Design Report Housing and Facilities 2011

177
Housing Development in Westonaria A Design Report submitted to the Faculty of Engineering and the Built Environment as partial fulfilment of the requirements of the degree  by Housing and Facilities Group C BACCALAUREUS INGENERIAE In CIVIL ENGINEERING SCIENCE At UNIVERSITY OF JOHANNESBURG STUDY LEADER: Dr Dundu 20 October 2011 

description

Feasablity Study for a self sufficient city in SA

Transcript of Design Report Housing and Facilities 2011

  • 5/28/2018 Design Report Housing and Facilities 2011

    1/177

    Housing Development in Westonaria

    A Design Report submitted to the Faculty of Engineering and the

    Built Environment as partial fulfilment of the requirements of the degree

    by

    Housing and Facilities Group C

    BACCALAUREUS INGENERIAE

    In

    CIVIL ENGINEERING SCIENCE

    At

    UNIVERSITY OF JOHANNESBURG

    STUDY LEADER: Dr Dundu

    20 October 2011

  • 5/28/2018 Design Report Housing and Facilities 2011

    2/177

    OWS 4B

    Housing Development in

    WestonariaDesign Report for Housing and Facilities

    10/20/2011

    Brenden Jordaan 200612481

    Edrie Du Toit 200602828

    Kelly Hall 200723064

    Larushkan Soobiah 200833658

    Mikhail Bramdaw 200823954

    Neil Pienar 200709097

    Sunette Verster 200602699

  • 5/28/2018 Design Report Housing and Facilities 2011

    3/177

    i

    ANTI-PLAGIARISM DECLARATION

    Title: Scoping Report for Housing and Facilities Development

    Full name: Edrie Du Toit

    Student number: 200602828

    Course: Civil Design 4B (OWS 4B)

    Lecturer: Prof. Legge

    Due date: 20 October 2011

    Plagiarism is to present someone elses ideas as my own. Where material written by other

    people has been used (either from a printed source or from the internet), this has been

    carefully acknowledged and referenced. I have used the Harvard Convention for citation and

    referencing. Every contribution to and quotation from the work of other people in this essay

    has been acknowledged through citation and reference. I know that plagiarism is wrong.

    I understand what plagiarism is and am aware of the Universitys policy in this regard. I know that I would plagiarise if I do not give credit to my sources, or if I copy sentences

    or paragraphs from a book, article or Internet source without proper citation.

    I know that even if I only change the wording slightly, I still plagiarise when usingsomeone elses words without proper citation.

    I declare that I have written my own sentences and paragraphs throughout my essay and Ihave credited all ideas I have gained from other peoples work.

    I declare that this assignment is my own original work. I have not allowed, and will not allow, anyone to copy my work with the intention of

    passing it off as his or her own work.

    SIGNATURE .DATE...

  • 5/28/2018 Design Report Housing and Facilities 2011

    4/177

    ii

    Abstract

    The Housing and Facilities Design Group are responsible for decisions regarding the sizing

    and basic layout of each housing and facility structure on the Syferfontein Farm, as well as

    the materials to be used with structural analysis, logic and innovative thinking as a guiding

    tool. These structures are designed with population growth as well as possible future

    development in mind.

    Green technology has been incorporated into the design where applicable to aid in lower

    carbon emissions and a more environmentally friendly construction practice. Keeping in

    mind that it is not always economically possible to use entirely green practise, a balanced

    approach is needed.

    Given the geological surroundings of the Syferfontein Farm, good foundation design is

    imperative to keep the housing and facilities structurally sound for short and long term.

    The completed project would accommodate a population of 257 500 on a 2000 ha site, whilst

    accounting for a population growth rate of 0.25% per annum. It was found that the total cost

    for the project would be approximately R 63.8 bn. and would require a construction time of

    approximately 15 years.

  • 5/28/2018 Design Report Housing and Facilities 2011

    5/177

    iii

    Acknowledgements

    The Group of Housing and Facilities would like to thank the following people for their help

    and guidance which aided in the completion of this report:

    Dr M Dundu (University of Johannesburg, Civil Engineering)

    Dr F Okonta (University of Johannesburg, Civil Engineering)

    Mr P van Tonder (University of Johannesburg, Civil Engineering)

    Ms S Potgieter (University of Johannesburg, Librarian)

    Martha de Jager (CNCI, Librarian)

    Susan Battison (CNCI, Librarian)

  • 5/28/2018 Design Report Housing and Facilities 2011

    6/177

    iv

    Table of Contents

    ANTI-PLAGIARISM DECLARATION .................................................................................... i

    Abstract ......................................................................................................................................ii

    Acknowledgements .................................................................................................................. iii

    Table of Contents ...................................................................................................................... iv

    List of Figures ............................................................................................................................ x

    List of Tables .......................................................................................................................... xiv

    1. Introduction ............................................................................................................................ 1

    2. Project Scope ......................................................................................................................... 2

    3. Site Description ...................................................................................................................... 6

    3.1 Climate ............................................................................................................................. 6

    3.2 Geological Setting ............................................................................................................ 7

    3.3 Topography ...................................................................................................................... 7

    3.4 Vegetation and Fauna ...................................................................................................... 8

    3.5 Water Resources .............................................................................................................. 8

    3.6 Archaeological, cultural and heritage interest. .............................................................. 10

    4. GREEN ALTERNATIVES ................................................................................................. 11

    4.1. Passive Heating and Cooling ........................................................................................ 11

    4.1.1 Passive Solar Heating ............................................................................................. 11

    4.1.2 Passive cooling........................................................................................................ 13

    4.2 Solar Geysers ................................................................................................................. 13

    4.2.1 Introduction ............................................................................................................. 13

    4.2.2 Benefits ................................................................................................................... 14

    4.2.3 Types of Solar Water Heating Systems .................................................................. 15

    4.2.4 Types of Collector Plates ........................................................................................ 16

    4.2.5 Eskom Rebate ......................................................................................................... 17

  • 5/28/2018 Design Report Housing and Facilities 2011

    7/177

    v

    4.3 Lighting .......................................................................................................................... 17

    4.3.1 LED globes ............................................................................................................. 17

    4.3.2 Sunlighting .............................................................................................................. 18

    4.3.3 Solar LED Garden and Landscaping Lights ........................................................... 18

    4.3.4 Day/Night Sensor .................................................................................................... 19

    4.3.5 Motion Sensors ....................................................................................................... 19

    4.4 Insulation........................................................................................................................ 19

    4.4.1 Roofs ....................................................................................................................... 19

    4.4.2 Walls ....................................................................................................................... 20

    4.4.3 Floors ...................................................................................................................... 20

    4.4.4 Windows and sliding doors ..................................................................................... 21

    4.5 Green Building Materials ............................................................................................... 21

    4.6 Green roofs..................................................................................................................... 26

    4.7 Rain water harvesting .................................................................................................... 28

    4.7.1. Introduction ............................................................................................................ 28

    4.7.2 Uses of harvested rain water ................................................................................... 29

    4.7.2 Proposed water harvesting systems ........................................................................ 30

    4.7.3 Advantages and Disadvantages............................................................................... 32

    4.8 Heat Pumps .................................................................................................................... 33

    5. Design Results ..................................................................................................................... 35

    5.1. Spatial Design ............................................................................................................... 35

    5.1.1. Housing .................................................................................................................. 35

    5.1.2. Facilities ................................................................................................................. 37

    5.1.3. Summary of Facilities ............................................................................................ 38

    5.2. Structural Design .......................................................................................................... 71

    5.2.1. Steel Truss .............................................................................................................. 71

    5.2.1.a. Specifications ...................................................................................................... 71

  • 5/28/2018 Design Report Housing and Facilities 2011

    8/177

    vi

    5.2.1.a.i. Overall Dimensions........................................................................................... 71

    5.2.1.a.ii. Loading Conditions .......................................................................................... 71

    5.2.1.a.iii. Bending Moment and Axial Force .................................................................. 72

    5.2.1.b. Sections ............................................................................................................... 73

    5.2.1.c. Connections ......................................................................................................... 74

    5.2.1.d. Base Plate ............................................................................................................ 76

    5.2.2. Masonry Structure .................................................................................................. 77

    5.2.2.a. Layout ................................................................................................................. 77

    5.2.2.b. Analysis and Design Methodology ..................................................................... 78

    5.2.2.c Design .................................................................................................................. 78

    5.2.2.c.i. Roof ................................................................................................................... 78

    5.2.2.c.ii. Slabs ................................................................................................................. 79

    5.2.2.d. Masonry Design .................................................................................................. 82

    5.2.2.e. Stairs .................................................................................................................... 84

    5.2.2.f. Foundation ........................................................................................................... 85

    5.2.3. Concrete Multi-Storey Structure ............................................................................ 86

    5.2.3.a. Specifications ...................................................................................................... 86

    5.2.3.a.i. Overall Dimensions........................................................................................... 86

    5.2.3.a.ii. Roof and Floors................................................................................................ 86

    5.2.3.a.iii. Stability ........................................................................................................... 86

    5.2.3.a.iv. Fire Resistance ................................................................................................ 88

    5.2.3.a.v. Loading Conditions .......................................................................................... 88

    5.2.3.a.vi. Exposure Conditions ....................................................................................... 89

    5.2.3.a.vii. Materials ........................................................................................................ 89

    5.2.3.a.viii. Foundations ................................................................................................... 89

    5.2.3.a.ix. Scope of design ............................................................................................... 89

    5.2.3.a.x. Design Process Followed ................................................................................. 90

  • 5/28/2018 Design Report Housing and Facilities 2011

    9/177

    vii

    5.2.3.b. Sizes of Members ................................................................................................ 91

    5.2.3.b.i. Slab ................................................................................................................... 91

    5.2.3.b.ii. Beam ................................................................................................................ 91

    5.2.3.b.iii. Column (EDGE & INTERNAL) .................................................................... 91

    5.2.3.c. Vertical Design Loads ......................................................................................... 92

    5.2.3.d. Design Moments ................................................................................................. 95

    5.2.3.d.i. Beam Moments ................................................................................................. 95

    5.2.3.d.ii. Column Moments .......................................................................................... 100

    5.2.3.e Lateral Loading .................................................................................................. 104

    5.2.3.f. Reinforcement ................................................................................................... 105

    5.2.3.f.i. Slab .................................................................................................................. 105

    5.2.3.f.ii. Beam ............................................................................................................... 106

    5.2.3.f.iii. Column (EDGE & INTERNAL)................................................................... 107

    5.2.3.g. Foundation Design ............................................................................................ 108

    5.2.3.g.i. Multi Story Basement ..................................................................................... 108

    5.2.3.g.ii. Methodology .................................................................................................. 109

    5.2.3.g.iii. Raft foundation ............................................................................................. 109

    5.2.3.g.iv. Reinforcement for Raft foundation ............................................................... 110

    5.2.3.g.v. Cantilever retaining wall ................................................................................ 111

    5.2.3.g.vi. Reinforcement for Cantilever wall ............................................................... 112

    5.2.3.g.vii Piles (Option) ................................................................................................ 112

    5.2.3.h. Isolation Joint Sizing......................................................................................... 112

    5.2.3.i. Green Design Considerations ............................................................................ 112

    5.2.3.j Roof Drainage ............................................................................................................. 114

    6. Costing ............................................................................................................................... 115

    7. Environmental Impact Assessment .................................................................................... 117

    7.1. Legal Framework ........................................................................................................ 117

  • 5/28/2018 Design Report Housing and Facilities 2011

    10/177

    viii

    7.1.1. The constitution of South Africa.......................................................................... 118

    7.1.2. The National Environmental Management Act ................................................... 118

    7.1.3. Legal Requirements in terms of Other Acts ........................................................ 119

    7.1.3.a. National Water Act (Act No. 36 of 1998) ......................................................... 119

    7.1.3.b. Conservation of Agriculture Resources Act (Act No. 57of 1983).................... 119

    7.1.3.c. White Paper on Integrated Pollution and Waste Management for South Africa

    ........................................................................................................................................ 120

    7.1.3.d. National Environmental Biodiversity Act (Act No. 10 of 2004) ...................... 120

    7.1.4. National Environmental Management Biodiversity Act (Act No.10 of 2004) .... 121

    7.1.5. National Environmental Management: Protected Areas Act (Act No.57 of 2003)

    ........................................................................................................................................ 121

    7.1.6. National Veld and Forest Fire Act (Act No.101 of 1998) ................................... 121

    7.1.7. National Heritages Resources Act (Act No.25 of 1999)...................................... 122

    7.1.8. National Environmental Management: Air Quality Act (Act No.39 0f 2003) .... 122

    7.1.9. Sustainable Development..................................................................................... 122

    7.1.10. National Building Regulations and Buildings Standards Act (Act No.103 of

    1997) .............................................................................................................................. 123

    7.2 Impact Assessment Methodology ................................................................................ 123

    7.3. Impacts and Mitigation ............................................................................................... 125

    7.3.1. Impacts during Construction Phase ..................................................................... 125

    7.3.2. Impacts during Operational Phase ....................................................................... 135

    7.4. Conclusion .................................................................................................................. 143

    8. Green Alternative Recommendations ................................................................................ 144

    8.1. Housing ....................................................................................................................... 144

    8.2. Community Related Facilities..................................................................................... 146

    8.3. Educational Facilities .................................................................................................. 148

    8.4. Public Service Facilities .............................................................................................. 150

    9. Conclusion ......................................................................................................................... 152

  • 5/28/2018 Design Report Housing and Facilities 2011

    11/177

    ix

    References .............................................................................................................................. 153

  • 5/28/2018 Design Report Housing and Facilities 2011

    12/177

    x

    List of Figures

    Figure 2.1: Steel Frame....................................................................................................... 3

    Figure 3.1: Map of Site Area ............................................................................................. 6

    Figure 3.2: Contour Map of the Site ................................................................................. 7

    Figure 3.3: South facing view of the property .................................................................. 8

    Figure 3.4: Quarry ............................................................................................................ 9

    Figure 3.5: Marsh just east of the dirt road on the property ............................................. 9

    Figure 4.1: Evacuated tube collectors on a roof ............................................................. 14

    Figure 4.2: Passive solar water heating system .............................................................. 15

    Figure 4.3: Illustration of how Sunlighting works .......................................................... 18

    Figure 4.4: Solar LED Garden and Landscaping Lights .................................................. 19

    Figure 4.5: Thermguard sprayed on the ceiling ............................................................... 20

    Figure 4.6: Cellulose fibre used for floor insulation ........................................................ 20

    Figure 4.7: Sublayers for a green roof ............................................................................ 27

    Figure 4.8: Rain water harvesting alternatives ................................................................ 30

    Figure 4.9: Rainwater Harvest system ............................................................................ 31

    Figure 4.10: Watree design............................................................................................. 32

    Figure 4.11: Heat pump outside a house ....................................................................... 34

    Figure 5.1.1: Market share of fresh produce markets in South Africa ........................... 39

    Figure 5.1.2: Roof Top farming ..................................................................................... 39

    Figure 5.1.3: Top view of market ................................................................................... 40

    Figure 5.1.4: Newtown Precinct Public Toilets ............................................................. 40

    Figure 5.1.5: Example of efficient layout for fire station ................................................ 61

  • 5/28/2018 Design Report Housing and Facilities 2011

    13/177

    xi

    Figure 5.1.6: 1st Floor ...................................................................................................... 64

    Figure 5.1.7: 2nd Floor ..................................................................................................... 64

    Figure 5.1.8: 3rd Floor ...................................................................................................... 65

    Figure 5.1.9: 4th Floor ..................................................................................................... 65

    Figure 5.1.10: Fifth Floor ................................................................................................. 66

    Figure 5.1.11: Roof .......................................................................................................... 66

    Figure 5.1.12: Green roof ................................................................................................. 67

    Figure 5.1.13: One double lane separated by foot paths ................................................. 70

    Figure 5.2.1: Steel truss ................................................................................................... 71

    Figure 5.2.2: Loading on the truss .................................................................................... 72

    Figure 5.2.3: The axial force diagram............................................................................... 72

    Figure 5.2.4: The bending moment diagram .................................................................... 73

    Figure 5.2.5: Front view of the eaves connection ........................................................... 74

    Figure 5.2.6: Angled view of the eaves connection ........................................................ 74

    Figure 5.2.7: Front view of apex connection ................................................................... 75

    Figure 5.2.8: Angled view of apex connection ................................................................ 75

    Figure 5.2.9: Dimensions of base plate ............................................................................. 76

    Figure 5.2.10: Illustration of RDP conceptual design ...................................................... 77

    Figure 5.2.11 : Layout of RDP Units ................................................................................ 77

    Figure 5.2.12: Roof truss dimensions ............................................................................... 79

    Figure 5.2.13: Imposed axial loads from roof truss .......................................................... 79

    Figure 5.2.14: 120 mm prestressed 1st floor slab ............................................................ 80

    Figure 5.2.15: Tendon Profile ......................................................................................... 80

  • 5/28/2018 Design Report Housing and Facilities 2011

    14/177

    xii

    Figure 5.2.16: Floor Slab Profile ................................................................................... 81

    Figure 5.2.17: 200 mm pre-stressed ground floor slab ................................................... 81

    Figure 5.2.18: Typical Masonry block to be used ........................................................... 82

    Figure 5.2.19: Outer block wall ........................................................................................ 82

    Figure 5.2.20: Centre wall block and grouting pattern ................................................... 83

    Figure 5.2.21: First floor slab minimum width ............................................................... 83

    Figure 5.2.22: Stair slabs ................................................................................................. 84

    Figure 5.2.23: Ground Floor Slab ................................................................................... 85

    Figure 5.2.24: Two-way spanning slab and monolithically cast T beam ..................... 86

    Figure 5.2.25: (a) Overall plan dimensions; (b) Half building design plan;

    (c) End elevation ............................................................................................................. 87

    Figure 5.2.26: Design algorithm ..................................................................................... 90

    Figure 5.2.27: Cross-section of beams ............................................................................ 91

    Figure 5.2.28: Load cases - critical columns for axial loading ....................................... 92

    Figure 5.2.29: Axial loading for internal columns .......................................................... 92

    Figure 5.2.30: Axial loading for edge columns ............................................................... 93

    Figure 5.2.31: Floor loading and critical frames for bending .......................................... 93

    Figure 5.2.32: Point load simplification for slab to beam load distribution .................... 94

    Figure 5.2.33: Load case factors for moment determination .......................................... 94

    Figure 5.2.34: Load Case 1 Bending Moment Diagram (Y-direction) .......................... 96

    Figure 5.2.35: Load case 2 Bending Moment Diagram (Y-direction) ............................. 96

    Figure 5.2.36: Load case 3 Bending Moment Diagram (Y-direction) ............................ 97

    Figure 5.2.37: Load Case 1 Bending Moment Diagram ........ ..........................................98

  • 5/28/2018 Design Report Housing and Facilities 2011

    15/177

    xiii

    Figure 5.2.38: Load Case 2 Bending Moment Diagram ................................................ 98

    Figure 5.2.39: Load Case 3 Bending Moment Diagram ................................................. 99

    Figure 5.2.40: Wind load and induced lateral floor loads .............................................. 104

    Figure 5.2.41: Slab reinforcement ................................................................................. 105

    Figure 5.2.42: Bending reinforcement in Y-Direction ................................................. 106

    Figure 5.2.43: Bending reinforcement in X-Direction ................................................ 106

    Figure 5.2.44: Internal column reinforcement ............................................................ 107

    Figure 5.2.45: Edge column reinforcement ................................................................. 108

    Figure 5.2.46: Basement Raft ..................................................................................... 110

    Figure 5.2.47: 8m span middle strip ........................................................................... 110

    Figure 5.2.48: 8m span column strip .......................................................................... 110

    Figure 5.2.49: 5m span middle strip ............................................................................. 111

    Figure 5.2.50: 5m span column strip ............................................................................. 111

    Figure 5.2.51: Retaining wall ......................................................................................... 111

    Figure 5.2.52: Sun-lighting system for building assuming maximum channelling

    distance of 20m ............................................................................................................. 113

    Figure 5.2.53: Low income High-rise 2ha plot ............................................................. 113

    Figure 5.2.54: Water Volumes prediction for green roof sections................................ 114

  • 5/28/2018 Design Report Housing and Facilities 2011

    16/177

    xiv

    List of Tables

    Table 2.1: Proposed Housing............................................................................................ 2

    Table 4.2: Green roof characteristics............................................................................ 28

    Table 4.3: Advantages and disadvantages of rainwater harvesting.............................. 32

    Table 5.1.1: Summary of Housing................................................................................... 35

    Table 5.1.2: Summary of Facilities................................................................................... 37

    Table 5.1.3: Religion in SA............................................................................................. 44

    Table 5.1.4 : Religious institution distribution.................................................................. 44

    Table 5.1.5: Summary of values..................................................................................... 45

    Table 5.1.6: Number of users........................................................................................... 46

    Table 5.1.7: Cars per income bracket and number of petrol stations required.................. 47

    Table 5.1.8: Division of pupils within economic groups................................................. 50

    Table 5.1.9: Division of areas for high income schools................................................. 51

    Table 5.1.10: Division of areas for medium income schools.............................................52

    Table 5.1.11: Division of areas for low income schools....................................................54

    Table 5.1.12: Division of areas for RDP schools.............................................................. 56

    Table 5.1.13: Number of disabled children by gender...................................................... 57

    Table 5.1.14: Hospital Beds ............................................................................................ 59

    Table 5.1.15: Number of floors for each clinic.............................................................. 59

    Table 5.1.16: Officer to citizen ratio................................................................................. 63

    Table 5.2.1: Truss sections............................................................................................... 73

    Table 5.2.2: Shear and Moment capacity checks............................................................ 84

  • 5/28/2018 Design Report Housing and Facilities 2011

    17/177

    xv

    Table 5.2.3: Imposed Loads............................................................................................ 88

    Table 5.2.4: Dead Loads.................................................................................................. 88

    Table 5.2.5: Beam Moments for Y-direction; bending about X-axis.............................. 95

    Table 5.2.6: Beam Moments for X-direction; bending about Y-axis.............................. 97

    Table 5.2.7: Cantilever Reinforcement........................................................................... 112

    Table 6.1: Costing for Complete Town.......................................................................... 115

    Table 7.1: Impact assessment ....................................................................................... 123

    Table 7.2: SP Value Definitions.................................................................................... 124

    Table 7.3: Anticipated Biophysical Impacts during Construction Phase...................... 125

    Table 7.4: Anticipated Socio-Economic Impacts during Construction Phase.............. 132

    Table 7.5: Anticipated Biophysical Impacts during Operational Phase....................... 135

    Table 7.6: Anticipated Socio-Economic Impacts during Operational Phase............... 135

  • 5/28/2018 Design Report Housing and Facilities 2011

    18/177

    1

    1. Introduction

    The demand for land is a growing problem around the world. Most of the land that is best

    suited for construction has already been used. This leaves engineers with the issue of finding

    new innovative ways of making use of lesser suited pieces of land. Areas which were

    previously avoided for terms of major construction will now have to be used to accommodate

    the population growth. Therefore these pieces of land will have to now be used for the

    development of new housing projects and towns.

    This responsibility lies predominantly on the shoulders of civil engineers. Areas such as

    Syferfontein with large amounts of dolomitic soil, as well as other problem soils will be

    increasingly dealt with in the future. Not only does this space need to be used as effectively

    and efficiently as possible, but new technologies and innovative approaches are a necessity

    for sustainability and lasting infrastructure that can benefit the community and society as a

    whole.

    One of the most crucial challenges relevant to current Engineers, is the growing amount of

    greenhouse gases. Incorporating solar heating, green roofing and recyclable materials in

    construction are some of the newer approaches that can vastly reduce carbon footprint, as

    well as ensure sustainability of precious resources.

    The Housing and Facilities Design group of 2011, have taken on various classical as well as

    innovative approaches to produce designs that are balanced between being green and

    economically viable, while adhering to a high standard of quality.

  • 5/28/2018 Design Report Housing and Facilities 2011

    19/177

    2

    2. Project Scope

    There is a need to promote growth and development of the area west of Johannesburg as well

    as address the current housing shortage in the country. The University of Johannesburg

    Group C, of the 4th

    year Civil Design class, was requested by LTE consulting to assist them

    with the feasibility study of a proposed high density development with regard to housing and

    facilities. The proposed 2000 hectare site was inspected and a desktop feasibility study was

    carried out in accordance with the general specifications and information gathered from the

    visit. The site is to house approximately 257 500 people, as well be self sustaining with

    regard to services such as water supply and power generation. The proposed development

    will comprise of:

    Table 2.2: Proposed Housing

    Income Group Number of Units People per Unit

    Total Population

    at Completion

    Date

    Population

    Increase 30

    years after

    completion

    RDP 22 500 6 135 000 10 501

    Low Income 12 500 5 62 500 4 862Medium Income 10 000 4 40 000 3 112

    High Income 5 000 4 20 000 1 556

    The study was done assuming that the project will be completed within a period of 15 years

    with a design life of 30 years thereafter. The growth of the population from the time of the

    projects completion to the end of the design life was accounted for in the design and

    therefore all buildings were designed with the capacity for upgrades. The population is

    estimated to grow at a rate of 0.25% per annum, therefore the design of housing and facilities

    need to accommodate for the impact of this growth. The residential buildings are therefore

    designed to allow for another floor at the top of the structure. At the end of the design life the

    population will have increased by approximately 20 031 people taking the total population

    that will require housing and facilities to 277 531.

    The project required a spatial design to be done for all facilities and residential buildings.

    This information was relayed to the Town Planning group so that a map of the town layout

  • 5/28/2018 Design Report Housing and Facilities 2011

    20/177

    3

    could be produced. The spatial design was done by using the guidelines set out by the CSIR

    Red Book, however due to the large population that will be designed for on a relatively small

    area of land; engineering judgements had to be made by the group to facilitate this demand.

    The structural design was done by analysing three different types of buildings, a steel truss

    structure, a masonry structure and a multi-storey concrete structure. The results from the

    structural analysis from these structures were then used in order to make a judgement on the

    feasibility of all the buildings in the town.

    Steel Truss

    The truss dimensions and general layout and purlin placement were initially determined.

    These dimensions were used to calculate the wind loading on the structure. The wind load

    that was used for further analysis was the worst case scenario.

    The worst case general load was calculated by calculating all 6load cases and selecting the

    worst loading case. The loading case that was used was 1.2DL + 1.6LL.

    The truss was analysed in Prokon to select initial sections and obtain the member forces and

    moments. These member forces and moments were used to check whether the selected

    sections were adequate. Once the final sections were selected the baseplate, connections andfoundations were calculated.

    Figure 2.1: Steel Frame

  • 5/28/2018 Design Report Housing and Facilities 2011

    21/177

    4

    Masonry Structure

    The RDP units were designed with maximum space, minimum materials and cost in mind,

    while incorporating environmentally friendly materials and practice as far as economically

    viable. For example making use of compressed earth blocks is considered to be

    environmentally friendly.

    Traditional structural analysis methods such as moment distribution method and other

    fundamental structural analysis methods were adopted. Software such as Microsoft Excel and

    Prokon were then used as checking tools.

    Basic research into masonry and timber design had to be undertaken, while making use of the

    SABS 0164 code for masonry design. Various design books were followed as are listed in the

    reference list. Concrete Manufacturer Association manuals were consulted for prestressed

    hollow core slab use.

    Multi-storey Concrete Structure

    The multi-storey concrete structure was analysed by considering a low income multi-storey

    building and analysing the structural requirements needed for that building. The analysis

    included determining the loads acting on the building, the sizing and reinforcement design ofcritical columns, beams and slabs, as well as the design of the foundation for the building.

    The analysis of the building was done by doing first principle hand calculations. These

    calculations were then checked using Prokon software.

    Once all the calculations were completed the feasibility study could be done. The preliminary

    sizes of all members in the building, obtained from the hand calculations, were then evaluated

    according to cost. The feasibility study also contained information of the time it would take to

    construct a project of this nature as well as the practicality of the project.

  • 5/28/2018 Design Report Housing and Facilities 2011

    22/177

    5

    Deliverables and Persons Responsible

    Scoping

    Site description [K]

    Project description and possible alternatives [L ,M]

    Legal framework [E , B]

    Overview of possible green building alternatives [ K, E, N ,S]

    Anticipated environmental impacts [S]

    QuantitativeAnalysis

    Estimation of housing types and facilities required [L,M,K,S,E,N]

    Estimation of erf area per building [L,M]

    Estimation of building dimensions [ALL]

    CAD drawings of buildings and/or [B,L ,M]

    floor layout s [ALL]

    This forms the basis of entire design project as all groups are dependant

    EstimationsBased on CSIR guidlines, population statistics and logistics

    Design

    Detailed structural design of a multistorey concrete building[L,B,M]

    Detailed Masonary Design of an RDP block [N,K] Detailed Structural design of a steel structure [E,S,N]

    Foundation designs and recommendations [K.N]

    All designs were done according to the relevant SANS codes and based

    on fundemantal structural design and analysis methods covered in thedegree (i.e from first principles)

    All designs have bene checked

    Feasability

    Overview of green aspects (materials, technology etc.) [ALL]

    Cost estimates [E,N,L,M]

    EIA (possible mitigation of impacts) [N,S,B]

    L Larushkan, N Neil, M Mikhail, E Edrie, K Kelly, B Brenden, S - Sunette

    COMPLETE

    COMPLETE

    COMPLETE

    COMPLETE

  • 5/28/2018 Design Report Housing and Facilities 2011

    23/177

    6

    3. Site Description

    The site that the proposed housing development will take place on is located south west of the

    Lenasia area at the co-ordinates of 262048S 274725E. It is located on the Syferfontein

    Farm in Westonaria and the farm can be accessed via dirt roads just off the N12 highway.

    The site is just under 2000ha in area and there is currently an airfield located on it as well as

    an old mine dump.

    Figure 3.1: Map of Site Area.

    The Syferfontein Farm lies just east of the South Deep Gold mine one of the deepest mines

    in the world, and south west of Lenasia. . The Baragwaneth Airport, which is still in

    operation, lies within the boundaries of the farm and is of heritage importance. African Bricks

    has used the property to mine clay for brick manufacturing.

    3.1 Climate

    Warm summers and mild winters characterise this region with a subtropical highland

    climate (Ward, 2002). The temperature occasionally drops below freezing point in winter but

    generally a moderate temperature. Afternoon thundershowers can be expected in the summer

    months and cold fronts in winter bring cold southerly winds.

  • 5/28/2018 Design Report Housing and Facilities 2011

    24/177

    7

    3.2 Geological Setting

    In the past, development of this region has been avoided due to unstable dolomites, flood

    plains, marshes, unstable alluvium and chert deposits, active clays and collapsible soils. The

    surrounding area of Lenasia consists of dolomite chert from the Malmani Subgroup. Just westof Lenasia the ground consists of shale and coal of the Ecca Group of the Karoo Super group

    which overlie dolomite. (Greater Johannesburg Metropolitan Council, 2000).

    There is dolomite present on the site and it will be accounted for in the geotechnical

    evaluation of the project.

    African Brick manufactures a large amount of bricks from the Syferfontein clay deposit it

    has a very high quality which is relatively rare in South Africa and is estimated to last until

    2018. (African Brick Centre, 2007)

    3.3 Topography

    The property has a fairly uniform flat terrain with a gentle South to North Slope of less than

    5 with a sharp incline to a ridge on the south end.

    Figure 3.2: Contour Map of the Site

    1590

    1750

  • 5/28/2018 Design Report Housing and Facilities 2011

    25/177

    8

    3.4 Vegetation and Fauna

    Fauna and flora for this area are fairly typical for the region with flat Highveld grasslands. A

    herd of goats were spotted near the low-lying wetland which could signify that the water is

    not poisonous. Very little to no large bushes or trees were observed except for large shrubsoverlying an old farm structure adjacent north of the wetland area.

    Figure 3.3: South facing view of the property. (Hall, 2011)

    3.5 Water Resources

    The farm does appear to have shallow ground water levels identified by some wetland just

    west of the centre of the property, and two dammed up areas; one in the quarry and one in a

    marsh where animal droppings appeared around the waters edge (possibly signifying that the

    water is not highly contaminated).

    According to locals, mining nearby the site has contaminated water resources in the area with

    uranium. It would thus not be suitable to use water on site for potable water, however further

    investigation will be needed to accurately assess contamination levels.

    There are no large water sources in the immediate vicinity of the site and the annual average

    rainfall usually just exceeds 700 mm.

  • 5/28/2018 Design Report Housing and Facilities 2011

    26/177

    9

    Figure 3.4: Quarry (Hall, 2011)

    Figure 3.5: Marsh just east of the dirt road on the property. (Hall, 2011)

  • 5/28/2018 Design Report Housing and Facilities 2011

    27/177

    10

    3.6 Archaeological, cultural and heritage interest.

    As yet, no archaeological or cultural points of interest on the farm have been identified. The

    Baragwaneth Airport, which is currently situated on the proposed site will be demolished,

    however the demolition will be required to be cleared with the municipal authority. Therequirement for building around an air field is a radius of at least 3km. Therefore if the

    demolition of the airport is not authorised an alternative site will have to be found.

  • 5/28/2018 Design Report Housing and Facilities 2011

    28/177

    11

    4. GREEN ALTERNATIVES

    4.1. Passive Heating and Cooling

    4.1.1 Passive Solar Heating

    Introduction

    During winter months, space heating in homes consumes major quantities of electricity.

    Using solar power decreases this usage and consequently has favourable effects on the

    environment.

    Process

    Sunlight enters the building through glass windows and objects inside the house either

    absorbs or reflects the sunlight. If it is reflected, the heat will travel through the room but

    wont be able to exit through the glass window and so it is contained within the building.

    At night when the sun has set heat cant be obtained any more. Thus it is necessary to

    regulate heat gathered during the day so that the house doesnt overheat during the day and so

    that there is still available heat at night. The heat can be managed by using materials in the

    house that have a high thermal mass. Materials that have high thermal masses take longer to

    heat up, thus preventing overheating of the room, but they also hold on to heat for longer.This is beneficial for night time as heat is always transferred from warm to cold areas. As the

    temperature of the room decreases at night time the objects with high thermal masses will

    start releasing gathered heat to the cold areas of the room. This ensures that the house stays

    warm no matter what time of day it is.

    Methods of Optimising the Process

    OrientationIn the southern hemisphere, building should be orientated with their glazing facing north.

    This must be true north and not magnetic north and efficiency is reported within 30of true

    north. However, the closer to true north, the more efficient.

    (http://www.nmsea.org/Passive_Solar/Passive_Solar_Design.htm)

    http://www.nmsea.org/Passive_Solar/Passive_Solar_Design.htmhttp://www.nmsea.org/Passive_Solar/Passive_Solar_Design.htmhttp://www.nmsea.org/Passive_Solar/Passive_Solar_Design.htm
  • 5/28/2018 Design Report Housing and Facilities 2011

    29/177

    12

    GlazingThe building should be designed and situated in such a way that as many of the windows as

    possible face north. This is called glazing. There should be enough glazing in a building to

    ensure sufficient heat in winter but not too much as this could cause overheating in summer.

    Tilted glass is very efficient for heat in winter but is more prone to overheating in summer.

    (http://www.nmsea.org/Passive_Solar/Passive_Solar_Design.htm)

    Sun temperingSun tempering involves adding more windows to the north side of a house so that more

    thermal mass can be exposed to heat from the sun.

    (http://www.nmsea.org/Passive_Solar/Passive_Solar_Design.htm)

    Thermal massMaterials with high thermal mass are very important in order to have a system with high

    functionality. These materials can absorb and retain heat making it very useful in ensuring

    that a house stays warm during the night. Examples include concrete, brick, tile, water etc.

    The abilities of these materials are because of their high density and specific heat and thermal

    conductivity properties. These materials are used in the interior of homes as walls, floors,

    fireplaces, etc. and dont necessarily need to have sunlight directly on them to absorb and

    store heat. (http://www.nmsea.org/Passive_Solar/Passive_Solar_Design.htm)

    Trombe wallPart of the north wall is built out of a material with high thermal mass and glass is placed a

    couple of centimetres from the wall. Heat enters through the glass and cant escape, giving

    the material in the wall time to absorb it. These walls then radiate the heat into the house at

    night. (http://www.nmsea.org/Passive_Solar/Passive_Solar_Design.htm)

    http://www.nmsea.org/Passive_Solar/Passive_Solar_Design.htmhttp://www.nmsea.org/Passive_Solar/Passive_Solar_Design.htmhttp://www.nmsea.org/Passive_Solar/Passive_Solar_Design.htmhttp://www.nmsea.org/Passive_Solar/Passive_Solar_Design.htmhttp://www.nmsea.org/Passive_Solar/Passive_Solar_Design.htmhttp://www.nmsea.org/Passive_Solar/Passive_Solar_Design.htmhttp://www.nmsea.org/Passive_Solar/Passive_Solar_Design.htmhttp://www.nmsea.org/Passive_Solar/Passive_Solar_Design.htmhttp://www.nmsea.org/Passive_Solar/Passive_Solar_Design.htmhttp://www.nmsea.org/Passive_Solar/Passive_Solar_Design.htmhttp://www.nmsea.org/Passive_Solar/Passive_Solar_Design.htmhttp://www.nmsea.org/Passive_Solar/Passive_Solar_Design.htmhttp://www.nmsea.org/Passive_Solar/Passive_Solar_Design.htm
  • 5/28/2018 Design Report Housing and Facilities 2011

    30/177

    13

    4.1.2 Passive cooling

    Landscaping

    Placing trees in strategic places can help with cooling of a house. If a tree is planted in front

    of a north facing window this will block the sunlight during the summer months. The tree

    wont interfere with winter warming techniques as the leaves will fal l off during winter

    allowing the sunlight through.

    (http://www.nmsea.org/Passive_Solar/Passive_Solar_Design.htm)

    Overhangs

    Overhangs for north facing windows are designed in such a way so as to prevent sunlight

    entering the house during summer months. However, they must also allow sun in during the

    winter months. This is possible since the suns rays are at a lower angle during winter

    months.

    Many variables dictate the sizing of the overhang such as climate, roof geometry, latitude,

    etc. But in South Africa the length should be about 0.5 meters.

    (http://www.hedon.info/EnergyEfficientHousingtoBenefitSouthAfricanHouseholds?bl=y)

    4.2 Solar Geysers

    4.2.1 Introduction

    More solar energy reaches the earth every day than can be used by the earths inhabitants in

    25 years. The power generated by the sun is equivalent to 1 kW/m of area exposed;

    therefore, utilising this energy can have significant benefits economically as well as

    environmentally. Both of these benefits are due to a decrease in electricity requirements.

    Environmentally, this results in a decrease in the consumption of fossil fuels and

    economically, a household saves on their electricity bill. On a domestic level, the largest

    portion of electricity usage goes toward water heating by the geyser. Thus using solar power

    to complete this task ensures benefits to the home owner and the environment. (Solar Heat

    Exchangers, 2011)

    http://www.nmsea.org/Passive_Solar/Passive_Solar_Design.htmhttp://www.nmsea.org/Passive_Solar/Passive_Solar_Design.htmhttp://www.nmsea.org/Passive_Solar/Passive_Solar_Design.htmhttp://www.hedon.info/EnergyEfficientHousingtoBenefitSouthAfricanHouseholds?bl=yhttp://www.hedon.info/EnergyEfficientHousingtoBenefitSouthAfricanHouseholds?bl=yhttp://www.hedon.info/EnergyEfficientHousingtoBenefitSouthAfricanHouseholds?bl=yhttp://www.hedon.info/EnergyEfficientHousingtoBenefitSouthAfricanHouseholds?bl=yhttp://www.nmsea.org/Passive_Solar/Passive_Solar_Design.htm
  • 5/28/2018 Design Report Housing and Facilities 2011

    31/177

    14

    Figure 4.1: Evacuated tube collectors on a roof.

    (http://www.sourcerenewable.com/en/pages/services-technologies.aspx)

    4.2.2 Benefits

    Although the initial installation of a water heater can be expensive, the pros far outweigh the

    cons. Some of the benefits are:

    Solar energy is free and unlimited and cannot be taxed. Reduction in electricity usage and also electricity bill. Reduces dependence on the electricity grid. Reduces dependence on fossil fuels. Contributes to the protection of the climate Solar water heaters have a service life of 20 years Between 50-90% of hot water can be supplied by solar power. The energy used to produce a solar water heater is 13 times less than the energy it

    produces.

    Energy is always available (the sun comes up every day), and little maintenance isrequired. (Solar Heat Exchangers, 2011)

  • 5/28/2018 Design Report Housing and Facilities 2011

    32/177

    15

    4.2.3 Types of Solar Water Heating Systems

    Active and passive systems

    Passive systems: This system is the most energy efficient since it solely relies on the

    thermosyphon properties of water. That is, when water heats up it expands and becomes more

    buoyant. This causes hot water to rise in the solar water heating system and any colder,

    denser water sinks. This requires the storage tank to be placed above the collector panel at an

    angle in order for the water to be able to rise to the tank. One problem is that at night time

    this system reverses due to cold temperatures. The water in the pipes on the collector plate

    cools and sinks. This pushes the hot water from the storage tank down to the plate where it

    also cools down. The flow is reversed and the water cools down. This can be avoided through

    correct placement of the storage tank or using a one way valve.

    (http://www.solarwaterheating.co.za/)

    Figure 4.2: Passive solar water heating system.

    (http://www.solarwaterheating.co.za/)

  • 5/28/2018 Design Report Housing and Facilities 2011

    33/177

    16

    Active systems: These systems use pumps to drive the hot water from the solar collector to

    the geyser. This means that the geyser doesnt have to be situated above the collector and can

    be hidden. This system thus has aesthetic benefits and is more efficient; however, it is less

    energy efficient since the pump uses electricity. (http://www.solarwaterheating.co.za/)

    Direct and Indirect Systems

    Direct systems:These systems allow water to run directly through the pipes situated on the

    collector plate and then into the storage tank. Thus the water that runs through the copper

    pipes is the hot water that is eventually used. This system holds certain problems for extreme

    temperatures; for example, when temperatures reach freeze point the water will freeze and

    possibly crack the pipes. Similarly these systems are problematic in high temperatures as they

    dont provide protection against overheating. (Solar Heat Exchangers, 2011)

    Indirect systems: In indirect systems, the pipes consist of a closed off system containing

    propylene glycol (antifreeze). Branches of small diameter pipes containing antifreeze run

    through the storage tank. The heated antifreeze from the collector plate rises and the copperpipes conduct the heat from the antifreeze to the water after which the cooled antifreeze

    moves back down the system. (Solar Heat Exchangers, 2011)

    4.2.4 Types of Collector Plates

    Flat plate collectors: This is considered the most durable collector and also the most suitable

    for domestic use as the temperatures reached are adequate for bathing or showering. The

    collector consists of an oven like glass covered box. The glass is of high quality and can

    withstand hail. It contains a black plate which absorbs heat from the sun and this heat is then

    transferred to the fluid containing copper pipes welded to the plate. There are two horizontal

    pipes (headers) at the top and the bottom of the pipe and many vertical pipes (risers) in

    between. The top horizontal pipe leads the fluid which has heated up into the storage tank and

    the cold fluid that leaves the storage tank sinks into the bottom horizontal pipe. Thus the

    process is repeated. (Solar Heat Exchangers, 2011)

  • 5/28/2018 Design Report Housing and Facilities 2011

    34/177

    17

    Evacuated tube collectors: This collector consists of many vertical tubes instead of risers

    that connect to the horizontal pipes. There are two tubes, one placed within the other with a

    vacuum between the two. The inner tube is covered with a black paint which attracts sunlight

    and the water is contained within this tube. The outer tube is clear glass allowing sunlight to

    reach the inner tube while the vacuum prohibits heat from exiting the system. These

    collectors are less durable due to the decreased quality of the rounded glass but they reach

    higher temperatures since heat cannot leave the system. (Solar Heat Exchangers, 2011)

    4.2.5 Eskom Rebate

    In response to recently announced electricity increases Eskom has created a rebate system for

    solar water heaters. The initiative is aimed at decreasing electricity usage by encouraging

    home owners to implement green alternatives. Buyers are required to purchase their solar

    water heater at an Eskom accredited supplier. The full amount must be paid and the rebate

    forms must all be completed and sent to the facilitating auditors. The rebate will be paid

    within 8 weeks from the date of the auditors receiving the forms. This initiative makes solar

    water heaters more affordable for high and middle income homes since prices are greatly

    reduced. For instance when purchasing a R33 000 (300 litre) solar water heater, the price can

    be reduced by as much as R12 000.

    (http://www.iolproperty.co.za/roller/news/entry/eskom_raises_solar_geyser_subsidy)

    4.3 Lighting

    4.3.1 LED globes

    Instead of the conventional 70W globes 9W LEDs will be used. A 9W LED emits the same

    light strength as a 70W globe. An LED globe is considerably more expensive but lasts for

    60 000 hours where the conventional incandescent bulb only provides 1 500 hours. Not only

    does it last longer but will save an immense amount of electricity in the long run.

  • 5/28/2018 Design Report Housing and Facilities 2011

    35/177

    18

    4.3.2 Sunlighting

    Sunlighting is a method that is used to collect the sunlight from outside and channelling it

    through buildings to provide a natural light source. For Sunlighting to be used, a

    concentration panel that collects the sunlight is required. This concentration panel is placedon the outside of a buildings walls. The system is made up of a series of reflective guides

    that sends the sunlight inside the building. (www.cfmd.com)

    Throughout the day, the suns movement is tracked by the optics, and the concentration of

    sunlight is factored by ten. The light is then transmitted through glazed windows. The light

    guides are thin narrow reflective film coated corridors. Despite the fact that electricity is

    greatly saved windows can now be treated to minimise glare and only function for the view

    which they provide. (www.cfmd.com)

    Figure 4.3: Illustration of how Sunlighting works(www.cfmd.com)

    4.3.3 Solar LED Garden and Landscaping Lights

    Green roofs and gardens can use the Solar LED Garden and Landscaping Lights to provide

    light during the evening. It works on the same concept as the Sun Jar. The LED lights are

    wrapped around objects or plants as shown in the figure below. The solar cell must however

  • 5/28/2018 Design Report Housing and Facilities 2011

    36/177

    19

    receive a maximum amount of sunlight during the day hence it should be placed in manner

    that prevents it from falling in the shade of any plants or walls.

    Figure 4.4: Solar LED Garden and Landscaping Lights (www.mantality.co.za)

    4.3.4 Day/Night Sensor

    Day/Night sensor globes are placed outside and switch on at night automatically. They are

    used to save electricity and act as a security measure.

    4.3.5 Motion Sensors

    Motion sensors are sensors that are attached to light globes. The light bulbs will only be on

    when the sensors detect motion. This technology is advantageous for corporate buildings and

    apartment corridors. It reduces the electricity usage.

    4.4 Insulation

    4.4.1 Roofs

    Roofs should be treated with a layer of cellulose fibres. It consists of recycled newspapers

    with non toxic chemicals added in order to make it rodent and fire resistant. In summer it

    prevents heat from entering the building through the roof. In winter it prevents heat from

    leaving the building through the roof. Using this form of insulation is easy to apply and

    relatively cheap, it is therefore recommended for use in all income brackets.(www.thermguard.co.za)

    http://www.mantality.co.za/http://www.mantality.co.za/http://www.mantality.co.za/http://www.mantality.co.za/
  • 5/28/2018 Design Report Housing and Facilities 2011

    37/177

    20

    Figure 4.5: Thermguard sprayed on the ceiling. (www.thermguard.co.za)

    4.4.2 Walls

    A layer of Rigifoam in a cavity wall will provide insulation and soundproof qualities to any

    building. The Rigifoam is able to insulate the cavity due to its closed cell nature. Rigifoam

    is the same as polystyrene except that it is environmentally friendly and contains no CFCs or

    HCFCs.

    4.4.3 FloorsThermguard is sprayed below the floor covering to prevent heat from escaping through the

    floors, and cold from entering your home in winter. During winter the cold tends to enter a

    building mainly through the floors. It is therefore vital for any building to have proper floor

    insulation.

    Figure 4.6: Cellulose fibre used for floor insulation (www.thermguard.co.za)

  • 5/28/2018 Design Report Housing and Facilities 2011

    38/177

    21

    4.4.4 Windows and sliding doors

    Double glazed glass will be used for its insulating properties. These are window panes that

    are separated by a spacer, usually air or gas. Air or a gas occupies the area between the

    window panes. The spacer seals the space and prevents the gas from leaking out. Thismethod is used to reduce the transfer of heat across the building. The areas temperature does

    not drop below zero in winter therefore a glass thickness of 3mm will be adequate. In

    addition, double glazed panes can prevent outside noise from entering the building.

    4.5 Green Building Materials

    Embodied energy

    The embodied energy of a building material can be understood as the total primary energy

    consumed (or carbon released over its life cycle). This would include extraction,

    manufacturing and transportation. (Inventory of Carbon & Energy (ICE) v1.6a, 2008).

    Recycled Aluminium

    Although the embodied energy of aluminium is one of the highest, it would be incorrect to

    assume that there are no green aspects related to its use. Aluminium is inherently durable

    and corrosion resistant which reduces life cycle costs as well as easy to mould reducing

    product manufacturing costs. Transport costs are also reduced due to its lightweight and

    modular assembly capability. Aluminium has a high thermal conductivity which for

    insulation purposes is not ideal, but it does however provide reflective insulation which

    retains energy (Paterson, 2010).

    One of the most important aspects of aluminium use is that it is easily recyclable, and

    facilities for this have been established for over 100 years (ibid). Re-melting aluminium

    requires less than 5% of the energy to produce primary aluminium and it can be recycled

    indefinitely without loss of properties with up to 95% of building material being recoverable

    (75% of all aluminium ever smelted is still in use today) (AFSA 2010)

  • 5/28/2018 Design Report Housing and Facilities 2011

    39/177

    22

    Advantages Disadvantages

    Durable / Corrosion resistant Expensive

    Lightweight High thermal conductivity

    Easy to work with Very high virgin embodied energyReadily recyclable Not generally used for structural purposes

    Reflective insulation

    Aluminium Embodied Energy (MJ/Kg)

    Virgin 218

    Recycled 28.8

    (Inventory of Carbon & Energy (ICE) v1.6a, 2008)

    Uses for aluminium:

    Finishes Window frames Roof sheeting Fenestration systems Drainage systems

    Life expectancy: 60+ Years

    Recycled Steel

    Steel has significantly lower embodied energies than aluminium. Steel is 100% recyclable

    and can be recycled indefinitely without loss of properties. Steel is easily available, can be

    relatively lightweight and corrosion resistant if galvanised.

    Advantages Disadvantages

    Durable / Corrosion resistant High thermal conductivity

    Cheaper than aluminium low embodied energy for metal

    Easy to work with

    Easily recyclable

  • 5/28/2018 Design Report Housing and Facilities 2011

    40/177

    23

    Steel Embodied Energy (MJ/Kg)

    Virgin 35.3

    Recycled 9.5

    Virgin Galvanised Sheet 39Engineering Steel (recycled) 13.1

    (Inventory of Carbon & Energy (ICE) v1.6a, 2008)

    Uses for aluminium:

    Finishes Window frames Roof sheeting Fenestration systems Drainage systems Doors Structural

    Life expectancy: 60+ Years

    Green Concrete

    Concrete is the most commonly used construction material in the world and, because of its

    extensive use, generates a relatively large carbon footprint. The major contributing factor

    towards concretes large carbon footprint is the production of cement; it is a rule of thumb that

    for every ton of cement clinker produced a ton of carbon is released into the atmosphere.

    The embodied energy of concrete is very low as concrete is a composite material, of which

    the bulk is aggregate with embodied minimal embodied energies as low as 0.01 (Inventory of

    Carbon & Energy (ICE) v1.6a, 2008).

    In a push towards sustainable development and reducing environmental degradation, the

    minimisation of the carbon emissions generated from concrete is of great importance. Hence

    greener concrete designs are becoming favourable. With the use cement replacement

    extenders formed as by-products from industrial processes the embodied energy of

    concrete can be further reduced. The appropriate use of admixtures, for example, to reduce

    water and thus cement content can also contribute to a more environmentally friendly greenconcrete.

  • 5/28/2018 Design Report Housing and Facilities 2011

    41/177

    24

    Advantages Disadvantages

    Can be designed for Durability Cement has a large carbon footprint

    Cheap Rubble very hard to recycle

    Easy to work with UnpredictableLow thermal conductivity Susceptible to climate i.e. corrosion of

    reinforcement

    Very low embodied energy Susceptible to climate i.e. corrosion of

    reinforcement

    Can be designed green Steel Reinforcement has high embodied energy

    Readily available

    Concrete Embodied Energy (MJ/Kg)

    General 0.95

    Prefabricated 2.00

    Blocks (13Mpa) 0.81

    50% Blast furnace slag (30Mpa) 0.82

    (Inventory of Carbon & Energy (ICE) v1.6a, 2008)

    Uses for concrete:

    Flooring, paving etc. Drainage systems Structural

    Life expectancy: Design based: usually 50 years +

    Timber

    Wood is environmentally friendly as long as it is forested for future sustainability. Wood has

    great versatility, excellent insulation properties and is aesthetically pleasing. The embodied

    energy is due to harvesting and preparation.

  • 5/28/2018 Design Report Housing and Facilities 2011

    42/177

    25

    Advantages Disadvantages

    Low cost Window frames are high maintenance

    Sustainable Wood expands and contracts depending on the temperature

    Versatile Becomes brittle once weatheredLight Weight Wood floors needs to be cleaned with special chemicals

    Recyclable Window frames shows larger air leakage than aluminium

    Reusable

    Durable

    Timber Embodied Energy (MJ/Kg)

    General 8.5

    Plywood 15

    (Inventory of Carbon & Energy (ICE) v1.6a, 2008)

    Uses of wood:

    Finishes Window frames Doors low load bearing Structures e.g. roof trusses

    Compressed Stabilised Earth Blocks (CSEB)

    CSEBs are a relatively new technology and are manufactured using the available natural soil

    in the area and a CSEB press. The soil is moistened and then poured into a press to form

    blocks. Stabilisation is achieved using small amounts of cement or lime, if necessary.

    Advantages include:

    Giving employment to locals and uplifting the community with the high labourintensity required.

    Minimisation of transportation and COemissions. Minimal time and money used by utilising local materials.

  • 5/28/2018 Design Report Housing and Facilities 2011

    43/177

    26

    Energy savings, with an energy consumption of 110 MJ (compare to kiln fired blocksusing 539 MJ), 16 kg/m2 CO2 emissions compared to concrete blocks at 26 kg/m2.

    Depending on the quantity of cement, CSEB blocks are almost always cheaper thankiln fired blocks.

    Deforestation is minimised as wood is not needed to burn the blocks as is requiredwith kiln fired. Another important aspect of CSEB blocks is that they are bio-

    degradable, unlike many other construction materials.

    (Auroville Earth Institute, Circa)

    Limitations include:

    Proper soil identification is required Low technical performances compared to concrete. Untrained teams can produce low quality products. Over-stabilization through fear or ignorance causes increased costs Under-stabilization results in low quality products.

    Uses for CESB:

    Masonry

    4.6 Green roofs

    A green roof involves growing vegetation on top of a roof with a waterproofing layer (and

    other optional layers). They not only provide good insulation for buildings, but also keep

    them cool during hot summer months. The roofs plants shade the building from solarradiation and reduce net heat gain in summer, while in winter the soil decreases the amount

    of energy required to heat the building. They are aesthetically pleasing and have good storm

    water retention properties.

  • 5/28/2018 Design Report Housing and Facilities 2011

    44/177

    27

    Figure 4.7: Sublayers for a green roof. (http://www.toronto.ca/greenroofs/what.htm)

    Extensive Green Roofs

    Thin layer of soil Low plant diversity Little or no irrigation required

    Intensive Green Roofs

    Deep Soil Irrigation system required High plant diversity

    Challenges

    Motivation and education to sustain green roofs. Intensive roofs impose a greater weight loading on roofs, have high capital cost, and

    expertise required.

  • 5/28/2018 Design Report Housing and Facilities 2011

    45/177

    28

    Selling the concept to the client.(Kuhn M. & Peck S. Circa.)

    Table 4.2: Green roof characteristics (www.igra-world.com)

    Extensive

    Semi-

    intensive Intensive

    Maintenance Low Periodically High

    Irrigation No Periodically Regularly

    Plant Communities Moss, grass Grass, Shrubs Shrubs, trees

    System Build up height60 - 200 mm 120 - 250 mm

    150 - 400

    mm

    Weight 60 - 150 kg/m120 - 200

    kg/m

    180 - 500

    kg/m

    Costs Low Middle High

    UseEcological

    protection layer

    Designed

    Green roof

    Park like

    garden

    4.7 Rain water harvesting

    4.7.1. Introduction

    Rain water harvesting would be a very effective green alternative for the proposed project.

    Considering that the MAR (mean annual rainfall) of the area is 0.5m and roof area for the

    proposed town is roughly 3 000 000 m2(20 000 000 m2* 25% of area for buildings * 60% of

    this is roof area), approximately 1.5 million cubic metres of rain water can be harvested per

    year.

    Rain water harvesting collects the water from a catchment area and then diverts the water to

    wherever needed.

  • 5/28/2018 Design Report Housing and Facilities 2011

    46/177

    29

    4.7.2 Uses of harvested rain water

    Storing the rain water

    The rain water is collected from a catchment area, and then stored in a surface or

    underground water tank for later use. The untreated water could then be used for irrigation,

    cleaning, flushing toilets, etc.

    Discharging rain water underground

    Due to the dense population in urban areas, rain has difficulty reaching the ground and thus,

    infiltration is reduced. As a result, plants without water irrigation die from inadequate water

    supply. In addition to this, urban areas are becoming more prone to flooding due to the

    decreased infiltration of storm water. Removing storm water through rain water harvesting

    eases the demands placed on storm water management systems and so, reduces the likelihood

    of flooding. This would have significant positive effects as the storm water level over urban

    areas can be four times as high as that over natural areas. (Wypych & Bokwa, 2003)

    Rain is typically relatively clean, good quality water, and requires little filtration for it to be a

    good source of drinking water. Due to pollution of groundwater and surface water and the

    increased demand for water, rainwater harvesting could be considered as an additional water

    source. (Worm & van Hattum, 2006)

  • 5/28/2018 Design Report Housing and Facilities 2011

    47/177

    30

    Figure 4.8: Rain water harvesting alternatives

    The figure above shows the possible alternatives that rain water harvesting could be used for.

    It moves from low cost on left to high cost rain water harvesting on right. One of the largest

    costs for rain water harvesting is storage of the water. What has to be determined is if storage

    should be on the surface or underground. Surface storage is cheaper than underground storage

    because necessary soil removal is reduced. It is also easier to repair if something goes wrong

    but lack of space means underground storage is a more realistic option.

    4.7.2 Proposed water harvesting systems

    Low Cost Housing

    The figure below shows how rain water harvesting could be done for low cost housing.

    Rain catchmentarea

    Light filtration(e.g. Leaves)

    Tank

    Used for simpletasks such as

    washing andirrigation

    Light filtration

    Surface storage(With greywater)

    Can be used forwashing,

    irrigation, toiletdischarges e.t.c

    Sub-surfacestorage (With

    greywater)

    Can be used forwashing,

    irrigation, toiletdischarges e.t.c

    Discharged intoground (e.g.

    soakaway pit)

    Required cleaningto make water

    drinkable

    Surface storage

    Used as regular

    clean water

    Sub-surfacestorage

    Used as regular

    clean water

  • 5/28/2018 Design Report Housing and Facilities 2011

    48/177

    31

    Figure 4.9: Rainwater Harvest system

    (http://savingh20.blogspot.com/2010/12/we-are-still-here.html

    High rise buildings

    For the high rise buildings, water can be collected on the roof and then transported to the

    ground floor by gravity. There was a study done in Singapore were it was determined an

    effective saving of 4% of water used. This water then didnt have to be pumped from the

    ground floor. This saved the amount of water to be used, as well as electricity and capital.

    (Srinivas, 2007)

    Rain catchment area

    Typically what is used as a rain catchment area is an impervious surface such as a roof. But

    there have been attempts at deviations from this such as a concept by an Australian designer

    called Chris Buerckner, called The Watree. Watree is something like an upside down

    umbrella that is designed to be placed in parks and playgrounds as a rain shelter for people, as

    well as to collect rain water to be stored in tanks. An example of one of the designs is shown

    in the figure below.

  • 5/28/2018 Design Report Housing and Facilities 2011

    49/177

    32

    Figure 4.10: Watree design. (Jolly, 2008)

    4.7.3 Advantages and Disadvantages

    Table 4.3: Advantages and disadvantages of rainwater harvesting

    Advantages DisadvantagesSimple construction: Construction of RWH

    systems is simple and local people can easily be

    trained to build these themselves. This reduces

    costs and encourages more participation,

    ownership and sustainability at community level.

    High investment costs: The cost of rainwater

    catchment systems is almost fully incurred during

    initial construction. Costs can be reduced by

    simple construction and use of local materials.

    Good maintenance: Operation and maintenance

    of a household catchment system is controlled

    solely by the tank owners family. As such, this is

    a good alternative to poor maintenance and

    monitoring of a centralised pipe water supply.

    Usage and maintenance: Proper operation and

    regular maintenance is a very important factor

    that is often neglected. Regular inspection,

    cleaning and occasional repairs are essential for

    success of the system.

    Relatively good water quality: Rainwater is of

    better quality than other available or traditional

    sources (groundwater may be unusable due to

    fluoride, salinity or arsenic).

    Water quality is vulnerable: Rainwater quality

    may be affected by air pollution, animal or bird

    droppings, insects, dirt and organic matter.

    (Worm & van Hattum, 2006)

  • 5/28/2018 Design Report Housing and Facilities 2011

    50/177

    33

    4.8 Heat Pumps

    Introduction

    Heat pumps work on the simple principle of transferring heat from one space to another.

    Electricity is used to do this however, since heat is only being transferred and not generated,

    electricity usage is minimal. This makes heat pumps energy efficient and in addition to space

    heating, they can also be used to heat water making them a viable alternative to solar geysers.

    Their setup costs are less than that of solar geysers however, their energy efficiency is not as

    good. (www.heatpumps.org.uk)

    How it works

    Heat pumps work in a similar manner to refrigerators. There are two heat exchangers, one

    that absorbs heat and the other that rejects it. This system is sealed so that no heat is lost and

    is connected to a piping system which is filled with refrigerant. A refrigerant is a fluid with a

    low boiling point and it is circulated by the compressor. The compressor exploits the fluids

    ability to evaporate when heated and then condensate, returning to liquid form. This ensures a

    continuous system of heat transfer. (www.heatpumps.org.uk)

    At a domestic level, heat pumps use the air outside as a heat source. Even during winter, heat

    is present in the air and can be used for space heating. During the summer months the process

    reverses and air inside of a house is used as the heat source. Thus, heat inside the house is

    expelled and the space is cooled. Geothermal heat pumps are also possible with the ground

    used as the heat source. (www.heatpumps.org.uk)

    http://www.heatpumps.org.uk/http://www.heatpumps.org.uk/http://www.heatpumps.org.uk/http://www.heatpumps.org.uk/http://www.heatpumps.org.uk/http://www.heatpumps.org.uk/http://www.heatpumps.org.uk/http://www.heatpumps.org.uk/http://www.heatpumps.org.uk/http://www.heatpumps.org.uk/http://www.heatpumps.org.uk/http://www.heatpumps.org.uk/
  • 5/28/2018 Design Report Housing and Facilities 2011

    51/177

    34

    Figure 4.11: Heat pump outside a house.

    (http://www.sourcerenewable.com/en/pages/services-technologies.aspx)

    Pros and Cons

    Pros

    Savings on electricity Dehumidifies the air in humid areas Low capital cost

    Cons

    Ineffective in areas where temperatures reach below 0C Heat produced isnt as intense as that of a heater Backup heating and cooling means are required Dehumidifies the air in dry areas

    (www.heatpumps.org.uk)

    http://www.sourcerenewable.com/en/pages/services-http://www.sourcerenewable.com/en/pages/services-http://www.sourcerenewable.com/en/pages/services-http://www.heatpumps.org.uk/http://www.heatpumps.org.uk/http://www.heatpumps.org.uk/http://www.heatpumps.org.uk/http://www.sourcerenewable.com/en/pages/services-
  • 5/28/2018 Design Report Housing and Facilities 2011

    52/177

    35

    5. Design Results

    5.1. Spatial Design

    These values were based on data from the latest CSIR Summary Guidelines and standards for the Planning of Social Facilities and Recreational

    Spaces in Metropolitan Areas 2010, population statistics and engineering judgements.

    The allocated land use for housing and facilities by town planning was a maximum of 40%. Therefore this requirement governed the spatial

    design considerations.

    5.1.1. Housing

    Table 5.1.1: Summary of Housing

    SINGLE-

    STAND Housing type DescriptionStoreys

    (floors)Units/

    floor Units / stand Number of Stands Stand size (ha)Total required Area

    (ha)

    RDP 4 block 1 4 4 5625 0.0315 178

    Low incomesingle 300

    sqm 1 1 1 500 0.03 15

    Mediumincome

    single 700sqm 1 1 1 1120 0.07 78.4

    High Incomesingle 1100

    sqm 1 1 1 1250 0.11 137.5

    Total 409

  • 5/28/2018 Design Report Housing and Facilities 2011

    53/177

    36

    MULTI-

    STOREY Housing typefloor area/

    UnitStoreys

    (floors)Units/

    floorUnits /

    BuildingNumber of

    BuildingsStand size /

    building(ha)Total required Area

    (ha)

    Low income80 sqm

    10 20 200 602 per 5 building

    grouping 24Medium

    income150 sqm

    8 60 480 18 4.5 81

    High Income 300 sqm 13 18 234 15 4.5 67.5

    Total 173

    COMPLEX Housing typefloor areas/

    UnitStoreys

    (floors)Units/

    floorUnits /

    ComplexNumber of

    co