DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely...
Transcript of DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely...
![Page 1: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/1.jpg)
7 AD-A0O 877 DELTA ELECTRONIC CONTROL CORP IRVINE CALIF
F/B 10/1DESIGN, CONSTRUCTION AND TESTING OF A 60 KW SOLAR ARRAY AND POW- ETCU)AUG 79 J S SUELZLE DAAK7O-78-C-GOIB
UNCLASSIFIED DECC-61211-003 NL
2flfllfllfllfllfllflEEE-EEEEEI-EOEhhEE~hEEghEEEmullllllullulIIE*E1111111II-EhlgllEEgllEE
![Page 2: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/2.jpg)
Report DECC-61211-003
DESIGN, CONSTRUCTION AND TESTING OF' A 6o Kcw
SOLAR ARRAY AND POWlER CONVERSION SYSTEM
L~.Final Report L EVEI~o0 J.S. ule
Delta Electronic Control Corporation2801 S.E. Main Street0 Irvine, California 92714
August 1979 V
Prepared for
co Department of the Army*L1 Mobility Equipment Research and Development Command
I . IFort Belvoir, Virginia 22060
Approved for Public Release;CU Distribution Unlimited
80 2 15 ()
![Page 3: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/3.jpg)
DISCLAIMER NOTICE
THIS DOCUMENT IS BEST QUALITYPRACTICABLE. THE COPY FURNISHEDTO DDC CONTAINED A SIGNIFICANTNUMBER OF PAGES WHICH DO NOT
REPRODUCE LEGIBLY.
![Page 4: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/4.jpg)
Report DECC-61211-003
DESIGN, CONSTRUCTION AND TESTING OF A 60 KW
SOLAR ARRAY AND POWER CONVERSION SYSTEM
Final Report
J.S. SuelzleDelta Electronic Control Corporation
2801 S.E. Main StreetIrvine, California 92714
August 1979
Prepared for
Department of the ArmyMobility Equipment Research and Development Command
Fort Belvoir, Virginia 22060
Approved for Public Release;Distribution Unlimited
/.N
![Page 5: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/5.jpg)
S&CURIY CLASSIFICATION Of TIlS PACE (When Does EtetE)
REPOT DCUMNTATON AGEREAD INWTRUCTIONSREPOT DCUMNTATON AGEBEFORE COMPLETING~ FORM4
1. REPORT Mummail 2. GOVT ACCESSION NO. V ClIVENwVs CAT &LOGi LiMse"
DECC-6Finl 3 ___________
De9sign, Construction and Testing of a 6' Fnl~'t T1 i-kW Solar Array and Power Conversion*PEOMIG0GR0T LS"
7. Au~sOR~s)* CONTRACTOR GRANT NuMALA.,
)J .S.S Suel z le D-K 78C 8
9. PERFORMING ORGANIZATION NAME AND ADDRESS 10 PROGRAM ELEMENT. PROircY.T~-
Delta Electronic Control Corporation AREA 6 WORK UNIT NOMflERS
2801 S.E. Main StreetfIrvine, CA 92714 1 /
IL CONTROLLING OFFICE NAME AND ADDRESSTE
U.S. Army Mobility Equipment Research and _'~jAuE9~"WDevelopment Command, Fort Belvoir, VA. ITNUM" E IF
14 MONITORING AGENCY NAME A AESSIf difi.,e. I'Mm Cnnt11-Iting 0III, eI S SF.CjflII CLASS (-f IN , *1510tI
Unclassifiedi%a nELAS ICATIjON 6_ON(.ACI
SCHNEfULE
16. DISTRIBUTION STATEMENT (of tis ftepofl)
Approved for public release; distribution unlimited
17 DISTRIBUTION STATEMENT (of the obstract *rIe,.d I, Black 20. it diII-.n fr-n RopoI)
III SUPPLEMENT ARY NOTES
to XEV WORDS fCn",.',*,,..d. It or.lf - .', ,, I,~ ho 1... . .
Photovoltaic, power conversion, peak power tracking, automaticreactive power control, efficient, utility augmentation
ABSTRACT (Contin, an rovems. side of oa.., ., I,It .M ho,, m.
A 60 kW photovoltaic array and power conversion
system wasdesigned, constructed, tested and installed by Delta ElectronicControl Corporation. The system is currently operative, augment-ing a remote diesel power generating station at Mt. Laguna AirForce Station. The system, which operates without on-site energystorage, operates unattended, extracting the maximum availablepower from the solar array. 4
D *j,7 1471 EDITIONOF I'NOVAIS IS O6OLZTIE
J~~c~j~7 () SECURITY CLASSIFICATION OF THIS PAGE (When Dots.I.I.*
![Page 6: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/6.jpg)
PREFACE
The work reported herein was performed by DECC (Delta
Electronic Control Corporation) under contract to the
United States Army Mobility Equipment Research and
Development Command (contract DAAK7Q-78-C-0018). The
Contracting Officer's Representative is Donal Faehn
at Fort Belvoir, Virginia. The work was sponsored by
the U.S. Department of Energy and the U.S. Air Force.
The entire project was under the direction of the
Defense Photovoltaic Program Office, U.S. Army MERADCOM.
Appreciation is expressed to Dietrich J. Roesler, pre-
sently of the Department of Energy, for his efforts as
Contracting Officer's Representative during the early
stages of the contract.
I)JRt / 1 Rld/or
i a
.... . .. ... . . . .. . . . . .. . .. ... . l ,
![Page 7: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/7.jpg)
SUMMARY
The objective of the effort described in this reportwas to demonstrate that a dc-ac photovol.taic energyconversion system without on-site energy storage couldeffectively augment a utility, e.g. a remote militarygrid. Delta Electronic Control Corporation (DECO)designed, constructed and installed such a system usingphotovoltaic modules provided by Jet Propulsion Lab-oratories under the Low-Cost Solar Array Project. The60 kW photovoltaic system is installed at Mt. LagunaAir F'orce Station where it augments a remote dieselpower plant. The system is entirely automatic, comingon-line when there is sufficient solar power availablein the morning, and returning to a stand-by state whenthe solar power is irsufficient to operate the system.The system is designed to extract the maximum poweravailable from the photovoltaic modules and operatesunmanned for extended periods of time. All observationsto date support the conclusion that such a system caneffectively augment a utility.
![Page 8: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/8.jpg)
TABLE OF CONTENTS
PARAGRAPH TITLE PAGE
Preface 1.
Summary ii
1.0 Introduction 1
2,0 Design and Construction
2.1 The System2
2.2 The Array 2
2.2.1 The Modules 52.2.2 Module Frames 5
2.2.3 Supports 12
2.2.4 Pertmuient Site Preparationand Footings 12
2.2.5 Flectrical Unterconnectionof Panels 12
*. .6 Grounding 17
2.3 Paralleling and Monitoring Panel 17
2.4 Power Conversion Unit 20
2.4.1 Input niid Output Contactors 23
2.4:2 Voltage Limiter 23
2.4.3 D-AC Inverter 21
2.4.4 System Control Circuitry 26
2.4.4.1 Peak Power Tracking and Power
Flow Control 26
2.4.4.2 Automatic Start-Up
2.4.4. . S1ut-Down 30
2.4.5 Monitors 33
2.5 Data Acquisition System 34
3.0 Results 42
3.1 Operation of the Power ConversionUnit From an Array Simulator 42
3.2 Field Tests With PV Array at tleDECC Facility 42
3.3 Operation at the Permanent Site 44
3.4 System Performance 44
3.4,1 Modes of Operation 45
3.4.2 The Power Conversion System 45-
i-A
![Page 9: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/9.jpg)
3.4.2:1 Input Power 463.4.2. InputVoltage 4
3.4.2.3 Output Power 46
3.4.2.4 Output Voltage 46
3.4.2.5 Efficiency 47
3.4.2.6 Harmonic Distortion and Waveform 47
3.4.2.7 System-Grid Interaction 47
3.4.2.8 Protective System 52
3.4.2.9 Expansion Capability 533.4.2.10 Electromagnetic Interference 53
3.4.2.11 Audible Noise 54
394*4.1 Output Power 5
3.4.4.2 The PV Modules 5
4oConclusions and Recommendations 62
41The Array Structure 62
4.2 ~ Array Wiring 6
4.3 Row Terminal Boxes 65
4.4 Solar Power Modules 654.5 Array Shorting 664.6 The PMP 68
4.7 Power Conversion Unit 68
4.8 Ground-Fault Protection 68
4.9 Operation 694.10 Conclusion 70
Appendix A Acceptance Test Al
Appendix B EMI Tests on Comparable Power
Conversion Equipment B1
iv
![Page 10: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/10.jpg)
LIST OF FIGURES
FIGURE TITLE PAGE
2-1 Block Diagram of the PhotovoltaicPower Generation System 3
2-2 Solar Power Module 6
2-3 Solarex Module 7
2-4 Solar Power Module: I-V Curves 9
2-5 Solarex Module: I-V Curves 10
2-6 Welding of a Solar Power Frame 11
2-7 Solar Power and Solarex FrameAssemblies 13
2-8 Frames Mounted on Shear Panels 14
2-9 Permanent Site After Grading andTrenching 15
2-10 Photovoltaic Array Installed atMt. Laguna 16
2-11 Array Interconnections 18
2-12 Schematic Diagram of the Parallelingand Monitoring Panel 19
2-13 Paralleling and Monitoring PanelFront View 21
2-14 Paralleling and Monitoring PanelInterior View 22
2-15 Power Conversion Equipment 24
2-16 Block Diagram of the Power ConversionUnit 25
2-17 Four-Quadrant Power Control 28
2-18 Start-Up Sequencing 29
2-19 Output from Demonstration Program onData Acquisition System 38
2-20 Data Acquisition System Output 39
2-21 Data Acquisition System Output 40
2-22 Typical Data Acquisition System Output--I-V Curve for a Solarex String 41
V
![Page 11: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/11.jpg)
3-1 Power Conversion System Efficiency 48
3-2 Output Current Waveform 49
3-3 Grid Voltage Waveform at System Output 50
3-4 Rate of Rise of Output Current atTurn-On 51
3-5 Test Set-Up for Cell Breakdown Tests 58
3-6 Comparison of Current-Normalized I-VCurves for Solar Power and SolarexPhotovoltaic Cells 60
LIST OF TABLES
TABLE TITLE PAGE
2-1 Solar Power System Characteristics 42-2 Photovoltaic Module Characteristics 8
2-3 Monitors 35
2-4 Outputs to the Data Acquisition System 37
vi.
![Page 12: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/12.jpg)
1.0 INTRODUCTION
This report discusses the design, fabrication and testing
of a photovoltaic power generation system. The system
consists of a 60 kW photovoltaic (PV) array, a 75 kVA
solid-state power inverter, and interconnecting, control
and monitoring equipment. The output of the inverter
drives the local utility grid in parallel with existing
diesel generators, providing up to 10% of the grid power.
The effort is part of the Military Applications of Photo-
voltaic Systems project, a joint effort of the Department
of Energy and the Department of Defense.
The objective of the effort has been to demonstrate that
a dc-ac photovoltaic energy conversion system without
on-site storage can effectively augment a remote military
power grid.
The system was originally assembled and tested at the
Delta Electronic Control Corporation (DECC) facility.
Because of time considerations and the delivery schedule
for PV modules, the tests at DECC were performed with
a half-power (30 kW) array. At DEOC the power conversion
equipment operated into the local utility grid.
![Page 13: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/13.jpg)
2.0 DESIGN AND CONSTRUCTION
2.1 THE SYSTEM. Figure 2-1 is a simplified block diagram
of the photovoltaic power system. Power from the PV
array is fed to the dc-ac power conversion unit through
a paralleling and monitoring panel (PMP). The power
conversion unit operates from the dc array voltage and
provides ac power suitable for transmission to the util-
ity grid (main diesel generator bus). The power conver-
sion unit has the following features:
(1) Dynamic peak power tracking (PPT) to extract
the maximum available power from the array
at any time and feed all available power to
the grid;
(2) Output power control circuitry to synchronize
the output to the grid and to control the
real and reactive components of the output
power;
(3) Automatic start-up and shut-down controls
for unmanned operation;
(4) Automatic protection circuitry.
The major parameters of the system are listed in Table 2-1.
2.2 THE ARRAY. The photovoltaic array is rated at 60 kW
at 50 C ambient and 1000 W/W 2 insolation. It is composed
of 169 strings of PV modules, each string consisting of
14 seriesed modules. A reverse diode installed across
each module bypasses and protects the module during
occlusion or malfunction.
2A
![Page 14: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/14.jpg)
0 0
~ 4 4J
0
00
.B C)
0 40
miiC
4)0 Cl).rii >
0U+
![Page 15: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/15.jpg)
T&BLE 2-I. SOLAR POWER SYSTEM CHARACTERISTICS
ARRAY
COMPOSITION
Vendor Code Z modules 756 (13 kWp)
Vendor Code Ymodules 1610 (117 kWp)
Number of modules perseries string 14
Number of series strings 169
ELECTRICAL
Output power (a) 500c, 1kW/r 2 60 kW
Normal operatint- outputvoltage 180?(-2() Vdc
Estimated annuial energyoutpit 120,OO kWhi
POWER CONVERSION SYSTEM
MFC IIAN LCAL
PMi, 76"i x 361"w x "2"d
Power conversion untit 79"Ii x 86"w x 1:"k
Coolitng I1lowtrs iitegral topower convoersLoii itnit
ELECTRICAL
I tput voltag;e 180-29() Vdc Ol)V'ritio1 ,100 Vdc maxitml
Output power 77, kW
On t)pLt frequenc) hatched to rrid (6O i1z)
O1utput voltage Matchod to Igrid(277/18() Vac, "-pli-s4-e)
lE'fficiency 92% a 60 kW91% 0 30 kW
Output current distortion(TI|D) 2.0% " 60 kW
4
![Page 16: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/16.jpg)
2o2o1 The Modules. The modules are of two typess the vendor
Code ZI modules shown in Figure 2-2 comprise 115 of the
strings (78% of the rated power); and the vendor Code Y
modules shown in Figure 2-3 comprise 54 strings (22% of
the rated power). These two types of Block 11 2 modules
differ in almost all parameters including electrical out-
put and physical dimensions. Table 2-2 lists the major
characteristics of the two types of modules and Figures
2-4 and 2-5 show typical I-V curves for the two types of
modules.
The modules of each series string were matched for output
current characteristics so that the higher-current modules
would not be limited by low-current modules in series.
The short-circuit current data provided by the manufactur-
ers were used for current matching.
2.2.2 Module Frames. Support frames were designed for the two
types PV modules. The frames for both were constructed
from rectugular steel tubing with T-section or rilht
angle cross braces. Figure 2-6 shows one of the Code Z
module frames being welded on a jig developed at DPCQ for
that purpose. After construction, the frames were hot-dip
galvanized for protection against the environment, rthe
Code Z support frames hold 7 modules (half of a string)
and the Code Y support frames hold 14 modules
I Refer to Report Number DOE/JPL-1012-W0, "1, viroumentalTesting of Block ITI Solar Cell Modules September 1, 1'7Q,prepared by Jet Propulsion 1,aboratory [,Pl )
2 .1P, designation.
5
![Page 17: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/17.jpg)
TOP V,:1A 1
Photos courtesy of JPL
FIGURE CODF Z MODILE
'I6
![Page 18: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/18.jpg)
TOP
BOTTOM
1 IAI I~ - I CODE, ' MOIl1I,
![Page 19: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/19.jpg)
TAiBLl 2-2". PHOTOVOLTAIC MODULF C HARA'CTIlISTICS
CODE Y CODE Z
PHYSICAL
Dimensions
Length 22. to 0 to
Widtl 22. o" 1. "
Ile igl t I . 8" I ."
Weirht q Ibs. I.7 Ibs
Ntmel)er o1 el c s vI; IsO
Cel t I li mtete 1"1
Cell type N-P 11-N
F1, 'T"R TICA IL
Rated voltage I).8 V I.8 V
Rnted cilrreiit I.1$ A 1.81 A
Rated power l8s. w 2.0 W
!$
![Page 20: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/20.jpg)
2.8[
MODULE SERIAL NQ: 780102405
2.4 -MODULE IRRADIATION; 100mW/cm2, AM1.S
MAXIMUM POWER
1.6- AT NOCT*
1.0 -CELLTEMP (*C)
*NCT=N ivn I'emenxuriix
VOLTAGE (VOLTS)
FIGURE 2-4.. CODE Z MOTAIL~s I-V CIURVFS
![Page 21: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/21.jpg)
2.0
MODULE SERIAL NO: 032537921.6- MODULE IRRADIATION. l00niW/cm2 AMI.5
1.4
'Ur.
z
.6-
CELL0TEMP Q C
NOCT* +20 -20
*NOCT=Norma. OperatingCell Ternperiiture=147. 10C
0
VOLTAGE (VOLTS)
FIGURE 2-5- CODE Y MODULES I-V CURVES
10
![Page 22: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/22.jpg)
ALA
![Page 23: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/23.jpg)
(one string). See Figure 2-7.
2.2.3 Supports. The module frames are supported by wooden
shear panels as shown in Figure 2-8. At the DECC tempo-
rary installation these shear panels were placed directly
on the ground. At the permanent site they are mounted
to concrete footings to withstand 120 knot winds.
The 250 tilt angle of the panels was selected to provide
the maximum integrated annual output power at the 32. 0
latitude of the permanent site.
2.2.4 Permanent Site Preparation and Footings. Figure 2-9
shows the permunent site for the solar installation
after grading and trenching. Concrete footings, 12" x 12"
in cross section and 191 to 28' in length, were cast at
a remote location, transported to the array site and set
into the soil. Splices between footings were poured in
place. The wooden shear panels are bolted and braced to
the concrete footings, and the frames are bolted to the
shear panels.
Figure 2-10 is a photograph of the installed array.
2.2.5 Electrical Interconnection of Panels. Each row of PV
modules consists of several strings (typically 12 for
Code Y and 9 for Code Z). The outputs of the
series connected strings are wired to a row terminal
-B j.12
![Page 24: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/24.jpg)
3"x11x'1 6"
RECTANGULARTUBING
FIGURE~~~~ 2-7. COEZ6N"CD
1683
![Page 25: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/25.jpg)
flwr
4e,
a '.-*-.L4
![Page 26: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/26.jpg)
H
-, <
H
1<I.
I h-I
-, V
- .-
-I
![Page 27: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/27.jpg)
I;
> I
16
![Page 28: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/28.jpg)
box. In addition to providing a termination point for
array wiring, the row terminal box contains surge sup-
pressors for lightning protection and test plugs for
monitoring individual string voltages. The array inter-
connections are depicted in Figure 2-11.
Underground multiconductor cables from the row terminal
boxes connect the series-string outputs to the parallel-
ing and monitoring panel. The paralleling and monitor-
ing panel is located in a building with the power conver-
sion unit. The power conversion building- is visible at
the left side of Fitulre 2-10.
2.2.6 Groundint. The PV module frames of each row are connect-
ed together and to a buried Cround bits which runs along
the west end of the array. The ground bus also circles
the power conversion building to provide a Tround for the
power conversion equipment. It is connected to the diesel
power plant ground.
2.3 PARALLELING AND MONITORING PANEL. Figure 2-12 is a sim-
plified sclematic diagram of the paralleling and monitor-
it r panel. The output of each string of PV modules is
normally connected to the common bus through a fise re-
presented by Fl, a blocking diode CR1 and a switch S1.
Meters MI, M2, M3, and M6 monitor the operation of-the
entire array: output voltage, current power and accumu-
lated kilowatt-hours. The 169 switches represented by
17
![Page 29: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/29.jpg)
Module Module' [ l.e Mdule [Modul e Module
1 2 7 8 1") 14
+ + + + -, +
At gntra-tring Wiring
Stringi IStrifid [" trill
S 2 -L 11
L Row Terminal Box
41 Undercround Multiconductor Cable to PMP
B. Inter-String Wiring, On1e of Eighteen Rowe
FIGURE 2-II. ARRAY INTERCONNECTIONS
18
![Page 30: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/30.jpg)
0. 0ar
00
H go4 0
0 0
CA 0 0
~0 En
_____ _____F-4
10 r14UOUl
.00
> HZ
HO
0
0Z
0~ H4FO~ 0 P-
44)
19
![Page 31: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/31.jpg)
Si are three-position switches. In the normal "line"
position each switch connects the corresponding string
to the common bus. In the "off" position, the switch
disconnects the string from the remainder of the system.
In the "test" position the switch connects the string
to a test bus for evaluation. M4 and M5 provide measure-
ment of the test-string voltage and current into a load
selected by S2t open, shorted, load A or load B. Loads
A and B are the average peak-power loads for the Code Z
and Code Y strings respectively.
A shunt resistor represented by RI is incorporated in
each string to provide individual string-current informa-
tion to a data acquisition system provided under separate
contract. (For more details see paragraph 2.5)
Fiutires 2-13 and 2-14 show the front panel und interior
construction of the paralleling and monitoring ptunel.
The wheel-like construction at the back of the cabinet
is the "- array bus" shown in Figire 2-12. The resistors
Ri can he seen radiating outward from it.
A ground fault detector is included in the paralleling
and monitoring panel. The detector transmits a fault
,ignal to the power conversion module to operate a warn-
ing lamp.
2.14 POWER CONVERSION UNIT. The power conversion unit, shown
20
![Page 32: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/32.jpg)
I t,
i 4$t v it i, i
7 At,
I"I I%( AN h) MO I IO IN( ___F
:?O I' V
![Page 33: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/33.jpg)
-i 43
![Page 34: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/34.jpg)
in Figure 2-15, includes input and output contactors,
an input voltage limiter, a dc-ac inverter, and system
control circuitry. Figtre 2-16 is a simplified block
diagram of the power conversion unit.
2.4.1 Input and Output Contactors. Input contactor KI is
operated to short the PV array and disconnect the array
from the pre-regulator when the inverter is off for any
reason. Output contactor K2 is operated to isolate the
inverter front the grid when the inverter is off. K1 and
K2 are used in the automatic start-up and shut-down
sequences.
2.4.2 Voltage Limiter. The preregulator limits the maxinuxin
inverter input voltage to 290 Vdc. During nornal opora-
tion this thyristor buck-type regulator is in the "ftill
on" condition and dissipates very little power (less
than 16). The limiter protects the inverter dutiiing the
start-up sequence between the time Kl is activated and
the time K2 is activated. During this period the iput
voltage front the unloaded array can be ats high ats 400 Vdc.
2.4.4 DC-AC Inverter. The dc-ac inverter is the same inverter
used by DECC in its Uninterruptible Power Supplies. This
self-commutated power inverter uses pulse-width modula-
tion techniques to generate a 3-phase, 12-step sine-wave
synthesis. The pulse-width modulation provides control
of the dc/ac voltage ratio. The lowest order harmonic
23
![Page 35: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/35.jpg)
I A
*640*0
A4
- - -- Cl
-- - a - - a a-
- -- -- - - - a a a
- - - - - - -a - a a a
24
![Page 36: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/36.jpg)
.0
0- V
C'd E 0.
4J~
L- F
N N CUU 0
4+) 4D
k 04HH
25)
![Page 37: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/37.jpg)
produced by the synthesis is the eleventh. Only ininimal
filtering is required to ensure a total harmonic distor-
tion of less than~ 3%. The series inductive component of
the output filter is also used in power flow control.
2. '.~s System Control Circuitry. The system control includes
array peak power trackine anid output power control, auto-
mat ic start-uip and shut-down controls, automatic safety
and protection c ircuiitry, remote sinit-down control, and
status moni tors.
2.4'. 1 Peak Powet, Tracking and Power Flow Control. Peak power
trackinug anid power I'1ow conitrolIs ext rac t the maximlum
aval latle power From the array, provide stability in the
face o t chaninitg a rray1 c ondi t ions, and minimiz~e the re-
act ive' outpuit power.
Th~e priI aryV -on t rol loo gneats phja e i t'1erenc e
9,ac ross the, serie s inductive c omponrent of the output
t'il.ter, resuilt lug in the flow of power to the grid and
load lug or the array.
A secondary control loop provides the peak power tracking.
Control c irculitry applies a half-Mortz modulation to the
phase diftference, .p and the pulse-width modulation index
of' he ilvrte, an moitos te drivaivedP/V a th
![Page 38: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/38.jpg)
the peak power point.
A tertiary control ioop adjusts the output ac voltage
from the inverter for zero reactive power as depicted
in Figure 2-17.
2.4.4.2 Automatic Start-Up. The solar power conversion system
was designed to allow unattended operation over long
periods of time; operation is entirely automatic from
start-up to shut-down. The operation sequencing is de-
picted in Figure 2-18. When there is insufficient solar
power available to support the system losses, (e~g. at
night) the power conversion unit turns off automatically.
When the power conversion unit is off, the input con-
tactor Kl is deactivated, shorting the array. A small
amount of power (65 watts) is drawn from the utility
grid to power stand-by circuitry. In the course of a
normal day, as the insolation increases, the array out-
put current through Kl increases. When this current
reaches 10% of the peak current, the start-up sequence
is initiated. If the grid voltage is not within 10% Of
the nominal value, start-up is delayed until the grid
returns to that range.
When the start-up conditions are met, the start-up se-
quence is initiated (TO). At To, bias power supplies
are energized. Five seconds later (T 0+5)o the input con-
tactor is energized, unshorting the array. The input
27
![Page 39: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/39.jpg)
L
V. V
V. = Inverter output voltage1
V = Grid voltagegVL = Voltage across L
L = Effective series inductance ofoutput filter
a. Single-Phase Equivalent Circuit
J
v L
Vg
power flow control
: power factor angle
V V: adjusted to set G =0
b. Vector Diagram
FIGURE 2-17. FOUR-QUADRANT POWER CONTROL
28
LI
![Page 40: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/40.jpg)
zd -) A- -- 4-
HH
P 0~ 0
UUr 0- 0 C
0 0. .U
0~ tu)0f
4.))
I'd-4 000 -
C:
CHr
b.) 0
00 -v. +4UU)
00 0 00 ) 0
0 1)4. 0 0 L taI0 (z 0 &0
44 i >U C4d U)U)4, U)
.0 4U) 0 U) Tq 1 0L c
k 0 4 *v4, 0) 0U) 0~ kU 0 CU -C0i C);I4L>~ .. -P v4
4J CUF.la 0 )), 2 0
'0 L~ 3) 0 4-29.
![Page 41: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/41.jpg)
voltage to thle power conversion unit rises and the pre-
regulator anid inverter comimence operation. Control
circuitry synichronizes the inverter output to the grid
and controls the inverter ouitput voltage. The preregu-
lator limits the input voltage to 290 Vdc.
Teti seconds latex, (T 0 +15), frequency error and lilie match
error detectors are activated. If the output frequency
deviates front the range of 00+2 Hz at any time after
T 0+1'), thle power conversion unit is g-ated off and "'error
recyc le" sequeticke is initiated ( see paragraph 2. 4.4.*3)
At T 0 +20, the three-phiase output contac tor K2 closes.
Closure is prevented, however, if the voltage across K:?
(any phalse) is gr eater thai: 7 of tile nominal linie-to-
neutral voltage. This assures that thle inverter output
is inatchedi to the g-rid inl voltage and phase.
After T ()+20, thle Power Conversion unit is ill thle opera-
t ion~al miode; all power flow. control and fault detection
circulittry is activated.
.4 ~. 3 Shut-Dow-ni. There are six basic types of shut-dow-n for
the power conversion unit:
(1) Manuacl Shut-down in Response to the On-Off Control
Switch. When the Inverter Power System on-off switch
on the front panel of the power conversion unit is turned
30
wmmU
![Page 42: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/42.jpg)
to the "Orr'" posiitoni, itor'ini 81u1 i-dowii 01'etIil's 'phi
POw('r couive r-41 oil ilt t ri'tfl i is 0 F' jiant-I I the' ow I tela Ls
tlrfliod to tilt,'toil,, p081. ti. Ol * 'Phi' powe r coiaveisiol 01 illit
thIeni starts lip i.f' the tiornui stioTt,-ap eoaid Iti ouas 11', ie
(2) M11.11111i Shilt-dowai Ii Re poaa so to the~ Einlrgvsliy 011'
Switch el 11111,111c the, wlomen it iy FVme' rgean'y 0r1' sitch'
iii1t Iiate 8 l ordeorlIy i t t;-dowii its tilt oti-oI swi 8tc'h does,
anld id-s0 oj)olls lilt ox terui . I tl.cii It 1wi';%kori, lreIIov i-i ii ii
ac0 powo'r t'vom tilt, titilt Thai' c I rot I Ie''kei 1.8 muomitod'
Ott tht' ivol. ofthi W'1' C rvolive ai4 I i )lidi ii. ,lldt mulst
Ill voe'i' 108e'I t1zl1al Iy to t-o iHiuIt' oivn'1liti 011
thte power' oIviab nI.I roil tile PV ara'l£V isI i-ltl' ii
Itth Is lOVQI'8e po ilo'2 low i'vos il-el it'v callt's lhitill%0
4b111111 ofa ph-o r ''l to C 'lw n 111- rih ti.' t * e 'I I' t oa ll- Cht I' i
rfv ~ ys ' tilt' I-VV S4 I)1.8 dl prevol 41111 8! I'o 1111l t- 10a
01- lil ' t te , t lt, ihtit' lug l-s~ri i l 1111 1 shitt o wi otII
(I, itt;-iowii wi th Aittonuioth l i' t. iirt whientheli F'.11t t;IsM
Cie~ia'ei Aui illtei'lovc C Ii'dI.t till'lm tilt powor 1'CoiivOX'M i
tiltilt ofT' It' all tinto riock loop 1 s opened. Tlhie titerloc k
![Page 43: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/43.jpg)
loop itic hides4 alxi 1. ary l~ciltat .s Oil tilt, 11141 jort 14s~'t-4,1ii
siw t tes , i.tieI tilt t lt- theit emt tt c iv t' I t twnaki'' o lit
tmI L t vo -Atavt -% ait tmit i t. I aI v wimi thev lk-op i . v I oftit
1 ) rovidedl till 1101i11111 s 1 a11 tt;-11 0p kitl( i. t.f l I I lle tilt
I) ) Slitit-dowit witth Anttoia tic Hlecyc 1 lug. tysv ys 1 ('11
'lil t's, s4ttch .. lit li Itv ltit. di st~it'it's , I t'ttd t o Io
t rat Ie to I It i na1 tnx r'e . PTe powt' 1, c oi%-(,s 1 on11 m% it pr1,o 1 4, s
it sc1. t, i l 1. I t t IIt, -4t' V IIn11. t s 11.% slt I t.II I I ( I kloI ttI*I Io I1vo i di
1111ttt0t' 4' S sit 11% i t't I 4 t III nh t 4, 'venl i oil t til 10,: CO~tt 0%vr I ti
111111. 1 a i t -1t' d t t-o 'st k t - il ;I t; it ;%%It -opw t .n t a N. S
vt't ko t s I tt't I stil' tt -down I C ut lit .t4' t itt I % II %-id a t i i o
i I'll f i tt' M tiltatI, v s t ' 1n .4 t't ' - tll t'It si htV Mlp ;I V
w fi I I I1 80 s trottis 0o I lit, o1. t, i ma I oan I I , t lit, ow I~~' % tOtt-
v&e 1-M 1 oil t uIIn A I sIt I I -; lohOito t I 1 ', t,' t u I I I y Ill I vt Vali I I is
(a) IcII.;it -&illtv gduil u i'it'civ h ~ t I f :'tg'(o0: i
v) v i k i i 'vo t age ull t N. t'gt it I I + I 1014)0
v) rics i dt vol I t lw t'i'ttt t'VcItt I I lii' loit't 111.1 vt't+
Vu c su st I vI , oil 't'l I t' ita 100ol ampsil I' 1 04 )ow ,I 0 n1 Vi V-
..;till till i . (t",ta I t 4 ' I . it 1 7' o iiils poea k Itt, anI a-II
staot -11p1.
(i) Sil t -ulowii H4,4t''i rt I 1tg Manna 1 11 o -t ( t So Sven ltVim I t t'ti-
11 e 1115 t'fht4' thei potWtt' V t'1 OIt' lou I uti tI %11hut tiowit
![Page 44: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/44.jpg)
until reset maiuily. These tire f'aults which require
attention by service persornirel. They includes
(a) Overvoltage at the dc bus-- input voltage
regulator not operating properly,
(b) Output undervoltage during start-up sequence-
inverter has not produced full output voltagee
by the expected point ini tihe setilencef
(c ) Openi fuse-at output or tit inverter power
stageo,
(d) Excessive reverse power into the inverter
from the grid--power flow control c ircuit ry
tIot opei'atitig Ipoerly,
(e) overtemp r'atrv w Ithi in the p)ow'er c otiverstIoni
unlit, anld
(f') Incorj'ect bias voltageos-bias suipplies iot
opei'ati It uI popt'] .
All six typos of' shut-dowii diet i viit KI , shorti tig the
array , .1nd( openl the Output con tac tor K2. * ilA supplie s
rematn atitvated f'or it shiort t int to as sure' orderlN
shut-dowit.
2.4 r Moitors * The solar power couwers toil system inc ludes
r meters 1(i stiltus lamtps For mo1u1to ring of uormal itid
abnormal operiit ion. 1iThe PMI' hits .qix mevtot's; the power
couvei'sion uiI.t hias elevenl meteprs tud twenty-six .4titus
lamps. Gonornrlly, fault condition iudiciitor lamps ro-
maxin it after shut dowit to assist iii fault diagnosis.
![Page 45: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/45.jpg)
The monitors and their functions are listed in Table 2-3.
No audible alarm is included in this system which is in-
stalled in an unmanned building.
2.5 DATA ACQUISITION SYSTEM. A data acquisition system, pro-
vided under separate contract, processes digital and
analog outputs from the power conversion system for local
monitoring or for recording on magnetic tape. The outputs
provided by the power conversion system are listed in
Table 2-4. The data acquisition system will also monitor
a weather station to be installed at a lateor data; al
insolometer has beei installed already. Tho data acqui-
sition system inc ludes data scatnuers, a pro(grammttable
computer, input keyboard, CRT display, printer, anid a
dynamic load. Fitres 2-19 throtih 2-22 are typical of
the types of output available at the CRT and p-riiter.
Figure 2-22 is an I-V curve for a s i.iglv ('ode Z
string. The curve is geterated itsing the dynamic load.
The data acquisition system was provided by Santdia
Laboratories.
34
![Page 46: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/46.jpg)
0
44-2
0'
02 d ) j)C
4) -10$4 D f
(d) 4U) U 1
o PU 4) CZ -fI4) 1 dcd
4) P m0 >> 4 'r - P , 0 :3 4 )
UUU-- 9 0- c0 P0C P uz )4 d kC--P 4 0 Cd4) 0 ) 4) $ CUC' -1 0U 4- Q - 0
> 0. o Y4-) P 14 4) ~-4 C.) -PHD 4 )k$o$0> )4)4 -)riPQ , , P4)C - V)+ QUU~ p) HOO +d 4) O0
M 4 -P- C 4)4D 4-)4DZ UZ 0 Z 4) + ) P4) 4' 0$ r r. 4-) 4)W. o 40 :3 ou 4 d4) 00 4)-P 0v 0 i CU 4) $.i( )-l ) 0 - Q 4 4 00 40 .- H -PP$ $4 4 Q) r 4) 4 >-~ 0 0 + -4 D
0 -0 - -H $4l -r4-) - PJj 4 CU P 4) 0 CU $4 u Z 9 0 0 0 0 0 (:0 .) d d41 F 9 F~ > 0 0 .,j> 00 kk 4 O- H Z 4 0
z ~ ~ ~~. +)P4-H$4 or o~ 0 P- - 0-PC4 >. H ,u :$4 k CI4) $4o0U) 4) UP-P-P b~~4J + -P-J P-4 P4- d$4k4-'4 4) 4) o co.)4k
>1> % > - - - 4): 30 : r 0 z 4) U 4)() .,1 ; 1- 1 > ) U~0- W 40- d~4 00 3." S 04 4-4 C-P44-) 04 u Cd 4 4) 1 1 1 -P
H C 1 4) Q.+ 4UU-1 4- .q+) + 41 04) +*r4 -, (4 H4-P$4)O> H -r
o d k$ 4a 4) k~U z 00 00 0-P_ Cd 4 4P+) 0 44 4-4-P4
n 14 -4 4 H H F-P- 0P- 0 00 00 I4)40 w D0
4) 4)4(D4)Q) 4) (1
CU 0CdC CCd mmCUmP914 44 P4 04 04 13
u () u u() u u CW 4 4 4Db. b r4-r -HE H-HEEEEr -
0 00 0 00 1 1 111 11 1-P- --- P- P-P P- P 4-)-P -P -P -P4 P- 3+ )4 J 3+ )- P- P-
.Hr jr r 4Hr r r H-H- H-f H-l *l r r H r r r r r r r 4 H 4
;Ik 4 $4 $ 4 k 4;;4 & $4k$k4 k &I 4 k $4 k $4$4 4 $4k
0O4) 4) 4) 4) 4))oococQ 0OC)O.OOOC).O4 -4 i - r-- -P - -HH H4 $4-14$4 $- 44 ;q4$44$ kf,
0
.ri 0 -NCli1 -t O L
35
![Page 47: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/47.jpg)
0 j b.
V. 0 00 0 0t 4 ~ 4
0 0 0 4) 04 . 44cU L
> >
0) +1 4)PrE4
4) 0 o4
0 Q4 CHWW4)uMOH
La.I
4, -
-H -
) k k $4 $4 14$4 . 14
0 0000 00 oo00
0
or 00 0000000-0 mmmmmmom
36
![Page 48: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/48.jpg)
TABLE 2-4. OUTPUTS TO THE
DATA ACQUISITION SYSTEM
Output Type Voltage
Series string current(169 outputs) Analog 1OOmV/A
Array current Conditionedanalog 5V/300A
Array voltage Conditionedanalog 5V/500V
Array power Conditionedanalog 5V/1OOkW
Array kWhr BCD 0/14 V
Output power Conditionedanalog 5V/1OOkW
Output kWhr BCD 0/14 V
On/Off Binary 0/14 V
Off-minsufficientsolar power Binary o/14 V
Off--error shutdown Binary o/14 V
Off--error recycle Binary 0/14 V
37
![Page 49: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/49.jpg)
tlT t Hu(iTfal Sol~.' T 1wfI
~~4Jrt~fl il& [I I I- 111 1! uEYr
CLL _20TOM WL
&W1511toN .1 r
FIGURE 2-19. OUTPUT FROM DEMONSTRATION PROGRAM OND)ATA ACQUISITION SYSTEM
738
. - ' . .- ' ' ' -
.. . . . , .. . . . . .. .. . . . . .. . .. . . . . , , - r . , . . . .. . ..L- .. . . . - . . . . ' ' . .
![Page 50: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/50.jpg)
rt,.I 14, 1 ;'9 1 "1-8 ,8 23
SYSTEI $TATLI$
S',STEM C OhlI 11 IOtNS
:.,:LFr 114i.,LAFI ION IS ' 1000.8 WATTS PER SCURRE IETEP
114 .ItIENT AIR TEIlP'EPTLIPE IS 68.0 DEGREES F
iF'PH', iIL11UT CUkRPEtT IS 250.9 RMPS
APPH- li' ll F' V i' Tl-,i IS 22. .4 VOLTS
mF'A.' 0I1PUI POWER 1. 57.6 KILOWATTS
(ONVEPTEF UL'TPUT F'IWER IS 52.0 KILOWATT':
i*RA, MET'R FFHDI, IS I1'F. KWH
',tjVF"P'k IETEF PEHEIING IS 899I WH
iwBt fiih t4 F ': INC C.FtElU . FF1I1I THE ARRAY
I,,l L.$ 1".7" - I 3 2" I IME AT STIPT OF SC Ai
i. 1.u 17. ;4 1.O 1.'98 1.98 1.". 1.67 1 .75' 1. - I 80 1.72 1.2 ) 2.0 2.00 2.01 2. O1 .0,
• .' 2. 1: 1 94 1.7. 1.99: 1.62 1.. 1 2-.00 1.81 I "
I.67 1 1 17 2.03 1.59 1.94 1.64 1.90 1.744 1.64 1 .8 1. 72 1.88 1.96 1.84 1.86 1.94
1.'4 101 1 h7 1.' 1.6 1.85 1.60 1.64 1.93 1.9'
1. 1.45 1 133 1. 31 1.89 1.65 I T2 1.94 1 .60 1.91.77 1 5' 1.90 1.4 1.52 1.91 1.71 1.88 1.91 1.81
, . I, 15:; 1. 89
6' 1 . 4 .' 1l ,45
1.0 1 : 1.85 1.-: 1 64 1.37 1.86 1.82 1.' 1.sl. , 1 1.5 1 1 1. 38 1.94 1.94 2.06 1I... ,.0 '
1: 2.20 1.66 1. I172 2.08 1 63 1.60 1.13 1.8
1 i'l 1.14 1.01 1 L 3 1.16 1 .15 1.23 1.21 1. :1.11 I.2"J .14 1.11 1.13 1. 10 1 .0 1.05 .91 1011.)1 1.11 .0. 1 0': 1.04 1.05 1 .0: 1.13 1.04 .
1, 1.12 1 .L I .0 .89 1.09 .92 1 .09 1.03 1 '1 I 1 0 1. 11 1.11 1.15 1.12 1.08R 1.19 1.13
14, 1","9 at 1"' 8:45 TIME RT END OF SCAN
FIGURE 2-20. DATA ACQUISITION SYSTEM OUTPUT
39
![Page 51: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/51.jpg)
. 14
"1... , , '"-a # ' , ,
I T LIi ' THRI I T -L% I-'I (J'.):. 1 1 h 7 I U.'l!1 '. I i.9 F' I-_
. \. Iii 'I i",II
Li "4 I
W~~~ ~ ~ I\1 111R
f I tl LILM04 i t1T 1.1, i I r. tol
q.1
FIGUR 2-1 AAACUSTO YSE U1U
- l ' "4o
![Page 52: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/52.jpg)
hl,9 13,19?9 1 '3I:54
Opl,) c rcult ,o t i , i ' 7'06. 92 Vo: I"Sksort c i rc iI C .dr r ', I1 . " Aimp,
max I filuM powtr of I' r Ing ls 176. Z . | 1 7 t i
u,,I.|, 2%0. 87b Vo I . "04 . IIpi
. 800
LA)EL
U
_-1CL
I..)
.10 0
clCLi-i
.200
FIF~tY C..T HGE: T '
Run on C1ug 1 3,1973 i 17: 1~E:kj
FIGURE*2-22. TYPICAL DATA ACQUISITION SYSTEM OUTPUT-
I-V CURVE FOR A CODE Y STRING
41
II
![Page 53: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/53.jpg)
3.0 RESULTS
Since the first testing of the power conversion unit in
September of 1978, the results have been extremely gratify-
ing.
3.1 OPERATION OF THE POWER CONVERSION UNIT FROM AN ARRAY
SIMULATOR. In early September, 1978, construction of
the power circuitry and basic control circuitry of the
power conversion unit were completed. Normal operation
of the power circuitry was verified in September. In
early October, the power conversion unit, operating from
a current-source array simulator, delivered power into
the Snuthern California Edison Company utility grid.
The tests demonstrated the stability of the power control
circuitry and the operation of the peak power tracking
circuitry. The tests performed were primarily qualita-
tive and the tinit met design goals, operating stably and
tracking peak power to within l9.
3.2 FIELD TESTS WITH PV ARRAY AT THE DECC FACILITY. During
the autumn of 1978, a partial array was installed at DECC
to allow system testing. The array consisted of some
Code Z and some Code Y PV modules mounted to their
frames and interconnected as they would be at the per-
manent site at Mt. Laguna. Some of the module frames
were mounted to shear panels while the remainder of the
shear panels were being installed at the permanent site.
42
![Page 54: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/54.jpg)
By January 10, 1979, enough strings of PV modules were
installed to begin system testing. There wer'e no sur-
prises when the system was operated in its normal mode,
extracting power from the array mid providing power to
the local utility grid. By March, 1Q79, the system had
operated successfully at array power levels up to 27 kW
(the maximum available from the partial array). The
system operated normally, without unnecessary operator
intervention for 43 days ( 414 operating hours) at the
DECC facility, extracting a total of 6218 kWhr from|| the
array and providing a total of 4861 kWhr to the utility
grid. Because the testing was performed during a southe'n-
California winter, the array was exposed to a variety of
environmental conditions: temperatures from 3t4-OOF,
bright sun, dark clouds, thick fog, heavy rain, and hail
with stones up to 3/8 inch iin diameter driven by strong
winds. The only environmental damage observed was the
flooding of some temporary underground cables from the
array to the power conversion system. Because of the
temporary nature of the installation, a-nd the expectation
that the underground conduit would remain dry, the tempo-
rary cables had not been designed for submerged operation.
Thoughout the testing at DECC the power conversion system
operated without failure. The entire system operated
through an hour-long series of intermittent brown-outs
and black-outs of the local utility grid, shutting
down for self-protection when necessary and restarting
automatioally when appropriate.
43
![Page 55: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/55.jpg)
3.3 OPERATION AT THE PERMANENT SITE. On May 29, 1979, the
power conversion unit, PMP and a few remaining array
elements were shipped to the permanent site at Mt. Laguna
Air Force Station. Most of the PV array and system inter-
connect wiring had already been installed at that time.
The power conversion equipment was installed and opera-
tional within a week. Since completion of the installa-
tion in July, the system has been tested and operated
under the local conditions. A formal acceptance test was
performed to verify conformance of' tile system to the
primary requirements of the purchase description. A copy
of the procedure and results of tile system tests at Mt.
Laguna and at DFCC are discussed below.
3.'I SYSTEM PERFORMANCE. Tests performed at DFCC and at the
permanent site verified that the photovoltaic power con-
version system met all of tile primary requirements of
the purchase description. Although tile formal acceptance
test (Appendix A) was performed during a brief two day
period and under tile prevailing environmental conditions,
additional data were taken during later operation and are
reported here. The data acquisition system was particu-
larly helpful in taking approximately concurrent readings
of the monitored parameters. At the time of the observa-
tions, the data acquisition system was programmed to
44
![Page 56: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/56.jpg)
provide "1hard copy" daIt" 1)titltolits onl request.
34. 1 Modes of Operation. Tho purchase description for the(
PV system called for a power convermion unit ciilpabl('
of operating in two distinctly di fferent modes with
only minor modi fications of the circuitry: (1) tile
atigmentat ion mode, wi th the system operating ini parallelI
with a uitility Irid and no hte s toratge , and (2?) tule
s tuid-alone mode, ilidepetldenit. of ' u 1. 1 1t poweri', wi th
battery storaev andi opel'mti on 1 mto a1 dodi-catod loau.
Thto powert cmOive PstIoi sy st em i Wl t i'st ei i-ii mode(1 1 , tho
.lgle t11-1ia t I on mode o, only.* The' Pc sumi t of 1. hosv5 tests
a .1ro ) tidh Io The poworu c ircu it ry of' the sy stvcii,
Ic ilig the' dc-dc( conveter ( Inplt regu a toIr/Vo It age
1 jmi tler) anid (ic-ac iiiverter are thoso tsed liv IWF' lit
its 02.1) liicmtoerrmpti.ble PloWor Smiplies (I'Ss ). Time
UPIS opera ito. 5 1Lkt' a :110(1 ? PV powr colive rsioti sys tenm,
e xc opt tha t the( Iiinpu t dc -c -oniverter operates f'romi
rce'ti fied tti-I-Ity power ra ther thii solaim powe.' 0111ny
the conitrol c ircititry wouild lim-vv to be modif1icvd to ccii-
ye rt the PV system from mode t toi mod.' 2 ope rait ion TI 'i v
02.1) kW UiPS charactertstics an,(' described below as 41n
Imdi at ion of' the performa-mce which can be expected in
a stand-a lotte op('ra ttont of' the( TPV juower c oliver1s iou1 sy'stem.
1.14.2 The Power Coniversion Systemi.
![Page 57: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/57.jpg)
1. & .2 *I. input Power. The owr~ emi xverxs toii sys$tem opt' iatotd prio-
perl'1y thrlough-Oout thlt ranlge t'xoml no0 i uxput Powe'r upl to
thle max twuni obst'i impt poweri, (P)kW * Thlt power Coll-
V0ex's ton sys temt tracked tile array penk power to wi thit
1% ( typically 0.1'4) ovoX' tile Input poweir ranige of 10-00 kw.
~* * * 2 llpt. Volt age * Thlt power conlve'i onl systeml operiatetd
pi'ope 'l y over thle rangeI~ ort peiak piwer1 p0oint s eltv oilit ered
and pr1ottttt ttsel t' aga Lust unloadted arrayv voltage.* The q
sy stemtt wasM totodtel t Litlput VoltagoM 2'01A allove mid lie low
thle twill power poijut 11% ope'at tlg tilt,' nutiltx 1 ovori'ite
akitlitstiiit . phe systeii opt't'ttetl stalIy bot'h ab~o and
bet'low tile' pe'ak powerI po i it
Ol.: * til Oupt Powt'u'. Opteralt out Io(t' t lit, powe r k colive 'SLou sy steml
fta s hoot' dt ttimoti s t 1'.t t td ,akt oil t, litt powe, I, I o'v t, I s up1 t o 60 k W
I 4 . .~i Olt t put vol tiage * As t estetd Lit mtott I opj'rat Ion, tilt powerF
ciy't ott Systemlt olitilput voltait Is ekilal. to thle liti-itv
gid t vot tlt' 11%. tI altitty. * PTe 4vs8tt out opt' vat ed pro pt' x.1
overt ii I i t%-va.ttgt gid t cotdi t tons e'it' olilttrt'a dur'Lig
te's t ittig.
ie'tu t ilt, 5itim.tt'tvt' Fr tot' hs liteen1 It sod I tII UPS appl lIt'l at I OtIM
i t iias ditttotts t at a'd t'xt'a 1 it olitplt eftaalett'ivst ics.
T'lt,' va I t 'tt't t'lu I it ti ott i s t yp Iti1 ly + 1%6 wi tit a Itamea
itilta 1attta'a tfit' les tittit 0, '1q0 titt) 1.1 o- to-titrt.l 1Volt afgt
PTe phxaist' t aiat''t'Imti 120+1'I0 for Ionta tutilbatii't till
![Page 58: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/58.jpg)
to 30%.
3.4.2.5 Efficiency. The measured efficiency of the system is
plotted as a function of output power in Figure 3-1.
The overall power conversion efficiency is 92% at 60 kW
and 91% at 30 kW. The no-load losses (input power from
array with zero output power) are less than 2.6 kW at
all normal array input voltages. The stand-by losses
are approximately 65 kW.
3.4.2.6 Harmonic Distortion and Waveform. The measured total
harmonic distortion of the output current in mode 1
operation is 2.696 over the output power range of 30-60 kW.
Below 30 kW the distortion amplitude remains relatively
constant (approximately 1.3* of the full power output).
The output current waveforms at 14 kW and 45 kW are shown
in Figure 3-2. There is no observable disturbance to the
utility grid voltage. Figure 3-3 shows the grid voltage
(a) with the power conversion system off, and (b) with
the power conversion system on and delivering 40 kW to
the grid.
The output voltage of the same inverter operating as an
UPS has a total harmonic distortion of less than 3% with
a maximum single harmonic distortion of less than 2%.
t.14.2.7 System-Grid Interaction. The power conversion system
incorporates soft-start characteristics to avoid
47
![Page 59: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/59.jpg)
80
~60-
50.
10 20 30 40 50 60POWER NkW)
FIGURE ')-I1. POWER CONVERSION SYSTEM EFFICIENCY
AS A FUNCTION OF OUJTPUT POWER
48
![Page 60: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/60.jpg)
Ii
I S
I,. I. I
~ \ S.
![Page 61: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/61.jpg)
i~t~ i
I. -.
LI
I * I
\ .\ "1
Ii
![Page 62: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/62.jpg)
spoon
FIGURE ~I 1 RATE~ OF WISP' OF' O UT'PUT ('1 IH1R IKN ATl ltI'PN- oN,
lIOIUIONTAi ,I,[ LE -4coN1)SIDLVIS ION
VERTI1CAL. SCALF :152 ANIS/I)JV-1.SIN
![Page 63: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/63.jpg)
disturbance of the grid at turn-on. Figure 3-4 shows
the typical rate of rise of the output current at turn-
on. The small mismatch in voltage and phase across the
output contactor is responsible for the discontinuity
seen at the point of turn-on. There is no observable
disturbance to the grid at turn-on.
There was some initial concern that the abrupt current
change at turn-off would affect the Mt. Laguna grid.
Fault shut-down during high-power operation was of partic-
ular concern. DECC planned to perform a set of tests,
shutting the system off, first at very low power, and
then at higher power levels to determine the affect on
the grid. During the first day of testing, however, the
system was accidently shut down with 65 kW output to the
grid. Since no significant disturbance was observed at
the main power station, no further tests were deemed
necessary.
3.4.2.8 Protective System. The protective circuitry of the PV
system includes, but is not limited to, that required by
the purchase description for the system. (See paragraph
2.4.4.) All protection circuitry operated properly and
workable fault thresholds were established for all pro-
tective circuits.
52
![Page 64: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/64.jpg)
During the design phase it was hioped that the ground fault
detector couild be oper;ated to provide anI additional mea-
sure of' personnel protection by iniiat ing the shut-down
and array- short ing -iequenc e wl en potentiallyv dangterouls
ground fault currents (more thani 50~ mA) Were dletected.
During tests at DFCC , however, i t was found thant whereas
the normal ground current on ;I d ry dat was approximate ly
2 mA, the total array g-roxnd ctinrreu t on Wet days frequently
reached 50 mA * Thu s the grotiid Cturn1t de tector-, as deliver-
ed, operates to provide an i hid ieat Lont of excessive ground
current otIl,, .
3. . 9 Expansion Capabil1i ty . The powert c onive si on svstem meets
the purchalse de se 1.1pt ion requiro'ment s fo r ex pandahi iit\'
in eithaer ope ratinug mode.* III mode, , add in ug mo ther inde-
pendent power c onvers iont -N-st em is e omplIe t clN stra~iighut-
forward.* Fac ii sv stemt is i deedntteon t ro Iled t~o oper-
ate into thme utilIitvl griti.
In mode 2, C ombila t ionl oft two on it s maly he acieved by
operatingl iin a master-si ave mode. flte inuverter has beeni
operated in thi s matnuel in manyi UPS itistallilt tolls.
3.4.*2.*10 Electromagnietic Interferenice. As unttioned a1bove, the
power conversion circuitry and cabinet designi of the PV
system tire identical to those of DFCC's 6:1.5 kVA I'PSs.
aThe resuilts of EMI tests performed on one Suchl UTPS unit
are given in Appendix 11 of this report. The PV power
![Page 65: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/65.jpg)
conversion unit includes additional input and output
filtering which should result in even lower conducted
emissions, and the removal of input rectifiers should
result in a slightly lower radiated emission in the PV
unit. Because of the low EMI levels, the low frequency
of the emissions, and the 200 yard distance between the
power conversion building and the nearest sensitive equip-
ment (with its 100 Mhz to several G~lz operating range),
there should be no significant interference with that
equipment. None has been reported.
3.4.2.11 Audible Noise. No lactual acotistic noise measurements
were made on the power conversion system. An uninter-
ruptible power supply using the same inverter, converter,
cabinet and blowers has a maximum acoustic noise of 85dB
measured at 6 feet from the cabinet. Two cooling fans
mounted in the ceiling of the power conversion building
produce a net ligible increase in the sound level.
3.4.3 The Array. Although the emphasis of this contract is
on the development and operation of the power conversion
system, some significant observations have been made about
the PV array itself.
'.4.4.1 IOtput Power. The measured array output power reached
a peak value of 69 kW. This higher-than-rated array
power was observed at a time when the insolation was
enhanced by reflection from nearby clouds. On a clear
54
![Page 66: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/66.jpg)
August day with 1016 WIM 2insolation and 71OF ambient
temperature, the array output power was 58 kW. WIhen
the data from the data acquisition system is reduced,
extensive detailed information on output power as a func-
tion of insolation and temperature will be available from
Sandia Laboratories.
3.4.4.2 The PV Modules. The only major problem which has arisen
in the system is with the Code Z PV modules. During
the system tests at the DECC facility, it was observed
that some of the Code Z PV cells operated at a con-
siderably higher temperature than others. The heating
effect was observed both with the array shorted and with
the array providing power to the power conversion system.
When the PV modules were shipped to Mt. Laguna, the tech-
nicians installing them began to notice bulges, or
"bursts" in some of the cells. New bursts are still
appearing at the time of this report. Although there has
been no appreciable reduction in the output power of the
array, it is clear that the continued development of
bursts will eventually cause deterioration of module per-
formance and failure of some modules to produce power.
The tendency of cells to develop bursts appears to be
correlated to the presence of high temperatures. The
bursts may be caused by even or uneven expansion of the
cells or of gasses trapped under the cells during
55
![Page 67: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/67.jpg)
encapsulation.
Jet Propulsion Laboratory (JPL), who provided the PV
modules under contract with the Department of Energy,
iz studying the temperature and burst problems and will
be publishing a full report of their findings. They
have found that the temperature of some cells exceeds
the temperature of others by as much as 800C. Two
heating mechanisms are responsible for the high tempera-
turest heating due to photocurrents in reverse biased
cells, and heating due to leakage or breakdown in re-
verse biased cells. A cell of a loaded module becomes
reverse biased when its current production capability
is significantly less than that of the cells connected
in series with it. The first heating mechanism occurs
in any reverse biased cell: the power dissipated by
this mechanism is equal to the photocurrent generated
in the cell times the bias voltage and may be as much
as the peak available power of the rest of the cells
of the module. The power, however, is distributed over
the entire photocurrent-generating area of the cell
for maximum power densities of approximately three
watts per square inch.
The second heating mechanism does not occur in all cells,
but does result in much higher power densities. Uneven
heating in some cells led DECC to investigate the reverse
56I. ih.
![Page 68: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/68.jpg)
breakdown characteristics of the PV cells. Tests were
performed on eight Code Z modules (320 cells). The test
set-up is shown in Figure 3-5. With a module shorted, its
cells were occluded one at a time by an opaque disc.
Ideally, covering one cell in the series set should result
in an open circuit and zero current through an external
short. In actuality, electrical leakage and leakage of
light around and under the covering disc result ini some
output current. For most cells, the "dark" current was
between 10 and 100 milliamps. Sixteen percent of the
cells, however, had "dark" currents in excess of 200
milliamps, 7.80 had "dark" currents in excess of 500
milliamps, and 2.2% had "dark" currents in excess of one
amp. The cells exhibiting "dark" currents of more than
500 milliamps became discernably hotter than the other
cells. In general the heating occurred in a very small
area of the cell, causing an extremely rapid rise in tem-
perature. In one case, when the opaque disc was inadver-
tently left in place too long, the surface of the module
reached a temperature of the order of 80-1000C. The result
was visible melting of the solder and of either the plastic
or the adhesive material under the cell. The cell became
physically distorted at the hot spot. These tests, per-
formed with totally occluded cells, resulted in greater
localization of the dissipation than would normally occur.
Under normal partial occlusion, the power dissipated in a
cell would be shared by the distributed photocurrent dis-
sipation and the localized breakdown dissipation.
57
![Page 69: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/69.jpg)
K> Ixj~4)
4-)8 /H
0 I
![Page 70: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/70.jpg)
Tite Code Z modules .4rev particularly prone to reverse bills-
tug. The I-V characteristics t'or the two ty-pes of' cells-
Lire different as soonttit Figuire 13-0. Vendor Z has attatined
a very sharp I-V curve with at consequent htigh coil eC~i-
ciency. Thto penalty paid for, tit- charc torts tic is the
str'ong dependence of' thet voltage on the current ait high
currents * IV onle cell can' t pr'oduc e as 111icit cuirrenit ats
the other cell s of' the module, the revinailitdei' of' thet modleb
maliy apply a1 sign I t1iclant reverse, voltalge to the liti tiig
Cell ( throuigh the, load).
Tests at IWCC von it'd what thlt en rvt' prod xIct with tilt
1110(1111 oper:a th- I tttito a niormal I oJd , at 20' dit' i ci one In
thlt cliveont c apal.)L I tv of' oile cel c.1ust s at sigiiIc att
(1.0-20? Vdc ) t'eve rst, Voltage across the c oll %Ixk sltn1' 1-
cant power d Iss ipat: bit in tito veil. Opt'atitg into at
short ciL en .1t , htoweve r, 41 vti't'vilt dot ic ietlt oil(lonly 10(%
wi 11 have the saint'e I' t'vet.
Un'o ttunAte ly , seoe t i real iit co"1d nd ition 5c anl re0sul t
ItI L0-20% itso latitl var tatt.i ots he twt'ot c-ells of' a m10(11it'o.
Singlev cci s mlIv hoe('l 01WS1itadowt'tItilt(t, to weed gr'owtht, auld
dirt i st ribu11tion is lit noet'ssai -ly even * Condenised or
proc ip i.ta ttd watter onl the mo(,dules somet timtos causes dirt
to collect on the lower cells. 11ind droplpings tire not
evenly istributed.
'iALI
![Page 71: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/71.jpg)
Code Z
Code Y
L~
H
0.25 0.5
VOLTAGE
FIGURE 3-6. COMPARISON OF CURRENT-NORMALIZED
I-V CURVES FOR SOLAR POWER AND
SOLAREX PHOTOVOLTAIC CELLS
60
![Page 72: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/72.jpg)
.'ONCI 'SIONS AND RECOMMENDATIONS
With the exception of the problems with the Code Z
photovoltaic modules, the operation of the 60 kW Solar
Array avid Power Conversion System has been more than satis-
factory in every way. The array has produced power in
excess of its rated ouitpuat, and the power conversion sys-
tem hits operated within its design goals and withotit fail-
tire during months of testing at DECC and at Mt. Lagna.
Much more information concerning long torm system opera-
tion will become available as the system continuies to
operate at Mt. Lagina and data become, ava ilahie frolm thle
data acquisition system.
Even a system as totally successfutl as this one imust be
evaluated carefuilly at completion with an eye to possible
improvements in future systems. Some of DFCCs observa-
tions and conclusions onl the Mt. Latna system are, di s-
cussed below along with some recommendations for ftuire
systems.
24.1THE ARRAY STRUCTURE. The mountintg frames for thle PV
modules were designed to support and protect thle modulezs
during winds of up to 120 knots. The fram~es were sized
on the basis of series stringr size, tile Code y frames
holding a complete string and the Code Z frames hold-
ing half a string. Thle PV modules couild theni be installed
onl tae frames and the intra-string wiring performed indoors
61
![Page 73: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/73.jpg)
with the panels not exposed to sunlight. Although the
assembled frames proved rather too large and heavy to be
carried by two men, this sizing of frames proved especially
convenient in this application where part of the array was
installed at DECC, disassembled, and moved to Mt. Laguna.
For systems to be installed in a more benign environment,
some savings in weight and cost might be achieved by re-
designing the frames. The frames were easy to construct
using welding jigs developed for that purpose, and a com-
plete Code Y frame could be assembled in approximately one
hour by an experienced welder.
In future systems, the use of wood for the shear panels
should be evaluated in terms of ease of installation and
site environment. Mechanical alignment of the long rows
of modules was difficult, and many mounting holes had to
be redrilled. The use of adjustable U-channel mountings
would ease the installation of large arrays. The ability
of' thv wood panels to withstand the harsh Mt. Laguna
environment should be evaluated after a few years of
exposure.
4.2 ARRAY WIRING. In this system, approximately 1000 cable-
mounted disconnect plugs were installed within the series
strings to allow isolation of pairs of modules and redue-
tion of the maximum daytime service-point voltage to
50 Vdc. The protection provided by these plugs is
62
- . .'j
![Page 74: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/74.jpg)
redundant. Servicing can be performed safely during
periods of low insolation or with the panels covered by
opaque covers supplied for that purpose. In future sys-
tems, the impact of these plugs on construction time,
cost and reliability should be weighed carefully against
the questionable contribution to safety.
Ideally, future PV modules should be fabricated with the
reverse diode installed internally and all connections
made through a connector molded into the unit. This
would drastically reduce the time required to install
large arrays and eliminate the need for additional dis-
connect plugs by eliminating any exposed terminals. At
the very least, the Junction box covers should snap into
place, rather than be held in place by four screws. Using
time estimates from MIL-HDIIK-472, more than 169 man-hours
were required Just to remove and replace the covers of
the junction boxes during wiring of this array. Location
of a faulty reverse diode within a strig could take as
long as an hour because of the time required to gain access
to the diodes in the junetion boxes.
In the Mt. 1a-na installation, the intra-string connect-
ing wires were mounted to the module support frames with
metal I-clip, to reduce wind damage to the wires. In the
design of future installations, some thouight might be
given to the provision of mounting holes or anchors for
tie wraps or other cable mounts.
61
![Page 75: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/75.jpg)
4.3 ROW TERMINAL BOXES. The row terminal boxes on the array
provide a termination point for series string outputs
and underground cables, and include surge suppressors for
lightning protection. They also include test Jacks for
measuring the outputs of all strings in that row. Since
the same information is available at the PMP, or at the
string output connector mounted to the PV module frame,
these terminals appear to be superfluous. Throughout
installation, checkout and testing of the system no
engineer or technician used these test jacks.
4.4 SOLAR POWER MODULES. There are two distinct problems to
be addressed concerning the Solar Power modules: (I)
how future module design might overcome the problems ob-
served with these modules, and (2) what might be done to
improve the operation and lifetime of existing modules.
The solution of the first problem is generally understood.
Both dissipation mechanisms described above can be mini-
mized by the addition of reverse diodes across subsets
of cells of a module. The number of cells in a subset,
"n", must be chosen such that (1) the peak power of n-1
cells can be dissipated by the nth cell without damage
to the cell, and (2) the maximum voltage of n-1 series
cells does not cause reverse breakdown in the nth cell.
From the construction of the Solar Power modules, it
appears to be relatively easy to install two reverse
64t a
![Page 76: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/76.jpg)
diodes in the module, each diode across 20 of the cells.
Installation of these diodes would reduce the maximum
photocurrent dissipation in a cell by a factor of two,
and eliminate breakdown in all but a small fraction of
the cells. DECC estimates that the cost of installing
these diodes would be approximately $30 per module.
Some consideration might be given to installing four
diodes, each across 10 cells. This modification would
be more difficult and the cost would be more than twice
the cost of installing 2 diodes. Further studies by JPL
should determine whether it is necessary to reduce the
maximum power by more than a factor of two, and whether
installation of the diodes could be performed without
adversely affecting the reliability of the module.
4.5 ARRAY SHORTING. The input contactor KI of the power
conversion system shorts the array whenever the power
conversion unit is off. The purpose of this is twofold.
Firstly, with the power conversion system off and the
array unshorted, the voltage at the unloaded array can
be as high as 400 Vdc. Shorting the array removes the
high voltage for the connected strings providing added
protection for service personnel. Shorting could be
particularly useful in the case of a ground fault due
to personnel contact between high voltage and ground.
Secondly, the current through the shorting circuit
65
![Page 77: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/77.jpg)
breaker is monitored to detect the presence of sufficient
solar power for start-up.
In view of the problems with the Solar Power modules, the
wisdom of shorting PV arrays has been questioned. Al-
though it would alleviate the problem somewhat, eliminat-
ing the shorting of the array will not solve the problem
of the Solar Power modules. Occluded cells are being
reverse biased whether the array is operating into a
short or into the power conversion system. There are,
however, other arguments for leaving the array open. The
high current contactor required for shorting the array
is generally quite expensive. It must be rated for inter-
ruption of the entire short circuit current. An insolo-
meter or two redundant insolometers could be used to sense
the presence of sufficient power for turn on. A shorting
switch or connector could be provided to allow shorting
of individual series strings or subarrays during servic-
ing.
DECC does not recommend that the present Mt. LaCuna system
be modified to operate with an open array. In normal
operation, the array will be shorted only when there is
insufficient solar power available, and the stress on the
PV cells is minimal. If the system is to remain off for
extended periods of high insolation, the individual strings
can be unshorted manually at the string select switches
in the PMP. In the design of future systems, the trade-
66
![Page 78: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/78.jpg)
off between cost and safety will have to be evaluated.
Some of the factors affecting the decision will be the
array voltage, array current, and PV cell characteristics.
4.6 THE PMP. Prior to the installation of the data acquisi-
tion system, the PMP was invaluable in identifying faulty
or inoperative strings of PV modules. One improvement
which might be made in future systems would be to replace
the fixed loads with a variable load (static or dynamic)
to allow plotting of the I-V curves of individual strings.
4.7 POWER CONVERSION UNIT. To allow mode 2 stand-alone opera-
tion as required by the purchase description, the power
conversion unit had to include an input dc-dc power con-
version stage to supply a regulated charge voltagre to the
battery. In the augmentation mode, thourh, the dc-dc con-
verter is operated only to protect the power inverter from
the high array voltages present at start-up. For fuiture
systems operating in the augmentation mode only, considera-
tion should be given to redesigning the inverter using
components capable of operating at the maximum array volt-
age. Improvements in cost, efficiency and simplicity
would result from elimination of the dc-dc conversion
stage.
4.8 GROUND-FAULT PROTECTION. Because of the ground current
measurements made during tests at the temporary site at
DECC (paragraph 3.4.2.8), the ground-fault detector does
67
... . . . - " ... . . . .' . .. .. ... .I'£III I II III l rol i.. .
![Page 79: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/79.jpg)
not initiate a shut-down and array-shorting sequence.
Although the 50 mA protection threshold was frequently
exceeded at the temporary installation, it will not
necessarily be exceeded with the system properly install-
ed at the permanent site, even during wet weather. DECC
recommends that operating personnel at Mt. Laguna monitor
the "ground fault" status lamp periodically during the
coming wet season, when the soil around the underground
cables is saturated with water. If the ground current
does not exceed 50 mA during these operating conditions,
the ground fault circuit should be modified. Addition of
a single wire will change the control circuitry so that a
ground fault indication initiates a shut-down, shorting the
array and removing high voltage from the array.
4.9 OPERATION. To date the system has operated reliably with-
out fault shutdowns. The power conversion system, however,
is located in an unmanned building and service personnel
must be dispatched periodically to verify that the system
is operating. It is therefore possible that the system
may remain off, with the array shorted, for some period
of time.
When the system wiring was done, extra wires were strung
through the conduit from the power conversion building
to the manned, diesel power generating station. It is
recommended that these wires be connected such that
on/off status contacts in the power conversion unit are
68
![Page 80: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/80.jpg)
operative to drive a lamp or other indicator in the manned
diesel power station. In this way, system shutdowns can
be attended to promptly without unnecessary stress on the
array or loss of solar power.
4.10 CONCLUSION. The 60 kW solar power array and power conver-
sion system is the first of its type: designed to be a
working component of a power generating station and to
provide a significant portion of the station power. The
primary design emphases were making the system stable,
efficient, self-protected, self-sufficient, and automatic.
Unlike previous research and development systems, the
Mt. Laguna solar power plant was designed to operate com-
pletely unmanlned over extended periods of time.
No major technical difficulties were encountered in the
development of the system. The design of the control
circuitry avoided the instabilities which have plagued
so many photovoltaic systems. All observations to date
support the belief that a dc-ac photovoltaic energy con-
version system without on-site energy storage can effec-
tively augment a utility grid, even in a remote location.
Continuing long-term operation and observation of the sys-
tem in the future will determine the system lifetime,
maintenance requirements and the actual fuel savings re-
sulting from system operation.
69
![Page 81: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/81.jpg)
APPENDIX A
ACCEPTANCE TEST
Al
I-
![Page 82: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/82.jpg)
AL' 1' II'ANt'' 1'vs iuot I'i' I) l N I
Fl 111
'4~o1. \ POWL'A1. t2QNVI R S LON SFl'
CON IRAC IDELTA ELECTRONIC CONTROL CORPt I V LWZ V IRVINE, CALIFORNIA, US A
CMI ('K
MIG DIECAP%'ROVL1'
APPRnVI D SIZE CODE IDENT NO IORAWING NO lviR
APV,'0VED 33434 7-10SCALE JWT SHEET
,HOP GRAPHICS/ACCUP11SS11
-,Ro" NOA-064 A
![Page 83: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/83.jpg)
1.0 SCOPE
The purpose of this test proc edure is to y ify li-oper
operation of the Photovoltaic Power ('nolver .ion Sys.tem,
DECC Model 61211, provided under I .,*. A 'iu\' I:IAD(PC
Conitrict DAAK7O-78-C-O018. Ti tests to bo perfornmed
fall into three main categories: (I) tests of tlh,
invorter anld PMP operatioi, (2) system tosts at
the D"CC facility (with a pa'tial a Ir';i ), ,i1d (3)
field tests of the final in-;tallatioll.
2.0 APPLCABLF DOCUIFNTS
MER.ADCOM Contract I)AAK70-78-C-OO18, Purch.ipsDescription
DFCC Workmanship .'tandards Mamual
3.0 TFST REQXIIREMENTS
3.1 GENERAL. Unless otherwise noted, all test- are to ,e
performed at ambient couditions. 'he te'st equipenIet
in Tall, 1 shall be used. Slihst i t, ioll of k'qttuivalv'lt
e(Iuipment shall be allowed only wlu'ii anproved by the
DECC QA manager, and all equipment substitutimn sliall
be noted on the data sheets. All test eqiilmezlt shall
have a sticker or tag showing the calibration date
A3
-A
![Page 84: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/84.jpg)
and tiit tliate tile ne'xt ciltllati oil Ii dum.. No ot'qu i p-
,Int'l Is shal II ybe Ii'ic be te It 0 Iv (A te ' c. i I rtiIoil I
due' * 1w sourW(' midt 0 13( loads I not '101 IWL'ca1..bat t
if .id('(llltatly moitorod by calii ta ted vqu i p100
s'uitiiits arel to be pe rlorod -(1 i(I 11114e la t .i rl'i'Ol'ile
inldeat 1 'd ill Sec tion It
1.2 INSP'L'l'I ON * All ot~titpilent shoi h e i spweteod Cr (-meti-
fot'iu11nce to draiwil ig anId to tho ~ Dl( \orl'lii~iill i p st .1ii(l-
'rds anId slhi 1 t1it- itimpected I'tti'l e' t' i 1 l jH l.tI
I 10V N' tr F STl an F Ii I P O t I Nti Vi. Fii N'F \ ~ 1) 11N 1
Ii t- t. 11 ,ii ~ i I i .I r h 't. I ' I ti I \. 4 t Ii I , I I
1.i~ o I c o I .Oi VI I ihi it I e I, I ,'ih . , I t I I
to Ilol~ls IS k I ?0 %*dc''l~l AN) ~l. Us (lilti. I 11)t' Iitttl'
%t. Io I1w c x sJ . S t
i A , C o, tl 11
![Page 85: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/85.jpg)
verter and PMP meters (Table 2). Calculate the per-
centage deviation of each panel meter reading, f'rom
the calibration source and record as indicated in
Table 2. Meter locations are shown in Filure 1.
3.5 TESTS WITH PARTIAL ARRAY. These tests are to be per-
formed at the DECC facility using a partial ai ray
(consisting of both types of PV panels) akiid the
Southern California Edison Company utility g,,rid.
See Figure 2. The purpose of these tests is to
verify proper and stable operation with a l)ioto-
voltaic soairce and utility interf'ace. J,,rform the
measurements and record the data is indicated .
Section I4 (Tables 3 and 4).
3.6 EXTENDED 01IERATION. Pollowing- tle 'ormall te-st. I i
the D'CC facility, operate the sys(-emi 1'om hit' &rr;tv
and into the utility until the peim;,,iit site is
ready. Keep an operation log to tiote ;my unsual
operating, conditions or system mnouil'mictiois. |Apjwnd
the log to the test data as Table 5. Note prill-iry
array parameters under various weaither cotiditious.
3.7 TESTS AT Till.' PERMANENT SITE. 'I'uest t('t.- veril'y
proper installation and operation ai the pel'. iiiit
site. The tests include verification Of proper
A5
![Page 86: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/86.jpg)
intercounnection of the arraiy an I'M11, vor'if ic;Itioii ot'
stabi I! ty with full power array mut~i lokc:ii m, ild
check of protection circuitry. Peru rm the iguwasmre-
merits and record the data as indiciitedl in Soc tioi 11,
Tables 6, 7, aid 8.
A6
![Page 87: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/87.jpg)
SN 101
i)at,, 4/27/784.0 TEST PROCEDURES
4.1 INSPECTION. Inspect all equipment for coill'ormanc,.
to drawing and DECC workmanship standard.-. Inspect
for general appearance. Attach to this procedure
a list of all non-conformances. If there are
none, indicate so below.
No non-conformance_ _ _ _
4.2 ISOLATION TEST OF Tl': INVI.IIT, ANI) I'MPi. PIrforli
the procedure described in' paralrralh 3. 3. Record
the measurod lenkaj:o currents helow.
Lakag-e from inptit leads to chisisis-osL,,,\
[,eakagle from output leads to cl,,t sisO I I 1\
4.3 M F'"I' ACURACY, INVI'TIE ANi) PMIP. Verify tiln,'-
ctivacy of the iiiverter and 'I'1 panel mete i's .i s do-
scribed in parallraph 3.4. lH,,erd dlati, im Table .
4.4 rv.STS WITH A PARTIAL ARRAY.
Note: Except where noted, mea sliroentll at ;i' e to be'made with the iierter in the AITI') mode.
4.4.1 Standby Power and Current. Coinect the system it,
the normal fashion with the pirtinl array ,miid the
local grid. Place all string swit,'h,,s on the PMI'
in the enter (off) position. With t ;tnra al. met-,',
neasur the input ctlrrent tiii the Ilnp it poucr I'l o
A7
![Page 88: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/88.jpg)
tl" it ili ty g:rid with the sy.st.o.,i oftT. IHvCo rd tlhe
mlll ilt lltlc ut s in Ta)1le I".
4.4.2 Start-V p. On a sunny day, switch tho stril switch..
to the LINE position one at a tim. Each -vwitch
iieton should result in an incret ,, in the, 11)t
cutrrent (M2). The inverter will ovettually starl up.
Record the input current (W?) ,jll.-t p'ior tt, start-u).
After start-up, record the inputt 1 ,. vt r (W) :111d til
outptt power (M117). Calciulat" t t, p owr'P to.,-, in
the system (M3-M17).
4.4.3 Operation. Perform the motsuiivetm.t, indicatol iLi
Table 3 and record the result- ill ';011% '.
I.4.4 Fault Protection and Automatitc Shut-l)owi. Test til,,
fault protection and shtit-dowt 'eatLtros mnd vriL'y
operation as indicated in Table 14. List any fail-
tires or unusual operations or conditotts it the
c olllnell t s C0 ll1un
1e.5 TESTS AFTrER FINAL INSTALLATION.
Note: Except where noted, measimreiietts ;o'e
to he mt'tlde with the inverter in the AUTO imode.
4.5.1 Strt-Up. On a sunny day, switch the stritt,
switches to the LINE position one at it time.
Verify that each switch action results in ui
increase in the input current (M2). Verify that
A8
![Page 89: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/89.jpg)
the inverter starts up at approximately 35 amps in-
put cti'rent.
4.5.2 Operation. Perform the measurements ijndicated in
Table 6 and record the data in Table 0.
4.5.3 Fault Protection and Automatic Siit-)own. Tst
fault protection and shut-down fatuires ;and verify
operation as indicated ini Table 7. Perform ititer-
lock test by opening and closiniig the remote circuit
breaker. List any failures or tlunu1.Suail cotiditions
in the comments column.
4.5.4 Comparison of Solar Cell Strini- Oiitltits. This test
is to be performed under conditions of stable iiol-
ation. If possible it should be porformed under
conditions of maximum insolation (between 1 I A.M. arnd
1 P.M. Pacific Standard Time on a clear sun,,y day.)
Select one Solar Power string and one Solare.x string
to serve as a reference. Operate the system in the
normal manner from the full array and into the utility
aet. Using the outputs to the data acquisition sys-
tem, measure the output current from each string com-
pared to the reference string. Record thre current of'
both and the ratio of the measured string, cutrrent to
the refrence string current.
A9
![Page 90: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/90.jpg)
4.5.5 Outputs to Data Acquisition System. The presen,:e of
string current outputs has been verified. Check cal-
ibration of analog outputs and presence of proper dit-
ital outputs as indicated in Table 8.
AIO
![Page 91: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/91.jpg)
09
* All
![Page 92: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/92.jpg)
LiL0J N
i
0 NIIgo-
4UI Lii
-.j
z40 L -dr
A12
![Page 93: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/93.jpg)
a.
LAJ
LL.
A1'
![Page 94: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/94.jpg)
Table 1. Test Equipment
DC Insulation Tester DECC Model b1107
Digital multimeter Danai 4200 or equivalent
Distortion analyzer 11P 13,1A or equivalent
Oscilloscope Tektronix 54311 orequivalent
Oscilloscope camera Tektronix C-12
Power meter Scientific Col'mbu.iDL-A2-609( oreqtiivalent
Stopwatch Accurate to 0.54
A 114
![Page 95: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/95.jpg)
c *d
In. *l
-c 0 0 C
$f4
+N N' z
4-) 4- M 0 o o ON 41o0 0 4) 0 '0" 0' v) 0
o~ P I I I H m C
tC 0 $ 0 l' :3 r z0 0 C' C ~ )r u C)
H4 0- H .u :,:
M Q-
H H -
n H t4 H(pU 4
C m (n ~
A15$4P
![Page 96: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/96.jpg)
f4 0
.0 c4) 4
I 40 1 1
Q 0o 0)
0 0
ON 0 0 -
C' 4 -H C N I-
o~ 4) I C N .
N~ ON - N
*4
0 ~ ~ ~ 1 c- 4 $ $ 4-
..-. ~ 4) -P P -P-4 )
4) 0 4J ) 4 ) 4
4.) 4 41
z $4 $4
P.. P. 4 . .4
0- 0 > 0 0dZ $ 4 H 4 $4 4
(n) 4)-)c~ P ) ) 4~$4 ~ CUQ
4-)
(-4P04)
A16
![Page 97: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/97.jpg)
UINE-P 4
0
oof4
0 c
N~ >0
434
0) CU
OCU --Pv
0 ) M 00 ~-A4C t4 0.*' S
CU 0U) rq
4) 4.)4.) 0) 01I
@20 if) *CV 91 -- r f ~~~~-4~~IL -C _ _ _ _ _ _ _ _ _ _
0 10 014)4
*4 U) 0go1 01 - &n 44 r+ H $q
4) E0
00 -P 4.)
@2 E E 4 4-
00 0. CU5 0c~ - -N 0i 01064
op. -. fl 4A17
![Page 98: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/98.jpg)
7 AD-AS A77 DELTA ELECTRONIC CONTROL CORP IRVINE
CALIF F/ 1h/1-
DESIGN, CONSTRUCTION AND TESTING OF A 60 KW SOLAR ARRAY AND PON--ETC(U)AUG 79 J S SUELZLE DAAK70-T -C-O018
UNCLASSIFIED DECC-61211-003 NL_hEE hhhEEEEEEIEEEEEIIIIII
2llllllllll
MMMMMMMM
![Page 99: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/99.jpg)
-~42
00
04 0,z -H 041
4-)-
co r, -cM CU
w o t - 0 a%. -t
to4 t.. -:T - t-- --. . 00 - 'j o ' 4
sl ;I C. N- - I~ N I
* 0 ,. 0 -
4-P-
14 4.1 - - --I I-
40 -40I
@0
4-PC
0
0.0 0 a004C
4.V4
0cU 11 E
01 H 0 0 N- (-4N
k0~ UA18
EM
![Page 100: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/100.jpg)
44
-Nz
r- -4V0 _-
- 4 - -4 - -4 > -%4 l
0~I No w 44 I o
0 r. 44 4 ) : 3
(n04) r. - t_
4) 4 J O 4) 1t
r: 4, M
'4-
00
4- 4) C4) r4 4) 4) 0 4) 4 4 ) 4)
4) ~ ~ 4 0) 4- P ~ C 4H H H 0$4-- fr H 4)LA. ) *4
$4
![Page 101: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/101.jpg)
Zt~
U- - - - - - - - - -
- - - - - - - - - - - - a -
~3I
0I
zC
H- a a - - - - a
C
U S -- - - - a a . - .. - -.
- a
H
- 5 a a a a a a a a
- a a a a a a - a - -
-~ 4~ *.~Q)
4)~ ,~(rI~.4 ~G.
![Page 102: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/102.jpg)
INSERT
Data for Model 61211 Solar
Power Conversion System
SN 001
The data log for system operation at the DECC facility was
lost during the move of the system from DECC to Mt. Lagtua.
The following summary data are available:
Total input kWH at DECC 6218
Total output kW1l at DECC 4861
Total running time at DFCC 413.6 II
The system was operated for 43 days, not including down-time
due to flooding of the temporary wiring from the array
to the PMP.
More extensive data will be available from Sandia when
Data Acquisition System output data are reduced.
A21
![Page 103: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/103.jpg)
r4.
0
4) rA
42A
W~ 0 4)1 1 t £
* 4 f4 (
0 Ol1 1 4 '4
4-b)
v4 0 > 4.
0lu LO (d -
a -
A22.
-lob
![Page 104: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/104.jpg)
ATP 6121 100
Dat 7/97
Utility Net Without Solir Input
V/cw~ 200
z-'.-cCr~5 mzE
A
A2'3
![Page 105: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/105.jpg)
40>.
Ct ' d OD
14~~~~~ 3 'n I I I C1
4).4)
0 N 4)'
%40
.4-4
*0
S4-1
4-4
0. 0 N +) - .- m
4) 4, 4-;I
Z E
0 - q,~
0- 4-40)4-) -.. V
t 0 l - -
![Page 106: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/106.jpg)
02
020Z__ Zd 0.
1,-. -1
4-0
0 r___
4,
00
#40 4:*
*144 0 W
04 I0
*- .
%25
![Page 107: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/107.jpg)
ATP 61211 0 oo1
Da te 7/19/79
'&AI F'
V/CIII 200 '
SC AL lF
/ 20
S ii 5 [its
A
- ttlt ll _ I1
,\I
![Page 108: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/108.jpg)
.00
0 0 a% 04
0, ., .- o ..
-l an Nv .v Cvf
i oti
(4.1
• r- .-
ILI I I "
(3 4 I I I I I I.
L.4b
43
0 o v. 4Ta '.c
4AI - I - I IA -I .- I - - I #
600
'Ca 4. ILIi . .
A T4 x-H C .,
a $4 ~~-i 44.'r 4)
_ c 4 T4 c 1
. 4
gfo
Go oo
-A27
7- M, - o. d A*
0 ;00.(,. s- 'I) I
![Page 109: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/109.jpg)
tic~e 0 C~ ~
p020
4-b .4 0
0'0o0
.5 6, 40
4-.
V.4
1
41.- g I 1I I (
> H 4- -4
o Lai - -,4 - jf
A~ 28_
![Page 110: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/110.jpg)
ATP 6t);,t
CIII,
![Page 111: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/111.jpg)
00
+14
4-)
43 4
00
Oq 4) Ql u Gb0 ~ I0 ' 4 3$4 -4 '- 0 -
-4. 0d C' P-4 H) 4 .,
4-) -.I IL)- C' 7-- c $4 4-W j. ,-4 4) 01 T 4)
41p4) E 4J' 4U 4' 4-) C.~
(d r4 -4Qj. 41J 4- U4 q 4, 0 14) C3 11~ :-:)~0 3 M4~. 0 06 Ul :0 :3 s
.144P .Q Z). ZI U) z;
0~ ~ 0. ' ~ ~ 4-'~Ci ' E41) 4 4 -
4) 04) 0 C, (P 4) 0
*r4 rj 0-0S e~014 C .~ H 4
.A 0 H 4) rj L 1:4
44 0 0 J u 1 l
(5 $4 1: ;4 -r :s :p 4) -P p u~ P ) 0 0 4
-4 $454 4 0 $4 $4 $
0 00 $ ~. 4) N3$ 4
![Page 112: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/112.jpg)
ATP 61211 g4 001
Data taken using Data AcquisitionSystem __ _ _
'T'ah, t&e, Comparvisoi- of ,' Sir1." O pitIt
Sol;r 'owor hoferenve String, Nmier 40
Strin, Stping efer. Ratio Sf ri n, Strig lh, ', ,No. * oil tpln t Striing N* OIt I puit Stri tIll
Output ,n? it -t
1.9? 1.82 1.05 4, 1.5, 1.2 '. 7
2 1.90 1.04 1. 82 1.00
3 I1.62 .89 .,( I1. 57 .*(,
1 . 90.... ....... .. 4.8
.1 81
5 1.8,j 1 .00 . 1.8( 1.02
6 1.8' 1.01 ? (.)8 2
7 1.61 .8 ~1.14".7
9 .7 " 1.52 .87
0O 10 I 10 8 . ,1 T
ooI . 8 '1 1 . 00 8
8 1 ''_3 1. Or .91 16
1 14 1.(15 . 1 VT 1 , 62 0.8
4)15 .6 .91 18
1.I 92 -1.05 ,'I1 82 It .Oi'
T4 188 6 921.0 1 1 .2
19 1.91 1.05 14;. .I'.. ___ 1 * 0 •1
117
21 1.89 1 .04 424 t .()I ,
22 1.9 t014 1.8 O
![Page 113: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/113.jpg)
ATI' 1112 1 1N 001
8 8. Conparison lla' Si it ,' 011' 11i,'' (,'mll I %)
o1 rPowo'r lie f'vretw e Stritig N~timi' '4
Stritifr str1li He fein , Un t to St 1Ili- : >t 1" Iil l llev','1' 1 1 ,No. O11t|+tlt Stt'i11e No. O t ll l i ,A ri,1 "1,
Ott) 1.8 .9tI ti .1.2 10
7.7' .8 71 1.27 1 8.
4 9, I . 8 i . 0 1 7 '' •1 . 7 • 8 6(I I'1.I . .. 8
0.2 1.00 0" . 9- .8
9o.. 1 .0 9
3,1 .53 .8 , .79.... I i i i
' 0 1 . 9 , 1, .0 0
1".1'' oI ! v'i • I 1. 0 . s8
',7 'N2 i0 9 6 j.1
4
8 o.24 .90 8 1 1 .1 .88
1 ."0
059 .8 I .9' I I .76 ,
j iW, I . 1802 1.7 I .. 65
61H I .61 I.0 ,1 1 1.79 .98'
.;,1.0 .(10 Si' 1.00 .88
oi "Al S. 4
611 1., .8 ,, 1,,01 h .720
r 1II 1 8 .l. .. "88 .6 iL
(10 Ib .61 1 9 1.71 94
.8.1.8~
A 12
![Page 114: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/114.jpg)
ATP 61211 SN 001
Dyte____2_7_dy
QA
Table 8. Comparison of String Outputs (cont'd)
Solar Power Reference String Number 4o
String String Refer. j RatioNo. Output StringII Output
93 1.76 1.82 .97
94 1.82 1.00
95 1.78 I .98
96 1.79 .98
97 1.78 .98
98 1.93 1.o6
99 1.87 1.03
100 1.91 1.05
101 2.03 1.12
102 2.07 1.14
103 3 1.00
104 1.87 1.03
105 1.69 .93
106 1.90 1.04
107 1.52 .84
10 1.- - .80
109 .62
110 1.39 1 .76
111 1.20 .66
112 1.73 .95
113 1.43 .79
11 1.65 .91
115 .64 90.. 4A33
![Page 115: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/115.jpg)
ATP 61211 SN 001
1).,t,' 8/2/79
Table 8. Comparison of Strini(: Otpit. (colit 'd)
Solarox Ileforence Stritij Ntmbler 136
String String Refer. Ratio Stri It'I Styr tIfer. i., i,,
No. 011tplit Stri itr {No. (h| lti I: , t H atl t p13 t pIt
116 I 1.09 1.00 1.09 I'T) .76 1.0 .76
117 .91 .91 111) .97 .97
118 1 09 1.09 11 I. 0 1 . I0+
119 .83, 8 i 1.52 1.05 1.05
120 1.06 I 1.06 I1'1 1.02 1.02
121 .97 1-. oIe 1.04 1.04
12 10 1.06 Ills I 98 .98122 I .06 I o6 14•89
__-_..._ .....
123 .(6 I .9( I!'(, 1 1.02 1 .02
1211 .85 .85 1117 1.01 1.01
12r .95 .95 048 1.06 .1.06
126 1.06 1.06 1 ',) .95 ,95
127 1 .03 1 .0 .96 .96
128 I* I 1 I1 1 1 1.04 1.04
12 ) 1. 10 1. 10 1 1.01 1.01
130 1.0') 1.09 b .96 .96
131 1.01 1.01 lIt .99 .99
132 .09 1.09 55.81 81
113 1.06 6 156 1.02 1.02
134 1.01 io0 1r,7 .86 .8b
135 1.0.) 1.03 158 1.03 1 I.0-
136 1.00 1.00 .96 .96
1 1.01 1.01 1,w 1.06 ,.06
38 .98 -. 98 161 1.02 J o2__ jIO2 -A
![Page 116: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/116.jpg)
ATP 61211 -O II..,_812179 . .
'ble( 8. Comparison olf Stvit I' (hitImt-, ('olt 'Ii
S i lrvx Reference String Nimli, 136
String String Refer. Ratio
No. Otitput StringOutput
162 1.01 1.00 1.01
163 1.05 1.05
164 1.01 1.01
165 1.05 1.05
166 1.01 1.01
167 .99 .99
168 1.10 1.10
169 .-4 ... 4
A35
- ________
![Page 117: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/117.jpg)
"'N 001-.§Z,,-82/72
Bly
Table 8. Outputs to Data Acquisitiol, yste,
Analog
Meas'd Input to % Calib.Value I).A.S.
Input voltage
Input current Meters compared toactual Data Acquisi- < I%
Input power tion System printout C
Output power <1%
BCD
Veri fe(
Input -WlI itoterOutput KWH meter
Status (liital)
Verified
Off
Off---l tfi' ic l t Solar Powor
Of f--Shut Down
Off--Error |R'cyc le
A36
![Page 118: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/118.jpg)
APPENDIX B
EMI TESTS ON COMPARABLE
POWER CONVERSION EQUIPMENT
BI
![Page 119: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/119.jpg)
HOFKINS ENGINEERING COMPANY QTR-556.5-425.
28 JAN 1975
QUALIFICATION TEST REPORT
ELECTROMAGNETIC INTERFERENCE TESTS
ON
UNINTERRUPTABLE POWER SUPPLY SYSTEM
t
Prepared For:
STATIC POWER INC.300 Campus BoulevardNewport Beach, California
by
HOPKINS ENGINEERING COMPANY12900 FoothIll Boulevard
Seri Fernando, Calif. 91342
Prepared by:.-rltd yo n A t
ar T T
m roEMI Specialist Vice Pr.e ntrope n-
1Hopkins Engineering CompanyA1proved2
ice Preside QOuality Control
![Page 120: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/120.jpg)
HOPKINS ENGINEERING COMPANY QTR-55635-425-1
TABLE OF CONTENTS
SECTION TITLE PAGE
-- REPORT SUMMARY
1.0 SCOPE 1
2.0 APPLICABLE DOCUMENTS I
3.0 GENERAL 1
3.1 TEST SAMPLE IDENTIFICATION I
3.2 SUMMARY OF TEST METHODS PERFORMED 1
3.3 TEST DATES 2
4.0 TEST PROCEDURES 2
4.1 TEST SITE 2
4.2 OPERATIONAL PROCEDURES 2
4.3 TEST INSTRUMENTATION 2
5.0 TEST RESULTS 2
5.1 CE02 CONDUCTED EMISSIONS 14KHz to 50MHz 2
5.2 RE02 RADIATED EMISSIONS 14KHz to 1000 MHz 2
5.3 REO4 RADIATED EMISSIONS H Fields 20Hz to 50KHz 2
6.0 CONCLUSIONS 3
113
![Page 121: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/121.jpg)
HOPKINS ENGINEERING COMPANY QTR-55635-425-1
REPORT SUMMARY
PURPOSE: Electromagnetic interference tests were performed on theUninterruptaole Power Supply (UPS) to verify that the UPSsystem provides adequate compliance with the applicableelectromagnetic compatibility control requirements.
TEST ITEMS: Uninterruptable Power Supply62.5 KVA
MANUFACTURED BYz ,Static Poter Inc.
Newport Beach, California
SPECIFICATION: MIL-STD-461A,/462 Notice 3
TEST PIRFORMED BY: HOPKINS ENGINEERING COMPANYSan Fernando, California 91342
TEST PERFORMED AT: STATIC POWERNewport Beach, California
AUTHORIZED BY: STI Purchase Order #4864 dated 12-11-74
TEST CIMPLETION: 12-18-74
SECURITY CLASSIFICATIONt Unclassified
SUMMARY OF RESULTS: The Uninterruptable Power Supply was foundto be in compliance with all applicableelectromagnetic control requirements whentested in accordance with MIL-SLD-461ANotice 3, Para. C E 0 2, R E 0 2 & R E 0 4.
B14
![Page 122: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/122.jpg)
HOPKINS ENGINEERING COMPANY QTR-55635-425-1
QUALIFICATION TEST REPORT
1.0 SCOPE
T is report presents the results of the electromagnetic interferencetest performed on the UPS 62.5KW manufactured by SPI, Newport Beach,California, and compares these results with the applicable require-ments of the specification.
2.0 APPLICABLE DOCUMENTS
Military Standards
mIL-STD-461A Electromagnetic Interference Characteristics,tOctice 3 requirements for Equipment.
MIL-STD-462 Electromagnetic Interference Characteristics,Notice 3 Measurement of.
APPROVED TEST PROCEDURE
Prfor to conducting the Radiated Emissions Test the perifery of thesfstem was probed to determine the position of maximum radiationaccording to approved test procedure of MIL/STD-462. The antennaeswere then positioned as specified and all radiated measurement takenat this locition. Conducted measurements were made using a currentprobe on input and output power 3 phases and neutral.
3.0 GENERAL
3.1 TEST SAMPLE IDENTIFICATION
The test sample system consisted of one console and applicable load.
3.2 SUMMARY OF TEST METHODS PERFORMED
The test sample system was subjected to the following applicabletest methods of MIL/STD-461Ai2 62 Notice 3.
METHOD TYPE or TEST Freq. Range
CE02 Conducted Emissions, Power Lines 1/4KHz-5OMHz(Input & output)
RE02 Radiated Emissions, E Field 14KHz-IOOOMHz
REO1. Radiated Emissions, H Field 20Hz - 50KHz
B5
![Page 123: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/123.jpg)
HOPKINS ENGINEERING COMPANY QTR-55635-425-1
3.3 TEST DATES
These tests wore started on 12/18/74 and completed on 12/18/74.
4.o TEST PROCEDURES
4.1 TEST SITE
The test prograr was conducted at S.T.I. facility at 3800 CampusBoulevard, Newport Beach, California. Since the test sample couldnot feasibly be housed in a shielded enclosure, radiated tests wererun after 11:00 PM because of day time Hi Ambient fields. Conductedtests were run after factory shut down.
4.2 OPERATIONAL PROCEDURES
All test sequences were performed with the UPS operating load,50 KVA.
4.3 TEST INSTRUMENTATION
The test instruments used during this test program are listed inAppendix A along with their applicable model numbers, serialnumbers and calibration dates.
5.0 TEST RESULTS
5.1 CEO2 Conducted Emissions, Phase A.B.C. & Neutral input andoutput 14KHz-r0MHz.
5.1.1 Broadband emissions on both Input & output all phase werewithin specification limits.(See Graphs Fig. #1 thro 8)There were no measureable Narrowband Emissions.
5.2 RE02 RADIATED EMISSIONS; E-FIELD (14KHz-10OOtz)
Broadband radiatad emission were within specification limitsall frequencies. (See Graphs Fig. 9 )There were no measureable Narrowband Emissions.
5.3 REO4 RADIATED EMISSIONS; H-FIELD (20Hz - 50KHz)
There was no measureable H-Field emission.
B6
![Page 124: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/124.jpg)
HOPKINS ENGINEERING COMPANY QTR-55635-425-1
6.0 CONCLUSIONS
When tested in accordance with mrL-STO-462 the UninterruptIblePower Supply conplied with all applicable Class I C requiremuntsof MIL-STD-461A Notice 3 Test Method CE02, RE02 and REO4.
B7
![Page 125: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/125.jpg)
HOPKINS ENGINEERING COMPANY QTR-55635-425-1I
APPENDIX A
TEST EQUIPMENT
The following primary meters were used during this test program:
RECEIVERS/METERS
Noise and Field Intensity Meter, Singer/Empire Model NF105 S/N 2083Calibration date 2-5-75. Stoddart N M 40 S/N 1Calibration date 5-17-75.
CURRENT PROBE
Stoddart Radio No. - 91550-1 S/n BF231
ANTE N NAS
Singerlmpire VX - 105
S inger/Empi re VA - 105
Honeywell Bi Conical Model 7825
Electro Magnetics Conical Log Spiral Model CLP-lA
Loop Antenna Model 90114-3
B8
![Page 126: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/126.jpg)
~i -IT I'
4/1
31
4' 4
C33
![Page 127: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/127.jpg)
9 IF
If I
-li L
1,4
st
B 10'
![Page 128: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/128.jpg)
W-7 7C.
-T A
-2 '' -. { i - 13
,1ITHRi
liv -.4 I 1
1 044 -4 4
4I t1 -
7 41- 1
t Fl
:t4/V q BI II
~ 1w
![Page 129: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/129.jpg)
I ~ ~ ~ ~ vT --I-LI~' ro -4 7
-t-
it
- fb jliActt
w '4 b-4
H 11
I A1 ~
m,4 ~1112 Ch
![Page 130: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/130.jpg)
' fl~a l
L: jiT--
P :
-
O w. --
p
r
L j C-)L)_
a4
A
- 7
I. #ll
j4itCI C3
![Page 131: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/131.jpg)
iIIH I: F N TSt....Z - Mt l
-- ,
I -
t..
+V
vi - I I A
L. .47
A-+-
c. 4I 2T r
'A ;;-) I 4
-T. -T i 4--
ilti
L Ll.44J 1j .. Izd1i' U AF/
![Page 132: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/132.jpg)
'J]
-~ Tt
06,,
j --
l
*I '0I*r
![Page 133: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/133.jpg)
I T I -T I JV I 111-t*, -
---- ----
TTr
41. a '.
7[ 0<
Li
51 D T 1- 1:H~r~
IV 3.t a..
itt - 4ki4 4 o-t.)1%5 T-
F~I r Ij4
ui il
i iIl
I, -1J1 ct
![Page 134: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/134.jpg)
T I VTrpv1TTT~~~
.1J 1
I ~~ t'l It
I. ~ 4 Al +-- 4
*r ~ ~ ~~~ MR ;:;: ~~-
iIE- L- A~
C~~~J -Zi-tl4}-L1 ..
I, 4i- 1-
4-
L4 L..A.
-
721 Ai /m a a aI
![Page 135: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/135.jpg)
-TtKw7 L~ __
K4 1- -__
IT J
L7.
-pT
1A ~ f -1t--T
spO3'Oil13~O~A~ O ~~~~ .
0 0 0 - N
4. 4.A l
![Page 136: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/136.jpg)
HOPKINS ENGINEERING COMPANY
ELECTROMAGNETIC INTERFERENCE DATA SHEET
TIEST CQUIPMKN ETE 8DT-2
STYPE i~sROAO3Amp ortONOUCTtO IZ1SION SlIgAL 0ORCEcIVEoDBY C KNITTEO MY
OF ONANRR@WIAND ONADIAT90 SCEucPTIBILITY jL!dfURENT PROGE 0ig, Caoo CO~l 1 IPOLZTEST 0 09-ONICIAL OSPINAL OwoO,. OLOOP
tF___S____________ STEADY STATE OTRANSIENT 0 _ _______________
L~~j1A~ ,'0' AIE_ 1 L& J ± ./00~~~~~~ eo. 9 2,iI± d
~,o ;~ L q/jj __
d.U I9Q go 5"d /1_
CIO 972 9_ 77 y di 7__ _6
__35__ V~ go ko q3j
77 0
.LLI2~~ c( ~ S ~ ~ j (~ 'l__k 10 7 -
rMe-,CT OP
B19
![Page 137: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/137.jpg)
HOPKINS ENGINEERING COMPANY
ELECTROMAG#4UTIC INTERFERENCE DATA MHEET
PROJECT ___ ESITM .'V ii;J4
TEST SP9C. 14LI I ~ PAR AGRAPH _____ _ -TEST POINT_________
~TET Qup::?~AF o~.... T E T ESTD:Y DATE
or I2ARROWSANO (: AITO CSXCPII Y cu FRIENT P OCISN DNOO ClOtPOLE
ES gL3 0 JOSI-C')MICAL OSPIRAL CMORN OLOOP
_______________ OSI EADY STATE 0 TRANSIENT 0[I _____________
M14
q4 ______J7~~' _
____ 3k,3 5 __ '
1 2-_ 6 -1 ,__ _
241 2f
9I-- IT or~___ )-J224~iJ)O____ B2
![Page 138: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/138.jpg)
HOPKINS ENGINEERING COMPANY
ELECTROMAGNETIC INTERFERENCE DATA SHEET
PROJECT ~V~ ~~ TEST ITEM LO (_LOA) -S-~~a
TEST SPEC......._ ___ PARAGRAPH _ ______TEST POINT ______
TEST EQUIPMUNT ___________ __________ _ DAT
Of C~ARR~@::o014ADIATELD CSLSCEPTISILITY QfURRNENT 101O111 0CLISN CR00 CIPOLE9
TaST 0 c 0t1CONICAL OSPIRqAL ONoRN CLOOP
I MooNf EI-lADY STATS 0 TRAWSIENT 0-
4 1-1
L~~~Z r/ _ , __ _
/7 -2-'. 'o j 6 7~ .'
____ L, -6 -
12 Al
5-- _ 6 7) ~ 3a- 1_
_ i __ 1 -K 1'163f. Orc.
A!L ~ A Z toe-Al l.£~ 2. L __ _
_~~~~"a or q 52 6 .i
_ _ ~ L 4~ B21
'1Lo6_
![Page 139: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/139.jpg)
HOPKINS ENGINEERING COMPANY
ELECTROMAGNETIC INTERFERENCE DATA SHEET
Rpojgtr~ S2AT . CO% I_ TEST ITUM ki U44S ~Li)
_____$PICe PAR kGNAPN _ TEST POINT_________
yggT EQUIPMIENT -I~ I.)TZ BY DATE
tyE TYP 60OAOUNO m(cooouvygO 0 EMISSION4 SI04AL CEcIVED my 0 XMITvrg mY
Of ONARNOVSAND ONADIAT&O 0GUICIEPTIMILITY f3feiJRRENT PROSI OLISN 0DOR0 QOIPOLE
VsT 0 3 U 00hCONICAL OSPINAL 014oRN O3LOOe
TEST UO009 ______ LSIAOY $TATE OTNlAmsIEI ____
,A01 4 7
~~ /dj~~7 35 C _ _ __ _
4j_ _o
1122
![Page 140: DESIGN, CONSTRUCTION AND TESTING CONTROL CORP IRVINE … · power plant. The system is entirely automatic, coming on-line when there is sufficient solar power available in the morning,](https://reader033.fdocuments.us/reader033/viewer/2022042200/5e9f59b09bfedc603e3dbb22/html5/thumbnails/140.jpg)
HOPKINS ENGINEERING COMPANY
ELECTROMAGNETIC INTERFERENCE DATA SHEET
TCST SPEC. ti/A/# P A~ _ PAAGRA P HT d ee
ILtst dkupm" T' $TED@ ZS',-( A ,
TVp9 i6,'RnOAornA~o 0- D~UCTED QI9missIOw SIGNAL 0 9CEIV90 MY 0 XMIT(O gY
OF 100ARROSAND IO1ADIATED O)SUSCEPTIuILyTY C CURRENT PROS LJLSk CriOo Co1uOo.9TEST 10 0 oribI-CONICAL OSPIRAL. ONORN DLOOP
TEST 6$eDR _ C STEADY STATE 0 TRANSIEN T 0 _______3_______
191
~~~. ~ 2 ____ ___