Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of...

39
Design, Construction and Operation of Gaspipelines Essen, 10. April 2014

Transcript of Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of...

Page 1: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

Design, Construction and Operation of Gaspipelines

Essen, 10. April 2014

Page 2: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

2

Content 1. Introduction 2. Basics / Regulations 3. Design 4. Construction 5. Operation / Safety 6. Film

Design, Construction and Operation of Gas Pipelines

Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

Page 3: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

3

Gas transmission pipelines (onshore) in Germany

Pressure: > 16 bar (currently up to 100 bar) Diameters: DN 100 (4“) to DN 1400 (56“) Temperature: -10°C to +60°C Length: few kilometers up to several hundred kilometers

1) Introduction

Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

Page 4: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

4

Procedure / Timeschedule of pipeline projects

ROV

Basic Design

Detailed Engineering Construction

Remaining work

Not

ifica

tion

of

regi

onal

pla

nnin

g

Acqu

isiti

on o

f lan

d W

ayle

ave

PFV

Privatrechtliche Verfahren

6 Mon. 12 Mon. 3–6 Mon.

UVU I und II Natura 2000 (FFH) LBP

3 Mon. 3 Mon.

Feasi- bility study

Project- Identi- fication

3–6 Mon.

9 Mon. 12 Mon.

final

cer

tific

ate

§6.2

§5

Anze

ige

8 Weeks

Plan

app

rova

l

Com

mis

sion

ing

IBN

pr

el. c

ertif

icat

e §6

.1

before constr.

End

of p

roje

ct

Proj

ect s

tart

Project duration: Project start - Commissioning: about 3,5 Years Project start - End: about 4,5 Years (incl. Restoration)

Right of way / Acquisition of rights

1) Introduction

Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

Page 5: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

5

Legal Basis

Law EnWG

(Energy Law)

Intra Coporate Instructions OGE Instructions, Guide Lines,

Technical Rules DVGW codes of practice, DIN-EN, ISO Standards

Regulation GasHDrLtg-VO

(High Pressure Gaspipeline Regulation)

2) Basics / Regulations

Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

Page 6: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

6

§ 49, Requirements for energy facilities (1) Technical security of energy facilities has to be ensured,

compliance with generally accepted standards of technology

(2) Compliance with generally accepted standards of technology shall be presumed when at the plants for the generation, transmission and distribution of: 1. Electricity: the technical rules of the Association of Electrical Engineers, 2. Gas: the technical rules of the German Association for Gas and Water

(DVGW) are observed.

Energy Industry Act – EnWG (Energy Law)

2) Basics / Regulations

Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

Page 7: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

7

...

§ 3 General requirements

§ 5 Notification and objection of pipeline projects

§ 5 (1): Notification to authority at least 8 weeks before start of construction

§ 6 Commissioning, prohibition

§ 6 (1): Preliminary certificate (after construction, before commissioning)

§ 6 (2): Final certificate (After completion of all tests)

...

§ 8 Monitoring

...

High pressure gas pipeline regulation - GasHDrLtg-VO

2) Basics / Regulations

Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

Page 8: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

8

8

Construction of gas pipelines made of steel pipes for operation at pressures in excess of 16 bar

Planning Design Construction Construction monitoring Commissioning

DVGW Code of Practice G 463

2) Basics / Regulations

Page 9: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

9

Material for gas pipelines: up to 10 bar operating pressure: often plastics (DVGW G 472) and steel > 10 bar operating pressure: steel (DVGW G 462 and G 463)

Coating 3 layer PE,PP, Epoxy internal lining Epoxy (thickness 0.4-0.5 mm)

Different steel gas tubes: Seamless pipes Longitudinally welded pipes or Spiral welded pipes Selection of tubes according to various criteria: Internal pressure Material Wall thickness Weldability Corrosion protection (active-CP / passive-pipe coating) Price

Gas Pipelines

5) Design 3) Design

Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

Page 10: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

10

Horizontal / vertical changes of direction by installing curved parts

Long laying radius: Deflection of the welded pipe string

with permitted elastic deformation

Smaller laying radius : Field bend; bends are made of coated steel pipes

at construction site with a bending machine (1 - 1,5°per step, e.g. bend DN 500 -> R about 25 m)

Factory bend, cut bend, production at the factory, heating through induction annealing and subsequent bending. (e.g. factory bend R = 10 x D, R = 5 x D)

Pipe fittings – Curved parts

3) Design

Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

Page 11: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

11

Tee, branches off the main line

Reducer, installation in case of necessary changes in diameter End Caps Flanges with screws / nuts and seals Insulated joints / insulating flanges Vent Slug catcher Pig trap etc.

Pipe fittings – Other

Tee Barred tee

Split tee

Pig trap

Slug catcher

Vent

3) Design

Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

Page 12: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

12

Distinction by type (ball valve, slide valve, gate valve)

Distinction by function (tightly – bit worn)

Large gas pipelines ⇨ mostly ball valves (advantage: low construction height & lower weight)

Valves

Ball valve

3) Design

Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

Page 13: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

13

Valve station – Structure

Valve station - Operation

Valve station - Construction

Venting system in order to be able to work without gas on single line sections

DVGW Code of Practice G 463: Distance service valve every 10 to 18 km DN 1000

3) Design

Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

Page 14: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

14

Corrosion control of underground piping

Buried steel pipes are protected by a combination of electrochemical protection (cathodic protection) and isolating plastic coating (passive corrosion protection).

Cathodic protection (CP)

Coke bed Reference electrode

Pipeline with isolating plastic coating

Anode (+)

Protective current device

Protective current connection (-)

Protective current

Coating defect

Signpost

Sample plate

Input supply

Earth electrode

+ -

passive corrosion protection

3) Design

Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

Page 15: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

15

In pipeline projects, many traffic routes have to be crossed (streets, railways, rivers, canals, nature reserves and landscape protection areas)

Possible crossing techniques Open building method

Closed building / trenchless pipe laying: - Impact ramming and thrust boring - Horizontal directional drilling (HDD) - Microtunneling - New methods, for example Direct Pipe

Crossings with traffic routes and barriers

3) Design

Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

Page 16: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

16

Total / partial blocking temporarily necessary Railways: installation of so-called temporary bridges for each track,

afterwards the trench will be built under it. Crossing of larger rivers / canals by pulling in a culvert Small streams / ditches can be crossed open

Crossings with traffic routes and barriers Open building method/ river crossing

3) Design

Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

Page 17: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

17

Product pipe jacking Trenchless laying is done in nominal size of the planned gas pipeline Advantages of a product pipe crossing:

- Warranty of safe CP - Simple technical structure - More cost-effective implementation

Casing pipe jacking Pipe jacking with a casing pipe Pulling of the product pipe with skids (insulating spacer)

Crossings with traffic routes and barriers Trenchless pipe laying

Note: Pipe jacking with casing should be avoided if possible (problems with CP)

3) Design

Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

Page 18: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

18

Crossings with traffic routes and barriers Horizontal directional drilling (HDD)

Basic structure „Rig-Site“

Basic structure „Pipe-Site“

1. 2.

3.

Crossings possible up to ca 2600 m and DN 1400

3) Design

Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

Page 19: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

19

Basis for construction execution Plan approval and “free wayleave“ Construction plans and calculation sheets Placed orders

Pipe laying Pipeline Method by long pipelines projects:

- As long as possible pipeline next to trench - Use of pipe-laying machines (side booms) - Installation services up to about 1,000 m / day

Single pipe installation: short pipes, built-up areas and working strip narrowing - Lowering of individual pipes in trenches with lifting equipment - Pipes are welded together in head access holes

Civil work and pipe construction

4) Construction

Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

Page 20: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

20

Sequence of operations by construction

6 Trenching 7 Lowering in 8 Construction survey 9 Backfilling 10 Pressure test 11 Route recovery

1 Preparation of the route 2 Pipe hauling 3 Pipe bending 4 Stringing and welding 5 Testing of welds and coatings

Civil work and pipe laying

10

11

4) Construction

Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

Page 21: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

21

Quality Assurance Example: Quality monitoring from the raw material to pipeline operation

Steel production Material testing / tensile test (K*s)

Weld testing and hydro- testing at workshop (each pipe)

Material certificate for each component

Tests: welder and welds

Tests: installation company and pipe installation

Stress testing of completed pipelines

Preliminary and final test certificate by TÜV inspection authority

Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

5) Operation / Safety

Page 22: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

22

Ensuring production requirements (pre-production meeting)

Control of the raw material

Production surveillance (Expediting)

Acceptance by independent experts

Complete documentation (APZ-acceptance test certificate)

Material

Planning and construction Review of planning documents (§ 5 reports)

Certified construction companies (DVGW GW 301)

Extensive testing (weld inspection, pressure test)

Reduction of laying / welding stresses before use (stress-pressure test)

Supervision of work by client

Acceptance by independent experts (§ 6 certificate)

Safety of the pipeline

5) Operation / Safety

Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

Page 23: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

23

Quality monitoring

5) Operation / Safety

Walking survey

Mobile survey

Aerial survey

Intelligent pigging Repairs

Investigation of reports

Cathodic protection monitoring

Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

Page 24: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

24

Corrosion protection

Protection against external influences

Pipeline Integrity Management System (PIMS)

Operation

Monitoring Control of the coating (intensive measuring)

CP control

Intelligent pigging

Safety of the pipeline

Protection from approaching construction measures

Assign the route (protective strip)

Leak detection by Helicopter (Charm)

Patrolling, Inspection

5) Operation / Safety

Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

Page 25: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

Natural Gas Pipeline Project Loop Sannerz-Rimpar

Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

25 6) Film

Page 26: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

26

Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

Thank you for your attention!

Your Questions......

Page 27: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

27

27

Hyperlinks Slide 32

Page 28: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

28

Top soil storage Witdh of

pipe trench Working track

Width of working strip

Excavation storage B- and C-Horizont

ca. 8 m ca. 14 m ca. 4 m ca. 8 m

ca. 34 m

Working strip (Example DN 1000)

4) Construction

Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014 back

Page 29: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

29

Preparation of the route (1)

Removal of top soil

Preparation of working strip

back

7) Construction

Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

4) Construction

Page 30: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

30

Pipe storage space

Pipe hauling (2)

Pipe hauling to the route

back Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

4) Construction

Page 31: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

31

Pipe bending (3)

Bending machine

back

7) Construction

Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

4) Construction

Page 32: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

32

Stringing and welding (4)

Stringing Welding

back Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

4) Construction

Page 33: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

33

Testing of welds and coatings (5)

ISO Test

Coating defect

back

7) Construction

Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

4) Construction

Page 34: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

34

Trenching (6)

back

7) Construction

Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

4) Construction

Page 35: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

35

Lowering in (7)

back Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

4) Construction

Page 36: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

36

Backfilling (9)

back Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

4) Construction

Page 37: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

37

Pressure test (10)

Proof- & tightness test (hydrostatic / high-level test:“Stress-test”)

back

7) Construction

Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

4) Construction

Page 38: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

38

Route recovery (11)

Application of topsoil

Recultivated route

Recultivated route after reseeding

7) Construction

Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014

4) Construction

Page 39: Design, Construction and Operation of Gaspipelines and... · Design, Construction and Operation of Gas Pipelines ... Horizontal / vertical changes of direction ... Slug catcher Pig

39

During construction………… and one year later !!

Recultivation of the route and landscape

back Design, Construction an Operation of Gas Pipelines| Essen | 10.04.2014