DESIGN PACKAGE C122 - BORED...
Transcript of DESIGN PACKAGE C122 - BORED...
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Document uncontrolled once printed. All controlled documents are saved on the CRL Document System
© Crossrail Limited UNCLASSIFIED
DESIGN PACKAGE C122 - BORED TUNNELS
CROSSRAIL PLUMSTEAD SIDINGS
LEVEL 2 FLOOD RISK ASSESSMENT
Submission GRE/2/9
Document Number: C122-OVE-T3-RGN-CR148-50004
Revision: Date: Prepared by: Checked by: Approved by: Reason for Issue:
2.0 15/10/2013 Jayne Lamont Paul White Rob McCrae TWAO Application
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Document uncontrolled once printed. All controlled documents are saved on the CRL Document System
© Crossrail Limited UNCLASSIFIED
Contents
Abbreviations ................................................................................................................. 4
Executive Summary ...................................................................................................... 5
1. Introduction ............................................................................................................... 7
1.1 Background ................................................................................................................ 7
1.2 Development Proposals ............................................................................................ 8
1.3 Proposed Construction Works and Programme ..................................................... 9
1.4 Scope ....................................................................................................................... 10
1.5 Previous Assessment .............................................................................................. 11
2. Policy Context ......................................................................................................... 12
2.1 Flood Zone Classification ....................................................................................... 12
2.2 Sequential Test ......................................................................................................... 13
2.3 Exception Test .......................................................................................................... 13
3. Assessment of Flood Risk...................................................................................... 14
3.1 Overview ................................................................................................................... 14
3.2 Historical Incidents of Flooding ............................................................................. 14
3.3 Fluvial Flood Risk .................................................................................................... 15
3.4 Tidal Flood Risk ....................................................................................................... 15
3.5 Surface Water Flood Risk ........................................................................................ 17
3.6 Groundwater Flood Risk ......................................................................................... 18
3.7 Other Sources of Flood Risk ................................................................................... 18
3.8 Climate Change ........................................................................................................ 18
4. Mitigation of All Sources of Flood Risk ................................................................. 20
4.1 Tidal ....................................................................................................................... 20
4.2 Surface Water ........................................................................................................... 20
4.3 Groundwater ............................................................................................................. 22
5. Conclusions and Recommendations .................................................................... 23
5.1 Conclusions .............................................................................................................. 23
5.2 Recommendations ................................................................................................... 24
References ................................................................................................................... 25
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Document uncontrolled once printed. All controlled documents are saved on the CRL Document System
© Crossrail Limited UNCLASSIFIED
Appendices
Appendix A.1 Proposed Development Site Boundary
Appendix A.2 Baseline Site Layout Plan Following Temporary Development
Appendix A.3 Drainage Plans
Appendix A.4 Environment Agency Flood Maps and Flood Risk Data
Appendix B NPPF Policy Tables
Appendix C SFRA Developer Guidance
Appendix D Strategic Flood Risk Assessment (SFRA) Maps
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Page 4 of 25 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System © Crossrail Limited UNCLASSIFIED
Abbreviations
AEP Annual Exceedence Probability
FRA Flood Risk Assessment
mAOD metres Above Ordnance Datum
mATD metres Above Tunnel Datum
NPPF National Planning Policy Framework
PPS25 Planning Policy Statement 25: Development and Flood Risk
SFRA Strategic Flood Risk Assessment
SuDs Sustainable Drainage System
SWMP Surface Water Management Plan
WCS Water Cycle Study
Annual Exceedence Probability (AEP)
The severities of the events discussed in this report are defined mainly as Annual Exceedence
Probabilities (AEP). The AEP is the probability that there will be an event exceeding a particular severity
in any one year.
Annual Exceedence Probability Probability (chance in any given year)
50% 1 in 2
10% 1 in 10
4% 1 in 25
3.3% 1 in 30
2% 1 in 50
1.33% 1 in 75
1% 1 in 100
0.5% 1 in 200
0.4% 1 in 250
0.1% 1 in 1000
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Page 5 of 25 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System © Crossrail Limited UNCLASSIFIED
Executive Summary
C122 (Arup and Atkins Joint Venture) has been commissioned by Crossrail Ltd to carry out a
Level 2 Flood Risk Assessment (FRA) for the development of the Plumstead Crossrail Sidings.
This site is located at the White Hart Triangle area of Plumstead, within the Royal Borough of
Greenwich (RBG). This Flood Risk Assessment will be used to support a Transport and Works
Act Order (“TWAO”) application for the Crossrail Plumstead Sidings. The site is well
documented both at a strategic level through assessments made by Crossrail (Crossrail, 2008)
and also by RB Greenwich, through the SFRA for Greenwich (Strategic Flood Risk Assessment,
2011).
It is proposed to use the Plumstead Crossrail Sidings, which will be located adjacent to the
Crossrail Plumstead tunnel portal, as an infrastructure maintenance facility for Crossrail’s
tunnelled central section and the passenger train stabling location for Crossrail’s south eastern
spur. The site currently has planning permission for use as a temporary railhead (herein also
referred to as the “Temporary Development”) to support the fit out of Crossrail under RBG
planning permission 13/0300/F. The Temporary Development is proposed to be constructed
from late 2013 and operate until late 2018.
The Plumstead Crossrail Sidings (“the Permanent Development”) will utilise some permanent
elements of the Temporary Development. These comprise earthworks (including drainage,
retaining wall and slope stabilisation), an electricity substation, two vehicle access points, hard
standing, rail tracks (including stabling and reception siding, a headshunt and associated
trackwork), and perimeter fencing.
The Permanent Development site lies predominately within Tidal Flood Zone 3a (high
probability of flooding) and within an ‘Area Benefitting from Defences. The National Planning
Policy Framework (NPPF) and associated Technical Guidance (both published by the
Department for Communities and Local Government (“DCLG”) in March 2012), and the PPS25
Development and Flood Risk Practice Guide (published in June 2008), require a site-specific
flood risk assessment to be carried out for all proposals for new development in Flood Zones 2
and 3. Given the nature of the permanent development and its location within an area of flood
risk level 3 it is necessary to complete a Level 2 FRA in order to provide a qualitative appraisal
of flood risk to the development, changes in flood risk elsewhere as a result of the development,
now and taking climate change into account, and the scope of any mitigation measures that
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Page 6 of 25 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System © Crossrail Limited UNCLASSIFIED
may be appropriate. The site itself is documented at strategic level and this FRA makes use of
information provided by the Environment Agency, Crossrail Ltd and the Royal Borough of
Greenwich (RBG) Strategic Flood Risk Assessment (SFRA, 2011).
The nature of the development (rail sidings and infrastructure maintenance facility) is such that
it falls within the category of ‘Less Vulnerable’ development (general industry) for the purposes
of flood risk assessment (in accordance with the definitions in Table 2 (flood risk vulnerability
classification) of the DCLG Technical Guidance.
The Southern Outfall Sewer (SOS) to the north of the site acts as a barrier in the unlikely event
of a breaching or overtopping scenario (tidal flooding) occurring from the tidal River Thames.
The SFRA shows that, without mitigation, the Plumstead Portal (situated on the south eastern
edge of the site) could convey flood flows and inundate the site in the event of breaching or
overtopping, causing flooding to the site. However, the ground elevations surrounding the
Plumstead Portal are being raised as part of the Crossrail works to ensure that it cannot act as
conveyance for flood flows should tidal or surface water flooding occur.
The existing surface water flood risk shows that the site is subject to surface water flooding of
over one metre (see Map 10 of the SFRA) during a 0.1% AEP with climate change.
The site is classed as a brownfield site and the SFRA developer guidance states that the
surface water drainage should improve the drainage of the site as part of the development. By
discharging surface water runoff rates down to greenfield rates the Proposed Development will
provide betterment for the site in terms of surface water flood risk.
The risk of groundwater flooding is low, however a previous FRA (Scott Wilson, 2007) for the
adjacent site suggests that a pumping system exists that maintains ground water at levels of
0mAOD. This system will be investigated further prior to the Temporary Development to ensure
that development on the site will not alter its operation and can be maintained both during the
construction and operation of the Proposed Development.
The assessment concludes that the flood risk to the permanent development is low, providing
the appropriate mitigation measures are implemented.
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Page 7 of 25 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System © Crossrail Limited UNCLASSIFIED
1. Introduction
1.1 Background
C122 (Arup and Atkins Joint Venture) has been commissioned by Crossrail to carry out a Level
2 Flood Risk Assessment (FRA) for the development of the Plumstead Crossrail Sidings. This
site is located at the White Hart Triangle (WHT) area of Plumstead, in Thamesmead, south east
London within the Royal Borough of Greenwich (RBG). The site is currently vacant however,
between mid 2014 and late 2018 it will be used as a temporary railhead facility (“the Temporary
Development”) to support the fit out of the Crossrail tunnels during construction. RBG granted
planning permission for the Temporary Development under the Town and Country Planning Act
1990 on 11 September 2013 under planning application no. 13/0300/F.
In total the site extends to approximately 5.5ha in area. The Proposed Development site
boundary is shown in Appendix Error! Reference source not found.. It is rectangular in shape
(approximately 85m wide by 390m long) and orientated approximately north east to south west.
The secondary (southern) part of the site is a 550m long west-east strip of land, varying in width
between 10m and 40m running parallel with the North Kent railway line to a point just west of
the White Hart Road bridge (incorporating the rail lines into the existing Network Rail sidings). A
triangle of land located immediately to the west of the former bowling green connects the main
part of the site with the southern part of the site and a vegetated embankment, which is within
the Proposed Development site boundary, separates the site from the adjacent allotments and
Seven Acres playing fields (which lie approximately 1m lower) to the south east.
The site occupies a low lying position within the wider townscape. To the south, Shooters Hill
rises to form a ridge line at Wins Common and to the north the townscape remains relatively flat
with the prominent built element being Belmarsh Prison. Prior to implementation of the
Temporary Development, the site mostly comprises open, vacant land, covered in grassland
and scrub vegetation throughout its central section with scrub and occasional birch trees in the
southern section and is generally flat except at its eastern end, where previously tipped material
has created an uneven surface and there are raised mounds, ranging in level from 2.6m to 7.6m
above tunnel datum (ATD), i.e. at a level up to 5m higher than that of White Hart Avenue to the
north west. In advance of the Temporary Development, a small area of the site has been
occupied by CRL office and welfare buildings and a temporary hard surfaced car park which
serves the construction site for the adjacent Plumstead portal.
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Page 8 of 25 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System © Crossrail Limited UNCLASSIFIED
This FRA has been completed in accordance with the NPPF and associated technical guidance,
which replaced Planning Policy Statement 25: Development and Flood Risk (PPS25) in March
2012.
The site lies within an area identified by RB Greenwich as an area for development (under the
Local Development Plan). The Unitary Development Plan (UDP) reference is DIA3. However
the proposed site does not cover the whole of site DIA3, which is 18.9ha.
Under the developer guidance (see Appendix C), taken from the SFRA the site is designated for
employment and a waste treatment facility. This type of development has a flood risk
vulnerability classification of ‘Less Vulnerable’ as per NPPF, Table 2 (Appendix B).
1.2 Development Proposals
Crossrail are proposing to construct a passenger train stabling and infrastructure maintenance
facility. The facility, known as Plumstead Crossrail Sidings (“the Proposed Development”) will
provide the functional elements described below:
Passenger Train Stabling:
Eight electrified sidings, each able to accommodate a passenger train up to
240m long and associated signalling equipment facilities;
Facilities for cleaning stabled trains including covered storage facilities with a
waste compactor; and
Accommodation and messing facility for infrastructure maintenance staff and
train crew. Facilities will include: offices, briefing, changing, shower and locker
accommodation and booking-on point.
Infrastructure Maintenance Facility:
Three non-electrified sidings for the stabling, formation, loading and unloading
of dedicated infrastructure maintenance rail vehicles;
Refuelling facilities for the infrastructure maintenance rail vehicles;
Facilities for maintaining the infrastructure maintenance rail vehicles;
Lay down space for the storage of infrastructure maintenance components
when they are not installed on a rail vehicle;
A facility for the manual jet washing of the infrastructure maintenance rail
vehicles;
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Page 9 of 25 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System © Crossrail Limited UNCLASSIFIED
Storage facilities for infrastructure maintenance equipment and consumables;
Parking for approximately 20 maintenance vans and trucks; and
Parking for approximately 100 staff vehicles.
Associated Trackwork:
The construction of trackwork for a headshunt and reception siding by which all
trains (maintenance rail vehicles and passenger trains) will egress the site and
gain access to the Crossrail lines.
1.3 Proposed Construction Works and Programme
Construction of the Proposed Development is programmed to be undertaken between mid 2017
and early 2019 and is expected to include the following works:
Reconfiguring hardstanding areas and roads retained from the Temporary Development;
Construction of support buildings:
- Accommodation building;
- Maintenance building;
- - Signalling equipment facilities; and
- Manual train wash.
Replacement of tracks for passenger stabling and maintenance trains; and
Replacement of the trackwork for the headshunt and reception siding.
No bulk earthworks for the Proposed Development will be required as this will be undertaken as
part of the Temporary Development.
Unless otherwise agreed with the relevant local authority through the Section 61 consent
process (under the Control of Pollution Act 1974), construction activities will be undertaken in
accordance with the Crossrail Environmental Minimum Requirements (EMR) i.e. during core
working hours (08:00-18:00 Monday to Friday and 08:00 – 13:00 on Saturday) and utilising a
start-up and close-down hour before and after these periods.
The operational phase of the Plumstead Crossrail Sidings will commence from early 2019. The
functional requirements of the facility are such that the site will be required to operate on a 24
hour / 7 days a week basis.
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Page 10 of 25 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System © Crossrail Limited UNCLASSIFIED
A Thames Water sewer, known as the ‘Marmadon sewer’, understood (from information
provided by Thames Water) to be a 1,280mm deep by 800mm wide egg / oval shaped Victorian
brick structure, runs beneath the site from Marmadon Road on a north eastern alignment
towards White Hart Avenue. The sewer, known to be in poor condition, is being diverted and
reconstructed as part of the Crossrail portal works prior to commencement of the Proposed
Development and these works will result in a permanent access shaft, four manholes and
pumping station being located within the site. The new sewer will consist of a 1.2m internal
diameter concrete pipe and will be connected to the combined Southern Outfall Sewer.
1.4 Scope
A Level 2 FRA is a scoping study which confirms the flood risk to the site and confirms if there is
likely to be an increase in flood risk as a result of the development. The FRA carried out for the
Plumstead temporary railhead (June 2012) forms the basis of this Level 2 FRA.
The Temporary Development comprises a temporary railhead and associated (permanent) civil
engineering works. It includes the construction of temporary rail sidings: buildings for
engineering train maintenance, inspection and cleaning and for staff welfare; storage facilities;
road vehicle access points, parking and circulation routes. At commencement of the Proposed
Development, the site baseline conditions will include an operational railhead including the
following permanent features, which will be retained from the Temporary Development:
Earthworks including drainage, retaining wall and slope stabilisation;
Electricity substation;
Two vehicle access points;
Hardstanding;
Rail tracks (including stabling and reception siding, headshunt and associated
trackwork); and
Perimeter fencing.
The site layout plan in Appendix A.2 shows the location and layout of these retained elements
which are assume to form part of the baseline conditions for this FRA.
The scoping study will also recommend potential measures that could be implemented to
reduce the risk to an acceptable level if applicable. Until further guidance in relation to the
requirements of a Level 2 FRA in line with the NPPF is made available, as best practice, the
scope of this FRA has been completed in line with the NPPF, the associated Technical
Guidance and PPS25 Guidance “Development and Flood Risk Practice Guide” (published by
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Page 11 of 25 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System © Crossrail Limited UNCLASSIFIED
DCLG in June 2008). Hence this Level 2 FRA includes the following, taking climate change into
account:
A qualitative appraisal of the flood risk posed to the site, and any potential impacts of the
development on flood risk elsewhere;
An appraisal of the possible mitigation measures to reduce flood risk to acceptable levels;
and
Demonstration of a risk based approach to the location of development by applying the
Sequential and if appropriate the Exception test.
In line with NPPF this FRA makes use of readily available information in the form of Fluvial
Modelling studies from Crossrail (Crossrail, 2008) and the Strategic Flood Risk Assessment for
the Royal Borough of Greenwich (Greenwich Council, 2011) and information provided by the
Environment Agency for the temporary railhead development (see Appendix A.4). This FRA
addresses the flood risk posed to both the construction and operational phases of the
Plumstead Crossrail Sidings.
1.5 Previous Assessment
The site is well documented both at a strategic level through assessments made by Crossrail
(Crossrail, 2008) and also by Greenwich Council, through the SFRA for Greenwich (Greenwich
Council, 2011). The SFRA provides a developer guidance summary and set of
recommendations for the site identified by the Local Development Plan (LDP). The LDP
identifies the site at Plumstead for development by Crossrail. The SFRA developer guidance for
this site can be found in Appendix C. A Level 2 FRA was also undertaken for the site as part of
the Temporary Development in 2012 (Appendix C1 of the ES for the Temporary Development
(C122-OVE-T1-XST-CR148-50002)).
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Page 12 of 25 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System © Crossrail Limited UNCLASSIFIED
2. Policy Context
In March 2012, the National Planning Policy Framework (NPPF) was published which revoked
PPS25, although the principles remain the same. This FRA has been completed in line with the
NPPF and the associated guidance. The aim of NPPF is to avoid inappropriate development in
areas at risk from flooding, but where development is necessary, making it safe without
increasing flood risk elsewhere, as per paragraphs 100 to 104 of the NPPF. In accordance with
NPPF proposed development in areas at risk from flooding, (i.e. located in Flood Zone 2 or 3)
require the submission of a FRA with the planning application. The Proposed Development is
located partially within Flood Zone 2 and 3 and thus this FRA is required in line with current
policy and as outlined in the Scoping Report for the Proposed Development (Document
reference C122-OVE-T1-RGN-CR148-50006).
2.1 Flood Zone Classification
NPPF guidance outlines four Flood Zone classifications of which three have been utilised by the
Environment Agency in the creation of their Flood Map. These Flood Zones should be used in
determining the appropriateness of Proposed Development uses when considering flood risk
through the application of the Sequential Test. They represent flooding without flood defences
in place.
The Flood Zones are defined as:
Flood Zone 1 – Areas with a ‘Low Probability’ of flooding and where the annual
probability of flooding is lower than 0.1% for either fluvial or sea flooding. NPPF impose
no constraints upon the type of development within Flood Zone 1.
Flood Zone 2 – Areas with a ‘Medium Probability’ of flooding and where the annual
probability of flooding is between 0.1 and 1.0% for fluvial flooding or between 0.5 and
0.1% for sea flooding. NPPF recommend that Flood Zone 2 is suitable for most types of
development with the exception of ‘Highly Vulnerable’ (see Appendix B) land uses which
require a passed Exception Test.
Flood Zone 3 – Areas with a ‘High Probability’ of flooding and where the annual
probability of flooding is 1.0% or greater for fluvial flooding or 0.5% or greater for sea
flooding. NPPF recommend that appropriate development is based upon a further
classification of Flood Zone 3 into 3a High Probability and 3b, functional floodplain,
(where water has to flow or be stored in times of flood).
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Page 13 of 25 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System © Crossrail Limited UNCLASSIFIED
According to NPPF the Proposed Development is classed as ‘Less Vulnerable’ (see bold text in
Appendix B, table B.1). This classification is based on Table 2: Flood Risk Vulnerability
Classification, within the NPPF and is included within this FRA in Appendix B.
Table B.2 in Appendix B has been taken from Table 3 (Flood risk vulnerability and flood zone
compatibility) in the NPPF and demonstrates where development, based on the vulnerability
classification is suitable, unsuitable and when the Exception Test is required. In line with these
tables, the temporary railhead development classed as Less Vulnerable and is therefore
suitable for development within Flood Zone 1, 2 and 3a.
2.2 Sequential Test
NPPF states that the Sequential Test should be carried out when allocating land for
development to demonstrate that there are no sites available for development in areas that are
at a lower risk from flooding. When an area is at risk from either fluvial or coastal flooding then
development should be allocated outside Flood Zones 2 and 3 where possible. However if there
are no reasonable sites for development within Flood Zone 1 then depending upon flood
vulnerability, proposed development sites could be allocated in Flood Zones 2 or 3. The
Sequential Test should be based on flood risk maps provided in a SFRA in preference to the
Environment Agency Flood Zone mapping in line with NPPF.
The proposed site for the Crossrail Plumstead Sidings has been allocated in the Unitary
Development Plan (UDP) reference (DIA3) for development under the LDP and recognised in
the SFRA as a site for development, therefore it can be concluded that this site has passed the
Sequential test. Appendix C provides the site Developer Guidance from the SFRA.
2.3 Exception Test
The SFRA, states that 52% of the identified site (DIA3) lies within Flood Zone 3a and is
appropriate for ‘Less Vulnerable’ developments (see Appendix C), 17% in Flood Zone 2 and
31% within Flood Zone 1. As per Table 3 in the NPPF, the site will not require an Exception
Test.
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Page 14 of 25 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System © Crossrail Limited UNCLASSIFIED
3. Assessment of Flood Risk
3.1 Overview
It is outlined within the accompanying technical guidance of NPPF (paragraph 9) that flood risk
from all sources must be addressed within the FRA to ensure that potential flood risk has been
considered during the development design and proposed works. Therefore this section outlines
all the potential sources of flood risk to the site and the implications these risks have on
development. It is also necessary to outline any records of previous flooding events as these
may identify areas vulnerable to flooding.
The topographical levels resulting from the Temporary Development will remain unaltered.
Based on these topographical levels the existing ground (as per the temporary railhead) will
vary between 3.7 metres above Ordnance Datum (mAOD) and 5.6mAOD. The ground level to
the north east of the site is higher than the ground to the south of the site. The site lies within an
area of general flat topography although it appears to have several raised or mounded areas.
Recent development in the vicinity of the site has altered ground levels in the area, for example
the current Crossrail Plumstead Portal construction work at the south west end of the site,
where the ground levels vary between 4mOD and 6mOD (Crossrail - C122-OVE, May 2012).
3.2 Historical Incidents of Flooding
Both the Environment Agency and the SFRA state that the site experienced tidal flooding in
1953. Appendix A.4 shows the historic flood extent for this event. As highlighted in the SFRA
and on Map 5 of the SFRA (Appendix D), Plumstead has previously had one incident of
groundwater flooding, in February 2001. The flooding did not occur on the site of the Proposed
Development. In addition, localised flooding of the Seven Acre Sports Club pitches and the
adjoining allotments occurred from mid 2012 until early 2013. Independent studies
commissioned by Crossrail, the Environment Agency and Thames Water were inconclusive as
to the source of the flooding. Surface water flooding also occurs on the Marmadon Road which
lies adjacent to the southern boundary of the site. The SFRA and the Environment Agency do
not refer to any further flooding from any source either on the site of Proposed Development or
adjacent to it.
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Page 15 of 25 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System © Crossrail Limited UNCLASSIFIED
3.3 Fluvial Flood Risk
There are no fluvial flood sources on the site of the Proposed Development. Therefore risk from
fluvial flooding is negligible.
3.4 Tidal Flood Risk
The site is located within an area benefitting from defences and within Flood Zone 3. The site is
at risk of tidal flooding from the River Thames. However the River Thames is very heavily
defended and the Environment Agency inspects the flood defences twice yearly. Whilst the
Thames flood defences can be maintained, the residual risk of overtopping or a breach of the
defence cannot be eliminated entirely. However, appropriate warning and mitigation can be
developed.
The Environment Agency has provided hydraulically modelled river levels for various scenarios
as part of this assessment (see Appendix A.4). The 1% AEP modelled present day level for the
modelled node closest to the site is 5.97mAOD and 6.63mAOD for the 0.1% AEP. The site has
a range in level from 3.7mAOD to 5.6mAOD. The Thames Flood Defences in relation to this site
provide a standard of protection for the 0.1% AEP and are maintained to a crest level of
7.20mAOD. This remains valid until the year 2070, at which point the standard of protection will
begin to decrease, the Thames Estuary 2100 project has studied options to manage flood risk in
the Thames Estuary up to the year of 2100 (Environment Agency, May 2012).
The SFRA and the Tunnel Flood Protection Strategy (Crossrail, 2008) have developed various
breaching and overtopping scenarios for both the site and the wider area through 2d hydraulic
modelling. Both the SFRA and Crossrail breach models have been developed in consultation
with the Environment Agency.
Flood Inundation Mapping
The same breach points have been used to develop breaching and overtopping scenarios in
both the Tunnel Flood Protection Strategy (Crossrail, 2008) and the SFRA. It is assumed that as
both models were carried out in consultation with the Environment Agency, that the breach
locations are deemed as fit for overtopping and breach modelling purposes by the Environment
Agency. The mapped output provides a good indication of flood inundation mapping for the site
of the Proposed Development (see maps 13 and 14 of the SFRA) (Appendix D).
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Page 16 of 25 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System © Crossrail Limited UNCLASSIFIED
For the purposes of the 2d hydraulic modelling the site lies within the East Greenwich
Embayment, also known as Thamesmead (Crossrail, 2008). This document will refer to the area
of 2d hydraulic modelling as the East Greenwich Embayment.
The East Greenwich Embayment has a major division across the embayment site due to the
embanked Southern Outfall Sewer (SOS). The SOS embankments mean that there are only
two flow routes from which water can flow from a north to south direction, one of these flow
connections is located at Plumstead Station and is known as the Plumstead Portal and the
other is from the South Mere culvert located to the east of the temporary railhead site.
The South Mere culvert flood conveyance does not affect the Plumstead Crossrail Sidings site
due to the dismantled railway (which lies to the eastern edge of the site) acting as an
embankment stopping flood conveyance flows from reaching the site.
It is at the Plumstead Portal that there is highest risk of inundation in the absence of mitigation.
The Plumstead Portal lies on the edge of the site proposed for development. Map 14 from the
SFRA (Appendix D) shows that the Plumstead Portal has a maximum flood depth of 3.5mAOD
following a breach. Further detailed hydraulic modelling of a breach scenario for the Plumstead
Portal (Crossrail, 2008) located on the site, states that maximum water level of 3.29mAOD
causes flooding. This scenario is the existing situation for a 0.1% AEP and includes the
Thames Barrier and existing defences. As expected, the Plumstead Portal is also shown to
flood under future climate change conditions.
Flood Hazard Mapping
The SFRA developer guidance summary for DIA3 (Appendix C), states that the 33% of the site
lies within a high residual risk category1, 6% lies in a medium and 13% in a low residual risk
category and 48% of the site is unaffected by residual risks. However the site area that
Crossrail wish to develop upon is approximately half the size which is designated for
1 Flood Risk to People – Phase 2 FD2321/TR2 Guidance Document, DEFRA, March 2006.
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Page 17 of 25 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System © Crossrail Limited UNCLASSIFIED
development by the LDP. The site boundary suggests that a majority of the site lies outside of
the area of high residual risk.
Assessment of Tidal Flood Risk
Whilst the Environment Agency are responsible for maintaining the Thames flood defences and
the probability that a breach or overtopping scenario is low, it is still recognised by Crossrail that
appropriate steps towards mitigation and appropriate warning should be carried out. These
steps taken by Crossrail will ensure that the Crossrail network can remain safe during a breach
or overtopping scenario.
Crossrail receive flood warnings from the Environment Agency for the whole Crossrail network
and have carried out site specific assessments of flooding for various sites including the
Plumstead Portal. As part of their assessments at Plumstead Portal, the ground elevation will be
raised at the entrance to the tunnel and therefore water will be prevented (from surface and
breach / overtopping flooding) from entering the tunnel (Crossrail, 2008). The Plumstead Portal
modification has been designed to resist a flood level of 104.553mATD (=4.553mAOD) (0.5%
AEP with climate change).
Following this assessment of tidal flood risk, it can be deemed that the risk of flooding from
overtopping or breaching of the site is low and can be mitigated.
3.5 Surface Water Flood Risk
As part of the SFRA, an assessment of surface water flooding has been undertaken. The high
level maps (Maps 9 and 10 of the SFRA) (Appendix D), show that parts of the site are subject to
a greater than one metre of surface water flooding under both the 0.1% AEP and the 0.1% AEP
with climate change. The site is shown to have greatest surface water flood risk in the area of
the Plumstead Portal.
Marmadon Road, which lies adjacent to, and along the southern boundary of the site, has had
occurrences of surface water flooding. Although the details of the flooding are not known, the
assessment carried out in the SFRA corroborates this.
The existing site currently drains to ground, and there are no existing drainage plans available
for the site, as it is a derelict/vacant Brownfield site.
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Page 18 of 25 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System © Crossrail Limited UNCLASSIFIED
Appropriate mitigation methods will be adopted (see section 4.2) to ensure that surface water
flooding does impact upon the Proposed Development, as per the SFRA developer guidance
(see Appendix C).
3.6 Groundwater Flood Risk
The site lies on a minor aquifer. There is a pumping system for the canal and lake network in
the area that maintains water levels below 0mAOD (Scott Wilson, 2007). Within the vicinity of
the site, one known incident of groundwater flooding occurred in Plumstead in February 2001,
see map 5 of the SFRA (Appendix D), however there are no further details. From the
information available it can be deemed that the risk of groundwater flooding to the site is low.
3.7 Other Sources of Flood Risk
There is a major sewer that runs across the northern boundary of the site, known as the
Southern Outfall Sewer (SOS). The sewer embankment buries the pipes of the Southern Outfall
Sewer on their way to the Crossness Sewage Treatment Works. This covered sewer is owned
and maintained by Thames Water and runs from Plumstead to Crossness. The sewer is
embanked and it has not been known to breach since it was constructed (Greenwich Council,
2011). The height of the sewer is 6.5mAOD (Crossrail - C122-OVE, May 2012). The
information available shows that the risk of flooding from other sources (such as reservoir flood
risk) is low.
3.8 Climate Change
As a result of climate change, flood risk to the site is likely to increase. Table 4 of the NPPF
accompanying technical guidance, shows the predicted changes in peak intensity and sea level
rise as outlined within NPPF. These values should be considered during a detailed assessment
for the lifetime of the development. However the UK Climate Projections (UKCP09) has been
published since PPS25 and reflects predictions in relation to climate change with updated
methodologies. NPPF makes use of the same changes as outlined within NPPF and hence the
values provided in Table B.1 and B.2 of NPPF is considered appropriate for this assessment.
The Environment Agency has provided river levels for the River Thames under two climate
change scenarios; 2055 and 2107. The 0.1% AEP levels for the year 2055 are modelled as
6.94mAOD and 7.48mAOD for the year 2070. The 1% AEP for the year 2055 is modelled as
6.29mAOD and 6.81mAOD for the year 2070.
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Page 19 of 25 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System © Crossrail Limited UNCLASSIFIED
After 2070 intervention would be required to maintain the minimum standard of protection.
However the Environment Agency is working on options to manage climate change within the
Thames Estuary. The Environment Agency project to manage climate change in the Thames
estuary is known as the ‘Thames Estuary 2100’ project and has studied options to manage
flood risk in the Thames estuary up to the year 2100.
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Page 20 of 25 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System © Crossrail Limited UNCLASSIFIED
4. Mitigation of All Sources of Flood Risk
4.1 Tidal
As the site lies within an area benefitting from defences, the actual flood risk to the site is low.
Residual risks of flooding present themselves as overtopping or breaching, and whilst this is
unlikely, previous assessment from Crossrail (2008, 2009) and the SFRA has been carried out
to determine the residual risks. Rates of inundation and maximum flood depths have been
determined both at the site (Crossrail, 2009)(Crossrail, 2008) and as part of a larger study
(Greenwich Council, 2011). It is recognised that forms of overtopping and breaching cannot be
completely eliminated and steps are being taken to ensure that the site is safe.
Steps are being taken to ensure that in the event of a breach or overtopping scenario, water
cannot reach the site of the Plumstead Crossrail Sidings. One of the flow routes to the site in
such an event is the Plumstead Portal. Raised ground levels at the Plumstead Portal are
designed to stop water from entering the running tunnels and conveying water from north to
south. The SOS embankment will also act as a barrier in an overtopping or breach scenario.
The layout of the Proposed Development will retain some elements from the temporary railhead
development (see Appendix A.2). These include earthworks (including drainage, retaining wall
and slope stabilisation), meaning that the site will have a proposed mean surface level of
5.1mATD. This will provide the relatively flat land required for the development of both the
temporary railhead and permanent development of the Plumstead Crossrail Sidings. Crossrail
have put into place a set of Emergency Procedures that determine actions to be taken at
various levels of warnings from the Environment Agency (Greenwich Council, 2011). It is
recommended that the Plumstead Crossrail Sidings development receives flood warnings from
the Environment Agency during both the construction phase and operation phase of the
Proposed Development.
4.2 Surface Water
The site is classed as a brownfield site (Greenwich Council, 2011). However the proposed
drainage has been designed to meet greenfield runoff rates, therefore providing a drainage
system which offers betterment to the existing situation. The storage capacity of the proposed
drainage has been designed to ensure capacity up to a 1% AEP flood event and will be
contained within the site. It is proposed that the site will have approximately 80% hardstanding
impermeable area, an increase of over 60% impermeability. By ensuring that runoff is mitigated
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Page 21 of 25 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System © Crossrail Limited UNCLASSIFIED
down to the greenfield runoff rate, the drainage system will provide betterment and hence
ensure that surface water flood risk is decreased and managed on-site. Therefore the Proposed
Development will not increase the flood risk elsewhere (see the site specific SFRA developer
guidance (see Appendix C)).
The installation of the surface water drainage system will have been undertaken as part of the
Temporary Development in accordance with Condition 14 of the planning permission granted by
RB Greenwich (13/0300/F) which states that:
‘No development shall take place until a surface water drainage scheme for the site,
based on sustainable drainage principles and an assessment of the hydrological and
hydrogeological context of the development, has been submitted to and approved in
writing by the local planning authority. The drainage strategy should demonstrate the off-
site surface water run-off generated up to and including the 1 in 100-year plus climate
change critical storm will not exceed 30 litres per second. The scheme shall
subsequently be implemented in accordance with the approved details before the
development is completed. The scheme shall also include details of: how the scheme
shall be maintained and managed after completion; any infiltration features’.
In addition, Condition 15 of the same planning permission states that:
‘No infiltration or surface water drainage into the ground is permitted other than with the
express written consent of the Local Planning Authority, which may be given for those
parts of the site where it has been demonstrated that there is no resultant unacceptable
risk to controlled waters.’
All infiltration methods have been discounted due to the risk of ground contamination. Following
implementation of the Temporary Development, the runoff generated on site will be collected
and conveyed into the site below the ground surface water drainage network and will discharge
off site to an external receiver. Porous paving will be utilised on the proposed site car parks, and
underground attenuation tanks constructed as part of the Temporary Development will store
water that cannot be discharged under normal greenfield runoff rates.
Proposed Site Drainage Plans are detailed in Appendix A.3. The proposed site drainage plans
show that a retaining wall will be built around the site as part of the temporary railhead
development, however as the discharge will be to greenfield runoff rates, there should not be
any impact upon surface water flood risk both on site and off site as a result of the retaining
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Page 22 of 25 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System © Crossrail Limited UNCLASSIFIED
wall, as the proposed surface water drainage will provide betterment (Chapter 4, Section 4.2,
Plumstead Temporary Railhead Level 2 Flood Risk Assessment, June 2012) (Appendix L of the
Plumstead Crossrail Sidings EIA Scoping Report reproduced in Appendix 04 of the ES for the
Proposed Development (C122-OVE-T1-XST-CR148-50004)).
4.3 Groundwater
The below ground development (attenuation storage tanks and the construction of inspection
pits forming part of the Temporary Development) will need to be maintained to ensure that the
risk of groundwater flooding is not increased. Appropriate measures will also be taken to ensure
that the groundwater flood risk does not increase during the construction phase of the
Permanent Development when below ground works are being carried out.
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Page 23 of 25 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System © Crossrail Limited UNCLASSIFIED
5. Conclusions and Recommendations
5.1 Conclusions
There are a number of conclusions that can be made from this assessment, these are as
follows:
1. The Proposed Development is classed as less vulnerable in line with NPPF;
2. The site is currently located within the Environment Agency and SFRA Flood Zones 1, 2 and
3 and within an area benefitting from defences;
3. The SOS embankment acts as barrier against water conveyance should a breaching or
overtopping scenario from the tidal River Thames occur;
4. The ground elevation around the Plumstead Portal is being raised to ensure that water
cannot be conveyed to the site in the event of flooding;
5. The retaining walls and ground levels as part of the temporary railhead proposal will remain
in situ. The retaining walls ensure that no risk from surface water will be transferred to areas
adjacent to the site. Surface water flood risk will be mitigated by discharge to 25.4l/s;
6. The fluvial flood risk to the site is negligible; and
7. Groundwater flood risk is low and currently maintained via a pumping system to ensure
groundwater does not reach 0mAOD.
Paragraph 103 of the NPPF provides guidance on developments in areas at risk of flooding. It
states that:
‘When determining planning applications, local planning authorities should ensure flood risk is
not increased elsewhere and only consider development appropriate in areas at risk of flooding
where, informed by a site-specific flood risk assessment following the Sequential Test, and if
required the Exception Test, it can be demonstrated that:
within the site, the most vulnerable development is located in areas of lowest flood risk
unless there are overriding reasons to prefer a different location; and
development is appropriately flood resilient and resistant, including safe access and
escape routes where required, and that any residual risk can be safely managed,
including by emergency planning; and it gives priority to the use of sustainable drainage
systems’.
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Page 24 of 25 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System © Crossrail Limited UNCLASSIFIED
The Proposed Development meets the criteria set out in paragraph 103 in the following
respects:
The levels across the site will be re-graded as part of the Temporary Development and
these levels will remain for the Proposed Development. The more vulnerable elements
of the development (offices) will be located on those parts of the site at a higher level in
the area at lowest risk of flooding;
Crossrail will implement their emergency procedures in response to flood warnings from
the Environment Agency to ensure that safe evacuation of the site can be carried out in
the event of flooding to the site; and
The temporary railhead development will create the necessary drainage to support its
development and this drainage system will remain in place for the permanent
development. As such this will provide betterment to the existing situation of no drainage
on the site and lower the risk of flooding from surface water both to the site and to
adjacent areas, as surface water run-off is reduced.
5.2 Recommendations
It is recommended that Crossrail receive flood warnings from the Environment Agency for this
site for both the construction and operation phase of the Proposed Development.
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Page 25 of 25 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System © Crossrail Limited UNCLASSIFIED
References
Communities and Local Government. (2012). Technical Guidance to the National Planning Policy
Framework.
Crossrail. (2012). Plumstead Temporary Railhead and Associated Permanent Works Environmental
Impact Assessment (C122-OVE-T1-XST-CR148-50004)
Crossrail - C122-OVE. (May 2012). Geotechnical Report - Desktop Study.
Crossrail. (2009). Flood Protection Strategy Report (CR-EG-CTS-CE-RT-00023).
Crossrail. (2008). Tunnel Flood Protection Strategy - Fluvial Modelling (CR-DV-PRW-X-SR-00020).
Department for Communities and Local Government. (2010). Planning Policy Statement 25: Development
and Flood Risk.
Environment Agency. (May 2012). KSL120417KR66_P4 Response.
Greenwich Council. (2011). Strategic Flood Risk Assessment.
Scott Wilson. (2007). Flood Risk Assessment - Project Harry, Thamesmead, Lodon.
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Document uncontrolled once printed. All controlled documents are saved on the CRL Document System
© Crossrail Limited UNCLASSIFIED
Appendices
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Document uncontrolled once printed. All controlled documents are saved on the CRL Document System
© Crossrail Limited UNCLASSIFIED
Appendix A.1 Proposed Development Site Boundary
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Document uncontrolled once printed. All controlled documents are saved on the CRL Document System
© Crossrail Limited UNCLASSIFIED
RE
ST
RIC
TE
D
TWAO Order Boundary
Plumstead Crossrail Depot
TWAO Application GRE/2/9
1:1250
Ove Arup & Partners Limited
Woolwich to Abbey Wood
C122-OVE-T-DDA-CR148_Z-82102
HD
S4
Bored Tunnels (Alignment and Track)
---
-
0 50m25m25m 75m 100m 125m
1:1250
TWAO Order Boundary
TWAO Application
N
' Crown copyright and database rights 2012 Ordnance Survey 100035971
H.DADE
P01
P01
K.MULLINS
KM11/10/2013
B.STRAW
BS
Fit for auth
orisation
www.crossrail.co.uk
Rev :
E14 5LQ
London
Canary Wharf
25 Canada Square
Crossrail Limited
Notes
Originator :
Location :
Scale : Drawing and CAD file No :
Title :
Suitability :
DateRev. Description By Chkd App
' Crossrail
Co
py
Ap
pr
ove
d f
or
Desi
gn -
Create
d:
12-
OC
T-
20
13
By :
Auth :
Contract :
@ A1
Chk :
App :
Auth
182
1.2mCHURCH MANOR WAY
216
180
150
142
162
172
180
Posts
El Sub Sta
65.4
Sienna
Mast
1.4m
CH
UR
CH M
AN
OR W
AY
CR
Ward B
dy
1.2m
El Sub Sta
188
CHURCH MANOR WAY
1.7m
232
118
Sports Ground
242
128
St Thomas A Becket Primary School
250
136
1.6m
St Paul’s AcademyAllotment Gardens
13
117
127
133
14
MO
TTIS
FO
NT R
OA
D
13
115
105
BIRKDALE ROAD
101
25
99
26
93 97
91
185
232
238
Pavilion
139
193
CH
UR
CH M
AN
OR
WA
Y
66
2.2m
3.2m
Letter Box
80
82
88
Foot Bridge
1
100
2
110
116
1
131
135
129
2719
2125
64
214
26
Ps
1
65
Ps
Sienna
5
Ps
3
Ps
Posts
202
2.1m
175
214
Sub Sta
El
Tennis Courts
226 228
183
120
1.9m
101115
132
MARMADON ROAD
127
El Sub Sta
142
2.0m
139
Dis
mantle
d Railw
ay
154
Bowling Green
Shelter
Pool
Paddling
Playground
Tennis Court
153
WHIT
E H
ART
AVEN
UE
PCs
166
2.1m
155
Plumstead Gardens
178
165
190
Pond
Sports Ground
FB
Shelter
Pond
67 to 70
El Sub Sta
CB
Tanks
Ps
65
7
Ridgew
ayWorksPPa
th
8
Ward B
dy
Southern O
utfall S
ewers
(high and lo
w lev
el)
Works
10
6
6 KELLNER
ROAD
108
37
4 9
1
WorksTank
55
Und
El S
ub Sta
55
126b
119 to 121
1
Works 55Works
Works12
6
7
77
77a
79
79a
81
81a
83
83a
85
85a
87
87a
89
89a
91
91a
93 95c
93a
95
95a
97
97a
99
99a
95b
SL
MP 10.5
WHITE HART AVENUE
El Sub Sta
Centre
Community
Trac
k
Path
HY
LT
ON S
TR
EE
T
20
56
14
13
BA
LG
OW
AN S
TR
EE
T
13
68
30
23
26
21
Sub Sta
El
82 3
5
40110
40
2.3m
71
71a
73a
75
75a73
97
105
115
75
63
65
2
117
70
133
1
82
49
92
104
MARMADON
ROAD
59 63
77
77a
79
79a
81
BA
NN
OC
KB
UR
N R
OA
D
81a
83
83a
85
85a
87
87a
89
BARTH MEWS
69125
69a
6
El Sub Sta
SL
El Sub Sta
WB
Builder’s Yard
Depot
Tanks
NORTH ROAD
Timber Yard
Timber Yard
FactoryPath
UndRi
dgew
ay
El Sub StaCB
South
ern O
utfall Sew
ers(hi
gh an
d low le
vel)
El Sub Sta
Trac
k
Ward B
dy
Path
Ridgew
ay
CBNATHAN
WAY
67 to 69
Works
Sub Sta
El
14
92
78
123
149
137
127
125a
WHIT
E H
AR
T R
OA
D
21
31
(SA)
Memorial Hall
50
Gordon
26
36
45
55
41
37
44
49
35
4
95
43
29
85
31
67
36
67a 69
1a
Cottages
Rose
46
13
1
BA
TES
ON S
TR
EE
T
81
4
28
1
56
REIDHAVEN ROAD
El Sub Sta
93
GUNNING STREET
66
21
7
101
92a
76
111
20
14
12
BO
UG
HT
ON R
OA
D
Crown Industrial Park
2
75 to 9
9
101
103
109
LB
115
El Sub Sta
MP 10.25
Ward Bd
y
Path
Ridgew
ay
Works
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Document uncontrolled once printed. All controlled documents are saved on the CRL Document System
© Crossrail Limited UNCLASSIFIED
Appendix A.2 Baseline Site Layout Plan Following Temporary Development
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Document uncontrolled once printed. All controlled documents are saved on the CRL Document System
© Crossrail Limited UNCLASSIFIED
www.crossrail.co.uk
Rev :
E14 5LQ
London
Canary Wharf
25 Canada Square
Crossrail Limited
Notes
Originator :
Location :
Scale : Drawing and CAD file No :
Title :
Suitability :
DateRev. Description By Chkd App
' Crossrail
Co
py
Ap
pr
ove
d f
or
Desi
gn -
Create
d:
02-
MA
Y-
20
13
By :
Auth :
Contract :
@ A1
Chk :
App :
Auth
226 228
183
129
131
MARMADON ROAD
61
142
2.0m
73
154
Shelter
Pool
Paddling
Playground
PCs
166
85
Plumstead Gardens
178
97
190
Pond
FB
Shelter
Pond
202
109
214
119
3945
2 4929
21
2a
11
9
2b
2c
1
2
HY
LT
ON S
TR
EE
T
1
20
14
13
BA
LG
OW
AN S
TR
EE
T
13
30
23
26
21
Sub Sta
El
35
40
40 120
132
2.3m
1.9m
77
77a
79
79a
81
81a
83
83a
85
85a
87
87a
89
89a
91
5
Ps
3
Ps
Posts
67 to 70
El Sub Sta
Ps
Ps
65
7
PSienna
Ps
1
65
91a
93 95c
93a
95
95a
2.1m101
97
97a
99
99a
95b 115127 2.1m
139153
155
175
165
SL
MP 10.5Sub Sta
El
Tennis Court
Tennis Courts
Bowling Green
El Sub Sta Dis
mantle
d Railw
ay
Sports Ground
El Sub Sta
WHIT
E H
ART
AVEN
UE
6
El Sub Sta
SL
El Sub Sta
WB
Builder’s Yard
Depot
Tanks
NORTH ROAD
WHITE HART AVENUE
Timber Yard
Timber Yard
FactoryPath
UndRi
dgew
ay
El Sub StaCB
South
ern O
utfall Sew
ers(hi
gh an
d low le
vel)
El Sub Sta
CentreTrac
kCommunity
Ward B
dy
Path
Ridgew
ay
CBNATHAN
WAY
67 to 69
Trac
k
SL
MP 10.25
Southern O
utfall S
ewers(High and Low Level)
Ward Bd
yCF
Path
NATHAN W
AY Ridgew
ay
Works
Works
Works
117
133
1
82
49
92
104
MARMADON
ROAD
59 63
77
77a
79
79a
81
81a
83
83a
85
69
85a
87
87a
89
69a
71
71a
68
73
73a
75
82
75a
Richard NeveHouse
49
47
51
14
28
21
31
67
36
67a 69
1a
Cottages
Rose
46
13
1
81
4
1
56
REIDHAVEN ROAD
El Sub Sta
93
66
7
101
92a
76
111
92
78
123
149
137
127
125a
125
31
(SA)
Memorial Hall
50
Gordon
36
45
41
37
44
35
4
95
85
97
BARTH MEWS
105
115
75
65
2
58
59
ABERY STREET
63a
201
TCB
8
1
2a
2 7
BA
TES
ON S
TR
EE
T
21
11
28
GUNNING STREET
HE
VE
RH
AM R
OA
D
21
7
49
27
13
43
29
47
BA
RT
H R
OA
D63
Posts
68
70
BROOKDENE ROAD
Hall
BA
NN
OC
KB
UR
N R
OA
D
42
44
56
2
1
15
14
3.8m
42
161
WHIT
E H
AR
T R
OA
D
2
21
14
26
HARTVILLE ROAD
15
1
26
55
3.3m
28
Letter Box
66
1
238
80
2322
CH
UR
CH M
AN
OR
WA
Y
2.2m
193
82
1185
881
39
Foot Bridge3.2m
100
50
1
2.0m
64
2
Posts
65.4
Sienna
110
116
Pavilion
1.7m
118
Sports Ground
128
1.6m
Allotment Gardens
95.0
100.0
105.0
110.0
115.0
95.0
100.0
105.0
110.0
115.0
RE
ST
RIC
TE
D
1:1250
Ove Arup & Partners Limited
Woolwich to Abbey Wood
C122-OVE-T-DDA-CR148_Z-81134
S4
Bored Tunnels (Alignment and Track)
---
-
-
0 50m25m25m 75m 100m 125m
1:1250
Sub-station access road
Plumstead Portal
Scale 1 : 500
Scale 1 : 500
Elevation 1- Reinforced Earth Retaining Wall
Proposed site level
Existing site level at boundary
Reinforced earth retaining wall
Proposed site levelReinforced earth retaining wall
Retaining wall
of wall.
fencing, 2.4m tall above top
High security welded mesh
wall.
mesh infill, 2m tall above top of
Pedestrian parapet with welded
welded mesh fencing.
2.4m tall, high security
C122-OVE-T-DDA-CR148_Z-88103
(for details refer to
Transformer Building
welded mesh fencing.
2.4m tall, high security
entrance/exit
Main vehicular
mesh fencing.
aperture welded
2m tall, large
Retaining Wall
future development.
The site will be cleared of all buildings and materials, and fully secured pending3.
all other internal vehicular circulation areas will be disused.
The vehicular access road to the Transformer Building will remain operational,2.
fencing and vehicular entrances and exits to remain in-situ.
All earthtworks, retaining walls, surface water drainage, utilities, perimeter security 1.
Existing site level at boundary
1
-
2
-
remain.
Headshunt to
SD01/05/2013 Environmental Scoping Appendix
(subject to design)
vehicular access
Secondary
Application boundary
Legend
Crossrail Plumstead Depot
Gabion retaining wall
Elevation 2 - Gabion and Reinforced Retaining Wall
Temporary Railhead Use
Baseline Site Layout Plan Following
sidings to remain.
Formation for stabling
to remain
Reception road
P01
P01
K.MULLINS
KM
S.DENHAM
B.STRAW
BS
Fit for auth
orisation
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Document uncontrolled once printed. All controlled documents are saved on the CRL Document System
© Crossrail Limited UNCLASSIFIED
Appendix A.3 Drainage Plans
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Document uncontrolled once printed. All controlled documents are saved on the CRL Document System
© Crossrail Limited UNCLASSIFIED
www.crossrail.co.uk
Rev :
E14 5LQ
London
Canary Wharf
25 Canada Square
Crossrail Limited
Notes
Originator :
Location :
Scale : Drawing and CAD file No :
Title :
Suitability :
DateRev. Description By Chkd App
' Crossrail
Co
py
Ap
pr
ove
d f
or
Desi
gn -
Create
d:
01-
OC
T-
20
12
By :
Auth :
Contract :
@ A1
Chk :
App :
Auth
Ps
Ps
Dismantled Railway
WHITE HART AVENUE
P
23+000
23+050
23+100
23+150
23+200
23+050
23+200
23+150
23+000
23+000
23+050
23+100
23+150
23+200
RG
RG
RG
RG
RG
RG
RG
TG
TG
Ø225
Ø150
Ø 150
Ø 150
89a
83a
87a
85a
85
89
87
MP 10.5
2.3m
WHITE HART AVENUE
Dismantled Railway
6.5m x 3m
A
LV Room
4.3m x 5m
A
Transformer
4.5m x 5m
A
HV Room
4.7m x 3m
Store
Comms/
4.5m x 5m
B
HV Room
6.5m x 3m
B
LV Room
4.3m x 5m
B
Transformer
9m2Office
Manager’s
M1.02
2.5m2W.C
M1.05
5m2Corr.
M1.03
48m2Store
M1.07 48m2Store
M1.08
13.5m2Store
M1.13
m2700 Shed
Maintenance
M1.01
m24
PointM1.04Tea
m211
PlantM1.09 6.5m2
RoomCommsM1.10
7.5m2RoomFMLV M1.11
6.5m2RoomLV
M1.12
9m2Store
M1.15
17m2Stair Ext.
M1.14
m246.5
WorkshopM1.06
RG
RG
RG
RG
RG
RG
RGR
G
RG
RG
RG
Ø450
Ø 300
Ø450
Ø 450
Ø300
Ø 225
Ø225
Ø 450
Ø 450
Ø 250
Ø 225
Ø 225
Ø 250
Ø 450
Ø 250
Ø 150
Ø 450
Ø 225
Ø 250
Ø 300
Ø 250
Ø 250
Ø 150
Ø250
Ø 250
Ø300
Ø 300
Ø 150
Ø 300
Ø150
Ø300
Ø 300
Ø 300
Ø 300
Ø 300
Ø 300
Ø 300
Ø 150
Ø 300
Ø750
Ø450
Ø150
Ø750Ø750
Ø225
Ø150
Ø 225
Ø 225
Ø750
Ø225
Ø225
Ø 750
Ø150
RG
RG
RG
RG
RGRG
RG
RG
RG
RG
RG
RG
RG
RG
RG
RG
RG
RE
RE
RE
RE
Ø450
Ø150
RE
Ø300
Ø300
Ø300
Ø 150
Ø 150
Ø 150
Ø 150
Ø 150
Ø 150
Ø 150
Ø 150
Ø 150
Ø 300
Ø225
Ø150
Ø150
Ø 150
Ø 150
Ø250
Ø225
Ø300
Ø 150
Ø 150
Ø 150
Ø 150
Ø225
Ø 150
Ø 225
RG
RG
RG
RG
RG
RG
RG
RE
RE
RE
RE
RE
RE
RE
RE
RE
Ø 150
TG
TG
TG
TG
TG
TG
TG
TG
TG
TG
TG
TG
TG
TG
TG
TG
DP
DP
Ø225
Ø 225
Ø 225
Ø 225
Ø 225
Ø150
Ø150 Ø150
Ø150 Ø150
Ø150Ø 150
Ø225
Ø225
RE
ST
RIC
TE
D
Ove Arup & Partners Limited
Woolwich to Abbey Wood
C122-OVE-T-DDA-CR148_Z-82104
S4
Bored Tunnels (Alignment and Track)
---
-
-
N
Legend
Plumstead Temporary Railhead
TCPA Planning Submission GRE/2/8
Drainage Plan
Red line site boundary
Foul water
Surface water
discharge to be agreed with Thames Water.
1. Level of flow control and attenuation of surface water
N
into Thames Water Sewer
Foul Water discharge
Interceptor tank
Interceptor tank
Interceptor tank
into Thames Water Sewer
Foul Water discharge
Rainwater Harvesting Tank
into Thames Water sewer
Surface water discharge
For continuation see a
bove
For c
ontin
uatio
n see b
elo
w
RMNDMCFirst Issue04/07/2012P01
---
P02
1:5000Scale 1:500
10m 10m 20m 30m 40m 50mSD28/09/2012
S.DENHAM
P02
P02
D.WILSON
DW
R.MCCRAE
RM
Fit for auth
orisation
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Document uncontrolled once printed. All controlled documents are saved on the CRL Document System
© Crossrail Limited UNCLASSIFIED
Appendix A.4 Environment Agency Flood Maps and Flood Risk Data
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Document uncontrolled once printed. All controlled documents are saved on the CRL Document System
© Crossrail Limited UNCLASSIFIED
Our ref: KSL120417KR66Date: 20 April 2012
Please note:
http://www.environment-agency.gov.uk/research/planning/33580.aspx
Ordnance Survey 1: 25 000 colour raster base mapping;Flood Zone 2 and Flood Zone 3;Relevant model node locations and unique identifiers (for cross referencing to the water levels, depths and flows table);
A table showing:
Model(s) extents;FRA site boundary (where a suitable GIS layer is supplied);Flood defence locations (where available/relevant) and unique identifiers; (supplied separately)
iv) local flood history data (where available/relevant).
This letter is not a Flood Risk Assessment. The information supplied can be used to form part of your Flood Risk Assessment. Further advice and guidance regarding Flood Risk Assessments can be found on our website at
Product 4 is designed for developers where Flood Risk Standing Advice FRA (Flood Risk Assessment) Guidance Note 3 i) "all applications in Flood Zone 3, other than non-domestic extensions less than 250 sq metres; and all domestic extensions", and
If you would like advice from us regarding your development proposals you can complete our pre application enquiry form which can be found at
Flood Map areas benefiting from defences (where available/relevant);
http://www.environment-agency.gov.uk/research/planning/82584.aspx
ii) Flood defence locations unique identifiers and attributes; (supplied separately)iii) Historic flood events outlines unique identifiers and attributes; and
Statutory (Sealed) Main River (where available within map extents);
Plumstead Railway Sidings, SE28
i) model node X/Y coordinate locations, unique identifiers, levels, flows and JFLOW depths;
This information is based on that currently available as of the date of this letter. You may feel it is appropriate to contact our office at regular intervals, to check whether any amendments/ improvements have been made. Should you re-contact us after a period of time, please quote the above reference in order to help us deal with your query.
If you will be carrying out computer modelling as part of your Flood Risk Assessment, please read the enclosed guidance which sets out our requirements and best practice for computer river modelling.
This information is provided subject to the enclosed notice which you should read.
ii) "all applications with a site area greater than 1 ha" in Flood Zone 2.
Product 4 (Detailed Flood Risk) for
Product 4 includes the following information:
Flood Map flood storage areas (where available/relevant);Historic flood events outlines (where available/relevant, not the Historic Flood Map) and unique identifiers;
Thames Barrier, Eastmoor Street, Charlton, London, SE7 8LXCustomer services line: 03708 506 506Email: [email protected] www.environment-agency.gov.uk
Modelled in-channel levels KSL120417KR66
Year10% 5% 2% 1% 0.5% 0.2% 0.1%
2005 5.35 5.55 5.82 6.04 6.26 6.53 6.732055 5.77 5.96 6.19 6.38 6.58 6.84 7.042107 6.39 6.54 6.75 6.92 7.11 7.39 7.60
Year10% 5% 2% 1% 0.5% 0.2% 0.1%
2005 5.32 5.51 5.76 5.97 6.17 6.43 6.632055 5.71 5.88 6.11 6.29 6.48 6.74 6.942107 6.30 6.45 6.65 6.81 6.99 7.27 7.48
Year10% 5% 2% 1% 0.5% 0.2% 0.1%
2005 5.31 5.50 5.75 5.95 6.15 6.41 6.612055 5.70 5.87 6.09 6.26 6.45 6.71 6.912107 6.28 6.42 6.63 6.79 6.98 7.25 7.46
Modelled water levels in the Thames for locations close to your site are shown in the tables below. All levels are provided in metres above Ordnance Datum Newlyn (mAODN). In modelling the levels, three main factors were considered; the astronomical tide, the surge tide and the flow coming from the non-tidal Thames. The location, or node, closest to your site is 3.04.
Annual Probability of Occurrence
Grid ref: TQ 41634 79577Location node 3.01
Annual Probability of Occurrence
Annual Probability of Occurrence
Modelled River Levels (mAODN)
Grid ref: TQ 44419 80001Location node 3.04
Modelled River Levels (mAODN)Location node 3.05Grid ref: TQ 45694 81290
Modelled River Levels (mAODN)
Thames Barrier, Eastmoor Street, Charlton, London, SE7 8LXCustomer services line: 03708 506 506Email: [email protected] www.environment-agency.gov.uk
Model notes KSL120417KR66
Model: Tidal Thames Joint Probability Extreme Water Levels 2008Date of creation: 12 May 2008
Notes: Our water levels are created from a 2-D joint-probability computer hydraulic model. As this is a joint-probability model the confluence of different factors such as astronomical tides, tide surge and river flows have been taken into account. In summary, the calculation of extreme water levels involves two main stages: 1) Estimating a matrix of water levels at various locations (or model nodes) along the estuary 2) Calculating the statistical frequency (return period) with which a particular water level might be expected to occur at each of the model nodes.
Climate change allowances:
This study modelled water levels to various annual probabilities (10%, 5%, 2%, 1%, 0.5%, 0.2% and 0.1%). Each of these probabilities have been modelled for present day (2005) and future years (2055 and 2107) taking into account DEFRA's climate change allowances as set out in the Planning Policy Statement 25 (PPS25).
Some of the levels are lower for the more extreme probabilities when including climate change because the hydraulic model used to produce these levels takes into account the Thames Barrier closure rule (circumstances/conditions of closure) and assumes that it remains unchanged up to 2107. Increased sea levels and fresh water flows mean that the Thames Barrier closure rule will be met more often. This means that a smaller number of tides will be allowed to flow up into central London each year. The highest tides experienced upstream of the Thames Barrier occur when the circumstances are within a fine margin of meeting the closure rule, and the decision is taken not to close (a near closure event). As there will be fewer tides per year upstream of the Barrier, and the ratio of near closure levels to regular tidal levels within this smaller number of tides remains constant, the number of near closure events will decrease, and therefore so do the modelled levels.
Thames Barrier, Eastmoor Street, Charlton, London, SE7 8LXCustomer services line: 03708 506 506Email: [email protected] www.environment-agency.gov.uk
Historic flood data KSL120417KR66Our records show that the area of your site has been affected by tidal flooding. Information on floods that have affected areas near your site is provided in the table below, and is shown on the attached map:
Historic Flood Events Unique ID Flood Event Code Flood Event Name Start Date End Date Source of Flooding Cause of Flooding
EA0619530300005 EA061953 TTD_FEO_1953 31/01/1953 01/02/1953 Tidal River Thames Overtopping and Breach of defence
Extra historic flood information:
Our records show that the area of your site has been affected by tidal flooding.
The site was subject to tidal flooding, due to a storm surge in the North Sea, on the night of the 31st January into the morning of 1st February 1953. An approximate level in the Thames at the time was 5.16 m AODN.
Please note the Environment Agency maps flooding to land not individual properties. Floodplain extents are an indication of the geographical extent of a historic flood. They do not provide information regarding levels of individual properties, nor do they imply that a property has flooded internally.
Thames Barrier, Eastmoor Street, Charlton, London, SE7 8LXCustomer services line: 03708 506 506Email: [email protected] www.environment-agency.gov.uk
Flood Defences KSL120417KR66General description:
The river Thames defences along this section of the river provide a standard of protection of 1 in 1000. This means that the defences protect against a tidal flooding event that has a 0.1% annual probability of occurring. This remains true up to the year 2070. After 2070 the standard of protection will decrease over time. However the Thames Estuary 2100 project has studied options to manage flood risk in the Thames estuary up to the year 2100. Public consultation of this study has finished, but you can access all the information here: http://www.environment-agency.gov.uk/research/library/consultations/106100.aspx
The defences along the tidal Thames in this area are all raised, man-made and privately owned. We inspect them twice a year to ensure that they remain fit for purpose. They must be maintained by their owners to a crest level of 7.10 m AODN downriver of Broadwater Dock and 7.20 m AODN upriver of Broadwater Dock (the Flood Defence Level in this reach of the Thames). The overall condition grade for defences in the area is 2 (good), on a scale of 1 (very good) to 5 (very poor).
Standard of protection provided by the tidal defences
Additional Notes
Thames Barrier, Eastmoor Street, Charlton, London, SE7 8LXCustomer services line: 03708 506 506Email: [email protected] www.environment-agency.gov.uk
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Rev 2.0. Submission Ref. GRE/2/9
Document uncontrolled once printed. All controlled documents are saved on the CRL Document System
© Crossrail Limited UNCLASSIFIED
Appendix B NPPF – Policy Tables
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Rev 2.0. Submission Ref. GRE/2/9
Document uncontrolled once printed. All controlled documents are saved on the CRL Document System
© Crossrail Limited UNCLASSIFIED
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Rev 2.0. Submission Ref. GRE/2/9
Document uncontrolled once printed. All controlled documents are saved on the CRL Document System
© Crossrail Limited UNCLASSIFIED
NPPF – Policy Tables
Flood Risk Vulnerability Classification
Land Use Vulnerability Type of Development
Essential Infrastructure Essential transport infrastructure (including mass evacuation routes) which has to cross the area at risk
Essential utility infrastructure, which has to be located in a flood risk area for operational reasons, including electricity generating power stations and grid and primary substations; and water treatment works that need to remain operational in times of flood.
Wind turbines.
Highly Vulnerable Police Stations, Ambulance Stations and Fire stations, Command Centres and telecommunications installations required to be operational during flooding.
Emergency dispersal points.
Basement dwellings.
Caravans, mobile homes and park homes intended for permanent residential use.
Installations requiring hazardous substances consent.
More Vulnerable Hospitals.
Residential institutions such as care homes, children’s homes, social services homes, prisons and hostels.
Buildings used for: dwelling houses; student halls of residence; drinking establishments; nightclubs and hotels.
Non-residential uses for health services, nurseries and educational establishments.
Landfill and sites used for waste management facilities for hazardous waste.
Sites used for holiday or short let caravans and camping, subject to specific warning and evacuation plans.
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Document uncontrolled once printed. All controlled documents are saved on the CRL Document System
© Crossrail Limited UNCLASSIFIED
Land Use Vulnerability Type of Development
Less Vulnerable Police Stations, Ambulance Stations and Fire stations which are not required to be operational during flooding.
Buildings used for: shops, financial, professional and other services; restaurants and cafes, hot food takeaways; offices; general industry; storage and distribution; non-residential institutions not included in ‘more vulnerable’; and assembly and leisure.
Land and buildings used for agriculture and forestry.
Waste treatment (except for landfill and hazardous waste facilities).
Minerals working and processing (except for sand and gravel working).
Water treatment plants which do not need to remain operational during times of flood.
Sewage treatment plants (if adequate pollution control measures in place).
Water Compatible Development
Flood control infrastructure.
Water transmission infrastructure and pumping stations.
Sewage transmission infrastructure and pumping stations.
Sand and Gravel workings.
Docks, Marinas and Wharves.
Navigation facilities.
MOD installations.
Shipbuilding, repairing and dismantling, dockside fish processing and refrigeration and compatible activities requiring a waterside location.
Water based recreation (excluding sleeping accommodation).
Lifeguard and coastguard operations.
Amenity open space, nature conservation and biodiversity, outdoor sports and recreation and essential facilities such as changing rooms.
Essential ancillary sleeping or residential accommodation for staff required by uses in this category, subject to specific warning and evacuation plans.
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Document uncontrolled once printed. All controlled documents are saved on the CRL Document System
© Crossrail Limited UNCLASSIFIED
Appropriate Development for each Flood Zone
Flood Risk Vulnerability
Classification (see Table D2 of PPS25)
Essential Infrastructure
Water Compatible
Highly Vulnerable
More Vulnerable
Less Vulnerable
Flo
od Z
one
(see
Tab
le D
1 of
PP
S25
)
Zone1
Low Probability
Zone2
Medium Probability
Exception Test required
Zone 3a
High Probability
Exception Test required
x Exception Test required
Zone 3b ‘Functional Floodplain’
Exception Test required
x x x
Development is appropriate
x Development should not be permitted
Climate Change
Recommended contingency allowances for net sea level (Table from NPPF (Communities and Local Government, 2012)
Net sea level rise (mm per year) relative to 1990
1990 to 2025 2025 to 2055 2055 to 2085 2085 to 2115
East of England, east midlands, London, south-east England (south of Flamborough Head)
4.0 8.5 12.0 15.0
Recommends national precautionary sensitivity ranges for peak rainfall intensities and peak river flows (Table 5 from NPPF (Communities and Local Government, 2012)
Parameter 1990 to 2025 2025 to 2055 2055 to 2085 2085 to 2115
Peak Rainfall Intensity
+5% +10% +20% +30%
Peak River Flow +10% +20%
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Document uncontrolled once printed. All controlled documents are saved on the CRL Document System
© Crossrail Limited UNCLASSIFIED
Appendix C SFRA Developer Guidance
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Document uncontrolled once printed. All controlled documents are saved on the CRL Document System
© Crossrail Limited UNCLASSIFIED
London Borough of Greenwich: site summary and recommendations
Site Details
Site Name UPD
Reference
Site Location (OS NGR) 18.9
Proposed use
Flood risk vulnerability
classification
Less
Vulnerable
Comments
Brown/Greenfield Brownfield
Flood Risk
Flood Zone (Fluvial & Tidal)
Flood Type
3b 3a 2 1
0% 0% 0% 100%
3b 3a 2 1
0% 52% 17% 31%
Comments
Residual risk:
Defended?Yes
Maintainer:Private
Standard of
Protection:1000 years
Comments
Residual Risk Yes Comments
if yes:
High Medium Low None
33% 6% 13% 48%
Other sources of flood risk:
Susceptibility to surface water
floodingLess - More
Comments
Risk of groundwater floodingYes
Bedrock
geologySand
AquiferMinor
Comments
Effect of climate change:
Is a site specific Flood Risk Assessment required?
FRA required?
Yes
Comments
Exception test required for
proposed use?
No
Comments
Recommendations for Development
Plumstead DIA3
TQ 456 790 Site Area (ha)
Employment, Waste Treatment Facility
Based on definitions stated in PPS25 Table D2
Tidal
Percentage of site in each Fluvial
Flood Zone
Percentage of site in each Tidal
Flood Zone
Based on the Environment Agency's Flood Zones map, March 2009
Based on NFCDD data
Assessment of residual risk conducted by JBA Consulting
Percentage of site in each
Residual Risk category
Susceptibility to surface water flooding for 0.1% AEP event with
climate change is measured in three categories; less (water 0.3 -
0.6m in depth), intermediate (water 0.6 - 1m in depth) and more
(water >1m in depth).
Groundwater poses a potential threat of flooding if the site is underlain by a chalk, sand or sand
and gravel bedrock, which forms a minor or major aquifer.
Defra guidance suggests a 980mm increase of tidal peak levels over the next 100 years due to climate change. This will increase the
residual risk at this site.
A FRA is required to assess tidal flood risk and flood risk from
other sources, including surface water and groundwater.
PPS25 guidance states less vulnerable development is
appropriate in all flood zones accept Flood Zone 3b.
The proposed usage of this development is for Less Vulnerable uses. This is an appropriate usage at this location, and therefore meets
the requirements of PPS25. As the development is behind existing defences there is a high residual risk, therefore plans for this site
should consider this residual risk and ensure the development remains safe, the development should require an emergency plan be put
in place in case of a breach in the defences. Part of the site is susceptible to surface water flooding. The development should improve
the drainage infrastructure to reduce flood risk on site (see report chapter 9.8.1).
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Document uncontrolled once printed. All controlled documents are saved on the CRL Document System
© Crossrail Limited UNCLASSIFIED
Appendix D Strategic Flood Risk Assessment (SFRA) Maps
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Document uncontrolled once printed. All controlled documents are saved on the CRL Document System
© Crossrail Limited UNCLASSIFIED
Crossrail Plumstead Sidings Level 2 Flood Risk Assessment
C122-OVE-T3-RGN-CR148-50004 Submission Ref. GRE/2/9
Document uncontrolled once printed. All controlled documents are saved on the CRL Document System
© Crossrail Limited UNCLASSIFIED