Design Manual 1

download Design Manual 1

of 366

Transcript of Design Manual 1

  • 7/27/2019 Design Manual 1

    1/366

    REPUBLICOFYEMEN

    MINISTRYOF PUBLICWORKSANDHIGHWAYS

    RURALACCESSPROJECT

    CENTRALMANAGEMENTOFFICE(RAPCMO)

    RURALROADS

    DESIGNMANUAL

    ISSUED:OCTOBER 2004

    REVISED FEBRUARY 2005

  • 7/27/2019 Design Manual 1

    2/366

    REVISED: FEBRUARY 2005

  • 7/27/2019 Design Manual 1

    3/366

    SECTION 1

    INTRODUCTION

    Section

    1

  • 7/27/2019 Design Manual 1

    4/366

    Rural Roads Design Manual

    Section 1 - Introduction

    Republic of Yemen

    Ministry of Public Works and Highways

    SECTION 1INTRODUCTION

    TABLE OF CONTENTS

    Page

    1.1 Background 11.2 Objectives 21.3 Scope 21.4 Design Process 31.5 RAP Roads Design Philosophy 6

  • 7/27/2019 Design Manual 1

    5/366

    Rural Roads Design Manual

    Section 1 - Introduction

    Republic of Yemen

    Ministry of Public Works and Highways

    SECTION 1

    INTRODUCTION

    1.1 BACKGROUND

    Insufficient infrastructure and inadequate access to social services have

    been a major deterrent to rural development in Yemen. In 1995 there was

    about 64,500 km of roads, 4,800 km of them paved (about 7.5%). Many

    areas are inaccessible to vehicles leaving a large sector of the populationsuffering from accessibility problems to the basic services they need. In

    1996 there were 229,000 passenger cars, a ratio of 31 people per car. In

    remote areas people rely principally on non-motorized transport.

    The Rural Access Program initiated by the Government of Yemen with

    support from the World Bank aims at improving the livelihood and

    reducing the isolation of the rural population in Yemen.

    To achieve this objective, the Program will improve planning and

    implementation of rural roads, thereby reducing a major obstacle to rural

    economic growth caused by poor access. The Program will be implemented

    in three phases:

    Phase I : (2001 to 2005) is setting up the institutional and technicalf d ti f l d j t Th h h b

  • 7/27/2019 Design Manual 1

    6/366

    Rural Roads Design Manual

    Section 1 - Introduction

    Republic of Yemen

    Ministry of Public Works and Highways

    1.2 OBJECTIVES

    The Ministry of Public Works and Highways Rural Access ProjectCentral Management Office (RAP-CMO) is in the process of contracting

    local consultants who will be responsible for the preparation of detailed

    design and supervision of construction for a number of Rural Intermediate

    Roads and Village Access Roads.

    As a part of the capacity building process adopted by RAP for local

    consultants, RAP has undertaken to develop comprehensive standards forrural roads to serve the country in effectively developing this sector.

    This Design Manual addresses the needs of road engineers and designers

    for safe, economical and environmentally sound designs of rural roads and

    rural intermediate roads in Yemen at the levels of the Governorate, District

    as well as Village Access. These roads are typically low volume roads with

    average daily traffic in the range of 100-1000 vehicles per day, located in

    various types of terrain and climatic conditions prevailing in Yemen.

    1.3 SCOPE

    The scope of work for developing this manual included review of existing

    design guidelines and standards developed previously, comments from

    MPWH and RAP, field visits undertaken to various projects sites,

    di i ith lt t d t t ll th k h

  • 7/27/2019 Design Manual 1

    7/366

    Rural Roads Design Manual

    Section 1 - Introduction

    Republic of Yemen

    Ministry of Public Works and Highways

    - AASHTOGuidelines for Geometric Design of Very Low-Volume

    Local Roads (ADT 400).

    - National Highway and Rural Access Master Plan Study Road

    Classification System, Ministry of Public Works and Highways

    Yemen.

    - TRL Road Note 6A Guide to Geometric Design, 1988.

    - TRL Road Note 31A Guide to the Structural Design of BitumenSurfaced Roads, 1993.

    - TRL Road Note 19 A guide to the design of hot mix asphalt in

    tropical and sub-tropical countries, 2002.

    - TRL Road Note 40A guide to axle load surveys and traffic counts

    for determining traffic loading on pavements, 2004.

    - World Bank The Roads Economic Decision Model (RED),

    SSATP working paper No. 78, July 2004.

    - World BankRoads and the Environment Handbook.

    - RAPCMOSectoral Environmental Assessment, Vol. 1, 2004.

    RAPCMO S l E i l A V l 2 S f d

  • 7/27/2019 Design Manual 1

    8/366

    Rural Roads Design Manual

    Section 1 - Introduction

    Republic of Yemen

    Ministry of Public Works and Highways

    Traffic analysis ofalternative routes

    Economic analysis

    Environmental Screeningand Categorization

    2

    9

    10

    Project, Planning,

    Prefeasibility and

    Feasibility Studies

    Preliminary GeometricDesign

    Geotechnical Studies

    EA Consultations

    and Impact Analysis

    3

    4

    10

    PreliminaryDesign

    Geometric Design3

    Project Process ActivitiesSection of this

    Manual

  • 7/27/2019 Design Manual 1

    9/366

    Rural Roads Design Manual

    Section 1 - Introduction

    Republic of YemenMinistry of Public Works and Highways

    DOCS-0974-04 1-5

    EA

    Phases EA Planning:

    Project

    Identification and

    Project Concept

    Preliminary and

    Final DesignProject Tendering

    Execution

    Project Managementand Supervision

    Project Completion

    and Post Evaluation

    Operation and

    Maintenance

    Project Cycle

    Processes

    Project Phases Operation &

    MaintenanceConstructionProject Preparation and Design

    Planning,Pre-feasibility and

    Feasibility Studies

    - Scoping and

    Screening

    - Identification of

    issues and

    applicable

    safeguards policies.

    - Categorization

    - Action plan

    CMO - E&S UnitResponsibilities

    EA, SFA &

    Consultations

    - Draft EA

    - Draft SFA

    - Womenconsultations

    - Disclosure of draft

    EA and SFA to

    communities

    - Signing of Final

    SFA

    - Final version of EA

    Consultant /

    CMO - E&S Unit

    Environmental

    ContractSpecification

    - Incorporation of

    EMP into contract

    documents

    - Pre-tender briefing

    CMO - E&S unit /Consultant, Districts

    & Communities

    Implementation and

    Monitoring

    - EMP

    implementation

    - Compliance

    monitoring and

    reporting on

    environmental and

    social mitigation

    measures

    Consultant /

    CMO - E&S Unit

    Post Evaluation

    - Compliance

    summary

    - Unanticipated

    impacts

    - Lessons learned

    ContractorsCMO - E&S Unit, RE

    & Local Community

    O & M Monitoring

    - Compliance

    monitoring and

    reporting onenvironmental and

    social mitigation

    measures

    ContractorsCMO - E&S Unit RE

    & Local Community

    EA

    Activities

    Figure 1.2- Integration of Environmental and Social Management Process in the Project Cycle

  • 7/27/2019 Design Manual 1

    10/366

    Rural Roads Design Manual

    Section 1 - Introduction

    Republic of Yemen

    Ministry of Public Works and Highways

    1.5 RAP ROADS DESIGN PHILOSOPHY

    The fundamental characteristics of rural roads that distinguish them fromother roads in the national network include:

    - Low traffic volumes with ADT generally < 1000 vehicles per day,

    with many roads having ADT 400 vpd. Such volumes of traffic

    indicate that accident-prone encounters between vehicles are rare

    events and the probability of collision is small.

    - The rural and local access natures of these roads indicate that most

    drivers using them are familiar with their nature as well as the

    nature of the terrain traveled. This familiarity reduces the elements

    of risk resulting from design features that may surprise unfamiliar

    drivers, but are anticipated by familiar drivers.

    - The nature of the mountainous terrain in Yemen makes it

    economically prohibitive, or physically impossible to constructroads at the normal standards. Thus, relaxed standards are

    necessary in order to ensure a cost-effective approach to the road

    system. Relaxation of standards apply especially for roads in

    difficult mountainous terrain and for road projects involving

    existing tracks or existing alignments where full reconstruction is

    economically unjustified. Thus the designer is encouraged to relax

    the standards to avoid unnecessary improvement on existing

    li b l l k f id f i ifi f

  • 7/27/2019 Design Manual 1

    11/366

    Rural Roads Design Manual

    Section 1 - Introduction

    Republic of Yemen

    Ministry of Public Works and Highways

    safety conservative and risk-averse, providing a margin of safety that takes

    into consideration a wide range of conditions that might occur on the road

    system. They are not based on rigorous cost-effectiveness approach, buthave established values that are judged to be reasonable and prudent, given

    overall costs, impacts, and benefits.

    The design guidelines for very low-volume roads developed by AASHTO

    are based on safety risk assessment which results in comparable margins of

    safety presented in the AASHTO Policy on Geometric Design of

    Highways and Streets for higher volume roads.

    For rural low volume roads the design criteria should be based on tradeoffs

    between, on one hand, differences in construction and maintenance costs,

    and estimated impacts on safety. This makes cost-effectiveness as the

    appropriate basis for defining minimum design criteria or values for low

    volume rural roads.

    This Manual is prepared to be a fairly comprehensive document and tocover all the important elements of rural road designs encountered by

    RAP. Yet, no manual can supersede good engineering judgment and

    the application of sound principles by knowledgeable designers who

    can tackle unique and often conflicting design requirements and

    develop tailored solutions to specific design problems.

  • 7/27/2019 Design Manual 1

    12/366

    SECTION 2

    ROAD CLASSES, DESIGN SPEED

    AND TRAFFIC

    Section

    2

  • 7/27/2019 Design Manual 1

    13/366

    Rural Roads Design Manual

    Section 2 - Road Classes, Design Speed and Traffic

    Republic of Yemen

    Ministry of Public Works and Highways

    SECTION 2ROAD CLASSES,DESIGN SPEED AND TRAFFIC

    TABLE OF CONTENTS

    Page

    2.1 Introduction 12.2 Road Classes 12.2.1 Roads Functional Classification 12.2.2 RAP Roads Design Classes 42.3 Design Speed 62.3.1 Design Speed Criteria 62.3.2 Design Speed Standards 72.3.3 Relaxation of Standards 72.4 Traffic 102.4.1 Design Life 102 4 2

    B li T ffi Fl E ti ti 11

  • 7/27/2019 Design Manual 1

    14/366

    Rural Roads Design Manual

    Section 2 - Road Classes, Design Speed and Traffic

    Republic of Yemen

    Ministry of Public Works and Highways

    SECTION 2

    ROAD CLASSES,DESIGN SPEED AND TRAFFIC

    2.1 INTRODUCTION

    The criteria used in the geometric design shall be pertinent to the local

    conditions with respect to technical application and development trends.

    They shall further be economically feasible, taking into consideration all

    the relevant conditions and circumstances such as climate, topography andgeotechnical conditions encountered in the different regions of the country.

    The design standards shall not impose any limits on the needs of society for

    the development of transportation and the implementation shall be

    undertaken with due regard to all relevant data and conditions, both

    existing and forecast. In this Section of the Manual, special emphasis has

    been placed on the functional classification of roads and as these are

    considered the most important parameters for harmonization of RAP road

    projects within the national road network.

    Economic constraints may justify adoption of lower geometric standards

    than are desirable, but economic restrictions will not justify abandoning a

    balanced geometric design by downgrading only some of the design

    elements, as for example, reducing the formation width without adjusting

    th d i d di l H th t i d i ill

  • 7/27/2019 Design Manual 1

    15/366

    Rural Roads Design Manual

    Section 2 - Road Classes, Design Speed and Traffic

    Republic of Yemen

    Ministry of Public Works and Highways

    This functional concept is important to the design of new roads, and is

    consistent with a systematic approach to design and transportation

    planning.

    In general, the system consists of primary, secondary and tertiary networks

    according to mobility and function, importance at the national level, and

    administrative jurisdiction.

    The Road Classification System recommended by the National Highway

    and Rural Access Master Plan Study (NHRAMP) emphasizes the attribute

    of administrative responsibility. The rationale is to enable the enactment of

    Law No. 4 of 2000 on Local Authority, whereby Mohafazas and Mudiriyas

    will in the future assume the responsibility for Secondary and Tertiary

    Road Networks in their respective areas. The following classification has

    been recommended:

    i. National (Primary) Road Network

    Jurisdiction: Ministry of Public Works and Highways (MPWH).

    Function: Primary routes linking major regions and formingdirect connections between Sanaa and the

    Mohafaza Centers, primary regions, and major

    international border crossings.

    Trip Lengths: Likely to be long and speeds relatively high.

    Geometric Standards: High.

  • 7/27/2019 Design Manual 1

    16/366

    Rural Roads Design Manual

    Section 2 - Road Classes, Design Speed and Traffic

    Republic of Yemen

    Ministry of Public Works and Highways

    District Centers, between National Roads and

    District Centers, Secondary ports and to secondary

    border crossings. Collection and distribution oftraffic between the primary and tertiary roads within

    the region.

    Trip Lengths: Traffic flows and trip lengths are of an intermediate

    level.

    Geometric Standards: Adequate geometric standards. Speeds

    depend on the type of terrain.

    iii. District (Tertiary) Road Network

    At the District level, roads are currently under the jurisdiction of

    MPWH. It is expected that the responsibility for these roads will be

    transferred to the Governorate, and ultimately to the Districts when

    their capacity is strengthened.

    Two classes have been recommended in this category:

    Distr ict Roads

    Function: Provide links between Governorate Roads, and give

    access from District centers to subdistricts and

    between subdistricts. Roads with traffic volume

    greater than 100 vehicles per day to tourist sites,

    i

  • 7/27/2019 Design Manual 1

    17/366

    Rural Roads Design Manual

    Section 2 - Road Classes, Design Speed and Traffic

    Republic of Yemen

    Ministry of Public Works and Highways

    The Tertiary Roads have relatively short trip lengths, serving local traffic as

    their main function. A relatively low design speed is normally applicable to

    local roads, especially in mountainous areas.

    Rural Roads and Village Access Roads come under classes (ii) and (iii)

    above.

    2.2.2 RAP Roads Design Classes

    International practice is to design roads according to a design speed which

    varies depending on the functional class of the road and type of terrain.

    However, the concept of design speed is not always appropriate as the basis

    for geometric design as it can be uneconomic.

    Designs should be justified economically and the optimum geometric

    standards will depend on both construction and road user costs.

    Construction costs will be related to the terrain and choice of pavement,

    while road user costs are directly related to the volume and composition oftraffic. It is therefore recommended that the basic parameters for road

    function, terrain type and traffic flow are defined initially. On the basis ofthese parameters, a design class is selected, while design speed is used only

    as an index which links design class to the design parameters of sight

    distance and curvature to ensure that a driver is presented with a reasonably

    consistent speed environment.

    RAP R d F ti l Cl ifi ti

  • 7/27/2019 Design Manual 1

    18/366

    Rural Roads Design Manual

    Section 2 - Road Classes, Design Speed and Traffic

    Republic of Yemen

    Ministry of Public Works and Highways

    movement and access functions. It should be noted that in practice there are

    many overlaps of functions, and clear distinctions will not always be

    apparent on functional terms alone.

    The design of village access roads should be based on the criterion of

    achieving an appropriate level of access, and should be based on minimum

    requirements of radii, width, and gradient for economic purposes.

    TABLE 2.1RAPROADS FUNCTIONAL CLASSIFICATION AND DESIGN CLASSES

    Road ClassDesign

    Class

    Traffic

    Flow

    (ADT)

    Number

    of Lanes

    Surface

    Type

    RuralIntermedi

    ate

    Secondary

    (Governorate)

    Tertiary

    (District)

    A 1000-3000 2 paved

    B 400-1000 2 paved

  • 7/27/2019 Design Manual 1

    19/366

    Rural Roads Design Manual

    Section 2 - Road Classes, Design Speed and Traffic

    Republic of Yemen

    Ministry of Public Works and Highways

    400-1000 vehicles per day. Design to the higher Design Class would result

    in an overdesigned facility during almost the whole of its life. If the initial

    flow were 410 vpd, design would still be Design class B.

    Types of Terrain

    The following classification of terrain types is adopted:

    Flat terrain Flat or gently rolling country which offers few obstacles tothe construction of a road having continuously unrestricted

    horizontal and vertical alignment (transverse terrain slopemax. 5%).

    Rolling terrain Rolling, hilly or foot-hill country where the slopes generally

    rise and fall moderately gently and where occasional steepslopes may be encountered. It will offer some restrictions inhorizontal and vertical alignment (transverse terrain slope

    5% - 20%).Mountainous

    terrain

    Rugged, hilly and mountainous country with river gorges.

    This class of terrain imposes definite restrictions on thestandard of alignment obtainable and often involves longsteep grades and limited sight distances (transverse terrainslope more than 20%).

    Escarpment

    terrain

    Long precipitous clifflike ridge commonly formed by

    faulting. This class of terrain introduces restrictions on cross-section width, lateral clearances, and driving safety.

    I l i i i h h diffi l d d f

  • 7/27/2019 Design Manual 1

    20/366

    Rural Roads Design Manual

    Section 2 - Road Classes, Design Speed and Traffic

    Republic of Yemen

    Ministry of Public Works and Highways

    maximum speed that could be attained on any road is dictated by the

    geometric characteristics of that road, other factors such as surface type and

    drivers perception of safety play a major role in setting the design speed.As for village access, the only influencing feature is the character of the

    terrain, since it is an established fact that these roads carry very low traffic

    volumes, and they are treated as low cost access roads, which eliminates

    the economic factor.

    2.3.2 Design Speed Standards

    Vertical and horizontal alignment, sight distance, and superlevation will

    vary appreciably with design speed. Such features as pavement width,

    shoulder width, and side clearances are usually not affected. On the other

    hand, the actual speeds are determined by geometry and the quality of the

    road surface.

    The choice of design speed shall be a logical one with respect to the

    different influencing features taking into account drivers behaviorespecially in flat terrain in Yemen. Accordingly, design speeds that are

    considered on the rural intermediate roads and village access range between

    20 kph in the difficult escarpments and 100-120 kph in flat areas with

    good visibility. Needless to say that for some extreme stretches, the speed

    may not exceed 10 kph. Table 2.1 presents proposed design speeds on

    different terrain types.

    TA 2 2 D S G S S O A OA S O A

  • 7/27/2019 Design Manual 1

    21/366

    Rural Roads Design Manual

    Section 2 - Road Classes, Design Speed and Traffic

    Republic of Yemen

    Ministry of Public Works and Highways

    In other cases, an already acceptable rate of return may be increased

    substantially by the inclusion of a short section of substandard road where

    achievement of the design standard would be expensive, although the safetyimplications of this would need careful consideration.

    Segments subject to speed reduction should have appropriate signing or

    other warning measures. On low flow roads where most of the drivers will

    be regular users, the increased risk will be less significant and the resultant

    number of accidents should be negligible. Greater care and consideration

    should be given to relaxations on high flow/high speed alignments.

    In special circumstances, where standards have been reduced on successive

    design elements, further relaxations may be made based on those reduced

    approach speeds. Sight distances, and the potential accident risk as a result

    of driver error, would need to be considered on a site-specific basis.

    Reductions in standards should only apply to stopping distances and

    curvature. Widths should not be reduced as they are particularly flowrelated, and additional widening may be required on curves with the tighter

    radii (TRRL Road Note No.6).

    The nature of the mountainous terrain in Yemen makes it economically

    prohibitive, or often physically impossible to construct roads at the normal

    standards. Thus, relaxed standards are necessary in order to ensure a cost-

    effective approach to the road system. Relaxation of standards apply

    i ll f d i diffi l i i d f d j

  • 7/27/2019 Design Manual 1

    22/366

    Rural Roads - Design Manual

    Section 2 - Road Classes, Design Speed and Traffic

    Republic of YemenMinistry of Public Works and Highways

    DOCS-0974-04 2-9

    TABLE 2.3DESIGN SPEED FOR RURAL ROADS BY DESIGN CLASS,TRAFFIC VOLUME AND TYPE OF TERRAIN

    Road ClassDesign

    ClassTraffic Flow

    Number of

    Lanes

    Surface

    Type

    Design Speed (Km/h)

    Flat Rolling Mountainous Escarpment

    RuralIntermediate

    Secondary

    A 1000-3000 2 paved 120 80 40 20

    (Governorate)

    Tertiary

    B 400-1000 2 paved 100 70 40 20

    VillageAccess

    (District)

    C 100-400 2

    paved 100 70 40 20

    unpaved 80 60 30 20

    Feeder

    D < 100 1

    paved 80 60 30 20

    unpaved 60 50 30 20

  • 7/27/2019 Design Manual 1

    23/366

    Rural Roads - Design Manual

    Section 2 - Road Classes, Design Speed and Traffic

    Republic of Yemen

    Ministry of Public Works and Highways

    2.4 TRAFFIC

    Traffic volume and composition are needed for the purpose of geometricdesign and the evaluation of economic benefits. On the other hand,

    pavement design is mainly based on the magnitude of individual axle loads

    and their frequency over the design life. Because the lighter vehicles have

    negligible contribution to pavement damage, they may be ignored and only

    the number of axle loading of the heavier vehicles need be considered.

    This section covers the methodology for estimating traffic flows and

    determining the esa cumulative number (see TRL Road Note 31). This

    methodology is shown in Figure 2.1 below.

    2.4.1 Design Life

    The choice of a design period is mainly governed by budgetary

    considerations, whereby in order to reduce the initial expenditures lower

    design periods may be considered.

    An economic analysis period of 10-20 years from the date of opening is

    normally used. At the end of the analysis period the road will still have a

    residual value. A pavement design life of 15 years is considered appropriate

    for many road projects. At the end of the design life, the pavement will

    need to be strengthened to be able to carry traffic over a further period.

    h i d i i d h ld b f d i h lif

  • 7/27/2019 Design Manual 1

    24/366

    Rural Roads - Design Manual

    Section 2 - Road Classes, Design Speed and Traffic

    Republic of Yemen

    Ministry of Public Works and Highways

    Determine DesignLife

    Survey of baseline

    Traffic Flows

    Traffic Forecasting

    -Normal traffic

    -Diverted traffic

    -Generated traffic

    Establishing axleloading

    -Survey of axle Loads

    -i i

  • 7/27/2019 Design Manual 1

    25/366

    Rural Roads - Design Manual

    Section 2 - Road Classes, Design Speed and Traffic

    Republic of Yemen

    Ministry of Public Works and Highways

    volumes are taken in one direction which requires care in interpreting

    AADT figures.

    Another estimate of daily traffic is the Average Daily Traffic (ADT)

    which is defined as the total traffic in both directions over a given period

    less than one year divided by the number of days in that period. The longer

    the period of traffic counts the more accurate the ADT approximates

    AADT, as traffic flows have daily, weekly and seasonal variations. Roads

    carrying less than 1000 vehicles per day exhibit high daily variability

    resulting in large errors in estimating ADT (and consequently annual traffic

    flows) from traffic counts measured over a period less than one week. A

    considerable decrease in the error of estimation can be realized with counts

    taken over a full week. This provides traffic flow data for work days,

    weekends as well as 24 hours variations. If a full week count is not

    possible, there should be at least one 24-hour count on a weekday and one

    during a weekend, with 16-hour counts on the other days. The 16-hours

    counts are grossed up to 24-hour values in the same proportion as the 16-

    hour/24 hour split (see section 2.4.7 below).

    In order to account for seasonal variations several one-week counts may be

    repeated, if possible, throughout the year. These automatic counts should be

    supplemented by manual classification counts to obtain information on

    vehicle classes.

    A formal country-wide traffic data collection program should be

  • 7/27/2019 Design Manual 1

    26/366

    Rural Roads - Design Manual

    Section 2 - Road Classes, Design Speed and Traffic

    Republic of Yemen

    Ministry of Public Works and Highways

    Such counts can be useful as a cross check on static counts and to assess

    the extent of daily or seasonal variations in traffic flow.

    2.4.3 Traffic Forecasting

    Three components contribute to overall traffic volumes:

    i. Normal Traffic

    Normal traffic is the traffic using the existing route if no pavement

    were provided.

    Normal traffic may be forecasted using linear time series

    extrapolation of traffic levels i.e. a fixed percentage increase. If

    Gross Domestic Product (GDP) forecasts are available, traffic flows

    can be forecasted by relating traffic growth linearly to GDP.

    ii. Diverted Traffic

    Diverted traffic is the traffic that is attracted from another route to

    the new road due to improved pavement.

    Traffic diversion occurs when parallel routes exist. Improving an

    existing road may result in diverting traffic from a shorter route

    because higher speeds and level of service are available on the

  • 7/27/2019 Design Manual 1

    27/366

    Rural Roads - Design Manual

    Section 2 - Road Classes, Design Speed and Traffic

    Republic of Yemen

    Ministry of Public Works and Highways

    responsiveness of traffic to the decrease in transport cost accruing

    from road improvement. Available data indicate that the elasticity

    of demand for passenger trips is slightly greater than one, while thatfor goods is much lower.

    In Section 9 of this Manual, generated traffic is defined by the

    Roads Economic DecisionModel in two components:

    i. Generated Traffic is the traffic attributable to decrease in

    transport costs, associated with existing users of the project

    road driving more frequently or driving further than before.

    Generated traffic may be defined as a percentage of the

    normal traffic, or by using a price elasticity of demand

    which reflects the % increase in traffic per percent decrease

    in transport costs.

    ii. Induced Traffic is the traffic attributable to local economic

    development, i.e. traffic attracted to the project due toincreased development activity in the roads zone of

    influence brought about by the project. Induced traffic is

    determined for each project alternative, each vehicle type

    and year induced.

    2.4.4 Axle Load Distribution

  • 7/27/2019 Design Manual 1

    28/366

    Rural Roads - Design Manual

    Section 2 - Road Classes, Design Speed and Traffic

    Republic of Yemen

    Ministry of Public Works and Highways

    1.1

    1.2

    1.21

    1.22

    1.22

    1.222

    1.2222

    1.2 + 2.2

  • 7/27/2019 Design Manual 1

    29/366

    Rural Roads - Design Manual

    Section 2 - Road Classes, Design Speed and Traffic

    Republic of Yemen

    Ministry of Public Works and Highways

    The equivalence factors that are used to convert single axle loads to

    equivalent standard axle is given by the relationship:

    Equivalence Factor = EF =

    4.5

    8.16

    (Tons)loadAxle

    Table 2.3 shows the equivalence factors (EF) for each of the wheel loads

    measured in the axle load survey. The above equation is used on all axle

    loads obtained by weighing axles separately. The EF per vehicle is obtained

    by adding the EFs for all axles of each vehicle. The factors for the axles aretotaled to give the equivalence factor for each of the vehicles. The mean

    equivalence factor for each class or type of vehicle traveling in each

    direction is then determined for all vehicles in the vehicle class whether

    loaded or empty.

    Table 2.3Equivalence Factors for different axle loads

    Wheel load

    (single & dual)(10

    3kg)

    Axle load(103kg) Equivalence FactorEF

    1.5 3.0 0.01

    2.0 4.0 0.04

    2.5 5.0 0.11

    3.0 6.0 0.25

    3.5 7.0 0.50

    4.0 8.0 0.91

    4.5 9.0 1.55

  • 7/27/2019 Design Manual 1

    30/366

    Rural Roads - Design Manual

    Section 2 - Road Classes, Design Speed and Traffic

    Republic of Yemen

    Ministry of Public Works and Highways

    (4) Determine the mean equivalence factor for each class of vehicle and

    for each direction from the results of the axle load survey (EF1i ,

    EF2i).

    (5) Calculate the cumulative equivalent standard axles for each

    direction (T1, T2) as follows:

    1i1i1 EFxVT , for direction 1 2i2i2 EFxVT , for direction 2

    T, the higher of the two directional values T1, T2 should be used for

    design.

    Where,

    T1 = Cumulative Equivalent Standard Axles for direction 1.

    T2 = Cumulative Equivalent Standard Axles for direction 2.

    V1i = Cumulative directional flow for class i vehicle over the design

    period for direction 1.

    V2i = Cumulative directional flow for class i vehicle over the design

    period for direction 2.

  • 7/27/2019 Design Manual 1

    31/366

    Rural Roads - Design Manual

    Section 2 - Road Classes, Design Speed and Traffic

    Republic of Yemen

    Ministry of Public Works and Highways

    In order to minimize the effects of errors of estimation and forecasting, the

    TRL Road Note 31 provides fixed structures for ranges of traffic as shown

    in Table 4.4. As long as the estimate of T is close to the center of a range,errors are not likely to affect the pavement design. If the value of T is close

    to the boundaries of the range, then sensitivity analyses should be made to

    ensure that the choice of traffic classes is appropriate.

    TABLE 2.4TRAFFIC CLASSESTraffic Classes Range (10

    6esa)

    T1 < 0.3

    T2 0.30.7T3 0.71.5

    T4 1.53.0

    T5 3.06.0

    T6 6.010

    T7 1017

    T8 1730

    2.4.7 Example on the analysis of traffic count data

    Given: A manual classified traffic count was conducted during a week in

    July on a site with equal traffic flow in both directions. The data for

    commercial vehicles are shown in Table A. The data for non-commercial

    vehicles has already been analyzed and gave an average number of 260

    vehicles per day. Information obtained from automatic traffic data recorded

    over a year is shown in Table B.

  • 7/27/2019 Design Manual 1

    32/366

    Rural Roads - Design Manual

    Section 2 - Road Classes, Design Speed and Traffic

    Republic of Yemen

    Ministry of Public Works and Highways

    TABLE AMANUAL CLASSIFIED TRAFFIC COUNT DATA IN BOTH DIRECTIONS

    HOURLY NUMBER OF COMMERCIAL VEHICLES

    Time Sat Sun Mon Tue Wed Thu Fri

    0:00-1:00 1 1

    1:00-2:00 0 0

    2:00-3:00 0 0

    3:00-4:00 1 0

    4:00-5:00 2 2

    5:00-6:00 3 1

    6:00-7:00 5 5 6 2

    7:00-8:00 11 12 13 3

    8:00-9:00 14 13 16 2 1

    9:00-10:00 18 17 20 4 2

    10:00-11:00 15 16 16 4 2

    11:00-12:00 13 12 14 5 1

    12:00-13:00 12 11 13 4 0

    13:00-14:00 8 7 8 3 1

    14:00-15:00 11 10 11 4 2

    15:00-16:00 12 11 10 5 2

    16:00-17:00 10 9 8 5

    17:00-18:00 8 7 9 3

    18:00-19:00 5 7 2

  • 7/27/2019 Design Manual 1

    33/366

    Rural Roads - Design Manual

    Section 2 - Road Classes, Design Speed and Traffic

    Republic of Yemen

    Ministry of Public Works and Highways

    Solution

    1. Average Daily Traffic (ADT)

    A = Estimated traffic count for Monday

    =counthour24of00:1800:12forcount

    counthour24talweekday tox

    00:1800:12for

    counttrafficactual

    = 55 x61

    158= 142

    B = Estimated traffic count for Tuesday

    =counthour24of00:2200:06forcount

    counthour24talweekday tox

    00:2200:06

    forcountactual

    = 146 x149

    158= 155

    C = Estimated traffic count for Wednesday

    = 85 x76

    158= 177

    Average weekday traffic = (Sun + Mon + Tue + Wed) / 4

    = (158 + 142 + 155 + 177) / 4

  • 7/27/2019 Design Manual 1

    34/366

    Rural Roads - Design Manual

    Section 2 - Road Classes, Design Speed and Traffic

    Republic of Yemen

    Ministry of Public Works and Highways

    2. Seasonal Correction Factors and AADT

    The seasonal correction factors are calculated from Table B as follows:

    Month ADT (CV)Seasonal Variation

    Factors

    Jan 145 1.05

    Feb 134 0.97

    Mar 132 0.95

    Apr 150 1.08

    Mai 161 1.16

    Jun 158 1.14

    Jul 125 0.90

    Aug 114 0.82

    Sep 120 0.86

    Oct 136 0.98

    Nov 145 1.05

    Dec 134 0.97

    Annual Mean 138 1.0

    From the ADT values above, it can be seen that the July value (125) is

    lower than the annual average value (138). The results from the traffic

    surveys carried out in July should be adjusted upwards accordingly to give

    the seasonally adjusted number.

    The traffic survey was carried out in July for which the adjustment factor is

  • 7/27/2019 Design Manual 1

    35/366

    Rural Roads - Design Manual

    Section 2 - Road Classes, Design Speed and Traffic

    Republic of Yemen

    Ministry of Public Works and Highways

    2.4.8 Example on Calculation of Equivalence Factors

    Given: Survey data for commercial vehicles shown in Table C.

    Calculate: 1) EF for axle roads, 2) EF for each vehicle, 3) Average EF for

    the vehicle type.

    TABLE CAXLE LOAD DATA FROM SURVEY

    No. TimeE=Empty

    F=FullLoad Type

    Axle Load (Tons)

    Axle 1 Axle 2 Axle 3

    1 7.05 E none 3.66 3.32 2.512 9.57 E none 2.68 4.38 2.71

    3 11.36 E none 4.00 2.81 2.64

    4 14.48 E none 4.20 5.46 5.45

    5 14.50 E none 4.04 4.80 4.53

    6 15.07 E none 4.11 3.86 2.49

    7 8.10 F Gravel 4.03 6.85 6.99

    8 8.14 F Gravel 5.32 13.31 13.14

    9 8.55 F Bottles 4.51 6.23 4.73

    10 9.21 F Gravel 6.30 12.94 14.36

    11 3.36 F Gravel 6.33 15.49 15.3212 3.39 F Gravel 6.07 14.75 14.56

    13 3.55 F Sand 6.50 14.56 14.24

    14 3.58 F Feeds 3.93 9.54 6.00

    15 10.15 F Gravel 3.80 6.09 6.18

    16 10.44 F Gravel 4.52 7.09 7.63

    17 10.52 F Gravel 4.26 7.17 6.88

    18 10.54 F Gravel 3.80 7.45 6.05

    19 14.32 F Sand 6.61 15.38 14.36

  • 7/27/2019 Design Manual 1

    36/366

    Rural Roads - Design Manual

    Section 2 - Road Classes, Design Speed and Traffic

    Republic of Yemen

    Ministry of Public Works and Highways

    TABLE DDATA ANALYSIS SHOWING EQUIVALENCEFACTORS

    No. Time E=EmptyF=Full

    LoadType

    Axle Load (Tons) Equivalence Factors Total EFper

    vehicleAxle 1 Axle 2 Axle 3 Axle 1 Axle 2 Axle 3

    1 7.05 E none 3.66 3.32 2.51 0.027 0.017 0.005 0.050

    2 9.57 E none 2.68 4.38 2.71 0.007 0.060 0.007 0.074

    3 11.36 E none 4.00 2.81 2.64 0.040 0.008 0.006 0.055

    4 14.48 E none 4.20 5.46 5.45 0.050 0.164 0.163 0.377

    5 14.50 E none 4.04 4.80 4.53 0.042 0.092 0.071 0.205

    6 15.07 E none 4.11 3.86 2.49 0.046 0.034 0.005 0.085

    7 8.10 F Gravel 4.03 6.85 6.99 0.042 0.455 0.498 0.935

    8 8.14 F Gravel 5.32 13.31 13.14 0.236 9.041 8.532 17.8099 8.55 F Bottles 4.51 6.23 4.73 0.069 0.297 0.086 0.452

    10 9.21 F Gravel 6.30 12.94 14.36 0.312 7.963 12.723 20.999

    11 3.36 F Gravel 6.33 15.49 15.32 0.319 17.891 17.024 35.233

    12 3.39 F Gravel 6.07 14.75 14.56 0.264 14.354 13.540 28.158

    13 3.55 F Sand 6.50 14.56 14.24 0.359 13.540 12.251 26.151

    14 3.58 F Feeds 3.93 9.54 6.00 0.037 2.020 0.251 2.308

    15 10.15 F Gravel 3.80 6.09 6.18 0.032 0.268 0.286 0.586

    16 10.44 F Gravel 4.52 7.09 7.63 0.070 0.722 0.733 1.031

    17 10.52 F Gravel 4.26 7.17 6.88 0.054 0.559 0.464 1.078

    18 10.54 F Gravel 3.80 7.45 6.05 0.032 0.664 0.260 0.956

    19 14.32 F Sand 6.61 15.38 14.36 0.388 17.225 12.723 30.335

    20 14.38 F Gravel 5.87 13.92 11.64 0.227 11.060 4.945 16.233

    21 14.45 F Sand 6.00 13.61 11.55 0.251 9.994 4.775 15.020

    22 15.19 F Sand 6.33 16.13 13.43 0.319 21.466 9.413 31.198

    23 15.50 F Fertilizer 6.44 12.53 7.62 0.345 6.889 0.735 7.969

    2. Calculating EF for each vehicle

  • 7/27/2019 Design Manual 1

    37/366

    Rural Roads - Design Manual

    Section 2 - Road Classes, Design Speed and Traffic

    Republic of Yemen

    Ministry of Public Works and Highways

    2.4.9 Example on Calculation of Cumulative Equivalent Standard Axles

    The result of an axle load survey on a road section for various truck typesand their annual growth rates are as follows:

    Truck Type Axle CodeADT one

    direction

    Mean EF for

    the Vehicle

    Type

    Annual

    Growth Rate

    (i)

    Medium Trucks 2 axlesGW < 11.5 Tons

    1.2 94 0.68 6%

    Heavy Trucks 2 axles

    GW > 11.5 Tons1.2 58 4.80 5%

    Heavy Trucks 3 axles

    GW > 11.5 Tons1.22 17 10.34 3%

    Heavy Truck - trailer

    4 axles1.222 9 8.85 3%

    Calculate the average annual numbers of equivalent standard axles for the

    current year for each truck type. Assuming the road section to be repaved

    during the current year, calculate the cumulative equivalent standard axlesfor a design life for the pavement of 15 years, and determine accordingly

    the appropriate traffic class for pavement design.

    Solution:

    1. Calculate the average daily esa in the current year:

  • 7/27/2019 Design Manual 1

    38/366

    Rural Roads - Design Manual

    Section 2 - Road Classes, Design Speed and Traffic

    Republic of YemenMinistry of Public Works and Highways

    DOCS-0974-04 2-25

    TABLE EDETERMINATION OF CUMULATIVE EQUIVALENT STANDARD AXLES

    Truck Type ADT (one direction) EF Average Daily esaesa current year

    (103esa)

    15-yr Cumulative

    Factor

    Cumulative esa for 15

    years (106esa)

    Medium Trucks 2 axlesGW > 11.5 Tons 94 0.68 64 23.36 23.28 0.54

    Heavy Trucks 2 axles

    GW > 11.5 Tons 65 4.80 312 113.88 21.59 2.46

    Heavy Trucks 3 axles

    GW > 11.5 Tons 17 10.34 176 64.24 18.6 1.20

    Heavy Truck - trailer4 axles 9 8.85 80 29.20 18.6 0.54

    T = 4.77

  • 7/27/2019 Design Manual 1

    39/366

    SECTION 3

    GEOMETRIC STANDARDS

    Section

    3

  • 7/27/2019 Design Manual 1

    40/366

    Rural Roads - Design Manual

    Section 3Geometric Standards

    Republic of Yemen

    Ministry of Public Works and Highways

    SECTION 3

    GEOMETRIC STANDARDS

    TABLE OF CONTENTS

    Page

    3.1 Introduction 13.2 Sight Distance 13.2.1 Stopping Sight Distance 13.2.2 Intermediate Site Distance 33.3 Superelevation 33.4 Horizontal Alignment 73.4.1 Circular Curves 73.4.2 Transition Curves 83.4.3 Improving Horizontal Alignment 103.4.4 Geometric Controls 10

  • 7/27/2019 Design Manual 1

    41/366

    Rural Roads - Design Manual

    Section 3Geometric Standards

    Republic of Yemen

    Ministry of Public Works and Highways

    SECTION 3

    GEOMETRIC STANDARDS

    3.1 INTRODUCTION

    As mentioned in Section 2, the geometric features for most of the rural

    roads in Yemen are governed by the natural terrain characteristics.

    However, this does not exclude the fact that the geometric design should be

    consistent with the traffic volume, composition of traffic and design speed.This Section provides a summary of the geometric design data and contains

    sufficient information for the majority of roadway design problems. A

    Policy on Geometric Design for Highways and Streets by the American

    Association of State Highways and Transportation Officials (AASHTO) is

    a reference in which the basic theory behind geometric design data is fully

    explained. Also, Guidelines for Geometric Design of Very Low-Volume

    Roads (ADT 400)by AASHTO, and TRRL Road Note No. 6 A guide

    to Geometric Design can be consulted.

    Several design standards from projects previously undertaken in Yemen

    have been reviewed. The Consultants have taken into consideration the

    technical aspect combined with the specific requirements of this project in

    developing a new set of geometric standards. The review covers the sight

    distance, horizontal and vertical alignment and cross sectional elements as

  • 7/27/2019 Design Manual 1

    42/366

    Rural Roads - Design Manual

    Section 3Geometric Standards

    Republic of Yemen

    Ministry of Public Works and Highways

    Stopping sight distance is generally determined as the sum of two

    distances:

    (1) Reaction Distance, the distance traveled by the vehicle from the

    instant the driver sights an object necessitating a stop to the instant

    the driver actually applies the brakes. This distance depends on the

    reaction time of the driver which varies according to the alertness of

    the driver. AASHTO Policy on Geometric Design for Highways

    and Streets uses a brake reaction time of 2.5s, while AASHTO

    Guidelines for Geometric Design of Low-Volume Local Roads

    (ADT 400) recommends a reaction time of 2s for rural roads.

    (2) Braking Distance, the distance required to stop the vehicle from

    the instant the brakes are applied. This distance is a function of the

    longitudinal friction factor, and thus deceleration of the vehicle.

    The stopping sight distance in the AASHTO Policy is given by the

    following formula which has two components corresponding to the twodistances mentioned above:

    a

    V039.0Vt278.0S

    2

    where,

    S = stopping sight distance, m

    t = brake reaction time, s

  • 7/27/2019 Design Manual 1

    43/366

    Rural Roads - Design Manual

    Section 3Geometric Standards

    Republic of Yemen

    Ministry of Public Works and Highways

    As discussed in Section 3.5.2, sight distance plays a key role in determining

    the minimum lengths of crest vertical curves. Stopping sight distance is

    measured from the drivers eyes (eye height, h1) to an object height (h2).AASHTO policy uses h1= 1080 mm and h2= 150mm or h2= 600mm if the

    object is a vehicle. With the increased use of SUVs, the average eye height

    has increased, so that h1could be assumed to be 1.4m and h215cm. This

    sight distance criterion should be checked for all classes of roads irrelevant

    of the number of lanes, traffic volume or pavement type. Measures to be

    taken to correct any deficiency include removal of obstacles, excavation of

    side slopes or trimming of sharp crest curves.

    3.2.2 Intermediate Site Distance

    The Intermediate sight distance is the distance needed for two drivers

    traveling with design speed to stop before colliding. This criterion is valid

    in the case of one-lane roads. For village access roads having a traffic load

    of less than 50 vehicles/day the intermediate sight distance can be neglected

    if the lane is widened up to at least 4.5m.

    Table 3.2 shows the proposed minimum normal and relaxed standards for

    sight distances related to design speeds for RAP roads.

    Table 3.2: Minimum Standards for Sight Distances Related to Design Speeds

    Design

    Speed,

    Minimum Sight Distance, m

    Stopping Intermediate

  • 7/27/2019 Design Manual 1

    44/366

    Rural Roads - Design Manual

    Section 3Geometric Standards

    Republic of Yemen

    Ministry of Public Works and Highways

    Superelevation may be defined as the rotation of the roadway cross section

    in such a manner as to overcome the centrifugal force that acts on a motor

    vehicle traversing a curve. On a superelevated carriageway, the centrifugalforce is resisted by:

    1. The weight component of the vehicle parallel to the superelevated

    surface and

    2. The side friction between the tires and the pavement.

    It is impossible to balance centrifugal force by superelevation alone,

    because for any given curve radius, a certain superelevation rate is exactlycorrect for only one operating speed around the curve. At all other speeds,

    there will be a side thrust outward or inward relative to the center of the

    curve, which must be offset by side friction.

    The general formula to calculate superelevation for various curve radii is

    the following:

    e+f = V

    2

    / 127Rwhere,

    e = Superelevation rate, in meter per meter width of road.

    f = side friction factor or coefficient of side friction between vehicle tires

    and road pavement.

    R = radius of curve, in meters.

    V = design speed in kph.

  • 7/27/2019 Design Manual 1

    45/366

    Rural Roads - Design Manual

    Section 3Geometric Standards

    Republic of Yemen

    Ministry of Public Works and Highways

    Superelevation slopes on curves shall extend the full width of the

    shoulders, except that the shoulder slope on the low side shall not be less

    than the minimum shoulder slope used on tangents.

    For 2-lane roadways, different superelevation slopes for each half of the

    road shall not be used; superelevation shall remain a plane for the full width

    of roadbed, except on transitions.

    The axis of rotation for superelevation is usually the centerline of the road.

    However, in special cases such as desert roads where curves are preceded

    by relatively long tangents, the plane of the superelevation may be rotatedabout the inside edge of pavement to improve perception of the curve. In

    level country, drainage pockets caused by superelevation may be avoided

    by changing the axis of rotation from the centerline to the inside edge of the

    pavement.

    Superelevation transition is the general term denoting the length of

    highway needed to accomplish the change in cross slope from a normalcrown section to the fully superelevated section, or vice versa. To meet the

    requirements of comfort and safety the superelevation run-off should be

    effected uniformly over a length adequate for the likely travel speed. The

    superelevation transition can be divided into two sections defined as

    follows:

    - Tangent Run-off or Run-out: This is the distance in which the level

  • 7/27/2019 Design Manual 1

    46/366

    Rural Roads - Design Manual

    Section 3Geometric Standards

    Republic of YemenMinistry of Public Works and Highways

    DOCS-0974-04 3-6

    Figure 3.1Typical Details for Superelevation Runoff

    Inside Edge of

    Roadway (P.G.L)

    Outside Edge of

    Roadway

    1 / 4 LA

    or 10m Max

    Tangent Run out Length of Superelevation Runoff

    Length of Application (as shown on the profile)

    Total Length of Application

    1 / 4 LA

    or 10m Max

    or 10m Maxor 10m Max

    Inside Edge of

    Roadway (P.G.L)

    Outside Edge of

    Roadway1 / 4 LA

    or 10m Max 1 / 4 LA

    or 10m Max

    Total Length of Application

    Outside Edge of

    Roadway

    Superelevation Application Details LA

    +e

    +eo

    -eo

    -e

    +e

    +eo

    -eo

    -e

    B

    B/2e

    B/2e

    B/2e2

    B/2e2

    B/2e

    B/2e

    +e

    -eo

    -e

    +e

    +eo

    -e

    P G L C/L

    B/2e2

    B/2e2

    Sign Convention for CrossfallMethod of Attaining Superlevation of

    Pavement Revolved aboutCenterlines of Roadways

    e

    e

    Inside Edge of

    Roadway (P.G.L)

    Outside Edge of

    Roadway

    1 / 4 LA

    or 10m Max

    Tangent Run out Length of Superelevation Runoff

    Length of Application (as shown on the profile)

    Total Length of Application

    1 / 4 LA

    or 10m Max

    or 10m Maxor 10m Max

    Inside Edge of

    Roadway (P.G.L)

    Outside Edge of

    Roadway1 / 4 LA

    or 10m Max 1 / 4 LA

    or 10m Max

    Total Length of Application

    Outside Edge of

    Roadway

    Superelevation Application Details LA

    +e

    +eo

    -eo

    -e

    +e

    +eo

    -eo

    -e

    B

    B/2e

    B/2e

    B/2e2

    B/2e2

    B/2e

    B/2e

    +e

    -eo

    -e

    +e

    +eo

    -e

    P G L C/L

    B/2e2

    B/2e2

    Sign Convention for CrossfallMethod of Attaining Superlevation of

    Pavement Revolved aboutCenterlines of Roadways

    e

    e

  • 7/27/2019 Design Manual 1

    47/366

    Rural Roads - Design Manual

    Section 3Geometric Standards

    Republic of Yemen

    Ministry of Public Works and Highways

    3.4 HORIZONTAL ALIGNMENT

    3.4.1 Circular Curves

    The natural terrain, as mentioned earlier, governs the horizontal alignments.

    The roads that are located on escarpments are therefore characterized by the

    multitude of hairpin curves that necessitate a back and forth maneuver in

    order to make the turn. For these roads, no minimum curvature can be

    specified, as speeds will drop to zero during the maneuver.

    For the remaining cases, the minimum radii will have to correspond to thedesign speeds as per the recommendations listed in Table 3.4, determined

    using the superelevation equation defined above:

    R =f)(e127

    V2

    Table 3.4: Horizontal Curve Design DataMinimum Radii (m)

    Design

    Speed

    kph

    fmax

    Rural Intermediate Roads Village

    Access

    Roads

    emax= 6%

    Flat/Rolling

    emax= 8%

    Mountainous

    emax= 6%

    Escarpment

    emax=4% emax =6%

    20 0.18 - 15(1)

    15(1)

    15(1)

    15

    30 0.17 - 30 35 30 30

  • 7/27/2019 Design Manual 1

    48/366

    Rural Roads - Design Manual

    Section 3Geometric Standards

    Republic of Yemen

    Ministry of Public Works and Highways

    Design Speed, Kph 30 40 50 60 70 85 100 120

    Side Friction Factor 0.33 0.30 0.25 0.23 0.20 0.18 0.15 0.15

    The values for horizontal curve design shown in Table 3.4 should be used

    for rural roads when practical. In constrained situations relaxed values

    based on reduced design speed shown in Table (3.5) may be used.

    In cases where the existing curve has a radius less than those listed, and

    widening entails land acquisition, high excavations or high fills, signs shall

    be posted to reduce the speed to correspond to the adopted radius.

    Table (3.5) Horizontal Curve Design Data Minimum Radii (m)

    for Reduced Design Speed

    Design

    Speed

    kph

    Reduced

    Design

    Speed

    kph

    fmax

    Rural Intermediate Roads Village

    Access

    RoadsFlat / Rolling Mountainous Escarpment

    emax= 8%

    emax= 6% emax= 4% emax= 6% emax= 6%

    20 20 0.180 __ 15(1) 15(1) 15(1) 15

    30 25 0.170__

    20 25 20 20

    40 30 0.170 30 30 35 30 30

    50 40 0.170 50 55 60 55 55

    60 50 0.160 80 90 100 90 90

  • 7/27/2019 Design Manual 1

    49/366

    Rural Roads - Design Manual

    Section 3Geometric Standards

    Republic of Yemen

    Ministry of Public Works and Highways

    Several methods exist for the calculation of transition curves and may be

    used in most situations. The rate of pavement rotation methodhas been

    adopted here. The rate of pavement rotation is defined as the change incrossfall divided by the time taken to travel along the length of transition at

    the design speed. The length of transition curve is derived from the

    formula:

    3.6n

    V.eLs

    where Ls= Length of transition curve (meters)

    e = Superelevation of the curve (meters per meter)V = Design speed (km/h)

    N = Rate of pavement rotation (meters per meter per second)

    The same values of rate of change of pavement rotation should be used to

    calculate the minimum length (Lc) over which adverse camber should be

    removed on a tangent section prior to the transition:

    3.6n

    V.eL nc

    where Lc= Length of section over which adverse camber is removed

    (meters)

    en= Normal crossfall of the pavement (meters per meter).

  • 7/27/2019 Design Manual 1

    50/366

    Rural Roads - Design Manual

    Section 3Geometric Standards

    Republic of Yemen

    Ministry of Public Works and Highways

    3.4.3 Improving Horizontal Alignment

    The major criteria for considering improvements to the horizontalalignment are the following:

    1. Safety

    2. Grade profile

    3. Type of Roadway

    4. Design speed

    5. Topography

    6. Cost (Construction, Maintenance, Operation)

    Of these considerations, safety comes first. Therefore, the stopping sight

    distance shall be adequate at all points of the roadway.

    The grade profile shall be considered next in mountainous and escarpment

    section. Critical grades are commonly encountered on existing roads

    located in these sections. The possible improvement of these grades byadjusting the horizontal alignment should be investigated in the cases

    where such an adjustment does not entail major earthworks or

    encroachment into private property.

    The road types that are considered in this Manual are the rural intermediate

    roads and the village access roads. The standards for the horizontal

    alignment will vary for each of these two road types.

  • 7/27/2019 Design Manual 1

    51/366

    Rural Roads - Design Manual

    Section 3Geometric Standards

    Republic of Yemen

    Ministry of Public Works and Highways

    Curve Length and Central Angle:Winding alignment composed of short

    curves shall be avoided since it results in erratic operation. In general, the

    length of curve should be at least 100 m long for a central angle of 5degrees. The minimum length shall be increased 30m for each 1 degree

    decrease in the central angle. Sight distance or other safety considerations

    shall not be sacrificed thereby. In general, the central angle of each curve

    shall be as small as physical conditions permit, in order to achieve the

    shortest possible route.

    Tangents or Straights Aff ording Passing Opportun ities: An 800m tangent

    is considered adequate for the purpose of providing passing opportunitieson 2-lane roadways. Passing tangents shall be provided as frequently as

    possible in keeping with the terrain. Shorter radii ensuring greater length of

    intervening tangent shall be preferred to sweeping curves of large radii

    which reduce the length of intervening tangents. However, sharp curves at

    the end of passing tangents and especially long tangents shall not be used.

    Compound Cur ves: These shall be avoided in general. On a compound

    curve the shorter radius shall be least 2/3 of the longer radius. The total arc

    length of a compound curve shall not be less than 100m.

    Curvature on Fi ll s:Other than flat curvature should be avoided on high,

    long fills. In the absence of cut slopes, shrubs, trees, etc., above the

    roadway, it is difficult for drivers to perceive the extent of curvature and

    adjust their operation to the conditions.

  • 7/27/2019 Design Manual 1

    52/366

    Rural Roads - Design Manual

    Section 3Geometric Standards

    Republic of Yemen

    Ministry of Public Works and Highways

    applied on the inside edge of pavement only, and preferably attained over

    superelevation runoff length. Widening values are given in Table 3.5.

    Figure 3.2 shows how carriageway widening on curves is gradually

    attained from the inside of the curve.

    Table 3.7: Horizontal Curve Design Data

    Widening on Curves for all Road Types

    Radius Pavement Widths, m

    4.0-4.9 5.0-5.9 6.0-6.9 7.0

  • 7/27/2019 Design Manual 1

    53/366

    Rural Roads - Design Manual

    Section 3Geometric Standards

    Republic of Yemen

    Ministry of Public Works and Highways

    curvature design standards for such alignments are to be reduced to the

    minimum in order to avoid land acquisition.

    The major criteria for considering improvements to the vertical alignment

    are the following:

    1. The grade line is a reference line by which the elevation of the

    pavement and other features of the highway are established. Though

    controlled mainly by the topography, other factors such as horizontal

    alignment, safety, sight distance, speed, construction costs and the

    performance of heavy vehicles on a grade should be considered.

    2. All portions of the grade line shall meet sight distance requirements for

    the design speed classification of the road.

    3. In level terrain, the elevation of the grade line is often controlled by

    drainage considerations. In rolling terrain a reasonably undulating

    grade line is desirable from the standpoint of operation and

    construction economy.

    4. Two vertical curves in the same direction separated by a short section

    of tangent grade shall in general be avoided, particularly in valley

    curves.

    5. It is desirable to reduce the grades at intersections. Turns are

  • 7/27/2019 Design Manual 1

    54/366

    Rural Roads - Design Manual

    Section 3Geometric Standards

    Republic of Yemen

    Ministry of Public Works and Highways

    2

    L

    x

    200

    L.Gy

    where y = vertical distance from the tangent to the curve (meters)

    x = horizontal distance from the start of the vertical curve

    (meters)

    G = algebraic difference in gradients (%)

    L = length of vertical curve (meters)

    3.5.2 Crest Curves

    The provision of ample sight distance for the road design speed represent

    the main control for safe operation on crest curves.

    The minimum lengths of crest curves are designed to provide sufficient

    sight distance during daylight conditions. Conditions normally do not allow

    full overtaking sight distance and the design should aim to reduce thelength of crest curves to provide minimum stopping sight distance in order

    to allow for increasing overtaking opportunities on the gradients on either

    side of the curve.

    Two conditions exist when considering minimum sight distance criteria on

    vertical curves. The first is where sight distance is less than the length of

    the vertical curve, and the second is where sight distance extends beyond

  • 7/27/2019 Design Manual 1

    55/366

    Rural Roads - Design Manual

    Section 3Geometric Standards

    Republic of Yemen

    Ministry of Public Works and Highways

    Tables 3.8 and 3.11 show the two vertical alignment design parameters for

    various terrain types: minimum vertical curvature in terms of K-values, and

    maximum gradient.

    Table 3.8 shows the minimum K-values for the following conditions using

    the equations above:

    1. Stopping sight distance measured from eye height h1of 1.080m to a

    stopped vehicle, i.e. object height h2 = 0.6m. K-values are for

    ADT

  • 7/27/2019 Design Manual 1

    56/366

    Rural Roads - Design Manual

    Section 3Geometric Standards

    Republic of Yemen

    Ministry of Public Works and Highways

    Table 3.8Minimum Vertical Curvature Values

    for Very-Low Volume Roads

    (1) K-values are for higher risk locations for ADT 100-250 vpd and all locations for

    250-400 vpd. K-values are for H1= 1080 mm and h2= 600 mm representing a stopped

    vehicle.

    (2) K-values are based on stopping sight distance measured from eye height of 1.05m and

    an object height of 0.2m.

    Design

    Speed

    (Kph)

    AASHTO ADT

  • 7/27/2019 Design Manual 1

    57/366

    Rural Roads - Design Manual

    Section 3Geometric Standards

    Republic of Yemen

    Ministry of Public Works and Highways

    access roads. No-passing signs should be erected where the available sight

    distance does not allow overtaking.

    3.5.3 Sag Curves

    It has been assumed that adequate sight distance will be available on sag

    curves in daylight. However, at night, visibility is limited by the distance

    illuminated by the headlamp beams, and minimum sag curve length for this

    condition is given as:

    For S < L: tan.200.

    1

    2

    Sh

    SG

    Lm

    For S > L:

    G

    ShLm

    tan.200 1

    Where h1= headlight height (meters)

    = angle of upward divergence of headlight beam (degrees)

    Appropriate values for h1and are 0.6 meters and 1.0 degrees respectively.

    The use of these equations can lead to requirements for unrealistically long

    vertical curves as, especially at higher speeds, sight distances may be in

    excess of the effective range of the headlamp beam, particularly when low

    meeting beams are used. Thus, the only likely situation when the above

  • 7/27/2019 Design Manual 1

    58/366

    Rural Roads - Design Manual

    Section 3Geometric Standards

    Republic of Yemen

    Ministry of Public Works and Highways

    For very low levels of traffic flow with only a few four-wheel drive

    vehicles, the maximum traversable gradient is in excess of 20 per cent.

    Small commercial vehicles can usually negotiate a 19 per cent gradient,whilst two-wheel drive trucks can successfully tackle gradients of 15-16

    per cent except when heavily laden.

    Gradients of 10 per cent or over will usually need to be paved to enable

    sufficient traction to be achieved, as well as for pavement maintenance

    reasons.

    As traffic flows increase, the economic disbenefits of more severegradients, measured as increased vehicle operating and travel time costs,

    are more likely to result in economic justification for reducing the severity

    and/or length of a gradient. On the higher design classes of road, the lower

    maximum recommended gradients reflect the economics, as well as the

    need to avoid the build up of local congestion. However, separate economic

    assessment of alternatives to long or severe gradients should be undertaken

    where possible or necessary.

    Table 3.11: Vertical Alignment Data Maximum Gradient

    Design Speed

    Kph

    Gradient, %

    Rural Intermediate RoadsVillage Access

    Flat/Rolling Mountainous Escarpment

    20 - 14(1)

    15(2)

    15(3)

    30 - 11 11 11

  • 7/27/2019 Design Manual 1

    59/366

    Rural Roads - Design Manual

    Section 3Geometric Standards

    Republic of Yemen

    Ministry of Public Works and Highways

    journey times and reduced vehicle operating costs. Benefits will increase

    with increases in gradient, length of gradient, traffic flow, the proportion of

    trucks, and in overtaking opportunities. The effect of a climbing lane inbreaking up queues of vehicles held up by a slow moving truck will

    continue for some distance along the road.

    Experience has shown that climbing lanes are unlikely to be justified other

    than on a small proportion of roads with heavy flows.

    As climbing lanes will be used largely by trucks and buses, they must be a

    minimum of 3.0 meters in width. They must be clearly marked and, wherepossible, should end on level or downhill sections where speed differences

    between different classes of vehicles are lowest to allow safe and efficient

    merging manoeuvres.

    3.6 CROSS SECTION

    3.6.1 Rationale for Determining Road Widths

    The cross section of a roadway is made up of:

    Number and width of lanes

    Shoulder width

    Cross slopes

  • 7/27/2019 Design Manual 1

    60/366

    Rural Roads - Design Manual

    Section 3Geometric Standards

    Republic of Yemen

    Ministry of Public Works and Highways

    Road class D: Village Access Roads with low volume of traffic (1000

    vpd): a running surface width of 6 7m allows vehicles in opposing

    directions to pass safely without the need to slow down or move laterally in

    their lanes.

    Economic considerations call for minimization of road width in order to

    reduce construction and maintenance costs, whilst being sufficient to carry

    the traffic flows efficiently and safely.

    Table 3.12 shows the recommended values for carriageway, shoulder and

    formation widths for various classes of roads.

    Figure 3.1 shows typical road cross section with dimension ranges.

    Rural Roads - Design ManualRepublic of Yemen

  • 7/27/2019 Design Manual 1

    61/366

    g

    Section 3Geometric Standards

    pMinistry of Public Works and Highways

    DOCS-0974-04 3-21

    Table 3.12Summary of Standards for Various Cross Section Elements

    Road Function

    ApproxRange of

    Traffic Flow

    (ADT)

    No. of LanesLane width

    (m)

    C/W width

    (m)

    Shoulder width

    (m)

    Cross Slopes (% )

    Pavement Shoulders Formation

    Rural Intermediate(Governorate)

    400-3000 2 3.0-3.5 6-7 0.0-1.5 2.0% 2-3% 2-3%

    Tertiary

    (District)100-1000 2 2.5-3.0 5-6 0.0-1.0 2.0% 2-3% 2-3%

    Feeder(Village Access)

  • 7/27/2019 Design Manual 1

    62/366

    g

    Section 3Geometric Standards

    pMinistry of Public Works and Highways

    DOCS-0974-04 3-22

    ROAD MARKING

    2-3%

    2-3% 2-3%

    2-3%

    2%2%

    FORMATION WIDTH

    6 - 8

    1 LANE1 LANE

    2.5 3.5 2.5 3.5 0.5 1.50.5 1.5

    CARRIAGEWAYGRAVEL

    SHOULDERGRAVEL

    SHOULDER

    C

    L

    Min0.5

    1.0

    ALL DIMENSIONS ARE IN METERS

    Crossfall

    Figure 3.3 Typical Cross Section Terminology and Dimensions

    Slope normally

    1V:2H for depth

    of 2m, or in

    accordance with

    type of soil and

    depth

    Slope

    according to

    type of soil and

    depth of Cut.

    For existing

    alignments a

    slope of 1:10may be used

    Drainage ditch

    usually V-shaped.

    Other shapes mayalso be used.

    Surfacing

    Base

    Subgrade

  • 7/27/2019 Design Manual 1

    63/366

    Rural Roads - Design Manual

    Section 3Geometric Standards

    Republic of Yemen

    Ministry of Public Works and Highways

    The shoulder widths depend upon the availability of Right-of-Way, type of

    terrain and the type of the road base (bound or unbound). These are

    observed to fall in the range of 0 to 2 meters. No paving is generally neededfor shoulders except in locations where water is likely to penetrate at the

    edge of the pavement which is an area particularly vulnerable to structural

    damage. Shoulders should also be paved if the level of traffic flow

    approaches the upper limit for a particular design class. In such cases a

    surface dressing or other seal may be applied.

    For 2-lane paved roads with carriageway width greater than 5 meters, full

    shoulders may be omitted in mountainous and escarpment type terrainwhere the costs of achieving desired cross sections are very high. In this

    case the minimum paved width shall be 5.5 meters and side drains and edge

    barriers should be given special considerations.

    For single lane roads the carriageway width shall be 3.0m. Shoulders

    widths may be 0-1.5m depending on traffic volume, mix and terrain.

    Two lane roads should be delineated by continuous lines at least 10cm wide

    situated on the shoulder immediately adjacent to the running surface.

    Centerline markings are also recommended on roads of at least 5m width.

    3.6.3 Cross Slope

    Cross slope (crossfall) is needed on all roads to assist in the draining of

  • 7/27/2019 Design Manual 1

    64/366

    Rural Roads - Design Manual

    Section 3Geometric Standards

    Republic of Yemen

    Ministry of Public Works and Highways

    the excavation of ditches on tracks through steep sidelong ground. In such

    cases drainage details should be provided. Figure 3.4 shows this concept

    with is advantages and disadvantages. Drainage channel shape and slope ofcutting are determined according to soil and terrain types.

    Side Slopes

    V1 V2Sound Rock Weathered Rock Sity Sand H

  • 7/27/2019 Design Manual 1

    65/366

    Rural Roads - Design Manual

    Section 3Geometric Standards

    Republic of Yemen

    Ministry of Public Works and Highways

    places and the potential difficulty of reversing. In general, passing places

    should be constructed at the most economic locations as determined by

    terrain and ground condition, such as at transitions from cut to fill, ratherthan at precise intervals.

    The length of individual passing places will vary with local conditions and

    the sizes of vehicles in common use but, generally, a length of 20 meters

    including tapers will cater for most commercial vehicles on roads of this

    type.

    A clear distinction should be drawn between, passing places and lay-bys.Lay-bys may be provided for specific purposes, such as parking or bus

    stops, and allow vehicles to stop safety without impeding through traffic

    Rural Roads - Design Manual

    S 3 G S d d

    Republic of YemenMi i f P bli W k d Hi h

  • 7/27/2019 Design Manual 1

    66/366

    Section 3Geometric StandardsMinistry of Public Works and Highways

    DOCS-0974-04 3-26

    Cross-Section with Cross-fall to Valley Side Cross-Section with Cross-fall to Mountain Side

    Advantages Disadvantages Advantages Disadvantages

    - no side drains required, resulting insubstantial reduction in earthworks.

    - less cross-drainage structures required

    - evenly spread surface water runoff alongroad edge reduces erosion problems.

    - potentially dangerous for vehicles slidingwhen surface slippery

    - careful maintenance of surface required toensure water drains evenly over shoulders

    - when gradient exceeds 8 percent, cross-fallmust be changed to mountain side.

    - safer for vehicles in wet and slipperyconditions

    - wider formation improves sight distance

    - critical outside edge of road less prone todamage

    - controlled surface drainage outlets

    - more earthworks because of the increasedwidth to accommodate drainage.

    - higher back slopes requiring protection.

    - frequent cross-drainage structures required

    - more expensive

    Source: WB Technical Paper 496.

    Figure 3.5Alternative Cross Sections in Mountainous Terrain

    Shoulder

    50 - 100

    C

    L

    Carriageway200-250

    Catch water drains where

    required; masonry lined

    channel and/or polythene

    sheet to avoid water from

    seeping into slope material

    Drain

    60 - 80

    3% - 5%

    In situ soil or

    optional gravel

    Bio-engineering

    slope protection on

    slopes below and

    above road

    Side drain: in weak

    material to be

    masonry linedNote: cut and fill to balance, avoid

    spoil as much as possible

    Construction steps: to allow for careful

    excavation with minimal disturbance of

    natural slope and regular, well compactedfill layers on stable ground

  • 7/27/2019 Design Manual 1

    67/366

    SECTION 4

    EARTHWORKS AND PAVEMENT

    Section

    4

  • 7/27/2019 Design Manual 1

    68/366

    Rural Roads - Design Manual

    Section 4 - Earthworks and Pavement

    Republic of Yemen

    Ministry of Public Works and Highways

    SECTION 4

    EARTHWORKS AND PAVEMENT

    TABLE OF CONTENTS

    Page

    4.1 General Definitions 14.1.1 Subgrade 14.1.2

    Base 1

    4.1.3 Surfacing 14.1.4 Pavement Section 24.2 Earthworks 44.2.1 Geotechnical Surveys 44.2.2 Borrow Pits & Dump Sites Location 44.2.3 Sand Dune Areas 74.2.4 Excavation 84.2.5 Embankments 94.3 Subgrade 104.3.1 General 104.3.2 Classes of Subgrade Bearing Strength 104.3.3 Improved Subgrade 114.4 Pavement Materials 11

  • 7/27/2019 Design Manual 1

    69/366

    Rural Roads - Design Manual

    Section 4 - Earthworks and Pavement

    Republic of Yemen

    Ministry of Public Works and Highways

    SECTION 4

    EARTHWORKS AND PAVEMENT

    4.1 GENERAL DEFINITIONS

    4.1.1 Subgrade

    - Subgrade is all the material below the pavement and may include

    in-situ material, fill and improved subgrade. For assessing anysection of subgrade the average CBR should be at least equal to the

    median for the category selected, and no CBR value should fall

    below the lowest value in the range. When subgrade CBR is below

    30% it is to be replaced by suitable material with CBR more than

    30% for a thickness of 20cm.

    - Improved Subgrade is a granular capping layer of selected fill

    material, the top of which is at formation level, placed where thenatural in-situ or fill material is unsuitable for the direct support of

    the pavement.

    - Formation is the surface of the ground, in its final shape, upon

    which the pavement structure, consisting of base and surfacing is

    constructed.

  • 7/27/2019 Design Manual 1

    70/366

    Rural Roads - Design Manual

    Section 4 - Earthworks and Pavement

    Republic of Yemen

    Ministry of Public Works and Highways

    - Bituminous Binders are petroleum-derived adhesives used to stick

    chippings on to a road surface, in surface dressings or to bind

    together a layer of asphalt concrete wearing course.

    - Cutback Bitumenis a bitumen whose viscosity has been reduced by

    the addition of a volatile diluent.

    - Bitumen Emulsionis a binder in which petroleum bitumen, in finely

    divided droplets, is dispersed in water by means of an emulsifying

    agent to form a stable mixture.

    - Prime Coatis an application of low viscosity bituminous binder to

    an absorbent surface, usually the top of the base. Its purposes are to

    waterproof the surface being sprayed and to help bind it to theoverlaying bituminous course.

    - Tack Coat is a light application of bituminous binder to a

    bituminous or concrete surface to provide a bond between this

    surface and the overlaying bituminous course.

    4.1.4 Pavement Section

    There are four types of pavement that can be used for rural intermediate

    roads and village access roads:

    1a. Flexible Asphalt Concrete Pavement Section comprises a 40mm

    thick layer of asphaltic concrete on top of high quality crushed

    aggregate base course layer or crushed natural granular material. Its

    use is economically justified only for the high traffic categories and

  • 7/27/2019 Design Manual 1

    71/366

    Rural Roads - Design Manual

    Section 4 - Earthworks and Pavement

    Republic of Yemen

    Ministry of Public Works and Highways

    20cm

    If subgrade strength (CBR) is 30% for 20cm.

    Bituminous Surface

    Dressing

    Fractured rock granular

    Base Course

    In-situ Material or

    Selected Fill

    Formation

    Subgrade

    Pavement

    Asphalt ConcreteSurfacing

  • 7/27/2019 Design Manual 1

    72/366

    Rural Roads - Design Manual

    Section 4 - Earthworks and Pavement

    Republic of Yemen

    Ministry of Public Works and Highways

    4.2 EARTHWORKS

    4.2.1 Geotechnical Surveys

    Geotechnical surveys are carried out at three stages in the project

    preparation process at increasing levels of detail: 1) identification, 2)

    feasibility and 3) design.

    For new roads geotechnical surveys are conducted to select and compare

    alternative routes for the road. Information is obtained on the supportingground for the road, earthworks, bridge sites, drainage, materials and water

    for construction.

    For upgrading and reconstruction works, geotechnical information is

    needed to determine the choice and properties of materials that are

    available for use in pavement construction.

    For route location, the principal terrain related factors include(1):

    - Subgrade strength, or present instability problems.

    - Materials used in construction.

    - Earthworks (cuttings and embankments).

    - Surface and subsurface drainage.

    - The need for structures.

    Rural Roads - Design Manual

    Section 4 - Earthworks and Pavement

    Republic of YemenMinistry of Public Works and Highways

  • 7/27/2019 Design Manual 1

    73/366

    Section 4 a thwo ks and avementy g y

    DOCS-0974-04 4-5

    TABLE 4.1STEPS OF THE GEOTECHNICAL SURVEY PROCESS BY PROJECT PREPARATION STAGE

    Project Preparation Stage Purpose and Means Information Sought

    1. Identification

    Reconnaissance Stage

    To identify possible alternative routes in terms of corridors

    using:

    - maps- satellite images 1:25,0001:500,000 (if necessary)- air photo mosaics 1:100,000

    Boundaries between terrain types and changes in topography, geology,

    drainage pattern, vegetation and land use, with consideration to:

    - courses of major rivers- catchment areas of major river systems- extent of flooding of low-lying areas- possible sources of water for construction- possible sources of construction materials- pattern of regional instability- extent of erosion- spread of deforestation- assessment of land acquisition/site clearance problems- location of all possible bridge sites.

    2. Feasibility To carry out an appraisal of the corridors in order to select thebest route using:

    1. air photos: 1:20,000 1:60,000 supplemented, if necessary,by color information from satellite images.

    2. site investigations of alternative routes to note key physicaland geotechnical features.

    3. selected lab tests.4. cost comparison of alternative alignments.

    Following items to be investigated:

    - foundation conditions-

    catchment areas and the location of culverts- location of spoil areas and possible borrow areas- possible sources of construction materials- identification of most favourable bridge sites- possible major hazard areas such as poorly drained soils, spring lines,

    unstable areas, erosion in river courses.

    3. Design for implementation Detailed field studies of the selected route with detailed airphoto interpretation to help plan a comprehensive site

    investigation with full sampling and testing program.

    Testing program should include:

    - construction materials- subgrade conditions- cuttings and embankments- areas of instability- erosion and soft ground- requirements for frequency and size of culverts- bridge sites

    l d lbli f

  • 7/27/2019 Design Manual 1

    74/366

    Rural Roads - Design Manual

    Section 4 - Earthworks and Pavement

    Republic of Yemen

    Ministry of Public Works and Highways

    In addition, the selection of dumping sites depends on the type of dumped

    material with respect to the site material. It should be kept in mind that if

    the dumped material contains contaminated substances, it should be

    dumped away from any ground water recharges areas and other

    environmental factors should be accounted for. Furthermore, the effect of

    the bulk volume and weight of the dumped stock pile should be studied in

    such a way as not to impose failure of below strata due to gravity.

    Due to the excavation works, an instability status may develop causing

    local or global failures that influence the surroundings. These problems

    may be avoided if a prior assessment of the existing ground conditions isperformed; this covers an assessment of the rock discontinuities and/or soil

    parameters. Moreover, environmental impact assessment and hydro-

    geological studies should be performed to avoid any damage to nature or

    water recharge areas.

    In line with the above, the following steps shall be carried out for

    identifying borrow areas and dump sites:

    1. Site topographical survey to determine the boundary limits of the

    proposed site and the estimated quantities.

    2. Visual inspection of in-place conditions to give the minimum

    possible safe distance between the borrow area boundary and

    surrounding sites, for example archeological site, natural resources,

    R l R d D i M lR bli f Y

  • 7/27/2019 Design Manual 1

    75/366

    Rural Roads - Design Manual

    Section 4 - Earthworks and Pavement

    Republic of Yemen

    Ministry of Public Works and Highways

    4.2.3 Sand Dune Areas

    All roads in sand dune areas require careful investigation to ensure that the

    accumulation of sand is minimized and does not provide a hazard to the

    road user. It is important that the alignment is selected after careful

    consideration of the wind direction. If at all possible, roads should be

    elevated on embankments above general dune crest height and cuts and all

    features causing wind speed to drop and sand deposition to occur should be

    avoided.

    In areas of varying wind direction and where considerable dune movementis occurring, extreme difficulty can be encountered in construction and

    maintaining any type of road.

    In dune areas, the availability of materials for road construction is usually

    severely limited and the need to import material, often for considerable

    distances should always be considered.

    The following considerations should be used to select alignments intransverse and longitudinal sand dune areas:

    If the road is parallel or inclined to dune but perpendicular to theprevailing wind direction, few problems are usually encountered. The

    road should be constructed in the interdune spaces keeping away from

    the leeward side of any dunes. If two transverse sand dunes are

    R l R d D i M lR bli f Y

  • 7/27/2019 Design Manual 1

    76/366

    Rural Roads - Design Manual

    Section 4 - Earthworks and Pavement

    Republic of Yemen

    Ministry of Public Works and Highways

    Another possibility in transversing transverse dunes is to join thecrests of the dunes rather than cutting dunes. Stable slopes of one in

    six need to be provided.

    Road alignment in the wind direction poses few problems and caneasily follow the line of interdune plain in the case of sand dunes.

    However, in the case of several longitudinal sand dunes being located

    adjacent to each other, the alignment should be located on the dune

    lee slope since this requires minimum cut and fill.

    Roads perpendicular to wind direction (or parallel to longitudinaldunes) or inclined to it, pose serious problems, since the prevailingwind direction is similar to that of the axes of the dunes. Cuttings and

    embankments can be subjected to serious sand drift and erosion.

    Valleys or saddles in a chain of longitudinal sand dunes can be safelyutilized for aligning the road. The alignment of the road will often

    become circuitous by following the interdune spaces but will be the

    best from construction and maintenance points of view.

    4.2.4 Excavation

    General

    Wherever a cutting is required, consideration needs to be given to the

    following factors that will affect its design and cost:

    R l R d D i M lR bli f Y

  • 7/27/2019 Design Manual 1

    77/366

    Rural Roads - Design Manual

    Section 4 - Earthworks and Pavement

    Republic of Yemen

    Ministry of Public Works and Highways

    - Clay 3V:1H- Weathered rock 4V:1H- Sound rock 6V:1H (in existing alignments it

    can be relaxed to 10:1)

    In the following situations, analytical slope stability appraisals shall be

    performed based on parameters obtained through detailed site investigation

    and associated laboratory testing:

    - Jointed rock conditions- Problematic material- Water table situations- Cutting depth exceeding 8 meters(ii ) Other Factors

    Partly for aesthetic and safety reasons a low angle slope is normally

    considered more desirable than a near vertical one, even if other factors will

    allow this latter course. The need for, or the surplus of fill material, willalso have an influence on slope angles.

    In deep cuttings, where the pavement is laid shortly after completion of the

    cutting, consideration should be given to heave.

    Guidance on satisfactory slope angles from the points of view of both

    Rural Roads Design ManualRepublic of Yemen

  • 7/27/2019 Design Manual 1

    78/366

    Rural Roads - Design Manual

    Section 4 - Earthworks and Pavement

    Repub