Detail Project Report1MWp SPV Power Plant
w w w . r e n e w p o w e r z o n e . i n Page 1
Acknowledgement
This analysis based report is done for the readers of my previous report 1MW Utility Scale SPVPower Plant, mainly for the readers from South region of INDIA as they are asking repeatedlyabout the probability and feasibility-technical & Financial-of a SPV power plant in their region.At the same time it’s not possible for me to design a report for each and every state from SouthIndia, so I took Chennai city. Also the previous report was not so detail, was very basic andmeant to the readers who want to get an overview on how a utility scale power plant works.Now, in this report, I discuss about in depth. From panel’s selection to CB sizing all arepresented in very detail. Hope, this time you get a strong knowledge on designing andestimation of 1MW solar PV power plant. Unlike the previous report, the financial aspectdiscussed at the end of the paper. In this paper, the financial assessment has done in very detailand considering the current scenario of SPV market including the cost of solar PV modules,inverters’ cost, cable, transformer etc. prices and the funding, interest rate.And if you have any queries or need clarification, please contact at [email protected] [email protected] .
DisclaimerThe presented data here are NOT TAKEN from any copyright materials and not showing undermy name. The meteo data collected from NASA website and NREL database which is free overthe internet. Designing of PV system is totally based on the practical experience of the author.
Assumption & Consideration
Shading consideration: No shading has been considered at the site during the calculationdesign. So it is advised that at the time of execution, please check whether there is any kind ofobstacle in the site which may cause partial/full shading on PV strings and/or PV array. If theshading occurs, then the estimated power generation will not match the actual powergenerated.Load Factor: It is assumed that the produced power from the PV plant will be fed to the localutility grid. So, while designing the system, no unbalanced load considered in 3 phaseconfiguration.Meteo data: The calculation based on the meteo data collected from NASA website which isvery reliable. Now, based on the co-ordinates the values have been presented in this report. So,total design is based on this data. For a different location (coordinates), the system design willdiffer. It is advised not to copy and implement the design without consulting the author or anycertified PV professional because this design estimation is valid only for a particular site.
Queries@ [email protected]
Detail Project Report1MWp SPV Power Plant
w w w . r e n e w p o w e r z o n e . i n Page 2
Site consideration: this design has been done by considering the PV modules & array will beground-mounted and the site-elevation angle taken 30 .
Cost Estimation: 1MW Solar PV power plant cost estimation has done considering the currentPV market scenario (Sept-Dec 2013), so after few months the cost may vary according themarket.CAD design & layout: I have not uploaded/attached the CAD design. If anybody interested insetting up the plant then only contact at the given e-mail ids to get the design file.
Transmission & wheeling losses: Here, in this report, while doing the technical assessment, thedistance from nearest substation to the 1MW solar PV power plant taken within 1.5 KM and sothe wheeling losses considered as 3% of total power transmission. And in the financialassessment, no wheeling charges have been considered.
Design Criteria: While designing & estimating the technical components & solutions, all therequired/applicable standard design codes have been considered. Mainly the IEC (InternationalElectrotechnical Commission) Codes, IS codes from BIS have been considered thoroughly.
Queries@ [email protected]
Detail Project Report1MWp SPV Power Plant
w w w . r e n e w p o w e r z o n e . i n Page 3
Contents1) Introduction 42) Project details 53) Location metrological details 64) Determination of optimum tilt angle 75) Solar power plant overview 86) Module selection & sizing 97) Inverter selection & sizing 118) Transformer selection 129) Other protective devices including switch gear details 1310) Cable sizing & selection 1411) Civil works details 1612) Performance analysis & simulation 1713) Timeline of the project 2114) Operation & maintenance structure of the plant 2215) Financial calculation, estimation of NCF, Payback period 2316) Guide on selection of various components 2717) Conclusion 2818) About the Author 28
Queries@ [email protected]
Detail Project Report1MWp SPV Power Plant
w w w . r e n e w p o w e r z o n e . i n Page 4
IntroductionIndia is densely populated and has high solar insolation, an ideal combination for using solar power inIndia. India is already a leader in wind power generation. In the solar energy sector, some large projectshave been proposed, and a 35,000 km2 area of the Thar Desert has been set aside for solar powerprojects, sufficient to generate 700 GW to 2,100 GW. Also India's Ministry of New and RenewableEnergy has released the JNNSM Phase 2 Draft Policy, by which the Government aims to install 10GW ofSolar Power and of this 10 GW target, 4 GW would fall under the central scheme and the remaining 6GW under various State specific schemes.
The Electricity Act, 2003, paves way for an innovative approach to solve our country’s power problems.It has paved the way for a competitive environment; open access to existing transmission anddistribution network to transmit electricity across regions; de-licensing of generation, captive power anddedicated transmission lines; licensing of distribution and supply companies and the restructuring ofState Electricity Boards.
The Ministry of Power has mandated to promote cogeneration and renewable sources for Powergeneration under Nodal agencies and hence it will play a major role in mainstreaming renewable energysector. The advantage or renewable resources includes their capacity to produce energy withoutproducing carbon-based warming and polluting agents into the atmosphere. The financial cost of itsapplications is not always cheap but if the environmental costs of using fossil are accounted for,renewable energy wins hands-down. There are also indirect savings on health and its costs as there areno harmful emissions.
In the above backdrop, YOUR COMPANY NAME has decided to set up a 1/1000 MW/KW Solar PowerPlant. This Detailed Project Report (DPR) brings out all technical details and overall costs justifying theselection of the project. The total power generation is envisaged to be 1050KW from Solar PhotovoltaicCell. It is a very important document that is required for Environmental Impact Assessment (EIA) studies,fixation of tariff, finalizing Power Purchase Agreement (PPA) and also for submission to FinancialInstitutions for obtaining project funding. The total project cost is expected to be Rs ___ Crores and theaverage cost of generation is expected to be Rs. 7.5/kWh (ASSUMED).
For this project, poly-crystalline technology based 3rd generation Solar PV modules will be used. Alongwith this, highly efficient, photon-tested string inverters going to be integrated to the system. Thesetechnologies are the best in the industry. So, It’s clear that our project is not compromising with thequality of the materials and or the components which obviously led this project to success.
Queries@ [email protected]
Detail Project Report1MWp SPV Power Plant
w w w . r e n e w p o w e r z o n e . i n Page 5
Client’ details
Country India
Location CHENNAI
Contact id [email protected]
Contact Person abc
company ABCXYZ
Purpose Power generation &distribution to State utility grid
Project DetailsType of installation Ground-mounted
Estimated array peakpower
1100KWp
Shading consideration Shade-free
Grid voltage 11KVPhase connection 3-phase
Grid frequency 50HzAvailable/required area 20000 m2(apprx)
Safety level IP65
Site Location/Layout
Site & Meteo DetailsLocation coordinates 10.5, 78.5 (assumed)
AmbientTemperature(0C)
Max Average Min28.5 27.2 25.5
Relative humidity 72.5%Daily Solar irradiation-
Horizontal5.19 KWh/m2/day
Atmospheric Pressure 100.1 kPA
Wind Speed 2.7 m/sEarth temperature Max Average Min
29.6 28.8 26.4Height from sea level 10m
Queries@ [email protected]
Detail Project Report1MWp SPV Power Plant
w w w . r e n e w p o w e r z o n e . i n Page 6
0
1
2
3
4
5
6
7
KWh/
m2/
day
Solar Irradiation
Solar Irradiation
23
24
25
26
27
28
29
30
31Air & earth temperature-monthly
Air temperature
earth temperature
Queries@ [email protected]
Detail Project Report1MWp SPV Power Plant
w w w . r e n e w p o w e r z o n e . i n Page 7
Optimum Tilt Angles For Solar PV Array Adjusted by Months
Jan Feb Mar Apr May Jun34° 26° 13° 0° 11° 14°
Jul Aug Sep Oct Nov Dec12° 5° 6° 19° 29° 35°
Figures shown in degrees from vertical
Irradiation Data on different tilt angles (respect to horizontal surface, KWh/m2/day)
Months 100 250 120
January 5.04 5.35 5.41February 5.98 6.16 6.16March 6.51 6.41 6.52April 5.76 5.39 5.85May 5.78 5.65 5.78June 5.28 5.22 5.29July 4.99 4.9 4.99August 5.09 4.9 5.1September 5.33 5.14 5.34October 4.67 4.69 4.71November 4.27 4.44 4.45December 4.5 4.78 4.84Annual avg. 5.26 5.25 5.36
* Here, 120 angle at AM1.5 has been chosen as fixed south faced model for the project
Winter
56° angle
Spring/Autumn
80° angle
Summer
104° angle
On the 21st December, the sun will rise 87° east of due south and set 87° west of due south.On the 21st March/21st September, the sun will rise 91° east of due south and set 91° west of duesouth.On the 21st June, the sun will rise 95° east of due south and set 95° west of due south.
Queries@ [email protected]
Detail Project Report1MWp SPV Power Plant
w w w . r e n e w p o w e r z o n e . i n Page 8
Solar PV System Design
System OverviewSPV Array Peak Power 1082KWp
No. of SPV strings 206Connection of PV modules in each string Series
Inverter 20KW MPPT based 3 phase string InverterInverter Type/Topology MPPT & Transformer Less
Total no. of Inverters 53Strings/Inverter 4/1
Modular Components
Components Specification Quantity Make
Solar PV modules Max Peak Power=250WpVoc= 36V ;Vmp= 29V
Isc= 9.25A ; Imp= 8.65A
4326
Non-Modular ComponentsComponents Electrical Specification Quantity MakeInverters 20KW, 3Phase &MPPT;
Vmax= 800V53
Transformer 1250KVA 1SCADA/MonitoringSystem
Integrated with RemoteMonitoring system web based
1
Circuit Breaker Inverter to Busbar= 46A 3p;busbar/Panel box totransformer= 1600A 3p;
531
DC Disconnect 1000V,20Amps 206Switch Gear Rated voltage=12KV;
Rated main busbarcurrent(Max)=1250A;SC withstand capacity = 25KA/3sDynamic capacity= 50KA
1
Distribution Panel NA 1Isolator Vmax= 12KV;
Max cont. current=1250A1
Cables DC Side= 10 mm2
AC Side=LT: 16mm2 & HT:185mm2
Queries@ [email protected]
Detail Project Report1MWp SPV Power Plant
w w w . r e n e w p o w e r z o n e . i n Page 9
Solar PV Module Specification & Array Sizing Details
Required Electrical Characteristics of SPV Modules
Design criteria IEC-61853-1
Watt Peak 250Wp
VOC 37.20V
VMPP 30.10V
ISC 8.87A
IMPP 8.30A
ModuleEfficiency/module area
15%
Power Tolerance ±2%
Technology Si-Poly
No. of cells 60 cells in series
Required Temperature Co-efficient Characteristics@ STC
NOCT (oC) 45 ± 2 oC
Module Efficiency (%/oC) -0.07 ± 0.01
Temp. Co-Eff. Of Pmax (%/oC) -0.43 ± 0.05
Temp. Co-Eff. Of Voc (%/oC) -0.34 ± 0.05
Temp Co-Eff. of Isc (%/oC) 0.065± 0.05
PV Module Behavior at different irradiance levelPV Parameters @ 1000W/m2 @800 W/m2 @ 400 W/m2
PMPP 249.8.2W 200.6 W 100.00VOC 37.2V 36.8 V 35.8VVMPP 30.1V 30.2 V 30.1VISC 8.87A 6.64A 3.55AIMPP 8.31A 7.10A 3.33AModule efficiency 15.54% 15.32% 15.27%Temperature co-eff -0.43%/0C -0.43%/0C -0.44%/0C
Required Operating Condition Details:Maximum SystemVoltage (IEC)
1000V
Maximum Fuse Rating 15A
Limiting ReverseCurrent
15A
Operating TempRange
(-10 to 60)0C
Max Static Load-front(Snow+Wind)
5500PA
Max Static Load-Rear(wind)
2500PA
Model design parameters
R shunt 250 ohm
R shunt (G=0) 2100 ohm
R series model 0.29 ohm
R series max 0.37 ohm
R series apparent 0.47 ohm
Queries@ [email protected]
Detail Project Report1MWp SPV Power Plant
w w w . r e n e w p o w e r z o n e . i n Page 10
Solar PV Array Sizing & Connection Detailsconditions At STC (250C) At Avg. Ambient temp. (280C)Suggested array Size 1100 KWp 1100KWp
Actual Solar PV Array Size 1082KWp 1100KWp
Watt Peak of each SPV module 250Wp 263WpTotal nos. of SPV modulerequired
4326 4326
Total nos. of strings 206 206Nos. of SPV modules in eachstring
21 21
SPV connection in each string Series SeriesString voltage (VMPP) 609V 630VString current (ISC / IMPP) 8.87A/8.3A 9.51A/8.82AConnection of strings Parallel ParallelArray voltage (VOC / VMPP) 780V/635V 750V/620VArray current (ISC / IMPP) 1830A/1710A 1960A/1816A
Queries@ [email protected]
Detail Project Report1MWp SPV Power Plant
w w w . r e n e w p o w e r z o n e . i n Page 11
Detail Solar Inverter Specification & Design Details
Inverter Type String Inverter (MPPT)Quantity 53INPUT (DC)Max. Power 23KW
Max absolute Input Voltage 1000VStart Voltage 350VNominal MPP voltage range 490V-800V
Max Input Current per string 41.5ANos. of Independent MPP inputs/stringsper MPP inputs
1/6
OUTPUT (AC)Rated Output Power 20000WMax. Apparent AC Power 20000VAPower Threshold 20WNominal AC Voltage/range 3/N/PE;230/460VAC Power Frequency/ range 50HzMax. output current 3x29APower factor at rated power 1Feed-In phases/connection phases 3/3EfficiencyMax. Efficiency 98.7%Protection DetailsDC Disconnect AvailableDC Surge Arrester AvailableProtection Class I (as per IEC 62103)Total harmonic distortion <1.8%Operating Temperature range -25◦-60◦CNoise Emission <35dBSelf Consumption <25WCooling option Forced Air-cooledProtection type IP65 (as per En 60529)Remote Monitoring SystemUser Interference & Communication
With RS-485/Ethernet
Electrically Isolated relay output AvailableStatus Display AvailableInverter to inverter communication AvailableAnti-islanding protection AvailableInverter connection detailsTotal nos. of inverter 53Nos. of strings per inverter 4Connection of strings/inverter ParallelInter-inverter connection Parallel into Cu busbarInter-Inverter isolator Provided
Queries@ [email protected]
Detail Project Report1MWp SPV Power Plant
w w w . r e n e w p o w e r z o n e . i n Page 12
Transformer SizingDesign Criteria IS-2026 / IEC-60076Transformer type Power transformer, core type with oil-immersed ;
650C winding temp riseCooling type ONAN(Oil Natural Air Natural)Rated KVA 1250KVAHigh Voltage rating 11000VLow Voltage Rating 460VNominal impedance 4.7%Impedance tolerance 7.5%Nominal secondary amps 1250AMax SC withstand current 20KA/3sHV connection DELTALV connection WyeOperating frequency 50HzTap changer ±5% of full load capacity
Protective devices
components Specification QuantityDC Disconnects String to inverter= 1000V, 15A; 2 pole
(As per IEC-60947)206
Switch gear Rated voltage=12KV;Rated main busbar current(Max)=1250A;SC withstand capacity = 25KA/3sDynamic capacity= 50KAIP55
1
Circuit breakers (MCCB)(NOT required if Inverter has inbuiltprotection)
Inverter to Busbar= 60A 3p;busbar/Panel box to transformer= A 3p;
531
Main Isolator (HT side)Design criteria IS-9921/IEC-129
Operating frequency 50hz ±3% Rated peak withstandcurrent (KA peak/rms)
63.5KA
Nominal system voltage 11KV 1.2/50 micro sec lightingwithstand Volts (KV peak)
To earth andisolating poles
Across the isolatingdistances
170 195Max system voltage 12KV Rated 1 minute power
frequency withstandvoltage(KV r.m.s)
To earth andisolating poles
Across the isolatingdistances
75 85
Max continuous current 2500A No. of poles 3
Rated SC current for 3s 40KA Min creepage distance 320mm
Queries@ [email protected]
Detail Project Report1MWp SPV Power Plant
w w w . r e n e w p o w e r z o n e . i n Page 13
Cable Sizing
DC Side Cables (strings to inverter)Design criteria IEC-60811 & IEC-60216Cable material CopperSingle cable length per string to inverter 70 ftCross section per string 4 mm2
Voltage drop 0.18VRelative power loss reference to Max DC power 0.07%Max withstand temp. Normal condition Short-circuited
condition900C 2500C
Max withstand current capacity 42KA/1secConductor type StrandedInsulation material XLPELT Cables (Inverters to busbur/distribution panel)Design criteria IEC-60228 & IEC-60811Cable material CopperMax Single cable length per inverter to panel box 60 ftCross section 16 mm2
Voltage drop (3phase) 0.46VRelative power loss reference to Max AC nominalpower
0.23%
Max withstand temp Normal condition Short-circuitedcondition
900C 2500CMax withstand current capacity 2KA/1secConductor type StrandedInsulation PVCHT Cables (from distribution panel to feed-in point)Design criteria IEC-60502Cable material AlCable length from distribution panel to feed-in point
25 ft
Cross section 185mm2
Voltage drop (total) L1 1.37VL2 1.37VL3 1.37V
Relative power loss reference to Max ACpower
0.57%
Voltage grade 11KV(UE), heavy dutySC withstand current capacity 26KA @1sInsulation XLPE
Queries@ [email protected]
Detail Project Report1MWp SPV Power Plant
w w w . r e n e w p o w e r z o n e . i n Page 14
Line LossesDC Side AC Side Total
Total cable length 8120 ft 3070 ft 11180 ftCable cross section 4 mm2 16 mm2 +185 mm2 4 mm2 +16 mm2 +185
mm2
Power loss @ nominaloperation
35 KW 5 KW 40KW
Relative power loss @nominal operation
0.07% 0.76% 0.83%
Busbar constructional AnalysisBusbar material Main busbar Auxilury busbar
Al alloy E91 Egrade
Copper
Busbar insulation Fully insulated
Busbar length Main Aux3.5mt 0.75mt x 52
Earthing bus materials GS (IEEE std. 80/IEC-60439-1)
Earthing & Lighting ProtectionDesign Criteria IEEE Standard-80
Grounding System Earth grid resistance Less than 10 ohm
Placing of earthelectrode
Earth Pit
Earth Electrode sizing
Physical Parameters Heavy duty GI pipes, 32mm dia, 3mt long
Material Galvanized Steel(GS), flat typeMin depth of earth pit 600mmComponents grounding Min 75x10mm GS stripLightning Protection
Design criteria As per IEC-62305Placing On the highest panel of arrayDimension 40mm dia with 3m height (vertical air
termination)
Queries@ [email protected]
Detail Project Report1MWp SPV Power Plant
w w w . r e n e w p o w e r z o n e . i n Page 15
CIVIL WORKS
Live Loads estimation of control room + admin building (as per IS 875:1987)parameters details RemarksRoof load 1750 kg/ m2 As per IS-456
Ground floor load Control room 18000kg/m2 As per IS-456Office 5000kg/ m2 IS-456
Piping load 50 kg/ m2 As per IS-456Electrical + HVAC 26 kg/ m2 As per IS-456
Seismic load As per IS-456Roof drainageRoof drain heads 6Construction detailsInterwall
Cement : Sand 1:6Interwall thickness 230mmParapet walls
Cement : Sand 1:4thickness 115mm
Steel work Reinforced bars will be providedas per IS 800:2007
PV Array mounting & constructional detailsPV tilted angle (optimized) 130 (@1070 W/m2/day)
Mounting type Ground mountedOverall dimension As per design
Foundation Plain cement concrete (PCC)Foundation grade 1:5:10
Wind load 9.72 Km/hrFixing type SS 304 fasteners
Total Land required 5 acres
Queries@ [email protected]
Detail Project Report1MWp SPV Power Plant
w w w . r e n e w p o w e r z o n e . i n Page 16
System Performance Analysis & Simulation
Solar Paths at site on monthly basis Reference Incident energy in collector plane
Normalized production per installed KWp
Queries@ [email protected]
Detail Project Report1MWp SPV Power Plant
w w w . r e n e w p o w e r z o n e . i n Page 17
Performance Ratio (PR) Normalized Production & Loss factor
Daily System Output Energy SPV Array Power Distribution
Queries@ [email protected]
Detail Project Report1MWp SPV Power Plant
w w w . r e n e w p o w e r z o n e . i n Page 18
Queries@ [email protected]
Detail Project Report1MWp SPV Power Plant
w w w . r e n e w p o w e r z o n e . i n Page 19
Overall Power plant performance SummeryTotal no. of PV modules 4326 (250Wp)Total nos. of Inverters 53 (20KW)
Max DC input per Inverter 21KWNominal PV power 1082 KWp
Max. PV power output 1027 KWdcNominal AC power 1060KWac
Max operating power @ STC 962KWacMax operating power @Ambient Temp. 1027KWac
Plant production 1655 MWh/yearSpecific production 1526KWh/KWp/year
Normalized production 4.2 kWh/KWp/dayArray losses 0.87 KWh/Kp/day
Overall losses 0.22 KWh/KWp/dayPerformance ratio 0.80
Queries@ [email protected]
Detail Project Report1MWp SPV Power Plant
w w w . r e n e w p o w e r z o n e . i n Page 20
Time line of the project
Design
•Preparation of design & estimation of the plant•15 working days required.
Landacquisition
•As per design requirement, proper land selection & acquisition processed.•Time required 1 month
PPA
•Power Purchase Agreement(PPA) with private power purchaser need to be finalized at a feasible rate.•Required time is 15 working days
DPR
•Preparation of Detailed Project Report including technical feasibility of the project prepared.•Time required 6 working days.
finance
•Arrangement of finance/fund for the project from nationalized or private financing agency with significant interest rateand equity share will be finalized.
•Required time for this stage is 1 month.
procurement
•After finalizing PPA and arrangement of fund for the project, procurement work starts including preparation & finalizing ofvendor selection, BOM, BOQ, order placing, follow-ups of delivery to site/warehouse.
•Estimated time for this step is 1 month.
construction
•After the processing of procurement, first civil construction at the site starts for PV mounting structure set-up andcontrol-room, administrative building. Finishing the civil works, PV installation & all electrical construction works includingthe Grid Evacuation will be processed.
•Estimated time for this whole work is 2 months.
commissioning
•Commissioning of the plant by authorized govt. body or certified 3rd party will be done followed by Completion of projectexecution.
•required time for this step is 6 working days.
Queries@ [email protected]
Detail Project Report1MWp SPV Power Plant
w w w . r e n e w p o w e r z o n e . i n Page 21
Operation & Maintenance of Plant
Why do we need an O&M for Solar PV power plant?As every plant needs a regular maintenance work to make it functional & in well-condition, soin this case also, a PV power plant also requires a sound & efficient operation & managementteam to perform all the work after plant commissioning.A detailed structure of O&M team has been provided here in a hierarchy model to demonstratein a simpler way.
Plant manager
Maintenanceengineer(E&IE)
Technician1
skilled labour1
Technician2
skilled labour2
control roomtechnician
maintenanceEngineer(Mech)
Skilled labour1 skilled labour2
operationmanager
Supply chainexecutive
Accountsexecutive
Queries@ [email protected]
Detail Project Report1MWp SPV Power Plant
w w w . r e n e w p o w e r z o n e . i n Page 22
Financial Analysis & feasibility
Initial Investment in terms of components’ cost & service charges
Sl.No.
Components/services Total cost(in INR)
Remarks
1. Solar PV modules 45,100,000 41rs/Watt peak2. Solar inverters 11,660,000 11rs/Watt peak3. Transformer 2,940,000 From international vendor4. Protective devices 1,200,000 From international vendor5. Wires/Cables 1,000,000 Considering IEC codes & ISO
certified6. SCADA/RMS 1,000,0007. Project execution & commissioning 2,000,0008. Construction works 4,000,0009. Grid evacuation 1,000,000 (assumed) Assumed because of having
no sufficient data10. Other official works 1,000,000 Subject to change as per
rulesTotal Project investment 70,900,000 INR
Total expenses over the year for plant O&M and staffing = 2,000,000This expense is considered for regular maintenance cleaning of PV array, checking the status ofinverter, cable-fault checking, emergency maintenance & replacement of components andannual salaries of O&M team of the plant.
Loan Interest rate is @12% over 70% of total project cost which shall be completed within next7 years (the rest 30% as equity shares).
Estimated time period 7 years 10 yearsTotal Loan amount 49,630,000 49,630,000Interest rate 12% 12%EMI 876,110 712,050Monthly interest 285,270 298,460total Interest paid 23,962,830 35,815,600
*all the amounts are considered in INR currency.
Queries@ [email protected]
Detail Project Report1MWp SPV Power Plant
w w w . r e n e w p o w e r z o n e . i n Page 23
Detailed Analysis of Installment, EMI, Interest of the 70% projectfinance/fund
Sl.No.
Installments EMI Monthly principle Monthly Interest
1) 0 0 0 02) 1 876,105 379,805 496,3003) 2 876,105 383,603 492,5024) 3 876,105 387,439 488,6665) 4 876,105 391,314 484,7926) 5 876,105 395,227 480,8787) 6 876,105 399,179 476,9268) 7 876,105 403,171 472,9349) 8 876,105 407,203 468,90310) 9 876,105 411,275 464,83111) 10 876,105 415,387 460,71812) 11 876,105 419,541 456,56413) 12 876,105 423,737 452,36914) 13 876,105 427,974 448,13115) 14 876,105 432,254 443,85116) 15 876,105 436,576 439,52917) 16 876,105 440,942 435,16318) 17 876,105 445,351 430,75419) 18 876,105 449,805 426,30020) 19 876,105 454,303 421,80221) 20 876,105 458,846 417,25922) 21 876,105 463,434 412,67123) 22 876,105 468,069 408,03624) 23 876,105 472,749 403,35625) 24 876,105 477,477 398,62826) 25 876,105 482,252 393,85327) 26 876,105 487,074 389,03128) 27 876,105 491,945 384,16029) 28 876,105 496,864 379,24130) 29 876,105 501,833 374,27231) 30 876,105 506,851 369,25432) 31 876,105 511,920 364,18533) 32 876,105 517,039 359,06634) 33 876,105 522,210 353,89635) 34 876,105 527,432 348,67436) 35 876,105 532,706 343,39937) 36 876,105 538,033 338,07238) 37 876,105 543,413 332,69239) 38 876,105 548,847 327,25840) 39 876,105 554,336 321,769
Queries@ [email protected]
Detail Project Report1MWp SPV Power Plant
w w w . r e n e w p o w e r z o n e . i n Page 24
41) 40 876,105 559,879 316,22642) 41 876,105 565,478 310,62743) 42 876,105 571,133 304,97244) 43 876,105 576,844 299,26145) 44 876,105 582,613 293,49246) 45 876,105 588,439 287,66647) 46 876,105 594,323 281,78248) 47 876,105 600,266 275,83949) 48 876,105 606,269 269,83650) 49 876,105 612,332 263,77351) 50 876,105 618,455 257,65052) 51 876,105 624,640 251,46653) 52 876,105 630,886 245,21954) 53 876,105 637,195 238,91055) 54 876,105 643,567 232,53856) 55 876,105 650,002 226,10357) 56 876,105 656,502 219,60358) 57 876,105 663,068 213,03859) 58 876,105 669,698 206,40760) 59 876,105 676,395 199,71061) 60 876,105 683,159 192,94662) 61 876,105 689,991 186,11463) 62 876,105 696,891 179,21464) 63 876,105 703,860 172,24665) 64 876,105 710,898 165,20766) 65 876,105 718,007 158,09867) 66 876,105 725,187 150,91868) 67 876,105 732,439 143,66669) 68 876,105 739,763 136,34270) 69 876,105 747,161 128,94471) 70 876,105 754,633 121,47272) 71 876,105 762,179 113,92673) 72 876,105 769,801 106,30474) 73 876,105 777,499 98,60675) 74 876,105 785,274 90,83176) 75 876,105 793,127 82,97977) 76 876,105 801,058 75,04778) 77 876,105 809,068 67,03779) 78 876,105 817,159 58,94680) 79 876,105 825,331 50,77481) 80 876,105 833,584 42,52182) 81 876,105 841,920 34,18583) 82 876,105 850,339 25,76684) 83 876,105 858,842 17,26385) 84 876,105 867,431 8,674
Queries@ [email protected]
Detail Project Report1MWp SPV Power Plant
w w w . r e n e w p o w e r z o n e . i n Page 25
Net Cash Flow/year Estimation (all amounts are in INR)Initial Investment 70,900,00Expenses for O&M per year 2,000,000Total amount paid/year for loan(7 years termconsidered)
10,513,320
Tolerance factor 2%Total amount to be paid per year 12,763,600Energy generated per year 1,655MWhPPA rate for next 12 years 7.5rs/KWhREC floor price 12,000rs/MWh (approx.)Gross cash flow through PPA 12,412,500Gross cash flow through REC trading 19,860,000Net Cash Flow (NCF) per year 21,759,180
0
100000
200000
300000
400000
500000
600000
700000
800000
900000
1000000
1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52 55 58 61 64 67 70 73 76 79 82 85
Installment
EMI
Monthly Principle
Monthly Interest
Queries@ [email protected]
Detail Project Report1MWp SPV Power Plant
w w w . r e n e w p o w e r z o n e . i n Page 26
NET CASH FLOW & PAY BACK PERIOD
Now according to Discounted Cash Flow method (considering @10% DCF)
years Present value of rs.1 @10%1 0.909 19,779,094.622 0.826 17,973,082.683 0.751 16,341,144.184 0.683 14,861,519.945 0.621 13,512,450.786 0.564 12,272,177.527 0.513 11,162,459.348 0.467 92,145,357.809 0.424 83,660,898.56
10 0.386 76,162,987.84
So, Pay Back Period= 6 years 1 month (approx.)
Queries@ [email protected]
Detail Project Report1MWp SPV Power Plant
w w w . r e n e w p o w e r z o n e . i n Page 27
Most suitable vendors/suppliers of the project componentsSolar PV modules 1. Vikram Solar
2. Waaree Energies3. Sova Power4. Canadian Solar5. Trina Solar6. First Solar
Inverter 1. Power One2. SMA3. Smart Power4. REFusol5. Delta6. Schneider Electric
Transformer 1. ABB2. Schneider Electric3. Ascott transformer4. Voltech
Switch gear 1. Schneider Electric2. Megawin
DC Disconnect 1. Schneider ElectricCircuit breaker 1. Megawin
2. ABB
SCADA/RMS 1. DrakerCables 1. Havells
2. Finolex cables3. RR Kabels4. Anchors
Isolator 1. ABB2. Schneider Electric3. Megawin
Queries@ [email protected]
Detail Project Report1MWp SPV Power Plant
w w w . r e n e w p o w e r z o n e . i n Page 28
Conclusion
I’d like to thank you for reading the whole paper. Hope you have got clear view on design &estimation of 1MW utility scale Solar PV Power Plant. Though I have discussed about thetechnical part as well as the financial part in detail, I might have been forgot to add anythingmore important. So, you are most welcome to give your valuable feedback & suggestion on thisreport. At the end, I discussed about some companies for the components. I have chosen thesecompanies because their products are fulfilling my design criteria. It is not that I’m representingthese companies and their products.
About Myself: I’m a Solar PV professional currently working with a solar EPC company asProject Engineer. I’ve done B.Tech in Electrical Engineering & holding a PG certificate inAdvanced Solar Energy from delft Technical University, Netherlands.
Personally I provide technical consulting including site survey, technical design, CAD design,preparation of DPR, guide in procurement & Construction.
You can review my papers/reports at www.wbut.academia.edu/amritmandal
Connect to my professional profile in linkedIn at –http://www.linkedin.com/pub/amrit-mandal/55/667/a3
Read solar PV related articles & learn about new technologies at- www.renewpowerzone.in
Contact me or send your queries at- [email protected] , [email protected]
THANK YOU