would be designed as per limit State Method of IS 456.

All water retaining concrete members would be designed as per IS 3370 Parts I, II and IV.

Page 23: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page6 of 13

ii. ESRs would have a circular container with a domed roof. The base would be flat supported on

beams.

iii. The staging supporting the ESR would consist of RCC columns and tie beams at intermediate

levels. The columns would be circular in shape.

iv. Minimum grade of concrete for staging and foundations would be M25 and for the container

including roof would be M30. For grade slabs, the concrete grade would be M15

v. Minimum cement content for M25 & M30 grade concrete would be respectively 350 kg / cum and

400 kg / cum.

vi. Cement of grade 43 conforming to IS 8112 would be used for the staging and of grade 53

conforming to IS 12269 for the water container. Sulphate resisting cement conforming to IS 12330

would be used if sulphate content in ground water and/or soil is high.

vii. Blinding and leveling concrete would be PCC of minimum 75 mm thick of mix 1:4:8.

viii. Water cement ratio would not be more than 0.45. Plasticizers of reputed makes may be used to

reduce the water cement ratio up to 0.40.

ix. Minimum dimensions for the concrete members would be as below

(a) Circular Column 400 mm

(b) Container Wall 200 mm

(c) Container bottom slab 150 mm

(d) Container dome slab 100 mm

(e) Parapets / Walkways 100 mm

(f) Column footings / raft 300 mm

(g) Beams 230 mm

x. The minimum cover to the main reinforcing bars for different members would be as follows unless

stated otherwise

For non water retaining members / surfaces:

a) Slab (Floor, roof, Staircase) 30 mm

Beams (Sides, bottom & top) 40 mm

Columns 50 mm

Pedestals (in contact with earth) 50 mm

Foundations 50 mm

For water retaining members / surfaces:

a) Face in contact with water 45 mm

Page 24: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page7 of 13

b) Face away from water and not

in contact with earth 30 mm

c) Face away from water and

in contact with earth 40 mm

d) Soffit of roof slab 45 mm

e) Foundations 50 mm

xi. Maximum 40mm aggregate size would be used for footings and rafts and with a maximum 20mm

aggregate size for all other structural members. Selected aggregates of proper sizes would conform

to IS 383.

Reinforcing Steel:

(a) Reinforcing bars and wires would be Thermo Mechanically Treated type conforming to grade Fe

415 or plain round bars conforming to IS 432 Grade I. Reinforcing bars higher than 32 mm

diameter would be avoided. Welding of laps for bars higher than 32 mm diameter (if required as

per design) would be done as per IS 2751.

(b) Minimum reinforcing steel would be as per IS 3370 for water retaining members and as per IS 456

for non-water retaining members.

(c) Maximum spacing of main reinforcement in slab or walls would not be more than 150 mm c/c.

The spacing of distribution steel or vertical bars in column would not be more than 300 mm.

x. The safe bearing capacity of the founding stratum, type and depth of foundations would be as per

3.0 above.

xi. Foundations would be designed to have a factor of safety of 1.5 against sliding and 2.0 against

overturning.

xii. Permissible deflections for concrete members would be as per IS 456 clause 23.2.

xiii. At the floor level of the ESRs, a cast iron or stainless steel grate would be provided over the

supply outlet and scour outlet. The grates will be of 20 mm x 20 mm with square frames.

xiv. The overflow outlets would not be connected to the distribution system. The overflow outlet will

always be left open.

a. Approved quality waterproofing compound would be added during concreting of all liquid

retaining structures in the proportions specified by manufacturer or 2% by weight of cement,

whichever is higher.

b. Two coats of Bitumen paint would be applied on the soffit of roof slab of the ESRs.

c. Water tightness testing of container of the ESRs would be done in accordance with IS: 3370,

Part I.

d. Curing period for water retaining members would be minimum 15 days.

Miscellaneous Steel Structures

General

The requirements for design, material and fabrication including connections of pipe supports and

miscellaneous structural steelwork like ladders, hand railing etc. are covered in this section.

Page 25: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page8 of 13

Unless otherwise specified, steel for hot rolled structural sections and plates would conform to IS

2062. Steel tubes for structural purpose would conform to IS 1161.

Design Method

All designs and details would be in compliance with IS 800. Working stress method will be

adopted. The allowable stresses and slenderness ratios would be as per IS 800

Connections

All shop connections would be welded (minimum structural weld 4mm throat thickness). Welders

will be certified before they are allowed to work.

Miscellaneous Structures

Ladders

Mild steel Ladders would be 450 mm wide and would not exceed 9m of straight run. A safety

cage would be provided for ladder higher than 6 m. For reservoirs, the ladders would be painted

with epoxy paint.

Platforms and Walkways

The minimum width of platforms and walkways would be 1000 mm.

Hand railing

Hand railing would be provided on both sides (on one side for spiral staircase) of all stairways,

platforms and walkways. Hand railing would consist of 32 mm dia (light) G.I. tubular member as

top rail, mid rail, lower rail and posts. Posts would be at 1.5 to 2.0m center to center

approximately. Height of handrail would be 1.0m.

3.13 GENERAL DESIGN CRITERIA FOR ELECTRICAL SYSTEM

All electrical equipment will be rated for 50°C designed ambient temperature. The installation will

generally conform to Indian Standards / IEC.

The following assumptions shall be made to arrive at the load

a) Load Factor

i) Main motor : 0.9

ii) Auxiliary load, gate valve motors, etc. : 0.9

iii) Lighting load : 1.0

b) Diversity Factor

i) Main motor : 1.0

ii) Auxiliary load, gate valve motors, etc. : 1.5

iii) Lighting load : 1.2

c) Power factor of Motors shall be as per manufacturer’s catalogue

d) Efficiency of Motors shall be as per manufacturer’s catalogue

e) Energy efficient, high performance motors are proposed for main pump motors for optimize

utilization of energy.

Page 26: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page9 of 13

Protections:

The following protections are proposed for switchboard, motors and other plant feeders.

a) 11kV Switchgear Main Transformer Feeders

i) IDMT over current, Instantaneous over current and Instantaneous earth fault

protection

ii) Transformer differential Protection only for ratings above 5 MVA.

iii) Transformer auxiliary protection (e.g. WTI, OTI, Bucholz, etc.)

Incomer and Outgoing Feeders i) IDMT over current, Instantaneous over current and Instantaneous earth fault

protection

b) LV switchboard

i) The ACB feeders shall be provided with electronic releases for IDMT Short circuit,

over current and earth fault.

ii) The ACB bus coupler feeders shall be provided with electronic releases for IDMT

short circuit and over current.

iii) The MCCB feeders shall be provided with Thermo magnetic releases for IDMT Short

circuit, over current and earth fault.

c) LV Motors

i) For motor ratings less than or equal to 132kW shall be provided with overload

protection by thermal (bimetal) relays in all the three phases to trip with single phase

preventer (SPP)

ii) For motor ratings above 132kW shall be provided electronic comprehensive motor

protection relay consisting of following protection thermal overload, locked rotor,

short circuit, negative sequence and earth fault.

Metering The following metering shall be provided.

a) 11 kV Incomer

i) Ammeters with ammeter selector switch

ii) Voltmeter with voltmeter selector switch

iii) kW meter

iv) Power factor meter

v) Kilowatthour meter

iv) Frequency meter

b) 11 kV Outgoing Feeders: Ammeters with ammeter selector switch

c) LV Incomer

i) Ammeters with ammeter selector switch

ii) Voltmeter with voltmeter selector switch

iii) kW meter

Page 27: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page10 of 13

iv) Power factor meter

v) Kilowatthour meter

v) Frequency meter

d) Indication

i. 11kV Incomer feeders: Circuit breaker ON, OFF & TRIP, spring charged, control

supply healthy and trip circuit healthy.

ii. LV Incomer: Mains ON (red, yellow & blue)

iii. LV Motor Feeders: Motor ON, OFF & Trip indication (Red, green & Amber)

The capacity of the transformers shall be decided based on 100 % standby (redundancy) i.e. in the

event of outage of any one of the transformer, other transformer can supply the complete load.

Here since the main motors are H.T and auxiliary motors L.T separate transformers are provided

for H.T and L.T.

L.T motor up to and equal 5.5kW shall be provided with DOL starters, motor ratings above 5.5kW

up to or equal to 250kW shall be provided with Star delta starters and all motor above 250kW shall

be provided with FCMA soft starters.

If motor ratings go beyond 250kW then H.T motors shall be used with voltage supply

3.3kV/6.6kV. The method of starting shall be either DOL or FCMA soft starter such that voltage

dip during shall be with in 15%.

The main LV switchboard is proposed with 'Form-4' enclosure as per the Indian Standards. All

indoor boards/panels and motors are proposed with a degree of protection of IP 54, while all

outdoor equipment will be with a degree of protection of IP55. Necessary metering, protections

and indications will be provided on the LV switchboard.

All power cables shall be sized based on continuous current capacity, permissible voltage drop and

short circuit current rating. The voltage drop will be limited to 2.5 % at rated equipment current

rating. The other rating factors for variation in ground temperature, variation in ambient air

temperature, grouping of cables, depth of laying, etc. shall also be considered for cable sizing.

All LV power cables up to 6 sq.mm shall have stranded copper conductors and above that it

shall be stranded aluminum conductor. Power cables shall be XLPE / PVC insulated, extruded

inner and outer sheaths and galvanized flat/wire armouring.

The main L.V cable from transformer secondary to the incomer of main L.V switchboard, which is

laid directly in ground, shall be XLPE insulated.

The outgoing cables from main L.V switchboards and Sub distribution boards, which are laid on

cable trays and trenches, shall be PVC insulated.

Control cables will be with stranded copper conductor, PVC insulation, extruded inner and outer

sheaths and galvanised flat/wire armouring

The illumination levels for various areas shall be considered as follows:

Area Illumination level (Lux)

Pump House 200

Office Room 300

Switchboard Room 200

Cable Galleries 150

All other indoor areas 150

Outdoor plant area and Road 10 – 20

Page 28: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page11 of 13

The earthing shall be carried out as per IS 3043. The material of earthing conductor will be GI.

The values of fault level for designing the electrical system shall be based on transformer capacity,

its impedance and system fault level. Fault clearing time for sizing of earth conductor will be taken

as one second.

While sizing the buried earth conductor, a corrosion allowance of at least 20 % shall be taken.

Plant earthing system shall be designed such that the overall earthing grid resistance is maximum

one ohm.

Main earthing conductors outside and inside the building shall be planned in such a manner

various equipment are connected to earthing system by two connections in a reliable manner.

Earth leakage Circuit Breaker (ELCBs) shall be provided at the incomer of Lighting panels.

Compliance to Standards:

The electrical safety and clearances will be maintained as per Indian Electricity Rules and CBIP

guidelines. The equipment selection and electrical installation will generally conform to the latest

edition of Indian Standards (IS) and the International Electro-technical Commission (IEC).

Page 29: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page12 of 13

Table III. 2: ASSESSED MASS CURVE (INFLOW/OUTFLOW vs. TIME)

Time Consumption

Rate (%)

Inflow

Rate (%)

Cumulative

Inflow (%) (%)

Difference

(Cum. Inflow-

Cum. Outflow)

Time

MID NT. 0.00 0.00 0.00 0.00

1 AM 0.00 0.00 0.00 0.00 0.00 1 0.00

2 AM 0.00 4.55 4.55 0.00 4.55 2 0.00

3 AM 0.00 4.55 9.09 0.00 9.09 3 0.00

4 AM 5.00 4.55 13.64 5.00 8.64 4 1.20

5 AM 11.38 4.55 18.18 16.38 1.81 5 2.73

6 AM 11.38 4.55 22.73 27.75 -5.02 6 2.73

7 AM 11.38 4.55 27.27 39.13 -11.85 7 2.73

8 AM 11.38 4.55 31.82 50.50 -18.68 8 2.73

9 AM 5.00 4.55 36.36 55.50 -19.14 9 1.20

10 AM 0.00 4.55 40.91 55.50 -14.59 10 0.00

11 AM 0.00 4.55 45.45 55.50 -10.05 11 0.00

NOON 0.00 4.55 50.00 55.50 -5.50 12 0.00

1 PM 0.00 4.55 54.55 55.50 -0.95 13 0.00

2 PM 0.00 4.55 59.09 55.50 3.59 14 0.00

3 PM 0.00 4.55 63.64 55.50 8.14 15 0.00

4 PM 0.00 4.55 68.18 55.50 12.68 16 0.00

5 PM 8.00 4.55 72.73 63.50 9.23 17 1.92

6 PM 8.00 4.55 77.27 71.50 5.77 18 1.92

7 PM 8.00 4.55 81.82 79.50 2.32 19 1.92

8 PM 8.00 4.55 86.36 87.50 -1.14 20 1.92

9 PM 8.00 4.55 90.91 95.50 -4.59 21 1.92

10 PM 4.50 4.55 95.45 100.00 -4.55 22 1.08

11 PM 0.00 4.55 100.00 100.00 0.00 23 0.00

MID NT. 0.00 0.00 100.00 100.00 0.00 24 0.00

100.00

Total 100.00 100.00

STORAGE

REQD.

>>>>>

Storage

capacity 31.82 %

Page 30: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page13 of 13

Fig. III.1: Mass Curve

Mass Curve

0.00

20.00

40.00

60.00

80.00

100.00

120.00

MID

NT.

2 AM

4 AM

6 AM

8 AM

10 A

M

NOON

2 PM

4 PM

6 PM

8 PM

10 P

M M

ID N

T.

Time

'% C

um

ula

tive

flo

w

Cumulative inflow

Cumulative outflow

Fig. III.2: Consumption Curve

Consumption curve

0.00

2.00

4.00

6.00

8.00

10.00

12.00

2 4 6 8 10 12 14 16 18 20 22

Time (hr)

Co

nsu

mp

tio

n in

%

Consumption rate in %

Inflow rate

Page 31: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

1 of8

CHAPTER – 4

PIPE MATERIAL SELECTION ASPECTS

4.1 GENERAL

This study assesses the suitability of pipes of different materials for use in water supply

systems for Nanded. Two groups of pipelines as given below have been considered.

(a) Trunk Mains/Transmission Mains (mostly 300 mm and above) between water

treatment plants and service reservoirs and

(b) Local distribution Lines (mostly 100 mm to 400 mm) down stream of service

reservoirs.

The materials covered are:

• High density polyethylene (HDPE)

• Medium density polyethylene (MDPE)

• Polyvinyl Chloride (PVC)

• Asbestos Cement (AC)

• Glass fiber reinforced plastics (GRP)

• Cast Iron (CI)

• Mild Steel (MS)

• Electrically welded steel (EWS)

• Ductile Iron (DI) and

• Prestressed concrete (PSC)

The main parameters which have been discussed are available sizes and lengths, applicable IS

codes, basic cost economics, weight, flexibility, available working pressure ratings, tensile

strength, impact strength, ease of tapping and repair, general availability in India, availability

of plant and skilled manpower for manufacturing, laying and maintenance, availability of

corrosion control techniques, ease of locating underground pipes, special bedding

requirements, laying speed and performance experience . Table-I-list the parameters of

various pipe material.

Major characteristics of various pipe materials are brought out as follows.

4.2 PIPE MATERIALS

HDPE

HDPE pipes are available in sizes up to 630 mm OD but they are commonly used up to 315

mm OD. The material is light, has very good impact strength, flexibility and corrosion

resistance. The jointing can be done by butt-welding, insert jointing or by flange jointing and

requires skilled manpower. HDPE pipes are tough and resilient and conform to the

topography of land when laid above ground or in trenches. They can bend to some extent

thus reducing use of specials like bends, elbows etc., there by reducing installations costs.

HDPE pipes are easy to carry and install because of their lightness. Metallic tags could be

fixed at regular intervals for ease in locating the pipe with a pipe locator. These pipes have

been used in India for pipeline laid under backwaters. The pipe has a very high C-value,

which does not deteriorate much with age. The bedding material has to be free and sharp

edges. Fine sand or screened excavated material is ideal. It is the costliest material as

compared to other pipes available in its range.

Page 32: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

2 of8

MDPE

MDPE pipes are available in sizes from 20 mm to 110 mm. MDPE belongs to family of

plastic pipes. A wide range of injection moulded fittings, including toes, elbows, reducers,

caps, pipe saddles, inserts and threaded adapters are available. Metallic tags need to be fixed

at regular intervals for locating the pipe. They have a smooth surface and hence the Hazen

Williams roughness co-efficient ‘C’ is high. Thus the carrying capacity is not reduced with

age. Special care needs to be taken about the bedding material, which should be either fine

sand or screened excavated material. If laid over ground they should be adequately supported

to prevent sagging. Also, storing of the pipes needs extra care. These pipes are ideal for

service connections. Tapping of service connections can be given through a saddle only.

Smaller diameter mains are coil able and can be easily bent during installation, eliminating

the use of specials like bends, elbows etc. thereby reducing fitting and installation costs.

They are lighter in weight and can be carried to heights as on hills. They can withstand

movement of heavy traffic. This would not cause any damage to the pipes because of their

flexural strengths. They have non-adherent surface, which reject any foreign materials,

which would impede the flow.

PVC

This is available in sizes up to 250 mm. The material is light, has fairly good impact strength,

high corrosion resistance and a high C-value. The pipes are easy to carry and install because

of their lightness. They need however be protected from high temperature and ultra-violet

light and require proper handling and storage facilities. It is advisable not to lay PVC pipes

above ground to prevent discoloration, surface cracking and brittleness. PVC pipes are also

prone to rodent attack. Tapping requires saddles but requires skilled manpower. Metallic

tags at regular intervals can be provided for ease in locating the pipe with the pipe locator.

The bedding material has to be free from sharp edges. Fine sand or screened excavated

material is ideal. PVC is cheaper than CI and HDPE but more expensive than AC for sizes

available in its range.

AC

This is available in sizes of 80 mm to 600 mm. However it is commonly used in sizes of 100

mm to 600 mm. It is light, has very good corrosion resistance and a high C-value. It is the

cheapest available material. It has low impact strength. It can be drilled and tapped easily.

Provision of saddles at the point of service connections is necessary to avoid possible

leakages near connections. The pipe material is prone to attack by sulfate bearing soils. For

heavy traffic, a cover of at least 1.25 m is desirable on top of the pipe. For locating AC pipes

by a pipe locator, it is desirable to provide metallic tags on pipes at a fixed distance.

GRP

This is available in sizes of 400mm – 2400mm and has been introduced in India a few years

back. The commonly used sizes range from 400 mm to 2000 mm. These pipes have been in

use abroad for many years with satisfactory performance. The pipe is light, has good impact

strength and has a very good corrosion resistance. The bedding of these pipes has to be

formed using granular material compacted to a specific Proctor Density. This can be

achieved with proper supervision and control during laying. Jointing methods consist of

double bell coupling, flanged jointing, mechanical coupling and butt strapping which is

satisfactory but requires skilled manpower. It has a superior C-value; it is more or less on par

Page 33: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

3 of8

with internally coated and externally gunited MS for 500 mm and larger sizes. The pipe has

greater durability and high resistance to internal and external corrosion unlike CI and MS

which would require coatings to resist corrosion. Cost of GRP pipe is about 30-40 percent

more than MS pipe with internal mortar lined and external gunited.

CI

This is available in sizes of 80 mm – 1000 mm though the commonly used range is 100mm –

1000 mm. It is widely used in water supply systems in India because of its longer life. There

are examples of cast iron mains in India, which continue to give service even after a century

of use though with reduced carrying capacity. CI pipes can be used in soils and waters of

slightly aggressive character. It would be preferable to have inside mortar lining for CI pipes

if water is aggressive. This will also improve its C-value. They are brittle materials.

Breakage's are expected in transport of pipes. They aren't available with internal mortar

lining.

MS

This can be manufactured from mild steel plates for required sizes. The material has high

impact strength due to high ductility. Specials of all kinds can be fabricated without

difficulty. Due to elasticity, MS pipes adopt themselves to changes in relative ground level

without failure and hence are suitable for laying in ground liable to subsidence. Here MS

pipe with flexible joints provides additional safeguard against failure. MS pipes being

flexible are best suited for high dynamic loading. Because of its low resistance to corrosion,

MS mains need protection from corrosion internally and externally. The internal coating

would improve the C-value. Skilled manpower is available for laying and jointing of MS

pipes. Tapping and repairs are easy. When a pipeline has to be laid over waterway or

railway, MS pipes are most suitable due to their flexibility and their light weight compared to

CI/PSC pipes. When internally coated and externally gunited it marginally differs in cost as

compared to internally coated CI pipe.

EWS

Electrically welded steel pipes (EWS) are readily available from manufacturers. The

characteristics are similar to MS pipe as discussed above. Basic cost it is slightly cheaper

than MS. However, transportation cost (from manufacturer to city & then to site) of large

diameter pipes is higher than MS pipes.

Page 34: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

4 of8

TABLE IV.1

Pipe Material Sr

No.

Parameters

HDPE PVC AC GRP CI MS/SWS DI PSC

1. Available Sizes(mm) 20-530 16-250 80-600 400-2000 80-1000 150-2000

for EWS AS

Required

for MS

80-1000 400-1800

2. Lengths (M) 5-20 5-9 3-5 6-12 3-4 3-5

for EWS

Required

for MS

2.75-6 4-6

3. Applicable I.S codes

for Manufacture Laying

and jointing, Fittings

4984 7328

7634

4985 7634 1592 6530 12709 1536 1537

1538 6163

7181

3114

3589

5822

8329 784 1343

783

4. Weight Light Light Light Light Heavy Medium Medium Heavy

5. Flexibility Maximum Medium Rigid Medium Rigid Medium Medium Rigid

6. Available Working

Pressure Range Kg/Cm2

6. 2-10 Class

1 to 5

2.5-10 Class

to10

2.5-12.5

Class 5 to

25

3-15 Class

LA,A,B

6-12 As Required 16-25 As Required

7. Tensile Strength 2.4 5-6 N.A Longitudinal

102-

1054 KN/m

and Hoop

120-9000

KN/m

depending

upon size

15 40 42 N.A

8. Impact Strength Very good Moderate Nil Good Nil Very good Very good Nil

9. C-value 130-150 130-140 130-140 135-150 100-130 100-130 110-120 100-130

10. Corrosion Resistance Very Good Very Good Normally

good but

Very Good Low in cor

soils and water

Good More

Resistance with

Good

Page 35: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

5 of8

Pipe Material Sr

No.

Parameters

HDPE PVC AC GRP CI MS/SWS DI PSC

prone to

attack by

soils with

Sulphates

internal lining

and outside

guniting than

C.I

When

Fabricated

with

Quality

Control

11.

Jointing Methods Butt welded

joint,

flanged

joint, insert

joint

Socket joint AC coupling

joint, CI

detachable

joint

Double Bell

coupling

joint,

mechanical

coupling

joint Butt

strap joint

Spigot &

Socket Joint

with Rubber

ring, flanged

joint

Welded

joint,

Flanged joint

Spigot &

Socket joint

with Rubber

ring, Flanged

joint

Spigot &

Socket

Rubber ring

joint,

confined or

Roll on type

12. Ease of tapping and

repair

Saddles

required

expensive

Saddles

required

expensive

Saddles

required

expensive

Saddles

required

expensive

Easy Easy Easy Difficult

13. General Availability Available in

India

Available in

India

Available in

India

Available in

India

Freely

Available in

India

Freely

Available in

India

Available in

India

Available in

India

15. Availability of corrosion

control techniques

N.A N.A N.A N.A Cathodic

protection can

be carried out

Mortar lining

from inside

necessary for

corrosive

water

Inside mortar

lining outside

guniting

practiced,

cathodic

protection can

be carried out

In very

aggressive

soils Cathodic

protection

needed

N.A

16. Ease of location for Not easy Not easy Not easy Not easy Easy Easy Easy Easy

Page 36: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

6 of8

Pipe Material Sr

No.

Parameters

HDPE PVC AC GRP CI MS/SWS DI PSC

underground pipe

17 Special bedding requiremeFine sand or

screened

excavated

material

Fine sand or scr

excavated mater

Nil Granular

material

compacted to

specific

proctor density

Nil Nil Over 700 mm

design being of

a thin wall

special care

needed in

bedding &

backfilling

Nil

18. Laying speed Fast Fast Slow Fast Slow Slow Slow Slow

19. Pipe performance experienGood with

reputed

contractors

with unskilled

contract-ors

leakage at

joints

observed.

Does not

deteriorate

with time

Good with

reputed

contractors

with unskilled

contract-ors

leakage at

joints

observed.

Does not

deteriorate

with time

Good liable

to fracture,

if not

handled

carefully

Less

experience in

India

Very good Very good

corrodes

rapidly and

fails if not

protected,

repairs are

easy

No experience

in India Needs

protection from

corrosion

With

unskilled

contractors

manufacturin

g defects,

leakage at

joints and

failure

observed .

Performance

of reputed

contractor is

good.

20. Basic cost Economics

as compared to MS

1100-2000 mm

N.A N.A N.A Costlier than

MS

N.A 100 for MS

and 81 to 91

for EWS

NA Cheaper

than MS

Page 37: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

7 of8

DI

Ductile Iron, also called nodular iron or spheroidal graphite iron has superior mechanical

characteristics. Ductile iron differs from cast iron by its greater tensile strength and by its

significant proof stress and elongation after yield. For protection from corrosion, inside and

outside linings are provided. Cement mortar lining material is typically applied. A seal coat

of asphalt material can also be applied over the cement mortar lining. Polyethylene internal

linings and epoxy coatings and linings are also used for special applications. Thus it has the

durability of CI and the ductile strength of MS. However it needs proper bedding and

backfilling for sizes 700 mm and above due to its thin wall design. DI has edge over the CI

pipes though they have 10 percent more cost. They are available with internal mortar lining .

As the pipes are internal mortar lined , they posses higher C-value. Therefore they have more

hydraulic capacity than CI pipes of the same diameter. It has good impact strength. Due to

this, breakages are absent in transportation. They are more corrosion resistant. Laying ,

jointing, and operation, maintenance and ease of connection is similar to CI pipes.

PSC

In India, Prestressed Concrete pipes are manufactured in sizes bewteen 300 mm and 1400

mm though at few places in size of 1800 mm has also been manufactured. The range of 400

mm – 1200 mm is most common. These pipes are used for trunk distribution mains and not

commonly used in the local distribution lines due to difficulty in tapping. The C-value of

PSC pipe is higher than that for CI. Its attraction lies in the fact it is a cheaper material as

compared to CI. It needs high degree of quality control during its manufacture. Laying of

these pipes with proper bedding and rubber rings also calls for skilled expertise and

supervision. This expertise is available only with reputed contractors. Rubber rings have to

be of good quality and storing the same without exposure to light is necessary. In addition to

producing pipes of standard specifications, reputed manufacturers can produce PSC pipes as

per the specifications of the customer. It is necessary to pre-qualify the contractors for

manufacturing and laying of PSC pipes to keep out contractors with unsatisfactory past

records of laying of PSC pipelines.

4.3 SELECTION OF PIPES

GENERAL

Final selection of pipe material depends upon the type of use it is going to be subjected to and

the cost economics. Various related aspects are covered in the ensuing paragraphs. Granular

bedding would be required for HDPE, PVC and GRP. Costs are worked out accordingly. It

is also necessary to compare the costs on a carrying capacity basis because the ‘C’ values

vary for different materials. For local distribution lines the candidate materials are HDPE,

PVC, AC, CI, MS/EWS, DI and PSC while for trunk mains the candidate materials are AC,

GRP, CI, MS/EWS, DI and PSC while for trunk mains the candidate materials are AC, GRP,

CI, MS/EWS, DI and PSC.

LOCAL DISTRIBUTION LINES

Local distribution lines are defined as the pipelines from the various service reservoirs to the

consumers. The sizes of these lines range from 100mm to 1200mm. The materials available

in this range are HDPE, PVC, AC, CI, MS/EWS, DI and PSC. Cost of AC pipes is the

lowest followed by PVC, PSC, MS and CI. AC pipes can be drilled and tapped easily leading

to unauthorized connections. The life of AC pipes is comparatively less, especially due to

Page 38: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

8 of8

alternate wet and dry conditions the life gets shortened and the pipe suffers from frequent

bursts. The same, therefore, are not recommended. PSC pipes are available from 400mm

size but it is difficult to provide branch lines in PSC pipes and hence are not recommended

for local distribution. PVC pipes can lead to leakage losses due to rodent attack. They can be

easily tapped and encourage unauthorized consumer connections. The life of PVC pipes is

comparatively less. They are not therefore recommended. The DI pipes are recommended,

since the pipes have better hydraulic capacity, though it has marginal higher cost. DI has

merits such as its good performance record, availability of reputed manufacturers and skilled

manpower for laying, jointing and operation and maintenance and the ease of making

connections. In local distribution system, DI pipes are preferable because in general their

performance is satisfactory. DI pipes are therefore recommended in local distribution

network up to 700mm diameter. For higher diameter mains internally mortar lined and

externally gunited MS pipes are recommended.

TRUNK DISTRIBUTION LINES

The pipes carrying treated water from MBR’s to various reservoirs are defined as trunk

distribution lines, the sizes of these lines normally range from 300mm to 1200mm. The

materials available in this range are HDPE (300 to 400), AC (300 to 600), GRP (400 to

1200), CI (300 to 1000), MS/EWS (300 to 1200), PSC (300 to 1200) and DI (300 to 1200).

AC pipes are the cheapest, however downtime and cost of repairs of AC pipes would be on a

higher scale with the resultant disruption of water supply in trunk mains. They have various

disadvantages as listed above. The same are therefore not recommended. The next cheapest

are PSC pipes, but in recent years, because of bad workmanship of unqualified agencies,

there are cases of failure of these pipelines.

PSC pipes could be relied upon only if vendors are prequalified before they are allowed to

quote. This will filter out unqualified contractors. It would be necessary to prepare stringent

specifications for manufacturing and laying of PSC pipes. Cradle bedding may be laid

through out the length of PSC lines to prevent settlement. NWCMC will have to carefully

monitor the operation during manufacturing and execution stages. PSC pipes are therefore

recommended for gravity. They are not recommended for places where black cotton soil

exists. MS pipes with internal mortar lining and external guniting are recommended here.

For pumping mains MS with internal mortar ling and external guniting is recommended, as

MS pipes with welded joints are better suited to withstand water hammer than PSC pipes

because of better flexibility. Hence they are recommended. The stretches of trunk

distribution lines under roads and where reversal of flow will be taking place as per the

phased programme of laying of these lines will be of MS.

Over 700 mm size MS pipelines are proposed because PSC pipes aren’t suitable for laying in

soil strata where soil is black cotton.

Page 39: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page1 of 13

CHAPTER - V

PROPOSED SYSTEM

Nanded (South) is the added area to erstwhile Nanded Municipal Council (original) forming

Nanded Waghala Municipal Corporation. Existing infrastructure of added area is lack of

infrastructure. such as Water Supply, Sewerage, Storm Water, Roads needs to be improved.

As part of Infrastructure Development, Government of Maharashtra and NWCMC are

planning to upgrade the whole infrastructure of Nanded (South) on priority.

Presently CIDCO (1.91km) area has only infrastructure facilities. Therefore the Detailed

Project Report for augmentation augmentation of Water Supply in other part of Nanded

(South).

5.1 SOURCE

Nominal capacity of this storage dam across Godavari is stated to be about 80.79 Mm

3 as per

Irrigation Department’s data. Presently some17 Mm3 storage has been earmarked for Nanded

Municipal Corporation (NWCMC) for its drinking water needs.

NWCMC has proposed to utilize this storage for its projected additional demand for drinking

water to the tune of 175 Mld. On an annual basis the additional requirements work out to

about 63 Mm3.With the present allocation of 17 Mm

3 for NWCMC already in force,

additional requirement of 63 Mm3 will require the full live capacity of Vishnupuri dam

(80.79Mm3) to be earmarked for NWCMC’s drinking water purposes.

Increasing the yield for water supply from the existing Vishnupuri storage which has been

serving vital irrigation needs, appears infeasible and impracticable given that first user rights

for irrigation has been established since long. However it can be examined whether the

present storage can at least meet the partial needs of drinking water for NWCMC. In this

context the following review is called for:

i. Review the irrigation releases pattern vis a vis agricultural demands as of present to cut

down on wasteful usages.

ii. Review the reservoir operation for the previous years.

iii. Establish the reliable yields for irrigation and water supply.

iv. Establish operation rules for “Normal” “Sub normal” and “Draught” years and identify

cutbacks on irrigation and water supply releases.

Gross water requirement for Nanded North is 50.0 Mld Water demand for the year

2023(Refer Appendix 1). It is considered that the losses in WTP and Raw Water

Transmission would be 3% each. With deduction of losses for WTP, total out put from WTP

would be 47.30 Mld. With deduction of existing treated water (50.0-12.0)=35 Mld additional

WTP would be required at Nanded (South) in the year 2023. 5.2 RAW WATER CONVEYANCE FROM VISHNUPURI

Economical analysis for pumping main diameter has been carried with 6 % interest

rate and 8% escalation rate for 2038 flows. Appendix-3 gives the details of analysis. A new raw water main of 900 mm diameter mild steel internal lined and external guniting is

proposed in addition to existing raw water main of 450 mm diameter cast iron for CIDCO

area. The proposed main would follow the alignment of existing raw water main (CIDCO) up

to Latur road, beyond; it would follow the proposed road towards Asadvan village.

Page 40: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page2 of 13

Drawal of raw water for CIDCO WTP and proposed WTP at ASADVAN from

upstream of Vishnupuri dam-Jackwell:

Existing jackwell at Vishupuri would be used for pumping raw water to proposed WTP plant

Existing 600 mm Reinforced Cement Concrete (RCC) inlet pipe to jack well for raw water is

adequate to draw of 50 Mld raw water from the reservoir. For drawal of raw water(12.75Mld)

for CIDCO WTP, existing two number pumps would be replaced with same capacity of new

pumps. Additional pumps 3 nos.(2+1) would be housed in the same jackwell to pumped 38.0

Mld raw water to proposed Water Treatment plant at ASADVAN village

5.3 TREATMENT PLANT AT ASADVAN VILLAGE

The Existing Water Treatment Plant after rehabilitation will cater to the water requirement of

year 2006. Then onwards New Water Treatment Plant would be required to cater future

demand. Hence proposed Water Treatment Plant (35 Mld) would be planned for the water

requirements of year 2023.

Economical analysis for different alternative for location Water Treatment has been

considered to evaluate the appropriate location of WTP. Finally WTP at Asadvan village

would be considered.

Two alternatives are considered while locating proposed WTP at Asadvan village and

Fattejanpur Economics analysis is carried out to identify the economical site for WTP (Refer

Appendix-3

Appendix-3 indicates that net present value with 6% interest and escalation rate of 8% per

annum would be less by 30 crores when WTP selected at ASADVAN village.

Existing Water Treatment Plant at CIDCO township consist of following treatment units.

1. Prechlorination

2. Aeration

3. Alum dosing

4. Clarification

5. Filtration

6. Post chlorination.

The same treatment process shall be adopted for the proposed Water Treatment plant at

Asadvan village.

Schematic flow diagram of the proposed water treatment plant at Asadvan is given in fig V.1.

Godavari Raw Water Analysis Report is enclosed Table V.1 a & b. However, seasonal

variations are not available. In the dry season the raw water is likely to be quite clear due to

natural settling in the Basin of Godavari River. However, in monsoon the water is likely to

become turbid. With silting in the river stretch increasing over a period of time, the water will

become more turbid. The water treatment plant shall be designed to suit range of raw water

quality given in Table V.1 a

Page 41: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page3 of 13

Table V.1.a: Water Quality

Date of collection: 6.06.2005 Date of receipt: 6.06.2005 Date of examination: 6.06.2005 &

onwards.

Sr.

No.

Source: Raw water from

Vishnupuri, Nanded

Water Standards

Parameter: mg/l (except for

turbidity and pH)

mg/l (except for

turbidity and pH)

1. Physical Appearance Slightly Turbid Water

2. Odour No Smell Unobjectionable

3. Turbidity (as N.T.U.) 9.7 NTU 1 NTU

4. PH 7.9 7.0 – 8.5

5. Chloride (as Cl) 33.00 200

6. Free & Saline Ammonia (as N) Not Detected

7. Albuminoidal Ammonia (as N) Not Detected

8. Nitrates (as NO3) 1.28 45

9. Nitrites (as N) Nil

10. Total Hardness (as CaCO3) 160.00 200

11. Permanent Hardness (as CaCO3) 2.00

12. Total Dissolved Solids 340.00 500

13. Oxygen absorbed in 5 minutes Not Detected

14. Oxygen absorbed in 4 hrs. @ 37 0C Not Detected

15. Iron (as Fe) 0.05 0.1

16. Fluoride (as F) 0.3 1

17. Other Tests (if any) Alkalinity 158.00 200

Page 42: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page4 of 13

Table V.1.b Water Quality

Report on chemical examination of water for drinking purpose

Date of collection: 13.06.2006 Date of receipt: 13.06.2006 Date of examination: 13.06.2006

& onwards

Analytical Result in mg/litre (except pH and Turbidity)

Source: 1) Raw water from New

Pump House, Nanded

2) Filter water from

New Pump House,

Nanded

Parameter:

Physical Appearance Faint Yellowish Colour Clear, Colourless.

Odour No Smell. No Smell.

Turbidity (as N.T.U.) 28.00 NTU 3.32 NTU

pH 8.01 7.59

Chloride (as Cl) 68.00 58.00

Free & Saline Ammonia (as N) Not Detected Not Detected

Albuminoidal Ammonia (as N) Not Detected Not Detected

Nitrates (as NO3) 26.58 17.72

Nitrites (as N) Nil Nil

Total Hardness (as CaCO3) 202.00 200.00

Permanent Hardness (as

CaCO3)

26.00 18.00

Total Dissolved Solids 350.00 340.00

Oxygen absorbed in 5 minutes Not Detected Not Detected

Oxygen absorbed in 4 hrs. @

37 0C

Not Detected Not Detected

Iron (as Fe) 0.05 0.04

Fluoride (as F) 0.2 0.2

Other Tests (if any) Alkalinity Not Detected Not Detected

Page 43: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Fig. V.1: Schematic Flow Diagram for the proposed water treatment plant at Asadvan

Page 44: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page6 of 13

Treated Water Analysis

The treated water shall meet the quality of drinking as enclosed in Table V.2a. The treated

water turbidity specified should be less than 1 NTU as against 2.5 JTU specified in CPHEEO

manual, in view of the latest technological advances.

A pneumatically operated butterfly valve shall be provided on the 1200 mm raw water inlet to

treatment plant to ensure constant flow to treatment plant. In order to prevent wastage of

water, this valve will be closed on power supply failure.

Pre-chlorination

In order to keep the treatment plant units in disinfected condition and also to kill the algae in

the raw water, it is proposed to provide pre-chlorination at a dose of 3 mg/lit. Two

Chlorinators (1w + 1s) each of capacity 5 kg/hr are proposed.

Aeration

The raw water contains traces of Iron. It will get removed aeration process. Cascade Type

aerator is recommended.

Alum Dosing

In the absence of jar test results, the alum dosing plant shall be sized, for a dose of 50 mg/lit.

to water with a solution concentration of 10% in alum dosing tank. Dosing shall be by

gravity dosers. 100% standby plant shall be provided.

Clarification

The various types of clarifiers being offered today are conventional radial flow

clariflocculator, conventional sludge blanket clarifiers (hopper bottom or flat bottom) and

pulsators. The rise rate varies from 1.5 m/hr to 4 m/hr.

In order to get the best cost effective technology, it is proposed to give freedom to the Bidder

to offer his technology. In order to prevent very high surface rate the dosing of

polyelectrolyte shall not be permitted.

Filtration

The filtration rate shall be between 1.5 - 2 mm/sec. The number of filters shall be selected by

Bidders. Three – (3) nos. standby Filters shall be provided. (One under draining, one under

washing & one under maintenance). Backwashing by air and water shall be provided.

Post-Chlorination

Post-Chlorination shall be done in the filtered water conduit. The chlorine dose will be

provided to dose 1 mg/lit of chlorine. Two (1w + 1s) nos chlorinators each of capacity 1.5

kg/hr are proposed.

Chlorine Contact Tank cum Treated Water Reservoir

A reservoir minimum of 30 minutes storage shall be provided to serve the dual purpose of

chlorine contact time and treated water storage.

Page 45: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page7 of 13

5.4 PROPOSED PUMPING STATION

The proposed Water Treatment Plant (Capacity-35 Mld) would be provided with proposed

clear water sump (Capacity-1.0 Ml), pumping station and Master Balancing Reservoir (MBR)

(Capcity-2.5 Ml) within the WTP complex. Proposed pumping would house two set of

pumps. One set would be for pumping water to MBR and the other for pumping water to near

by zonal reservoir

5.5 PROPOSED TRANSMISSION SYSTEM

Handed (South) is undulating between the levels fro 405.00m to 353.00 m at river bank.

Treated water would be pumped to MBR at WTP complex. Water would flow by gravity to

proposed Elevated Service Reservoirs. Clear water transmission system is shown in Exhibit-2.

Diameters of the pipe lines in the transmission system rages from 250 mm to 900mm. Total

length of the pipe line would be 12845m.

.

5.6 SERVICE RESERVOIRS

6 nos of reservoirs are proposed, which ranges from 1.5 ml to 2.5ml capacity. Appendix 1

gives the details of the proposed reservoirs. The proposed reservoirs will get water from

Pumping Station at Asadvan WTP.

Typical section of proposed ESR is shown in Exhibit-6.

List of Proposed Reservoirs with F.S.L. are given in Appendix 1,

5.7 DISTRIBUTION SYSTEM

Presently a area of CIDCO (1.91 Sq.km.) is only covered in Water Supply. The existing

CIDCO zone would continue as it is. Rest of the area of Nanded (south) would be covered

with proposed water supply pipe lines. For the proposed system, Zoning for Water

Distribution is done freshly with due considerations to ground topography and the natural

obstruction. Proposed distribution zones are shown in Exhibit 3 and 4 The proposed

distribution system is designed using Environmental Protection Agency (EPA) computer

program.

5.8 PROPOSED REHABILITATION

CIVIL WORKS

Prior to the implementation of proposed works for the year 2023, it is mandatory to improve

the efficiency of the existing works and rehabilitate the existing works. Presently the existing

works related to existing Water Treatment Plants require rehabilitation. Following works have

been identified for the rehabilitation for existing treatment for Nanded (North) Water Supply

System.

1. Replacement of filter sand at CIDCO Water Treatment Plant

2. Replacement of shutter of doors and windows.

3. Installation of electromatic full bore bulk Flow meter at strategic points (12 locations).

5.9 ELECTRICAL SYSTEM AT VARIOUS SITES 5.9.1 CIDCO Raw Water Pumping Station

Its proposed to install express 11kV feeder from new 33kV / 11kV Vishnupuri Substation

which is having 5 MVA transformer. This substation is with 2kM radius of pumping station.

Page 46: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page8 of 13

Provisional sum allocation shall be made in tender and payment shall be made to MSEB for

developing the overhead line up to pumping station premises.

Single indoor VCB panel shall be installed which will be located at mezzanine floor in pump

house consisting of one incomer and outgoings as follows,

�� 2 Nos for 11kV / 415V, 750kVA transformers.

�� 1 Nos for spare.

Existing Transformer will be replaced by 2Nos of 11kV / 415V, 750kVA capacity which

provides 100% stand by.

New 415V MCC shall be provided consisting of two incomer, bus coupler and out going

feeders as follows,

�� 2 Nos Star-delta feeders for 132kW motors

�� 3 Nos Star-delta feeders for 200kW motors

�� 2 Nos feeder for existing capacitor bank with APFCR.

�� 1 Nos feeder for Sub-distribution board

The Sub-distribution board shall have incomer from MCC and outgoing feeders as follows,

�� 5 Nos DOL starter feeder for 1.5kW motors

�� 1Nos feeder for Lighting panel

�� 1 Nos feeder for welding socket

Wall mounted Lighting panel shall be provided, existing light fittings shall be replaced HPSV

medium bay fitting and overall conduit wiring shall be replaced.

Overall cabling shall be replaced, cable carrier system shall be upgraded using proper cable

trays and supports.

D.C power supply system with Ni-Cd battery, battery charger and D.C distribution board.

Power earthing shall be provided with Internal external earth grids and treated earth pits.

5.9.2 CIDCO 12mld Water Treatment Plant And Clear Water Pumping Station

Its proposed to install express 11kV feeder from Wagala Grid Substation. This substation is

within 2.5kM radius of WTP. Provisional sum allocation shall be made in tender and payment

shall be made to MSEB for developing the overhead line up to WTP premises.

The New MCC for CWPS which having following feeders,

�� 3 Nos Star-delta feeders New pumps.

�� 1 Nos feeder on each bus for APFCR panel with Capacitor.

�� 1 Nos feeder for WTP MCC

The New MCC for WTP which having following feeders,

�� 2 Nos Star-delta feeders compressors.

�� 9 Nos DOL starter feeders.

�� 1 Nos feeder for Lighting panel

Wall mounted Lighting panel shall be provided, existing light fittings shall be replaced HPSV

medium bay fitting, and internal road lighting and overall conduit wiring shall be replaced.

Overall cabling shall be replaced, cable carrier system shall be upgraded using proper cable

trays and supports.

Page 47: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page9 of 13

Power earthing shall be provided with Internal external earth grids and treated earth pits.

5.10 PROPOSED REHABILITATION FOR MECHINCAL SYSTEM AT VARIOUS SITES 5.10.1 CIDCO Raw Water Pumping Station

Both the pumping units (Pump + Motor) shall be replaced with new units.

New Pressure gauges, Level measurement system and flow measurement system shall be

provided.

5.10.2 CIDCO Water Treatment Plant ( 12 Mld)

The open channel flow meter is not in working condition and same shall be replaced with a

new unit.

To over come the algae problem it is proposed to install a new pre chlorination plant of 0 - 2.5

Kg/Hr .

All the three Agitators in Alum preparation tank shall be replaced with new units. The

existing Alum piping ( 40%) shall be replaced with new along with the damaged / leaking

valves.

Both the flocculators shall be replaced and clarifier bridge and scrapper mechnisum shall be

rehabilitated.

The lime mixing system shall be rehabilitated and brought back to service. The damaged part

of the existing lime piping shall be replaced with new, along with the damaged / leaking

valves.

All the filter valves and gates shall be refurbished and reinstalled. Both the existing air blower

unit shall be replaced with new units. Rate of flow/loss of head indicator shall be replaced.

The existing post chlorination system shall be replaced with a new system of 0 – 1 kg/hr

chlorination system including complete safety kit.

.

5.10.3 Clear Water Pumping Station

The existing pumping unit shall be replaced with new unit; all the Pressure gauges shall also

be replaced.

Flow measuring system on the discharge header shall to be installed to measure the actual

quantity of pure water being pumped. The pure water sump level measuring system shall be

installed.

Page 48: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page10 of 13

5.11 ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT

The impacts due to various pre constructions, during construction and post construction

activities are identified and appropriate measures are recommended in this chapter.

Effect of the project on the environment depends both on the type of project and surrounding

environmental setting.

Table –V.3

Possible Environmental And Social Issues In

Urban Infrastructure Projects

Project 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

Water Supply

1. Laying of Pipes + - - - - - - + +

2. Water treatment Plants ++ - - - + + -

3. ESR + - + +

4. Pumping stations ++ - - + +

1. Land use 6. Noise 11. Urban Aesthetics

2. Hydrology and Drainage

Patterns

7. Solid Waste 12. Public Health and Safety

3. Surface and Ground Water

Quality

8. Destruction of habitat/

Vegetation

13. Smell and Smoke

4. Water Logging 9. Disturbance to other services 14. Hazards due to handling of

toxic chemical

5. Air Quality 10. Urban Congestion 15. Resettlement and

Rehabilitation

NOTES

Major Negative Impact - -

Minor Negative Impact -

Major Positive Impact + +

Minor Positive Impact +

Page 49: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page11 of 13

Table – V.4

Summary of Mitigation Measures

Water Supply Components

Project

Component

Activities Impacts Phase of

Construction

Mitigatory measures

Earthwork

excavation

Dust pollution Construction

stage

Construction site & access roads

should be sprinkled/washed with

water, where there is substantial

dust pollution

Road blockage

& traffic

diversion.

Construction

stage

Adequate & safe measures for

diverting of traffic will be

provided. Restrict timing of

operations. Liase with police &

Highway authorities.

Pipe laying

Laying of pipes

Construction of

valve chambers

Water

pollution

Construction

stage

Adequate clearance between

water mains & sewer lines shall

be maintained. Lateral clearance

= 3m, vertical clearance =0.5m

between invert of water Main

& top of sewer line. Water

supply lines will be laid above

the sewers.

Earthwork

excavation &

filling

Dust pollution Construction

stage

Construction site & access roads

should be sprinkled/washed with

water where there is substantial

dust pollution.

Noise pollution Post

construction

Stage

Frequent lubrication, periodic

inspection & proper use of spare

parts.

Pumping mains

& Pumping

Stations

Operation of

pumping

systems

& diesel

generator

sets Water

pollution

Post

construction

stage

Water should not get

contaminated due to usage of

fuel & lubricants

Earthwork

excavation,

Dust pollution Construction

stage

Construction site & access roads

should be sprinkled/washed with

water

Filling,

Embankment

Formation There is substantial dust

pollution.

Construction of

Water Treatment

Water

pollution

Construction

stage

Adequate facilities for disposal

of sludge to be provided

Plant

Water

Treatment Plant

Page 50: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page12 of 13

Project

Component

Activities Impacts Phase of

Construction

Mitigatory measures

Proper operation of WTP by

undertaking preventive

maintenance, corrective

maintenance with prompt

repairs, good house keeping,

process monitoring &

Operation of

water Treatment

Plant

Odour

pollution

Post

construction

stage

Proper documentation of

operation &

Maintenance activities shall be

maintained.

Filling up of

excavated

Dust pollution.

Marginal

Construction

stage

Construction site & access roads

should be sprinkled/ washed

with water.

Areas ( Plying of

trucks)

increase in

levels

of oxides

Construction equipments and

vehicles should be kept well

tuned.

Nitrogen &

Sulphur.

ESR Earthwork

excavation,

Dust pollution Construction

stage

Construction site & access roads

should be sprinkled/washed with

water where

Filling,

Embankment

Formation There is substantial dust

pollution.

Construction of

ESRs

Construction

stage

Adequate provision for drainage

of water and disposal of sludge

arising from periodic cleaning

Page 51: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page13 of 13

5.12 SUMMARY OF THE PROPOSED WORKS

1. Water treatment plant of 35 MLD capacities at Asadvan.

2. Additional clear water pumps at Asadvan

3. 7 service reservoirs with capacities from 1.5 MLD to 2.5 MLD.

4. Inlet mains to reservoirs, DI pipes of dia. 150 mm to 600 mm @ 10 km length.

5. Distribution pipelines.

6. Rehabilitation of Pumping Stations and WTP.

Page 52: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page1 of 1

CHAPTER - VI

PROJECT IMPLEMENTATION SCHEDULE

6.1: IMPLEMENTATION SCHEDULE

The implementation schedule for the project is envisaged component wise in following six

packages.

The first package will be of installation of additional pumping machinery at Vishnupuri and

clear water pumping station at CIDCO WTP. The implementation period is 10 months from

the award of contract and one month for testing and commissioning. The period of

preparation of bid documents, submission of documents by bidder, evaluation and award of

tender is estimated to take about 4 months.

The second package will be of rehabilitation of existing 12 Mld Water Treatment Plant

equipment. The period is 10 months from the award of contract and one month for testing and

commissioning. The period of preparation of bid documents, submission of documents by

bidder, evaluation and award of tender is estimated to take about 4 months.

The third package will be Clear Water Transmission Main of about 12.85 km length to

proposed elevated service reservoirs. The work is planned to be completed in one year. The

period of preparation of bid documents, submission of documents by bidder, evaluation and

award of tender is estimated to take about 4 months.

The fourth package will be of construction of 7 elevated service reservoirs, which is planed to

be completed within 10 months from the award of project. The period of preparation of bid

documents, submission of documents by bidder, evaluation and award of tender is estimated

to take about 4 months.

The fifth package will be of distribution system pipes, which is planed to be completed within

10 months from the award of project. The period of preparation of bid documents, submission

of documents by bidder, evaluation and award of tender is estimated to take about 4 months.

The sixth package will be of New WTP at Asadvan which would be planned to be completed

within 10 months from the award of project. The period of preparation of bid documents,

submission of documents by bidder, evaluation and award of tender is estimated to take about

4 months.

The bar chart of the proposed system is given in Appendix 2.

Page 53: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page 1 of 2

CHAPETR - VII

BASIS OF COST ESTIMATE

7.1 COST BASIS FOR PROPOSED WORKS Project cost is estimated based on Schedule of Rates (SOR), Maharashtra Jeevan Pradhikaran

(MJP) for the year 2005 – 06 Public Works Department, Government of Maharashtra. Also

the data available on soil characteristics and physical data such as ground level, location of

road, waterways etc. are considered. It is essential to undertake detailed soil investigation and

survey prior to detail engineering. The total cost estimate at present may have a small

variation at a later stage, which could be covered under physical contingencies.

7.2 WATER SUPPLY SYSTEM

PROPOSED WATER TREATMENT PLANTS

Cost of the proposed treatment plant is arrived on Mld basis. MJP DSR Cost of 35Mld WTP

is 2.76 Crores, which works out to be 7.88 Lacs per Mld. MJP’s per Mld cost seems to be on

lower side. As per TCE’s experience in similar projects (Nagpur Municipal Corporation), the

cost of 100 Mld Treatment Plant including Clear water pumping station is 14.5 Crores as per

the work (Year 2004) awarded cost, which works out to be Rs. 14.00 lacs Per Mld. This forms

the basis of cost estimates of WTP. This cost includes electrical components and mechanical

component of the WTP.

SERVICE RESERVOIRS IN THE CITY

Quantity estimates is prepared for elevated service reservoir. Unit rate for concrete is referred

from SOR. Reinforcement is considered as per norm of Indian standard specifications.

Detailed cost estimation for each reservoir has been worked out for various capacities of the

reservoirs on the basis of structural design and analysis done in STAAD.Pro. The estimates of

the ESRs have been given in Appendix 4.

Based on the estimates per litre ESR cost works out to be Rs.3. For the similar work of ESRs,

the awarded per litre ESR cost was Rs. 4. Hence provision of cost for the ESR s is made in

cost estimates on the basis of Rs. 4.00 per litre.

TRUNK SYSTEM

D.I/MS. pipe is proposed for the additional / proposed pipes required in the transmission

system and distribution system within the city. DI pipes are internal lined and MS pipes are

with mortar internal lined and external gunited.

Cost per meter length is inclusive of following components.

• Ex factory cost of pipe

• All taxes (central & local)

• Freight

• Unloading from train

• Loading into truck

• Transport to site

• Unloading

• Stacking

Page 54: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Page 2 of 2

LAND ACQUISITION

Presently land for all proposed 6 elevated service reservoirs, proposed WTP is not in

possession of NWCMC. Requirement of land for reservoir would be one hecture/reservoir.

For WTP, land of 4 hectares would be required However the NWCMC has indicated that the

land would be made available for construction of elevated reservoirs and WTP. Therefore no

cost provision is made for land acquisition.

DISTRIBUTION SYSTEM

The existing distribution system is reorganised into existing and proposed zones. The analysis

has been carried out for the equi-distribution of water.

For the cost estimates of the pipes, 100% soil is considered for excavation. Clear cover of 1m

is considered for excavation.

Cost of special is considered on weight basis. The valves cost is estimated on the basis of

actual number basis in the system. (Refer Table 7.4 Appendix 4)

EXISTING WATER TREATMENT PLANT AND PUMPING STATION

Cost of Rehabilitation of existing WTP & Pumping Station are calculated on the basis

quotation called from the reputed vendors for Urban Water Supply and Environmental

Improvement in Madhya Pradesh Project and Maharashtra Jeevan Pradhikaran ‘District

schedule of rate’ for Aurangabad region.

REINSTATEMENT OF ROADS

After pipes are laid in position, the road is required to restore in original position. Item of road

reinstatement is considered for all pipes bitumen material. Rate analysis is carried out for road

reinstatement by bitumen l. (Refer Table 7.8 Appendix 4)

INCIDENTAL COST FOR WATER SUPPLY ARRANGEMENT FOR PILGRIMS

Tri cenetarity function of Guru Govind Singhji (Gur-ta Gaddi) would be celebrated in

September 2008. Large numbers of pilgrims are expected to attain this function. The water

supply arrangement would be required to provide the water. Hence cost provision of 2 Crore

is made.

The Detail Costs are given in Appendix 4.

Page 55: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 1Population Estimation for Nanded City

(South of Godavari)

Ward No Total Ward Area(Ha.)

1 59 464.5 14940 19759 71970 1724812 60 834.0 18229 24108 87812 2422763 61 20.8 12486 14564 14564 145644 62 12.2 8712 8712 8712 87125 63 15.9 11434 11434 11434 114346 64 18.1 11301 13182 13182 131827 65 676.7 16952 22419 81660 225301

Total 2042 94054 114177 289334 687951

Ward wise PopulationSr. No. Ward and Area Details

Year2006

Year2008

Year2023

Year2038

Job No.:4904A Page 1of1

Page 56: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 2

ESR Details for Nanded City

(South of Godavari)

S1 60 43.33%

S2 60 50.61%

59 38.00%

60 6.06%

59 37.00%

65 18.00%

61 100.00%

62 100.00%

63 100.00%

64 100.00%

59 25.00%

S6 65 53.00%

S7 65 29.00%

Total

S3

S4

Zone No. Ward No. % of ward area

S5

(Served by

Existing 12

Mld WTP)

2038

LocationCapacity

(ML)

MWL (m)

FSL (m)

Capacity

(ML)

2.01 5.56 Near Asarjan 2378

3832 and 1.6

2.35 6.49 Kavatha 2.5377

3822 no 2.00

2.29 6.32 Asadvan 2400

4052 no 2.00

1.25 3.46 Asadvan 1.5415

4202.25

11.83 31.60 12.5 20.60

2023 2038

Proposed Reservoir

(Mld)

2023

385

390

390

395

Vasarni

Near Latur

Road

2 2 no 1.50

2.5 2.15 and 1.6

1.73 4.25

2.19 5.53

Reservoir Capacity Required

(Ml)

Job No.:4904A Page 1of1

Page 57: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table3

Zonal Demand Calculation for Nanded City

(South of Godavari)

S1 60

S2 60

59

60

59

65

61

62

63

64

59

S6 65

S7 65

Total

S5

(Served by

Existing 12

Mld WTP)

Zone No. Ward No.

S4

S3

2006 2008 2023 2038

361.37 1.25 1.66 6.04 16.67

422.09 1.47 1.94 7.06 19.47

358.65 1.43 1.89 6.87 18.97

196.24 0.78 1.03 3.76 10.38

2042 14.9 18.1 46.0 109.3

8.39 10.46 14.45183.16 7.57

Total area of the

Zone (Ha.)

Toal Zonal Water Demand

(Mld)

Considering 15%

Distribution Losses

293.67 1.36 1.80 6.56 16.58

227.05 1.08 1.42 5.19 12.74

Job No.:4904A Page 1of1

Page 58: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Sl. No. Task Name1 Modification of existing pumping machinery at

CIDCO Pumping Station (Vishnupuri)

Preparation of tender document

Preparation of expression of interest issue inpaper and evaluation of expression of interest

Issue of tender documents pre bid meeting andissue of addendum

Submission of bid document Technicalevaluation of bids, Clarification from biddersSubmission of technical evaluation reportSubmission of financial evaluation reportFinalisation of the bidder and award of contract

Aug Sep Oct Nov Dec Jan Feb Mar2006

Task Milestone

TCE CONSULTING ENGINEERS LTD.

APPENDIX 2 TAMILNADU WATER INVESTMENT COMPANY

NANDED WAGHALA MUNICIPAL CORPORATIONPREPARATION OF D.P.R. FOR WATER & SEWERAGE SYSTEM

BAR CHART FOR PROJECT IMPLEMENTATION SCHEME (NANDED - SOUTH WATER SUPPLY SYSTEM)

Revision No. - P0 Dated: 11/08/2006 1 of 5 Job No. - TCE.4904A

Prepared by: Checked by: Approved by:

Page 59: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Sl. No. Task Name2 Tender for Rehabilitation of existing water treatment

plant

Preparation of tender document

Preparation of expression of interest issue inpaper and evaluation of expression of interest

Issue of tender documents pre bid meeting andissue of addendum

Submission of bid document Technicalevaluation of bids, Clarification from biddersSubmission of technical evaluation reportSubmission of financial evaluation reportFinalisation of the bidder and award of contract

Aug Sep Oct Nov Dec Jan Feb Mar2006

Task Milestone

TCE CONSULTING ENGINEERS LTD.

APPENDIX 2 TAMILNADU WATER INVESTMENT COMPANY

NANDED WAGHALA MUNICIPAL CORPORATIONPREPARATION OF D.P.R. FOR WATER & SEWERAGE SYSTEM

BAR CHART FOR PROJECT IMPLEMENTATION SCHEME (NANDED - SOUTH WATER SUPPLY SYSTEM)

Revision No. - P0 Dated: 11/08/2006 2 of 5 Job No. - TCE.4904A

Prepared by: Checked by: Approved by:

Page 60: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Sl. No. Task Name3 Tender for Trunk Distribution

Preparation of tender document

Preparation of expression of interest issue inpaper and evaluation of expression of interest

Issue of tender documents pre bid meeting andissue of addendum

Submission of bid document Technicalevaluation of bids, Clarification from biddersSubmission of technical evaluation reportSubmission of financial evaluation reportFinalisation of the bidder and award of contract

Aug Sep Oct Nov Dec Jan Feb Mar2006

Task Milestone

TCE CONSULTING ENGINEERS LTD.

APPENDIX 2 TAMILNADU WATER INVESTMENT COMPANY

NANDED WAGHALA MUNICIPAL CORPORATIONPREPARATION OF D.P.R. FOR WATER & SEWERAGE SYSTEM

BAR CHART FOR PROJECT IMPLEMENTATION SCHEME (NANDED - SOUTH WATER SUPPLY SYSTEM)

Revision No. - P0 Dated: 11/08/2006 3 of 5 Job No. - TCE.4904A

Prepared by: Checked by: Approved by:

Page 61: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Sl. No. Task Name4 Tender for R.C.C. ESRs

Preparation of tender document

Preparation of expression of interest issue inpaper and evaluation of expression of interest

Issue of tender documents pre bid meeting andissue of addendum

Submission of bid document Technicalevaluation of bids, Clarification from biddersSubmission of technical evaluation reportSubmission of financial evaluation reportFinalisation of the bidder and award of contract

Aug Sep Oct Nov Dec Jan Feb Mar2006

Task Milestone

TCE CONSULTING ENGINEERS LTD.

APPENDIX 2 TAMILNADU WATER INVESTMENT COMPANY

NANDED WAGHALA MUNICIPAL CORPORATIONPREPARATION OF D.P.R. FOR WATER & SEWERAGE SYSTEM

BAR CHART FOR PROJECT IMPLEMENTATION SCHEME (NANDED - SOUTH WATER SUPPLY SYSTEM)

Revision No. - P0 Dated: 11/08/2006 4 of 5 Job No. - TCE.4904A

Prepared by: Checked by: Approved by:

Page 62: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Sl. No. Task Name5 Tender for D.I. Distribution system

Preparation of tender document

Preparation of expression of interest issue inpaper and evaluation of expression of interest

Issue of tender documents pre bid meeting andissue of addendum

Submission of bid document Technicalevaluation of bids, Clarification from biddersSubmission of technical evaluation reportSubmission of financial evaluation reportFinalisation of the bidder and award of contract

6 Proposed Water Treatment Plant at AsadvanCapacity 35 MLD

Aug Sep Oct Nov Dec Jan Feb Mar2006

Task Milestone

TCE CONSULTING ENGINEERS LTD.

APPENDIX 2 TAMILNADU WATER INVESTMENT COMPANY

NANDED WAGHALA MUNICIPAL CORPORATIONPREPARATION OF D.P.R. FOR WATER & SEWERAGE SYSTEM

BAR CHART FOR PROJECT IMPLEMENTATION SCHEME (NANDED - SOUTH WATER SUPPLY SYSTEM)

Revision No. - P0 Dated: 11/08/2006 5 of 5 Job No. - TCE.4904A

Prepared by: Checked by: Approved by:

Page 63: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

APPENDIX- 3

The selection of location for water treatment site determines the number of local pumping

station, wastage treated water. Following Alternatives are considered for location of Water

Treatment Plant for economic evaluation.

Alternative-I: Location of WTP at Fattejangpur at 360.0 m level at Vishnupuri dam road

junction

Alternative-II: Location of WTP at Foot of hill at Asadvan village at 392.0 m level at

Technical details Alt-I Alt-2

1. Location Fattejangpur Asadvan

2. Lip of WTP inlet chamber(m) 368.0 398.0

3. Length of pumping main(Raw Water)(m) 3160 4500

4. Diameter of pumping main(Raw Water)(mm) 900 900

5. WTP Capacity 35 35

6. Range of pipe diameter of transmission mains 200-900 350-900

7. Total length of transmission system(m) 12845 14340

8. MBR Capacity(Ml) -- 2.50

9. Total ESR Capacity(Ml) 12.5 12.50

10. H.P. Required 1380 900

Refer cost table.

Page 64: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Alternative - 2

Vishnupuri- Asadvan WTP- Nanded (With MBR)

Capital Cost for 35 Mld scheme

Sl. No. ComponentsEstimated Cost

(Crores Rs.)

1New raw water pumping machinery (300 hp (2W + 2S) Horizontal

Centrifugal pumps)1.80

2 900 mm dia MS Raw water pumping main of 4.5 Km length 4.50

3 Nallah crossing, National Highway crossing and Sundry 0.10

4 35 Mld WTP at Asadvan ( 14 Lakh per Mld) 4.90

5 2.5 Ml MBR at Asadvan (22 m Staging Height, Rs. 5 per Litre) 1.25

6Clear water Pumping station Asadvan (150 Hp (2W + 1 S) Horizontal

Centrifugal pumps)0.72

7 900 mm dia MS & 450 mm dia DI K9 Clear water pumping main 0.45

8 250 mm - 800 mm dia DI K9 and MS gravity mains 4.25

Total Capital Cost 17.97

Annual Operation and Maintenance Cost

1 a) Raw water pumps 1.63

b) Staffing 0.13

c) O & M 0.09

2 a) Treatment Plant 0.05

b) Staffing 0.14

c) Chemicals 0.30

3 a) Clear water pumps 0.81

b) O & M 0.04

Total Annual Charges 3.18

Net Present Value of O&M Cost 72.18

Net Present Value for Alt-2 90.15

Note: For calculation of Net Present Value of O & M cost, inflation at 8%

and interest rate of 6% is considered.

Page 65: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

It would be seen that capital cost and recurring cost for 30 years of alternative-II for WTP at

Asadvan is less than Alternative-II of treatment plant at Fattejangpur. Hence alternative-II is

preferred and selected.

Alternative - 2

Vishnupuri- Asadvan WTP- Nanded (With MBR)

Capital Cost for 35 Mld scheme

Sl. No. ComponentsEstimated Cost

(Crores Rs.)

1New raw water pumping machinery (300 hp (2W + 2S) Horizontal

Centrifugal pumps)1.80

2 900 mm dia MS Raw water pumping main of 4.5 Km length 4.50

3 Nallah crossing, National Highway crossing and Sundry 0.10

4 35 Mld WTP at Asadvan ( 14 Lakh per Mld) 4.90

5 2.5 Ml MBR at Asadvan (22 m Staging Height, Rs. 5 per Litre) 1.25

6Clear water Pumping station Asadvan (150 Hp (2W + 1 S) Horizontal

Centrifugal pumps)0.72

7 900 mm dia MS & 450 mm dia DI K9 Clear water pumping main 0.45

8 250 mm - 800 mm dia DI K9 and MS gravity mains 4.25

Total Capital Cost 17.97

Annual Operation and Maintenance Cost

1 a) Raw water pumps 1.63

b) Staffing 0.13

c) O & M 0.09

2 a) Treatment Plant 0.05

b) Staffing 0.14

c) Chemicals 0.30

3 a) Clear water pumps 0.81

b) O & M 0.04

Total Annual Charges 3.18

Net Present Value of O&M Cost 72.18

Net Present Value for Alt-2 90.15

Note: For calculation of Net Present Value of O & M cost, inflation at 8%

and interest rate of 6% is considered.

Page 66: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 7.1 - Project Cost

Sl. No. ItemCost in Rs.(Crores )

Remarks

1Rehabilitation of Water Treatment Plant-Civil Works

0.58 Table 7.10

2Rehabilitation of pumping Stations at- Source and WTP --Electrical Works

1.61 Table 7.11

3Rehabilitation of pumping Stations at- Source and WTP-Mechanical Works

0.73 Table 7.12

4Transmission Main from CIDCO Raw water Pump House to Asdvan WTP & from Clear Water Sump at WTP to MBR and various ELSRs

10.94 Table 7.2 and 7.3

5Elevated Service Reservoirs 11 numbers of various capacities in Distribution System

5.00 Table 7.9

6Distribution System of various sizes for a total length of 88 Km including Road restoration

13.05 Table 7.4 and 7.5

7 New WTP at Asadvan - 35 Mld Capacity 4.90

8Incidental cost for water supply arrangement for pilgrims

2.00

Total 38.82Contingencies @3% 1.16

TOTAL COST 39.98

Water Supply to Nanded (South)

Job No.:4904A Page 1 of 1

Page 67: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 7.2Cost Estimation

forTransmission System

Year 2038 for Nanded City (South)

Sl. No. Description of Items Quantity Unit RateAmount

(Rs.)Manufacturing, providing and supplying spirally welded ERW/ SAW/ Fabricated M.S. Pipes (commercial quality), including transportRatesMJP S.O.R. for the year 2005-06, Page 163Clear Water Transmission, Dia. 900 mm 925 7311.00 6762675.00

Raw Water Transmission, Dia 900 mm 4500 7311.00 32899500.00

Providing D.I. Pipes of grade D.I. K-9 with internal cement mortar lining and including all taxes, transportation, loading, unloading, stacking etc. (16% ED)RatesMJP S.O.R. for the year 2005-06, Page 58350 mm 400 2283.00 913200.00

400 mm 1810 2760.00 4995600.00

450 mm 4190 3334.00 13969460.00

500 mm 0 3863.00 0.00

600 mm 765 5121.00 3917565.00

700 mm 775 6202.00 4806550.00

750 mm 975 6073.00 5921175.00

Excavation for pipe trenches in earth, soils of alltypes, including removing the excavated materialupto a distance of 50 m, excluding backfilling

Lift 0 to 1.5 mMJP S.O.R. for the year 2005-06, Page 29

26084.25 Cu.M. 34.00 886864.50

Lift 1.5 to 3.0 mMJP S.O.R. for the year 2005-06, Page 29

3533.575 Cu.M. 37.00 130742.28

4

Filling in trenches with contractor's murum forbedding in 20 cm layers including watering andcompaction completeMJP S.O.R. for the year 2005-06, Page 33

2243.75 Cu.M. 130.00 291687.50

5

Refilling the trenches with available excavatedstuff with soft material first over pipeline and thenhard material in 15 cm layers with all leads andlifts including consolidation, surcharghing etc.completeMJP S.O.R. for the year 2005-06, Page 33

15054.55 Cu.M. 16.00 240872.80

6

Disposal of excavated earth material from worksite to a distance of 3.00 km including loading,unloading & stacking etc. completeMJP S.O.R. for the year 2005-06, Page 20

4719.15 Cu.M. 80.43 379561.23

7

Reinstatement of asphalt pavement of requiredthickness.Refer Table 7.8, Appendix 4

2152.5 Sq. M 268.00 576870.00

1

2

3

RMT

RMT

Job No.: 4904A Page 1of 4

Page 68: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 7.2Cost Estimation

forTransmission System

Year 2038 for Nanded City (South)

Sl. No. Description of Items Quantity Unit RateAmount

(Rs.)

8

Lowering laying in position to correct line andlevel including MS pipes with/without anyoutcoating, including transportation upto 500 metc. completed as specifiedMJP S.O.R. 2005-06, Page 179

5425 RMT 161.00 873425.00

9

Providing and applying with mechanicalarrangement 1:3 proportion cement sand gunite, 40 to 50 mm thick to M.S. pipe surface under 2.1kg/ sq. cm pressure to 2.80 kg/ sq. cm pressureincluding removing the loose materials andincluding scrapping the surface with wire brushes,degreasing, cleaning by compressed air andproviding fixing BRC fabric no. 14 asreinforcement, curing for 21 days, etc. complete asdirected by Engineer-in-chargeMJP S.O.R. for the year 2005-06, Page 192

15475.17 Sq. M 200.00 3095034.25

10

Providing and applying pipe coating of fibres,coaltar and solvent based rubber modifiedbituminous primer, including material coating andwrapping over the pipes, handling, preparation ofsurface, labour, material etc. completeMJP S.O.R. for the year 2005-06, Page 192

15338.83 Sq. M 541.99 8313490.37

11

Providing and making inner cement mortar liningto M.S. pipes with mechanical devices in cementmortar 1:1 proportion, including cost of allmaterials, labour, special sand required,machinery, including carrying out "C" valueperformance test of pipeline, complete job as perthe directions of the Engineer-In- ChargeMJP S.O.R. for the year 2005-06MJP S.O.R. forthe year 2005-06, Page 193

15338.83 Sq. M 160.00 2454212.18

12

Butt Welding in all positions for MS pipes, 8 mmthickMJP S.O.R. 2005-06, Page 187

5425 RMT 279.00 1513575.00

13

Hydraulic testing of MS Pipeline to specifiedpressure900 mm Dia.MJP S.O.R. 2005-06, Page 191

5425 RMT 19.64 106547.00

Job No.: 4904A Page 2of 4

Page 69: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 7.2Cost Estimation

forTransmission System

Year 2038 for Nanded City (South)

Sl. No. Description of Items Quantity Unit RateAmount

(Rs.)

Lowering laying and jointing D.I. K-9 pipes withSBR rubber gaskets including conveyance ofmaterial, cost of jointing materials and rubberrings, labour, giving hydraulic testing etc.completeMJP S.O.R. 2005-06, Page 59 & 55

350 mm 400 78.00 31200.00

400 mm 1810 92.00 166520.00

450 mm 4190 101.00 423190.00

500 mm 0 119.00 0.00

600 mm 765 159.00 121635.00

700 mm 775 206.00 159650.00

750 mm 975 253.00 246675.00

Providing and supplying ISI Standard D.I.Specials and fittings with sealing rubber gasket ofS.B.R., complete with C.I. Follower gland andM.S. nuts & bolts protected from rusting,including cost of labours etc. complete.MJP S.O.R. 2005-06, Page 64 (Weight of onefitting considered 1 kg)

350 mm 400 80.00 32000.00

400 mm 1810 80.00 144800.00

450 mm 4190 80.00 335200.00

500 mm 0 80.00 0.00

600 mm 765 80.00 61200.00

700 mm 775 80.00 62000.00

750 mm 975 80.00 78000.00

14

RMT

RMT

15

Job No.: 4904A Page 3of 4

Page 70: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 7.2Cost Estimation

forTransmission System

Year 2038 for Nanded City (South)

Sl. No. Description of Items Quantity Unit RateAmount

(Rs.)

Nallah CrossingsProviding and laying M25 grade cement concretefor RCC work in footing of RCC columnsincluding normal dewatering, form work,compaction, finishing and curing, etc, complete.Excluding MS or Tor reinforcement.MJP S.O.R. for the year 2005-06, Page 36

2 Cu.M. 2586.00 5172.00

Providing and laying M30 grade cement concretefor RCC work as per design and drawingincluding normal dewatering, centering, formwork, compaction, finishing the formed surfaceswith CM 1:3 of sufficient minimum thickness andcuring, etc, complete. Excluding MS or Torreinforcement.MJP S.O.R. for the year 2005-06, Page 36

3 Cu.M. 2850.00 8550.00

Providing and fixing in position Tor steel barreinforcement of various diameters for footings,foundations, columns etc. as per detailed designs,drawings and schedules; including cutting,bending, hooking the bars, binding with wires ortack welding and supporting as required, etc,complete

MJP S.O.R. for the year 2005-06, Page 39

0.5 Cu.M. 30840.00 15420.00

Full-Bore Electromagnetic Flow MetersMJP S.O.R. for the year 2005-06, Page 258900 mm 2 732005.00 1464010.00

450 mm 3 495967.64 1487902.92

400 mm 2 414796.00 829592.00

350 mm 1 365384.00 365384.00

Total 9.91 CroresValves, Valve Chamber & Air Valves 0.41 Crores

Total for Transmission 10.32 CroresTotal Escalated Cost for 2006-07 Rate 10.94 Crores

16

Refer Table 7.3, Appendix 4

Escalated by 6%

No.

17

Job No.: 4904A Page 4of 4

Page 71: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 7.3Bill of Quantities for Valve Chambers in Transmission System for Nanded City

(South)SL. NO.

ITEM QTY UNIT RATE AMOUNT(Rs.)

1

Providing, supplying following flanged sluicevalves, class PN-1.6, including flanged tailpieces with rubber gasket of S.B.R. at bothends, complete as per specification.MJP SOR 2005-06, Page 125

a 350 1 No. 51799.00 51800.00b 400 2 No. 66131.00 132300.00c 450 2 No. 89148.00 178300.00d 500 0 No. 107919.00 0.00e 600 1 No. 150102.00 150200.00f 700 1 No. 261502.00 261600.00g 750 1 No. 420472.00 420500.00h 800 0 No. 433170.00 0.00i 900 (Butterfly Valve) 1 No. 278375.00 278400.00

2

Lowering, laying and jointing in position andtesting the following sluice valves including alljointing materials like bolts, nuts, washers,rubber packing, dismantling pieces, tail piecesetc. complete as per specification.MJP SOR 2005-06, Page 128

a 350 1 No. 2300.00 2300.00b 400 2 No. 2570.00 5200.00c 450 2 No. 2720.00 5500.00d 500 0 No. 3020.00 0.00e 600 1 No. 3330.00 3400.00f 700 1 No. 3640.00 3700.00g 750 1 No. 4620.00 4700.00h 800 0 No. 5830.00 0.00i 900 1 No. 6040.00 6100.00

Job No.:4904A 1 of 3

Page 72: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 7.3Bill of Quantities for Valve Chambers in Transmission System for Nanded City

(South)SL. NO.

ITEM QTY UNIT RATE AMOUNT(Rs.)

Total for Valves 1503400.00

3

Excavation for foundation in earth, soils of alltypes, including removing the excavatedmaterial upto a distance of 50 m, excludingbackfilling, etc. completeLift 0-1.5 mMJP SOR 2005-06, Page 29

122.92 Cu. M 34.00 4200.00

4

Excavation for foundation in earth, soils of alltypes, including removing the excavatedmaterial upto a distance of 50 m, excludingbackfilling, etc. completeLift 1.5-3.0 mMJP SOR 2005-06, Page 29

92.55 Cu. M 37.00 3500.00

5

Excavation for foundation in earth, soils of alltypes, including removing the excavatedmaterial upto a distance of 50 m, excludingbackfilling, etc. completeLift 3.0-4.5 mMJP SOR 2005-06, Page 29

30.37 Cu. M 40.00 1300.00

6

Providing, supplying, transporting, installing,aligning, fixing in position and testing of 100mm dia double acting kinetic cast steel airvalve of approved make for pipeline with anisolating sluice valve including all accessoriesand jointing material like bolts, nuts, washers,rubber packing etc. complete as specification.MJP SOR 2005-06, Page 136

9.00 No 29590.00 266400.00

7Reinstatement of asphalt pavement of requiredthickness.Refer Table 7.8, Appendix 4

87.47 Sq.M 268.00 23500.00

8

Providing and laying reinforced concrete ofClass M20 for cast in situ and precast membersexcluding reinforcement but includingformwork, with coarse aggregate of size 20 mmdowngraded in walls, slabs, etc. includingfinishing, formwork, vibrating, curing etc.complete.MJP SOR 2005-06, Page 36

35.18 Cu. M 2425.00 1809000.00

Job No.:4904A 2 of 3

Page 73: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 7.3Bill of Quantities for Valve Chambers in Transmission System for Nanded City

(South)SL. NO.

ITEM QTY UNIT RATE AMOUNT(Rs.)

9

Providing and laying cement concrete of ClassM15 excluding reinforcement for footings,base slabs, Anchor blocks and encasement ofpipes with all other miscellaneous works. Therate shall include cost of shuttering,scaffolding, finishing, vibrating, curing etc.complete.MJP SOR 2005-06, Page 36

21.26 Cu. M 2277.00 48400.00

10

Providing and fixing in position steel barreinforcements of various diameters for R.C.C.pipes, caps, footings, foundation, slabs, beams,columns, canopies, staircases, newels, chajjas,lintels, pardies, copings, fins, arches etc.including cutting, bending, hooking the bars,binding with wires or tack welding andsupporting as required, etc. completeMJP SOR 2005-06, Page 39

Tor steel 7.39 MT 30840.00 228000.00Total for Valves 38.87 Lakh

Escalated Cost for 2006-07 Rates Escalated by 6% 41.20 Lakh

Job No.:4904A 3 of 3

Page 74: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

TABLE 7.4COST ESTIMATION FOR PROPOSED DISTRIBUTION PIPES

Sl. No.

Description of Items Quantity Unit Rate

Providing D.I. Pipes of grade D.I. K-9 with internal cement mortar lining andincluding all taxes, transportation, loading, unloading, stacking etc. (16% ED)

Rates For Pipe DiameterMJP S.O.R. for the year 2005-06, Page 58

100 39324 580.00 22808000.00150 16100 842.00 13556200.00200 13913 1150.00 16000000.00250 4731 1520.00 7191200.00300 4400 1821.00 8012400.00350 1781 2283.00 4066100.00400 3094 2760.00 8539500.00450 2863 3334.00 9545300.00500 1887 3863.00 7289500.00600 541 5121.00 2770500.00Excavation for pipe trenches in all types of soils, including removing theexcavated material upto a distance of 50 m, excluding backfillingLift 0 to 1.5 mMJP S.O.R. for the year 2005-06, Page 29

94467.91 34.00 3212000.00

Lift 1.5 to 3.0 mMJP S.O.R. for the year 2005-06, Page 29

2219.01 37.00 82200.00

Filling in trenches with contractor's murum for bedding in 20 cm layersincluding watering and compaction completeMJP S.O.R. for the year 2005-06, Page 33

13846.11 Cu.m 130.00 1800000.00

Refilling the trenches with available excavated stuff with soft material first overpipeline and then hard material in 15 cm layers with all leads and lifts includingconsolidation, surcharghing etc. completeMJP S.O.R. for the year 2005-06, Page 33

79533.48 Cu.m 16.00 1272600.00

Disposal of excavated earth material from work site to a distance of 3.00 kmincluding loading, unloading & stacking etc. completeMJP S.O.R. for the year 2005-06, Page 20

17090.57 Cu.m 80.43 1374600.00

7 Reinstatement of asphalt pavement of required thickness.Refer Table 7.8, Appendix 4

6000.00 Sq. M 268.00 1608000.00

Lowering laying and jointing D.I. K-9 pipes with SBR rubber gasketsincluding conveyance of material, cost of jointing materials and rubber rings,labour, giving hydraulic testing etc. completeMJP S.O.R. for the year 2005-06, Page 55

100 39324 24.00 943800.00150 16100 33.00 531300.00200 13913 43.00 598300.00250 4731 56.00 265000.00300 4400 65.00 286000.00350 1781 78.00 139000.00400 3094 92.00 284700.00450 2863 101.00 289200.00500 1887 119.00 224600.00600 541 159.00 86100.00Providing and supplying ISI Standard D.I. Specials and fittings withsealing rubber gasket of S.B.R., complete with C.I. Follower gland and M.S.nuts & bolts protected from rusting, including cost of labours etc. complete.MJP S.O.R. for the year 2005-06, Page 64

100 to 300 mm dia. 15694 70.00 1098600.00350 mm and above dia. 2033 80.00 162700.00

RMT

4

8

3

2

1

RMT

Cu.m

kg

9

5

Job No.: 4904A Page 1 of 2

Page 75: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

TABLE 7.4COST ESTIMATION FOR PROPOSED DISTRIBUTION PIPES

Sl. No.

Description of Items Quantity Unit Rate

110 Nallah CrossingsProviding and laying M25 grade cement concrete for RCC work in footing ofRCC columns including normal dewatering, form work, compaction, finishingand curing, etc, complete. Excluding MS or Tor reinforcement.MJP S.O.R. for the year 2005-06, Page 36

35 Cu.M. 2586.00 90600.00

Providing and laying M30 grade cement concrete for RCC work as per designand drawing including normal dewatering, centering, form work, compaction,finishing the formed surfaces with CM 1:3 of sufficient minimum thickness andcuring, etc, complete. Excluding MS or Tor reinforcement.MJP S.O.R. for the year 2005-06, Page 36

70 Cu.M. 2850.00 199500.00

Providing and fixing in position Tor steel bar reinforcement of variousdiameters for footings, foundations, columns etc. as per detailed designs,drawings and schedules; including cutting, bending, hooking the bars, bindingwith wires or tack welding and supporting as required, etc, complete

MJP S.O.R. for the year 2005-06, Page 39

10.5 MT 30840.00 323900.00

11.46

0.85

12.3113.05

TOTAL COST Crores of RupeesESCALATED COST FOR 2006-07 RATES (@ 6%) Crores of Rupees

Crores of RupeesTOTAL

Cost of Valves and Valve Chambers (Refer Table 7.5, Appendix 4 ) Crores of Rupees

Job No.: 4904A Page 2 of 2

Page 76: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 7.5Bill of Quantities for Valve Chambers in Distribution System

SL. NO.

ITEM QTY UNIT RATE AMOUNT(Rs.)

AMOUNT(Rs.)

1

Providing, supplying following flanged sluicevalves, class PN-1.0, including flanged tailpieces with rubber gasket of S.B.R. at bothends, complete as per specification.MJP SOR 2005-06, Page 125

a 80 0 No. 5063.00 0.00 0.00b 100 29 No. 6467.00 187543.00 187600.00c 150 18 No. 9707.00 174726.00 174800.00d 200 26 No. 15137.00 393562.00 393600.00e 250 10 No. 22099.00 220990.00 221000.00f 300 9 No. 26582.00 239238.00 239300.00g 350 4 No. 43113.00 172452.00 172500.00h 400 5 No. 55378.00 276890.00 276900.00I 450 5 No. 73171.00 365855.00 365900.00j 500 6 No. 89814.00 538884.00 538900.00k 600 4 No. 124654.00 498616.00 498700.00l 700 0 No. 237396.00 0.00 0.00

2

Lowering, laying and jointing in position andtesting the following sluice valves including alljointing materials like bolts, nuts, washers,rubber packing, dismantling pieces, tail piecesetc. complete as per specification.MJP SOR 2005-06, Page 128

a 80 0 No. 465.00 0.00 0.00b 100 29 No. 660.00 19140.00 19200.00c 150 18 No. 1030.00 18540.00 18600.00d 200 26 No. 1100.00 28600.00 28600.00e 250 10 No. 1450.00 14500.00 14500.00f 300 9 No. 1880.00 16920.00 17000.00g 350 4 No. 2300.00 9200.00 9200.00h 400 5 No. 2570.00 12850.00 12900.00I 450 5 No. 2720.00 13600.00 13600.00j 500 6 No. 3020.00 18120.00 18200.00k 600 4 No. 3330.00 13320.00 13400.00l 700 0 No. 3640.00 0.00 0.00

Job No.:4904A 1 of 3

Page 77: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 7.5Bill of Quantities for Valve Chambers in Distribution System

SL. NO.

ITEM QTY UNIT RATE AMOUNT(Rs.)

AMOUNT(Rs.)

Total for Valves 3233546.00 3233600.00

3

Excavation for foundation in earth, soils of alltypes, including removing the excavatedmaterial upto a distance of 50 m, excludingbackfilling, etc. completeLift 0-1.5 mMJP SOR 2005-06, Page 29

494.82 Cu. M 34.00 16823.83 16900.00

4

Excavation for foundation in earth, soils of alltypes, including removing the excavatedmaterial upto a distance of 50 m, excludingbackfilling, etc. completeLift 1.5-3.0 mMJP SOR 2005-06, Page 29

400.36 Cu. M 37.00 14813.20 14900.00

5

Excavation for foundation in earth, soils of alltypes, including removing the excavatedmaterial upto a distance of 50 m, excludingbackfilling, etc. completeLift 3.0-4.5 mMJP SOR 2005-06, Page 29

3.90 Cu. M 40.00 156.06 200.00

6Reinstatement of asphalt pavement of requiredthickness.Refer Table 7.8, Appendix 4

686.06 Sq.M 268.00 183865.07 183900.00

7

Providing and laying reinforced concrete ofClass M20 for cast in situ and precast membersexcluding reinforcement but includingformwork, with coarse aggregate of size 20 mmdowngraded in walls, slabs, etc. includingfinishing, formwork, vibrating, curing etc.complete.MJP SOR 2005-06, Page 36

264.78 Cu. M 2425.00 3430129.09 3430200.00

Job No.:4904A 2 of 3

Page 78: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 7.5Bill of Quantities for Valve Chambers in Distribution System

SL. NO.

ITEM QTY UNIT RATE AMOUNT(Rs.)

AMOUNT(Rs.)

8

Providing and laying cement concrete of ClassM15 excluding reinforcement for footings,base slabs, Anchor blocks and encasement ofpipes with all other miscellaneous works. Therate shall include cost of shuttering, scaffolding,finishing, vibrating, curing etc. complete.MJP SOR 2005-06, Page 36

149.88 Cu. M 2277.00 341270.27 341300.00

9

Providing and fixing in position steel barreinforcements of various diameters for R.C.C.pipes, caps, footings, foundation, slabs, beams,columns, canopies, staircases, newels, chajjas,lintels, pardies, copings, fins, arches etc.including cutting, bending, hooking the bars,binding with wires or tack welding andsupporting as required, etc. completeMJP SOR 2005-06, Page 39

Tor steel 41.20 MT 30840.00 1270557.22 1270600.00Total for Valves 84.91 Lakh 84.91 Lakh

Escalated Cost for 2006-07 Rates Escalated @6% 90.01 Lakh 90.01 Lakh

Job No.:4904A 3 of 3

Page 79: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 7.6UNIT RATE CALCULATION OF D.I. PIPES

S S Providing Depth Depth Qty.of Qty.of Qty.of Cost of Cost of Qty.of Cost of Lowering Total L I DI pipe of of earth B.fill Road exvn. Road murum murum & N Z Grade K-9 murum earth work Reinstatement B. fill. Reinstatement fill. fill. laying O E bedding work charges

mm Rs./m mm mm Cum./mCum./m Sq.m/m Rs./m Rs./m Cum./m Rs./m Rs./m Rs./m1 2 3 4 5 6 7 8 9 10 11 12 13 15

1 100 580.00 200.00 1300.00 0.91 0.76 0.70 55.03 350.00 0.14 18.20 24.00 900.002 150 842.00 200.00 1350.00 1.01 0.84 0.75 61.43 375.00 0.15 19.50 33.00 1200.003 200 1150.00 200.00 1400.00 1.12 0.93 0.80 68.33 400.00 0.16 20.80 43.00 1500.004 250 1520.00 200.00 1450.00 1.23 1.01 0.85 75.74 425.00 0.17 22.10 56.00 1900.005 300 1821.00 200.00 1500.00 1.35 1.10 0.90 83.79 450.00 0.18 23.40 65.00 2200.006 350 2283.00 200.00 1550.00 1.47 1.19 0.95 92.35 475.00 0.19 24.70 78.00 2700.007 400 2760.00 200.00 1600.00 1.60 1.27 1.00 101.43 500.00 0.20 26.00 92.00 3200.008 450 3334.00 200.00 1650.00 1.73 1.36 1.05 111.03 525.00 0.21 27.30 101.00 3900.009 500 3863.00 200.00 1700.00 1.87 1.45 1.10 121.15 550.00 0.22 28.60 119.00 4400.00

10 600 5121.00 200.00 1800.00 2.16 1.64 1.20 142.94 600.00 0.24 31.20 159.00 5800.0011 700 6598.00 200.00 1900.00 2.47 1.83 1.30 166.80 650.00 0.26 33.80 206.00 7300.00

Cost per meter for Ductile Iron Pipes

Job No.:4904A Page 1 of 1

Page 80: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 7.7UNIT RATE ANALYSIS FOR M.S. PIPES

S S ThickCost of spirally weldedCost of Cost of Depth Depth Qty.of Qty.of Qty.of Cost of Cost of Butt HydraulicLowering L I ness ERW/SAW/Fabricatedinternal guniting of of earth B.fill Road exvn. Road Welding Testing & Total N Z of MSM.S. pipes linning murum earth work Reinst- B. fill. Reinst- laying O E Plate bedding work atement bedding atement charges

mm mm Rs./m Rs./m. Rs./m. mm Cum./mCum./m Sq.m/m Rs./m Rs./m Rs./m Rs./m Rs./m1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

1 800 8 6525.00 402.12 507.68 200.00 2.00 2.80 2.02 1.40 229.14 700 279 19.64 161.00 9000.002 900 8 7311.00 452.39 570.51 200.00 2.10 3.16 2.21 1.50 259.74 750 279 19.64 161.00 10000.003 1000 8 8096.00 502.65 633.35 200.00 2.20 3.52 2.41 1.60 292.42 800 279 19.72 161.00 11000.00

Cost per meter for Mild Steel Pipes

Job No.: 4904A Page 1 of 1

Page 81: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 7.8Cost Estimation for Bituminous Pavements

for 1 lane carriagewayConsidering 7% CBR and traffic intensity of 01 MSA

No Item Unit No L B H Quantity Rate Amount

1

Providing, laying,spreading and compactingspecified graded crush stone in Granular SubBase course (drainage layer) includingpremixing the material in mechanical mixer layingin uniform layers of 75 mm (compactingthickness each) with Motor grader/ paver finisheron prepared murrum surface and compactingwith 10 T vibrating tandem roller to achieve thedensity of 98% of MDD including all material ,labour , machinery with all leads and lifts etc.complete as directed by Engineer-In-charge.

Cum 1 1000 3.5 0.15 525 206.07 108186.8

2

Providing and laying water bound macadam75mm consolidated thickness, includingconveying metal with leads upto 0.5km and liftsspreading, sectioning, compaction and spreadingblindage, includig artificial watering etc.complete. Grade II metal 63mm to 40mm(I 61/Pg 19 , MCC DSR 2001 2002)

Cum 1 1000 3.5 0.225 787.5 542.746 427412.5

Road Estimate for Bituminous Road

Job No.:4904A Page 1 of 2

Page 82: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 7.8Cost Estimation for Bituminous Pavements

3

Providing 20 mm thick premix bituminous carpetincluding supplying all material, preparing &cleaning the base, heating bitumen, mixing hotbitumen & aggregates in a bitumen mixer,layingthe carpet layers and compaction with vibratoryroller complete by using bulk asphalt (the ratedoes not include cost of tack coat and seal coat)with Bitumen 60/70 grade( I 101 Pg 248, PuneDSR)

Sqm 1 1000 3.5 3500 62.15 217525

4

Providing earthwork in embankment withapproved materials obtained from privte land,including all lifts and 50m lead laying in layers of20cm to 30cm thickness breaking clods, dressingto the required lines, curves grades and section,watering and compaction to 95% of standardProctor Density complete (I 32/ Pg 237 , PuneDSR 2005 2006 )

Cum 1 1000 3.5 0.6 2100 77.3 162330

side shoulders 2 1000 0.15 0.395 118.5 77.3 9160.05

Total Pavement Thickness 0.375 m (Rs.) 924614.3

Rate per sqm Rs. Sqm264.1755052

924614.2681

Job No.:4904A Page 2 of 2

Page 83: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 7.9.1COST ESTIMATE FOR ESR AT ASARJAN AND VASARNI

CAPACITY OF THE TANK 2.00 ML

STAGING HEIGHT 15.0 m

Item No.

Description of Item Quantity Unit Rate (Rs) Amount (Rs)

I EARTHWORK1 Earthwork in excavation including clearing away

vegetation, shrubs, etc., if any, for foundation in earth,soil of all types (ordinary/ hard soil) in both dry andwet conditions, sand, gravel and soft murum, includingdewatering, dressing of sides and ramming of bottomand transporting the excavated material beyond thebuilding area, stacking, spreading and levelling, etc.all complete as specified and as directed.For depthupto 1.5 m from GL(MJP-SOR-Year 2005-2006, page -29)

868.4 m3 34.00 29524.17

2 Earthwork in excavation including clearing awayvegetation, shrubs, etc., if any, for foundation in earth,soil of all types (ordinary/ hard soil) in both dry andwet conditions, sand, gravel and soft murum, includingdewatering, dressing of sides and ramming of bottomand transporting the excavated material beyond thebuilding area, stacking, spreading and levelling, etc.all complete as specified and as directed.For depth1.5 m to 3.0m (MJP-SOR-Year 2005-2006, page -29)

1,057.3 m3 40.00 42292.04

3 Filling above raft at all depths/ elevation withapproved excavated materials in 15 cm to 20 cmlayers including watering, ramming, compacting to95% Modified Proctor density and dressing, levellingto the required profiles, etc. complete as directed bythe Engineer.(MJP-SOR-Year 2005-2006, page -33)

1,410.7 m3 17.00 23981.99

4 Providing and laying minimum 230 mm thick dryrubble (soling) packing under floor/ grade slabs withapproved hard stone set in regular lines, handpacked, filling the interstices with small stone chipsand sand, ramming, watering and compactingcomplete. (MJP-SOR-Year 2005-2006, page -33)

230.6 m3 340.00 78390.45

TOTAL FOR EARTHWORK 174188.65

SCHEDULE OF QUANTITIESESR AT ASARJAN AND VASARNI

Job No.:4904A

Page 84: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 7.9.1COST ESTIMATE FOR ESR AT ASARJAN AND VASARNI

CAPACITY OF THE TANK 2.00 ML

STAGING HEIGHT 15.0 m

Item No.

Description of Item Quantity Unit Rate (Rs) Amount (Rs)

SCHEDULE OF QUANTITIESESR AT ASARJAN AND VASARNI

II CONCRETE AND ALLIED WORKS5 Providing and laying in situ cement concrete in

proporation 1:4:8 of trap metal for foundation andbedding, including bailing out water manually,formwork, compacting and curing etc. complete.(Bd.E-1/page-287, year 2004-05, increase 10%)

43.5 m3 1500.00 65207.68

6 Providing and casting in situ cement concrete M15 oftrap metal for R.C.C. work as per detailed drawingsand designs or as directed, including normaldewatering, centering formwork, compacting,roughening the surface if special finish is to beprovided and curing etc.complete (Excluding steelreinforcement.) (MJP-SOR-Year 2005-2006)a) Grade slab (page-38) 42.3 m3 2475.00 104645.87

7 Providing and casting in situ cement concrete M25 oftrap metal for R.C.C. work as per detailed drawingsand designs or as directed, including normaldewatering, centering formwork, compacting,roughening the surface if special finish is to beprovided and curing etc.complete (Excluding steelreinforcement.) (MJP-SOR-Year 2005-2006)a) Raft (page-36) 229.0 m3 2586.00 592251.16

b) Column (page-36) 94.0 m3 2795.00 262673.61

c) Beams and Braces (page-37) 237.4 m3 2745.00 651740.48

d) Staircase (page-38) 16.0 m3 2825.00 45084.37

8 Providing and casting in situ cement concrete M30 oftrap metal for R.C.C. work as per detailed drawingsand designs or as directed, including normaldewatering, centering formwork, compacting,roughening the surface if special finish is to beprovided and curing etc.complete (Excluding steelreinforcement.) (MJP-SOR-Year 2005-2006)a)Vertical Wall and floor slab (page-38) 331.5 m3 2870.00 951292.50

b) Dome (page-39) 44.6 m3 3110.00 138690.16

9 Providing and fixing in position HYSD bar of variousdiameters for R.C.C. pile caps, footings, foundations,slabs, beams, columns, canopies, staircases, newels,chajjas, lintels, pardies, coping, fins, arches, etc. asper detailed designs, drawings and schedules,including cutting, bending, hooking the bars, bindingwith wires or tack welding and supporting as requiredetc.complete (MJP-SOR-Year 2005-2006, page -39)

91.0 M.T 30840.00 2807535.56

TOTAL FOR CONCRETE AND ALLIED WORKS 5619121.40

Job No.:4904A

Page 85: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 7.9.1COST ESTIMATE FOR ESR AT ASARJAN AND VASARNI

CAPACITY OF THE TANK 2.00 ML

STAGING HEIGHT 15.0 m

Item No.

Description of Item Quantity Unit Rate (Rs) Amount (Rs)

SCHEDULE OF QUANTITIESESR AT ASARJAN AND VASARNI

III MISCELLANEOUS WORKS 10 Providing and fixing G.I. Pipe railing having 1.0 m

height consisting 50 x50 x6 mm M.S angle as verticalat 1.5 m c/c with 3 rows of 25 mm dia G.I. Pipes ofmedium class as horizontal and painting 3 coats of oilpaint over one coat of anticorrosive paint of approvedcolour etc. complete (MJP-SOR-Year 2005-2006, page -46)

78.5 RMT 460.00 36128.32

11 Providing and applying colour wash of approvedcolour, shade and quality in two coat to new surface,including scaffolding, brushing and brooming downetc. complete.(excluding two coats of white wash asbase coat to be paid separately)(Bd.P-2/page-412, year 2004-05, increase 10%)

3,443.8 m2 4.00 13775.13

12 Ladder LS 5000.00

13 Providing D.I. Pipes of D.I.K-9 with internal cementmorted lining and including all taxes, insurance,railway freight, unloading from railway wagon, loadinginto truck, transport to depertmental stores/site,unloading, stacking, etc. complete(MJP-SOR-Year 2005-2006, page -58)

a) Inlet 300mm dia. Pipe 25.0 RMT 1821.00 45525.00b) Outlet 400mm dia. pipe 20.0 RMT 2760.00 55200.00c) Washout 400mm dia pipe 25.0 RMT 2760.00 69000.00

14 Valve and valve chamber of dia 300mm 1.0 NO. 88000.00 88000.00

TOTAL FOR MISCELLANEOUS WORKS 312628.45GRAND TOTAL 6105938.50COST PER LITRE OF WATER Rs. 3.05

Job No.:4904A

Page 86: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 7.9.2COST ESTIMATION FOR ESR AT KAVATHA, NEAR LATUR ROAD

CAPACITY OF THE TANK 2.50 ML

STAGING HEIGHT 20.0 m

Item No. Description of Item Quantity Unit Rate (Rs) Amount (Rs)

I EARTHWORK1 Earthwork in excavation including clearing away

vegetation, shrubs, etc., if any, for foundation in earth,soil of all types (ordinary/ hard soil) in both dry andwet conditions, sand, gravel and soft murum, includingdewatering, dressing of sides and ramming of bottomand transporting the excavated material beyond thebuilding area, stacking, spreading and levelling, etc.all complete as specified and as directed.For depthupto 1.5 m from GL(MJP-SOR-Year 2005-2006, page -29)

1,069.8 m3 34.00 36373.62

2 Earthwork in excavation including clearing awayvegetation, shrubs, etc., if any, for foundation in earth,soil of all types (ordinary/ hard soil) in both dry andwet conditions, sand, gravel and soft murum, includingdewatering, dressing of sides and ramming of bottomand transporting the excavated material beyond thebuilding area, stacking, spreading and levelling, etc.all complete as specified and as directed.For depth1.5 m to 3.0m (MJP-SOR-Year 2005-2006, page -29)

1,303.1 m3 40.00 52123.03

3 Filling above raft at all depths/ elevation with approvedexcavated materials in 15 cm to 20 cm layersincluding watering, ramming, compacting to 95%Modified Proctor density and dressing, levelling to therequired profiles, etc. complete as directed by theEngineer. . (MJP-SOR-Year 2005-2006, page -33)

1,703.3 m3 17.00 28955.72

4 Providing and laying minimum 230 mm thick dryrubble (soling) packing under floor/ grade slabs withapproved hard stone set in regular lines, hand packed, filling the interstices with small stone chips and sand,ramming, watering and compacting complete.(MJP-SOR-Year 2005-2006, page -33)

286.1 m3 340.00 97267.32

TOTAL FOR EARTHWORK 214719.68

SCHEDULE OF QUANTITIESESR AT KAVATHA, NEAR LATUR ROAD

Job No.:4904A

Page 87: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 7.9.2COST ESTIMATION FOR ESR AT KAVATHA, NEAR LATUR ROAD

CAPACITY OF THE TANK 2.50 ML

STAGING HEIGHT 20.0 m

Item No. Description of Item Quantity Unit Rate (Rs) Amount (Rs)

SCHEDULE OF QUANTITIESESR AT KAVATHA, NEAR LATUR ROAD

II CONCRETE AND ALLIED WORKS5 Providing and laying in situ cement concrete in

proporation 1:4:8 of trap metal for foundation andbedding, including bailing out water manually,formwork, compacting and curing etc. complete.(Bd.E-1/page-287, year 2004-05, increase 10%)

53.5 m3 1500.00 80316.78

6 Providing and casting in situ cement concrete M15 oftrap metal for R.C.C. work as per detailed drawingsand designs or as directed, including normaldewatering, centering formwork, compacting,roughening the surface if special finish is to beprovided and curing etc.complete (Excluding steelreinforcement.) (MJP-SOR-Year2005-2006)a) Grade slab (page-38) 53.0 m3 2475.00 131150.41

7 Providing and casting in situ cement concrete M25 oftrap metal for R.C.C. work as per detailed drawingsand designs or as directed, including normaldewatering, centering formwork, compacting,roughening the surface if special finish is to beprovided and curing etc.complete (Excluding steelreinforcement.) (MJP-SOR-Year2005-2006)a) Raft (page-36) 318.1 m3 2586.00 822571.06

b) Column (page-36) 119.8 m3 2795.00 334864.56

c) Beams and Braces (page-37) 325.1 m3 2745.00 892437.59

d) Staircase (page-38) 20.1 m3 2825.00 56895.31

8 Providing and casting in situ cement concrete M30 oftrap metal for R.C.C. work as per detailed drawingsand designs or as directed, including normaldewatering, centering formwork, compacting,roughening the surface if special finish is to beprovided and curing etc.complete (Excluding steelreinforcement.) (MJP-SOR-Year2005-2006)a)Vertical Wall and floor slab (page-38) 409.1 m3 2870.00 1174084.77

b) Dome (page-39) 55.1 m3 3110.00 171225.44

Job No.:4904A

Page 88: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 7.9.2COST ESTIMATION FOR ESR AT KAVATHA, NEAR LATUR ROAD

CAPACITY OF THE TANK 2.50 ML

STAGING HEIGHT 20.0 m

Item No. Description of Item Quantity Unit Rate (Rs) Amount (Rs)

SCHEDULE OF QUANTITIESESR AT KAVATHA, NEAR LATUR ROAD

9 Providing and fixing in position HYSD bar of variousdiameters for R.C.C. pile caps, footings, foundations,slabs, beams, columns, canopies, staircases, newels,chajjas, lintels, pardies, coping, fins, arches, etc. asper detailed designs, drawings and schedules,including cutting, bending, hooking the bars, bindingwith wires or tack welding and supporting as requiredetc.complete (MJP-SOR-Year 2005-2006, page -39)

121.6 M.T 30840.00 3751018.70

TOTAL FOR CONCRETE AND ALLIED WORKS 7414564.61

III MISCELLANEOUS WORKS 10 Providing and fixing G.I. Pipe railing having 1.0 m

height consisting 50 x50 x6 mm M.S angle as verticalat 1.5 m c/c with 3 rows of 25 mm dia G.I. Pipes ofmedium class as horizontal and painting 3 coats of oilpaint over one coat of anticorrosive paint of approvedcolour etc. complete (MJP-SOR-Year2005-2006, page -46)

87.3 RMT 460.00 40174.69

11 Providing and applying colour wash of approvedcolour, shade and quality in two coat to new surface,including scaffolding, brushing and brooming downetc. complete.(excluding two coats of white wash asbase coat to be paid separately) (Bd.P-2/page-412,year 2004-05, increase 10%)

4,355.0 m2 4.00 17420.15

12 Ladder LS 5000.00

13 Providing D.I. Pipes of D.I.K-9 with internal cementmorted lining and including all taxes, insurance,railway freight, unloading from railway wagon, loadinginto truck, transport to depertmental stores/site,unloading, stacking, etc. complete(MJP-SOR-Year 2005-2006, page -58)

a) Inlet 450mm dia. Pipe 25.0 RMT 3334.00 83350.00b) Outlet 500mm dia. pipe 20.0 RMT 3863.00 77260.00c) Washout 500mm dia pipe 25.0 RMT 3863.00 96575.00

14 Valve and valve chamber of dia 450mm 1.0 NO. 214000.0 214000.00

TOTAL FOR MISCELLANEOUS WORKS 533779.84GRAND TOTAL 8163064.13COST PER LITRE OF WATER Rs. 3.27

Job No.:4904A

Page 89: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 7.9.3COST ESTIMATE FOR ESR AT ASADVAN

CAPACITY OF THE TANK 2.00 ML

STAGING HEIGHT 20.0 m

Item No. Description of Item Quantity Unit Rate (Rs) Amount (Rs)

I EARTHWORK1 Earthwork in excavation including clearing away

vegetation, shrubs, etc., if any, for foundation in earth,soil of all types (ordinary/ hard soil) in both dry and wetconditions, sand, gravel and soft murum, includingdewatering, dressing of sides and ramming of bottomand transporting the excavated material beyond thebuilding area, stacking, spreading and levelling, etc. allcomplete as specified and as directed.For depth upto1.5 m from GL(MJP-SOR-Year 2005-2006, page -29)

900.5 m3 34.00 30615.67

2 Earthwork in excavation including clearing awayvegetation, shrubs, etc., if any, for foundation in earth,soil of all types (ordinary/ hard soil) in both dry and wetconditions, sand, gravel and soft murum, includingdewatering, dressing of sides and ramming of bottomand transporting the excavated material beyond thebuilding area, stacking, spreading and levelling, etc. allcomplete as specified and as directed.For depth 1.5 mto 3.0m (MJP-SOR-Year 2005-2006, page -29)

1,096.5 m3 40.00 43858.68

3 Filling above raft at all depths/ elevation with approvedexcavated materials in 15 cm to 20 cm layersincluding watering, ramming, compacting to 95%Modified Proctor density and dressing, levelling to therequired profiles, etc. complete as directed by theEngineer. (MJP-SOR-Year 2005-2006, page -33)

1,464.5 m3 17.00 24896.05

4 Providing and laying minimum 230 mm thick dryrubble (soling) packing under floor/ grade slabs withapproved hard stone set in regular lines, hand packed,filling the interstices with small stone chips and sand,ramming, watering and compacting complete.(MJP-SOR-Year 2005-2006, page -33)

235.5 m3 340.00 80064.10

TOTAL FOR EARTHWORK 179434.49

SCHEDULE OF QUANTITIESESR AT ASADVAN

Job No.:4904A

Page 90: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 7.9.3COST ESTIMATE FOR ESR AT ASADVAN

CAPACITY OF THE TANK 2.00 ML

STAGING HEIGHT 20.0 m

Item No. Description of Item Quantity Unit Rate (Rs) Amount (Rs)

SCHEDULE OF QUANTITIESESR AT ASADVAN

II CONCRETE AND ALLIED WORKS5 Providing and laying in situ cement concrete in

proporation 1:4:8 of trap metal for foundation andbedding, including bailing out water manually,formwork, compacting and curing etc. complete.(Bd.E-1/page-287, year 2004-05, increase 10%)

45.1 m3 1500.00 67615.42

6 Providing and casting in situ cement concrete M15 oftrap metal for R.C.C. work as per detailed drawingsand designs or as directed, including normaldewatering, centering formwork, compacting,roughening the surface if special finish is to beprovided and curing etc.complete (Excluding steelreinforcement.) (MJP-SOR-Year 2005-2006)a) Grade slab (page-38) 42.3 m3 2475.00 104645.87

7 Providing and casting in situ cement concrete M25 oftrap metal for R.C.C. work as per detailed drawingsand designs or as directed, including normaldewatering, centering formwork, compacting,roughening the surface if special finish is to beprovided and curing etc.complete (Excluding steelreinforcement.) (MJP-SOR-Year 2005-2006)a) Raft (page-36) 237.6 m3 2586.00 614389.49

b) Column (page-36) 122.8 m3 2795.00 343266.71

c) Beams and Braces (page-37) 267.8 m3 2745.00 735190.28

d) Staircase (page-38) 20.1 m3 2825.00 56895.31

8 Providing and casting in situ cement concrete M30 oftrap metal for R.C.C. work as per detailed drawingsand designs or as directed, including normaldewatering, centering formwork, compacting,roughening the surface if special finish is to beprovided and curing etc.complete (Excluding steelreinforcement.) (MJP-SOR-Year 2005-2006)a)Vertical Wall and floor slab (page-38) 331.5 m3 2870.00 951292.50

b) Dome (page-39) 44.6 m3 3110.00 138690.16

9 Providing and fixing in position HYSD bar of variousdiameters for R.C.C. pile caps, footings, foundations,slabs, beams, columns, canopies, staircases, newels,chajjas, lintels, pardies, coping, fins, arches, etc. asper detailed designs, drawings and schedules,including cutting, bending, hooking the bars, bindingwith wires or tack welding and supporting as requiredetc.complete (MJP-SOR-Year 2005-2006, page -39)

96.6 M.T 30840.00 2978593.65

Job No.:4904A

Page 91: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 7.9.3COST ESTIMATE FOR ESR AT ASADVAN

CAPACITY OF THE TANK 2.00 ML

STAGING HEIGHT 20.0 m

Item No. Description of Item Quantity Unit Rate (Rs) Amount (Rs)

SCHEDULE OF QUANTITIESESR AT ASADVAN

TOTAL FOR CONCRETE AND ALLIED WORKS 5990579.38

Job No.:4904A

Page 92: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 7.9.3COST ESTIMATE FOR ESR AT ASADVAN

CAPACITY OF THE TANK 2.00 ML

STAGING HEIGHT 20.0 m

Item No. Description of Item Quantity Unit Rate (Rs) Amount (Rs)

SCHEDULE OF QUANTITIESESR AT ASADVAN

III MISCELLANEOUS WORKS 10 Providing and fixing G.I. Pipe railing having 1.0 m

height consisting 50 x50 x6 mm M.S angle as verticalat 1.5 m c/c with 3 rows of 25 mm dia G.I. Pipes ofmedium class as horizontal and painting 3 coats of oilpaint over one coat of anticorrosive paint of approvedcolour etc. complete (MJP-SOR-Year 2005-2006, page -46)

78.5 RMT 460.00 36128.32

11 Providing and applying colour wash of approvedcolour, shade and quality in two coat to new surface,including scaffolding, brushing and brooming downetc. complete.(excluding two coats of white wash asbase coat to be paid separately)(Bd.P-2/page-412, year 2004-05, increase 10%)

3,944.2 m2 4.00 15776.83

12 Ladder LS 5000.00

13 Providing D.I. Pipes of D.I.K-9 with internal cementmorted lining and including all taxes, insurance,railway freight, unloading from railway wagon, loadinginto truck, transport to depertmental stores/site,unloading, stacking, etc. complete(MJP-SOR-Year 2005-2006, page -58)

a) Inlet 300mm dia. Pipe 25.0 RMT 1821.00 45525.00b) Outlet 400mm dia. pipe 20.0 RMT 2760.00 55200.00c) Washout 400mm dia pipe 25.0 RMT 2760.00 69000.00

14 Valve and valve chamber of dia 300mm 1.0 NO. 88000.00 88000.00

TOTAL FOR MISCELLANEOUS WORKS 314630.14GRAND TOTAL 6484644.02COST PER LITRE OF WATER Rs. 3.24

Job No.:4904A

Page 93: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 7.9.4COST ESTIMATION FOR ESR AT ASADVAN

CAPACITY OF THE TANK 1.50 ML

STAGING HEIGHT 10.0 m

Item No.

Description of Item Quantity Unit Rate (Rs) Amount (Rs)

I EARTHWORK1 Earthwork in excavation including clearing away

vegetation, shrubs, etc., if any, for foundation inearth, soil of all types (ordinary/ hard soil) in both dryand wet conditions, sand, gravel and soft murum,including dewatering, dressing of sides and rammingof bottom and transporting the excavated materialbeyond the building area, stacking, spreading andlevelling, etc. all complete as specified and asdirected.For depth upto 1.5 m from GL(MJP-SOR-Year 2005-2006, page -29)

745.8 m3 34.00 25358.41

2 Earthwork in excavation including clearing awayvegetation, shrubs, etc., if any, for foundation inearth, soil of all types (ordinary/ hard soil) in both dryand wet conditions, sand, gravel and soft murum,including dewatering, dressing of sides and rammingof bottom and transporting the excavated materialbeyond the building area, stacking, spreading andlevelling, etc. all complete as specified and asdirected.For depth 1.5 m to 3.0m (MJP-SOR-Year 2005-2006, page -29)

907.8 m3 40.00 36312.96

3 Filling above raft at all depths/ elevation withapproved excavated materials in 15 cm to 20 cmlayers including watering, ramming, compacting to95% Modified Proctor density and dressing, levellingto the required profiles, etc. complete as directed bythe Engineer. (MJP-SOR-Year2005-2006, page -33)

1,245.9 m3 17.00 21179.74

4 Providing and laying minimum 230 mm thick dryrubble (soling) packing under floor/ grade slabs withapproved hard stone set in regular lines, handpacked, filling the interstices with small stone chipsand sand, ramming, watering and compactingcomplete. (MJP-SOR-Year 2005-2006, page -33)

186.7 m3 340.00 63492.25

TOTAL FOR EARTHWORK 146343.37

SCHEDULE OF QUANTITIESESR AT ASADVAN

Job No.:4904A

Page 94: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 7.9.4COST ESTIMATION FOR ESR AT ASADVAN

CAPACITY OF THE TANK 1.50 ML

STAGING HEIGHT 10.0 m

Item No.

Description of Item Quantity Unit Rate (Rs) Amount (Rs)

SCHEDULE OF QUANTITIESESR AT ASADVAN

II CONCRETE AND ALLIED WORKS5 Providing and laying in situ cement concrete in

proporation 1:4:8 of trap metal for foundation andbedding, including bailing out water manually,formwork, compacting and curing etc. complete.(Bd.E-1/page-287, year 2004-05, increase 10%)

37.3 m3 1500.00 56018.52

6 Providing and casting in situ cement concrete M15of trap metal for R.C.C. work as per detaileddrawings and designs or as directed, includingnormal dewatering, centering formwork, compacting,roughening the surface if special finish is to beprovided and curing etc.complete (Excluding steelreinforcement.) (MJP-SOR-Year 2005-2006)a) Grade slab (page-38) 31.4 m3 2475.00 77709.79

7 Providing and casting in situ cement concrete M25of trap metal for R.C.C. work as per detaileddrawings and designs or as directed, includingnormal dewatering, centering formwork, compacting,roughening the surface if special finish is to beprovided and curing etc.complete (Excluding steelreinforcement.) (MJP-SOR-Year 2005-2006)a) Raft (page-36) 171.8 m3 2586.00 444289.92

b) Column (page-36) 66.7 m3 2795.00 186333.76

c) Beams and Braces (page-37) 145.5 m3 2745.00 399313.03

d) Staircase (page-38) 11.8 m3 2825.00 33273.44

8 Providing and casting in situ cement concrete M30of trap metal for R.C.C. work as per detaileddrawings and designs or as directed, includingnormal dewatering, centering formwork, compacting,roughening the surface if special finish is to beprovided and curing etc.complete (Excluding steelreinforcement.) (MJP-SOR-Year 2005-2006)a)Vertical Wall and floor slab (page-38) 248.1 m3 2870.00 712123.12

b) Dome (page-39) 38.6 m3 3110.00 119964.30

Job No.:4904A

Page 95: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 7.9.4COST ESTIMATION FOR ESR AT ASADVAN

CAPACITY OF THE TANK 1.50 ML

STAGING HEIGHT 10.0 m

Item No.

Description of Item Quantity Unit Rate (Rs) Amount (Rs)

SCHEDULE OF QUANTITIESESR AT ASADVAN

9 Providing and fixing in position HYSD bar of variousdiameters for R.C.C. pile caps, footings,foundations, slabs, beams, columns, canopies,staircases, newels, chajjas, lintels, pardies, coping,fins, arches, etc. as per detailed designs, drawingsand schedules, including cutting, bending, hookingthe bars, binding with wires or tack welding andsupporting as required etc.complete(MJP-SOR-Year 2005-2006, page -39)

70.4 M.T 30840.00 2171238.02

TOTAL FOR CONCRETE AND ALLIED WORKS 4200263.91

Job No.:4904A

Page 96: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 7.9.4COST ESTIMATION FOR ESR AT ASADVAN

CAPACITY OF THE TANK 1.50 ML

STAGING HEIGHT 10.0 m

Item No.

Description of Item Quantity Unit Rate (Rs) Amount (Rs)

SCHEDULE OF QUANTITIESESR AT ASADVAN

III MISCELLANEOUS WORKS 10 Providing and fixing G.I. Pipe railing having 1.0 m

height consisting 50 x50 x6 mm M.S angle asvertical at 1.5 m c/c with 3 rows of 25 mm dia G.I.Pipes of medium class as horizontal and painting 3coats of oil paint over one coat of anticorrosive paintof approved colour etc. complete (MJP-SOR-Year 2005-2006, page -46)

68.8 RMT 460.00 31648.40

11 Providing and applying colour wash of approvedcolour, shade and quality in two coat to new surface,including scaffolding, brushing and brooming downetc. complete.(excluding two coats of white wash asbase coat to be paid separately) (Bd.P-2/page-412,year 2004-05, increase 10%)

2,530.6 m2 4.00 10122.59

12 Ladder LS 5000.00

13 Providing D.I. Pipes of D.I.K-9 with internal cementmorted lining and including all taxes, insurance,railway freight, unloading from railway wagon,loading into truck, transport to depertmentalstores/site, unloading, stacking, etc. complete(MJP-SOR-Year 2005-2006, page -58)

a) Inlet 300mm dia. Pipe 25.0 RMT 1821.00 45525.00b) Outlet 400mm dia. pipe 20.0 RMT 2760.00 55200.00c) Washout 400mm dia pipe 25.0 RMT 2760.00 69000.00

14 Valve and valve chamber of dia 300mm 1.0 NO. 88000.00 88000.00

TOTAL FOR MISCELLANEOUS WORKS 304496.00GRAND TOTAL 4651103.27COST PER LITRE OF WATER Rs. 3.10

Job No.:4904A

Page 97: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 7.10COST ESTIMATION FOR REHABILITATION OF CIVIL WORKS

Sl. No.

Description Quantity Rate Cost in Rs.

a Widows and doorsProviding and fixing in position cold rolled pressed steel sheet door/ window frame of size 100 x 60 x 1.25 mm. (18 B.W.G. thickness) including holdfasts, no member at bottom of frame 10 mm. thick rebate and depth of rebate after shutter thickness, hinges, holdfast etc. fitted after shutter requirement, powder coating to the frame and filling the frame with concrete or mortar etc. complete.As per Maharashtra PWD DSR Aurangabad Region, 2004-05 Cl. 302 BDT 2A 72 200 14400

Providing and fixing in position mild steel door/window shutters including mild steel

angle frame of size 25 X 25 X 5 mm. for fixing mild steel sheet 24 gauge including welding

fixing to frame and all necessary fixtures including electrostatic powder coating etc.

complete.As per Maharashtra PWD DSR Aurangabad

Region, 2004-05 Cl. 371 BD ADL-29 60 1000 60000

b Replacement of sand m3750 5300 3975000

c

Manufacture,supply and commission electromagnetic flow meter, raw water and pure water ith accuracy 0.5% of measured value & protection as per given specifications for size 100-1000mm. Including sensor, transmitter,surge arrester,25 mtr sensor/transmitter cable,GI duct of suitablensize for 25 mtr/each flow meter,including pipe cutting,levelling & installation of flow meter in pipe line with necessary tool tackles,crane etc, as may be required at site & based on technical specificationsCIDCO WTP inlet and outlet - 450 mm 2 467894 935800CIDCO ESR - 250 mm 2 242769 485600

Total Rs. 5470800

Escalated Cost for 2006-07 Rate 5799000Say Rs, 5800000

Escalated @ 6% per year

Rehabilitation Civil Works at Kabranagar

Job No.:4904A Page 1 of 1

Page 98: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 7.11 Cost Estimation of Electrical Rehabilitation Works

Job No.:4904A

Electrical Cost Estimate for Design Period of year 2023

Sr No

Description Qty Rate Total Amount

A CIDCO RAW WATER PUMPING STATION 1 11kV Cable 50 mtre 2301 115043 2 11kV Indoor Termination kits 3 Nos 7789 23367 3 11kV outdoor Termination kits 3 Nos 11872 35616 4 11kV Indoor VCB panel with 1 incomer and 3

outgoings 1 set 1516186 1516186

11KV /415V,750kVA Transformer 2 Nos 517896 1035792 5 415V Main MCC 1 Nos 2180523 2180523 6 415V Sub distribution boards 1 Nos 814562 814562 11kV Overhead line 2kM 600000 600000 7 Battery ,Battery charger and DCDB 1 Nos 1421575 1421575 8 Capacitor bank with APFCR 2 set 572112 1144224 9 L.T cables with Glands, Lugs and cable carrier

system with trays 1 Lot 1973379 1973379

10 Earthing 1 Lot 74549 74549 11 Lighting Panel 1 Nos 20549 20549 12 ON-OFF Push Button Station 8Nos 5292 5292 13 Lighting fixtures and point wiring 1 Lot 192826 192826 11153483

B CIDCO 12MLD WATER TREATMENT PLANT AND CLEAR WATER PUMPING STATION 1 415V MCC at CWPS 1 Nos 546050 546050 2 WTP MCC 1 Nos 441657 441657 3 Lighting Panel 1 Nos 20549 20549 4 Capacitor bank with APFCR 1 set 553320 553320 5 L.T cables with Glands , Lugs and Cable

Carrier System with trays and supports 1 Lot 2179903 2179903

6 Earthing 1 Lot 96036 96036

Page 99: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 7.11 Cost Estimation of Electrical Rehabilitation Works

Job No.:4904A

7 ON-OFF Push Button Station 15Nos 9923 9923 8 Lighting fixtures and point wiring 1 Lot 318619 318619 9 11kV Overhead line 2.5kM 750000 750000

Total 4916056 Grand Total A+B 16069539 Note : For details refer back up sheets

Page 100: Detailed Project Report - nwcmcnwcmc.gov.in/JNNURM/ilfs/NAD-12/WS-South Nanded.pdf · Elevated Service Reservoir Liters per Capita per Day ... perspective plan & detailed project

Table 7.12Cost Estimate Mechanical Works

Sr. No.: ITEM DESCRIPTIONDESIGN

CRITERIA QTY UNIT PRICE PRICE1 CIDCO RWPS (existing)

a Vertical Pumps580 cum/hr H = 52 mtr 2 1000000 2000000 M & P quote for MP Job

b Motors 132 kW 2 350000 700000 M & P quote for MP Jobd Pressure Gauges 4 750 3000 MJP price Schdule of 2005

e Level Transmitter 1 125000 125000Toshbro Controls offer dt. 28.12.2005 Sr. No. 1a)

f Flow meter 1 325000 325000Estimate from previous project (E & H)

g Installation etc 1 200000 200000 estimate

2 12 Mld WTP (CIDCO)a Alum constant Head contrller 1 50000 50000 Quote to be obtainedb Flash Mixer 1 90000 90000 Pooja Const co Estic Flocculator 2 75000 150000 Pooja Const co Estid Alum Mixer 3 100000 300000 Lysander-Hind Eng Co offere Lime Mixer 2 100000 200000 Lysander-Hind Eng Co offerf Pipes and Valve (chemical) 1 50000 50000 Estimateh Valves 1 300000 300000 EstimateI Gates 1 150000 150000 Puja Const. Co offer

j Rate of Flow and Loss of Head ind. 3 60000 180000 Quote to be obtainedk Clarifier bridge/ scrappermechnisum 1 200000 200000

l Pre chlorination 0-2.5 kg/hr 1 300000 300000

Quote of Efficient Connections ( Wallace & Tiernanmake) dt 24.10.05

m Post Chlorination 0-1 kg/hr 1 200000 200000

Quote of Efficient Connections ( Wallace & Tiernanmake) dt 24.10.05

n Installaion/rehabilitation 500000 500000

3 PWPS

a Hori. Split case Pumps525 cum/hr, H = 20 mtr 2 200000 400000 M & P offer for MP Job

b Motors for above 45 Kw 2 125000 250000 M & P offer for MP Jobc Pressure Gauges 4 750 3000 MJP price Schdule of 2005

d flow meter 1 325000 325000

Estimate from previous project (E & H)

e Level Transmitter 1 125000 125000Toshbro Controls offer dt. 28.12.2005 Sr. No. 1a)

e refurbishment 1 200000 200000 Estimate7326000

Cost includes, installation, refurbishment, commissioning etc

COST ESTIMATE(SOUTH BANK/CIDCO EXISTING) NANDED ( 11.08.2006)

Job No.:4904A Page 1 of 1