Design Manual 1
-
Upload
alfonso-rodriguez-aguilar -
Category
Documents
-
view
226 -
download
1
Transcript of Design Manual 1
-
7/27/2019 Design Manual 1
1/366
REPUBLICOFYEMEN
MINISTRYOF PUBLICWORKSANDHIGHWAYS
RURALACCESSPROJECT
CENTRALMANAGEMENTOFFICE(RAPCMO)
RURALROADS
DESIGNMANUAL
ISSUED:OCTOBER 2004
REVISED FEBRUARY 2005
-
7/27/2019 Design Manual 1
2/366
REVISED: FEBRUARY 2005
-
7/27/2019 Design Manual 1
3/366
SECTION 1
INTRODUCTION
Section
1
-
7/27/2019 Design Manual 1
4/366
Rural Roads Design Manual
Section 1 - Introduction
Republic of Yemen
Ministry of Public Works and Highways
SECTION 1INTRODUCTION
TABLE OF CONTENTS
Page
1.1 Background 11.2 Objectives 21.3 Scope 21.4 Design Process 31.5 RAP Roads Design Philosophy 6
-
7/27/2019 Design Manual 1
5/366
Rural Roads Design Manual
Section 1 - Introduction
Republic of Yemen
Ministry of Public Works and Highways
SECTION 1
INTRODUCTION
1.1 BACKGROUND
Insufficient infrastructure and inadequate access to social services have
been a major deterrent to rural development in Yemen. In 1995 there was
about 64,500 km of roads, 4,800 km of them paved (about 7.5%). Many
areas are inaccessible to vehicles leaving a large sector of the populationsuffering from accessibility problems to the basic services they need. In
1996 there were 229,000 passenger cars, a ratio of 31 people per car. In
remote areas people rely principally on non-motorized transport.
The Rural Access Program initiated by the Government of Yemen with
support from the World Bank aims at improving the livelihood and
reducing the isolation of the rural population in Yemen.
To achieve this objective, the Program will improve planning and
implementation of rural roads, thereby reducing a major obstacle to rural
economic growth caused by poor access. The Program will be implemented
in three phases:
Phase I : (2001 to 2005) is setting up the institutional and technicalf d ti f l d j t Th h h b
-
7/27/2019 Design Manual 1
6/366
Rural Roads Design Manual
Section 1 - Introduction
Republic of Yemen
Ministry of Public Works and Highways
1.2 OBJECTIVES
The Ministry of Public Works and Highways Rural Access ProjectCentral Management Office (RAP-CMO) is in the process of contracting
local consultants who will be responsible for the preparation of detailed
design and supervision of construction for a number of Rural Intermediate
Roads and Village Access Roads.
As a part of the capacity building process adopted by RAP for local
consultants, RAP has undertaken to develop comprehensive standards forrural roads to serve the country in effectively developing this sector.
This Design Manual addresses the needs of road engineers and designers
for safe, economical and environmentally sound designs of rural roads and
rural intermediate roads in Yemen at the levels of the Governorate, District
as well as Village Access. These roads are typically low volume roads with
average daily traffic in the range of 100-1000 vehicles per day, located in
various types of terrain and climatic conditions prevailing in Yemen.
1.3 SCOPE
The scope of work for developing this manual included review of existing
design guidelines and standards developed previously, comments from
MPWH and RAP, field visits undertaken to various projects sites,
di i ith lt t d t t ll th k h
-
7/27/2019 Design Manual 1
7/366
Rural Roads Design Manual
Section 1 - Introduction
Republic of Yemen
Ministry of Public Works and Highways
- AASHTOGuidelines for Geometric Design of Very Low-Volume
Local Roads (ADT 400).
- National Highway and Rural Access Master Plan Study Road
Classification System, Ministry of Public Works and Highways
Yemen.
- TRL Road Note 6A Guide to Geometric Design, 1988.
- TRL Road Note 31A Guide to the Structural Design of BitumenSurfaced Roads, 1993.
- TRL Road Note 19 A guide to the design of hot mix asphalt in
tropical and sub-tropical countries, 2002.
- TRL Road Note 40A guide to axle load surveys and traffic counts
for determining traffic loading on pavements, 2004.
- World Bank The Roads Economic Decision Model (RED),
SSATP working paper No. 78, July 2004.
- World BankRoads and the Environment Handbook.
- RAPCMOSectoral Environmental Assessment, Vol. 1, 2004.
RAPCMO S l E i l A V l 2 S f d
-
7/27/2019 Design Manual 1
8/366
Rural Roads Design Manual
Section 1 - Introduction
Republic of Yemen
Ministry of Public Works and Highways
Traffic analysis ofalternative routes
Economic analysis
Environmental Screeningand Categorization
2
9
10
Project, Planning,
Prefeasibility and
Feasibility Studies
Preliminary GeometricDesign
Geotechnical Studies
EA Consultations
and Impact Analysis
3
4
10
PreliminaryDesign
Geometric Design3
Project Process ActivitiesSection of this
Manual
-
7/27/2019 Design Manual 1
9/366
Rural Roads Design Manual
Section 1 - Introduction
Republic of YemenMinistry of Public Works and Highways
DOCS-0974-04 1-5
EA
Phases EA Planning:
Project
Identification and
Project Concept
Preliminary and
Final DesignProject Tendering
Execution
Project Managementand Supervision
Project Completion
and Post Evaluation
Operation and
Maintenance
Project Cycle
Processes
Project Phases Operation &
MaintenanceConstructionProject Preparation and Design
Planning,Pre-feasibility and
Feasibility Studies
- Scoping and
Screening
- Identification of
issues and
applicable
safeguards policies.
- Categorization
- Action plan
CMO - E&S UnitResponsibilities
EA, SFA &
Consultations
- Draft EA
- Draft SFA
- Womenconsultations
- Disclosure of draft
EA and SFA to
communities
- Signing of Final
SFA
- Final version of EA
Consultant /
CMO - E&S Unit
Environmental
ContractSpecification
- Incorporation of
EMP into contract
documents
- Pre-tender briefing
CMO - E&S unit /Consultant, Districts
& Communities
Implementation and
Monitoring
- EMP
implementation
- Compliance
monitoring and
reporting on
environmental and
social mitigation
measures
Consultant /
CMO - E&S Unit
Post Evaluation
- Compliance
summary
- Unanticipated
impacts
- Lessons learned
ContractorsCMO - E&S Unit, RE
& Local Community
O & M Monitoring
- Compliance
monitoring and
reporting onenvironmental and
social mitigation
measures
ContractorsCMO - E&S Unit RE
& Local Community
EA
Activities
Figure 1.2- Integration of Environmental and Social Management Process in the Project Cycle
-
7/27/2019 Design Manual 1
10/366
Rural Roads Design Manual
Section 1 - Introduction
Republic of Yemen
Ministry of Public Works and Highways
1.5 RAP ROADS DESIGN PHILOSOPHY
The fundamental characteristics of rural roads that distinguish them fromother roads in the national network include:
- Low traffic volumes with ADT generally < 1000 vehicles per day,
with many roads having ADT 400 vpd. Such volumes of traffic
indicate that accident-prone encounters between vehicles are rare
events and the probability of collision is small.
- The rural and local access natures of these roads indicate that most
drivers using them are familiar with their nature as well as the
nature of the terrain traveled. This familiarity reduces the elements
of risk resulting from design features that may surprise unfamiliar
drivers, but are anticipated by familiar drivers.
- The nature of the mountainous terrain in Yemen makes it
economically prohibitive, or physically impossible to constructroads at the normal standards. Thus, relaxed standards are
necessary in order to ensure a cost-effective approach to the road
system. Relaxation of standards apply especially for roads in
difficult mountainous terrain and for road projects involving
existing tracks or existing alignments where full reconstruction is
economically unjustified. Thus the designer is encouraged to relax
the standards to avoid unnecessary improvement on existing
li b l l k f id f i ifi f
-
7/27/2019 Design Manual 1
11/366
Rural Roads Design Manual
Section 1 - Introduction
Republic of Yemen
Ministry of Public Works and Highways
safety conservative and risk-averse, providing a margin of safety that takes
into consideration a wide range of conditions that might occur on the road
system. They are not based on rigorous cost-effectiveness approach, buthave established values that are judged to be reasonable and prudent, given
overall costs, impacts, and benefits.
The design guidelines for very low-volume roads developed by AASHTO
are based on safety risk assessment which results in comparable margins of
safety presented in the AASHTO Policy on Geometric Design of
Highways and Streets for higher volume roads.
For rural low volume roads the design criteria should be based on tradeoffs
between, on one hand, differences in construction and maintenance costs,
and estimated impacts on safety. This makes cost-effectiveness as the
appropriate basis for defining minimum design criteria or values for low
volume rural roads.
This Manual is prepared to be a fairly comprehensive document and tocover all the important elements of rural road designs encountered by
RAP. Yet, no manual can supersede good engineering judgment and
the application of sound principles by knowledgeable designers who
can tackle unique and often conflicting design requirements and
develop tailored solutions to specific design problems.
-
7/27/2019 Design Manual 1
12/366
SECTION 2
ROAD CLASSES, DESIGN SPEED
AND TRAFFIC
Section
2
-
7/27/2019 Design Manual 1
13/366
Rural Roads Design Manual
Section 2 - Road Classes, Design Speed and Traffic
Republic of Yemen
Ministry of Public Works and Highways
SECTION 2ROAD CLASSES,DESIGN SPEED AND TRAFFIC
TABLE OF CONTENTS
Page
2.1 Introduction 12.2 Road Classes 12.2.1 Roads Functional Classification 12.2.2 RAP Roads Design Classes 42.3 Design Speed 62.3.1 Design Speed Criteria 62.3.2 Design Speed Standards 72.3.3 Relaxation of Standards 72.4 Traffic 102.4.1 Design Life 102 4 2
B li T ffi Fl E ti ti 11
-
7/27/2019 Design Manual 1
14/366
Rural Roads Design Manual
Section 2 - Road Classes, Design Speed and Traffic
Republic of Yemen
Ministry of Public Works and Highways
SECTION 2
ROAD CLASSES,DESIGN SPEED AND TRAFFIC
2.1 INTRODUCTION
The criteria used in the geometric design shall be pertinent to the local
conditions with respect to technical application and development trends.
They shall further be economically feasible, taking into consideration all
the relevant conditions and circumstances such as climate, topography andgeotechnical conditions encountered in the different regions of the country.
The design standards shall not impose any limits on the needs of society for
the development of transportation and the implementation shall be
undertaken with due regard to all relevant data and conditions, both
existing and forecast. In this Section of the Manual, special emphasis has
been placed on the functional classification of roads and as these are
considered the most important parameters for harmonization of RAP road
projects within the national road network.
Economic constraints may justify adoption of lower geometric standards
than are desirable, but economic restrictions will not justify abandoning a
balanced geometric design by downgrading only some of the design
elements, as for example, reducing the formation width without adjusting
th d i d di l H th t i d i ill
-
7/27/2019 Design Manual 1
15/366
Rural Roads Design Manual
Section 2 - Road Classes, Design Speed and Traffic
Republic of Yemen
Ministry of Public Works and Highways
This functional concept is important to the design of new roads, and is
consistent with a systematic approach to design and transportation
planning.
In general, the system consists of primary, secondary and tertiary networks
according to mobility and function, importance at the national level, and
administrative jurisdiction.
The Road Classification System recommended by the National Highway
and Rural Access Master Plan Study (NHRAMP) emphasizes the attribute
of administrative responsibility. The rationale is to enable the enactment of
Law No. 4 of 2000 on Local Authority, whereby Mohafazas and Mudiriyas
will in the future assume the responsibility for Secondary and Tertiary
Road Networks in their respective areas. The following classification has
been recommended:
i. National (Primary) Road Network
Jurisdiction: Ministry of Public Works and Highways (MPWH).
Function: Primary routes linking major regions and formingdirect connections between Sanaa and the
Mohafaza Centers, primary regions, and major
international border crossings.
Trip Lengths: Likely to be long and speeds relatively high.
Geometric Standards: High.
-
7/27/2019 Design Manual 1
16/366
Rural Roads Design Manual
Section 2 - Road Classes, Design Speed and Traffic
Republic of Yemen
Ministry of Public Works and Highways
District Centers, between National Roads and
District Centers, Secondary ports and to secondary
border crossings. Collection and distribution oftraffic between the primary and tertiary roads within
the region.
Trip Lengths: Traffic flows and trip lengths are of an intermediate
level.
Geometric Standards: Adequate geometric standards. Speeds
depend on the type of terrain.
iii. District (Tertiary) Road Network
At the District level, roads are currently under the jurisdiction of
MPWH. It is expected that the responsibility for these roads will be
transferred to the Governorate, and ultimately to the Districts when
their capacity is strengthened.
Two classes have been recommended in this category:
Distr ict Roads
Function: Provide links between Governorate Roads, and give
access from District centers to subdistricts and
between subdistricts. Roads with traffic volume
greater than 100 vehicles per day to tourist sites,
i
-
7/27/2019 Design Manual 1
17/366
Rural Roads Design Manual
Section 2 - Road Classes, Design Speed and Traffic
Republic of Yemen
Ministry of Public Works and Highways
The Tertiary Roads have relatively short trip lengths, serving local traffic as
their main function. A relatively low design speed is normally applicable to
local roads, especially in mountainous areas.
Rural Roads and Village Access Roads come under classes (ii) and (iii)
above.
2.2.2 RAP Roads Design Classes
International practice is to design roads according to a design speed which
varies depending on the functional class of the road and type of terrain.
However, the concept of design speed is not always appropriate as the basis
for geometric design as it can be uneconomic.
Designs should be justified economically and the optimum geometric
standards will depend on both construction and road user costs.
Construction costs will be related to the terrain and choice of pavement,
while road user costs are directly related to the volume and composition oftraffic. It is therefore recommended that the basic parameters for road
function, terrain type and traffic flow are defined initially. On the basis ofthese parameters, a design class is selected, while design speed is used only
as an index which links design class to the design parameters of sight
distance and curvature to ensure that a driver is presented with a reasonably
consistent speed environment.
RAP R d F ti l Cl ifi ti
-
7/27/2019 Design Manual 1
18/366
Rural Roads Design Manual
Section 2 - Road Classes, Design Speed and Traffic
Republic of Yemen
Ministry of Public Works and Highways
movement and access functions. It should be noted that in practice there are
many overlaps of functions, and clear distinctions will not always be
apparent on functional terms alone.
The design of village access roads should be based on the criterion of
achieving an appropriate level of access, and should be based on minimum
requirements of radii, width, and gradient for economic purposes.
TABLE 2.1RAPROADS FUNCTIONAL CLASSIFICATION AND DESIGN CLASSES
Road ClassDesign
Class
Traffic
Flow
(ADT)
Number
of Lanes
Surface
Type
RuralIntermedi
ate
Secondary
(Governorate)
Tertiary
(District)
A 1000-3000 2 paved
B 400-1000 2 paved
-
7/27/2019 Design Manual 1
19/366
Rural Roads Design Manual
Section 2 - Road Classes, Design Speed and Traffic
Republic of Yemen
Ministry of Public Works and Highways
400-1000 vehicles per day. Design to the higher Design Class would result
in an overdesigned facility during almost the whole of its life. If the initial
flow were 410 vpd, design would still be Design class B.
Types of Terrain
The following classification of terrain types is adopted:
Flat terrain Flat or gently rolling country which offers few obstacles tothe construction of a road having continuously unrestricted
horizontal and vertical alignment (transverse terrain slopemax. 5%).
Rolling terrain Rolling, hilly or foot-hill country where the slopes generally
rise and fall moderately gently and where occasional steepslopes may be encountered. It will offer some restrictions inhorizontal and vertical alignment (transverse terrain slope
5% - 20%).Mountainous
terrain
Rugged, hilly and mountainous country with river gorges.
This class of terrain imposes definite restrictions on thestandard of alignment obtainable and often involves longsteep grades and limited sight distances (transverse terrainslope more than 20%).
Escarpment
terrain
Long precipitous clifflike ridge commonly formed by
faulting. This class of terrain introduces restrictions on cross-section width, lateral clearances, and driving safety.
I l i i i h h diffi l d d f
-
7/27/2019 Design Manual 1
20/366
Rural Roads Design Manual
Section 2 - Road Classes, Design Speed and Traffic
Republic of Yemen
Ministry of Public Works and Highways
maximum speed that could be attained on any road is dictated by the
geometric characteristics of that road, other factors such as surface type and
drivers perception of safety play a major role in setting the design speed.As for village access, the only influencing feature is the character of the
terrain, since it is an established fact that these roads carry very low traffic
volumes, and they are treated as low cost access roads, which eliminates
the economic factor.
2.3.2 Design Speed Standards
Vertical and horizontal alignment, sight distance, and superlevation will
vary appreciably with design speed. Such features as pavement width,
shoulder width, and side clearances are usually not affected. On the other
hand, the actual speeds are determined by geometry and the quality of the
road surface.
The choice of design speed shall be a logical one with respect to the
different influencing features taking into account drivers behaviorespecially in flat terrain in Yemen. Accordingly, design speeds that are
considered on the rural intermediate roads and village access range between
20 kph in the difficult escarpments and 100-120 kph in flat areas with
good visibility. Needless to say that for some extreme stretches, the speed
may not exceed 10 kph. Table 2.1 presents proposed design speeds on
different terrain types.
TA 2 2 D S G S S O A OA S O A
-
7/27/2019 Design Manual 1
21/366
Rural Roads Design Manual
Section 2 - Road Classes, Design Speed and Traffic
Republic of Yemen
Ministry of Public Works and Highways
In other cases, an already acceptable rate of return may be increased
substantially by the inclusion of a short section of substandard road where
achievement of the design standard would be expensive, although the safetyimplications of this would need careful consideration.
Segments subject to speed reduction should have appropriate signing or
other warning measures. On low flow roads where most of the drivers will
be regular users, the increased risk will be less significant and the resultant
number of accidents should be negligible. Greater care and consideration
should be given to relaxations on high flow/high speed alignments.
In special circumstances, where standards have been reduced on successive
design elements, further relaxations may be made based on those reduced
approach speeds. Sight distances, and the potential accident risk as a result
of driver error, would need to be considered on a site-specific basis.
Reductions in standards should only apply to stopping distances and
curvature. Widths should not be reduced as they are particularly flowrelated, and additional widening may be required on curves with the tighter
radii (TRRL Road Note No.6).
The nature of the mountainous terrain in Yemen makes it economically
prohibitive, or often physically impossible to construct roads at the normal
standards. Thus, relaxed standards are necessary in order to ensure a cost-
effective approach to the road system. Relaxation of standards apply
i ll f d i diffi l i i d f d j
-
7/27/2019 Design Manual 1
22/366
Rural Roads - Design Manual
Section 2 - Road Classes, Design Speed and Traffic
Republic of YemenMinistry of Public Works and Highways
DOCS-0974-04 2-9
TABLE 2.3DESIGN SPEED FOR RURAL ROADS BY DESIGN CLASS,TRAFFIC VOLUME AND TYPE OF TERRAIN
Road ClassDesign
ClassTraffic Flow
Number of
Lanes
Surface
Type
Design Speed (Km/h)
Flat Rolling Mountainous Escarpment
RuralIntermediate
Secondary
A 1000-3000 2 paved 120 80 40 20
(Governorate)
Tertiary
B 400-1000 2 paved 100 70 40 20
VillageAccess
(District)
C 100-400 2
paved 100 70 40 20
unpaved 80 60 30 20
Feeder
D < 100 1
paved 80 60 30 20
unpaved 60 50 30 20
-
7/27/2019 Design Manual 1
23/366
Rural Roads - Design Manual
Section 2 - Road Classes, Design Speed and Traffic
Republic of Yemen
Ministry of Public Works and Highways
2.4 TRAFFIC
Traffic volume and composition are needed for the purpose of geometricdesign and the evaluation of economic benefits. On the other hand,
pavement design is mainly based on the magnitude of individual axle loads
and their frequency over the design life. Because the lighter vehicles have
negligible contribution to pavement damage, they may be ignored and only
the number of axle loading of the heavier vehicles need be considered.
This section covers the methodology for estimating traffic flows and
determining the esa cumulative number (see TRL Road Note 31). This
methodology is shown in Figure 2.1 below.
2.4.1 Design Life
The choice of a design period is mainly governed by budgetary
considerations, whereby in order to reduce the initial expenditures lower
design periods may be considered.
An economic analysis period of 10-20 years from the date of opening is
normally used. At the end of the analysis period the road will still have a
residual value. A pavement design life of 15 years is considered appropriate
for many road projects. At the end of the design life, the pavement will
need to be strengthened to be able to carry traffic over a further period.
h i d i i d h ld b f d i h lif
-
7/27/2019 Design Manual 1
24/366
Rural Roads - Design Manual
Section 2 - Road Classes, Design Speed and Traffic
Republic of Yemen
Ministry of Public Works and Highways
Determine DesignLife
Survey of baseline
Traffic Flows
Traffic Forecasting
-Normal traffic
-Diverted traffic
-Generated traffic
Establishing axleloading
-Survey of axle Loads
-i i
-
7/27/2019 Design Manual 1
25/366
Rural Roads - Design Manual
Section 2 - Road Classes, Design Speed and Traffic
Republic of Yemen
Ministry of Public Works and Highways
volumes are taken in one direction which requires care in interpreting
AADT figures.
Another estimate of daily traffic is the Average Daily Traffic (ADT)
which is defined as the total traffic in both directions over a given period
less than one year divided by the number of days in that period. The longer
the period of traffic counts the more accurate the ADT approximates
AADT, as traffic flows have daily, weekly and seasonal variations. Roads
carrying less than 1000 vehicles per day exhibit high daily variability
resulting in large errors in estimating ADT (and consequently annual traffic
flows) from traffic counts measured over a period less than one week. A
considerable decrease in the error of estimation can be realized with counts
taken over a full week. This provides traffic flow data for work days,
weekends as well as 24 hours variations. If a full week count is not
possible, there should be at least one 24-hour count on a weekday and one
during a weekend, with 16-hour counts on the other days. The 16-hours
counts are grossed up to 24-hour values in the same proportion as the 16-
hour/24 hour split (see section 2.4.7 below).
In order to account for seasonal variations several one-week counts may be
repeated, if possible, throughout the year. These automatic counts should be
supplemented by manual classification counts to obtain information on
vehicle classes.
A formal country-wide traffic data collection program should be
-
7/27/2019 Design Manual 1
26/366
Rural Roads - Design Manual
Section 2 - Road Classes, Design Speed and Traffic
Republic of Yemen
Ministry of Public Works and Highways
Such counts can be useful as a cross check on static counts and to assess
the extent of daily or seasonal variations in traffic flow.
2.4.3 Traffic Forecasting
Three components contribute to overall traffic volumes:
i. Normal Traffic
Normal traffic is the traffic using the existing route if no pavement
were provided.
Normal traffic may be forecasted using linear time series
extrapolation of traffic levels i.e. a fixed percentage increase. If
Gross Domestic Product (GDP) forecasts are available, traffic flows
can be forecasted by relating traffic growth linearly to GDP.
ii. Diverted Traffic
Diverted traffic is the traffic that is attracted from another route to
the new road due to improved pavement.
Traffic diversion occurs when parallel routes exist. Improving an
existing road may result in diverting traffic from a shorter route
because higher speeds and level of service are available on the
-
7/27/2019 Design Manual 1
27/366
Rural Roads - Design Manual
Section 2 - Road Classes, Design Speed and Traffic
Republic of Yemen
Ministry of Public Works and Highways
responsiveness of traffic to the decrease in transport cost accruing
from road improvement. Available data indicate that the elasticity
of demand for passenger trips is slightly greater than one, while thatfor goods is much lower.
In Section 9 of this Manual, generated traffic is defined by the
Roads Economic DecisionModel in two components:
i. Generated Traffic is the traffic attributable to decrease in
transport costs, associated with existing users of the project
road driving more frequently or driving further than before.
Generated traffic may be defined as a percentage of the
normal traffic, or by using a price elasticity of demand
which reflects the % increase in traffic per percent decrease
in transport costs.
ii. Induced Traffic is the traffic attributable to local economic
development, i.e. traffic attracted to the project due toincreased development activity in the roads zone of
influence brought about by the project. Induced traffic is
determined for each project alternative, each vehicle type
and year induced.
2.4.4 Axle Load Distribution
-
7/27/2019 Design Manual 1
28/366
Rural Roads - Design Manual
Section 2 - Road Classes, Design Speed and Traffic
Republic of Yemen
Ministry of Public Works and Highways
1.1
1.2
1.21
1.22
1.22
1.222
1.2222
1.2 + 2.2
-
7/27/2019 Design Manual 1
29/366
Rural Roads - Design Manual
Section 2 - Road Classes, Design Speed and Traffic
Republic of Yemen
Ministry of Public Works and Highways
The equivalence factors that are used to convert single axle loads to
equivalent standard axle is given by the relationship:
Equivalence Factor = EF =
4.5
8.16
(Tons)loadAxle
Table 2.3 shows the equivalence factors (EF) for each of the wheel loads
measured in the axle load survey. The above equation is used on all axle
loads obtained by weighing axles separately. The EF per vehicle is obtained
by adding the EFs for all axles of each vehicle. The factors for the axles aretotaled to give the equivalence factor for each of the vehicles. The mean
equivalence factor for each class or type of vehicle traveling in each
direction is then determined for all vehicles in the vehicle class whether
loaded or empty.
Table 2.3Equivalence Factors for different axle loads
Wheel load
(single & dual)(10
3kg)
Axle load(103kg) Equivalence FactorEF
1.5 3.0 0.01
2.0 4.0 0.04
2.5 5.0 0.11
3.0 6.0 0.25
3.5 7.0 0.50
4.0 8.0 0.91
4.5 9.0 1.55
-
7/27/2019 Design Manual 1
30/366
Rural Roads - Design Manual
Section 2 - Road Classes, Design Speed and Traffic
Republic of Yemen
Ministry of Public Works and Highways
(4) Determine the mean equivalence factor for each class of vehicle and
for each direction from the results of the axle load survey (EF1i ,
EF2i).
(5) Calculate the cumulative equivalent standard axles for each
direction (T1, T2) as follows:
1i1i1 EFxVT , for direction 1 2i2i2 EFxVT , for direction 2
T, the higher of the two directional values T1, T2 should be used for
design.
Where,
T1 = Cumulative Equivalent Standard Axles for direction 1.
T2 = Cumulative Equivalent Standard Axles for direction 2.
V1i = Cumulative directional flow for class i vehicle over the design
period for direction 1.
V2i = Cumulative directional flow for class i vehicle over the design
period for direction 2.
-
7/27/2019 Design Manual 1
31/366
Rural Roads - Design Manual
Section 2 - Road Classes, Design Speed and Traffic
Republic of Yemen
Ministry of Public Works and Highways
In order to minimize the effects of errors of estimation and forecasting, the
TRL Road Note 31 provides fixed structures for ranges of traffic as shown
in Table 4.4. As long as the estimate of T is close to the center of a range,errors are not likely to affect the pavement design. If the value of T is close
to the boundaries of the range, then sensitivity analyses should be made to
ensure that the choice of traffic classes is appropriate.
TABLE 2.4TRAFFIC CLASSESTraffic Classes Range (10
6esa)
T1 < 0.3
T2 0.30.7T3 0.71.5
T4 1.53.0
T5 3.06.0
T6 6.010
T7 1017
T8 1730
2.4.7 Example on the analysis of traffic count data
Given: A manual classified traffic count was conducted during a week in
July on a site with equal traffic flow in both directions. The data for
commercial vehicles are shown in Table A. The data for non-commercial
vehicles has already been analyzed and gave an average number of 260
vehicles per day. Information obtained from automatic traffic data recorded
over a year is shown in Table B.
-
7/27/2019 Design Manual 1
32/366
Rural Roads - Design Manual
Section 2 - Road Classes, Design Speed and Traffic
Republic of Yemen
Ministry of Public Works and Highways
TABLE AMANUAL CLASSIFIED TRAFFIC COUNT DATA IN BOTH DIRECTIONS
HOURLY NUMBER OF COMMERCIAL VEHICLES
Time Sat Sun Mon Tue Wed Thu Fri
0:00-1:00 1 1
1:00-2:00 0 0
2:00-3:00 0 0
3:00-4:00 1 0
4:00-5:00 2 2
5:00-6:00 3 1
6:00-7:00 5 5 6 2
7:00-8:00 11 12 13 3
8:00-9:00 14 13 16 2 1
9:00-10:00 18 17 20 4 2
10:00-11:00 15 16 16 4 2
11:00-12:00 13 12 14 5 1
12:00-13:00 12 11 13 4 0
13:00-14:00 8 7 8 3 1
14:00-15:00 11 10 11 4 2
15:00-16:00 12 11 10 5 2
16:00-17:00 10 9 8 5
17:00-18:00 8 7 9 3
18:00-19:00 5 7 2
-
7/27/2019 Design Manual 1
33/366
Rural Roads - Design Manual
Section 2 - Road Classes, Design Speed and Traffic
Republic of Yemen
Ministry of Public Works and Highways
Solution
1. Average Daily Traffic (ADT)
A = Estimated traffic count for Monday
=counthour24of00:1800:12forcount
counthour24talweekday tox
00:1800:12for
counttrafficactual
= 55 x61
158= 142
B = Estimated traffic count for Tuesday
=counthour24of00:2200:06forcount
counthour24talweekday tox
00:2200:06
forcountactual
= 146 x149
158= 155
C = Estimated traffic count for Wednesday
= 85 x76
158= 177
Average weekday traffic = (Sun + Mon + Tue + Wed) / 4
= (158 + 142 + 155 + 177) / 4
-
7/27/2019 Design Manual 1
34/366
Rural Roads - Design Manual
Section 2 - Road Classes, Design Speed and Traffic
Republic of Yemen
Ministry of Public Works and Highways
2. Seasonal Correction Factors and AADT
The seasonal correction factors are calculated from Table B as follows:
Month ADT (CV)Seasonal Variation
Factors
Jan 145 1.05
Feb 134 0.97
Mar 132 0.95
Apr 150 1.08
Mai 161 1.16
Jun 158 1.14
Jul 125 0.90
Aug 114 0.82
Sep 120 0.86
Oct 136 0.98
Nov 145 1.05
Dec 134 0.97
Annual Mean 138 1.0
From the ADT values above, it can be seen that the July value (125) is
lower than the annual average value (138). The results from the traffic
surveys carried out in July should be adjusted upwards accordingly to give
the seasonally adjusted number.
The traffic survey was carried out in July for which the adjustment factor is
-
7/27/2019 Design Manual 1
35/366
Rural Roads - Design Manual
Section 2 - Road Classes, Design Speed and Traffic
Republic of Yemen
Ministry of Public Works and Highways
2.4.8 Example on Calculation of Equivalence Factors
Given: Survey data for commercial vehicles shown in Table C.
Calculate: 1) EF for axle roads, 2) EF for each vehicle, 3) Average EF for
the vehicle type.
TABLE CAXLE LOAD DATA FROM SURVEY
No. TimeE=Empty
F=FullLoad Type
Axle Load (Tons)
Axle 1 Axle 2 Axle 3
1 7.05 E none 3.66 3.32 2.512 9.57 E none 2.68 4.38 2.71
3 11.36 E none 4.00 2.81 2.64
4 14.48 E none 4.20 5.46 5.45
5 14.50 E none 4.04 4.80 4.53
6 15.07 E none 4.11 3.86 2.49
7 8.10 F Gravel 4.03 6.85 6.99
8 8.14 F Gravel 5.32 13.31 13.14
9 8.55 F Bottles 4.51 6.23 4.73
10 9.21 F Gravel 6.30 12.94 14.36
11 3.36 F Gravel 6.33 15.49 15.3212 3.39 F Gravel 6.07 14.75 14.56
13 3.55 F Sand 6.50 14.56 14.24
14 3.58 F Feeds 3.93 9.54 6.00
15 10.15 F Gravel 3.80 6.09 6.18
16 10.44 F Gravel 4.52 7.09 7.63
17 10.52 F Gravel 4.26 7.17 6.88
18 10.54 F Gravel 3.80 7.45 6.05
19 14.32 F Sand 6.61 15.38 14.36
-
7/27/2019 Design Manual 1
36/366
Rural Roads - Design Manual
Section 2 - Road Classes, Design Speed and Traffic
Republic of Yemen
Ministry of Public Works and Highways
TABLE DDATA ANALYSIS SHOWING EQUIVALENCEFACTORS
No. Time E=EmptyF=Full
LoadType
Axle Load (Tons) Equivalence Factors Total EFper
vehicleAxle 1 Axle 2 Axle 3 Axle 1 Axle 2 Axle 3
1 7.05 E none 3.66 3.32 2.51 0.027 0.017 0.005 0.050
2 9.57 E none 2.68 4.38 2.71 0.007 0.060 0.007 0.074
3 11.36 E none 4.00 2.81 2.64 0.040 0.008 0.006 0.055
4 14.48 E none 4.20 5.46 5.45 0.050 0.164 0.163 0.377
5 14.50 E none 4.04 4.80 4.53 0.042 0.092 0.071 0.205
6 15.07 E none 4.11 3.86 2.49 0.046 0.034 0.005 0.085
7 8.10 F Gravel 4.03 6.85 6.99 0.042 0.455 0.498 0.935
8 8.14 F Gravel 5.32 13.31 13.14 0.236 9.041 8.532 17.8099 8.55 F Bottles 4.51 6.23 4.73 0.069 0.297 0.086 0.452
10 9.21 F Gravel 6.30 12.94 14.36 0.312 7.963 12.723 20.999
11 3.36 F Gravel 6.33 15.49 15.32 0.319 17.891 17.024 35.233
12 3.39 F Gravel 6.07 14.75 14.56 0.264 14.354 13.540 28.158
13 3.55 F Sand 6.50 14.56 14.24 0.359 13.540 12.251 26.151
14 3.58 F Feeds 3.93 9.54 6.00 0.037 2.020 0.251 2.308
15 10.15 F Gravel 3.80 6.09 6.18 0.032 0.268 0.286 0.586
16 10.44 F Gravel 4.52 7.09 7.63 0.070 0.722 0.733 1.031
17 10.52 F Gravel 4.26 7.17 6.88 0.054 0.559 0.464 1.078
18 10.54 F Gravel 3.80 7.45 6.05 0.032 0.664 0.260 0.956
19 14.32 F Sand 6.61 15.38 14.36 0.388 17.225 12.723 30.335
20 14.38 F Gravel 5.87 13.92 11.64 0.227 11.060 4.945 16.233
21 14.45 F Sand 6.00 13.61 11.55 0.251 9.994 4.775 15.020
22 15.19 F Sand 6.33 16.13 13.43 0.319 21.466 9.413 31.198
23 15.50 F Fertilizer 6.44 12.53 7.62 0.345 6.889 0.735 7.969
2. Calculating EF for each vehicle
-
7/27/2019 Design Manual 1
37/366
Rural Roads - Design Manual
Section 2 - Road Classes, Design Speed and Traffic
Republic of Yemen
Ministry of Public Works and Highways
2.4.9 Example on Calculation of Cumulative Equivalent Standard Axles
The result of an axle load survey on a road section for various truck typesand their annual growth rates are as follows:
Truck Type Axle CodeADT one
direction
Mean EF for
the Vehicle
Type
Annual
Growth Rate
(i)
Medium Trucks 2 axlesGW < 11.5 Tons
1.2 94 0.68 6%
Heavy Trucks 2 axles
GW > 11.5 Tons1.2 58 4.80 5%
Heavy Trucks 3 axles
GW > 11.5 Tons1.22 17 10.34 3%
Heavy Truck - trailer
4 axles1.222 9 8.85 3%
Calculate the average annual numbers of equivalent standard axles for the
current year for each truck type. Assuming the road section to be repaved
during the current year, calculate the cumulative equivalent standard axlesfor a design life for the pavement of 15 years, and determine accordingly
the appropriate traffic class for pavement design.
Solution:
1. Calculate the average daily esa in the current year:
-
7/27/2019 Design Manual 1
38/366
Rural Roads - Design Manual
Section 2 - Road Classes, Design Speed and Traffic
Republic of YemenMinistry of Public Works and Highways
DOCS-0974-04 2-25
TABLE EDETERMINATION OF CUMULATIVE EQUIVALENT STANDARD AXLES
Truck Type ADT (one direction) EF Average Daily esaesa current year
(103esa)
15-yr Cumulative
Factor
Cumulative esa for 15
years (106esa)
Medium Trucks 2 axlesGW > 11.5 Tons 94 0.68 64 23.36 23.28 0.54
Heavy Trucks 2 axles
GW > 11.5 Tons 65 4.80 312 113.88 21.59 2.46
Heavy Trucks 3 axles
GW > 11.5 Tons 17 10.34 176 64.24 18.6 1.20
Heavy Truck - trailer4 axles 9 8.85 80 29.20 18.6 0.54
T = 4.77
-
7/27/2019 Design Manual 1
39/366
SECTION 3
GEOMETRIC STANDARDS
Section
3
-
7/27/2019 Design Manual 1
40/366
Rural Roads - Design Manual
Section 3Geometric Standards
Republic of Yemen
Ministry of Public Works and Highways
SECTION 3
GEOMETRIC STANDARDS
TABLE OF CONTENTS
Page
3.1 Introduction 13.2 Sight Distance 13.2.1 Stopping Sight Distance 13.2.2 Intermediate Site Distance 33.3 Superelevation 33.4 Horizontal Alignment 73.4.1 Circular Curves 73.4.2 Transition Curves 83.4.3 Improving Horizontal Alignment 103.4.4 Geometric Controls 10
-
7/27/2019 Design Manual 1
41/366
Rural Roads - Design Manual
Section 3Geometric Standards
Republic of Yemen
Ministry of Public Works and Highways
SECTION 3
GEOMETRIC STANDARDS
3.1 INTRODUCTION
As mentioned in Section 2, the geometric features for most of the rural
roads in Yemen are governed by the natural terrain characteristics.
However, this does not exclude the fact that the geometric design should be
consistent with the traffic volume, composition of traffic and design speed.This Section provides a summary of the geometric design data and contains
sufficient information for the majority of roadway design problems. A
Policy on Geometric Design for Highways and Streets by the American
Association of State Highways and Transportation Officials (AASHTO) is
a reference in which the basic theory behind geometric design data is fully
explained. Also, Guidelines for Geometric Design of Very Low-Volume
Roads (ADT 400)by AASHTO, and TRRL Road Note No. 6 A guide
to Geometric Design can be consulted.
Several design standards from projects previously undertaken in Yemen
have been reviewed. The Consultants have taken into consideration the
technical aspect combined with the specific requirements of this project in
developing a new set of geometric standards. The review covers the sight
distance, horizontal and vertical alignment and cross sectional elements as
-
7/27/2019 Design Manual 1
42/366
Rural Roads - Design Manual
Section 3Geometric Standards
Republic of Yemen
Ministry of Public Works and Highways
Stopping sight distance is generally determined as the sum of two
distances:
(1) Reaction Distance, the distance traveled by the vehicle from the
instant the driver sights an object necessitating a stop to the instant
the driver actually applies the brakes. This distance depends on the
reaction time of the driver which varies according to the alertness of
the driver. AASHTO Policy on Geometric Design for Highways
and Streets uses a brake reaction time of 2.5s, while AASHTO
Guidelines for Geometric Design of Low-Volume Local Roads
(ADT 400) recommends a reaction time of 2s for rural roads.
(2) Braking Distance, the distance required to stop the vehicle from
the instant the brakes are applied. This distance is a function of the
longitudinal friction factor, and thus deceleration of the vehicle.
The stopping sight distance in the AASHTO Policy is given by the
following formula which has two components corresponding to the twodistances mentioned above:
a
V039.0Vt278.0S
2
where,
S = stopping sight distance, m
t = brake reaction time, s
-
7/27/2019 Design Manual 1
43/366
Rural Roads - Design Manual
Section 3Geometric Standards
Republic of Yemen
Ministry of Public Works and Highways
As discussed in Section 3.5.2, sight distance plays a key role in determining
the minimum lengths of crest vertical curves. Stopping sight distance is
measured from the drivers eyes (eye height, h1) to an object height (h2).AASHTO policy uses h1= 1080 mm and h2= 150mm or h2= 600mm if the
object is a vehicle. With the increased use of SUVs, the average eye height
has increased, so that h1could be assumed to be 1.4m and h215cm. This
sight distance criterion should be checked for all classes of roads irrelevant
of the number of lanes, traffic volume or pavement type. Measures to be
taken to correct any deficiency include removal of obstacles, excavation of
side slopes or trimming of sharp crest curves.
3.2.2 Intermediate Site Distance
The Intermediate sight distance is the distance needed for two drivers
traveling with design speed to stop before colliding. This criterion is valid
in the case of one-lane roads. For village access roads having a traffic load
of less than 50 vehicles/day the intermediate sight distance can be neglected
if the lane is widened up to at least 4.5m.
Table 3.2 shows the proposed minimum normal and relaxed standards for
sight distances related to design speeds for RAP roads.
Table 3.2: Minimum Standards for Sight Distances Related to Design Speeds
Design
Speed,
Minimum Sight Distance, m
Stopping Intermediate
-
7/27/2019 Design Manual 1
44/366
Rural Roads - Design Manual
Section 3Geometric Standards
Republic of Yemen
Ministry of Public Works and Highways
Superelevation may be defined as the rotation of the roadway cross section
in such a manner as to overcome the centrifugal force that acts on a motor
vehicle traversing a curve. On a superelevated carriageway, the centrifugalforce is resisted by:
1. The weight component of the vehicle parallel to the superelevated
surface and
2. The side friction between the tires and the pavement.
It is impossible to balance centrifugal force by superelevation alone,
because for any given curve radius, a certain superelevation rate is exactlycorrect for only one operating speed around the curve. At all other speeds,
there will be a side thrust outward or inward relative to the center of the
curve, which must be offset by side friction.
The general formula to calculate superelevation for various curve radii is
the following:
e+f = V
2
/ 127Rwhere,
e = Superelevation rate, in meter per meter width of road.
f = side friction factor or coefficient of side friction between vehicle tires
and road pavement.
R = radius of curve, in meters.
V = design speed in kph.
-
7/27/2019 Design Manual 1
45/366
Rural Roads - Design Manual
Section 3Geometric Standards
Republic of Yemen
Ministry of Public Works and Highways
Superelevation slopes on curves shall extend the full width of the
shoulders, except that the shoulder slope on the low side shall not be less
than the minimum shoulder slope used on tangents.
For 2-lane roadways, different superelevation slopes for each half of the
road shall not be used; superelevation shall remain a plane for the full width
of roadbed, except on transitions.
The axis of rotation for superelevation is usually the centerline of the road.
However, in special cases such as desert roads where curves are preceded
by relatively long tangents, the plane of the superelevation may be rotatedabout the inside edge of pavement to improve perception of the curve. In
level country, drainage pockets caused by superelevation may be avoided
by changing the axis of rotation from the centerline to the inside edge of the
pavement.
Superelevation transition is the general term denoting the length of
highway needed to accomplish the change in cross slope from a normalcrown section to the fully superelevated section, or vice versa. To meet the
requirements of comfort and safety the superelevation run-off should be
effected uniformly over a length adequate for the likely travel speed. The
superelevation transition can be divided into two sections defined as
follows:
- Tangent Run-off or Run-out: This is the distance in which the level
-
7/27/2019 Design Manual 1
46/366
Rural Roads - Design Manual
Section 3Geometric Standards
Republic of YemenMinistry of Public Works and Highways
DOCS-0974-04 3-6
Figure 3.1Typical Details for Superelevation Runoff
Inside Edge of
Roadway (P.G.L)
Outside Edge of
Roadway
1 / 4 LA
or 10m Max
Tangent Run out Length of Superelevation Runoff
Length of Application (as shown on the profile)
Total Length of Application
1 / 4 LA
or 10m Max
or 10m Maxor 10m Max
Inside Edge of
Roadway (P.G.L)
Outside Edge of
Roadway1 / 4 LA
or 10m Max 1 / 4 LA
or 10m Max
Total Length of Application
Outside Edge of
Roadway
Superelevation Application Details LA
+e
+eo
-eo
-e
+e
+eo
-eo
-e
B
B/2e
B/2e
B/2e2
B/2e2
B/2e
B/2e
+e
-eo
-e
+e
+eo
-e
P G L C/L
B/2e2
B/2e2
Sign Convention for CrossfallMethod of Attaining Superlevation of
Pavement Revolved aboutCenterlines of Roadways
e
e
Inside Edge of
Roadway (P.G.L)
Outside Edge of
Roadway
1 / 4 LA
or 10m Max
Tangent Run out Length of Superelevation Runoff
Length of Application (as shown on the profile)
Total Length of Application
1 / 4 LA
or 10m Max
or 10m Maxor 10m Max
Inside Edge of
Roadway (P.G.L)
Outside Edge of
Roadway1 / 4 LA
or 10m Max 1 / 4 LA
or 10m Max
Total Length of Application
Outside Edge of
Roadway
Superelevation Application Details LA
+e
+eo
-eo
-e
+e
+eo
-eo
-e
B
B/2e
B/2e
B/2e2
B/2e2
B/2e
B/2e
+e
-eo
-e
+e
+eo
-e
P G L C/L
B/2e2
B/2e2
Sign Convention for CrossfallMethod of Attaining Superlevation of
Pavement Revolved aboutCenterlines of Roadways
e
e
-
7/27/2019 Design Manual 1
47/366
Rural Roads - Design Manual
Section 3Geometric Standards
Republic of Yemen
Ministry of Public Works and Highways
3.4 HORIZONTAL ALIGNMENT
3.4.1 Circular Curves
The natural terrain, as mentioned earlier, governs the horizontal alignments.
The roads that are located on escarpments are therefore characterized by the
multitude of hairpin curves that necessitate a back and forth maneuver in
order to make the turn. For these roads, no minimum curvature can be
specified, as speeds will drop to zero during the maneuver.
For the remaining cases, the minimum radii will have to correspond to thedesign speeds as per the recommendations listed in Table 3.4, determined
using the superelevation equation defined above:
R =f)(e127
V2
Table 3.4: Horizontal Curve Design DataMinimum Radii (m)
Design
Speed
kph
fmax
Rural Intermediate Roads Village
Access
Roads
emax= 6%
Flat/Rolling
emax= 8%
Mountainous
emax= 6%
Escarpment
emax=4% emax =6%
20 0.18 - 15(1)
15(1)
15(1)
15
30 0.17 - 30 35 30 30
-
7/27/2019 Design Manual 1
48/366
Rural Roads - Design Manual
Section 3Geometric Standards
Republic of Yemen
Ministry of Public Works and Highways
Design Speed, Kph 30 40 50 60 70 85 100 120
Side Friction Factor 0.33 0.30 0.25 0.23 0.20 0.18 0.15 0.15
The values for horizontal curve design shown in Table 3.4 should be used
for rural roads when practical. In constrained situations relaxed values
based on reduced design speed shown in Table (3.5) may be used.
In cases where the existing curve has a radius less than those listed, and
widening entails land acquisition, high excavations or high fills, signs shall
be posted to reduce the speed to correspond to the adopted radius.
Table (3.5) Horizontal Curve Design Data Minimum Radii (m)
for Reduced Design Speed
Design
Speed
kph
Reduced
Design
Speed
kph
fmax
Rural Intermediate Roads Village
Access
RoadsFlat / Rolling Mountainous Escarpment
emax= 8%
emax= 6% emax= 4% emax= 6% emax= 6%
20 20 0.180 __ 15(1) 15(1) 15(1) 15
30 25 0.170__
20 25 20 20
40 30 0.170 30 30 35 30 30
50 40 0.170 50 55 60 55 55
60 50 0.160 80 90 100 90 90
-
7/27/2019 Design Manual 1
49/366
Rural Roads - Design Manual
Section 3Geometric Standards
Republic of Yemen
Ministry of Public Works and Highways
Several methods exist for the calculation of transition curves and may be
used in most situations. The rate of pavement rotation methodhas been
adopted here. The rate of pavement rotation is defined as the change incrossfall divided by the time taken to travel along the length of transition at
the design speed. The length of transition curve is derived from the
formula:
3.6n
V.eLs
where Ls= Length of transition curve (meters)
e = Superelevation of the curve (meters per meter)V = Design speed (km/h)
N = Rate of pavement rotation (meters per meter per second)
The same values of rate of change of pavement rotation should be used to
calculate the minimum length (Lc) over which adverse camber should be
removed on a tangent section prior to the transition:
3.6n
V.eL nc
where Lc= Length of section over which adverse camber is removed
(meters)
en= Normal crossfall of the pavement (meters per meter).
-
7/27/2019 Design Manual 1
50/366
Rural Roads - Design Manual
Section 3Geometric Standards
Republic of Yemen
Ministry of Public Works and Highways
3.4.3 Improving Horizontal Alignment
The major criteria for considering improvements to the horizontalalignment are the following:
1. Safety
2. Grade profile
3. Type of Roadway
4. Design speed
5. Topography
6. Cost (Construction, Maintenance, Operation)
Of these considerations, safety comes first. Therefore, the stopping sight
distance shall be adequate at all points of the roadway.
The grade profile shall be considered next in mountainous and escarpment
section. Critical grades are commonly encountered on existing roads
located in these sections. The possible improvement of these grades byadjusting the horizontal alignment should be investigated in the cases
where such an adjustment does not entail major earthworks or
encroachment into private property.
The road types that are considered in this Manual are the rural intermediate
roads and the village access roads. The standards for the horizontal
alignment will vary for each of these two road types.
-
7/27/2019 Design Manual 1
51/366
Rural Roads - Design Manual
Section 3Geometric Standards
Republic of Yemen
Ministry of Public Works and Highways
Curve Length and Central Angle:Winding alignment composed of short
curves shall be avoided since it results in erratic operation. In general, the
length of curve should be at least 100 m long for a central angle of 5degrees. The minimum length shall be increased 30m for each 1 degree
decrease in the central angle. Sight distance or other safety considerations
shall not be sacrificed thereby. In general, the central angle of each curve
shall be as small as physical conditions permit, in order to achieve the
shortest possible route.
Tangents or Straights Aff ording Passing Opportun ities: An 800m tangent
is considered adequate for the purpose of providing passing opportunitieson 2-lane roadways. Passing tangents shall be provided as frequently as
possible in keeping with the terrain. Shorter radii ensuring greater length of
intervening tangent shall be preferred to sweeping curves of large radii
which reduce the length of intervening tangents. However, sharp curves at
the end of passing tangents and especially long tangents shall not be used.
Compound Cur ves: These shall be avoided in general. On a compound
curve the shorter radius shall be least 2/3 of the longer radius. The total arc
length of a compound curve shall not be less than 100m.
Curvature on Fi ll s:Other than flat curvature should be avoided on high,
long fills. In the absence of cut slopes, shrubs, trees, etc., above the
roadway, it is difficult for drivers to perceive the extent of curvature and
adjust their operation to the conditions.
-
7/27/2019 Design Manual 1
52/366
Rural Roads - Design Manual
Section 3Geometric Standards
Republic of Yemen
Ministry of Public Works and Highways
applied on the inside edge of pavement only, and preferably attained over
superelevation runoff length. Widening values are given in Table 3.5.
Figure 3.2 shows how carriageway widening on curves is gradually
attained from the inside of the curve.
Table 3.7: Horizontal Curve Design Data
Widening on Curves for all Road Types
Radius Pavement Widths, m
4.0-4.9 5.0-5.9 6.0-6.9 7.0
-
7/27/2019 Design Manual 1
53/366
Rural Roads - Design Manual
Section 3Geometric Standards
Republic of Yemen
Ministry of Public Works and Highways
curvature design standards for such alignments are to be reduced to the
minimum in order to avoid land acquisition.
The major criteria for considering improvements to the vertical alignment
are the following:
1. The grade line is a reference line by which the elevation of the
pavement and other features of the highway are established. Though
controlled mainly by the topography, other factors such as horizontal
alignment, safety, sight distance, speed, construction costs and the
performance of heavy vehicles on a grade should be considered.
2. All portions of the grade line shall meet sight distance requirements for
the design speed classification of the road.
3. In level terrain, the elevation of the grade line is often controlled by
drainage considerations. In rolling terrain a reasonably undulating
grade line is desirable from the standpoint of operation and
construction economy.
4. Two vertical curves in the same direction separated by a short section
of tangent grade shall in general be avoided, particularly in valley
curves.
5. It is desirable to reduce the grades at intersections. Turns are
-
7/27/2019 Design Manual 1
54/366
Rural Roads - Design Manual
Section 3Geometric Standards
Republic of Yemen
Ministry of Public Works and Highways
2
L
x
200
L.Gy
where y = vertical distance from the tangent to the curve (meters)
x = horizontal distance from the start of the vertical curve
(meters)
G = algebraic difference in gradients (%)
L = length of vertical curve (meters)
3.5.2 Crest Curves
The provision of ample sight distance for the road design speed represent
the main control for safe operation on crest curves.
The minimum lengths of crest curves are designed to provide sufficient
sight distance during daylight conditions. Conditions normally do not allow
full overtaking sight distance and the design should aim to reduce thelength of crest curves to provide minimum stopping sight distance in order
to allow for increasing overtaking opportunities on the gradients on either
side of the curve.
Two conditions exist when considering minimum sight distance criteria on
vertical curves. The first is where sight distance is less than the length of
the vertical curve, and the second is where sight distance extends beyond
-
7/27/2019 Design Manual 1
55/366
Rural Roads - Design Manual
Section 3Geometric Standards
Republic of Yemen
Ministry of Public Works and Highways
Tables 3.8 and 3.11 show the two vertical alignment design parameters for
various terrain types: minimum vertical curvature in terms of K-values, and
maximum gradient.
Table 3.8 shows the minimum K-values for the following conditions using
the equations above:
1. Stopping sight distance measured from eye height h1of 1.080m to a
stopped vehicle, i.e. object height h2 = 0.6m. K-values are for
ADT
-
7/27/2019 Design Manual 1
56/366
Rural Roads - Design Manual
Section 3Geometric Standards
Republic of Yemen
Ministry of Public Works and Highways
Table 3.8Minimum Vertical Curvature Values
for Very-Low Volume Roads
(1) K-values are for higher risk locations for ADT 100-250 vpd and all locations for
250-400 vpd. K-values are for H1= 1080 mm and h2= 600 mm representing a stopped
vehicle.
(2) K-values are based on stopping sight distance measured from eye height of 1.05m and
an object height of 0.2m.
Design
Speed
(Kph)
AASHTO ADT
-
7/27/2019 Design Manual 1
57/366
Rural Roads - Design Manual
Section 3Geometric Standards
Republic of Yemen
Ministry of Public Works and Highways
access roads. No-passing signs should be erected where the available sight
distance does not allow overtaking.
3.5.3 Sag Curves
It has been assumed that adequate sight distance will be available on sag
curves in daylight. However, at night, visibility is limited by the distance
illuminated by the headlamp beams, and minimum sag curve length for this
condition is given as:
For S < L: tan.200.
1
2
Sh
SG
Lm
For S > L:
G
ShLm
tan.200 1
Where h1= headlight height (meters)
= angle of upward divergence of headlight beam (degrees)
Appropriate values for h1and are 0.6 meters and 1.0 degrees respectively.
The use of these equations can lead to requirements for unrealistically long
vertical curves as, especially at higher speeds, sight distances may be in
excess of the effective range of the headlamp beam, particularly when low
meeting beams are used. Thus, the only likely situation when the above
-
7/27/2019 Design Manual 1
58/366
Rural Roads - Design Manual
Section 3Geometric Standards
Republic of Yemen
Ministry of Public Works and Highways
For very low levels of traffic flow with only a few four-wheel drive
vehicles, the maximum traversable gradient is in excess of 20 per cent.
Small commercial vehicles can usually negotiate a 19 per cent gradient,whilst two-wheel drive trucks can successfully tackle gradients of 15-16
per cent except when heavily laden.
Gradients of 10 per cent or over will usually need to be paved to enable
sufficient traction to be achieved, as well as for pavement maintenance
reasons.
As traffic flows increase, the economic disbenefits of more severegradients, measured as increased vehicle operating and travel time costs,
are more likely to result in economic justification for reducing the severity
and/or length of a gradient. On the higher design classes of road, the lower
maximum recommended gradients reflect the economics, as well as the
need to avoid the build up of local congestion. However, separate economic
assessment of alternatives to long or severe gradients should be undertaken
where possible or necessary.
Table 3.11: Vertical Alignment Data Maximum Gradient
Design Speed
Kph
Gradient, %
Rural Intermediate RoadsVillage Access
Flat/Rolling Mountainous Escarpment
20 - 14(1)
15(2)
15(3)
30 - 11 11 11
-
7/27/2019 Design Manual 1
59/366
Rural Roads - Design Manual
Section 3Geometric Standards
Republic of Yemen
Ministry of Public Works and Highways
journey times and reduced vehicle operating costs. Benefits will increase
with increases in gradient, length of gradient, traffic flow, the proportion of
trucks, and in overtaking opportunities. The effect of a climbing lane inbreaking up queues of vehicles held up by a slow moving truck will
continue for some distance along the road.
Experience has shown that climbing lanes are unlikely to be justified other
than on a small proportion of roads with heavy flows.
As climbing lanes will be used largely by trucks and buses, they must be a
minimum of 3.0 meters in width. They must be clearly marked and, wherepossible, should end on level or downhill sections where speed differences
between different classes of vehicles are lowest to allow safe and efficient
merging manoeuvres.
3.6 CROSS SECTION
3.6.1 Rationale for Determining Road Widths
The cross section of a roadway is made up of:
Number and width of lanes
Shoulder width
Cross slopes
-
7/27/2019 Design Manual 1
60/366
Rural Roads - Design Manual
Section 3Geometric Standards
Republic of Yemen
Ministry of Public Works and Highways
Road class D: Village Access Roads with low volume of traffic (1000
vpd): a running surface width of 6 7m allows vehicles in opposing
directions to pass safely without the need to slow down or move laterally in
their lanes.
Economic considerations call for minimization of road width in order to
reduce construction and maintenance costs, whilst being sufficient to carry
the traffic flows efficiently and safely.
Table 3.12 shows the recommended values for carriageway, shoulder and
formation widths for various classes of roads.
Figure 3.1 shows typical road cross section with dimension ranges.
Rural Roads - Design ManualRepublic of Yemen
-
7/27/2019 Design Manual 1
61/366
g
Section 3Geometric Standards
pMinistry of Public Works and Highways
DOCS-0974-04 3-21
Table 3.12Summary of Standards for Various Cross Section Elements
Road Function
ApproxRange of
Traffic Flow
(ADT)
No. of LanesLane width
(m)
C/W width
(m)
Shoulder width
(m)
Cross Slopes (% )
Pavement Shoulders Formation
Rural Intermediate(Governorate)
400-3000 2 3.0-3.5 6-7 0.0-1.5 2.0% 2-3% 2-3%
Tertiary
(District)100-1000 2 2.5-3.0 5-6 0.0-1.0 2.0% 2-3% 2-3%
Feeder(Village Access)
-
7/27/2019 Design Manual 1
62/366
g
Section 3Geometric Standards
pMinistry of Public Works and Highways
DOCS-0974-04 3-22
ROAD MARKING
2-3%
2-3% 2-3%
2-3%
2%2%
FORMATION WIDTH
6 - 8
1 LANE1 LANE
2.5 3.5 2.5 3.5 0.5 1.50.5 1.5
CARRIAGEWAYGRAVEL
SHOULDERGRAVEL
SHOULDER
C
L
Min0.5
1.0
ALL DIMENSIONS ARE IN METERS
Crossfall
Figure 3.3 Typical Cross Section Terminology and Dimensions
Slope normally
1V:2H for depth
of 2m, or in
accordance with
type of soil and
depth
Slope
according to
type of soil and
depth of Cut.
For existing
alignments a
slope of 1:10may be used
Drainage ditch
usually V-shaped.
Other shapes mayalso be used.
Surfacing
Base
Subgrade
-
7/27/2019 Design Manual 1
63/366
Rural Roads - Design Manual
Section 3Geometric Standards
Republic of Yemen
Ministry of Public Works and Highways
The shoulder widths depend upon the availability of Right-of-Way, type of
terrain and the type of the road base (bound or unbound). These are
observed to fall in the range of 0 to 2 meters. No paving is generally neededfor shoulders except in locations where water is likely to penetrate at the
edge of the pavement which is an area particularly vulnerable to structural
damage. Shoulders should also be paved if the level of traffic flow
approaches the upper limit for a particular design class. In such cases a
surface dressing or other seal may be applied.
For 2-lane paved roads with carriageway width greater than 5 meters, full
shoulders may be omitted in mountainous and escarpment type terrainwhere the costs of achieving desired cross sections are very high. In this
case the minimum paved width shall be 5.5 meters and side drains and edge
barriers should be given special considerations.
For single lane roads the carriageway width shall be 3.0m. Shoulders
widths may be 0-1.5m depending on traffic volume, mix and terrain.
Two lane roads should be delineated by continuous lines at least 10cm wide
situated on the shoulder immediately adjacent to the running surface.
Centerline markings are also recommended on roads of at least 5m width.
3.6.3 Cross Slope
Cross slope (crossfall) is needed on all roads to assist in the draining of
-
7/27/2019 Design Manual 1
64/366
Rural Roads - Design Manual
Section 3Geometric Standards
Republic of Yemen
Ministry of Public Works and Highways
the excavation of ditches on tracks through steep sidelong ground. In such
cases drainage details should be provided. Figure 3.4 shows this concept
with is advantages and disadvantages. Drainage channel shape and slope ofcutting are determined according to soil and terrain types.
Side Slopes
V1 V2Sound Rock Weathered Rock Sity Sand H
-
7/27/2019 Design Manual 1
65/366
Rural Roads - Design Manual
Section 3Geometric Standards
Republic of Yemen
Ministry of Public Works and Highways
places and the potential difficulty of reversing. In general, passing places
should be constructed at the most economic locations as determined by
terrain and ground condition, such as at transitions from cut to fill, ratherthan at precise intervals.
The length of individual passing places will vary with local conditions and
the sizes of vehicles in common use but, generally, a length of 20 meters
including tapers will cater for most commercial vehicles on roads of this
type.
A clear distinction should be drawn between, passing places and lay-bys.Lay-bys may be provided for specific purposes, such as parking or bus
stops, and allow vehicles to stop safety without impeding through traffic
Rural Roads - Design Manual
S 3 G S d d
Republic of YemenMi i f P bli W k d Hi h
-
7/27/2019 Design Manual 1
66/366
Section 3Geometric StandardsMinistry of Public Works and Highways
DOCS-0974-04 3-26
Cross-Section with Cross-fall to Valley Side Cross-Section with Cross-fall to Mountain Side
Advantages Disadvantages Advantages Disadvantages
- no side drains required, resulting insubstantial reduction in earthworks.
- less cross-drainage structures required
- evenly spread surface water runoff alongroad edge reduces erosion problems.
- potentially dangerous for vehicles slidingwhen surface slippery
- careful maintenance of surface required toensure water drains evenly over shoulders
- when gradient exceeds 8 percent, cross-fallmust be changed to mountain side.
- safer for vehicles in wet and slipperyconditions
- wider formation improves sight distance
- critical outside edge of road less prone todamage
- controlled surface drainage outlets
- more earthworks because of the increasedwidth to accommodate drainage.
- higher back slopes requiring protection.
- frequent cross-drainage structures required
- more expensive
Source: WB Technical Paper 496.
Figure 3.5Alternative Cross Sections in Mountainous Terrain
Shoulder
50 - 100
C
L
Carriageway200-250
Catch water drains where
required; masonry lined
channel and/or polythene
sheet to avoid water from
seeping into slope material
Drain
60 - 80
3% - 5%
In situ soil or
optional gravel
Bio-engineering
slope protection on
slopes below and
above road
Side drain: in weak
material to be
masonry linedNote: cut and fill to balance, avoid
spoil as much as possible
Construction steps: to allow for careful
excavation with minimal disturbance of
natural slope and regular, well compactedfill layers on stable ground
-
7/27/2019 Design Manual 1
67/366
SECTION 4
EARTHWORKS AND PAVEMENT
Section
4
-
7/27/2019 Design Manual 1
68/366
Rural Roads - Design Manual
Section 4 - Earthworks and Pavement
Republic of Yemen
Ministry of Public Works and Highways
SECTION 4
EARTHWORKS AND PAVEMENT
TABLE OF CONTENTS
Page
4.1 General Definitions 14.1.1 Subgrade 14.1.2
Base 1
4.1.3 Surfacing 14.1.4 Pavement Section 24.2 Earthworks 44.2.1 Geotechnical Surveys 44.2.2 Borrow Pits & Dump Sites Location 44.2.3 Sand Dune Areas 74.2.4 Excavation 84.2.5 Embankments 94.3 Subgrade 104.3.1 General 104.3.2 Classes of Subgrade Bearing Strength 104.3.3 Improved Subgrade 114.4 Pavement Materials 11
-
7/27/2019 Design Manual 1
69/366
Rural Roads - Design Manual
Section 4 - Earthworks and Pavement
Republic of Yemen
Ministry of Public Works and Highways
SECTION 4
EARTHWORKS AND PAVEMENT
4.1 GENERAL DEFINITIONS
4.1.1 Subgrade
- Subgrade is all the material below the pavement and may include
in-situ material, fill and improved subgrade. For assessing anysection of subgrade the average CBR should be at least equal to the
median for the category selected, and no CBR value should fall
below the lowest value in the range. When subgrade CBR is below
30% it is to be replaced by suitable material with CBR more than
30% for a thickness of 20cm.
- Improved Subgrade is a granular capping layer of selected fill
material, the top of which is at formation level, placed where thenatural in-situ or fill material is unsuitable for the direct support of
the pavement.
- Formation is the surface of the ground, in its final shape, upon
which the pavement structure, consisting of base and surfacing is
constructed.
-
7/27/2019 Design Manual 1
70/366
Rural Roads - Design Manual
Section 4 - Earthworks and Pavement
Republic of Yemen
Ministry of Public Works and Highways
- Bituminous Binders are petroleum-derived adhesives used to stick
chippings on to a road surface, in surface dressings or to bind
together a layer of asphalt concrete wearing course.
- Cutback Bitumenis a bitumen whose viscosity has been reduced by
the addition of a volatile diluent.
- Bitumen Emulsionis a binder in which petroleum bitumen, in finely
divided droplets, is dispersed in water by means of an emulsifying
agent to form a stable mixture.
- Prime Coatis an application of low viscosity bituminous binder to
an absorbent surface, usually the top of the base. Its purposes are to
waterproof the surface being sprayed and to help bind it to theoverlaying bituminous course.
- Tack Coat is a light application of bituminous binder to a
bituminous or concrete surface to provide a bond between this
surface and the overlaying bituminous course.
4.1.4 Pavement Section
There are four types of pavement that can be used for rural intermediate
roads and village access roads:
1a. Flexible Asphalt Concrete Pavement Section comprises a 40mm
thick layer of asphaltic concrete on top of high quality crushed
aggregate base course layer or crushed natural granular material. Its
use is economically justified only for the high traffic categories and
-
7/27/2019 Design Manual 1
71/366
Rural Roads - Design Manual
Section 4 - Earthworks and Pavement
Republic of Yemen
Ministry of Public Works and Highways
20cm
If subgrade strength (CBR) is 30% for 20cm.
Bituminous Surface
Dressing
Fractured rock granular
Base Course
In-situ Material or
Selected Fill
Formation
Subgrade
Pavement
Asphalt ConcreteSurfacing
-
7/27/2019 Design Manual 1
72/366
Rural Roads - Design Manual
Section 4 - Earthworks and Pavement
Republic of Yemen
Ministry of Public Works and Highways
4.2 EARTHWORKS
4.2.1 Geotechnical Surveys
Geotechnical surveys are carried out at three stages in the project
preparation process at increasing levels of detail: 1) identification, 2)
feasibility and 3) design.
For new roads geotechnical surveys are conducted to select and compare
alternative routes for the road. Information is obtained on the supportingground for the road, earthworks, bridge sites, drainage, materials and water
for construction.
For upgrading and reconstruction works, geotechnical information is
needed to determine the choice and properties of materials that are
available for use in pavement construction.
For route location, the principal terrain related factors include(1):
- Subgrade strength, or present instability problems.
- Materials used in construction.
- Earthworks (cuttings and embankments).
- Surface and subsurface drainage.
- The need for structures.
Rural Roads - Design Manual
Section 4 - Earthworks and Pavement
Republic of YemenMinistry of Public Works and Highways
-
7/27/2019 Design Manual 1
73/366
Section 4 a thwo ks and avementy g y
DOCS-0974-04 4-5
TABLE 4.1STEPS OF THE GEOTECHNICAL SURVEY PROCESS BY PROJECT PREPARATION STAGE
Project Preparation Stage Purpose and Means Information Sought
1. Identification
Reconnaissance Stage
To identify possible alternative routes in terms of corridors
using:
- maps- satellite images 1:25,0001:500,000 (if necessary)- air photo mosaics 1:100,000
Boundaries between terrain types and changes in topography, geology,
drainage pattern, vegetation and land use, with consideration to:
- courses of major rivers- catchment areas of major river systems- extent of flooding of low-lying areas- possible sources of water for construction- possible sources of construction materials- pattern of regional instability- extent of erosion- spread of deforestation- assessment of land acquisition/site clearance problems- location of all possible bridge sites.
2. Feasibility To carry out an appraisal of the corridors in order to select thebest route using:
1. air photos: 1:20,000 1:60,000 supplemented, if necessary,by color information from satellite images.
2. site investigations of alternative routes to note key physicaland geotechnical features.
3. selected lab tests.4. cost comparison of alternative alignments.
Following items to be investigated:
- foundation conditions-
catchment areas and the location of culverts- location of spoil areas and possible borrow areas- possible sources of construction materials- identification of most favourable bridge sites- possible major hazard areas such as poorly drained soils, spring lines,
unstable areas, erosion in river courses.
3. Design for implementation Detailed field studies of the selected route with detailed airphoto interpretation to help plan a comprehensive site
investigation with full sampling and testing program.
Testing program should include:
- construction materials- subgrade conditions- cuttings and embankments- areas of instability- erosion and soft ground- requirements for frequency and size of culverts- bridge sites
l d lbli f
-
7/27/2019 Design Manual 1
74/366
Rural Roads - Design Manual
Section 4 - Earthworks and Pavement
Republic of Yemen
Ministry of Public Works and Highways
In addition, the selection of dumping sites depends on the type of dumped
material with respect to the site material. It should be kept in mind that if
the dumped material contains contaminated substances, it should be
dumped away from any ground water recharges areas and other
environmental factors should be accounted for. Furthermore, the effect of
the bulk volume and weight of the dumped stock pile should be studied in
such a way as not to impose failure of below strata due to gravity.
Due to the excavation works, an instability status may develop causing
local or global failures that influence the surroundings. These problems
may be avoided if a prior assessment of the existing ground conditions isperformed; this covers an assessment of the rock discontinuities and/or soil
parameters. Moreover, environmental impact assessment and hydro-
geological studies should be performed to avoid any damage to nature or
water recharge areas.
In line with the above, the following steps shall be carried out for
identifying borrow areas and dump sites:
1. Site topographical survey to determine the boundary limits of the
proposed site and the estimated quantities.
2. Visual inspection of in-place conditions to give the minimum
possible safe distance between the borrow area boundary and
surrounding sites, for example archeological site, natural resources,
R l R d D i M lR bli f Y
-
7/27/2019 Design Manual 1
75/366
Rural Roads - Design Manual
Section 4 - Earthworks and Pavement
Republic of Yemen
Ministry of Public Works and Highways
4.2.3 Sand Dune Areas
All roads in sand dune areas require careful investigation to ensure that the
accumulation of sand is minimized and does not provide a hazard to the
road user. It is important that the alignment is selected after careful
consideration of the wind direction. If at all possible, roads should be
elevated on embankments above general dune crest height and cuts and all
features causing wind speed to drop and sand deposition to occur should be
avoided.
In areas of varying wind direction and where considerable dune movementis occurring, extreme difficulty can be encountered in construction and
maintaining any type of road.
In dune areas, the availability of materials for road construction is usually
severely limited and the need to import material, often for considerable
distances should always be considered.
The following considerations should be used to select alignments intransverse and longitudinal sand dune areas:
If the road is parallel or inclined to dune but perpendicular to theprevailing wind direction, few problems are usually encountered. The
road should be constructed in the interdune spaces keeping away from
the leeward side of any dunes. If two transverse sand dunes are
R l R d D i M lR bli f Y
-
7/27/2019 Design Manual 1
76/366
Rural Roads - Design Manual
Section 4 - Earthworks and Pavement
Republic of Yemen
Ministry of Public Works and Highways
Another possibility in transversing transverse dunes is to join thecrests of the dunes rather than cutting dunes. Stable slopes of one in
six need to be provided.
Road alignment in the wind direction poses few problems and caneasily follow the line of interdune plain in the case of sand dunes.
However, in the case of several longitudinal sand dunes being located
adjacent to each other, the alignment should be located on the dune
lee slope since this requires minimum cut and fill.
Roads perpendicular to wind direction (or parallel to longitudinaldunes) or inclined to it, pose serious problems, since the prevailingwind direction is similar to that of the axes of the dunes. Cuttings and
embankments can be subjected to serious sand drift and erosion.
Valleys or saddles in a chain of longitudinal sand dunes can be safelyutilized for aligning the road. The alignment of the road will often
become circuitous by following the interdune spaces but will be the
best from construction and maintenance points of view.
4.2.4 Excavation
General
Wherever a cutting is required, consideration needs to be given to the
following factors that will affect its design and cost:
R l R d D i M lR bli f Y
-
7/27/2019 Design Manual 1
77/366
Rural Roads - Design Manual
Section 4 - Earthworks and Pavement
Republic of Yemen
Ministry of Public Works and Highways
- Clay 3V:1H- Weathered rock 4V:1H- Sound rock 6V:1H (in existing alignments it
can be relaxed to 10:1)
In the following situations, analytical slope stability appraisals shall be
performed based on parameters obtained through detailed site investigation
and associated laboratory testing:
- Jointed rock conditions- Problematic material- Water table situations- Cutting depth exceeding 8 meters(ii ) Other Factors
Partly for aesthetic and safety reasons a low angle slope is normally
considered more desirable than a near vertical one, even if other factors will
allow this latter course. The need for, or the surplus of fill material, willalso have an influence on slope angles.
In deep cuttings, where the pavement is laid shortly after completion of the
cutting, consideration should be given to heave.
Guidance on satisfactory slope angles from the points of view of both
Rural Roads Design ManualRepublic of Yemen
-
7/27/2019 Design Manual 1
78/366
Rural Roads - Design Manual
Section 4 - Earthworks and Pavement
Repub