Designer Liability - theconstructionreport.orgtheconstructionreport.org/Presentations/Designer...

45
Designer Liability Lorman Education Services June 25, 2003 1 Brian W. Erikson Quilling, Selander, Cummiskey & Lownds, P.C. 2001 Bryan Street, Suite 1800 Dallas, Texas 75214 214-880-1844

Transcript of Designer Liability - theconstructionreport.orgtheconstructionreport.org/Presentations/Designer...

  • Designer LiabilityLorman Education Services

    June 25, 2003

    1

    Brian W. EriksonQuilling, Selander, Cummiskey & Lownds, P.C.

    2001 Bryan Street, Suite 1800

    Dallas, Texas 75214

    214-880-1844

  • Traditional Organizational Chart

    Owner Designer

    General Contractor

    2

    General Contractor

    Trade Contractor

    Trade Contractor

    TradeContractor

    Etc.

  • Construction Manager Chart

    Owner Designer

    General Contractor

    ConstructionManager

    3

    General Contractor

    Trade Contractor

    Trade Contractor

    TradeContractor

    Etc.

  • Designer Liability

    • Contract

    • Tort– Negligence

    – Professional

    4

    – Professional negligence

    • Vicarious

  • Designer Liability

    • Architect/Engineer Liability– Liability to Owner

    – Liability to Contractor

    5

    – Liability to Contractor• Contractor not third

    party beneficiary

    • Professional negligence

    • Texas law in flux

  • Designer Liability

    • Architect/Engineer Liability– Owner or contractor

    must show causal

    6

    must show causal connection between A/E negligence and specific damages

  • Contract Liability

    • Economic Loss Rule– Liability for breach of

    contract damages

    – No negligence claims

    7

    – No negligence claims by party with privity

  • Economic Loss Rule

    • Does not apply to physical property damage or personal injury

    8

    injury

  • Contract Issues

    • Contract Formation– Capacity &

    consideration

    – Validity of contract

    9

    – Validity of contract

  • Contract Issues

    • Intent of the Parties– Determined from

    agreement as a whole

    – Contemporaneous

    10

    – Contemporaneous construction by the parties

  • Contract Issues

    • Rules of Construction– Ambiguity

    • Construing against drafting party

    – Boiler plate provisions

    11

    – Boiler plate provisions• Lose out to negotiated

    provisions

    – All provisions to have some meaning

    – Avoidance of illusory promises

  • Contract Issues

    • Parol Evidence Rule– Excludes prior

    inconsistent communications or agreements

    12

    agreements

    – Does not bar consistent communications or agreements

  • Contract Issues

    • Parol Evidence Rule– Does not bar evidence

    of fraudulent statements or writings

    13

    – Does not bar subsequent modifications to contract

  • Contract Issues

    • Contract Forms– Oral contract not

    worth the paper its not printed on

    14

    – AIA B141

    – EJCDC

    – AGC Design Build

  • Contract Issues

    • Key Provisions– Scope of work

    • Inclusions

    • Exclusions

    15

  • Contract Issues

    • Key Provisions– Schedule for

    performing design services

    16

    • Delays

  • Contract Issues

    • Pay When Paid vs. Pay If Paid

    17

  • Contract Issues

    • Notice Requirements– AIA B141

    • “Prompt notice”

    – A 201

    18

    – A 201• “21 days”

    – Cf. Texas Civil Practice & Remedies Code §16.071

    • Notice requirement less than 90 days is void

  • Contract Issues

    • Attorney’s Fees– Provision for recovery

    by prevailing party

    – Texas Civil Practice &

    19

    – Texas Civil Practice & Remedies Code §38.001

  • Contract Issues

    • Alternative Dispute Resolution– Mediation

    – Arbitration

    20

    – Arbitration

    – Standing arbitration panel

    – Summary jury trial

  • Contract Issues

    • Mediation– Confidential

    – Inexpensive

    – Effective

    21

    – Effective

    – Virtually mandatory

  • Contract Issues

    • Arbitration– Private

    – Knowledgeable fact finders

    22

    finders

    – Limited appeal rights

    – Faster

  • Contract Issues

    • Standing Arbitration Panel

    23

  • Contract Issues

    • Summary Jury Trial

    24

  • Contract Clauses

    • Implied Contract Obligations– Owner not to delay or

    obstruct designer or

    25

    obstruct designer or contractor

    – Contractor to perform in good and workmanlike manner

  • Contract Clauses

    • Implied Contract Obligations– Owner’s failure to

    provide adequate plans

    26

    provide adequate plans and specifications

    • The Longeran case vs. the Shintech case

  • Contract Clauses

    • Implied Contract Obligations– No implied duty of

    good faith

    27

    good faith

    – Disclaimers

  • Contract Clauses

    • Differing Site Conditions– Equitable allocation of

    unknown risk

    28

    unknown risk

    – Pros and cons of inclusion

  • Contract Clauses

    • Differing Site Conditions– Type I

    • Conditions materially

    29

    • Conditions materially different from contract indications

    – Type II• Unusual conditions not

    ordinarily encountered

  • Contract Clauses

    • Differing Site Conditions– Site inspection

    obligations

    30

    obligations

    – Disclaimers

  • Contract Clauses

    • Exculpatory Clauses– Indemnity

    – No Damages for Delay

    31

    Delay

    – Disclaimers of Liability

    – Limitations of Liability

  • Contract Clauses

    • Exculpatory Clauses– Indemnity

    • Express negligence doctrine

    • Fair notice

    32

    • Fair notice– Conspicuousness

    • Texas Civil Practice & Remedies Code §130.002

  • Contract Clauses

    • Exculpatory Clauses– No Damages for

    Delay• General rule

    33

    • No damages for delay clause at work

  • Contract Clauses

    • Exculpatory Clauses– No Damages for

    Delay• Exceptions

    34

    – Delays not contemplated

    – Owner’s active interference

    – Bad faith

    – Intentional misconduct

  • Contract Clauses

    • Exculpatory Clauses– Disclaimers of

    Liability• No damages for delay

    35

    • Defects in plans and specifications

    • Extra costs

    • Soil conditions

    • Regulatory changes

    • Shifting of risk

  • Contract Clauses

    • Exculpatory Clauses– Limitations of

    Liability• Liability limited to fee

    36

    • Liability limited to insurance proceeds

    • Liability limited to set amount

    • Liability on comparative negligence basis

  • Extras and Changes

    • Scope of Work– The Devil is in the

    Details

    37

  • Extras and Changes

    • Constructive Changes– Change that only one

    side recognizes

    38

  • Extras and Changes

    • Pricing– Examine Contract

    Terms

    – Unit Prices from Bid

    39

    – Unit Prices from Bid

    – Negotiated Amount

    – Time and Materials

  • Extras and Changes

    • Change Orders, Exceptions and Reservations– Exceptions

    40

    – Exceptions• Quantum meruit

    • Waiver

    • Breach of contract

    • Oral Contract

    • Promissory Estoppel

  • Project Delivery Methods

    • Design / Build– Design / Build Team

    – Sole Design Builder

    – Design Build

    41

    – Design Build Developer

  • Project Delivery Methods

    • Design / Build– Advantages

    • Accountability

    • Lower costs

    42

    • Faster completion

  • Project Delivery Methods

    • Design / Build– Pitfalls

    • Design / Builder’s mind reading ability

    • Design / Builder’s

    43

    • Design / Builder’s conflict of interest

    • Fewer checks and balances

    • Fewer deep pockets

  • Project Delivery Methods

    • Design / Build– Pricing

    • Guaranteed max

    44

  • Designer Liability

    45

    Brian W. EriksonQuilling, Selander, Cummiskey & Lownds, P.C.

    2001 Bryan Street, Suite 1800

    Dallas, Texas 75214

    214-880-1844