DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE AVOIDANCE From the Owner’s Perspective 1 Presented by: Brian Goodreau, PSP, ENV-SP Andrew Morse, AC, PSP October 27, 2015 Ohio Transportation Engineering Conference

Transcript of DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE ... · DESIGN-BUILD – EFFECTIVE PROJECT...

Page 1: DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE ... · DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE AVOIDANCE From the Owner’s Perspective 1 Presented by: Brian

DESIGN-BUILD – EFFECTIVE PROJECTCONTROLS AND DISPUTE AVOIDANCEFrom the Owner’s Perspective

1

Presented by:Brian Goodreau, PSP, ENV-SPAndrew Morse, AC, PSP

October 27, 2015Ohio Transportation Engineering Conference

Page 2: DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE ... · DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE AVOIDANCE From the Owner’s Perspective 1 Presented by: Brian

© Arcadis 2015

Health & Safety Moment

2

Page 3: DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE ... · DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE AVOIDANCE From the Owner’s Perspective 1 Presented by: Brian

About Arcadis

3

Page 4: DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE ... · DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE AVOIDANCE From the Owner’s Perspective 1 Presented by: Brian

© Arcadis 2015

About Arcadis#13 Top 500 Design FirmsTop 20 by Sector• #4 General Building• #7 Water• #2 Hazardous Waste

Engineering & Manufacturing• #2 Pure Engineering• Top 50% Overall

U.S. Stats

• 8,000 employees • 200+ offices in U.S.

4

Page 5: DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE ... · DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE AVOIDANCE From the Owner’s Perspective 1 Presented by: Brian

© Arcadis 2015

On-Call Claims Transportation Clients

5

Page 6: DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE ... · DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE AVOIDANCE From the Owner’s Perspective 1 Presented by: Brian

About the Speakers

6

Page 7: DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE ... · DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE AVOIDANCE From the Owner’s Perspective 1 Presented by: Brian

© Arcadis 2015

6 Years at Arcadis• NYC Operations Leader – Contract Solutions• Senior Claims Analyst

8 Years as a Subcontractor• Concrete, Masonry, Sitework• Estimating, Scheduling, Project Management

CMAA New England Chapter• Founding Co-Chair Rising CM (Young Members)

Education / Accreditation • Degree in Construction Management• Planning & Scheduling Professional (AACEI)• Institute for Sustainable Infrastructure (ENV-SP)

Brian Goodreau, PSP, ENV-SP

7

Page 8: DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE ... · DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE AVOIDANCE From the Owner’s Perspective 1 Presented by: Brian

© Arcadis 2015

4 years at Arcadis

13 years of industry experience• Successfully managed complex construction

schedules on projects ranging from $2 million to well over $1 billion

Planning and Scheduling Professional (PSP)• Association for the Advancement of Cost

Engineering International (AACEI)

Associate Constructor (AC)• American Institute For Constructors (AIC)

Andrew Morse, AC, PSP

8

Page 9: DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE ... · DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE AVOIDANCE From the Owner’s Perspective 1 Presented by: Brian

© Arcadis 2015

(“GlobalConstructionDisputes2015–TheHighertheStakes,TheBiggerthe

Risk”,Arcadis)

Causes of Disputes

Number 1 Cause? Failure to Properly Administer Contract9

Page 10: DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE ... · DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE AVOIDANCE From the Owner’s Perspective 1 Presented by: Brian

© Arcadis 2015

Speaker CautionThe opinions expressed herein are the speakers.

More important, the opinions expressed in this seminar are general in nature and do not relate to any individual project or case. For this reason, these opinions may or may not be relevant or apply to any individual case.

Finally, the opinions merely reflect the experience of the speakers who both have extensive experience in their respective fields.

10

Page 11: DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE ... · DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE AVOIDANCE From the Owner’s Perspective 1 Presented by: Brian

© Arcadis 2015

Learning Objectives1. Understand why the use of effective project

controls can help you avoid disputes on your projects.

2. Identify tricks, traps and ploys of the design build delivery system and ways to combat them.

3. List key features, both positive and negative, for the design build delivery method.

4. Apply techniques to avoid, mitigate, and resolve disputes on your design build projects.

11

Page 12: DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE ... · DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE AVOIDANCE From the Owner’s Perspective 1 Presented by: Brian

The Problem Project

12

Page 13: DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE ... · DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE AVOIDANCE From the Owner’s Perspective 1 Presented by: Brian

© Arcadis 2015 13

Page 14: DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE ... · DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE AVOIDANCE From the Owner’s Perspective 1 Presented by: Brian

© Arcadis 2015 14

Page 15: DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE ... · DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE AVOIDANCE From the Owner’s Perspective 1 Presented by: Brian

© Arcadis 2015 15

Page 16: DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE ... · DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE AVOIDANCE From the Owner’s Perspective 1 Presented by: Brian

© Arcadis 2015 16

Page 17: DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE ... · DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE AVOIDANCE From the Owner’s Perspective 1 Presented by: Brian

© Arcadis 2015

Are They Predictable?YES!! (sort of):

• Contracts not matched to your needs

• Incomplete documents

• Unrealistic objectives and expectations

• Insufficient money

• Insufficient time

• Unrealistic bids

• Significant unknowns or changes

17

Page 18: DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE ... · DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE AVOIDANCE From the Owner’s Perspective 1 Presented by: Brian

© Arcadis 2015

Are They Preventable?YES!! (sort of):

• Contracts matched to your needs

• Complete documents

• Realistic objectives and expectations

• Sufficient money

• Sufficient time

• Realistic bids

• Few unknowns or changes

18

Page 19: DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE ... · DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE AVOIDANCE From the Owner’s Perspective 1 Presented by: Brian

© Arcadis 2015

Problem Projects Are You at Risk?Probably:

• Acceleration

• Changes

• Defective/deficient contract documents

• Delay/disruption

• Differing site conditions

• Maladministration

• Quantity Variations

• Suspensions

• Terminations

19

Page 20: DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE ... · DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE AVOIDANCE From the Owner’s Perspective 1 Presented by: Brian

What is Design Build?

20

Page 21: DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE ... · DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE AVOIDANCE From the Owner’s Perspective 1 Presented by: Brian

© Arcadis 2015

Design Build• No longer a “new” concept, increased popularity

• Seen as a way to address limitations other methods

• Provides “one stop shopping” for owners

• Transfers risk to those best able to control it

• Many common disputes become internal within D/B team

• Widely misunderstood project delivery method

Nearly all types of claims still exist in Design Build

“Selecting the D/B delivery method alone will not prevent disputes”

21

Page 22: DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE ... · DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE AVOIDANCE From the Owner’s Perspective 1 Presented by: Brian

© Arcadis 2015

Design Build

• Faster project delivery

• Single point of accountability

• Cost efficiencies

• Transfer risk to the appropriate party

• Qualifications based selection

Advantages• Less design control

• Owner must make quick decisions

• Limited checks and balances

• Complicates agency approval process

Disadvantages

22

Page 23: DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE ... · DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE AVOIDANCE From the Owner’s Perspective 1 Presented by: Brian

© Arcadis 2015

Tricks, Traps and Ploys• Less competition among contractors

• Opportunity for favoritism

• Hidden exclusions in bid

• Quality assurance and quality control

• Due diligence for design

• Change orders must be reviewed carefully

23

Page 24: DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE ... · DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE AVOIDANCE From the Owner’s Perspective 1 Presented by: Brian

Avoid, Mitigate, and Resolve Disputes

24

Page 25: DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE ... · DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE AVOIDANCE From the Owner’s Perspective 1 Presented by: Brian

© Arcadis 2015 25

Resolve

Mitigate

AvoidN

otic

e to

Pro

ceed

Pro

ject

Com

plet

ion

Technology

Knowledge

Innovation

Page 26: DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE ... · DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE AVOIDANCE From the Owner’s Perspective 1 Presented by: Brian

© Arcadis 2015 26

MitigateN

TP PC

Concept Design Construct Closeout

Avoid

Resolve

Page 27: DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE ... · DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE AVOIDANCE From the Owner’s Perspective 1 Presented by: Brian

© Arcadis 2015 27

AvoidN

TP PC

Concept Design Construct Closeout

Document management Schedule development Cost controls Risk management Value engineering

Document management Schedule development Cost controls Risk management Value engineering

Page 28: DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE ... · DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE AVOIDANCE From the Owner’s Perspective 1 Presented by: Brian

© Arcadis 2015 28

Update schedule Monitor cost Good decisions 

Update schedule Monitor cost Good decisions 

NTP

Mitigate

PC

Concept Design Construct Closeout

Page 29: DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE ... · DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE AVOIDANCE From the Owner’s Perspective 1 Presented by: Brian

© Arcadis 2015 29

Document review Schedule / financial 

analysis Litigation preparation

Document review Schedule / financial 

analysis Litigation preparation

NTP PC

Resolve

Concept Design Construct Closeout

Page 30: DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE ... · DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE AVOIDANCE From the Owner’s Perspective 1 Presented by: Brian

Summary & Conclusions

30

Page 31: DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE ... · DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE AVOIDANCE From the Owner’s Perspective 1 Presented by: Brian

© Arcadis 2015

Summary & Conclusions• Problem projects can put owners at risk, despite the

method chosen to deliver the project

• Design build has many advantages including faster project delivery and a single point of contact for the Owner

• There are many disadvantages too including less control of the design

• Effective project controls can minimize the risk of disputes on design build projects

31

Page 32: DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE ... · DESIGN-BUILD – EFFECTIVE PROJECT CONTROLS AND DISPUTE AVOIDANCE From the Owner’s Perspective 1 Presented by: Brian

© Arcadis 2015

Questions/DiscussionBrian J. Goodreau, PSP, ENV-SPOperations LeaderArcadis of New York, Inc.212.682.9271 [email protected]

Andrew Morse, AC, PSPClaims Analyst / SchedulerArcadis [email protected]