Design Activity Update

• Past Month and Ongoing:– April 14: Presentation to Commissioner’s Court and

Court approval

– May 6: Approval by HDRC

– May 9: Robert Hammond Community Lecture, SAMA

– Since April 15:– Study of potential, future construction phasing options

– Organizing for and launching the 70% design

– Continued architectural design progress

Page 3: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval

2012: Bexar County authorized Preliminary Engineering Report (PER)

2012: Bexar County, City of San Antonio, and San Antonio River Authority executed Letter Agreement for interagency coordination on San Pedro Creek Improvements Project

May 2013: Bexar County presented results of PER study and authorizes $125 million toward the project

December 2013: Bexar County approved design budget and design team

February 2014: Commissioners Court approved Cooperative Agreement with San Antonio River Authority authorizing initiation of final design phase, launching the 40% design

Background/History

3

Page 4: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval

Components of 40% Design

Further investigation of existing conditions Survey, utility coordination, geotechnical

Cultural resources (intensive pedestrian surveys, standing structures, historic context)

Environmental Site Assessments (ESA’s), Phase I and Phase II

Permitting constraints, water rights and supply study

Floodplain (hydraulics and hydrology)

4

Page 5: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval

Components of 40% Design, Cont

Further development of design elements Maximizing flood capacity

Architectural design development

Incorporating public comments

Coordinating with adjacent property owners

Visualization of design elements

Refining project cost and construction approaches

5

Page 6: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval

Summary of Key Project Elements

Approximately 2 miles of channel with a project area covering 22 acres

Almost 4 miles of paseo (trail)

About 11 ½ acres of landscaped area

30 acres of the City removed from the corrected floodplain

8 City street bridges replaced

6 new pedestrian bridges

6 existing City bridges with rehabilitation

1 new railroad bridge

About 60,000 linear feet of new walls

3 new channel gates

1 new amphitheater

6

Page 7: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval

Engineering Update, 40%

HDR Engineering, Inc

Pape Dawson Engineers, Inc

15

Page 8: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval

8

Flood Control Summary

30 acres along the project is within the corrected floodplain

With the 40% design, the project will contain the floodplain

within the channel and remove all this property from the

floodplain

Design includes modifications to channel and bridges

Channel design will have additional capacity to significantly

reduce historic flooding concerns in the Elmira

neighborhood

Coordination underway with City of San Antonio to determine COSA

infrastructure that will be a necessary part of future solutions

Page 9: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval

9

Floodplain Will Be Contained

US Project Limit to Houston St. Cesar Chavez Blvd. Camp St.Houston St. to Cesar Chavez Blvd. Camp St. to DS Project Limit

Floodplain Area Outside the Channel:

Floodplain U/S Cesar Chavez D/S Cesar Chavez Total

Existing 4.09 ac 26.11 ac 30.20 ac

Acreage does not include main channel area.

LegendMain Channel Area

Project Floodplain

Page 10: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval

10

Page 11: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval

11

Page 12: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval

Water Supply

River water supplied to the project will be used to:Overcome evaporative losses

Irrigate landscaped areas

Aid in the control of algae growth

Maximum annual water requirements = 300 acft/yr

Water supply facilities sized to deliver 1 cubic ft/sec (cfs) for seasonal peaking

12

Page 13: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval

Key Permitting

USACE PermittingSection 408 review of potential effect to federal flood risk

infrastructure

Section 404 review of potential effect to aquatic resources

Includes review of potential effect to historic properties (coordinated with other agencies)

Critical path to start channel construction

Water Rights Permitting (TCEQ)3 new reservoirs created by gate facilities

Bed & banks authorization to use San Antonio River for delivery of SAWS recycle water to project; part of existing COSA allocation

13

Page 14: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval

Environmental

Phase 2 Environmental Site Assessments (ESA’s) Conducted88 Soil borings/196 soil samples

Groundwater evaluation at 6 locations

All materials confirmed as non-hazardousMaterials can be transported and accepted at local landfill (same

manner as household garbage)

19 additional soil borings conducted to verify acceptance and reduce stockpiling

Required groundwater management has been minimized

14

Page 15: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval

ARCHITECTURAL

PRESENTATION

H Munoz & Company

27

Page 16: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 17: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 18: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 19: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval

3

Page 20: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 21: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 22: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 23: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 24: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 25: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 26: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 27: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 28: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 29: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 30: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 31: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 32: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 33: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 34: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 35: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 36: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 37: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 38: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 39: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 40: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 41: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 42: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 43: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 44: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 45: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 46: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 47: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 48: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 49: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 50: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 51: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 52: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 53: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 54: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 55: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 56: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 57: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 58: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 59: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 60: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 61: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 62: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 63: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 64: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 65: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 66: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 67: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 68: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 69: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 70: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 71: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 72: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 73: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 74: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 75: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 76: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 77: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 78: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 79: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 80: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 81: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 82: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval
Page 83: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval

Next Steps April-May 2015 – Coordinate and reconcile anticipated costs,

project phasing, construction contracting, start to 70% design

May 30, 2015 – Third public outreach

June 2015 – City of San Antonio action to convey parcels and reuse water to project

July 31, 2015 – 70% design deliverable

August 2015 – Secure needed property

February 2016 – Final design

May 2016 – Start construction

May 2018 – Complete significant section for 300th Anniversary

83

Page 84: Design Activity Update · 2019-06-13 · Design Activity Update •Past Month and Ongoing: –April 14: Presentation to Commissioner’s Court and Court approval –May 6: Approval

Potential Construction Phasing

84