Design, m ultipacting simulations and conditioning of 500 kW FPCs for the BNL ERL SRF Gun

21
Design, multipacting simulations and conditioning of 500 kW FPCs for the BNL ERL SRF Gun Wencan Xu Brookhaven National Lab

description

Design, m ultipacting simulations and conditioning of 500 kW FPCs for the BNL ERL SRF Gun . Wencan Xu Brookhaven National Lab. Outline. Brief introduction of the BNL R&D ERL project Design of the FPCs for the SRF gun Multipacting simulation of the FPCs - PowerPoint PPT Presentation

Transcript of Design, m ultipacting simulations and conditioning of 500 kW FPCs for the BNL ERL SRF Gun

Page 1: Design,  m ultipacting  simulations and  conditioning  of 500 kW FPCs for the  BNL ERL  SRF Gun

Design, multipacting simulations and conditioning of 500 kW FPCs for

the BNL ERL SRF Gun

Wencan Xu Brookhaven National Lab

Page 2: Design,  m ultipacting  simulations and  conditioning  of 500 kW FPCs for the  BNL ERL  SRF Gun

• Brief introduction of the BNL R&D ERL project• Design of the FPCs for the SRF gun• Multipacting simulation of the FPCs• The FPC conditioning test and comparison

with test results• Summary

Outline

Page 3: Design,  m ultipacting  simulations and  conditioning  of 500 kW FPCs for the  BNL ERL  SRF Gun

High current ERL-prototype: 500mA

50 kW 703.75 MHzsystem

Control room

Cryo-module

SRF cavity

1 MW 703.75 MHzKlystron

e- 2.0MeV

Laser

SC RF Gun e- 2.0 MeV

Beam dump

Cryo-module

e- 15-20 MeV

30-35 MeV

The assembly of ERL beamline is in progress. Commissioning of the SRF gun is scheduled for Aug. 2012.

Page 4: Design,  m ultipacting  simulations and  conditioning  of 500 kW FPCs for the  BNL ERL  SRF Gun

High current ERL-prototype: SRF gun

Dual-FPCs for 1 MW CW power delivery.

Page 5: Design,  m ultipacting  simulations and  conditioning  of 500 kW FPCs for the  BNL ERL  SRF Gun

High Power CW FPCs Design

The design was done by collaboration of AES and BNL1 MW transmitted power was used in simulations. Water cooling (9.6psi for window) make sure the temperature rise less than 0.1°C. The maximum stress at the window is 6144 psi from the heat load and ambient pressure, which is approximately one third of the tensile strength of BeO.

Page 6: Design,  m ultipacting  simulations and  conditioning  of 500 kW FPCs for the  BNL ERL  SRF Gun

BNL ERL prototype: high power CW FPCs

0.60 0.62 0.64 0.66 0.68 0.70 0.72 0.741.0

1.2

1.4

1.6

1.8

2.0

2.2

2.4

Frequency [GHz]

VSW

R

1 MW transmitted power was used in simulations.

1 GPM water flowing around the inner corner of the doorknob to keep the temperature (72°C) increase <1°C.

Page 7: Design,  m ultipacting  simulations and  conditioning  of 500 kW FPCs for the  BNL ERL  SRF Gun

High Power CW FPCs

Pringle tip at the inner conductor to increase the Qext: 40,000~50,000. Water cooling for the inner conductor and air side, 5 K hellium gas cooling at the

vacuum side outer conductor.

Page 8: Design,  m ultipacting  simulations and  conditioning  of 500 kW FPCs for the  BNL ERL  SRF Gun

Multipacting simulations by ACE3P

S3P calculates the field distribution;Track3P simulates the electron behavior /trajectories.The simulations were carried out for the FPC conditioning setup: standing wave, full reflection at different phases, different frequencies .

Page 9: Design,  m ultipacting  simulations and  conditioning  of 500 kW FPCs for the  BNL ERL  SRF Gun

Multipacting simulation: Results

Multipacting in the coupler: left - vacuum side, right - window no phase sensitivity

Multipacting simulation at different frequencies: left - 703.9 MHz, right - 703.75 MHz not much frequency sensitivity for MP zone, but time consuming is different for different frequency

Page 10: Design,  m ultipacting  simulations and  conditioning  of 500 kW FPCs for the  BNL ERL  SRF Gun

Multipacting simulation: Results

Multipacting at 110 kW

Multipacting at 60 kW

Page 11: Design,  m ultipacting  simulations and  conditioning  of 500 kW FPCs for the  BNL ERL  SRF Gun

Prior to installation on the gun the couplers must be RF processed at high power. The goals of the processing are:

1. To help remove any surface contaminations from the fabrication step.

2. To check for, and process through, any multipacting barriers that may be encountered.

3. To ensure the copper plating on the outer conductor is well adhered.

4. To help outgas the UHV components prior to installation on the gun.

5. To ensure the parts are capable of handling the designed power level prior to installation on the gun.

6. To verify the cooling circuits function properly and provide adequate cooling to the respective parts.

FPC conditioning

Page 12: Design,  m ultipacting  simulations and  conditioning  of 500 kW FPCs for the  BNL ERL  SRF Gun

FPC conditioning setup

Page 13: Design,  m ultipacting  simulations and  conditioning  of 500 kW FPCs for the  BNL ERL  SRF Gun

HF + AM + FM

Generator

Computer controlled attenuator

Vacuum controlled attenuator

RF switch Amplifier CavityInput Coupler

Output Coupler

Terminatingload

CPU

Vacuum analog

loop

Vacuum Gauges

Circulator

Terminatingload A red vacuum loop ensures RF is

never applied if pressure exceeds 2.0x10-7 torr.

A dashed bule vacuum loop, CPU controlled, executes the automated process.

FPC conditioning control system

Page 14: Design,  m ultipacting  simulations and  conditioning  of 500 kW FPCs for the  BNL ERL  SRF Gun

Watching the signals

Page 15: Design,  m ultipacting  simulations and  conditioning  of 500 kW FPCs for the  BNL ERL  SRF Gun

FPC conditioning: Multipacting observed

The FPC conditioning began in various pulse modes, from 100 µs / 10 ms to 2 ms / 10 ms pulse length / period, followed by CW mode with gradual increase of RF power to the maximum value.

Multipacting zones at 8 to 10 kW, 16 to 25 kW, 40 to 70 kW, 85 to 120 kW and about 165 to 185 kW. Above 185 kW, there was a lot of out gassing.

For different RF phases (every 10°), the processing went similar and the conditioning time was close except for the very first run, which took most of the test time to ramp up the RF power and it was much shorter time for the later runs.

Page 16: Design,  m ultipacting  simulations and  conditioning  of 500 kW FPCs for the  BNL ERL  SRF Gun

Comparison of simulation and test

Simulation shows multipacting will happen at the RF power level about are 8 to 10 kW, 16 to 25 kW, 40 to 70 kW, 85 to 120 kW and about 165 to 185 kW. All these featuresd were observed in the experiments

The simulation also shows that multipacting zone is not sensitive to frequency. However, the strength of multipacting changes with frequency.

The multipacting is not sensitivity to the phase, since the multipacting mainly happens in the vacuum side.

Page 17: Design,  m ultipacting  simulations and  conditioning  of 500 kW FPCs for the  BNL ERL  SRF Gun

Summary High power fundamental power was designed for

the SRF gun. We have successfully tested 500 kW FPCs for the

R&D ERL SRF gun with standing wave up to 250kW in pulse mode(limited by klystron collector) and 125 kW in CW (administrative limit).

Observed MP barriers were in very good agreement with those predicted by simulations with Track3P.

Page 18: Design,  m ultipacting  simulations and  conditioning  of 500 kW FPCs for the  BNL ERL  SRF Gun

AcknowledgementBNL: Z. Altinbas, S. Belomestnykh, I. Ben-Zvi,

S. Deonarine, J. Jamilkowski, D. Gassner, D. Kayran, P. Kankiya, N. Laloudakis, G. McIntyre, L. Masi Jr, D. Pate, D. Philips, T. Seda, A. Steszyn, T. Tallerico, R. Todd, D. Weiss, A. Zaltsman

AES: M. Cole, G. WhitbeckCERN: Eric MontesinosSLAC: Liling Xiao, Lixin Ge, Kwok Ko, Cho Ng

Thank you for your attention!

Page 19: Design,  m ultipacting  simulations and  conditioning  of 500 kW FPCs for the  BNL ERL  SRF Gun

Backup slide

Page 20: Design,  m ultipacting  simulations and  conditioning  of 500 kW FPCs for the  BNL ERL  SRF Gun

Parameters High Current High charge

Bunch charge [nC] 0.7 5

Passes 1 1

Energy max/injection, [MeV]

20/2.0 20/3.0

Bunch rep. rate [MHz] 700 9.383

Average current [mA] 500 50

Injected/ejected beam power [MW]

1.0 0.15

RMS emittances ex/ey, [mm*mrad]1.4/1.4 4.8/5.3

RMS DE/E 3.5x10-3 1x10-2

RMS Bunch length [ps] 18 31

ERL-prototype parameters

Page 21: Design,  m ultipacting  simulations and  conditioning  of 500 kW FPCs for the  BNL ERL  SRF Gun

Heat load and temperature rise are based on 1MW through power. For all water circuits the system pressure should not exceed 70. psiaVacuum side inner conductor: 567 watts, 1.3 GPM, DP = 33.4 psid temp rise = 1.7KInlet and outlet tubes are 3/16” O.D.Window O.D.: 160 watts, 6.9 GPM, DP= 9.6 psid temp rise = .08K Air Side of the FPCAir side inner conductor: 346 watts, 3.0 GPM, DP = 10.8 psid temp rise = .44 KAir side outer conductor: 86 watts, 3.0 GPM, DP = 10.5 psid temp rise = .11 KWaveguide & Doorknob: 174 watts, 1.0 GPM, DP = 1.73 psid temp rise = .66KWaveguide temperature near short and doorknob calculated as 72.ºC. Protective cage or other safety feature may be required.Transition section and cold flangeThe helium requirement is .075 g/sec. Helium flows through the cold flange then into the transition section.

Power and cooling requirement for the FPC